Вы находитесь на странице: 1из 8

The Use of Corrugated Metal Pipe and

Structural Plate for Aggregate Tunnel


and Conveyor Enclosure Applications
By Jim Noll, P.E.; Steve Tysl, P.E.; and Matt Westrich, P.E.

DECEMBER 2009
Professional Development Series

The Use of Corrugated Metal Pipe and Structural Plate


for Aggregate Tunnel and Conveyor Enclosure Applications
By Jim Noll, P.E.; Steve Tysl, P.E.; and Matt Westrich, P.E.

A
ggregate processing and involves the use of large corrugated connections, hopper and feeder chute
handling facilities, mining metal pipes (CMP) or corrugated struc- openings, floor slabs, lighting, and
sites, and related industrial tural plate pipes (SPP) and corrugated other features unique to such tunnel
operations often need to structural plate arches (SPA) for these applications must be addressed while
transport aggregate and ore across tunnel structures. Advantages include keeping the key structural aspects of
various points on their properties. reduced design time and related costs; flexible corrugated metal pipe design
The need to maximize surface area simplicity of construction; the option in mind.
on such sites necessitates the use of to utilize site personnel for the assem- This article will discuss the general
tunnels for transporting bulk materi- bly and installation phases of tunnel design, installation, and other specific
als under roadways and parking areas construction; reduced installation considerations for aggregate and ore
and processing these materials. Some costs; and lower maintenance costs. tunnel applications involving the use
applications involve tunnels complete While CMP, SPP, and SPA are of CMP, SPP, and SPA. The details asso-
with hopper openings and feeder viable and attractive options for the ciated with special appurtenances will
chutes located under bulk material construction of such tunnel structures, also be addressed.
piles. These are used for receiving they must be properly designed and
and processing the aggregate and ore installed to provide the desired level of Shape options
material and then transporting this structural performance and service life. CMP aggregate tunnels are
material to other locations on site. Understanding the basic principles of constructed using round CMP, while
One of the logical options available flexible metal pipe design and installa- structural plate tunnels are either
that offers economic advantages in tion is a critical requirement. The need round or arch shapes (see Figure 1).
the design, installation, operation, and for appurtenances such as escape Arches typically are half-circle, single-
maintenance phases of these projects pipes, end walls (bulkheads), utility radius shapes that are placed on rein-

Continuing Education
The Professional Development Series is a unique oppor- opment hour (equivalent to 0.1 continuing education unit
tunity to earn continuing education credit by reading in most states). Note: It is the responsibility of the licensee to
specially focused, sponsored articles in CE News. If you determine if this method of continuing education meets his or
read the following article, display your understanding her governing board(s) of registrations requirements.
of the stated learning objectives, and follow the simple
Learning Objectives
instructions, you can fulfill a portion of your continuing
After reading this article you should understand:
education requirements at no cost to you. This article
The benefits of utilizing CMP, SPP, and SPA for aggre-
also is available online at www.cenews.com/continuing-
gate and conveyor tunnel applications.
education.html.
The basic design principles that apply to CMP, SPP, and
Instructions SPA structures.
First, review the learning objectives below, then read the The select backfill envelope requirements for such
Professional Development Series article. Next, complete aggregate and conveyor tunnel structures.
the quiz and submit your answers to the Professional How to handle penetrations in such pipe tunnels for
Development Series sponsor. Submittal instructions are escape pipes, feeder and hopper penetrations, etc.
provided on the Reporting Form on page 6. Your quiz How to deal with end walls and bulkheads.
answers will be graded by the Professional Development The installation of utility conduits, lighting, etc. in such
Series sponsor. If you answer at least 80 percent of the tunnel structures.
questions correctly, you will receive a certificate of comple-
Professional Development Series Sponsor
tion from the Professional Development Series sponsor
within 90 days and will be awarded 1.0 professional devel- CONTECH Construction Products Inc.

2 PDH Professional Development Advertising Section CONTECH Construction Products Inc.


forced concrete slab foundations or The design premise of CMP is factors such as cover
raised, pedestal-type footings where that these pipes carry loads in ring height, load distribu-
added interior clearance is desired. compression, with the pipe supported tion at the travelling
Two radius arch shapes (commonly by the soil envelope and the pipe wall surface, and load dissipa-
referred to as horseshoe arches) may carrying the applied loads in compres- tion through the fill zone above
be used when high vertical clearance sive thrust. The total load pressure the crown of the pipe tunnel. The
is needed and if the site conditions over the pipe consisting of both the types of vehicles being considered, the
allow their use. dead loads, represented by the applied tire footprint, and the load pattern are
Normally, the interior of the tunnel soil and aggregate material overbur- all relevant. Adequate minimum cover
has a concrete floor slab to provide a den weights, and the live loads, repre- consisting of properly placed select
reasonably level and uniform working sented by any temporary construction backfill must be in place and well
surface. For full-round pipe shapes, traffic or more permanent vehicle live maintained for vehicle and equipment
the floor is constructed by placing loads operating over the tunnel is loads operating at low cover heights.
a granular bed on top of the pipe calculated. This combined load pres- After the ring compression force
invert, and then a concrete surface sure is used to determine the ring value has been determined, the pipe
is poured on top of the bedding. compression force acting within the is checked for wall buckling, required
Flexible metal pipes will experience pipe wall, using Equation 1: wall area, required installation stiffness,
slight deflections and shape changes and seam strength (if applicable). The
during installation, backfilling, and Ring Compression Force (Wall Thrust) design procedure is outlined in the
under loads. Therefore, it is recom- = Pt x Span/2 (Equation 1) referenced documents.
mended to construct concrete floors
after the pipe has been backfilled and where: Proper installation and backfill
initially loaded to prevent problems Pt = Pll + Pdl requirements
with spalled concrete due to natural Pll = live load pressure These tunnels, as with any buried
shape changes. Shrinkage is expected Pdl = dead load pressure flexible structure, require proper instal-
with curing concrete and any gaps at Span = maximum horizontal measure- lation to perform structurally. This
the edges of the concrete floor can be ment (width) of the pipe tunnel starts with installing such structures on
sealed with mastic or another type of a competent foundation and this
suitable sealant material after the floor The unit weight of the aggregate applies to the adjacent side fill embank-
slab cures. material, along with the height of the ments as well as to the pipe. The side
pile above the pipe, are critical factors fill zones must be supported to prevent
Basic flexible corrugated metal in determining the dead load acting differential settlement and loss of stable
pipe design principles on the tunnel. Many of these tunnels soil support for the pipe. Competent
CMP, SPP, and SPA are classified as have aggregate piles above them select fill must be used in the back-
flexible pipe structures. They are by that rise and fall with storage volume fill envelope. Ideally, this should be a
design less stiff than the surrounding needs. Because the loading is cyclical clean, well-graded, angular road base
soil backfill envelope. As such, they in nature, the tunnel is carrying signifi- fill material with maximum particle
behave as soil-structure interaction cant dead load near maximum cover size of 3 inches and a maximum of
systems that rely on the stiffness and heights as well as often carrying live 15 percent passing the #200 sieve.
density of the surrounding backfill for loads at near minimum cover heights. The aggregate processed at the site
support under applied loads. Such Live load pressures are governed by may meet the requirements for select
structures installed in a competent
backfill envelope that has been prop-
erly placed and compacted can carry Figure 1: Shape options for CMP and structural plate tunnels include round, single radius
significant amounts of overburden arch, and horseshoe arch.
loads. The proper design and instal-
lation of these CMP and structural
plate structures are covered in nation-
ally recognized specifications such as
American Association of State Highway
and Transportation Officials (AASHTO)
and ASTM, as well as industry-related
references such as those provided by
the National Corrugated Steel Pipe
Association (NCSPA).

Professional Development Advertising Section CONTECH Construction Products Inc. PDH 3


Aggregate Tunnel and Conveyor Enclosures

fill and, if used, the protection is provided by using protec- and detailing of such reinforcement.
separator or indicator tive spray on coatings. Impermeable However, a simplistic approach is to use
layer that denotes the barriers such as plastic membranes the ring compression force in the pipe
top of the minimum select combined with subdrains can be tunnel wall as a bending load applied
fill envelope must not be compro- installed within the top fill envelope to to the reinforcing members spanning
mised, encroached upon, or removed. prevent corrosive material or leachate across the opening. Simple span beam
Backfill material should be placed from reaching the pipe surface. formulas can be used to determine the
in balanced, 8- to 10-inch loose lifts bending moment:
and compacted to 90 percent Modified Escape tunnels or outlet pipes
Proctor Density (AASTHO T180). Side Mine Safety and Health M = C x L2/8 (Equation 2)
fill embankments are to be level and Administration (MSHA) regulations
extend out far enough to provide stable, typically require escape or outlet pipes where:
lateral resistance for the pipe tunnel. to provide emergency evacuation. C = ring compression force (wall
See Figure 2 for depiction of a proper Such outlet pipes and stubs for escape thrust)
backfill envelope for these structures. tunnels are treated as typical CMP L = length of opening
Select backfill should be free of fittings and will likely need to be framed M = bending moment
materials that are potentially corro- with suitable reinforcing members
sive or harmful to the pipe. If the ore designed to carry the ring compres- The ends of the beam members are
or aggregate material is corrosive in sion loads around the pipe opening. tied to compression members (curved
nature, then the material must be Industry guidelines and specifications to fit the pipe tunnel wall) that carry the
isolated from the pipe. Additional are available for reference in the design end thrust from the longitudinal beams.

Figure 2: Typical aggregate tunnel backfill envelope and installation detail

4 PDH Professional Development Advertising Section CONTECH Construction Products Inc.


The reinforcing framework can ably soil-tight seal; however, such normally fabricated
be comprised of standard structural flashing is not intended to carry the from flat steel plates or
shapes for the smaller size openings. full weight of the hoppers and feeders corrugated plates that
Longer openings in larger-diameter and material transported inside. are reinforced with welded
tunnels under high fills may require a A fairly common scenario is to channels. Such end walls may
reinforced concrete collar framework locate hopper penetrations and feeder have an escape pipe through them for
to carry these loads. chutes at reinforced concrete junction evacuation.
structures, with the corrugated metal
Hopper openings, feeder or structural plate tunnel stubbing into Lighting, utilities, catwalks,
chute penetrations, and the concrete structure and thus elimi- and platforms
conveyor hanger supports nating some of the above concerns. Light fixtures and small service
Conveyor tunnels often are installed Conveyors should be supported on conduits are readily mounted to the
under aggregate and ore piles and floor-mounted columns when possi- CMP, SPP, or SPA using self-tapping
have hopper and feeder mechanisms ble. In the event that conveyor support or blind hardware. Heavy utilities
penetrating through the crowns of the framework is intended to be mounted such as steam pipes and cable trays
tunnels. Typically these heavy machine or suspended from the crown of require special detailing similar to the
components are supported indepen- the pipe tunnel, there will need to approach used for conveyor trusses.
dently of the pipe tunnel by either an be additional structural members Catwalks and platforms should be
internal, floor-mounted support system that distribute point loads from the supported by the floor.
or an external, footing-supported collar conveyor supports up to the conveyor
system above the pipe. The opening in tunnel crown to help retain shape of Maintenance issues
the pipe tunnel is still reinforced, but the pipe tunnel. These tunnels may CMP and SPP tunnels with coatings
this reinforcement is intended to carry experience slight shape changes and compatible with the installed envi-
the ring compression loads around the deflections during installation and ronment usually require little main-
opening, not to bear the weight of the under load cycles. Mechanisms to tenance. Sealing or caulking at the
hoppers, feeders, and material inside adjust the conveyor hanging system juncture between the floor slab and
of those structures. and conveyor belt components should the tunnel wall may be required occa-
In situations where the tunnel is be used to ensure smooth operation. sionally to seal any openings caused
expected to carry the loads from the by curing of the concrete or by normal
hoppers and feeder chutes, a suitable End walls (bulkheads) pipe movement and shape changes.
heavy structural framework that carries End walls can be constructed from
the loads well beyond the opening reinforced concrete or from metal end Future modifications
and provides shape control and added panels. Reinforced concrete end walls Tunnels can be extended in length
stiffness to the tunnel structure would are formed, poured, and cured similarly if future needs dictate. The juncture
be required. to standard headwalls. Typically, prefab- between old and new sections of tunnel
Flashing around such openings may ricated steel end walls are detailed as can be accomplished using reinforced
be incorporated to provide a reason- reinforced diaphragms. End walls are concrete headwalls or through the

Bulk material is piled over this SPA. Material enters the tunnel A floor-mounted conveyor on a concrete slab is installed in this
through hoppers before it is transported out on the conveyor. round SPP tunnel.

Professional Development Advertising Section CONTECH Construction Products Inc. PDH 5


Aggregate Tunnel and Conveyor Enclosures

use of bands or simi- tunnels, installed properly, provide openings, conveyor support, hopper
lar connections. Care years of service and offer the flexibility and feeder chute requirements, and
must be taken during of future modifications. utility needs ensures a functional, safe,
any future modifications Attention to details such as fittings, and practical tunnel structure.
to keep loads and soil envelope
support for the tunnels balanced and
uniform. Any tap-ins or similar modifica-
REFERENCES
tions must be done in a manner to keep
AASHTO, 2002, Standard Specification for Highway Bridges, 17th Edition, Section 12
the entire tunnel periphery symmetri-
Soil-Corrugated Metal Structure Interaction Systems
cally loaded and supported and to
AASHTO, 2007, LRFD Bridge Design Specifications, 4th Edition, Section 12 Buried
maintain stability of the soil envelope. Structures and Tunnel Liners
AASHTO T 180 Standard Method of Test for Moisture-Density Relations of Soils Using
Summary and conclusions a 4.54-kg (10-lb) Rammer and a 457-mm (18-in.) Drop
CMP, SPP, and SPA tunnels offer an ASTM A-796 Standard Practice for Corrugated Steel Pipe, Pipe-Arches and Arches for
affordable, practical, and low-main- Storm and Sanitary Sewers and Other Buried Applications
tenance alternative to other means ASTM A-798 Standard Practice for Installing Factory-Made Corrugated Steel Pipe for
of aggregate tunnel construction. Sewers and Other Applications
The combined strength of the pipe ASTM A-998 Standard Practice for Structural Design of Reinforcements for Fittings in
product and the surrounding select Factory-Made Corrugated Steel Pipe for Sewers and Other Applications
backfill envelope functioning in a soil- NCSPA Installation Manual for Corrugated Steel Pipe, Pipe Arches, Structural Plate

structure interaction system provides NCSPA, 1999, Design Data Sheet No. 18A

the load-carrying capability and struc- NCSPA, 2008, Corrugated Steel Pipe Design Manual, First Edition

tural performance required. Such pipe

Professional Development Series Sponsor:


9025 Centre Pointe Dr., Suite 400, West Chester, OH 45069
Phone: 800-338-1122 Fax: 513-645-7993 Email: info@contech-cpi.com
Web: www.contech-cpi.com

CE News Professional Development Series Reporting Form


Article Title: The Use of Corrugated Metal Pipe and Structural Plate for Aggregate Tunnel and Conveyor Enclosure Applications
Publication Date: December 2009
Sponsors: CONTECH Construction Products Inc. Valid for credit until: December 2011

Instructions: Select one answer for each quiz question and clearly circle the appropriate letter. Provide all of the requested contact informa-
tion. Fax this Reporting Form to 513-645-7993. (You do not need to send the Quiz; only this Reporting Form is necessary to be submit-
ted.)
1) a b c d e 6) a b c d e
2) a b c d e 7) a b c d
3) a b c d 8) a b c d
4) a b c d e 9) a b c d
5) a b c d 10) a b c d e

Required contact information


Last Name: First Name: Middle Initial:
Title: Firm Name:
Address:
City: State: Zip:
Telephone: Fax: E-mail:

Certification of ethical completion: I certify that I read the article, understood the learning objectives, and completed the quiz ques-
tions to the best of my ability. Additionally, the contact information provided above is true and accurate.
Signature: Date:

6 PDH Professional Development Advertising Section CONTECH Construction Products Inc.


Jim Noll, P.E., is the director of Engineering Services for CONTECH. He has more than 30 years experience in the corrugated
metal pipe industry and is an active member of various technical organizations, including ASCE, AREMA, and ASTM. Contact him
at jnoll@contech-cpi.com. Steve Tysl, P.E., is a civil engineer for CONTECH and an active member in ASTM and SEAoO. He has
more than 18 years experience in civil engineering and materials/construction engineering. He can be contacted at tysls@contech-cpi.
com. Matt Westrich, P.E., is a civil engineer for CONTECH. He has more than 12 years experience in the civil/structural engineering field. He can
be reached at westrichm@contech-cpi.com.

1. B
 enefits of using corrugated metal tunnels for conveyor 6. A corrugated metal tunnel will have a 3-foot x 3-foot opening
enclosures and aggregate tunnels include: that will require reinforcing to span the length of the opening.
a) There are different shape options available to fit the site- The ring compression, C, in the structure is 40,000 pounds
specific requirements such as foundation requirements and per foot. What is the approximate moment used to size the
conditions and clearance requirements. reinforcing that will run perpendicular to the corrugations?
b) Reduced design time and ease of construction versus other a) 45 pound-ft. d) 45,000 pound-ft.
tunnel options. b) 450 pound-ft. e) 540,000 pound-ft.
c) Large bulk material piles can be dumped directly on the c) 5,400 pound-ft.
tunnel without a backfill envelope.
d) Both a and b 7. W
 hen constructing a concrete paved invert or floor system in
e) Both a and c a SPP, the recommended sequence is:
a) Assemble the plate structure without the crown, place
2. W
 hat advantage(s) are there to a floor-mounted conveyor concrete, install crown plates, backfill.
versus supporting a conveyor from the top of the tunnel? b) Assemble the plate structure completely, install structural
a) A floor-mounted conveyor system does not typically apply backfill zone, place concrete.
any loads to the tunnel structure that require reinforcing. c) Assemble the plate structure completely, place concrete,
b) Changes in shape that occur from hanging loads from the install backfill.
crown are avoided. d) Precast the concrete on the invert places, set with crane,
c) Additional reinforcing typically required if the conveyor is assemble the balance of crown plates, backfill.
attached to the top of the pipe is not needed.
d) Both a and c 8. W
 hich of the following are true statements regarding shape
e) All of the above selection for typical aggregate tunnel applications?
a) Use round or half-circle arch shapes that enclose the
3. When designing a corrugated metal pipe structure by industry required clearances while providing allowances for
standards, the ring compression force is first determined using installation tolerances and nominal deflection.
the applied loads, and then several design checks are required. b) Use very tall, slender arch shapes with straight sides.
Which of the following is not required to be checked? c) Use multiple-radius geometries such as pipe arches and
a) Installation stiffness c) Required wall area underpass shapes for tight clearance situations.
b) Radial tension d) Buckling d) All of the above

4. If a 12-foot-diameter corrugated metal pipe is used for 9. A


 common technique to clearly mark the extent of the
an aggregate tunnel with 3 feet of structural backfill dead structural backfill zone or select fill envelope is to:
load of 120 pcf, a stockpile dead load of 40 feet of 100-pcf a) Use clay as select fill to distinguish it from the aggregate material.
material, and no live load, what is the ring compression force b) Use an indicator layer such as brightly colored paint
acting within the pipe wall (per foot of pipe length)? between the select fill and aggregate rock layers.
a) 3,270 pounds d) 26,160 pounds c) Use a non-woven geotextile or a highly visible geogrid
b) 6,540 pounds e) 52,320 pounds product to mark the separation between granular materials.
c) 13,080 pounds d) Both b and c

5. O
 f the following, which would be considered the most 10. A
 general description of the material used as select backfill
appropriate material for the backfill envelope around a for such tunnel structures would include:
corrugated metal tunnel structure? a) Well-graded, granular, crushed rock.
a) Crushed rock varying in size from 1 inch to 4 inches. b) Chemically inert.
b) Well-graded, crushed rock varying in size from inch to 2 inches. c) Characterized by an established Proctor Curve.
c) Sandy silt. d) Clean and free of deleterious materials.
d) Native soils consisting primarily of clays and silts. e) All of the above

Professional Development Advertising Section CONTECH Construction Products Inc. PDH 7


Bringing Bridge
Solutions to Life
Over 65,000 installations now in place worldwide!

Plate, Precast, Truss - clear spans available from 5 to 250 and more

Knowledge. Solutions. Service.

Visit www.contech-cpi.com and use our exclusive online tool ... DYOB Design Your Own Bridge
Tel: 800-338-1122 Fax: 513-645-7993

Вам также может понравиться