Вы находитесь на странице: 1из 8

Sag and tension calculations for

mountainous terrain
J. Bradbury, Dip. Tech. (Eng.), G.F. Kuska, C. Eng., M.I.E.E., and D.J. Tarr
Indexing terms: Cables and overhead lines, Power transmission

Abstract: While normal sag and tension calculations based on the 'equivalent-span' concept are satisfactory,
when applied to transmission lines located in a reasonably undulating terrain, the answers obtained by this
method are inaccurate for mountainous terrain. An alternative method of calculation, which is based on the
analysis of the change of state equation for each span of a section in turn, is given. It is shown that when
using this new approach the full effect of both the suspension and tension insulators can be included together
with the influence of the running-out blocks on the sag of the conductor.
The paper also shows how this concept can be adapted to the function of line design and gives several
examples of critical areas where existing methods may give unacceptable results.
When stringing conductors in mountainous terrain, it is not always practical to measure the conductor sag
using conventional techniques and the paper gives three additional means which may be used, and discusses
the advantages and disadvantages of each.
List of symbols a = coefficient of thermal expansion of complete conduc-
tor, per deg C
A = cross-sectional area of conductor, mm2 /3 = blow-out angle of conductor (Fig. 2b), degrees
a,b,c,d = constants depending on sag>> 7 = angle to the vertical of the suspension or tension insu-
C catenary constant = H/W,m lator sets, degrees
E = Young's modulus of complete conductor, kg/mm2 Ah = height difference between tower and conductor attach-
H = horizontal tension of conductor, kg ment points (Fig. 9), m
H' = component of tension in line with AG (Fig. 2d), kg Ax = horizontal difference corresponding to Ah, m
h = height difference between attachment points at adjacent 5 = angle between chord line and the horizontal in the un-
towers, m resolved plane, degrees
ht = vertical distance from tower to instrument, m 6 = conductor temperature, C
K = unstretched length of conductor in a span (i.e. length i// = angle between chord line and the horizontal in the re-
after removing the tension at 0 C), m solved plane (Fig. 2d), degrees
L = chord length between adjacent towers (Fig. 1), m to = weight of tension or suspension insulator set, kg
/ = length of tension or suspension insulator set, m <t> = angle of the tangent at point F to the horizontal
S = stretched length of conductor in a span, m (Fig. 1), degrees
T = total (tangential) tension in conductor, kg Subscripts 1 and 2 denote different values for the same vari-
V = vertical load at attachment point due to conductor (up- ables.
lift load denoted by negative value), kg
W = conductor weight per unit length, kg/m 1 Introduction
Wh = conductor wind load per unit length (wind acting Since the advent of transmission lines, theories have been pro-
normal to conductor), kg/m gressively developed to define the sag and tension behaviour of
Wr = resolved conductor weight per unit length in the plane the conductor. Initially these were oriented towards manual
(as shown in Fig. 2c), kg/m calculations and, consequently, were based upon the parabolic
Wv = W + weight of ice per unit length, kg/m theory (Boyse and Simpson [1]). With the introduction of
W' = resolved conductor weight per unit length in the plane computers most theories are now based upon the accurate
(as shown in Fig. 2b), kg/m catenary equations (Rieger [2]). In multi-span sections, it is
X = horizontal span length, m usual to assume that the horizontal tensions will react to
Xo = horizontal distance from attachment point to low changes in load and temperature as a single span referred to by
point datum (Fig. 1), m the well known term 'equivalent span'. The mathematical
Xp = horizontal distance from any point on the catenary to treatment to obtain the 'equivalent span' is based upon para-
low point datum (Fig. 1), m bolic theory, and there is no similar concept using full ca-
x = horizontal distance from attachment point to any tenary equations.
point on the catenary, m While the methods give acceptable and practical results for
xt = horizontal distance from tower to instrument, m the majority of lines constructed'in normal, reasonably undu-
y = sag from chord line at point x on the catenary, m lating terrain, e.g. in the UK, in mountainous areas these
y0 = sag from attachment point at low point datum (Fig. theories produce significant errors. Overhead-line engineers are
already aware of this problem, as illustrated by Winkelman [3],
yh = maximum value of y occurring at point X/2 (absence of which develops the parabolic and catenary theories for appli-
tension insulators) (Fig. 1), m cation to inclined sections. Our recent experience, on applying
yh ' = maximum value of y not necessarily at point X/2 in this method to very mountainous terrain, highlighted the pres-
presence of tension insulators (Fig. 4), m ence of further inaccuracies which will result in the towers and
Z = transverse horizontal load at attachment point due to conductors experiencing loads in excess of their limiting design
conductor, kg values. In an attempt to overcome these problems, a theory
has been developed which is the subject of this paper. At
the development stage it became evident that the above in-
Paper 20S4C (P8), first received 2nd November 1981 and in revised accuracies were valid for both the single- and multi-span
form 20th May 1982 sections.
The authors are with Balfour Beatty Power Construction Limited, Power
Transmission Division, 7 Mayday Road, Thorton Heath, Surrey CR4 This paper was originally presented to the 2nd inter-
7XA, England national conference on 'Progress in cables and overhead lines
IEEPROC, Vol. 129, Pt. C, No. 5, SEPTEMBER 1982 0143-7046/82/050213 + 08 $01.50/0 213

Authorized licensed use limited to: UNIVERSIDADE DO PORTO. Downloaded on July 1, 2009 at 09:11 from IEEE Xplore. Restrictions apply.
for 220 kV and above' [4] and has now been expanded to in- angle to the horizontal of the tangent at point F
clude practical examples using the methods of calculations
described. = tan" 1 ! s i n h l - ^ |} (9)
2 Theory
2.2 Change-of-state equation
2.1 Basic equations
When considering a length of conductor suspended between
Before detailed considerations were given to the problem, it two towers, after it has been clamped in, it is assumed that the
was recognised that there are two theories, inelastic [2,3] and unstretched length K of the conductor at 0C is constant, i.e.
elastic (Hattingh [5]), applicable to the solution of a catenary. it equals the length given by the catenary equation less the
Considering the two theories, it became evident that the elastic elastic and thermal changes.
treatment requires lengthy computation without producing To utilise the above statement in the development of the
worthwhile improvements in the accuracy of the result. It is change-of-state equation, two simplifications have been made
therefore felt that the inelastic theory gives a tolerable related to the unstretched length of the conductor and its
accuracy, and, for this reason, the inelastic catenary equations tension. With respect to the former, an assumption was made
are used. These, by reference to Fig. 1, are given below: that, when calculating the elastic and thermal changes, the value
LT
of K is equal to the chord length L. This assumption causes an
catenary constant C = error of less than 0.01 % in the estimation of the unstretched
(1)
length. It is felt that this accuracy is sufficient for practical
= c/cosh^- purposes, but, if further accuracy is required, it can be improved
(2) by adopting the second-term-approximation system given in
length of conductor between points A and D step (d) of Section 3.1.
Regarding the tension, in calculating the elastic changes, the
S = Csinh (3) mean total tension in the conductor length has been assumed
C to equal the horizontal tension.
horizontal length Xo (D' A) Referring to Fig. 1, the change-of-state equation becomes:
h
Xo = -Csinh"1 (4)
X
2Csinh
yi A (Y)
also sinh h sinh (10)
EA
C2
Xo = Csinh" 1 (5)
H where subscripts 1 and 2 denote two different conditions.
vertical component of tension at point A It should be noted that this equation is only valid for still-
air conditions. When the conductor is subjected to wind acting
V = //sinh^- normal to it, the vertical and transverse forces present must
(6) be resolved in the deflected plane of the conductor before
total tension at point A applying eqn. 10. The method for resolving these forces is
given in Fig. 2 and explained below:
T = ^ (7) Step 1: Fig. 2a shows an inclined span under the influence
of a wind force. Consider the forces acting on the conductor
half-span sag element, i.e. the wind force Wh acting normal to the conductor
and the vertical force Wv due to the conductor and ice weight.
yh = C |cosh-1 Force Wv must be resolved along two axes normal to and par-
1+ (8)
allel with the chord line.
X
2 Csinh Step 2: Fig. 2b shows a section through the element (Fig. 2a)
2C~
along the X X axis. The forces acting are Wh, Wv cos 5 and Wv
sin 5, the latter applied parallel with the chord line. The result-
ant force W' acting at an angle j3 to the vertical is obtained.
Step 3: Fig. 2c shows the inclined span rotated about axis
AB through angle /3. The forces in the deflected plane, W' and
Wv sin 5, are combined to give the resultant force Wr acting at
an angle i// to the normal to the chord line.
Step 4: Fig. 2d shows the inclined span rotated about point
A, such that the chord line makes an angle \p to the line AG.
This line represents the 'horizontal' plane in which the catenary
equations are valid. Under this condition, force Wr is the
only force present and acts 'vertically', thus satisfying the re-
quirements to solve the change-of-state equation (eqn. 10).
To use eqns. 110 the parameters H and W should be replaced
by H' and Wr, respectively.
Having solved eqn. 1 for the unknown H'2 it should be
Xo
noted that this is the 'horizontal' tension in the rotated plane
Fig. 1 Inclined span (Fig. 2d~), and not the inline horizontal force at the tower. To
Sign convention: Xo positive and Xp negative for the case shown, i.e. if obtain the tension components H, V and Z at tower A (Fig. 2a),
point F is to the left of D, Xp becomes positive it is first necessary to calculate the Vertical' force in the rotated
214 IEEPROC, Vol. 129, Pt. C, No. 5, SEPTEMBER 1982

Authorized licensed use limited to: UNIVERSIDADE DO PORTO. Downloaded on July 1, 2009 at 09:11 from IEEE Xplore. Restrictions apply.
Q=Wh
c = W v sin8
d = Wwcos6

Fig. 2 Resolution of forces under wind conditions


a Span subjected to a wind force normal to the conductor
6 Deflection of element through section X X
c Span through section Y Y
d Span in resolved plane

suspension suspension
insulator insulator

Fig. 3 Forces on suspension insulators


a Conductor on running-out blocks
b Conductor clamped in

IEEPROC, Vol. 129, Pt. C, No. 5, SEPTEMBER 1982 215

Authorized licensed use limited to: UNIVERSIDADE DO PORTO. Downloaded on July 1, 2009 at 09:11 from IEEE Xplore. Restrictions apply.
plane at point A (eqn. 6) and then reverse the above step-by- on the solution of eqn. 10 and are ignored. As far as the error
step procedure. in sag is concerned, the effect can be significant.
By reference to Fig. 4, the following equations apply:
2.3 Effect of suspension insulators
Two conditions must be considered, when the conductor is on H Ax
running out blocks, and when it is clamped in. tan 7 (13)
V + co/2 Ah
2.3.1 Conductor on running-out blocks: Consider Fig. 3a which also3
shows the conductor mounted immediately below the sus-
pension insulator. Assuming the block to be frictionless, it / = VA/J2 + Ax2 (14)
follows that:
The horizontal tension H is known from the change-of-state
T = \IH\ + v\ = \ltii + v\ (11) equation and the insulator weight co given. The vertical force
V is dependent on Xo and hence on Ah. The solution for Ah
Taking moments about point Q, the following equation is and Kcan be achieved by iterative technique.
derived: To provide the necessary sagging information during string-
ing, the maximum sag y^ (which does not necessarily occur
H2 at X/2) must be calculated. In this respect, it should be noted
7 = tan - l (12) that eqn. 8 no longer applies; and a practical approach is given
below:
Furthermore, as the block is free to rotate thus permitting (i) Calculate y for three different values of*
conductor movement between spans, the unstretched length (ii) Solve
in individual spans is not constant. Obviously, the total un-
stretched length in a section is constant. y = ax2 + bx + c (15)
2.3.2 Conductor clamped in: Once the conductor is clamped (iii) Calculate JC for maximum sag, i.e. JC = b/2a
in, the unstretched length in individual spans remains constant, (iv) Substitute x from (iii) into eqn. 15 thus obtaining ^
because no conductor movement occurs at the clamp.
Considering this condition, it is evident that although pre- 3 Application of theory by computer programming
vious theories assumed the suspension set to be always vertical For the purpose of tower design, profiling and stringing, an
this assumption is incorrect, because the verticality depends overhead line contractor requires data resulting from a large
upon the geometry of the section and the temperature. For number of sag and tension calculations. These must, particu-
this reason Fig. 3b shows the suspension insulator at an angle larly in mountainous terrain, reflect the geometry of the line.
7 to the vertical. Again by taking moments about Q, eqn. 12 Under conditions of excessive gradients the suspension insu-
can be derived. It follows that the horizontal tensionsHx and lator will swing longitudinally, with the result that the hori-
H2 in the adjacent spans are different unless 7 equals zero. zontal tensions in adjacent spans may not be equal. Conse-
quently, the 'equivalent span' concept is not valid. The solution
2.4 Effect of tension insulator to the problem lies in the evaluation of the elastic and thermal
The length and weight of a tension insulator cause errors in sag effects in the conductor in each individual span, i.e. span-by-
and tension, particularly in EHV downleads. However, with span analysis. Without the aid of a computer program it is not
regard to tension, the reduction in span length X and the slight practical to undertake these calculations. While the program-
variation in height difference h have only a marginal influence ming of the sag equations was straightforward, the tension
equations presented some difficulties. For multi-span sections
these were overcome by the method outlined below:

3.1 Starting conditions


To carry out the calculations two parameters of the line must
be known at a given point in time, namely, the angle 7 of all
suspension insulators and a limit tension. Normally the
suspension insulators are assumed to be vertical at the expected
stringing temperature. The assumed tension values relate to a
limit in the horizontal or total component, as required by the
specification. For calculating the left-hand side of eqn. 10 the
procedure is as follows:

(a) The vertical and transverse loads are estimated at each


tower position.
(b) The total tension is estimated at the first tower.
(c) The left-hand side of eqn. 10 is evaluated for the first
span in the section, using the value of the chord length
for the unstretched length.
(d) Should further accuracy in the unstretched length be
required (see Section 2.2), the left-hand side of eqn. 10
can be recalculated using the value for the unstretched
length found under step (c) above. (This improves the
accuracy in calculating the unstretched length to better
than 0.0001 %).
Fig. 4 Span with tension insulator (e) Steps (c) and (d) are repeated for all spans in the section
216 IEEPROC, Vol. 129, Pt. C, No. 5, SEPTEMBER 1982

Authorized licensed use limited to: UNIVERSIDADE DO PORTO. Downloaded on July 1, 2009 at 09:11 from IEEE Xplore. Restrictions apply.
taking into account the angle 7, if any, of the suspension adopt more than one sag and tension method for its construc-
insulator, using eqn.12 for calculation of the hori- tion. Hence, at an early stage, one method is selected and used
zontal tension in succeeding spans. throughout the line; even though, when the conventional
method is selected, isolated sections may be found which
3.2 Condition when conductor is clamped in slightly exceed the limits given above. With some line construc-
This refers to the evaluation of the right-hand side of eqn. 10, tions, where conventional techniques may be ideal, isolated
i.e. for a condition other than the starting condition. The mountainous sections may be present where the method from
procedure adopted is as follows: this paper must be considered.
(a) Using the equivalent-span technique the horizontal,
vertical and transverse tensions are estimated at each 5 Practical application to line design
tower.
(b) The total tension is estimated at the first tower. Following the development of the program, it has been found
(c) The right-hand side of eqn. 10 is evaluated for each span increasingly useful in connection with studies and calculations
and angle 7 of the suspension insulator, changed to relevant to the following design activities:
accommodate any variation in the chord length. Before (a) the determination, for tower-design purpose, of all loads
considering the next span the horizontal tension is imposed by the conductors and earthwires
altered according to eqn 12. (b) the design and selection of profile-plotting templates
(d) By reiteration of steps (b) and (c), convergence on the which reflect the effect of gradients
position of the conductor attachment point at the last (c) the investigation of tower loads in cases where a combi-
tower is obtained. nation of long and short spans may result in unaccept-
able out-of-balance longitudinal and vertical loads
3.3 Condition when conductor is on running-out blocks (d) an accurate determination of sags and tensions in cir-
This refers to the conductor being free to move and the pro- cumstances where the route topography imposes a
cedure adopted is the same as under Section 3.2 with the ex- severe limitation on tower locations. This, in cases of
ception of step (c), which is as follows: excessive gradients, can lead to critical ground-clearance
(c) A summation of the values for the right-hand side of problems
eqn. 10 is made. When considering successive spans, the hori- (e) the production of sags and tension data for field use. In
zontal tension is changed according to eqn. 11. mountainous terrain the output refers to two stringing
conditions:
4 Application of theory to practical line situations (i) when the conductor in a section is located on run-
ning-out blocks
Conventional sag and tension methods are satisfactory for the (ii) when the conductor in a section is clamped in
majority of situations, and use of the method described above, (f) the evaluation of suspension-insulator longitudinal-
cannot be normally justified in view of the additional data re- swing and out-of-balance tensions. This may be re-
quired. Computer runs have shown that for normal level single- quired when dealing with very long sections
span sections there is no difference between conventional (g) use as a general-purpose design aid for the evaluation
methods and the one now proposed; unlike multi-spans, where of sags and tensions leading to rapid solution of field
even with level span sections, there is a small difference of problems
approximately 0.3 % between the theories. This is due to the
fact that under wind conditions, if conventional suspension In order that a better understanding of this theory can be ob-
insulators are used, the bottom of the suspension insulator tained, a number of examples are given below. These examples
will move in the transverse direction, causing an increase in the relate to a 'Zebra' conductor (54/7/3.18mm ACSR) strung to
chord length between the fixing points. This effect is included typical UK loading conditions. This Section, however, does
in the present theory, but ignored in conventional techniques. not constitute a criticism of UK practice which employs a
As conditions on the line change from a level span, the differ- special technique, see below, for safely overcoming the inade-
ence between conventional methods and the one proposed quacies of conventional sag and tension calculations, mentioned
gradually increases. Under extreme circumstances, limited in this paper.
investigations have shown that conventional theories will In the UK external loads and factors of safety related to
underestimate the maximum tension and sag by up to about transmission lines are governed by the Statutory Instruments
20%; hence, it is apparent that in critical situations there is a 1970, number 1355. Clause 9.2 defines the minimum factor
need for more accurate sag and tension techniques. It is there- of safety for total (tangential) tensions of the conductors as
fore necessary to have available a method of assessing these 2.0. For the 'Zebra' conductor this corresponds to a tension of
critical situations. As guidelines, the following empirical con- 6722 kg. The conventional UK practice for sag and tension cal-
ditions have been developed, to determine the sections in which culations for this conductor is to employ a maximum hori-
the more rigorous treatment given in this paper should be zontal tension of 5505 kg. The difference between these two
considered: figures is more than sufficient to account for any increases
in tension due to the nature of the terrain in the UK.
(a) if the span gradient for any span within the section ex-
ceeds 0.2 or if the average span gradient within the sec-
tion exceeds 0.15 5.1 Variation of tensions with span gradients
(b) if the conventional sag and tension using the modifi- In most specifications, the maximum working tension (MWT)
cations given by Winkelman [3] give an offset in excess in the conductors refers to the maximum tension anywhere in
of 0.5 m the conductor's length. This occurs at the highest point of
(c) for all sections containing spans in excess of 1 km, e.g. attachment of the conductor to the tower. Tension calculations
river crossings (eqn. 10) are ruled by the horizontal tensions. Thus, the tension
(d) if aircraft warning spheres are fitted used in eqn. 10 should be reduced as the span gradient is
(e) if for some reason one or more suspension sets are not increased, to ensure that the MWT is not exceeded. Fig. 5
designed to be vertical at the time of clamping. illustrates this reduction in horizontal tension against span
gradient, to ensure that the tension on a 366 m span does not
Naturally, when considering a complete line, it is not ideal to exceed 2651 kg under still-air conditions anywhere in the span
IEEPROC, Vol. 129, Pt. C, No. 5, SEPTEMBER 1982 217

Authorized licensed use limited to: UNIVERSIDADE DO PORTO. Downloaded on July 1, 2009 at 09:11 from IEEE Xplore. Restrictions apply.
length. This shows, considering a span having a difference in vertical and, hence, longitudinal loads of a magnitude H2
height between the conductor attachment points of 100 m Hi are transmitted to the suspension towers. The magnitude
that the tension in eqn. 10 should be reduced to 2454 kg, a of this force is influenced by the length of the insulator string
reduction of 7.4%. Even on level spans, this figure shows the or earthwire set. In the case of insulator sets, owing to their
specified tension should be reduced by 0.7%, a fact often length, the transmitted force is normally very small. However,
ignored when conventional sag and tension equations are used. in recent years, there has been a tendency to reduce the length
of the earthwire set which connects the earthwire to the tower.
0.6 >. specified maximum Fig. 7 shows that if this set is made too short, this may give
>v tension n200 rise to high longitudinal loads at the tower. This Figure was
0.5 constructed assuming a level two-span section having 150
\ \ and 500 m span lengths. It was further assumed the set is
E
- 0.4 - 150g vertical when under wind conditions, and the longitudinal
c out-of-balance forces shown are calculated at 75 C in still air.
I 0.3 100? c 1.0
o j |
in 0.2 : \

sets,
c si
- o 0.8
a, a
"50 ^
0.1 \ & 0.6

thwi
\ 0.4
0 o
2000 2200 2400 2600 <D
0.2
horizontal tension, kg "o

ength
0
Fig. 5 Horizontal tension on a 366 m span to ensure conductor's 0 2 4 6 8 10 12 14 16
tension should not exceed 2651 kg horizontal tension applied to earthwire
peak at suspension tower, "U
5.2 Profile plotting
Fig. 7 Loads applied to the suspension tower
The problems mentioned in Section 5.1 cause further compli-
cations during the profile plotting stage, because the templates
are based on horizontal tensions. It follows, therefore, that 5.4 Effect of masses on conductors
template selection is a function of equivalent span length and On some lines, located in the vicinity of aircraft flight paths, it
span gradient. This problem has been solved by introducing a is necessary to install aircraft warning spheres on the earth-
graph, Fig. 6, from which template selection is made . wires. These form effective masses at discrete points of the
line, causing a discontinuity in eqn. 2 at the point of their
application. While the effect of this is mainly on the sag
calculations, a second and far more important effect can
arise with some designs, because the sag of the earthwire
should be equal or less than the sag of the conductor from
electrical considerations. This results in the tension of the
earthwire being increased. Fig. 8 shows a simplified example
of this, in which the increase in tension has been calculated to
accomodate a single-centre span mass, placed on a 366 m level
span; so that the sag remains the same as a conductor without
such a mass.
When considering additional masses under MWT conditions,

equivalent span,m- 30- 3400


Fig. 6 Sketch of template selection graph

Fig. 6 is obtained by determining the number of templates,


and tensions for each template, to be used during plotting. The
program is run to predict the horizontal tension, at maximum 3200
operating temperature, from the specified limiting conditions
for a number of spans and span gradients. From this data, Fig. 6
can be drawn by plotting the lines corresponding to the hori-
zontal tension chosen for the templates. The straight line given
3000
in the Figure represents the level single-span condition, below
which the graph is indeterminate.
In practice, this graph is used in the following manner: 10
(a) The worst span in a section is visually selected, usually
having the highest span gradient 2800
(b) Any template is offered to this span and the weight
span at the highest tower read off the template
(c) The weight span is checked against Fig. 6, and the
correct template selected for use in final plotting 0 20 40 60 80 100
weight of central mass, kg
5.3 Transverse loads on suspension earth wire peaks
Fig. 8 Increase in tension to accommodate a centre span mass with-
As eqn. 12 shows, the suspension insulator is not normally out increasing sag
218 IEEPROC, Vol. 129, Pt. C, No. 5, SEPTEMBER 1982

Authorized licensed use limited to: UNIVERSIDADE DO PORTO. Downloaded on July 1, 2009 at 09:11 from IEEE Xplore. Restrictions apply.
the effect of the weight of ice load and extra wind load on the 6.3 Low-point method
added masses, together with their weight, must also be included With this method (Fig. 9c), the instrument, e.g. theodolite
in the tension calculations. or dumpy level, is located at a distance y0 below the con-
To accommodate this additional tension caused by fitting ductor attachment point. Obviously, its application is limited
spheres, while still maintaining the required factors of safety, to cases having a low-point datum, and the accuracy achieved
the selected earthwire must be sufficiently strong. Failure is dependent upon the variation of y0 with changes in tem-
to achieve this can result in a situation in which the sag of the perature. If the variation is small the method may be unsuitable.
earthwire dictates the main conductor sags, which can prove to
be an uneconomical solution. 6.4 Tangent method
Fig. 9d illustrates the case where the location of the theodolite
6 Sag measuring techniques is defined by limited access. In application, the stringing en-
gineer, having fixed its location, is required to make use of the
When stringing conductors in mountainous terrain it is not following equations:
always possible or desirable to use the conventional sagging
technique. To provide field staff with alternatives, four further (16)
methods have been developed. Each has its limitations, but the
selection of the appropriate method will be dictated by site where d = C In (tan 0 + sec 0) (17)
circumstances, and is made by the stringing engineer.
The difficulty in using this method lies in the reiterative calcu-
6.1 Conventional method lation for 0 and the accuracy with which it has to be measured.
This is illustrated in Fig. 9a, where the gun sight and the For reason of accuracy and site calculation this method is to
sighting board are fixed to the towers at a distance yh> below be avoided if possible.
the conductor attachment points. The field application is
straightforward, but limited to cases when yh' is less than the 6.5 Tension method
tower heights. Its accuracy will decease with small spans. When considering short span sections, an accurate sagging
method can be achieved by the use of a load cell prior to con-
6.2 Modified conventional method ductor marking and the installation of tension insulator. This
By reference to Fig. 9b, it is seen that this method applies to technique lends itself to situations where compression dead-
conditions when the gun sight and the sighting board cannot ends are made aloft.
be located on the tower. It requires care in accurate location
of the theodolite, and has the same limitations as in Section 6.6 Stringing tables
6.1. It is not possible to provide site staff with sufficient informa-
tion in conventional sag-chart form to string conductors using

sighting
board

Fig. 9 Method of sag measurement


a Conventional
b Modified conventional
c Low-point datum
d Tangent

IEEPROC, Vol. 129, Pt. C, No. 5, SEPTEMBER 1982 219

Authorized licensed use limited to: UNIVERSIDADE DO PORTO. Downloaded on July 1, 2009 at 09:11 from IEEE Xplore. Restrictions apply.
Table 1 : Typical stringing table obtained from computer

Temperature Horizontal Total tension Half low tower number high tower number
load low tower high tower span X Y X Y
number number sag
C kg kg kg m m m m m

0.00 2400 2400 2422 3.32 -31.95 0.60 233.74 16.50


5.00 2290 2290 2312 3.48 -25.86 0.52 227.65 16.42
10.00 2189 2189 2211 3.64 -20.26 0.46 222.05 16.36
15.00 2096 2097 2118 3.80 -15.13 0.42 216.92 16.32
20.00 2011 2012 2033 3.96 -10.43 0.40 212.22 16.30
25.00 1933 1934 1955 4.12 -6.11 0.39 207.90 16.29
30.00 1862 1862 1883 4.20 -2.14 0.39 203.93 16.29
35.00 1796 1796 1817 4.44 1.51 0.40 200.28 16.30

all five methods given above. The program provides computer- In many instances, where conditions were so severe that the
printout tables, illustrated in Table 1, which has an added use of helicopters became the only means of access, the use of
advantage over conventional sag-chart owing to ease of reading the tension method, where the tangential tension is measured
rather than interpolation of graphs. by a load cell, proved extremely effective.

7 Conclusions 8 Acknowledgments

To satisfy the statutory ground clearance requirements, and to The authors acknowledge the help of their colleagues in the
ensure that the specified factors of safety of the line are main- preparation of this work, and wish to thank the General
tained, an accurate method of span-to-span analysis has been Manager of the Power Transmission Division, Balfour Beatty
developed. This is of particular importance in mountainous Power Construction Limited, and the Directors of Balfour
terrain, where existing techniques may result in noticeable Beatty Limited for permission to publish this paper.
errors.
Normally, in reasonable terrain, consideration need not be 9 References
given to the out-of-balance loads due to the longitudinal swing
of the suspension insulator. However, in long multi-span sec- 1 BOYSE, CO., and SIMPSON, N.G.: 'The problem of conductor
tions with excessive gradients this effect can be significant and sagging on overhead transmission lines', J. IEE, 1944, 91, Pt. II,
pp. 219-238
should be examined. 2 RIEGER, H.: 'Der Freileitungsbau' (Springer Verlag, 1960)
In mountainous terrain, where the conventional method of 3 WINKELMAN, P.F.: 'Sag-tension computations and field measure-
sagging is either impossible or impracticable, then, alternative ments of Bonneville Power Administration', Trans. Amer. Inst. Elect.,
methods must be available to the site organisation. During the Engrs., 1959, 78, Pt. Ill B pp. 1532-1547
4 BRADBURY, J., KUSKA, G.F., and TARR, D.J.: 'Sag and tension
construction of the 400 kV line through the formidable Zagros calculations in mountainous terrain'. IEE Conf. Publ. 176, 1979,
mountains in Central Iran, it was necessary to apply the full pp. 1-5
range of methods, as detailed under Section 6, each being deter- 5 HATTINGH, J.T.: 'A universal stress-sag chart (for line computa-
mined by the relative conditions of each section encountered. tions)' (Blackie & Sons, 1936)

220 IEEPROC, Vol. 129, Pt. C, No. 5, SEPTEMBER 1982

Authorized licensed use limited to: UNIVERSIDADE DO PORTO. Downloaded on July 1, 2009 at 09:11 from IEEE Xplore. Restrictions apply.

Вам также может понравиться