Вы находитесь на странице: 1из 296

DAILY CONSTRUCTION

PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - - - - - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - - - - - -
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG Mechanical Engineer M/D - - - - - 1
- - - - - -
- - - - - -
Material Control M/D - - - - - -
MAT'L Document Control M/D - - - - - -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - - - - - -
Safety Man M/D - - - - - -
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - - - - - -
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - - - - - -
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D - - - - - 2

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M Scaffolding F/M M/D - - - - - -
Rigging Foreman M/D - - - - - -
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - - - - - 2
WORKERS

Rigger M/D - - - - - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - - - - - -
- - - - - -
- - - - - -
Sub-Total M/D - - - - - 2
Manpower Total M/D - - - - - 4

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 0 0 0 0 1
INDONESIAN M/D 0 0 0 0 0 3
TOTAL M/D 0 0 0 0 0 4

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
PROGRESS CONTROL ENGIN Supervisor Mechanical SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 31-Aug-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- - - 1 - 1 KOR
- - - - - - INA
- - - - - - INA
- - - - - - KOR
- - - - - - INA
- - - - - - INA
- - - 1 - 1 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - -
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - 2 - 2

- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - -
- - - - - -
- - - 2 - 2
- - - 4 - 4

TODAY ACCUMULATE REMARK


0 0 0 1 0 1
0 0 0 3 0 3
0 0 0 4 0 4

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - - - - - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - - - - - -
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG Mechanical Engineer M/D - - - - - 1
- - - - - -
- - - - - -
Material Control M/D - - - - - -
MAT'L Document Control M/D - - - - - -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - - - - - -
Safety Man M/D - - - - - -
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - - - - - -
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - - - - - -
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D - - - - - 2

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M Scaffolding F/M M/D - - - - - -
Rigging Foreman M/D - - - - - -
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - - - - - 2
WORKERS

Rigger M/D - - - - - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - - - - - -
- - - - - -
- - - - - -
Sub-Total M/D - - - - - 2
Manpower Total M/D - - - - - 4

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 0 0 0 0 1
INDONESIAN M/D 0 0 0 0 0 3
TOTAL M/D 0 0 0 0 0 4

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
PROGRESS CONTROL ENGIN Supervisor Mechanical SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 1-Sep-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- - - 1 - 1 KOR
- - - - - - INA
- - - - - - INA
- - - - - - KOR
- - - - - - INA
- - - - - - INA
- - - 1 - 1 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - -
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - 2 - 2

- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - -
- - - - - -
- - - 2 - 2
- - - 4 - 4

TODAY ACCUMULATE REMARK


0 0 0 1 0 1
0 0 0 3 0 3
0 0 0 4 0 4

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - - - - - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - - - - - -
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG Mechanical Engineer M/D - - - - - 1
- - - - - -
- - - - - -
Material Control M/D - - - - - -
MAT'L Document Control M/D - - - - - -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - - - - - -
Safety Man M/D - - - - - -
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - - - - - -
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - - - - - -
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D - - - - - 2

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M Scaffolding F/M M/D - - - - - -
Rigging Foreman M/D - - - - - -
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - - - - - 2
WORKERS

Rigger M/D - - - - - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - - - - - -
- - - - - -
- - - - - -
Sub-Total M/D - - - - - 2
Manpower Total M/D - - - - - 4

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 0 0 0 0 1
INDONESIAN M/D 0 0 0 0 0 3
TOTAL M/D 0 0 0 0 0 4

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
PROGRESS CONTROL ENGIN Supervisor Mechanical SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 31-Aug-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- - - 1 - 1 KOR
- - - - - - INA
- - - - - - INA
- - - - - - KOR
- - - - - - INA
- - - - - - INA
- - - 1 - 1 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - -
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - 2 - 2

- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - -
- - - - - -
- - - 2 - 2
- - - 4 - 4

TODAY ACCUMULATE REMARK


0 0 0 1 0 1
0 0 0 3 0 3
0 0 0 4 0 4

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - - - - - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG Mechanical Engineer M/D 1 1 - 2 1 1
- - - - - -
- - - - - -
Material Control M/D - - - - - -
MAT'L Document Control M/D - - - - - -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - - - - - -
Safety Man M/D - 1 - 1 - 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - - - - - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - - - - - -
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 1 3 - 4 1 5

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M Scaffolding F/M M/D - 1 - 1 - 1
Rigging Foreman M/D - - - - - -
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 2 - 2 - 2
WORKERS

Rigger M/D - - - - - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - 2 - 2 - 2
Electrician M/D - - - - - 1
- - - - - -
- - - - - -
Sub-Total M/D - 5 - 5 - 6
Manpower Total M/D 1 8 - 9 1 11

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 1 0 1 0 2
INDONESIAN M/D 1 7 0 8 1 9
TOTAL M/D 1 8 0 9 1 11

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
PROGRESS CONTROL ENGIN MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 3-Sep-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- - - 1 - 1 KOR
- - - - - - INA
- - - - - - INA
- 2 2 2 - 4 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - 1 - 1 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 4 2 8 - 10

- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 2 - 4 - 4 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 2 - 4 - 4 INA
- 1 - 1 - 1 INA
- - - - - -
- - - - - -
- 6 - 11 - 11
- 10 2 19 - 21

TODAY ACCUMULATE REMARK


0 1 0 3 0 3
0 9 2 16 0 18
0 10 2 19 0 21

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG Mechanical Engineer M/D 1 1 - 2 1 1
- - - - - -
- - - - - -
Material Control M/D - - - - - -
MAT'L Document Control M/D - - - - - -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - - - - - -
Safety Man M/D - 1 - 1 - 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - - - - - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - - - - - -
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 1 4 - 5 1 5

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M Scaffolding F/M M/D - 1 - 1 - 1
Rigging Foreman M/D - - - - - -
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 2 - 2 - 2
WORKERS

Rigger M/D - - - - - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - 2 - 2 - -
Electrician M/D - - - - - 1

Sub-Total M/D - 5 - 5 - 4
Manpower Total M/D 1 9 - 10 1 9

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 1 7 0 8 1 7
TOTAL M/D 1 9 0 10 1 9

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
PROGRESS CONTROL ENGIN MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 5-Sep-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 2 2 2 - 4 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - 1 - 1 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 5 2 9 - 11

- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 2 - 4 - 4 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - 2 - 2 INA
- 1 - 1 - 1 INA

- 4 - 9 - 9
- 9 2 18 - 20

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 7 2 14 0 16
0 9 2 18 0 20

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG Mechanical Engineer M/D 1 1 - 2 1 1
- - - - - -
- - - - - -
Material Control M/D - - - - - -
MAT'L Document Control M/D - - - - - -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - - - - - -
Safety Man M/D - 1 - 1 - 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - - - - - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - - - - - -
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 1 4 - 5 1 5

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M Scaffolding F/M M/D - 1 - 1 - 1
Rigging Foreman M/D - - - - - -
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 2 - 2 - 2
WORKERS

Rigger M/D - - - - - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - 2 - 2 - -
Electrician M/D - - - - - 1

Sub-Total M/D - 5 - 5 - 4
Manpower Total M/D 1 9 - 10 1 9

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 1 7 0 8 1 7
TOTAL M/D 1 9 0 10 1 9

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
PROGRESS CONTROL ENGIN MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 4-Sep-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 2 2 2 - 4 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - 1 - 1 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 5 2 9 - 11

- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 2 - 4 - 4 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - 2 - 2 INA
- 1 - 1 - 1 INA

- 4 - 9 - 9
- 9 2 18 - 20

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 7 2 14 0 16
0 9 2 18 0 20

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG Mechanical Engineer M/D 1 1 - 2 1 1
- - - - - -
- - - - - -
Material Control M/D - - - - - -
MAT'L Document Control M/D - - - - - -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - - - - - -
Safety Man M/D - 1 - 1 - 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - - - - - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - - - - - -
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 1 4 - 5 1 5

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M Scaffolding F/M M/D - 1 - 1 - -
Rigging Foreman M/D - - - - - -
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 2 - 2 - 2
WORKERS

Rigger M/D - - - - - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - 2 - 2 - -
Electrician M/D - - - - - 1

Sub-Total M/D - 5 - 5 - 3
Manpower Total M/D 1 9 - 10 1 8

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 1 7 0 8 1 6
TOTAL M/D 1 9 0 10 1 8

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
PROGRESS CONTROL ENGIN MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 6-Sep-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 2 2 2 - 4 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - 1 - 1 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 5 2 9 - 11

- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - 1 - 1 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 2 - 4 - 4 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - 2 - 2 INA
- 1 - 1 - 1 INA

- 3 - 8 - 8
- 8 2 17 - 19

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 6 2 13 0 15
0 8 2 17 0 19

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG Mechanical Engineer M/D 1 1 - 2 1 1
Mechanical Supervisor - - - - 1
- - - - -
Material Control M/D - - - - - -
MAT'L Document Control M/D - - - - - -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - - - - - -
Safety Man M/D - 1 - 1 - 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - - - - - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - - - - - -
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 1 4 - 5 1 6

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M Scaffolding F/M M/D - - - - - -
Rigging Foreman M/D - - - - - -
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 2 - 2 - 2
WORKERS

Rigger M/D - - - - - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - 1 - 1 - 1

Sub-Total M/D - 3 - 3 - 3
Manpower Total M/D 1 7 - 8 1 9

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 1 5 0 6 1 7
TOTAL M/D 1 7 0 8 1 9

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
PROGRESS CONTROL ENGIN MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 7-Sep-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 2 2 2 - 4 INA
- - - 1 - 1 INA
- - - ### - ### INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - 1 - 1 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 5 2 ### - ###

- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
2 - 4 - 4 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA

- 3 - 6 - 6
- 8 2 ### - ###

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 6 2 ### 0 ###
0 8 2 ### 0 ###

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - -
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - -
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 1 - 2 - -
Mechanical Supervisor M/D - - - - -
Material Control M/D - - - - 1 -
MAT'L Document Control M/D - - - - - -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - - - - - -
Safety Man M/D - 1 - 1 1 -
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - - - - - -
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - - - - - -
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 1 4 - 5 2 -

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
F/M Scaffolding F/M M/D - - - - - -
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
F/M comm
Rigging Foreman M/D - - - - 1 -
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 2 - 2 - -
WORKERS

Rigger M/D - - - - 5 -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - 1 -
Rigger (Crane) M/D - - - - - -
Electrician M/D - 1 - 1 - -

Sub-Total M/D - 3 - 3 7 -
Manpower Total M/D 1 7 - 8 9 -

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 0
INDONESIAN M/D 1 5 0 6 9 0
TOTAL M/D 1 7 0 8 9 0

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
PROGRESS CONTROL ENGIN MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 8-Sep-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- - - 1 - 1 KOR
- - - - - - INA
- - - - - - INA
- - - 1 - 1 KOR
- - - - - - INA
- - - - - - INA
- - 1 1 - 2 INA
- - - - - - INA
- 1 1 - - 1 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 1 1 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 2 3 4 - 7

- - - - - - INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- 1 1 - - 1 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - 2 - 2 INA
- 5 5 - - 5 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 1 - - 1 INA
- - - - - - INA
- - - 1 - 1 INA

- 7 7 3 - 10
- 9 10 7 - 17

TODAY ACCUMULATE REMARK


0 0 0 2 0 2
0 9 10 5 0 15
0 9 10 7 0 17

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 1 1
Mechanical Supervisor - 1 - 1 - -
Material Control M/D - - - - - -
MAT'L Document Control M/D - - - - - -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - - - - - -
Safety Man M/D 1 - - 1 - -
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - - - - - -
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 4 - 6 1 4

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
F/M Scaffolding F/M M/D - - - - - -
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
F/M comm
Rigging Foreman M/D - 1 - 1 - -
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 2 - - - 2
WORKERS

Rigger M/D - - - - - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - - - - - -

Sub-Total M/D - 3 - 1 - 2
Manpower Total M/D 2 7 - 7 1 6

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 5 0 5 1 4
TOTAL M/D 2 7 0 7 1 6

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
PROGRESS CONTROL ENGIN MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 9-Sep-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 2 2 1 - 3 INA
- - - 1 - 1 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - 1 - - 1 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 5 3 8 - 11

- - - - - - INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - 1 - 1 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
2 - 4 - 4 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA

- 2 - 5 - 5
- 7 3 13 - 16

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 5 3 9 0 12
0 7 3 13 0 16

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 1 -
Mechanical Supervisor - 1 - 1 - -
Material Control M/D - - - - - -
MAT'L Document Control M/D - - - - - -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - - - - - -
Safety Man M/D 1 - - 1 - -
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - - - - - -
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 4 - 6 1 3

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
F/M Scaffolding F/M M/D - - - - - -
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
F/M comm
Rigging Foreman M/D - 1 - 1 - -
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 2 - - - 2
WORKERS

Rigger M/D - - - - - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - - - - - -

Sub-Total M/D - 3 - 1 - 2
Manpower Total M/D 2 7 - 7 1 5

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 5 0 5 1 3
TOTAL M/D 2 7 0 7 1 5

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
PROGRESS CONTROL ENGIN MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 10-Sep-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 2 - - 2 INA
- - - 1 - 1 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - 1 - - 1 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 4 3 7 - 10

- - - - - - INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - 1 - 1 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
2 - 4 - 4 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA

- 2 - 5 - 5
- 6 3 12 - 15

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 4 3 8 0 11
0 6 3 12 0 15

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 1 -
Mechanical Supervisor - - - - - -
Material Control M/D - - - - - -
MAT'L Document Control M/D - - - - - -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - - - - - -
Safety Man M/D 1 - - 1 - -
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - - - - - -
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 3 - 5 1 3

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
F/M Scaffolding F/M M/D - - - - - -
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
F/M comm
Rigging Foreman M/D - - - - - -
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 2 - - - 2
WORKERS

Rigger M/D - - - - - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - - - - - -

Sub-Total M/D - 2 - - - 2
Manpower Total M/D 2 5 - 5 1 5

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 3 0 3 1 3
TOTAL M/D 2 5 0 5 1 5

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
PROGRESS CONTROL ENGIN MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 11-Sep-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 2 - - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - 1 - - 1 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 4 3 6 - 9

- - - - - - INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
2 - 4 - 4 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA

- 2 - 4 - 4
- 6 3 10 - 13

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 4 3 6 0 9
0 6 3 10 0 13

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 1 -
Mechanical Supervisor - - - - - -
Material Control M/D - - - - - -
MAT'L Document Control M/D - - - - - -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - - - - - -
Safety Man M/D 1 - - 1 - -
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - - - - - -
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 3 - 5 1 3

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
F/M Scaffolding F/M M/D - - - - - -
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
F/M comm
Rigging Foreman M/D - - - - - -
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 2 - - - 2
WORKERS

Rigger M/D - - - - - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - - - - - -

Sub-Total M/D - 2 - - - 2
Manpower Total M/D 2 5 - 5 1 5

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 3 0 3 1 3
TOTAL M/D 2 5 0 5 1 5

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
PROGRESS CONTROL ENGIN MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 12-Sep-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 2 - - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - 1 - - 1 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 4 3 6 - 9

- - - - - - INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
2 - 4 - 4 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA

- 2 - 4 - 4
- 6 3 10 - 13

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 4 3 6 0 9
0 6 3 10 0 13

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 1 -
Mechanical Supervisor - - - - - -
Material Control M/D - - - - - -
MAT'L Document Control M/D - - - - - -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - - - - - -
Safety Man M/D 1 - - 1 - -
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - - - - - -
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 3 - 5 1 3

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
F/M Scaffolding F/M M/D - - - - - -
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
F/M comm
Rigging Foreman M/D - - - - - -
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 2 - - - 2
WORKERS

Rigger M/D - - - - - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - - - - - -

Sub-Total M/D - 2 - - - 2
Manpower Total M/D 2 5 - 5 1 5

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 3 0 3 1 3
TOTAL M/D 2 5 0 5 1 5

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
PROGRESS CONTROL ENGIN MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 13-Sep-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 2 - - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - 1 - - 1 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 4 3 6 - 9

- - - - - - INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
2 - 4 - 4 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA

- 2 - 4 - 4
- 6 3 10 - 13

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 4 3 6 0 9
0 6 3 10 0 13

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 1 -
Mechanical Supervisor - - - - - -
Material Control M/D - - - - - -
MAT'L Document Control M/D - - - - - -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - - - - - -
Safety Man M/D 1 - - 1 - -
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - - - - - -
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 3 - 5 1 3

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
F/M Scaffolding F/M M/D - - - - - -
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
F/M comm
Rigging Foreman M/D - - - - - -
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 2 - - - 5
WORKERS

Rigger M/D - - - - - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - - - - - -

Sub-Total M/D - 2 - - - 5
Manpower Total M/D 2 5 - 5 1 8

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 3 0 3 1 6
TOTAL M/D 2 5 0 5 1 8

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
PROGRESS CONTROL ENGIN MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 14-Sep-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 2 - - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - 1 - - 1 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 4 3 6 - 9

- - - - - - INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
5 - 7 - 7 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 5 - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA

- 10 - 7 - 7
- 14 3 13 - 16

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 12 3 9 0 12
0 14 3 13 0 16

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 1 -
Mechanical Supervisor - - - - - -
Material Control M/D - - - - - -
MAT'L Document Control M/D - - - - - -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - - - - - -
Safety Man M/D 1 - - 1 - -
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - - - - - -
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 3 - 5 1 3

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
F/M Scaffolding F/M M/D - - - - - -
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
F/M comm
Rigging Foreman M/D - - - - - -
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 5 - - - 7
WORKERS

Rigger M/D - - - - - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - - - - - 1

Sub-Total M/D - 5 - - - 8
Manpower Total M/D 2 8 - 5 1 11

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 6 0 3 1 9
TOTAL M/D 2 8 0 5 1 11

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
PROGRESS CONTROL ENGIN MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 15-Sep-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 2 - - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - 1 - - 1 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 4 3 6 - 9

- - - - - - INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
7 - 12 - 12 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 1 - 1 INA

- 8 - 13 - 13
- 12 3 19 - 22

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 10 3 15 0 18
0 12 3 19 0 22

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 1 -
Mechanical Supervisor - - - - - -
Material Control M/D - - - - - -
MAT'L Document Control M/D - - - - - -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - - - - - 1
Safety Man M/D 1 - - 1 - -
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - - - - - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 3 - 5 1 5

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
F/M Scaffolding F/M M/D - - - - - -
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
F/M comm
Rigging Foreman M/D - - - - - 1
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 7 - - - 4
WORKERS

Rigger M/D - - - - - 3
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - 1
Rigger (Crane) M/D - - - - - -
Electrician M/D - 1 - - - -

Sub-Total M/D - 8 - - - 9
Manpower Total M/D 2 11 - 5 1 14

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 9 0 3 1 12
TOTAL M/D 2 11 0 5 1 14

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
PROGRESS CONTROL ENGIN MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 16-Sep-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 2 - - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 1 - 1 INA
- - 1 - - 1 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 1 - 1 INA
- - - - - - INA
- - - - - - INA
- 6 3 8 - 11

- - - - - - INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- 1 - 1 - 1 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
4 - 11 - 11 INA
- 3 - 3 - 3 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 1 - 1 INA
- - - - - - INA
- - - 1 - 1 INA

- 9 - 17 - 17
- 15 3 25 - 28

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 13 3 21 0 24
0 15 3 25 0 28

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 1 -
Mechanical Supervisor - - - - - -
Material Control M/D - - - - - 1
MAT'L Document Control M/D - - - - - -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - - - - - 1
Safety Man M/D 1 - - 1 - -
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 4 - 6 1 6

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - 1 - 1 - 1
Surveyor M/D - - - - - 1
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 4 - - - 4
WORKERS

Rigger M/D - 3 - 3 - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - 1 - 1 - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - - - - - -

Sub-Total M/D - 9 - 5 - 6
Manpower Total M/D 2 13 - 11 1 12

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 11 0 9 1 9
TOTAL M/D 2 13 0 11 1 11

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
PROGRESS CONTROL ENGIN MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 17-Sep-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 2 - - 2 INA
- - - - - - INA
- 1 - 1 - 1 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 1 - 1 INA
- - 1 - - 1 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 7 3 10 - 13

- - - - - - INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- 1 - 2 - 2 INA
- 1 - 1 - 1
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
4 - 8 - 8 INA
- - - 3 - 3 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - 1 - 1 INA
- - - - - - INA
- - - - - - INA

- 6 - 15 - 15
- 13 3 25 - 28

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 10 3 20 0 23
0 12 3 24 0 27

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 1 -
Mechanical Supervisor - - - - - -
Material Control M/D - - - - - 1
MAT'L Document Control M/D - - - - - -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - - - - - 1
Safety Man M/D 1 - - 1 - -
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 4 - 6 1 6

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - 1 - 1 - -
Surveyor M/D - - - - - 1
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 4 - - - 4
WORKERS

Rigger M/D - 3 - 3 - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - 1 - 1 - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - - - - - -

Sub-Total M/D - 9 - 5 - 5
Manpower Total M/D 2 13 - 11 1 11

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 11 0 9 1 8
TOTAL M/D 2 13 0 11 1 10

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
PROGRESS CONTROL ENGIN MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 18-Sep-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 2 - - 2 INA
- - - - - - INA
- 1 - 1 - 1 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 1 - 1 INA
- - 1 - - 1 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 7 3 10 - 13

- - - - - - INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - 1 - 1 INA
- 1 - 1 - 1
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
4 - 8 - 8 INA
- - - 3 - 3 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - 1 - 1 INA
- - - - - - INA
- - - - - - INA

- 5 - 14 - 14
- 12 3 24 - 27

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 9 3 19 0 22
0 11 3 23 0 26

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 1 -
Mechanical Supervisor - - - - - -
Material Control M/D - - - - - 1
MAT'L Document Control M/D - - - - - -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - - - - - -
Safety Man M/D 1 - - 1 - -
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 2
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 4 - 6 1 6

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - 1 - 1 - 1
Surveyor M/D - - - - - -
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 4 - - - 4
WORKERS

Rigger M/D - - - - - 5
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - 1 4
Rigger (Crane) M/D - - - - 2 -
Electrician M/D - - - - - -

Sub-Total M/D - 5 - 1 3 14
Manpower Total M/D 2 9 - 7 4 20

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 7 0 5 4 18
TOTAL M/D 2 9 0 7 4 20

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
PROGRESS CONTROL ENGIN MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 19-Sep-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 2 - - 2 INA
- - - - - - INA
- 1 - 1 - 1 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - 1 - - 1 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 2 - 3 - 3 INA
- - - - - - INA
- - - - - - INA
- 7 3 10 - 13

- - - - - - INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- 1 - 2 - 2 INA
- - - - - -
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
4 - 8 - 8 INA
- 5 - 5 - 5 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 5 1 4 - 5 INA
- 2 2 - - 2 INA
- - - - - - INA

- 17 3 19 - 22
- 24 6 29 - 35

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 22 6 25 0 31
0 24 6 29 0 35

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 1 -
Mechanical Supervisor - - - - - -
Material Control M/D - - - - - 1
MAT'L Document Control M/D - - - - - -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - - - - - -
Safety Man M/D 1 - - 1 - 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 2
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 4 - 6 1 7

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - 1 - 1 - 1
Surveyor M/D - - - - - -
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 4 - - - 4
WORKERS

Rigger M/D - 5 - - - 2
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - 1 4 1 1 -
Rigger (Crane) M/D - 2 - 2 2 -
Electrician M/D - - - - - -

Sub-Total M/D - 13 4 4 3 7
Manpower Total M/D 2 17 4 10 4 14

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 15 4 8 4 12
TOTAL M/D 2 17 4 10 4 14

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
PROGRESS CONTROL ENGIN MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 20-Sep-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 2 - - 2 INA
- - - - - - INA
- 1 - 1 - 1 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 1 1 - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 2 - 3 - 3 INA
- - - - - - INA
- - - - - - INA
- 8 3 11 - 14

- - - - - - INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
4 - 8 - 8 INA
- 2 - 7 - 7 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 1 1 4 6 INA
- 2 2 2 - 4 INA
- - - - - - INA

- 10 3 20 4 27
- 18 6 31 4 41

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 16 6 27 4 37
0 18 6 31 4 41

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 1 -
Mechanical Supervisor - - - - - -
Material Control M/D - 1 - 1 - 1
MAT'L Document Control M/D - - - - - -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - - - - - -
Safety Man M/D 1 - - 1 - 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 5 - 7 1 6

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - 4 - - - 4
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - 1 - 1 - 1
Surveyor M/D - - - - - -
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 4 - - - 4
WORKERS

Rigger M/D - - - - - 3
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - 1 - 1 - 1
Rigger (Crane) M/D - 2 - 2 - -
Electrician M/D - - - - - -

Sub-Total M/D - 12 - 4 - 13
Manpower Total M/D 2 17 - 11 1 19

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 15 0 9 1 17
TOTAL M/D 2 17 0 11 1 19

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
PROGRESS CONTROL ENGIN MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 21-Sep-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 2 - - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 1 1 - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 7 3 11 - 14

- - - - - - INA
- - - - - - INA
- 4 - 8 - 8 INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
4 - 8 - 8 INA
- 3 - 3 - 3 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - 2 - 2 INA
- - - - - - INA

- 13 - 25 - 25
- 20 3 36 - 39

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 18 3 32 0 35
0 20 3 36 0 39

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 1 -
Mechanical Supervisor - - - - - -
Material Control M/D - 1 - 1 - 1
MAT'L Document Control M/D - - - - - -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - - - - - -
Safety Man M/D 1 - - 1 - 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 5 - 7 1 6

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - 1 - - - 1
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - 1 - 1 - -
Surveyor M/D - - - - - -
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - 2
Semi skill M/D - 4 - - - 4
WORKERS

Rigger M/D - - - - - 3
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - 1 - 1 - 1
Rigger (Crane) M/D - 2 - 2 - -
Electrician M/D - - - - - -

Sub-Total M/D - 9 - 4 - 11
Manpower Total M/D 2 14 - 11 1 17

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 12 0 9 1 15
TOTAL M/D 2 14 0 11 1 17

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
PROGRESS CONTROL ENGIN MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 23-Sep-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 2 - - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 1 1 - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 7 3 11 - 14

- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - 1 - 1 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 2 - 2 - 2 INA
4 - 8 - 8 INA
- 3 - 3 - 3 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - 2 - 2 INA
- - - - - - INA

- 11 - 20 - 20
- 18 3 31 - 34

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 16 3 27 0 30
0 18 3 31 0 34

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 1 -
Mechanical Supervisor - - - - - -
Material Control M/D - 1 - 1 - 1
MAT'L Document Control M/D - - - - - -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - - - - - -
Safety Man M/D 1 - - 1 - 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 5 - 7 1 6

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - 1 - 1 - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - - - - - -
Surveyor M/D - - - - - 1
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - 2 - 2 - -
Semi skill M/D - 4 - 4 - 4
WORKERS

Rigger M/D - 3 - 3 - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - 1 - 1 - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - - - - - 1
-
Sub-Total M/D - 11 - 11 - 6
Manpower Total M/D 2 16 - 18 1 12

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 14 0 16 1 10
TOTAL M/D 2 16 0 18 1 12

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
PROGRESS CONTROL ENGIN MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 24-Sep-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 2 - - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 1 1 - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 7 3 11 - 14

- - - - - - INA
- - - - - - INA
- - - 1 - 1 INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- 1 - 1 - 1 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - 2 - 2 INA
4 - 8 - 8 INA
- - - 3 - 3 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - 1 - 1 INA
- - - - - - INA
- 1 - 1 - 1 INA

- 6 - 17 - 17
- 13 3 28 - 31

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 11 3 24 0 27
0 13 3 28 0 31

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 1 -
Mechanical Supervisor - - - - - -
Material Control M/D - 1 - 1 - 1
MAT'L Document Control M/D - - - - - -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - - - - - -
Safety Man M/D 1 - - 1 - 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 5 - 7 1 6

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - - - - - -
Surveyor M/D - - - - - 1
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 4 - 4 - 4
WORKERS

Rigger M/D - - - - - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - - - - - -
-
Sub-Total M/D - 4 - 4 - 5
Manpower Total M/D 2 9 - 11 1 11

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 7 0 9 1 9
TOTAL M/D 2 9 0 11 1 11

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
PROGRESS CONTROL ENGIN MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 25-Sep-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 2 - - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 1 1 - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 7 3 11 - 14

- - - - - - INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- 1 - 1 - 1 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
4 - 8 - 8 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA

- 5 - 9 - 9
- 12 3 20 - 23

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 10 3 16 0 19
0 12 3 20 0 23

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 1 -
Mechanical Supervisor - - - - - -
Material Control M/D - 1 - 1 - 1
MAT'L Document Control M/D - - - - - -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - - - - - -
Safety Man M/D 1 - - 1 - 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 5 - 7 1 6

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - 1 - 1 - 1
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - - - - - -
Surveyor M/D - 1 - 1 - 1
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - 3
Semi skill M/D - 4 - 4 - 4
WORKERS

Rigger M/D - - - - - 2
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - 1 - 1 - 1
-
Sub-Total M/D - 7 - 7 - 12
Manpower Total M/D 2 12 - 14 1 18

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 10 0 12 1 16
TOTAL M/D 2 12 0 14 1 18

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
MECHANICAL ENGINEER MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 26-Sep-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 2 - - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 1 1 - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 7 3 11 - 14

- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 3 - 3 - 3 INA
4 - 8 - 8 INA
- 2 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA

- 12 - 19 - 19
- 19 3 30 - 33

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 17 3 26 0 29
0 19 3 30 0 33

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 1 -
Mechanical Supervisor - - - - - -
Material Control M/D - 1 - 1 - 1
MAT'L Document Control M/D - - - - - -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - - - - - -
Safety Man M/D 1 - - 1 - 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 5 - 7 1 6

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - 1 - 1 - 1
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - - - - - -
Surveyor M/D - 1 - 1 - 1
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - 3 - 3 - 3
Semi skill M/D - 4 - 4 - 6
WORKERS

Rigger M/D - 2 - 2 - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - 1 - 1 - 1
-
Sub-Total M/D - 12 - 12 - 12
Manpower Total M/D 2 17 - 19 1 18

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 15 0 17 1 16
TOTAL M/D 2 17 0 19 1 18

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
MECHANICAL ENGINEER MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 27-Sep-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 2 - - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 1 1 - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 7 3 11 - 14

- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 3 - 6 - 6 INA
6 - 10 - 10 INA
- - - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA

- 12 - 24 - 24
- 19 3 35 - 38

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 17 3 31 0 34
0 19 3 35 0 38

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 1 -
Mechanical Supervisor - - - - - -
Material Control M/D - 1 - 1 - 1
MAT'L Document Control M/D - - - - - -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - - - - - -
Safety Man M/D 1 - - 1 - 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 5 - 7 1 6

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - 1 - 1 - 1
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - - - - - -
Surveyor M/D - 1 - 1 - 1
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - 3 - 3 - 3
Semi skill M/D - 6 - 6 - 6
WORKERS

Rigger M/D - - - - - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - 1 - 1 - 1
-
Sub-Total M/D - 12 - 12 - 12
Manpower Total M/D 2 17 - 19 1 18

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 15 0 17 1 16
TOTAL M/D 2 17 0 19 1 18

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
MECHANICAL ENGINEER MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 28-Sep-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 2 - - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 1 1 - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 7 3 11 - 14

- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 3 - 6 - 6 INA
6 - 12 - 12 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA

- 12 - 24 - 24
- 19 3 35 - 38

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 17 3 31 0 34
0 19 3 35 0 38

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 1 -
Mechanical Supervisor - - - - - -
Material Control M/D - 1 - 1 - 1
MAT'L Document Control M/D - - - - - -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - - - - - -
Safety Man M/D 1 - - 1 - 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 5 - 7 1 6

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - 1 - 1 - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - - - - - -
Surveyor M/D - 1 - 1 - 1
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - 3 - 3 - -
Semi skill M/D - 6 - 6 - 6
WORKERS

Rigger M/D - - - - - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - 1 - 1 - 1
-
Sub-Total M/D - 12 - 12 - 8
Manpower Total M/D 2 17 - 19 1 14

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 15 0 17 1 12
TOTAL M/D 2 17 0 19 1 14

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
MECHANICAL ENGINEER MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 29-Sep-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 2 - - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 1 1 - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 7 3 11 - 14

- - - - - - INA
- - - - - - INA
- - - 1 - 1 INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - 3 - 3 INA
6 - 12 - 12 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA

- 8 - 20 - 20
- 15 3 31 - 34

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 13 3 27 0 30
0 15 3 31 0 34

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 1 -
Mechanical Supervisor - - - - - -
Material Control M/D - 1 - 1 - 1
MAT'L Document Control M/D - - - - - -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - - - - - -
Safety Man M/D 1 - - 1 - 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 5 - 7 1 6

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - - - - - -
Surveyor M/D - 1 - 1 - 1
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 6 - 6 - 6
WORKERS

Rigger M/D - - - - - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - 1 - 1 - 1
-
Sub-Total M/D - 8 - 8 - 8
Manpower Total M/D 2 13 - 15 1 14

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 11 0 13 1 12
TOTAL M/D 2 13 0 15 1 14

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
MECHANICAL ENGINEER MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 1-Oct-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 2 - - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 1 1 - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 7 3 11 - 14

- - - - - - INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
6 - 12 - 12 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA

- 8 - 16 - 16
- 15 3 27 - 30

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 13 3 23 0 26
0 15 3 27 0 30

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 1 -
Mechanical Supervisor - - - - - -
Material Control M/D - 1 - 1 - 1
MAT'L Document Control M/D - - - - - -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - - - - - -
Safety Man M/D 1 - - 1 - 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 5 - 7 1 6

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - - - - 1 -
Surveyor M/D - 1 - 1 - 1
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 6 - 6 - 6
WORKERS

Rigger M/D - - - - 3 -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - 1 - 1 - 1
-
Sub-Total M/D - 8 - 8 4 8
Manpower Total M/D 2 13 - 15 5 14

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 11 0 13 5 12
TOTAL M/D 2 13 0 15 5 14

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
MECHANICAL ENGINEER MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 2-Oct-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 2 - - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 1 1 - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 7 3 11 - 14

- - - - - - INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- 1 1 - - 1 INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
6 - 12 - 12 INA
- 3 3 - - 3 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA

- 12 4 16 - 20
- 19 7 27 - 34

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 17 7 23 0 30
0 19 7 27 0 34

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 1 -
Mechanical Supervisor - - - - - -
Material Control M/D - 1 - 1 - 1
MAT'L Document Control M/D - - - - - -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - - - - - -
Safety Man M/D 1 - - 1 - 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 5 - 7 1 6

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - - - - - -
Surveyor M/D - 1 - 1 - 1
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 6 - 6 - 6
WORKERS

Rigger M/D - - - - - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - 1 - 1 - 1
-
Sub-Total M/D - 8 - 8 - 8
Manpower Total M/D 2 13 - 15 1 14

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 11 0 13 1 12
TOTAL M/D 2 13 0 15 1 14

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
MECHANICAL ENGINEER MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 3-Oct-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 2 - - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 1 1 - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 7 3 11 - 14

- - - - - - INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
6 - 12 - 12 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA

- 8 - 16 - 16
- 15 3 27 - 30

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 13 3 23 0 26
0 15 3 27 0 30

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 1 -
Mechanical Supervisor - - - - - -
Material Control M/D - 1 - 1 - 1
MAT'L Document Control M/D - - - - - -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - 1 - 1 - 1
Safety Man M/D 1 - - 1 - 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 6 - 8 1 7

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - - - - 1 1
Surveyor M/D - 1 - 1 - 1
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 6 - 6 - 6
WORKERS

Rigger M/D - - - - 3 4
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - 1 - 1 - 1
-
Sub-Total M/D - 8 - 8 4 13
Manpower Total M/D 2 14 - 16 5 20

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 12 0 14 5 18
TOTAL M/D 2 14 0 16 5 20

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
MECHANICAL ENGINEER MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 4-Oct-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 2 - - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 1 - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 8 3 13 - 16

- - - - - - INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- 2 1 1 - 2 INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
6 - 12 - 12 INA
- 7 3 4 - 7 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA

- 17 4 21 - 25
- 25 7 34 - 41

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 23 7 30 0 37
0 25 7 34 0 41

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 1 -
Mechanical Supervisor - - - - - -
Material Control M/D - 1 - 1 - 1
MAT'L Document Control M/D - - - - - -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - 1 - 1 - 1
Safety Man M/D 1 - - 1 - 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 6 - 8 1 7

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D 1 1 - 2 1 1
Surveyor M/D - 1 - 1 - 1
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 6 - 6 - 6
WORKERS

Rigger M/D 3 4 - 7 3 4
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - 1 - 1 - 1
-
Sub-Total M/D 4 13 - 17 4 13
Manpower Total M/D 6 19 - 25 5 20

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 6 17 0 23 5 18
TOTAL M/D 6 19 0 25 5 20

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
MECHANICAL ENGINEER MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 5-Oct-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 2 - - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 1 - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 8 3 13 - 16

- - - - - - INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- 2 2 2 - 4 INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
6 - 12 - 12 INA
- 7 6 8 - 14 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA

- 17 8 26 - 34
- 25 11 39 - 50

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 23 11 35 0 46
0 25 11 39 0 50

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 1 -
Mechanical Supervisor - - - - - -
Material Control M/D - 1 - 1 - 1
MAT'L Document Control M/D - - - - - -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - 1 - 1 - 1
Safety Man M/D 1 - - 1 - 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 6 - 8 1 7

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D 1 1 - 2 - -
Surveyor M/D - 1 - 1 - 1
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 6 - 6 - 6
WORKERS

Rigger M/D 3 4 - 7 - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - 1 - 1 - 1
-
Sub-Total M/D 4 13 - 17 - 8
Manpower Total M/D 6 19 - 25 1 15

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 6 17 0 23 1 13
TOTAL M/D 6 19 0 25 1 15

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
MECHANICAL ENGINEER MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 7-Oct-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 2 - - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 1 - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 8 3 13 - 16

- - - - - - INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - 1 1 - 2 INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
6 - 12 - 12 INA
- - 3 4 - 7 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA

- 8 4 21 - 25
- 16 7 34 - 41

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 14 7 30 0 37
0 16 7 34 0 41

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 1 -
Mechanical Supervisor - - - - - -
Material Control M/D - 1 - 1 - 1
MAT'L Document Control M/D - - - - - -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - 1 - 1 - 1
Safety Man M/D 1 - - 1 - 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 6 - 8 1 7

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - - - - - -
Surveyor M/D - 1 - 1 - 1
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 6 - 6 - 6
WORKERS

Rigger M/D - - - - - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - 1 - 1 - 1
-
Sub-Total M/D - 8 - 8 - 8
Manpower Total M/D 2 14 - 16 1 15

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 12 0 14 1 13
TOTAL M/D 2 14 0 16 1 15

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
MECHANICAL ENGINEER MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 8-Oct-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 2 - - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 1 - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 8 3 13 - 16

- - - - - - INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
6 - 12 - 12 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA

- 8 - 16 - 16
- 16 3 29 - 32

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 14 3 25 0 28
0 16 3 29 0 32

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 1 -
Mechanical Supervisor - - - - - -
Material Control M/D - 1 - 1 - 1
MAT'L Document Control M/D - - - - - -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - 1 - 1 - 1
Safety Man M/D 1 - - 1 - 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 6 - 8 1 7

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - - - - - -
Surveyor M/D - 1 - 1 - 1
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 6 - 6 - 6
WORKERS

Rigger M/D - - - - - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - 1 - 1 - 1
-
Sub-Total M/D - 8 - 8 - 8
Manpower Total M/D 2 14 - 16 1 15

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 12 0 14 1 13
TOTAL M/D 2 14 0 16 1 15

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
MECHANICAL ENGINEER MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 9-Oct-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 2 - - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 1 - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 8 3 13 - 16

- - - - - - INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
6 - 12 - 12 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA

- 8 - 16 - 16
- 16 3 29 - 32

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 14 3 25 0 28
0 16 3 29 0 32

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 1 -
Mechanical Supervisor - - - - - -
Material Control M/D - 1 - 1 - 1
MAT'L Document Control M/D - - - - - -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - 1 - 1 - 1
Safety Man M/D 1 - - 1 - 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 6 - 8 1 7

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - - - - - -
Surveyor M/D - 1 - 1 - 1
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 6 - 6 - 6
WORKERS

Rigger M/D - - - - - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - 1 - 1 - 1
-
Sub-Total M/D - 8 - 8 - 8
Manpower Total M/D 2 14 - 16 1 15

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 12 0 14 1 13
TOTAL M/D 2 14 0 16 1 15

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
MECHANICAL ENGINEER MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 13/10/2013 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 2 - - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 1 - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 8 3 13 - 16

- - - - - - INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
6 - 12 - 12 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA

- 8 - 16 - 16
- 16 3 29 - 32

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 14 3 25 0 28
0 16 3 29 0 32

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 1 -
Mechanical Supervisor - - - - - -
Material Control M/D - 1 - 1 - 1
MAT'L Document Control M/D - - - - - -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - 1 - 1 - 1
Safety Man M/D 1 - - 1 - 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 6 - 8 1 7

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - - - - - -
Surveyor M/D - 1 - 1 - 1
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 6 - 6 - 6
WORKERS

Rigger M/D - - - - - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - 1 - 1 - 1
-
Sub-Total M/D - 8 - 8 - 8
Manpower Total M/D 2 14 - 16 1 15

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 12 0 14 1 13
TOTAL M/D 2 14 0 16 1 15

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
MECHANICAL ENGINEER MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 10-Oct-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 2 - - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 1 - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 8 3 13 - 16

- - - - - - INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
6 - 12 - 12 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA

- 8 - 16 - 16
- 16 3 29 - 32

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 14 3 25 0 28
0 16 3 29 0 32

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 1 -
Mechanical Supervisor - - - - - -
Material Control M/D - 1 - 1 - 1
MAT'L Document Control M/D - - - - - -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - 1 - 1 - 1
Safety Man M/D 1 - - 1 - 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 6 - 8 1 7

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - - - - - -
Surveyor M/D - 1 - 1 - 1
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 6 - 6 - 6
WORKERS

Rigger M/D - - - - - 5
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - 1 - 1 - 1
-
Sub-Total M/D - 8 - 8 - 13
Manpower Total M/D 2 14 - 16 - 13

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 12 0 14 1 18
TOTAL M/D 2 14 0 16 0 20

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
MECHANICAL ENGINEER MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 10-Oct-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 2 - - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 1 - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 8 3 13 - 16

- - - - - - INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
6 - 12 - 12 INA
- 5 - 5 - 5 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA

- 13 - 21 - 21
- 21 3 34 - 37

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 19 3 30 0 33
0 21 3 34 0 37

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 1 -
Mechanical Supervisor - - - - - -
Material Control M/D - 1 - 1 - 1
MAT'L Document Control M/D - - - - - -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - 1 - 1 - 1
Safety Man M/D 1 - - 1 - 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 6 - 8 1 7

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - - - - - -
Surveyor M/D - 1 - 1 - 1
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 6 - 6 - 6
WORKERS

Rigger M/D - - - - - 5
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - 1 - 1 - 1
-
Sub-Total M/D - 8 - 8 - 13
Manpower Total M/D 2 14 - 16 - 13

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 12 0 14 1 18
TOTAL M/D 2 14 0 16 0 20

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
MECHANICAL ENGINEER MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 14-Oct-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 2 - - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 1 - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 8 3 13 - 16

- - - - - - INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
6 - 12 - 12 INA
- 5 - 5 - 5 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA

- 13 - 21 - 21
- 21 3 34 - 37

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 19 3 30 0 33
0 21 3 34 0 37

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 1 -
Mechanical Supervisor - - - - - -
Material Control M/D - 1 - 1 - 1
MAT'L Document Control M/D - - - - - -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - 1 - 1 - 1
Safety Man M/D 1 - - 1 - 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 6 - 8 1 7

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - - - - - -
Surveyor M/D - 1 - 1 - 1
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 6 - 6 - 6
WORKERS

Rigger M/D - - - - - 5
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - 1 - 1 - 1
-
Sub-Total M/D - 8 - 8 - 13
Manpower Total M/D 2 14 - 16 - 13

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 12 0 14 1 18
TOTAL M/D 2 14 0 16 0 20

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
MECHANICAL ENGINEER MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 16-Oct-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 2 - - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 1 - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 8 3 13 - 16

- - - - - - INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
6 - 12 - 12 INA
- 5 - 5 - 5 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA

- 13 - 21 - 21
- 21 3 34 - 37

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 19 3 30 0 33
0 21 3 34 0 37

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 1 -
Mechanical Supervisor - - - - - -
Material Control M/D - 1 - 1 - 1
MAT'L Document Control M/D - - - - - -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - 1 - 1 - 1
Safety Man M/D 1 - - 1 - 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 6 - 8 1 7

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - - - -
Surveyor M/D - 1 - 1 - 1
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 6 - 6 - 6
WORKERS

Rigger M/D - - - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - 1 - 1 - 1
-
Sub-Total M/D - 8 - 8 - 8
Manpower Total M/D 2 14 - 16 1 15

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 12 0 14 1 13
TOTAL M/D 2 14 0 16 1 15

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
MECHANICAL ENGINEER MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 17-Oct-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 2 - - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 1 - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 8 3 13 - 16

- - - - - - INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
6 - 12 - 12 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA

- 8 - 16 - 16
- 16 3 29 - 32

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 14 3 25 0 28
0 16 3 29 0 32

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 1 -
Mechanical Supervisor - - - - - -
Material Control M/D - 1 - 1 - 1
MAT'L Document Control M/D - - - - - -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - 1 - 1 - 1
Safety Man M/D 1 - - 1 - 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 6 - 8 1 7

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - - - -
Surveyor M/D - 1 - 1 - 1
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 6 - 6 - 6
WORKERS

Rigger M/D - - - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - 1 - 1 - 1
-
Sub-Total M/D - 8 - 8 - 8
Manpower Total M/D 2 14 - 16 1 15

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 12 0 14 1 13
TOTAL M/D 2 14 0 16 1 15

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
MECHANICAL ENGINEER MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 18-Oct-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 2 - - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 1 - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 8 3 13 - 16

- - - - - - INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
6 - 12 - 12 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA

- 8 - 16 - 16
- 16 3 29 - 32

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 14 3 25 0 28
0 16 3 29 0 32

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 1 -
Mechanical Supervisor - - - - - -
Material Control M/D - 1 - 1 - 1
MAT'L Document Control M/D - - - - - -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - 1 - 1 - 1
Safety Man M/D 1 - - 1 - 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 6 - 8 1 7

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - - - -
Surveyor M/D - 1 - 1 - 1
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 6 - 6 - 8
WORKERS

Rigger M/D - - - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - 1 - 1 - 1
-
Sub-Total M/D - 8 - 8 - 10
Manpower Total M/D 2 14 - 16 1 17

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 12 0 14 1 15
TOTAL M/D 2 14 0 16 1 17

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
MECHANICAL ENGINEER MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 19-Oct-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 2 - - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 1 - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 8 3 13 - 16

- - - - - - INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
8 - 14 - 14 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA

- 10 - 18 - 18
- 18 3 31 - 34

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 16 3 27 0 30
0 18 3 31 0 34

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 2 -
Mechanical Supervisor - - - - - -
Material Control M/D - 1 - 1 - 1
MAT'L Document Control M/D - - - - - -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - 1 - 1 - 1
Safety Man M/D 1 - - 1 - 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 6 - 8 2 7

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - - - -
Surveyor M/D - 1 - 1 - -
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 8 - 8 - 10
WORKERS

Rigger M/D - - - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - 1 - 1 - 1
-
Sub-Total M/D - 10 - 10 - 11
Manpower Total M/D 2 16 - 18 2 18

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 14 0 16 2 16
TOTAL M/D 2 16 0 18 2 18

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
MECHANICAL ENGINEER MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 21-Oct-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 2 3 - - 3 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 1 - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 9 4 13 - 17

- - - - - - INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- - - 1 - 1 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
10 - 18 - 18 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA

- 11 - 21 - 21
- 20 4 34 - 38

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 18 4 30 0 34
0 20 4 34 0 38

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 2 -
Mechanical Supervisor - - - - - -
Material Control M/D - 1 - 1 - 1
MAT'L Document Control M/D - - - - - -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - 1 - 1 - 1
Safety Man M/D 1 - - 1 - 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 6 - 8 2 7

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - - - -
Surveyor M/D - 1 - 1 - -
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 10 - 10 - 10
WORKERS

Rigger M/D - - - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - 1 - 1 - 1
-
Sub-Total M/D - 12 - 12 - 11
Manpower Total M/D 2 18 - 20 2 18

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 16 0 18 2 16
TOTAL M/D 2 18 0 20 2 18

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
MECHANICAL ENGINEER MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 24-Oct-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 2 3 - - 3 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 1 - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 9 4 13 - 17

- - - - - - INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- - - 1 - 1 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
10 - 20 - 20 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA

- 11 - 23 - 23
- 20 4 36 - 40

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 18 4 32 0 36
0 20 4 36 0 40

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 2 -
Mechanical Supervisor - - - - - -
Material Control M/D - 1 - 1 - 1
MAT'L Document Control M/D - - - - 1 -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - 1 - 1 - 1
Safety Man M/D 1 - - 1 - 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 6 - 8 3 7

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - - - -
Surveyor M/D - 1 - 1 - -
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 10 - 10 - 10
WORKERS

Rigger M/D - - - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - 1 - 1 - 1
-
Sub-Total M/D - 12 - 12 - 11
Manpower Total M/D 2 18 - 20 3 18

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 16 0 18 3 16
TOTAL M/D 2 18 0 20 3 18

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
MECHANICAL ENGINEER MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 25-Oct-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 2 3 - - 3 INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 - - 1 INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 1 - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 10 5 13 - 18

- - - - - - INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- - - 1 - 1 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
10 - 20 - 20 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA

- 11 - 23 - 23
- 21 5 36 - 41

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 19 5 32 0 37
0 21 5 36 0 41

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 2 -
Mechanical Supervisor - - - - - -
Material Control M/D - 1 - 1 - 1
MAT'L Document Control M/D - - - - 1 -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - 1 - 1 - 1
Safety Man M/D 1 - - 1 - 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 6 - 8 3 7

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - - - -
Surveyor M/D - 1 - 1 - -
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 10 - 10 - 10
WORKERS

Rigger M/D - - - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - 1 - 1 - 1
-
Sub-Total M/D - 12 - 12 - 11
Manpower Total M/D 2 18 - 20 3 18

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 16 0 18 3 16
TOTAL M/D 2 18 0 20 3 18

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
MECHANICAL ENGINEER MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 27-Oct-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 2 3 - - 3 INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 - - 1 INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 1 - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 10 5 13 - 18

- - - - - - INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- - - 1 - 1 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
10 - 20 - 20 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA

- 11 - 23 - 23
- 21 5 36 - 41

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 19 5 32 0 37
0 21 5 36 0 41

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 2 -
Mechanical Supervisor - - - - - -
Material Control M/D - 1 - 1 - 1
MAT'L Document Control M/D - - - - 1 -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - 1 - 1 - 1
Safety Man M/D 1 - - 1 - 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 6 - 8 3 7

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - - - -
Surveyor M/D - 1 - 1 - -
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 10 - 10 - 10
WORKERS

Rigger M/D - - - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - 1 - 1 - 1
-
Sub-Total M/D - 12 - 12 - 11
Manpower Total M/D 2 18 - 20 3 18

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 16 0 18 3 16
TOTAL M/D 2 18 0 20 3 18

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
MECHANICAL ENGINEER MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 28-Oct-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 2 3 - - 3 INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 - - 1 INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 1 - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 10 5 13 - 18

- - - - - - INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- - - 1 - 1 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
10 - 20 - 20 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA

- 11 - 23 - 23
- 21 5 36 - 41

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 19 5 32 0 37
0 21 5 36 0 41

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 2 -
Mechanical Supervisor - - - - - -
Material Control M/D - 1 - 1 - 1
MAT'L Document Control M/D - - - - 1 -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - 1 - 1 - 1
Safety Man M/D 1 - - 1 - 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 6 - 8 3 7

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - - - -
Surveyor M/D - 1 - 1 - -
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 10 - 10 - 10
WORKERS

Rigger M/D - - - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - 1 - 1 - 1
-
Sub-Total M/D - 12 - 12 - 11
Manpower Total M/D 2 18 - 20 3 18

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 16 0 18 3 16
TOTAL M/D 2 18 0 20 3 18

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
MECHANICAL ENGINEER MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 29-Oct-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 2 3 - - 3 INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 - - 1 INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 1 - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 10 5 13 - 18

- - - - - - INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- - - 1 - 1 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
10 - 20 - 20 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA

- 11 - 23 - 23
- 21 5 36 - 41

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 19 5 32 0 37
0 21 5 36 0 41

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 2 -
Mechanical Supervisor - - - - - -
Material Control M/D - 1 - 1 - 1
MAT'L Document Control M/D - - - - 1 -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - 1 - 1 - 1
Safety Man M/D 1 - - 1 - 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 6 - 8 3 7

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - - - -
Surveyor M/D - 1 - 1 - -
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 10 - 10 - 10
WORKERS

Rigger M/D - - - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - 1 - 1 - 1
-
Sub-Total M/D - 12 - 12 - 11
Manpower Total M/D 2 18 - 20 3 18

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 16 0 18 3 16
TOTAL M/D 2 18 0 20 3 18

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
MECHANICAL ENGINEER MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 30-Oct-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 2 3 - - 3 INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 - - 1 INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 1 - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 10 5 13 - 18

- - - - - - INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- - - 1 - 1 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
10 - 20 - 20 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA

- 11 - 23 - 23
- 21 5 36 - 41

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 19 5 32 0 37
0 21 5 36 0 41

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 2 -
Mechanical Supervisor - - - - - -
Material Control M/D - 1 - 1 - 1
MAT'L Document Control M/D - - - - 1 -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - 1 - 1 - 1
Safety Man M/D 1 - - 1 - 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 6 - 8 3 7

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - - - -
Surveyor M/D - 1 - 1 - -
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 10 - 10 - 10
WORKERS

Rigger M/D - - - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - 1 - 1 - 1
-
Sub-Total M/D - 12 - 12 - 11
Manpower Total M/D 2 18 - 20 3 18

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 16 0 18 3 16
TOTAL M/D 2 18 0 20 3 18

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
MECHANICAL ENGINEER MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 31-Oct-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 2 3 - - 3 INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 - - 1 INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 1 - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 10 5 13 - 18

- - - - - - INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- - - 1 - 1 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
10 - 20 - 20 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA

- 11 - 23 - 23
- 21 5 36 - 41

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 19 5 32 0 37
0 21 5 36 0 41

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 2 -
Mechanical Supervisor - - - - - -
Material Control M/D - 1 - 1 - 1
MAT'L Document Control M/D - - - - 1 -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - 1 - 1 - 1
Safety Man M/D 1 - - 1 - 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 6 - 8 3 7

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - - - -
Surveyor M/D - 1 - 1 - -
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 10 - 10 - 10
WORKERS

Rigger M/D - - - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - 1 - 1 - 1
-
Sub-Total M/D - 12 - 12 - 11
Manpower Total M/D 2 18 - 20 3 18

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 16 0 18 3 16
TOTAL M/D 2 18 0 20 3 18

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
MECHANICAL ENGINEER MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 1-Nov-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 2 3 - - 3 INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 - - 1 INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 1 - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 10 5 13 - 18

- - - - - - INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- - - 1 - 1 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
10 - 20 - 20 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA

- 11 - 23 - 23
- 21 5 36 - 41

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 19 5 32 0 37
0 21 5 36 0 41

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 2 -
Mechanical Supervisor - - - - - -
Material Control M/D - 1 - 1 - 1
MAT'L Document Control M/D - - - - 1 -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - 1 - 1 - 1
Safety Man M/D 1 - - 1 - 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 6 - 8 3 7

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - - - -
Surveyor M/D - 1 - 1 - -
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 10 - 10 - 10
WORKERS

Rigger M/D - - - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - 1 - 1 - 1
-
Sub-Total M/D - 12 - 12 - 11
Manpower Total M/D 2 18 - 20 3 18

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 16 0 18 3 16
TOTAL M/D 2 18 0 20 3 18

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
MECHANICAL ENGINEER MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 2-Nov-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 2 3 - - 3 INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 - - 1 INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 1 - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 10 5 13 - 18

- - - - - - INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- - - 1 - 1 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
10 - 20 - 20 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA

- 11 - 23 - 23
- 21 5 36 - 41

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 19 5 32 0 37
0 21 5 36 0 41

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 2 -
Mechanical Supervisor - - - - - -
Material Control M/D - 1 - 1 - 1
MAT'L Document Control M/D - - - - 1 -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - 1 - 1 - 1
Safety Man M/D 1 - - 1 - 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 6 - 8 3 7

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - - - -
Surveyor M/D - 1 - 1 - -
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 10 - 10 - 10
WORKERS

Rigger M/D - - - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - 1 - 1 - 1
-
Sub-Total M/D - 12 - 12 - 11
Manpower Total M/D 2 18 - 20 3 18

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 16 0 18 3 16
TOTAL M/D 2 18 0 20 3 18

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
MECHANICAL ENGINEER MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 3-Nov-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 2 3 - - 3 INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 - - 1 INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 1 - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 10 5 13 - 18

- - - - - - INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- - - 1 - 1 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
10 - 20 - 20 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA

- 11 - 23 - 23
- 21 5 36 - 41

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 19 5 32 0 37
0 21 5 36 0 41

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 2 -
Mechanical Supervisor - - - - - -
Material Control M/D - 1 - 1 - 1
MAT'L Document Control M/D - - - - 1 -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - 1 - 1 - 1
Safety Man M/D 1 - - 1 - 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 6 - 8 3 7

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - - - -
Surveyor M/D - 1 - 1 - -
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 10 - 10 - 10
WORKERS

Rigger M/D - - - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - 1 - 1 - 1
-
Sub-Total M/D - 12 - 12 - 11
Manpower Total M/D 2 18 - 20 3 18

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 16 0 18 3 16
TOTAL M/D 2 18 0 20 3 18

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
MECHANICAL ENGINEER MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 4-Nov-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 2 3 - - 3 INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 - - 1 INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 1 - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 10 5 13 - 18

- - - - - - INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- - - 1 - 1 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
10 - 20 - 20 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA

- 11 - 23 - 23
- 21 5 36 - 41

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 19 5 32 0 37
0 21 5 36 0 41

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 2 -
Mechanical Supervisor - - - - - -
Material Control M/D - 1 - 1 - 1
MAT'L Document Control M/D - - - - 1 -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - 1 - 1 - 1
Safety Man M/D 1 - - 1 - 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 6 - 8 3 7

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - - - -
Surveyor M/D - 1 - 1 - -
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 10 - 10 - 10
WORKERS

Rigger M/D - - 5 -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - 1 - 1 - 1
-
Sub-Total M/D - 12 - 12 5 11
Manpower Total M/D 2 18 - 20 8 18

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 16 0 18 8 16
TOTAL M/D 2 18 0 20 8 18

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
MECHANICAL ENGINEER MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 5-Nov-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 2 3 - - 3 INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 - - 1 INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 1 - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 10 5 13 - 18

- - - - - - INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- - - 1 - 1 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
10 - 20 - 20 INA
- 5 5 - - 5 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA

- 16 5 23 - 28
- 26 10 36 - 46

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 24 10 32 0 42
0 26 10 36 0 46

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 2 -
Mechanical Supervisor - - - - - -
Material Control M/D - 1 - 1 - 1
MAT'L Document Control M/D - - - - 1 -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - 1 - 1 - 1
Safety Man M/D 1 - - 1 - 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 6 - 8 3 7

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - - - -
Surveyor M/D - 1 - 1 - -
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 10 - 10 - 10
WORKERS

Rigger M/D - - - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - 1 - 1 - 1
-
Sub-Total M/D - 12 - 12 - 11
Manpower Total M/D 2 18 - 20 3 18

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 16 0 18 3 16
TOTAL M/D 2 18 0 20 3 18

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
MECHANICAL ENGINEER MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 6-Nov-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 2 3 - - 3 INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 - - 1 INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 1 - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 10 5 13 - 18

- - - - - - INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- - - 1 - 1 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
10 - 20 - 20 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA

- 11 - 23 - 23
- 21 5 36 - 41

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 19 5 32 0 37
0 21 5 36 0 41

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 2 -
Mechanical Supervisor - - - - - -
Material Control M/D - 1 - 1 - 1
MAT'L Document Control M/D - - - - 1 -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - 1 - 1 - 1
Safety Man M/D 1 - - 1 - 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 6 - 8 3 7

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - - - -
Surveyor M/D - 1 - 1 - -
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 10 - 10 - 10
WORKERS

Rigger M/D - - - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - 1 - 1 - 1
-
Sub-Total M/D - 12 - 12 - 11
Manpower Total M/D 2 18 - 20 3 18

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 16 0 18 3 16
TOTAL M/D 2 18 0 20 3 18

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
MECHANICAL ENGINEER MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 7-Nov-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 2 3 - - 3 INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 - - 1 INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 1 - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 10 5 13 - 18

- - - - - - INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- - - 1 - 1 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 10 - 20 - 20 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA

- 11 - 23 - 23
- 21 5 36 - 41

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 19 5 32 0 37
0 21 5 36 0 41

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 2 -
Mechanical Supervisor - - - - - -
Material Control M/D - 1 - 1 - 1
MAT'L Document Control M/D - - - - 1 -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - 1 - 1 - 1
Safety Man M/D 1 - - 1 - 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 6 - 8 3 7

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - - - -
Surveyor M/D - 1 - 1 - -
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 10 - 10 - 10
WORKERS

Rigger M/D - - - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - 1 - 1 - 1
-
Sub-Total M/D - 12 - 12 - 11
Manpower Total M/D 2 18 - 20 3 18

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 16 0 18 3 16
TOTAL M/D 2 18 0 20 3 18

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
MECHANICAL ENGINEER MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 8-Nov-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 2 3 - - 3 INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 - - 1 INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 1 - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 10 5 13 - 18

- - - - - - INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- - - 1 - 1 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 10 - 20 - 20 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA

- 11 - 23 - 23
- 21 5 36 - 41

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 19 5 32 0 37
0 21 5 36 0 41

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 2 -
Mechanical Supervisor - - - - - -
Material Control M/D - 1 - 1 - 1
MAT'L Document Control M/D - - - - 1 -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - 1 - 1 - 1
Safety Man M/D 1 - - 1 - 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 6 - 8 3 7

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - - - -
Surveyor M/D - 1 - 1 - -
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 10 - 10 - 10
WORKERS

Rigger M/D - - - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - 1 - 1 - 1
-
Sub-Total M/D - 12 - 12 - 11
Manpower Total M/D 2 18 - 20 3 18

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 16 0 18 3 16
TOTAL M/D 2 18 0 20 3 18

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
MECHANICAL ENGINEER MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 9-Nov-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 2 3 - - 3 INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 - - 1 INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 1 - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 10 5 13 - 18

- - - - - - INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- - - 1 - 1 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 10 - 20 - 20 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA

- 11 - 23 - 23
- 21 5 36 - 41

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 19 5 32 0 37
0 21 5 36 0 41

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 2 -
Mechanical Supervisor - - - - - -
Material Control M/D - 1 - 1 - 1
MAT'L Document Control M/D - - - - 1 -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - 1 - 1 - 1
Safety Man M/D 1 - - 1 - 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 6 - 8 3 7

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - - - -
Surveyor M/D - 1 - 1 - -
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 10 - 10 - 10
WORKERS

Rigger M/D - - - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - 1 - 1 - 1
-
Sub-Total M/D - 12 - 12 - 11
Manpower Total M/D 2 18 - 20 3 18

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 16 0 18 3 16
TOTAL M/D 2 18 0 20 3 18

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
MECHANICAL ENGINEER MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 11-Nov-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 2 3 - - 3 INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 - - 1 INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 1 - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 10 5 13 - 18

- - - - - - INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- - - 1 - 1 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 10 - 20 - 20 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA

- 11 - 23 - 23
- 21 5 36 - 41

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 19 5 32 0 37
0 21 5 36 0 41

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 2 -
Mechanical Supervisor - - - - - -
Material Control M/D - 1 - 1 - 1
MAT'L Document Control M/D - - - - 1 -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - 1 - 1 - 1
Safety Man M/D 1 - - 1 - 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 6 - 8 3 7

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - - - -
Surveyor M/D - 1 - 1 - -
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 10 - 10 - 10
WORKERS

Rigger M/D - - - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - 1 - 1 - 1
-
Sub-Total M/D - 12 - 12 - 11
Manpower Total M/D 2 18 - 20 3 18

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 16 0 18 3 16
TOTAL M/D 2 18 0 20 3 18

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
MECHANICAL ENGINEER MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 12-Nov-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 2 3 - - 3 INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 - - 1 INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 1 - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 10 5 13 - 18

- - - - - - INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- - - 1 - 1 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 10 - 20 - 20 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA

- 11 - 23 - 23
- 21 5 36 - 41

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 19 5 32 0 37
0 21 5 36 0 41

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 2 -
Mechanical Supervisor - - - - - -
Material Control M/D - 1 - 1 - 1
MAT'L Document Control M/D - - - - 1 -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - 1 - 1 - 1
Safety Man M/D 1 - - 1 - 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 6 - 8 3 7

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - - - -
Surveyor M/D - 1 - 1 - -
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 10 - 10 - 10
WORKERS

Rigger M/D - - - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - 1 - 1 - 1
-
Sub-Total M/D - 12 - 12 - 11
Manpower Total M/D 2 18 - 20 3 18

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 16 0 18 3 16
TOTAL M/D 2 18 0 20 3 18

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
MECHANICAL ENGINEER MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 13-Nov-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 2 3 - - 3 INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 - - 1 INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 1 - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 10 5 13 - 18

- - - - - - INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- - - 1 - 1 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 10 - 20 - 20 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA

- 11 - 23 - 23
- 21 5 36 - 41

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 19 5 32 0 37
0 21 5 36 0 41

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 2 -
Mechanical Supervisor - - - - - -
Material Control M/D - 1 - 1 - 1
MAT'L Document Control M/D - - - - 1 -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - 1 - 1 - 1
Safety Man M/D 1 - - 1 - 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 6 - 8 3 7

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - - - -
Surveyor M/D - 1 - 1 - -
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 10 - 10 - 14
WORKERS

Rigger M/D - - - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - 1 - 1 - 1
-
Sub-Total M/D - 12 - 12 - 15
Manpower Total M/D 2 18 - 20 3 22

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 16 0 18 3 20
TOTAL M/D 2 18 0 20 3 22

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
MECHANICAL ENGINEER MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 14-Nov-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 2 3 - - 3 INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 - - 1 INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 1 - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 10 5 13 - 18

- - - - - - INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- - - 1 - 1 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 14 - 24 - 24 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA

- 15 - 27 - 27
- 25 5 40 - 45

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 23 5 36 0 41
0 25 5 40 0 45

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 2 -
Mechanical Supervisor - - - - - -
Material Control M/D - 1 - 1 - 1
MAT'L Document Control M/D - - - - 1 -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - 1 - 1 - 1
Safety Man M/D 1 - - 1 - 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 6 - 8 3 7

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - - - -
Surveyor M/D - 1 - 1 - -
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 14 - 14 - 14
WORKERS

Rigger M/D - - - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - 1 - 1 - 1
-
Sub-Total M/D - 16 - 16 - 15
Manpower Total M/D 2 22 - 24 3 22

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 20 0 22 3 20
TOTAL M/D 2 22 0 24 3 22

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
MECHANICAL ENGINEER MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 16-Nov-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 2 3 - - 3 INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 - - 1 INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 1 - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 10 5 13 - 18

- - - - - - INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- - - 1 - 1 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 14 - 28 - 28 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA

- 15 - 31 - 31
- 25 5 44 - 49

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 23 5 40 0 45
0 25 5 44 0 49

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 2 -
Mechanical Supervisor - - - - - -
Material Control M/D - 1 - 1 - 1
MAT'L Document Control M/D - - - - 1 -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - 1 - 1 - 1
Safety Man M/D 1 - - 1 - 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 6 - 8 3 7

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - - - -
Surveyor M/D - 1 - 1 - -
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 14 - 14 - 14
WORKERS

Rigger M/D - - - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - 1 - 1 - 1
-
Sub-Total M/D - 16 - 16 - 15
Manpower Total M/D 2 22 - 24 3 22

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 20 0 22 3 20
TOTAL M/D 2 22 0 24 3 22

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
MECHANICAL ENGINEER MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 17-Nov-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 2 3 - - 3 INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 - - 1 INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 1 - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 10 5 13 - 18

- - - - - - INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- - - 1 - 1 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 14 - 28 - 28 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA

- 15 - 31 - 31
- 25 5 44 - 49

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 23 5 40 0 45
0 25 5 44 0 49

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - - -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 - - 1 2 -
Mechanical Supervisor - - - - - -
Material Control M/D - 1 - 1 - 1
MAT'L Document Control M/D - - - - 1 -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - 1 - 1 - 1
Safety Man M/D 1 - - 1 - 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 1
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 2 6 - 8 3 7

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - -
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - - - -
Surveyor M/D - 1 - 1 - -
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - -
Tig Welder M/D - - - - - -
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - 14 - 14 - 14
WORKERS

Rigger M/D - - - -
Helper M/D - - - - - -
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - 1 - 1 - 1
-
Sub-Total M/D - 16 - 16 - 15
Manpower Total M/D 2 22 - 24 3 22

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 2 20 0 22 3 20
TOTAL M/D 2 22 0 24 3 22

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
MECHANICAL ENGINEER MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 18-Nov-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 2 3 - - 3 INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 - - 1 INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- 1 1 1 - 2 INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 10 5 13 - 18

- - - - - - INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- - - 1 - 1 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 14 - 28 - 28 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA

- 15 - 31 - 31
- 25 5 44 - 49

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 23 5 40 0 45
0 25 5 44 0 49

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - 1 -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 1 - 2 1 1
Mechanical Supervisor M/D - - - - - -
Material Control M/D 1 - - 1 1 -
MAT'L Document Control M/D - - - - 1 -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - 1 - 1 - 1
Safety Man M/D 1 1 - 2 1 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 1 - 1 - 2
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 3 7 - 10 5 8

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - - - - - 1
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - - - -
Surveyor M/D - 1 - 1 - 1
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - - - - - 3
Millwright M/D - - - - - 5
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - - - - - -
WORKERS

Rigger M/D - - - -
Helper M/D - 6 - 6 - 6
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - 1 - 1 - 1
-
Sub-Total M/D - 8 - 8 - 17
Manpower Total M/D 3 15 - 18 5 25

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 3 13 0 16 5 23
TOTAL M/D 3 15 0 18 5 25

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
MECHANICAL ENGINEER MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 19-Nov-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- 1 1 - - 1 INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 2 2 2 - 4 INA
- - - - - - INA
- 1 2 - - 2 INA
- 1 1 - - 1 INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- 2 2 2 - 4 INA
- - - - - - INA
- 2 - 3 - 3 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 13 8 15 - 23

- 1 - 1 - 1 INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- 3 - 3 - 3 INA
- 5 - 5 - 5 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 6 - 12 - 12 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA

- 17 - 25 - 25
- 30 8 40 - 48

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 28 8 36 0 44
0 30 8 40 0 48

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - 1 -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 1 - 2 1 1
Mechanical Supervisor M/D - - - - - -
Material Control M/D 1 - - 1 1 -
MAT'L Document Control M/D 1 - - 1 1 -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - 1 - 1 - 1
Safety Man M/D 1 1 - 2 1 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 2 - 2 - 2
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 4 8 - 12 5 8

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - 1 - 1 - 1
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - - - -
Surveyor M/D - 1 - 1 - 1
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - 3 - 3 - 3
Millwright M/D - 5 - 5 - 5
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - - - - - -
WORKERS

Rigger M/D - - - -
Helper M/D - 6 - 6 - 6
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - 1 - 1 - 1
-
Sub-Total M/D - 17 - 17 - 17
Manpower Total M/D 4 25 - 29 5 25

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 4 23 0 27 5 23
TOTAL M/D 4 25 0 29 5 25

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
MECHANICAL ENGINEER MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 20-Nov-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- 1 1 - - 1 INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 2 2 2 - 4 INA
- - - - - - INA
- 1 2 - - 2 INA
- 1 2 - - 2 INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- 2 2 2 - 4 INA
- - - - - - INA
- 2 - 4 - 4 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 13 9 16 - 25

- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- 3 - 6 - 6 INA
- 5 - 10 - 10 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 6 - 12 - 12 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA

- 17 - 34 - 34
- 30 9 50 - 59

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 28 9 46 0 55
0 30 9 50 0 59

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - 1 -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 1 - 2 1 1
Mechanical Supervisor M/D - - - - - -
Material Control M/D 1 - - 1 1 -
MAT'L Document Control M/D 1 - - 1 1 -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - 1 - 1 - 1
Safety Man M/D 1 1 - 2 1 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 2 - 2 - 2
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 4 8 - 12 5 8

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - 1 - 1 - 1
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - - - -
Surveyor M/D - 1 - 1 - 1
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - 3 - 3 - 3
Millwright M/D - 5 - 5 - 5
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - - - - - -
WORKERS

Rigger M/D - - - -
Helper M/D - 6 - 6 - 6
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - 1 - 1 - 1
-
Sub-Total M/D - 17 - 17 - 17
Manpower Total M/D 4 25 - 29 5 25

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 4 23 0 27 5 23
TOTAL M/D 4 25 0 29 5 25

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
MECHANICAL ENGINEER MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 21-Nov-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- 1 1 - - 1 INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 2 2 2 - 4 INA
- - - - - - INA
- 1 2 - - 2 INA
- 1 2 - - 2 INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- 2 2 2 - 4 INA
- - - - - - INA
- 2 - 4 - 4 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 13 9 16 - 25

- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- 3 - 6 - 6 INA
- 5 - 10 - 10 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 6 - 12 - 12 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA

- 17 - 34 - 34
- 30 9 50 - 59

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 28 9 46 0 55
0 30 9 50 0 59

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - 1 -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 1 - 2 1 1
Mechanical Supervisor M/D - - - - - -
Material Control M/D 1 - - 1 1 -
MAT'L Document Control M/D 1 - - 1 1 -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - 1 - 1 - 1
Safety Man M/D 1 1 - 2 1 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 2 - 2 - 2
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 4 8 - 12 5 8

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - 1 - 1 - 1
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - - - -
Surveyor M/D - 1 - 1 - 1
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - 3 - 3 - 3
Millwright M/D - 5 - 5 - 5
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - - - - - -
WORKERS

Rigger M/D - - - -
Helper M/D - 6 - 6 - 6
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - 1 - 1 - 1
-
Sub-Total M/D - 17 - 17 - 17
Manpower Total M/D 4 25 - 29 5 25

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 4 23 0 27 5 23
TOTAL M/D 4 25 0 29 5 25

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
MECHANICAL ENGINEER MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 22-Nov-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- 1 1 - - 1 INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 2 2 2 - 4 INA
- - - - - - INA
- 1 2 - - 2 INA
- 1 2 - - 2 INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- 2 2 2 - 4 INA
- - - - - - INA
- 2 - 4 - 4 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 13 9 16 - 25

- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- 3 - 6 - 6 INA
- 5 - 10 - 10 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 6 - 12 - 12 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA

- 17 - 34 - 34
- 30 9 50 - 59

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 28 9 46 0 55
0 30 9 50 0 59

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :
DAILY CONSTRUCTION
PROJECT TITLE : CILACAP RFCC PR

PROJECT CONTRACT NO. LOCATION


101830 15/00000/2011-S2 CILACAP, CENTER JAV
DISCIPLINE MECHANICAL
SUB-CON PT. INDO TEHNIK INDUSTRI

2. DAILY MANPOWER STATUS

Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
2.1 INDIRECT MANPOWER
Project Manager M/D - - - - - -
Site Manager M/D - 1 - 1 - 1
MGR General Manager M/D - - - - 1 -
HSE Manager M/D - - - - - -
Mechanical Manager M/D - 1 - 1 - 1
Supervisor Engineer M/D - - - - - -
Progress Control Eng. M/D - - - - - -
ENG
Mechanical Engineer M/D 1 1 - 2 1 1
Mechanical Supervisor M/D - - - - - -
Material Control M/D 1 - - 1 1 -
MAT'L Document Control M/D 1 - - 1 1 -
Tool/Store Keeper M/D - - - - - -
Q.C Engineer M/D - - - - - -
QC
Q.C Inspector M/D - 1 - 1 - 1
Safety Man M/D 1 1 - 2 1 1
HSE
HSE Admin M/D - - - - - -
Mechanical Supervisor M/D - 2 - 2 - 2
SPV Welder Supervisor M/D - - - - - -
Scaffolding Spv. M/D - - - - - -
Administration M/D - - - - - -
Accounting M/D - - - - - -
General Affair M/D - - - - - -
Purchasing M/D - - - - - -
ADM
Time Checker M/D - - - - - -
Driver M/D - 1 - 1 - 1
Office Girl M/D - - - - - -
Security M/D - - - - - -
Sub-Total M/D 4 8 - 12 5 8

2.2 DIRECT MANPOWER


Mechanical Foreman M/D - 1 - 1 - 1
Support Foreman M/D - - - - - -
Scaffolding F/M M/D - - - - - -
F/M
Previous Today
Category Description Unit Pre-
Shop Field Total Shop Field
comm
F/M
Rigging Foreman M/D - - - -
Surveyor M/D - 1 - 1 - 1
Welding Foreman M/D - - - - - -
Mechanical Fitter M/D - 3 - 3 - 3
Millwright M/D - 5 - 5 - 5
Plate Welder M/D - - - - - -
Tack Welder M/D - - - - - -
Scaffolder M/D - - - - - -
Semi skill M/D - - - - - -
WORKERS

Rigger M/D - - - -
Helper M/D - 6 - 6 - 6
Common Labour M/D - - - - - -
Iron Worker M/D - - - - - -
Operator M/D - - - - - -
Rigger (Crane) M/D - - - - - -
Electrician M/D - 1 - 1 - 1
-
Sub-Total M/D - 17 - 17 - 17
Manpower Total M/D 4 25 - 29 5 25

NATIONALITY UNIT PREVIOUS TODAY


KOREAN M/D 0 2 0 2 0 2
INDONESIAN M/D 4 23 0 27 5 23
TOTAL M/D 4 25 0 29 5 25

PREPARED BY, CHECKED BY, APPROVED BY,

PT. INDO TEHNIK INDUST PT. INDO TEHNIK INDUSTRI PT. INDO TEHNIK INDUSTRI
MECHANICAL ENGINEER MECHANICAL MANAGER SITE MANAGER
DATE : DATE : DATE :
NSTRUCTION REPORT
TITLE : CILACAP RFCC PROJECT

DATE WEATHER
CILACAP, CENTER JAV 23-Nov-13 CLEAR

Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm

- - - - - - KOR
- 1 - 2 - 2 KOR
- 1 1 - - 1 INA
- - - - - - INA
- 1 - 2 - 2 KOR
- - - - - - INA
- - - - - - INA
- 2 2 2 - 4 INA
- - - - - - INA
- 1 2 - - 2 INA
- 1 2 - - 2 INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- 2 2 2 - 4 INA
- - - - - - INA
- 2 - 4 - 4 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
- 13 9 16 - 25

- 1 - 2 - 2 INA
- - - - - - INA
- - - - - - INA
Today Accumulate
Pre- Pre- Remark
Total Shop Field Total
comm comm
- - - - - - INA
- 1 - 2 - 2 INA
- - - - - - INA
- 3 - 6 - 6 INA
- 5 - 10 - 10 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 6 - 12 - 12 INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- - - - - - INA
- 1 - 2 - 2 INA

- 17 - 34 - 34
- 30 9 50 - 59

TODAY ACCUMULATE REMARK


0 2 0 4 0 4
0 28 9 46 0 55
0 30 9 50 0 59

REVIEW BY, APPROVED BY,

T. INDO TEHNIK INDUSTRI GS ENG. & CONTS. GS ENG. & CONTS.


SUPERVISOR MECHANIC MECHANICAL MANAGER
DATE : DATE :

Вам также может понравиться