Академический Документы
Профессиональный Документы
Культура Документы
There are different types of labours that are required for the
construction:
Skilled labours
Semi-skilled labours
Unskilled labours
All these types of labours have different skills and different salaries. Their
optimum use in every work in construction is essential to minimize the
construction cost.
S. Recomme
Description of work Unit Labour
No. in days.
Labour
0.50
Concrete : Bhisti
0.10
Mixing by machine (mixer) at
4) M3
banker, cement concrete (with Mixer
0.07
20mm graded coarse aggregate) operator
0.07
Mixer
mason
0.10
Labour
1.63
bhisti
0.70
5) Mixer mixed cement concrete M3
mixer
0.07
operator
0.07
mixer
0.07
vibrator
mason
0.17
mixer
constants for items include mixing, 0.07
operator
pouring, consolidating and curing.
0.07
This does not include fair finish.) mixer
0.07
vibrator
mason
0.24
Labour
2.50
Reinforced cement concrete in bhisti
0.90
situ in suspended floors/roofs
7) M3
excluding form work, and mixer
0.07
reinforcement. operator
0.07
mixer
0.07
vibrator
Mortars:
Mixing by hand, cement mortar of
Labour 0.75
any mix/proportions (Labour
8) M3
required will be approximately
Bhisti 0.07
same for different mix
proportions.)
Carpente
Formwork / Shuttering: r
0.25
a) fabrication and erection with all
Labour
supports, struts, braces, etc, and 0.20
dressing with oil as cleaning of Carpente
M3 0.23
formwork: r
11) M2
1) rectangular column and walls M2 0.20
Labour
Labour
Reinforcement:
Bar reinforcement including cutting
to length, hooked ends, cranking or Bar
1.00
bending, hoisting and placing in bender
12) Quintal
any position, binding wire and
1.00
holding firmly so as not to be Labour
disturbed while placing and
ramming of concrete
mixing of mortar
bhisti 0.10
bhisti 0.10
C = Mass of cement
Sc, Sfa and Sca are the specific gravities of cement, fine aggregates and
coarse aggregates respectively.
Cement = 3.15
Sand = 2.6
= 1 : 1.7 : 3.3
Thus, for the proportion of mix considered, with one bag of cement of 50
kg, 0.1345 m3of concrete can be produced.
0.71
1 1 0.25 12.5 1015 20.3
0
0.85
1 1.5 0.28 14 815 16.3
5
0.96
1 2 0.3 15 687 13.74
3
1.10
1 4 0.53 26.5 395 7.9
6
1.19
1 6 0.7 35 285 5.7
7
1.23
1 8 0.9 45 220 4.4
2
0.39
1 1 2 0.3 15 560 11.2 0.784
2
0.60
1 2 2 0.42 21 430 8.6 0.602
2
0.41
1 1.5 3 0.42 21 395 7.9 0.828
4
0.46
1 2 3.5 0.53 26.5 330 6.6 0.808
2
0.43
1 2 4 0.55 27.5 310 6.2 0.868
4
0.53
1 2.5 3.5 0.57 28.5 305 6.1 0.748
4
0.49
1 2.5 4 0.6 30 285 5.7 0.798
9
0.55
1 3 4 0.65 32.5 265 5.3 0.742
6
0.44
1 2.5 5 0.65 32.5 255 5.1 0.892
6
0.50
1 3 5 0.69 34.5 240 4.8 0.84
4
Notes:
2. The table is based on assumption that the voids in sand and crushed
stone are 40 and 45 percent respectively.
4. No allowance has been made in the table for bulking of sand and
wastage.
MEASUREMENT OF REINFORCED
CONCRETE WORKS
Measurement of reinforced concrete works such as foundation, columns,
beams, slabs pedestal are needed for calculation of actual cost of
construction and payment to the contractor. This article provides
guidelines for the measurement including formulas for the calculation of
quantities of various reinforced concrete works.
Opening up to 0.1 m2
Volume occupied by reinforcement.
Rectangular Volume = L x B x D
Beams shall be measured from face to face of columns and shall include
haunches, if any, between columns and beams. The depth of beams shall
be measured from bottom of slab to bottom of the beam except in case of
inverted beam where it shall be measured from top of slab to top of
beam.
d) Works consists cubical contents which involve volume like earth work,
cement concrete, Masonry etc are expressed in Cubic metres.
RM = Running meter
2 Surface dressing m2 m2
6 Jail works m2 m2
23 Centering, shuttering m2 m2
31 Grouting m2 m2
35 Supply of steel, G.I. sheet, bare electric line Quintal Per quintal
36 Supply of GI sheet m2 m2
Sl. Quantity in
RCC Member Size of reinforcement required
No kg/m3
9 Roof slab
All above mentioned steel are round tapered steel. This data is just for
estimation of quantity of steel for various RCC works. This does not
provide actual steel required for all the members. Actual quantity of steel
required can be calculated from the drawings prepared after structural
design.
In this method, the wall along the length of room is considered to be long
wall while the wall perpendicular to long wall is said to be short wall. To
get the length of long wall or short wall, calculate first the centre line
lengths of individual walls. Then the length of long wall, (out to out) may
be calculated after adding half breadth at each end to its centre line
length. Thus the length of short wall measured into in and may be found
by deducting half breadth from its centre line length at each end. The
length of long wall usually decreases from earth work to brick work in
super structure while the short wall increases. These lengths are
multiplied by breadth and depth to get quantities.
This method is suitable for walls of similar cross sections. Here the total
centre line length is multiplied by breadth and depth of respective item to
get the total quantity at a time. When cross walls or partitions or
verandah walls join with main wall, the centre line length gets reduced by
half of breadth for each junction. Such junction or joints are studied
carefully while calculating total centre line length. The estimates prepared
by this method are most accurate and quick.
This method is adopted when external (i.e., around the building) wall is of
one thickness and the internal walls having different thicknesses. In such
cases, centre line method is applied to external walls and long wall-short
wall method is used to internal walls. This method suits for different
thicknesses walls and different level of foundations. Because of this
reason, all Engineering departments are practicing this method.
Practical-Guide / Reinforcement
Category : Construction