Q: No.4 Who is responsible for installing Green scaffold tag for scaffolds less than 6 m (20 ft.) tall?
A: - T & I coordinator B: - Loss prevention representative
C: - Area inspector D: - Scaffold supervisor
Q: No.5 Which scaffold certification is required to supervise the erection and the inspection of any scaffold?
A: - Scaffold supervisor 1 B: - Scaffold supervisor 1-S
C: - Scaffold supervisor 2-S D: - Scaffold supervisor 2-T
Q: No.6 Which scaffold certification permits the supervisor and inspector of any tube and coupler scaffolds less than
12.2 m (40 ft.) excluding special scaffold?
A: - Scaffold supervisor 1 B: - Scaffold supervisor 1-S
C: - Scaffold supervisor 2-S D: - Scaffold supervisor 2-T
Q: No.7 Which scaffold certification permits the supervisor and inspector of any system and fabricated tubular frame
scaffolds less than 12.2 m (40 ft.) excluding special scaffold?
A: - Scaffold supervisor 1 B: - Scaffold supervisor 2-S
C: - Scaffold supervisor 1-S D: - Scaffold supervisor 2-T
Q: No.8 Scaffold plan must be prepare and submit for review if the scaffold is over.
A: - 3 m (10 ft.) B: - 12.2 m (40 ft.)
C: - 6 m (20 ft.) D: - 38 m (125 ft.)
Q: No.12 What color tag is used when a scaffold is being erected or dismantling?
A: - Red B: - Yellow
C: - Green D: - None
Q: No.13 What color tag is used when a scaffold is being altered or has failed inspection?
A: - Green B: - Red
C: - Yellow D: - None
Q: No.15 Which scaffold must be inspected by the supervisor and the inspector?
A: - Scaffolds over 1.8 m (6 ft.) tall B: - Scaffold over 3 m (10 ft.) tall
C: - Scaffold over 5.5 m (18 ft.) tall D: - Scaffold over 6 m (20 ft.) tall
Q: No.20 When must a scaffold with green or yellow scaffold tag be re-inspected?
A: - Every week B: - Every three week
C: - Every four week D: - Every two week
Q: No.21 Refer to drawing 1001. How many lift is the inner section of the scaffold?
A: - Five lift B: - Nine lift
C: - Eleven lift D: - Fourteen lift
Q: No.22 Refer to drawing 1001. What is the height from the ground to the bottom of the soldier beam?
A: - 15 meters B: - 14.25 meters
C: - 15.85 meters D: - 14.50 meters
Q: No.23 Refer to drawing 1002. How many bays long is the scaffold?
A: - Four bays B: - Six bays
C: - Eight bays D: - Ten bays
Q: No.24 Refer to drawing 1002. How high above ground level is the first working platform?
A: - 0.5 meters B: - 1.0 meter
C: - 1.5 meters D: - 2.0 meters
Q: No.25 Refer to drawing 1003. How many plane braces are on the mobile scaffold?
A: - One B: - Two
C: - Three D: - Four
Q: No.27 Refer to drawings 1004. How many rocking base plate are on the outer row of post (standards)?
A: - Seven B: - Fourteen
C: - Twenty-one D: - Twenty-eight
Q: No.28 Refer to drawing 1005. How many levels of ties tubes are bulled to the column?
A: - Five B: - Nine
C: - Seven D: - Eleven
Q: No.30 Refer to drawing 1007. What is the total length of the posts (standards)?
A: - 8.0 meters B: - 6.8 meters
C: - 5.5 meters D: - 9.5 meters
Q: No.31 Refer to drawing 1006. What is the size of outermost bays of the working platform?
A: - 1.0 meter 1.3 meters B: - 1.0 meter 2.3 meters
C: - 1.0 meter 3.3 meters D: - 1.0 meter 1.0 meter
Q: No.33 Refer to drawing 1007. How many cantilevered frames are there?
A: - One B: - Two
C: - Three D: - Four
Q: No.34 Refer to drawing 1008. What length is the ladder (sure) beam?
A: - 6.1 meters B: - 5.1 meters
C: - 4.1 meters D: - 3.1 meters
Q: No.35 Refer to drawing 1008. How wide is the working platform?
A: - Three boards B: - Five boards
C: - Four boards D: - Six boards
Q: No.36 Refer to drawing 1009. How many trapezoidal sections are there is the upper (smaller) platform?
A: - Eight B: - Twelve
C: - Fourteen D: - Sixteen
Q: No.38 Refer to drawing 1010. What is the width of scaffold working platform?
A: - 0.6 meters B: - 1.6 meters
C: - 1.1 meters D: - 2.1 meters
Q: No.39 Refer to drawing 1010. What height is the first joint pin?
A: - 12.0 meters B: - 4.0 meters
C: - 6.0 meters D: - 3.0 meters
Q: No.40 What must be done when a ladder is found with a split or damaged rung?
A: - Removed from the Saudi ARAMCO property or project B: - Repaired and approved by a supervisor
C: - Repaired and tested by the inspector department D: - Only used to high below the lowest defect
Q: No.41 What must be portable ladder positioned to allow workers safe access to the platforms?
A: - Sloped at 3:1 and extended 1.2 m (4 ft.) the platforms B: - Placed vertically and secured at the top only
C: - Sloped at 4:1 and extended 0.9 m (3 ft.) the platforms D: - Sloped at 5:1 and extended 0.6 m (2 ft.) the platforms
Q: No.43 The clearance between rungs and projecting climbing objects on the climbing side?
A: - 300 mm (12) B: - 750 mm (30)
C: - 450 mm (18) D: - 400 mm (16)
Q: No.44 What type of ladder is not use near electrical power lines?
A: - Fiberglass ladder B: - Wooden ladder
C: - Job made ladder D: - Aluminum ladder
Q: No.52 A twist from end to end in a scaffold planks must be no more than ..
A: - 6.5 mm (1/4) B: - 25 mm (1)
C: - 13 mm (1/2) D: - 38 mm (11-1/2)
Q: No.53 What must be done to a scaffold coupler that has been marked with orange paint?
A: - Remove from the jobsite and repaired B: - Remove from the jobsite and use another job
C: - Remove from the jobsite and destroyed D: - The paint remove and use again
Q: No.54 What must be stamped on the edges of laminated veneer lumber (LVL) scaffold planks?
A: - Scaffold plank B: - Plank OSHA tested
C: - OSHA D: - ANSI approved
Q: No.55 A split on the end of a banded scaffold planks must be no more than
A: - 100 mm (4) B: - 250 mm (10)
C: - 400 mm (16) D: - 300 mm (12)
Q: No.60 Which type of scaffold has a maximum load rating of 240 kg/m2 (50 psf)?
A: - Light-duty B: - Heavy-duty
C: - Medium -duty D: - Special-duty
Q: No.61 What is the load rating for a scaffold used for masonry work?
A: - Light-duty B: - Medium-duty
C: - General-duty D: - Special-duty
Q: No.62 What is the load rating for a scaffold used to support larger piping or heavy equipment?
A: - Light-duty B: - General-duty
C: - Medium -duty D: - Special-duty
Q: No.63 What is the load rating for a scaffold used for a abrasive (sand blasting) where the optional for buildup of
abrasive is possible?
A: - Light-duty B: - General-duty
C: - Medium-duty D: - Special-duty
Q: No.64 What is the minimum number of posts that must be placed on a sill (sole board)?
A: - One B: - Three
C: - Two D: - Four
Q: No.67 The size of the timber sills (sole plates) must be at least?
A: - 215 mm (8.6) by 38 mm (1-1/2) B: - 300 mm (12) by 50 mm (2)
C: - 225 mm (9) by 38 mm (1-1/2) D: - 25 mm (1) by 38 mm (1-1/2)
Q: No.69 What must be checked when erecting the foundation for scaffolds?
A: - The ground must be wet B: - The ground must be wet
C: - Check available electrical supply D: - Any sign of underground piping
Q: No.70 What are screw jack used for?
A: - To compensate for variation in ground level B: - To compensate for setting foundation
C: - To distribute loads over a greater surface area D: - To replace sills on sloped ground
Q: No.76 What type of bracing is installed as close as possible to the node points along the length of the scaffold?
A: - Transverse B: - Longitudinal (faade)
C: - Bracing D: - Scissor bracing
Q: No.77 When must longitudinal (faade) bracing be installed on a scaffold whose length is greater than its height?
A: - Every third post B: - Every fifth post
C: - Every second post D: - Every post
Q: No.80 What is the maximum number of open bays if transverse zig-zag bracing is installed along the width of a
birdcage scaffold?
A: - Four B: - Five
C: - Three D: - Six
Q: No.81 What is the maximum distance that bracing can be installed from a node point on a scaffold?
A: - 200 mm (8) B: - 150 mm (6)
C: - 300 mm (12) D: - 250 mm (10)
Q: No.85 How many lifts can there be above a raker tie-in point?
A: - Fourth B: - One
C: - Three D: - Two
Q: No.88 How many posts (standards) or runners (ledgers) must be tie tube be connected to?
A: - At least 4 B: - At least 3
C: - At least 1 D: - At least 2
Q: No.90 What is one of the methods used to connect a tie tube to a column?
A: - Bridle tie B: - Two ways (through) tie
C: - Box tie D: - Reveal tube
Q: No.94 What height must ties be fitted to a scaffold that is 30 foot high?
A: - 12 feet B: - 26 feet
C: - 16 feet D: - 30 feet
Q: No.95 What height must ties be fitted to a scaffold that is 3 feet wide 8 feet long?
A: - 9 feet B: - 12 feet
C: - 24 feet D: - 32 feet
Q: No.96 What height must a guardrail system be fitted to all open sides of a scaffold platform?
A: - 1.0 m (3 ft.) B: - 1.8 m (6 ft.)
C: - 2.4 m (8 ft.) D: - 3.0 m (10 ft.)
Q: No.99 The distance between uprights used to support guardrails must no more than.
A: - 2.1 m (7 ft.) B: - 2.7 m (9 ft.)
C: - 3.0 m (10 ft.) D: - 3.7 m (12 ft.)
Q: No.100 A guardrail system must be fitted if the distance between a working platform and a wall is more
than.
A: - 100 mm (4) B: - 200 mm (8)
C: - 360 mm (14) D: - 460 mm (18)
Q: No.101 At what height must top rails be fitted above working platforms?
A: - Between 90 cm (35) and 110 cm (43) B: - Between 95 cm (38) and 115 cm (45)
C: - Between 100 cm (39) and 120 cm (47) D: - Between 105 cm (41) and 125 cm (49)
Q: No.102 The distance between supports for 38 mm (1-1/2) wood planks must be no more than..
A: - 1.5 m (5 ft.) B: - 2.7 m (9 ft.)
C: - 3.0 m (10 ft.) D: - 3.6 m (12 ft.)
Q: No.103 The distance between supports for 50 mm (2) wood planks must be no more than..
A: - 1.2 m (4 ft.) B: - 2.4 m (8 ft.)
C: - 3.0 m (10 ft.) D: - 3.6 m (12 ft.)
Q: No.104 Scaffold planks (boards), without cleats extend must beyond the end support by at least.
A: - 50 mm (2) B: - 100 mm (4)
C: - 150 mm (6) D: - 300 mm (12)
Q: No.105 Scaffold planks (boards) must not extend beyond the end support by more than..
A: - 200 mm (8) B: - 300 mm (12)
C: - 450 mm (18) D: - 610 mm (24)
Q: No.107 How can a gap of more than 600 mm (2 ft.) on a platform be covered?
A: - Cover with plywood, overlapping by 200 mm B: - Cover with 1 plywood, overlapping by 200 mm
C: - Cover the gap with at least 2 tin sheets D: - Cover the gap with cross planks (boards)
Q: No.108 The gap between scaffold planks (boards) must be no more than
A: - 150 mm (6) B: - 75 mm (3)
C: - 50 mm (2) D: - 25 mm (1)
Q: No.110 The slope (vertical: horizontal) of scaffold platforms must be no more that
A: - 1:2 B: - 1:3
C: - 1:4 D: - 1:6
Q: No.111 The height between top rails and a working platform must be no more than..
A: - 90 cm (36) B: - 100 cm (40)
C: - 115 cm (45) D: - 120 cm (48)
Q: No.112 The height between top rails and a working platform must be at least..
A: - 80 cm (32) B: - 85 cm (34)
C: - 89 cm (35) D: - 95 cm (38)
Q: No.117 The size of openings in wire mesh screens used to protect workers from falling objects, must be more
than ..................
A: - 3 mm (1/8) B: - 7 mm (1/4)
C: - 13 mm (1/2) D: - 19 mm (3/4)
Q: No.118 If the working platform on a scaffold is 27 m (90 ft.), and three ladders are installed. How many rest
platform (Landings) must be erected?
A: - One B: - Two
C: - Three D: - Four
Q: No.119 What is the width of an access opening for an internal ladder in a scaffold?
A: - 450 mm (18) (2 planks) B: - 675 mm (27) (3 planks)
C: - 900 mm (30) (4 planks) D: - 1,125 mm (45) (5 planks)
Q: No.120 The width for a ladder landing (rest platform) must be at least..
A: - 1 scaffold plank (225 mm/9) B: - 2 scaffold planks (450 mm/18)
C: - 3 scaffold planks (675 mm/27) D: - 5 scaffold planks (1125 mm/45)
Q: No.121 In a tube and coupler scaffold, what coupler (fitting) must be used to secure a runner (ledger) to a post
(standard)?
A: - Right-angle (Double) coupler B: - Bearer (putlog) coupler
C: - Adjustable (swivel) coupler D: - Girder coupler
Q: No.122 When connecting posts (standards) together in a tube and coupler scaffold, what erection procedure must
be followed?
A: - Joints must be made with double couplers B: - Joints must be made with swivel couplers
C: - Joints must be in the same lift height D: - Joints in adjacent posts (standards) must be staggered
Q: No.123 Where must be runners (ledgers) be installed on tube and coupler scaffolds?
A: - Every bay across the width of the scaffold B: - Every bay along the length of the scaffold
C: - Every other bay across the width of the scaffold D: - Every other bay along the length of the scaffold
Q: No.124 On tube and coupler scaffolds, the vertical distance between lift must be no more than..
A: - 1.5 m (5 ft.) B: - 2 m (6.5 ft.)
C: - 2.6 m (8.5 ft.) D: - 1.2 m (4 ft.)
Q: No.125 Where must be bearers (transoms) and board bearers (intermediate transom) be installed on tube and
coupler scaffolds?
A: - Underneath runners (ledgers) B: - Diagonally
C: - Alongside runners D: - On top of runners (ledgers)
Q: No.126 The distance from a post (standard) and sleeve coupler joint in a runner (ledger) must be no more than
A: - 150 mm (6) B: - 225 mm (9)
C: - 100 mm (4) D: - 300 mm (12)
Q: No.127 What must be done when making joints in runners (ledgers) in a tube and coupler scaffold?
A: - The joints must be made with single couplers B: - The joints must be made with swivel couplers
C: - The joints must be in the same lift height D: - The joints must not be in the same bay
Q: No.129 The distance between bracing and node point in a tube and coupler scaffold must be no more than
A: - 150 mm (6) B: - 225 mm (9)
C: - 300 mm (12) D: - 100 mm (4)
Q: No.130 What type of coupler (fitting) must be used to join bracing tubes?
A: - End-toend (sleeve) coupler B: - Right-angle (Double) coupler
C: - Bearer (putlog) coupler D: - Girder coupler
Q: No.131 What is the height of base lift (kicker lift) on a typical tube and coupler scaffold?
A: - 225 mm (9) B: - 150 mm (6)
C: - 300 mm (12) D: - 100 mm (4)
Q: No.132 Where must bearers (transoms) be installed in tube and coupler scaffolds?
A: - To two posts in every bay across the width B: - To two posts in every bay along the length
C: - To two posts in every other bay across the width D: - To two posts in every other bay along the length
Q: No.133 In a tube and coupler scaffold, the distance a bearer (transom) can extend beyond a runner (ledger) must
be at least.
A: - 225 mm (9) B: - 150 mm (6)
C: - 300 mm (12) D: - 100 mm (4)
Q: No.134 If two posts (standards) are jointed, they must not be..
A: - In the same length B: - Opposite in the same lift
C: - Side by side in the same lift D: - In the same width
Q: No.135 On a tube and coupler scaffold. If bearers (transoms) are coupled to runners (ledgers), the distance from
the posts (standards) to the bearer must be no more than
A: - 125 mm (9) B: - 300 mm (12)
C: - 450 mm (18) D: - 750 mm (30)
Q: No.136 In a tube and coupler scaffold, the distance between a post (standard) and a sleeve-coupler joint in a
runner (ledger) must be no more than
A: - 1200 mm (48) B: - 900 mm (36)
C: - 600 mm (24) D: - 300 mm (12)
Q: No.137 What procedure must be followed when erecting SYSTEM scaffolds?
A: - OSHA standards and Saudi Aramco B: - European standards and Saudi Aramco requirements
C: - Manufacturers instructions and Saudi Aramco requirements. D: - ANSI standards and Saudi Aramco requirements
Q: No.138 What part of the system scaffold may be connected using tube and coupler components?
A: - Bearers (Transoms) B: - Bracing
C: - Runners (Ledgers) D: - Posts (Standards)
Q: No.139 Unless otherwise specified in the manufacturers instruction, where must diagonal braces be installed on a
SYSTEM scaffold?
A: - Every 10 m (33 ft.) B: - Every 20 m (65 ft.)
C: - Every 30 m (98 ft.) D: - Every 40 m (130 ft.)
Q: No.140 For a system scaffold, what type of fitting must be used to join posts (standards)?
A: - Bearer (putlog) coupler B: - Adjustable (swivel) coupler
C: - Bolted spigot D: - Right-angle (Double) coupler
Q: No.141 The height of a fabricated tubular frame scaffold must be no more than.
A: - 6 m (20 ft.) B: - 8 m (26 ft.)
C: - 10 m (33 ft.) D: - 12 m (40 ft.)
Q: No.145 Where must plan (horizontal) bracing be installed on mobile and tower scaffolds?
A: - Every other lift B: - Top and bottom lifts only
C: - Bottom, top, and every third lift D: - Bottom lift only
Q: No.146 The diameter of the casters (wheels) on a LIGHT-DUTY mobile scaffold must be at least..
A: - 100 mm (4) B: - 120 mm (5)
C: - 170 mm (7) D: - 200 mm (8)
Q: No.147 The diameter of the casters (wheels) on a MEDIUM-DUTY mobile scaffold must be at least..
A: - 100 mm (4) B: - 120 mm (5)
C: - 170 mm (7) D: - 200 mm (8)
Q: No.148 What must be installed on all mobile scaffold casters?
A: - Chocks B: - Screwjack
C: - Wheel locks D: - Wedges
Q: No.149 The height of the mobile or freestanding tower scaffold must be no more than..
A: - 3 times the smallest base dimension B: - 4 times the smallest base dimension
C: - 5 times the smallest base dimension D: - 6 times the smallest base dimension
Q: No.150 What must be fitted if the top work platform on a free standing tower scaffold is five times the height of the
smallest base dimension?
A: - Plan braces B: - Ties
C: - Additional bearers (transoms) D: - Cross braces
Q: No.151 What is the minimum number of board bearers that must be fitted if the longitudinal post spacing exceeds
1.5 meters (5 feet) on a scaffold?
A: - 1 B: - 2
C: - 3 D: - 4
Q: No.152 The distance between a trapeze tube and a runner (ledger), on an underhung scaffold must be at least
A: - 1150 mm (4 ft.) B: - 300 mm (1 ft.)
C: - 910 mm (3 ft.) D: - 600 mm (2 ft.)
Q: No.153 What type of coupler must be used to attach runners (ledgers) and bearers (transoms) to a hanger tube
on an underhung scaffold?
A: - Right-angle (Double) coupler B: - Adjustable (swivel) coupler
C: - Bearer (putlog) coupler D: - End-to end (sleeve) coupler
Q: No.155 What is the minimum number of couplers required if a splice is used in a hanger tube?
A: - 2 B: - 3
C: - 4 D: - 5
Q: No.157 If 38 mm (1-1/2) boards are used on a bracket scaffold, the distance between brackets must not be more
than
A: - 3.0 m (10 ft.) B: - 2.0 m (6.5 ft.)
C: - 1.5 m (5 ft.) D: - 1.2 m (4 ft.)
Q: No.158 The distance between the brackets on a tank builders scaffold must be at least
A: - 1.2 m (4 ft.) B: - 1.5 m (5 ft.)
C: - 2.0 m (6.5 ft.) D: - 3.2 m (10 ft.6)
Q: No.159 Who must examine a tank before straps are welded on to support a bracket scaffold?
A: - A Saudi Aramco certified scaffolder inspector B: - The Proponents Engineering Unit
C: - Saudi Aramco Loss Prevention D: - The Maintenance Superintendent
Q: No.160 Who must approve the welds on the straps before the brackets are fitted for a bracket scaffold?
A: - A Saudi Aramco certified scaffolder inspector B: - Saudi Aramco Loss Prevention
C: - A Saudi Aramco certified welding inspector D: - The Maintenance Superintendent
Q: No.161 What rope must be used for top rails and mid rails on a bracket scaffold?
A: - 3 mm (1/8) wire rope B: - 6 mm (11/4) wire rope
C: - 10 mm (3/8) wire rope D: - 18 mm (3/4) wire rope
Q: No.162 The width of the working platform on a bracket scaffold must be at least.
A: - 1 plank B: - 2 planks
C: - 4 planks D: - 5 planks
Q: No.163 The width of the working platform on a bracket scaffold must be no more than..
A: - 4 planks B: - 1 plank
C: - 2 planks D: - 3 planks
Q: No.165 The travel distance to an exit point on a working platform must be no more than..
A: - 7.6 meters B: - 15 meters
C: - 45 meters D: - 60 meters
Q: No.168 The vertical distance between landings on a temporary stairway must be no more than..
A: - 3 meters B: - 3.7 meters
C: - 4.8 meters D: - 6.1 meters
Q: No.176 At what height above a lower level, must a ramp or walkway be provided with a guardrail system?
A: - 0.6 meters B: - 1.2 meters
C: - 1.8 meters D: - 2.4 meters
Q: No.178 How many working levels can be there on a LIGHT-DUTY scaffold, with 8 planked levels?
A: - 0 B: - 1
C: - 2 D: - 3
Q: No.179 How many working levels can be there on a LIGHT-DUTY scaffold, with 7 planked levels?
A: - 0 B: - 1
C: - 2 D: - 3
Q: No.180 How many working levels can be there on a LIGHT-DUTY scaffold, with 5 planked levels?
A: - 0 B: - 1
C: - 2 D: - 3
Q: No.181 How many working levels can be there on a LIGHT-DUTY scaffold, with 4 planked levels?
A: - 0 B: - 1
C: - 2 D: - 3
Q: No.182 How many working levels can be there on a MEDUM-DUTY scaffold, with 6 planked levels?
A: - 0 B: - 1
C: - 2 D: - 3
Q: No.183 How many working levels can be there on a MEDUM-DUTY scaffold, with 3 planked levels?
A: - 0 B: - 2
C: - 1 D: - 4
Q: No.184 How many working levels can be there on a MEDUM-DUTY scaffold, with 2 planked levels?
A: - 4 B: - 2
C: - 1 D: - 0
Q: No.185 The distance between any scaffold post and the edge of an unshored excavation must be at least..
A: - The depth of the excavation B: - 1.5 times the depth of the excavation
C: - 2 times the depth of the excavation D: - The depth of the excavation + 1.2 meters
Q: No.186 The distance between scaffold tubes and an insulated 16.7 kV electrical power line must be at least
A: - 1 meter B: - 3 meters
C: - 3 meters + 100 mm for every 100 V over 10 kV D: - Twice the length of the scaffold tube
Q: No.187 The distance between scaffold tubes and an insulated 60 kV electrical power line must be at least..
A: - 1 meter B: - 3 meters
C: - 4 meters D: - Twice the length of the scaffold tube
Q: No.188 The distance between scaffold tubes and an un-insulated 6.7 kV electrical power line must be at least
A: - 1 meter B: - 3 meters
C: - 3 meters + 100 mm for every 1000 V over 50 kV D: - Twice the length of the scaffold tube
Q: No.189 On a LIGHT-DUTY tube and coupler scaffold constructed with EMBOSSED tubing, with a transverse post
spacing of 1 meter, the longitudinal post must be no more than.
A: - 2.3 meters B: - 1.8 meters
C: - 2.4 meters D: - 2.7 meters
Q: No.190 On a LIGHT-DUTY tube and coupler scaffold constructed with EMBOSSED tubing, with a longitudinal post
spacing of 2.7 meters, the transverse post spacing must be no more than.
A: - 2.7 meters B: - 1.2 meters
C: - 1 meter D: - 2.4 meters
Q: No.191 On a LIGHT-DUTY tube and coupler scaffold constructed with EMBOSSED tubing, with a transverse post
spacing of 1.2 meter, the longitudinal post spacing must be no more than.
A: - 2.4 meters B: - 2.7 meters
C: - 2.3 meters D: - 1.8 meters
Q: No.192 On a LIGHT-DUTY tube and coupler scaffold constructed with EMBOSSED tubing, with a longitudinal post
spacing of 2.4 meters, the transverse post spacing must be no more than.
A: - 1 meter B: - 1.2 meters
C: - 2.4 meters D: - 2.7 meters
Q: No.193 On a LIGHT-DUTY tube and coupler scaffold constructed with NON-EMBOSSED tubing, and a transverse
post spacing of 1 meter, the longitudinal post spacing must be no more than.
A: - 2.4 meters B: - 2.3meters
C: - 2.7meters D: - 1.8 meters
Q: No.194 On a LIGHT-DUTY tube and coupler scaffold constructed with NON-EMBOSSED tubing, and a
longitudinal post spacing of 2.3 meters, the transverse post spacing must be no more than.
A: - 1.2 meters B: - 1.8 meters
C: - 1 meter D: - 2.3 meters
Q: No.195 On a LIGHT-DUTY tube and coupler scaffold constructed with NON-EMBOSSED tubing, and a transverse
post spacing of 1.2 meters, the longitudinal post spacing must be no more than.
A: - 1.0 meter B: - 1.8 meters
C: - 1.2 meters D: - 2.3 meters
Q: No.196 On a LIGHT-DUTY tube and coupler scaffold constructed with NON-EMBOSSED tubing, and a
longitudinal post spacing of 1.8 meters, the transverse post spacing must be no more than
A: - 1 meter B: - 1.8 meters
C: - 2.3 meters D: - 1.2 meters
Q: No.197 Refer to handout on CUPLOK System scaffolds. If a MEDIUM-DUTY Birdcage scaffold constructed with
CUPLOK has a transverse post spacing of 1.6 meters, the longitudinal post spacing must be no more than
Note
1. The above maximum spans may increase when decking systems do not require board bearers (intermediate transoms).
For 2.5 m (8.2) span this would require the use of SGB Cuplok modular steel or aluminum decking systems.
2. SGB reserved the right to amend and re-issue this table when, and if, new products are introduced.
** denotes GR 43 60.3 mm intermediate Transom. HD denotes Heavy Duty Ledger
RUNNE
R/LEDG
ER
BEAR
TRAN
SPAN
SPAN
SOM
ER/
INTERME
DIATE
TRANSOM
SPACING
(2 PAIRS)
A: - 2.5 meters B: - 1.6 meters
C: - 1.8 meters D: - 1.3 meters
Q: No.198 Refer to handout on CUPLOK System scaffolds. If a MEDIUM-DUTY Birdcage scaffold constructed with
CUPLOK has a longitudinal post spacing of 1.8 meters, the transverse post spacing must be no more than
SGB Manufactured Cuplok Loads
SGB for use in Saudi Aramco Date: Pg Sp 03
Note
1. The above maximum spans may increase when decking systems do not require board bearers (intermediate transoms).
For 2.5 m (8.2) span this would require the use of SGB Cuplok modular steel or aluminum decking systems.
2. SGB reserved the right to amend and re-issue this table when, and if, new products are introduced.
** denotes GR 43 60.3 mm intermediate Transom. HD denotes Heavy Duty Ledger
TRAN
SPAN
SPAN
SOM
ER/
ER
AN
AN
SO
AR
BE
TR
SP
M
SPAN
A: - 0 B: - 1
C: - 2 D: - INTERME
3
Q: No.200 Refer to handout on CUPLOK System scaffolds. If aDIATE
LIGHT-DUTY Tower scaffold constructed with
TRANSOM
CUPLOK has a post spacing of 1.8 meters 1.8 meters, the number of board bearers used must be at least
SPACING
(2 PAIRS)
SGB Manufactured Cuplok Loads
SGB for use in Saudi Aramco Date: Pg Sp 02
ER
AN
AN
SO
AR
BE
TR
SP
M
SPAN
A: - 0 B: - 1
C: - 2 D: - 3 INTERME
Q: No.201 Refer to handout on CUPLOK System scaffolds. If aDIATE
LIGHT-DUTY Tower scaffold constructed with
TRANSOM
CUPLOK has one board bearers, the post spacing must be no more than ..
SPACING
(2 PAIRS)
SGB Manufactured Cuplok Loads
SGB for use in Saudi Aramco Date: Pg Sp 02
ER
AN
AN
SO
AR
BE
TR
SP
M
SPAN
A: - 1.3 1.6 meters B: - 2.5 1.6 meters
C: - 1.8 1.8 meters INTERME
D: - 2.5 2.5 meters
DIATE
Q: No.202 Refer to handout on CUPLOK System scaffolds. If aTRANSOM
MEDIUM-DUTY Tower scaffold constructed with
SPACING
CUPLOK has a post spacing of 1.6 meters 1.8 meters, the number of board bearers used must be at least
(2 PAIRS)
SGB Manufactured Cuplok Loads
SGB for use in Saudi Aramco Date: Pg Sp 03
Note
1. The above maximum spans may increase when decking systems do not require board bearers (intermediate transoms).
For 2.5 m (8.2) span this would require the use of SGB Cuplok modular steel or aluminum decking systems.
2. SGB reserved the right to amend and re-issue this table when, and if, new products are introduced.
** denotes GR 43 60.3 mm intermediate Transom. HD denotes Heavy Duty Ledger
TRAN
SPAN
SPAN
SOM
ER/
INTERME
A: - 2 B: - 1
DIATE
C: - 3 D: - 0
TRANSOM
SPACING
Q: No.203 Refer to handout on CUPLOK System scaffolds. If a MEDIUM-DUTY Tower scaffold constructed with (2 PAIRS)
CUPLOK has two pairs of common board bearers, the post spacing must be no more than ..
SGB Manufactured Cuplok Loads
SGB for use in Saudi Aramco Date: Pg Sp 03
Note
1. The above maximum spans may increase when decking systems do not require board bearers (intermediate transoms).
For 2.5 m (8.2) span this would require the use of SGB Cuplok modular steel or aluminum decking systems.
2. SGB reserved the right to amend and re-issue this table when, and if, new products are introduced.
** denotes GR 43 60.3 mm intermediate Transom. HD denotes Heavy Duty Ledger
TRAN
SPAN
SPAN
SOM
ER/
INTERME
A: - 1.6 1.6 meters B: - 1.6 1.8 meters
DIATE
C: - 1.8 1.8 meters D: - 1.3 1.8 meters
TRANSOM
SPACING
Q: No.204 Refer to handout on CUPLOK System scaffolds. If a LIGHT-DUTY Birdcage Scaffold constructed with
(2 PAIRS)
CUPLOK has a transverse post spacing of 1.8 meters, the longitudinal post spacing must be no more than
SGB Manufactured Cuplok Loads
SGB for use in Saudi Aramco Date: Pg Sp 02
ER
AN
AN
SO
AR
BE
TR
SP
M
SPAN
A: - 1.3 meters B: - 1.6 meters
C: - 1.8 meters D: - 2.5 meters INTERME
Q: No.205 The transverse post spacing on an underhung, MEDIUM-DUTY tube and coupler scaffold constructed of DIATE
EMBOSSED tubing, must be no more than.. TRANSOM
SPACING
(2 PAIRS)
A: - 1 meter B: - 1.1 meters
C: - 1.2 meters D: - 1.4 meters
Q: No.206 The longitudinal spacing between the hanger post on an underhung, MEDIUM-DUTY tube and coupler
scaffold constructed with EMBOSSED tubing, must be no more than..
A: - 1.8 meters B: - 2.1 meters
C: - 2.4 meters D: - 2.7 meters
Q: No.207 A Light-duty Mobile Scaffold (Tower) constructed with NON-EMBOSSED tubing, the post spacing must be
no more than..
A: - 3.0 meters B: - 1.7 meters
C: - 1.3 meters D: - 2.5 meters
A Base-Supported Tube and Coupler Scaffold: This must be constructed with 6-foot (1.8 m) post spacing,
3 lifts high, 4 bays long, 5 planks wide, and tied at 2 points.
A Under Hung Scaffold: This must be 10 feet (3 m) long, and a minimum of 4 boards wide.
ALTERNATE No.2
A Base-Supported Tube and Coupler Scaffold: This must be constructed with 6-foot (1.8 m) post spacing,
3 lifts high, 4 bays long, 5 planks wide, and tied at 2 points.
The Under Hung Scaffold: This must be 10 feet (3 m) long, and a minimum of 4 boards wide
The Under Hung Scaffold: This must be 10 feet (3 m) long, and a minimum of 4 boards wide
ALTERNATE No.4
A Tube and Coupler Mobile Scaffold: This must be constructed with a working height of 14 feet (4.25 m),
and 5 planks wide.
The Under Hung Scaffold: This must be 10 feet (3 m) long, and a minimum of 4 boards wide.
ALTERNATE No.5
A Tube and Coupler Tower Scaffold: This must be constructed with a base of 5.6 (1.7 m) 4 feet (1.2
m), and 3 lift high.
The Under Hung Scaffold: This must be 10 feet (3 m) long, and a minimum of 4 boards wide.
ALTERNATE No.6
A Light-Duty, Tube and Coupler Mobile Scaffold: This must be constructed with a base of 5.6 (1.7 m)
4 feet (1.2 m), and 3 lift high.
The Under Hung Scaffold: This must be 10 feet (3 m) long, and a minimum of 4 boards wide.
POSTS (STANDARDS)
FAULTS
2
RUNNERS (LEDGERS)
FAULTS
3
BEARERS (TRANSOMS)
FAULTS
4
BRACING
FAULTS
5
GUARDRAILS
FAULTS
7
9 LADDERS / ACCESS
FAULTS
ARAMCO SCAFFOLDING PIRATICAL PAPER
POSTS (STANDARDS)
FAULTS
2
RUNNERS (LEDGERS)
FAULTS
3
BEARERS (TRANSOMS)
FAULTS
4
BRACING
FAULTS
5
GUARDRAILS
FAULTS
7