Export does not support the sub-unit time format. Make sure
the Sub-unit checkboxes are clear in the Edit, User
Preferences, Time Units tab.
Select export format and subject area Open the project in the
Project Management module you want to export. Choose File, Export to
start the Export wizard. Choose Spread Sheet, then click Next.
Select the
subject areas you
want to export,
then click Next.
Select a Subject Area in the Modify Template dialog box to modify its
options. In the Columns tab, select the fields to export. The available
options are based on the selected subject area.
In the Modify Template dialog box, click the Filter tab to select the
activities you want to export for the selected subject area. If using more
than one filter, choose to show activities that meet all selection criteria
in each filter, or to show activities that must meet only one selection
criteria in each filter. Select the filter(s) to use for the export file. If
necessary, click Modify to edit the selected user-defined filter. The
fields available for filtering are based on the selected subject area.
Click the Sort tab in the Modify Template dialog box to apply order to
the columns during export. Select the sort order for each field name.
Click OK to save your modifications to the template.
Click Next to define the location to save the export file. Double click in
the File Name field and click the Browse button if you want to change
the name and location of the export file.
Click Next to view the summary information for the export file. Click
Finish to export the project data to an XLS file.
For information about Update unit, cost, duration, percent complete, and date
sheet names for subject fields When updating unit, cost, duration, and percent complete fields,
areas, refer to the you may want to import one updated field at a time into the Project
Primavera Project Management module. For example, you can export the Activities
Management module Help. subject area, and update the activity percent complete and the remaining
duration in the export file. When you import the Excel file, PM updates
the activity data. However, to update other activity values related to the
remaining duration and percent complete, PM needs to know which
field was updated first. In PM, you cannot update these fields
simultaneously.
To update unit, cost, duration, and percent complete fields, make a copy
of the export file you want to update.
In the copied file, update the necessary field for an activity. In that
activity row, blank out the remaining fields that are not marked (*) to
give it a null value. As a result, during import, PM will not update the
fields with null values in the project, and PM will calculate the other
fields as necessary.
In PM, choose File, Import to import the Excel file into the selected
project. Repeat these steps for each unit, cost, duration, percent
complete, and date field.
Activities Activity ID
For more information on Select import format Choose File, Import. Choose Spreadsheet,
importing, refer to the then click Next.
Project Management Help.
Select the Excel file to import Type the location of the XLS file or
click the Browse button to select the file you want to import. Click Next.
Click Next to display information about the import file. Click Finish to
complete the import.
Select export type and project Open the project you want to
export. Choose File, Export. Choose Primavera Project Planner, then
click Next.
Mark the Export checkbox next to the project you want to export, then
click Next.
Select planning unit Choose the planning unit (hours or days) that
you want P3 3.x to use to schedule project data. The Project
Management module uses only hourly planning units. If you choose
Days, you can select to export the resource units as hours or days. Click
Next.
Choose cost calculation rules You can set several Autocost rules
for the exported project. Default settings are used for all other Autocost
rules. These calculations apply only when the project is scheduled in P3
3.x. You can change these settings when you open the project in P3 3.x.