Академический Документы
Профессиональный Документы
Культура Документы
METHOD STATEMENT
FOR
TESTING AND COMMISSIONING
Issue Prepared
Rev Date
Purpose by:
Signature Reviewed by Signature Approved by Signature
I. METHOD OF STATEMENT
1.0 Criteria
Before starting air balancing, it is essential that the following conditions be fulfilled:
a. The building is complete. Ceilings, doors and windows installed, windows
glazed, doors or windows in their normal open or closed state. If spaces are
not architecturally sealed, abnormal pressure distributions will unbalance the
system and lead to inconsistent and insignificant results.
b. The duct system is completed and clean. Any duct leakage testing required
is completed remedial treatments fully carried out. All grilles, dampers,
diffusers, filters and coils installed.
c. The system is ready for setting to work. (See required TCx-certificate forms in
item no. IV).
The technique to be used in balancing the air distribution system will be Proportional
Balancing Method which is accepted as the most appropriate method of effectively
regulating distribution systems. Successful application of the technique is dependent
upon the inclusion of sufficient regulating devices (volume dampers, splitter, etc.)
suitably positioned in the ductwork installation. The balancing procedure and
underlying principles describe in this section assume that such devices have been
installed in the ductwork branches to every terminal.
The principles of proportionally balancing require that all the dampers in the
distribution system be fully open and that at least one outlet volume damper (the
T&C Procedure Air Conditioning & Ventilation System Page 2
Vector Three
outlet with the lowest percent of design flow) will remain open. If the system has
branch ducts, at least one branch volume damper (the branch with the lowest percent
of design flow) will remain full open. Because the air outlets on the low pressure side
of any system the following proportionally balancing procedure can be used.
3.0 Preparation
a. Open all duct system and terminal dampers but keep the main fan damper partly
closed. Set the diffuser to give full downward discharge and set adjustable grille
louvers at right angle to the grille face. Open the plant dampers to establish the
conditions for the maximum demand system airflow.
b. Run the fan and check the motor current to ensure that its design full load value
is not exceeded. Adjust the main fan damper until the fan motor current is close
to the design value. If the amperage exceeds the nameplate full load amperage,
stop the fan to determine the cause or to make the necessary adjustment.
c. Walk around the system checking that air is flowing from each supply terminal or
being extracted. Confirm that all related system fans serving each area within the
space being balanced are operating. If not, pressure differences, and infiltration
and exfiltration may adversely influence the balancing. Preliminary studies will
have revealed whether or not the supply air quantity exceeds the exhaust air
quantity from each area. Positive and negative pressures zones should be
identified at the time.
Traverse Location:
Equation 1.0
d = 4ab /
Where:
d = equivalent duct diameter in inches
a = length of one side of rectangular duct in inches
b = length of adjacent side of rectangular duct in inches
= 3.1416
Solution:
d = 4 x 24 x 20 / 3.1416= 24.7
d. Measure the total flow rate at the fan by a duct pitot-tube traverse and also
the fan pressure rise after checking the fan speed. The fan should be
delivering at least +10% of the design value. If the measured air volume of
the supply fan varies more or less than 10% from design, adjust the drive of
each fan to obtain approximate required air volume record fan suction static
pressure, fan discharge static pressure, amperage and air volume
measurements. Confirm that the fan motor is not overloaded. Also,
T&C Procedure Air Conditioning & Ventilation System Page 3
Vector Three
determine the volume of air being handled by the exhaust fan. If there is
several exhaust fans it is generally not necessary to measure air volume of
exhaust fans until after the supply system is balanced. Open the main
damper to ensure that the design full load current is not exceeded.
If there is no possible location we can use the vane anemometer. Using the
vane anemometer we can measure the fan CFM by getting four points of
reading or intervals depending on the size of the duct and dividing it from the
number of readings and multiply by the correction factor (K). The point
interval of vane should not be less than 100mm or greater than 150 mm
center to center distance of the vane. We can also use a balometer if
applicable on the size of diffuser.
a. Determine which outlet has the lowest percent of design airflow (%D).
Typically the outlet with the lowest %D will be on the branch farthest from the
fan. This outlet will be called Key outlet.
* Design flow is either the original design airflow per the contract specifications
or new calculated design airflow.
* Percent design airflow is equal to the measured flow divide by the design
airflow.
b. Starting with the key outlet, as needed, adjust outlet of that branch duct in
sequence, from the highest percent of design air flow to the lowest percent of
design airflow.
* The ratio of the percent of design airflow between each outlet must be plus or
minus 10%. Ratio of design airflow is equal to outlet X %D divided by outlet Y
%D.
c. Go to branch that has the outlet with the next lowest percent design flow as
determined from the initial readout. Typically this Key outlet will be on the
second farthest branch. Balance all the outlets on this branch to the key
outlet to within plus or minus 10% of the design airflow.
d. Continue until all the outlets on all branches have been balanced to within
plus or minus 10% of the design airflow on each other.
e. Starting with the branch with the lowest percent of design flow as the key
branch proportionately balance all branch ducts from the lowest %D airflow to
the highest %D airflow within 10% of each other.
a. When the entire duct network is balanced, measure the flow in the main duct
using the pitot-tube and micro manometer. If the flow is higher than the design
value, adjust the main damper. If the pressure drop across the main damper in
the final position is a significant part of the total system pressure, a reduction in
fan speed should be considered.
If the flow is less than the design rating, open the damper making sure that the
maximum permissible fan motor current is not exceeded.
b. It is essential, while using the proportional balancing technique, that absolute flow
rates are calculated from time to time during the procedure and at the end in
order to ensure that there is a satisfactory correlation between the flow rates from
terminals in the sub-branches and main branches and the total system flow rate.
Due to wide variety and mix of terminals, which can be available on any one
system, flow rate technique may vary. Simply balancing on anemometer velocity
readings alone, with continual reference to absolute values can lead to poor
result.
d. Lock all dampers in position. Alternatively, inscribe the position of the damper
arm and seal the operating screw.
f. Record the Final Datas using the Testing & Commissioning Checklist format on
item no. IV.
B. AIR-CONDITIONING EQUIPMENT
Note: The valve of the gauge manifold and the liquid charging line
shall be opened before the opening of the shut-off valve of the
nitrogen cylinder.
d. First, check the gauge manifold, service hoses and service valve
connections for leaks. If pressure wont increase, check the system
for leaks. Leaks are located by applying soap solution to joints and
connections.
e. After the leaks are found, release the system pressure. Then,
repair leaks by cleaning and repairing the joints.
g. Re-check the system for leaks. If no leaks are found, allow the
pressure to remain for twenty four (24) hours. After this time check
the system pressure. If no pressure change was noted, the system
is considered leak free.
1.2 Evacuation
Note: The valve of the gauge manifold and the liquid charging line
shall be opened before the opening of the shut-off valve of the
nitrogen cylinder.
e. First, check the gauge manifold, service hoses and service valve
connections for leaks. If pressure wont increase, check the system
for leaks. Leaks are located by applying soap solution to joints and
connections.
e. After the leaks are found, release the system pressure. Then,
repair leaks by cleaning and repairing the joints.
i. Re-check the system for leaks. If no leaks are found, allow the
pressure to remain for twenty four (24) hours. After this time check
the system pressure. If no pressure change was noted, the system
is considered leak free.
2.2 Evacuation
C. VENTILATION EQUIPMENT
A. Air Measurement
1. Pro Hood Flow Grid
2. Vane Anemometer
T&C Procedure Air Conditioning & Ventilation System Page 10
Vector Three
3. Micro Manometer Flow / Pressure
4. Micro Manometer Pressure
5. Inclined Tube Manometer
6. Pitot Tube (Static)
7. Pitot Tube (Telescopic)
8. Balometer
B. Temperature Measurements
1. Sling Psychrometer
2. Whirling Hygrometer
3. Thermo Hygrometer
4. Infrared Thermometer
C. Electrical Measurements
1. Clamp Meter
2. Multi Tester
3. Earth Impedance Tester
4. Phase Rotation Tester
1. Tachometer
2. Sound Level Meter
All instruments shall be calibrated prior to use on site, as required in the Construction
Technical Specification.
1. Air-Distribution System
1.1 Design Information Checklist
1.2 Pre-commissioning Checklist
1.3 Final Inspection Checklist
1.4 Setting to Work Checklist
1.5 Duct System (Main Duct Traverse)
1.6 Duct System (Branch Duct Traverse)
1.7 Duct System (Branch Duct Terminal Summary)
1.8 Fan Performance Test
3. Ventilation Equipment
3.1 Visual & Functional Test of Toilet Exhaust Fan
3.2 Exhaust Fan - Pre-commissioning Checklist
3.3 Exhaust Fan Fan Performance Test
3.4 Supply Fan Pre-commissioning Checklist
3.5 Supply Fan Fan Performance Test
3.6 Transfer Fan Pre-commissioning Checklist
3.7 Transfer Fan Fan Performance Test