Вы находитесь на странице: 1из 71

PUBLIC WORKS DEPARTMENT

GOVERNMENT OF MAHARASHTRA 2010

1
( FOR INTERNAL USE ONLY )
( SECOND EDITION )

GUIDELINES FOR

BUILDING DESIGN

(GENERAL PROCEDURE

FOLLOWED IN

THE DESIGNS CIRCLE)

R. B. GADGE
Sup erintending Engineer
D esigns Circle (Bldg.)

(DT. 08/03/2010)

2
PREFACE OF SECOND EDITION

The publication of this guidelines could not have been possible but for the
untiring efforts put in by a large number of individuals working in the Designs
Circle.

The first edition of these guidelines were issued in 1996. Thereafter


modification to I.S.13920 and I.S.456 have been issued. There also have been
some changes in practices in the design procedure adopted by Designs Circle.
In view of this, it was decided to have modifications in these guidelines.
Hence, a small group of officers working in the Designs Circle was formed
and the work of updating and modification to the first edition of these
guidelines was undertaken. The new chapters such as structural models and
seismic analysis, design criteria are added and some modifications are done in
existing chapter.

The contribution of this group comparising of Shri V.P.Ramgude, Executive


Engineer (Standards) Building, Smt. Rupa Raul, Executive Engineer,
Building-Mumbai, Shri R.G.Shete and Shri S.A.Ninawe, Sub-Divisional
Engineers, Bldg.-Mumbai, are specially acknowledged.

Also The efforts taken by Shri S.G.Bhoir, Shri S.Y.Gaikwad, Tracers,


Smt.P.P.Pable, Smt.S.P.Naware, Steno-Typists, Shri S.B.Gadhave, Sr.Clerk
and other staff in the Designs Circle in recasting the second edition of
guidelines are acknowledged.

This second edition is expected to meet the demands of the building designer
while planning for building designs.

Date : 08/03/2010 ( R. B. GADGE )


Superintending Engineer
Designs Circle (Bldg.)

3
FOREWORD

Designs Circle (Bldg.) of the P.W.Department has been set up to carry out
Structural Design work of important buildings for the Government of Maharashtra.

Since the inception of Designs Circle in 1958, it has been instrumental in


absorption and application of latest design practices based on I.S. codes and field
experiences. The construction practices evolved over the years have been compiled in
the form of Designs Circles Technical Notes, No.7502 and 7503, and are already in
circulation among the field engineers.

It was a long felt need that the entire process of Building Design as followed
in Designs Circle should also be made available to field engineers so that they will be
in a better position to prepare, the Design of Structures, which are required to be
prepared at the field level itself. Keeping this in view, the present Document has been
prepared.

I am sure that this Document will serve its purpose and all the Engineers of
Department will find it extremely useful.

I wish to congratulate the authors of this book, Shri S.S.Phatak, Shri


P.K.Ninawe, Shri K.S.Jangde for their endeavour in writing the same.

I would appreciate suggestion for further improvement of this document.

G.K.DESHPANDE
SECRETARY (WORKS)
PUBLIC WORKS DEPARTMENT
GOVERNMENT OF MAHARASHTRA
MUMBAI.

4
INTRODUCTION

There was a long felt need to have a documented methodology to tackle


Design of R.C.C. Multistoried Buildings for the benefit of engineers of the Public
Works Department. With this intention, this document has been prepared, keeping in
view, the present practices and procedures adopted in Designs Circle. By following
this document the engineers will be in a position to tackle R.C.C. Design of buildings
independently.

Thanks are due to Shri L.C.Shah and Shri H.L.Sisodia, Executive Engineers,
Shri S.V.Jadhav, Assistant Engineer (I) of the BUILIDNG WING for many good
suggestions. Thanks are also due to, Mrs.S.B.Rangari and Mrs.J.U.Shenoy, Steno-
Typists who have typed the drafts, Shri S.K.Patil, Shri J.S.Shah, Shri V.G.Jadhav,
Tracers who have prepared the sketches. Thanks are also due to Shri K.S.Karmarkar,
Deputy Engineer and Desk Officer, Computer Cell P.W.D. Mantralaya, who have
guided in the preparation o f page layouts using computer software and his staff who
have prepared print copy.

Every care has been taken to make the matter more lucid, free from errors.
However, a few might have still escaped attention. Readers are requested to give their
valuable suggestions and point out the errors etc.

We hope that this book will serve its purpose.

S.S. PHATAK, Executive Engineer (BL-II)

K.S. JANGDE, Superintending Engineer (Bridge)

P.K. NINAWE, Superintending Engineer (Bldg.)

KONKAN BHAVAN, NAVI MUMBAI.

5
TABLE OF CONTENTS

SR.NO. CONTENTS PAGE

I. CHAPTER I
General philosophy of Building Designs
1 General Introduction. 1
2. Design philosophy. 2
3. Computer aided design. 2
4. Steps involved in R.C.C. Design. 3

II CHAPTER II
Prerequisites of Building Design
1 Study of Architectural drawing. 6
2 Study of field data. 7
3 List of I.S. Codes for Building Design. 8
4. General practice followed in Design Circle. 12

III. CHAPTER III


General procedure of Building Design
1. a) Guideline for preparation of R.C.C. layout . 14
b) Numbering system and notations to be adopted in layout. 14
2. Guidelines for fixing the position and orientation of columns 16
in the layout.
3. Guidelines for fixing the beam position. 17
4. Guidelines for fixing the slab directions. 18
5. Guidelines for beams and load combinations considered in 18
6. design 19
Preliminary column design and determination of size and
7. column sections. 20
Analysis of building frames.

6
IV. CHAPTER IV
Structural model and seismic analysis
1. Seismic Analysis 22
2. Preparation of STADD PRO Model of building 26
3. Analysis by STADD PRO 27
4. Design of various R.C.C elements of building (footing, 28
columns, beams, slabs etc.)
5. Computer aided design using in-house developed software 33
6. Earthquake resistance design guide lines as per I.S.4326. 33

V. CHAPTER V
Detailing
1. Notes to appear on various schedules. 39
2. Various format 43
3. Field data. 48
4. Sketches. 53
5. Govt. Circular of November 1980. 63

7
CHAPTER-I

GENERAL PHILOSOPHY OF BUILDING DESIGN.

DESIGN OF R.C.C. MEMBERS OF c) If the work is budgeted, item


BUILDINGS, PROCEDURE number of work and its page
FOLLOWED IN THE DESIGNS number in the Budget Book.
CIRCLE.

1. INTRODUCTION : Instructions (d) Proposed construction programme


about the preparation of R.C.C design i.e. proposed dates of start of
of building works have been issued different stages of construction and
vide Govt. in P.W.D. Circular scope of different phases
No.BDG-1080/ 80838 (394)/Desk-2, of construction, in case of
dt.3rd Nov.1980. (Kept at page 63) phased construction.

1.1 This circular states that R.C.C. (e) Field Data in standard proforma
design of all load bearing prescribed by the Designs Circle.
structures and R.C.C. framed Copy of the standard proforma is
structures upto four stories i.e. kept at page 48 .
G+3 upper, except in case of
structures requiring wind and/or 1.4 It is also desired that Field
seismic analysis, shall be prepared Engineer should communicate to
by the field engineers. Designs Circle, the present
position of the tender for the work
1.2 The design of R.C.C. frame i.e. the date of issue of tender
structures having more than G+3 notice, date of receipt of the tender
upper floors as well as structures and likely date of issue of work
with more that G+2 upper floors order. This information will be
requiring wind and/or seismic helpful to Designs Circle, in
analysis are required to be planning the design work and
prepared by Design Circle. there will be less likelihood of
delay in supply of R.C.C.
1.3 Designs Circle will undertake the Schedules from time to time i.e. as
work of preparing R.C.C. design per the construction programme
for a structure only after the proposed by field engineers.
receipt of the following
information from the field 1.5 It is a prerequisite that, before
engineers. undertaking actual design work,
the design engineer should have
(a) Copy of Administrative approval to basic knowledge of Strength of
the estimate of the structure, (based materials, Properties of
on approved Architectural materials, Behaviour of
drawings.) along with a blue print structures,, Analysis of
set of original Architects plans structures and thorough
(No traced copies are acceptable). knowledge about detailing of
reinforcement, etc. Also he should
(b) Copy of Technical sanction from be acquainted with various I.S.
the competent authority. Codes which are required to be
referred to in the design work. It

8
is, therefore, advised that the R.C.C. structures as per Limit State
designer should refresh his Method, since early eighties.
knowledge by referring to the
various technical books and codes. 2.3 Codes: In carrying out the design
calculations, one has to comply to
the provisions of various I.S.
2. DESIGN PHILOSOPHY : Codes. Use of special publications
of B.I.S. and Hand Books for
2.1 R.C.C. design of building is being design methodology and
carried out mainly (1) Limit state readymade design tables can also
method. be made. A List of frequently
referred codes/hand books is given
2.2. The Limit state method is now in on page 7.
vogue in all government design
offices and premier private 2.4 The designer is advised to study
consulting firms. The B.I.S. I.S. codes carefully and also
have published I.S.:456-2000 discuss the provisions among his
incorporating the use of Limit State colleagues/superior officers for
Method as a main philosophy of clarification/s for better
design. The designer should understanding.
therefore get well versed with the
theory of Limit State Method of 2.5 Besides analytical part of structural
design. design, following factors should
also be kept in mind while
Working Stress Method: Used over designing the structure.
decades, this method is now
practically outdated in many (a) Strength of structure.
advanced countries of the world,
because of its inherent limitations. (b) Durability of structure.

The I.S.:456-2000 code gives (c) Serviceability of structure,


emphasis on Limit State Method during construction as well as
which is the modified form of during design life time of the
Ultimate Load Method. structure.

Limit State Method is a judicious (d) Economy in building materials


amalgamation of Working Stress ease of construction and
Method and Ultimate Load maintenance.
Method, removing the drawbacks
of both the methods but retaining (e) Economy in centering and form
their good points. It is also based work.
on sound scientific principles and
backed by more than 25 years of (f) Aesthetics of structure.
research. The Limit State Method
has proved to have an edge over
the Working Stress Method from 3. COMPUTER AIDED DESIGN :
the economic point of view.
Consequently we need not stick to 3.1 Personal computers of sufficiently
Working Stress Method any more. high speed and large memory
Accordingly, Designs Circle in capacity have been made available
P.W. Department is designing the to Designs Circle. Designs Circle
has developed various design

9
software and same are being used. quick construction. Concrete Mix
Software available presently in to be adopted for beams and slabs
Designs Circle are discussed in as per IS :456-2000 page No.20.
Chapter IV. Designer should get
conversant with the Users Manuals (vi) Group the members such as
of these programmes so that he can columns, beams, slabs, footings
work independently on the etc. wherever possible, on the basis
computer. of the similarity of loading pattern,
spans, end conditions etc. It
At present mainly STAAD. Pro reduces the quantum of calculation
/Struds are being used for design of work.
buildings in Designs Circle. (vii) Prepare R.C.C. Layouts and
get approval from the Architect to
4. STEPS INVOLVED IN R.C.C. the R.C.C. layouts and tentative
DESIGN : sizes of beams and columns and
other structural members if any. In
The R.C.C. design of a building the R.C.C. layouts, show the
is carried out in following steps. structural arrangement and
orientation of columns, layout of
(i) Study the architectural beams, type of slab (with its design
drawings. (See page 6) live load) at different floor levels.

(ii) Study the field data. (See page For a building, generally following
7) R.C.C. layouts are prepared.

(iii)Prepare R.C.C. layouts at (a) R.C.C. layout at pile cap/plinth


various floor levels. (See page 14). level/tie level (if any).

(iv) Decide the imposed live load (b) R.C.C. layout at various floor
and other loads such as wind, levels or at typical floor level
seismic and other miscellaneous (depending on Architectural
loads, (where applicable), as per plans).
I.S.:875, IS 1893-2000 considering
the contemplated use of space, and (c) R.C.C. layout at terrace level.
seismic zone of the site of
proposed building. (d) R.C.C. layout at staircase roof
level.
(v) Fix the tentative slab and beam
sizes and then prepare preliminary and where lifts are provided.
beam design. Using values of
support reactions from preliminary (e) R.C.C. layout at lift machine
beam design, prepare preliminary room floor level.
column design and based on these
load calculations, fix tentative (f) R.C.C. layout at lift machine
column section and its concrete room roof level.
mix. As far as possible, for
multistories buildings, the same Where good foundation is available
column size and column mix at reasonably shallow depth, provision
should be used for at least two of plinth beams in Non Seismic Areas
stories so as to avoid frequent can be omitted. However, this should
changes in column size and be got approved from Superintending
concrete mix facilitate easy and Engineer/competent authority. In such

10
case the R.C.C. layout at plinth level For design of other types of footing
may be prepared accordingly. refer standard text books.

(viii) Finalise various structural frames (xiv) Design slabs manually by using
in X-direction and Y-direction Hand Book for R.C.members Vol.I
followed by preparation of frame or by using computer programme
sketches and filling in, data of the SLAB.
frames on coding sheets, for computer
aided frame analysis. (xv) Design beams by using the frame
analysis output. It gives required area
(ix) Feed the data of frames on of reinforcement at various locations
computer and recheck the data so and diameter and spacing of shear
stored, by getting a print out. reinforcement. Ductility shall be
applied for building in Seismic Zone-
(x) Analyse the frames using STAAD III & IV above.
Pro.
Designers work now involves.
(xi) Calculation of Horizontal
forces : Whenever the structure is to be (a) Fix the bar diameter and
designed for horizontal forces (due to number of bars (at top and
seismic or wind forces) refer I.S.:1893 bottom) at various locations
for seismic forces and I.S.:875 Part-III along the beam span, as per
for wind forces. codal provisions and practice.

All design parameters for (b) Finalise the diameter and


seismic/wind analysis shall be got spacing of shear
approved from Superintending reinforcement as per analysis
Engineer before starting design results and as per codal
calculations and frame analysis. The provisions of detailing where
proper selection of the various ever applicable.
parameters is a critical stage in design
process. (xvi) Preparation of R.C.C.
schedules for footings, slabs, beams
(xii) Design column sections and columns at various levels, on
Assemble the design data for column completion of respective design.
design, using results obtained in
analysis of respective X and Y As these R.C.C. schedules are to
direction frames, which include the be used during the execution, designer
column under considerations. The should take maximum care in
design of column can be done using preparing them. Schedules should be
computer programme ASP2 or prepared by one Engineer, and
manually by referring to Hand Book thoroughly cross checked by another
of R.C.members (Limit State Design) Engineer, before submitting the same
Volume II (Govt. of Maharashtra for approval to the competent
Publication). authority. In schedules, special
instructions to the field engineers
(xiii) Design footings manually using should be highlighted and sketches
Hand Book of R.C.C. members (Limit should be drawn wherever necessary.
State Design) Volume II or by using General notes to be mentioned on
the computer programme FOOT or schedules are kept at page 39.
other suitable programme Software for
design of isolated or combined footing.

11
Form of schedule of footings schedule
of columns, schedule of beams,
schedule of slabs are kept at page 44,
45, 46, 47 & 48 respectively.

12
CHAPTER-II

PRE-REQUISITES OF BUILDING DESIGN.

1. STUDY OF ARCHITECTURAL sizes required by Architect (on


DRAWINGS : architectural grounds) are given
or otherwise.
1.1 As the building is to be constructed
as per the drawings prepared by the (ii) Whether the plans and
Architect, it is very much schedules of doors and
necessary for the Designer to windows etc. are supplied so as
correctly visualize the structural to enable designer to decide
arrangement as proposed by the beam sizes at these locations.
Architect. A Designer, after
studying Architects plans, can (iii) Whether thickness of various
suggest necessary changes like walls and their height is given.
additions / deletions and Head room in stair and ramp,
orientations of columns and beams porch basement should be
as required from structural point of checked with reference of
view. required depth of beam.

1.2 For this, the designer should have a (iv) Whether functional
complete set of prints of original requirements and utility of
approved architectural drawings of various spaces are specified in
the building namely i) Plans at all the plans. These details will
the floor levels, ii) Elevations, help in deciding the imposed
(front, back and sides), iii) Salient load on these spaces.
cross sections where change in
elevation occurs and any other (v) Whether material for walls is
sections that will aid to visualize specified.
the structure more easily. The
cross sections should show the (vi) The structural arrangement and
internal details like locations of sizes proposed by the Architect
windows, doors, toilets, staircases, should not generally be
lift machine room, staircase rooms, changed except where
and any other special features like structural design requirements
gutter at roof level, projections can not be fulfilled by using
proposed to give special elevation other alternatives like using
treatment, etc. higher grade of concrete mix or
by using higher percentage of
1.3 During the study following points steel or by using any other
should be noted. The drawings suitable alternate structural
should be examined to find out, arrangement. Any change so
necessitated be made in
(i) Whether the plan shows all the consultation with the
required dimensions and levels Architect. Further design
so that the designer can arrive should be carried out
at the lengths and sizes of accordingly.
different members. Wherever
necessary, obligatory member

13
(vii) Note the false ceiling, (xi) Whether the location/s of the
lighting arrangements, lift/s over head water tanks
along with their individual specified by the Architect and
carrying capacity (either whether Field Data
passenger or goods), Air submitted by field engineer
Conditioning ducting, furnishes the required
acoustical treatment, R.C.C. capacity of each over head
cladding, finishing items, water tank.
fixtures, service/s opening
proposed by the Architect. (xii) What type of water proofing
treatment is proposed in
(viii) Note the position/s of toilet blocks and on terrace.
expansion joints, future
expansion (horizontal and / The findings of the above
vertical) contemplated in scrutiny should be brought to the
the Architects plan and notice of the Architect and his
check up with the present clear opinion in this matter
scope of work (indicated in should be obtained before
the Field Data submitted proceeding ahead with R.C.C.
by the field engineers). design.
The design of the present
phase will account for
future expansion provision 2. STUDY OF FIELD DATA :
such as loads to be
considered for column and 2.1 The architectural drawings give the
footing design (combined / details only from architectural
expansion joint footing) point of view. As such the
resulting if any. designer must also have thorough
information of the site where the
If this aspect is neglected it will structure is proposed to be
create design as well as constructed. For this a standard
execution problems in the next proforma has been prescribed by
phase of work. In case of Designs Circle. The field engineer
vertical expansion in future, the has to submit the field data in this
design load for the present proforma while requesting Designs
terrace shall be maximum of Circle for supply of R.C.C.
the future floor level design designs. Copy of the form of
load or present terrace level Field Data is kept as page 48.
design load.
2.2 The Field Data is essential before
(ix) Whether equipment layout has starting design work. However, it
been given, particularly in the is generally noticed, that the Field
areas where heavy machinery is Data lacks vital information such
proposed to be located. as bearing capacity of the founding
strata, proposed location and
(x) Special features like sun capacity of over head water tank/s,
breakers, fins, built-in electrical lift loads, future
cupboards with their sections horizontal and/or vertical
so as to enable designer to take expansion etc. So on receipt of
their proper cognizance. Field Data it should be checked
thoroughly and if any data is found
to be missing, the same should be

14
called from field engineer proposed (with reasons) and
immediately, to avoid delay in safe bearing capacity of the
starting the design work. founding strata and its depth
from the general ground level
2.3 Besides information on the points alongwith trial bore log
mentioned in prescribed proforma, details and test results on
information on special points also rock samples.
is to be supplied where applicable
by the field officers, like : (viii) If necessary,
(i) Machinery and/or Superintending Engineer,
equipment layout. Designs Circle shall visit the
site, in case of critical site OR
(ii) Air cooling/air conditioning field data is inadequate.
ducting layouts including
exhaust arrangements. 3. LIST OF I.S. CODES
GENERALLY REQUIRED TO
(iii) False ceiling arrangements, BE REFFERED TO FOR
proposed acoustical BUILIDNG DESIGN.
treatment, electrical lighting
and audio system fixtures. 3.1 The important I.S. Codes (with
their latest editions/amendments) to
(iv) Fire fighting pipeline/s or be referred to for design of
any other special ducting buildings are as follows :
layouts.
(i) I.S.:456-2000 : Code of
(v) Sub soil and sub soil water practice
properties particularly Sulfide for plain and
and Chloride contents where reinforced
the building is located in concrete.
coastal and or highly polluted
industrial area. (ii) I.S.:800-1962 : Code of
practice
(vi) Importance factor (I) and for use of
zone factor as per I.S.1893; to structural steel
be considered for the in general
proposed building when the building
building is being constructed construction.
in seismic zone. It may be
noted that the importance (iii) I.S.:875-1987 : Design loads
factor more than 1.0 leads to (Part I to V) other than
increased seismic forces earthquake for
consequently the building
reinforcement requirement design.
increases considerably.
Therefore before starting Part-I : Dead loads.
Seismic Analysis, importance Part-II : Imposed
factor (I) should be got loads.
approved from the Part-III : Wind loads.
Superintending Engineer. Part-IV : Snow loads.
Part-V : Special loads
(vii) In case foundations other and load
than open type of foundation combinations.

15
foundation.
(iv) I.S.:1080-1965: Code of (xi) I.S.:2911:1990: Code of
practice practice
for Design and (Part I to IV) for design and
construction of construction of
shallow pile
foundation in foundation.
soils (other
than (xii) I.S.:2950-1981: Code of
Raft, Ring and practice for
Shell) design and
construction of
(v) I.S.: 1642-1988: Fire safety of raft foundation.
Bldgs.
(General) (xiii) I.S.:3370-1965: Code of
Details of practice for
Construction. water
retaining
(vi) I.S.:1643-1988: Code of structures.
Practice
for Fire safety (xiv) I.S.:3414-1987: Code of
of Bldgs. Practice for
(General) Design and
Exposure installation of
Hazard. joints in
Buildings.
(vii) I.S.:1644-1988: Code of
practice for fire (xv) I.S.:4326-1993: Code of
safety of Bldgs. practice for
(General) Exit earthquake
requirements resistant
and design
personal of structure.
Hazards.
(xvi) I.S.:6403-1981: Code of
(viii)I.S.:1888-1972:Methods of Practice for
load test Determination
on soils. of bearing
pressure of
(ix)I.S.:1893-(Part 1): Criteria for shallow
2002 earthquake foundation.
resistant design
of structures. (xvii) I.S.:13920-1993: Code of
(reaffirmed practice for
(x) I.S.:1904-1986: Code of 1998) ductility
practice detailing of
for design & reinforced
construction of concrete
foundation in structures
soil structural subjected to
safety of seismic
building forces.

16
I.S. Codes are also available for 3.2.1 General Provisions :
design of special types of structures Clause No.20 : Deals with
like folded plate, shell structures stability of the
etc. Refer Publication list of BIS structure
for the same. against
overturning
Similarly there are special and sliding.
publications of I.S. which are
useful for design of buildings such Clause No.26.2.1 : Development
as. length of bars.

(i) SP-16 : Design Aids to Clause No.26.3.2: Minimum


I.S.:456-2000. distance
between
(ii) SP-22 : Explanation of individual bars.
I.S.1893 &
I.S.:4326. Clause No.26.3.3: Maximum
distance
(iii) SP-23 : Concrete Mix. between
bars in tension.
(iv) SP-24 : Explanation of
I.S.:456-2000. Clause No.26.4 : Nominal Cover
to
(v) SP-25 : Cracks in buildings reinforcement.
and their repairs.
Clause No.27 : Expansion
(vi) SP-34 : Detailing in R.C.C. joints.
structures.
3.2.2 Provision regarding slabs :
(vii) SP-38 : Design of steel
trusses. Clause No.22.2 : Effective span.

Besides above mentioned I.S. Clause No.22.4.1: Arrangement of


Codes Hand Book for Imposed load.
R.C.Members (Limit State
Design) Vol.I.and II by P.L. Clause No.22.5 : Moment and
Bongirwar and U.S.Kalgutkar, shear
published by P.W.D. (Govt. of co-efficient
Maharashtra) is very useful. for continuous
beams.
For aspects which are not covered
by any other I.S. codes available, Clause No.23.2 : Control of
relevant British Standard codes deflection.
may be referred to.
Clause No.24.1 : Provisions
3.2 While designing R.C.C. structures, regarding solid
important provisions of I.S.Codes slabs.
must be borne in mind. Some of Clause No.26.5.2.1: Minimum
the important provisions of reinforcement.
I.S.:456-2000 are as follow :
Clause No.26.5.2.2: Maximum
diameter.

17
3.2.3 Provisions Regarding Beams : Clause No.25.1.3: Unsupported
length.
Clause No.22.2 : Effective span.
Clause No.25.2 : Effective
Clause No.22.4.1: Arrangement length of
of live load. compression
members.
Clause No.22.5 : Moment and
Shear Clause No.25.3: Slenderness
co-efficient limits for
for continuous columns.
beams.
Clause No.25.4 : Minimum
Clause No.23.2 : Control of eccentricity.
deflection.
ClauseNo.26.5.3.1:
Clause No.23.3 : Slenderness Longitudinal
Limits reinforcement.
for beams.
Clause No.26.5.3.2: Transverse
Clause No.26.5.1.1: Requirement reinforcement.
of tensile
reinforcement Clause No.43 : Cracking
for beams. consideration.

Clause No.26.5.1.2: Compression 3.2.5 Provisions for footings :


reinforcement.
Clause No.34.1.2 : Thickness at
Clause No.26.5.1.3: Side face the edge of
reinforcement. footing.
Clause No.34.4 : Transfer of
Clause No.26.5.1.5: Maximum load at the
Spacing base of
of shear columns.
reinforcement.
Other references / Literature
Clause No.26.5.1.6: Minimum generally referred to are
shear
reinforcement. 1.Reinforced Concrete Designers
Hand Book by Reynolds &
Steelman.
Clause No.26.5.1.7: Distribution 2.Limit State Theory & Design of
of torsion Reinforced Concrete by Karve and
reinforcement. Shah.
3.Hand Book of Reinforced Concrete
3.2.4 Provisions for Columns : Design (I.S.455-1978) by Karve.
4. Limit State Design of Reinforced
Clause No.25.1.2: Short and Concrete by Vergis.
slender
compression
members.

18
4. GENERAL PRACTICE (ix) Deduction in dead loads for
FOLLOWED IN DESIGNS openings in walls need not be
CIRCLE : considered.

(i) The loading to be (x) Unless otherwise specified,


considering for design of different the weight of various materials
parts of the structure including shall be considered as given below
wind loads shall be generally as per :
I.S.:875-1987 (Part I to IV) and
I.S.:1893-2002 (seismic loads) with (a) Brick masonry :1920
their latest amendments/s. kg/m3

(ii) Live load for sanitary block (b) Reinforced cement :2500
shall be 200 kg/m2. concrete kg/m3.

(iii) Lift machine room slab (c) Floor finish for : 100
shall be designed for live load of heavy weight suitably kg/m2
1000 kg/m2. added and for light
weight subtracted.
(iv) Lift loads shall be
considered as per relevant I.S. (d) Brick Bat Coba of : 200
codes as per capacity of lift and the 112 mm. thickness kg/m2
same shall be increased by 100% laid on terrace for
for impact while designing. water proofing
treatment.
(v) Loading due to electrical
installation e.g. A.C. ducting, (e) Brick Bat Coba in :1920
exhaust fans etc. shall be got bath & W.C. kg/m3.
confirmed from the Executive depending on
Engineer, electrical wing of P.W. thickness of water
Department. proofing treatment .

(vi) Seismic loads shall be as (xi) The analysis shall be


per I.S.:1893-2002 and I.S.4326- carried out separately for dead
1993. The method of analysis and loads, live loads, seismic loads,
values of various parameters shall wind loads. All the structural
be taken as per relevant provisions components shall be designed for
of the codes. the worst combination of the above
loads as per I.S.:1893-2002.
(vii) Ductility provisions
specified in I.S.:4326-1993 and (xii) Minimum reinforcement in
I.S.:13920-reaffirmed 1998 Edition all structural members shall be as
1.2, 2002-2003 shall be adopted in per relevant clauses of I.S.: 456-
design, for the buildings located in 2000.
Seismic Zone III, IV & V.
(xiii) The R.C.C. detailing in
(viii) Any other loads which may general shall be as per SP:34 and as
be required to be considered in the per the sketches given in this
designs due to special type or guidelines.
nature of the structure shall be got
approved in advance from the
Superintending Engineer.

19
(xiv) High Yield Strength
Deformed bars shall be used for
main and distribution
reinforcement.

(xv) Diameter of bars in


footings, shall be not less than 10
mm.

(xvi) Spacing of stirrups in


beams shall not exceed 25 cm.

(xvii) Thickness of slab shall not


be less than 12 cm. and in toilet
blocks not less than 15 cm.

(xviii) Depth of beam shall not be


less than 23 cm.

(xix) Spacing of ties in columns


shall not exceed 25 cm.

(xx) The longitudinal bars in


columns shall not be less than 12
mm. in diameter.

20
CHAPTER-III

GENERAL PROCEDURE OF DESIGN

1A. GUIDELINES FOR capacities. Such movement joints,


PREPARATION OF R.C.C. however shall be provided right to
LAYOUTS. the bottom of the foundation,
unlike the expansion joints which
1.1 The preparation of R.C.C. layouts are provided only upto the top of
involves fixing of locations of the foundation. In this regard refer
columns and beams, denoting slabs to S.P.34, (explanatory Hand Book
with respect to design live load, of I.S.:456-2000 clause 27 and also
type of slab and numbering these refer clause 5.1.1 of I.S.:4326-
structural elements. 1993. As per this clause the
minimum total gap between these
1.2 There are two types of joints which joints shall be 25 mm.
need to be considered in the
layouts. They are (a) movements 1.5 Separate R.C.C. layouts are to be
joints, (b) Expansion joints. prepared for different levels i.e.
plinth, typical or at each floor level
1.3 If the length of building exceeds 45 (if the plans are not identical at all
m., expansion joints shall be floor levels) terrace floor level,
provided to split it into suitable staircase block roof level and
parts which are individually less where applicable lift machine room
than 45 m. in length. Building floor level, lift machine room roof
having wings in different directions level, water tank bottom level.
shall be provided with expansion
joints at the connection of the 1.6 R.C.C. layouts are generally
wings to central core to avoid prepared on tracing paper from the
torsional effects. Expansion joints architectural drawings, by tracing
may also be provided when there is only the walls, columns and other
a sudden change in plan structural members. In the layout,
dimensions. For details of the the door and window positions are
joints refer to I.S.:3414-1968, not shown.
I.S.:4326-1976 and I.S.:3370-1965
(Part-I), I.S.:1893-2000. 1B NUMBERING SYSTEM AND
NOTATIONS TO BE
1.4 In case the building is having ADOPTED IN LAYOUTS
different number of stories for
different parts of the building, thus 1.1 Columns:
having different dynamic
characteristics, then such parts Columns are numbered serially
shall be kept separated by a with integer number suffixed to
movement joint to avoid unequal letter C i.e. C1, C2, C3 etc. The
loading, unequal settlement and columns are numbered from lower
collusion during an earthquake. most left corner of the R.C.C.
Movement joints may also to be layout. Numbering shall proceed
provided if the different parts of from left to right in X direction and
building are located on different proceeding successively in positive
stratas and of different safe bearing Y direction. R.C.C. layout

21
showing column numbering is kept (iii) For numbering the secondary
as page 43. beams in X direction the first
part of beam number shall be a
1.2 Beams : reference column which shall
be the nearest left side column
(i) Beam actually supported over a of the beam. The second part
column is called main beam. shall be odd number except 1
Beam supported over other i.e. 3, 5 etc. serially in X
beam is called secondary beam. direction. e.g.5.3, 5.5 etc.

(ii) A beam number is composed of Similarly secondary beams in


two parts e.g.5.1, 5.2 etc. The Y direction can be numbered
part to the left of decimal point e.g. 5.4, 5.6 etc. except 2.
denotes the left side reference
column number. The part to (iv)If the beams are at intermediate
the right represents serial level above the floor under
number of the beam. consideration then the beam
number will be suffixed with a
Beams in X direction here the letter like A, B & M. e.g. If 5.1
reference column is left is main beam at 1st floor level,
supporting column. If left 5.1 A is a beam in X direction
supporting column is absent at 1 st floor lintel level, and 5.2
then right supporting column is M is a beam in Y direction at
considered as reference MIDLANDING LEVEL
column. For X direction beam between the 1st floor and 2nd
serial number (2 nd part) is floor levels. A refers to floor
always odd e.g. 1, 01, 3, 03 etc. level and B refers to lintel
Beams to the right side of level and M refers
reference column is numbered midlanding level.
as 5.1 etc. While beams to the
left of reference column is (v) A R.C.C. layout showing
numbered as 5.01, where the the beam numbering is kept
reference column is C 5. at page 43.

Beams in Y direction in this 1.3 Slabs :


case reference column is
bottom most column. If the The slab notation is composed of
bottom column is absent then four parts. The first, second and
the upper supporting column third part are written on the left
can be considered as the side of the decimal point and the
reference column. For Y 4th is written on the right hand side
direction beam serial number of the decimal point e.g. 200S1.1,
(2nd part) is always even 500S2.2.
number e.g.5.2, 5.02, 5.4 etc.
Beams in positive Y direction (i) The first part denotes the
of reference column are imposed live load intensity in
numbered as 5.2 while beams Kg./sqm. for which the
in negative Y direction of the particular slab is designed.
reference column are numbered This load is decided on the
as 5.02, where the reference basis of designated use of the
column number is. C 5. particular space (the slab) as
shown in the Architects plans

22
and as per provisions of The dead load of various
I.S.875. This practice is useful structural material and live loads
and advantageous for adopted for different slabs and
maintaining a proper record the R.C.C. layouts shall be got
especially when different slab approved from Superintending
panels are designed for Engineer.
different live loads. This
record is also useful to avoid
over loading of the slab in 2 GUIDELINE FOR FIXING THE
future change of usage. POSITION AND ORIENTATION
OF COLUMNS IN THE LAYOUT.
(ii) The second part represents the
type of the slab fore e.g. This is an important stage. It is
skillful job and economy in design
S denotes general floor slab, is achieved by locating columns at
SF denotes staircase flight proper and/ideal locations.
slab,
SR denotes room roof level (i) Normally the positions of the
slab / staircase room roof level columns are shown by Architect in
slab, his plans.
SM denotes machine room
floor slab (ii) Columns should generally and
SC denotes cantilever slab preferably be located at or near
and corners and intersection/junction of
ST denotes terrace slab. walls.

(iii) The third part is either 1 or (iii) If the site restrictions make it
2 , 1 denotes the slab is obligatory to locate column
one way. The 2 denotes the footings within the property line
slab is two way. the column may be shifted inside
along a cross wall to accommodate
(iv) The fourth part is the serial footings within the property line.
number of the slab in one Alternatively trapezoidal footing,
way/two way category. Slabs eccentric footing can also be
having different end adopted.
conditions shall be treated as
different slabs for this In residential buildings, generally
notation. columns should be located at 3 to 4
m.c/c. to avoid large spans of
(v) Slabs shall be grouped on the beam. This will also control
basis of panel dimensions, deflection and cracking.
loading pattern and end
conditions. (iv) While fixing the orientation of
columns care should be taken that
(vi) The notation for one way slab, it does not change architectural
two way slab, 23 cm. brick elevation. This can be achieved by
wall, 15 cm. thick brick wall, keeping the column orientations
R.C.C. pardi is shown on and side restrictions as proposed in
sample R.C.C. layout kept at plans by the Architect.
page 43.

23
(v) As far as possible, column (xiii) As far as possible every column
projection/s outside the walls must be connected (tied) in both
should be avoided, unless directions with beams at each floor
Architects plans show contrary or level, so as to avoid slender
same is required as structural columns.
requirement.
(xiv) As far as possible columns
(vi) Columns should not obstruct door supported on beam should be
and window position/s shown in avoided. (Such columns are
the Architects plans. commonly called as floating
columns)
(vii) As far as possible columns should
be so positioned, that continuous (xv) When columns along with
frames from one end to the other connecting beams form a frame,
end of building in both X and Y the columns should be so
directions are available. This will orientated that as far as possible the
increase the global stiffness of the larger dimension of the columns is
building against horizontal forces. perpendicular to the major axis of
bending. By this arrangement
(viii) When the locations of two column sections and there
columns are near to each other (for reinforcement are utilized to the
e.g. the corner of the building and best structural advantage.
intersection of the walls) then as
far as possible only one column 3. GUIDELINES FOR
should be provided or secondary FINALISING THE BEAM
beam shall be provided. POSITIONS :

(ix) As far as possible columns should (i) Normally beams shall be provided
not be closer than 2m. c/c to avoid below all the walls.
stripped/combined/continuous
footings. (ii) Beams shall be provided for
Generally the maximum distance supporting staircase flights at floor
between two columns should not levels and at mid landing levels.
be more that 8m. c/c.
(iii) Beams should be positioned so to
(x) Column should be normally restrict the slab thickness, to 15
provided around staircases and lift cm, satisfying the deflection
wells. criteria. To achieve this, secondary
beams shall be provided where
(xi) Preferably overhead water tank necessary.
should rest on the columns as
shown in the Architects plan. The (iv) Generally we come across with the
height of water tank should be upto situation that there is a gap
2.0 m. Clear height between top of between the floor level beam and
Terrace and Bottom of water tank beam supporting the chajja. Here
should not be less than 0.90 m. the depth of floor beam shall be so
chosen that it can support chajja
(xii) Twin columns of equal size are also. However if depth so required
desirable at expansion joints from is large (distance between floor
aesthetic point of view. beam bottom and lintel top, greater
than 30 cm) provide separate beam.

24
(v) As far as possible, cantilever beams Where Lx is shorter span and
should not be projected from Ly is longer span of the slab.
beams, to avoid torsion.
(ii) However as per Designs
(vi) Beams of equal depths shall be Circles practice slabs upto 2.5 m.
provided on both sides of the spans may be designed as one
expansion joint from aesthetical way slabs.
point of view.
(iii) Canopy, Chajja, balcony slabs
(vii) To get the required minimum are generally provided as
head room, following alternatives cantilever slabs.
can be tried.
(a) Reduce the beam depth without (iv) W.C. slab is generally made
violating deflection criteria and sloping or sunk by about 50 cm.
maximum percentage of steel OR as indicated in architects
criteria for beams. drawing below general floor level
for Indian type water closet.
(b) In case there is a wall, over the Slabs for toilet block and Nahani
beam without any opening, slab are generally sunk by 20 cm.
inverted beam may be provided in OR as indicated in architectures
consultation with Architect. drawing below general floor
level.
(viii)Where secondary beams are
proposed to reduce the slab (v) Staircase waist slab shall be
thickness and to form a grid of generally one way slab.
beams, the secondary beams shall
preferably be provided of lesser (vi) Loft slabs over toilets are
depth than the depth of supporting generally supported on partition
beams so that main reinforcement walls of toilet and W.C. Loft load
of secondary beams shall always should be considered while
pass above the reinforcement of designing the beams supporting
main beams. these walls.

(ix)In toilet block provide minimum


number of secondary beams so that 5. PRELIMINARY BEAM
casting of slabs and beams will be DESIGN (P.B.D.)
simple. No secondary beam
condition would be ideal. All secondary beams may be
(x) Beams which are required to give a treated a simply supported beams.
planer look from the underside
shall be provided as Inverted 5.1 Begin with fixing the dimensions
Beams, e.g. canopies. of beam. The width of the beam
under a wall is preferably kept
equal to the width of that wall to
4. GUIDELINES FOR FIXING avoid offsets i.e. if the wall is of 23
THE SLAB DIRECTIONS : cm. then provide beam width of 23
cm.
(i) Slab shall be designed as one
way slabs if ratio of Ly to Lx is 5.2 Minimum width of main and
more than 2 and two way slab, secondary beam shall 23 cm.
if the ratio is equal or less than However secondary beams can be
2. of 15 cm. in case of beams of toilet

25
block. The width of the beam (iii) As T beam if it supports
should also satisfy architectural slab on both sides.
considerations.
5.7 Arrangement of imposed load :
5.3 The span to depth ratio for beam be
adopted as follows : (a) Consideration may be limited to
combinations of :
For Buildings in seismic zone
between 10 to 12 and for non- (i) Design dead load on all
seismic zone 12 to 15. spans with full design live
load on two adjacent spans.
In case of Building located in
Seismic Zone III, IV, V width to (ii) Design dead load on all
depth ratio shall be more than 0.30. spans with full design live
The depth so calculated shall be as load on alternate spans.
shown in the Architects plan.
(b) When design live load does not
5.4 To limit deflection, of a beam (upto exceed 75% of the Design Dead
10 m. span) within the permissible load, the loading arrangement may
limit, under service load, the be, Design Dead load and Design
I.S.:456 clause 23.2.1 provides the live load, on all spans.
following span to depth ratios.
5.8 For beams and slabs continuous
(i) For cantilever not more over supports, Load combinations
than 7 given in 5.7 above may be
assumed.
(ii) For simply supported
beam not more than 20. 5.9 STAAD and Struds software is
used for design.
(iii) For continuous beam
not more than 26.
6. PRELIMINARY COLUMN
These ratios can be further DESIGN AND
modified according to Modification DETERMINATION OF SIZE
Factor depending upon percentage OF COLUMN SECTION :
steel used in the section as per (P.C.D.)
I.S.:456 clause 23.2.1 (e).
6.1 The dimensions of a particular
5.5 The beams shall be designed as column section, is decided in the
deep beam/slender beam as the following way :
case may be.
(i) A column shall have
5.6 The beam shall be treated as minimum section 23 cm. X
23 cm. if it is not an
(i) A rectangular beam if it obligatory size column.
does not support any slab
on either side also if it is an (ii) The size of the obligatory
inverted beam. column/s shall be taken as
shown on the architects
(ii) As L beam if it supports plan. For non obligatory
a slab on one side and columns as far as possible
the smaller dimension shall

26
equal to wall thickness as to building at least two floors should
avoid any projection inside have the same column section.
the room. The longer Preferably least number of column
dimension should be chosen sizes should be adopted in the
such that it is a multiple of entire building and mix of all the
5 cm. and ratio Pu/fck bd is columns on a particular floor
restricted to, for non- should be same.
seismic area 0.4 (for corner
columns it may be 0.35) 6.4 Effective length of column shall be
and for seismic region 0.35 calculated as per figure 26 and 27
(for corner columns it may of I.S.456-2000.
be 0.30).
6.5 Columns shall be designed for
Where Pu, Fck, B, D have the direct load and uniaxial or biaxial
following meaning : bending considering different for
load combinations as given in
Pu is the factored load on the I.S.:456:2000.
column. (in Newton)
6.6 Grouping of columns can be done
Fck is characteristic compressive on the basis of size, orientation and
strength of concrete. forces acting on it.
(Newton/mm2)
6.7 All R.C.C. layouts, tentative sizes
b is the breadth of the column of beam, and column sections
(mm). should be got approved from the
Architect before starting analysis
d is the depth of the column (mm) of frames.

6.2 The above ratios will ultimately 7. ANALYSIS OF BUILDING


help in keeping the requirements of FRAMES
steel for column within 0.8 to
2.5% which is economical and will 7.1 In Designs Circle, at present, space
avoid congestion of steel. analysis is done by treating the
Generally the concrete mix in building as composed of only plane
R.C.C. work shall be as per Table frames.
No.5 of I.S.:456-2000. For
moderate exposure condition M- A building may be required to be
20 for R.C.C. and for severe designed for Non Seismic/-
exposure condition minimum grade Seismic Forces and/wind forces
shall be M-30. (whichever is governing)
depending on the location, plan
6.3 If the size of a column is obligatory dimensions and height of the
or if size can not be increased to building.
desired size due to Architectural
constraints and if the ratio of 7.2 An another software STRUDS is
Pu/fck bd works out to be more available in the Designs Circle.
than the limit specified above it The same is used for small
will be necessary to upgrade the buildings.
mix of concrete. For ease of
construction frequent changes in 7.3 The other inhouse programmes
column size should be avoided. As FOOT, EC FOOT, SLAB,
far as possible in multistoried ASP2 are available. These

27
Programmes are used for design of The magnitude of seismic nodal
various components such as Isolated horizontal forces are worked out.
Footing, Combined Footing, Slab
and Columns. Before starting the analysis of
frames the forces for which the
7.4 For buildings located in all Seismic building is to be designed and the
Zone, seismic analysis is required to design parameters and particularly
be carried out and ductile detailing is Importance Factor (I) and for
not done for Zone I & II. Seismic Design to be adopted
approved from Superintending
Engineer.

28
CHAPTER-IV

STRUCTURAL MODEL AND SEISMIC ANALYSIS

1 SEISMIC ANALYSIS Regular and irregular buildings


other than above all seismic
1.1 For Calculating seismic forces refer zones can be designed for
provisions of I.S.:1893-2002 (PART seismic forces by static method
I) of analysis.

1.2 It should be noted that provisions of At present, most of the buildings


I.S.:1893-2002 (Part I) are we come across, use of static
applicable to buildings, elevated approach is adequate.
structures, industrial and stack like
structures, bridges, concrete However, for important
masonry and earth dams, buildings where it is felt
embankments and retaining walls necessary to carry out Dynamic
and other structures. Analysis, the Superintending
Engineer may advice to carry out
Temporary elements such as the Response Spectrum Method
scaffolding, temporary excavations or Modal analysis.
need not be designed for earthquake
forces. For all buildings checking for
drift and torsion is necessary.
1.3 Dynamic analysis shall be performed This can be done by necessary
to obtain the design seismic forces commands in STAAD Pro
and its distribution to different levels Model Analysis.
along the height of the building, for
the following buildings : 1.2. STATIC APPROACH FOR
SEISMIC ANALYSIS
a) Regular buildings :
1.2.1 In this approach the structure is
Buildings greater than 40 m. treated as a discrete system,
in height in Zone IV & V and having concentrated masses at
those greater than 90 m. in the different floor levels which
height in Zone II and III. compose of mass that of columns
and walls of half the floor above
b) Irregular buildings : (As and half of the floor below.
defined in Clause 7.1 of
I.S.1893:2002 (Part I) 1.2.2 Using details from STAAD Pro
Model analysis the base shear
All framed buildings for can be worked out as follows :
height more than 12 m. in
Zones IV & V, and those (i) Find seismic weight (w) of
greater than 40 m. in height the building; by taking sum
in Zone II & III. of all reactions at footings
level by considering full
Dead load and Appropriate
% of Imposed load as per
Clause 7.3.1, Table 8 of
I.S.:1893-2002 (Part I).

29
Seismic Weight (W)
Ta = 0.09h where,
Full Dead Load of building + d
Appropriate % Live load on h = Height of building in m.
all floors except terrace. (Clause 7.6.1)
(Clause 7.4.2) I.S.:1893-2002
(Part I) ) d = Base dimension of the building
at plinth level in m. along the
(ii) For calculating the considered direction of the
earthquake forces on terrace lateral force.
(roofs) the live load may not
be considered. (Clause 7.3.2) (iv) Calculate base shear (Vb),
using formula given in
(iii) Find the design horizontal I.S.:1893 Clause 7.5.3.
seismic co-efficient (Ah)
(Clause 6.4.2) (Vb) = Ah x W

Ah = Z. I x Sa (v) Distribute the base shear


2R g between all floors of building
as per Clause 7.7.1 of
Where, I.S.:1893. These are floor
lateral shear forces for space
Z = Zone factor frame analysis.
[ as per Table 2 of
I.S.1893-2002 (Part-I) ] For this,
a) Find seismic weight of
I = Importance factor each floor.
[ as per Table 6 of
I.S.1893-2002 (Part-I) ] b) Find lump weight of each
floor (wi) (Clause 7.4.1)
R = Response reduction
factor [ as per Table 7 of c) Distribute the base shear
I.S.1893-2002 (Part-I) ] VB along the height of the
building to different floor
Sa/g = Average Response levels as per the following
acceleration co-efficient for expression :
rock or soil sites as given by
Fig.2 or Table 3 of I.S.:1893- Qi = VB Wi hi 2
n
2002 (Part I) and based on S Wjhj2
j=1
appropriate fundamental Where,
natural periods (Ta)
Qi = Design lateral force at
For buildings without brick Floor i
infill panel Wi = Seismic weight of floor i

Ta = 0.075 h0.75 .. For R.C.Frame hi = height of floor i measured


building. from base.

Ta = 0.085 h0.75 .. For Steel Frame n = Number of storeys in the


building. building is the number of
For building with brick infill levels at which the
panel- masses are located.

30
horizontal fore say 5 KN or
1.2.3 Seismic Analysis is carried out any Value in X & Z direction
based on the following at each joint. (F element)
assumptions and run the STAAD Pro
Programme for load
(i) The Seismic Force acts, at a combination cases using
time along one direction partial load factor 1.
only, i.e. when seismic force
alongwith Dead and live load Generally the deflection in a
act on a space frame along X frame at terrace level, is
direction, then on Z direction maximum.
only Dead and live load
forces are acting and vise As stated earlier the total base
versa. Also, earthquake is not shear is shared in all X Z space
likely to occur frame joints of the building in
simultaneously with wind or inverse proportion of their
maximum flood or maximum deflections. The inverse of
sea weaves. deflection for each space frame
joint is calculated. Then using
(ii) The nature of seismic force these values, ratio of (inverse of
action is reversible in deflection of a particular frame
direction (i.e. + and forces joint (X/Z) Direction/sum of
can act on the space frame) inverses of deflections of all
(X/Z) Direction joint is worked
(iii) Horizontal deflection of all out for each and every space
joints of a frame, at particular frame joint. This value
floor level is same. multiplied by the lateral force at
that floor in a particular direction
(iv) The individual space frame gives the Horizontal force to be
joint, shares the storey shear applied at that joint in a
in proportion to its stiffness. particular direction.

(v) The inverse of deflection of a 1.2.6 After applying all horizontal


joint is treated as a measure seismic forces at all frame joints
of its stiffness. in X & Z direction, analysis is
carried out for all required load
1.2.4 A judicious choice of beam combination cases and detailed
sections (as explained in para 5) space frame analysis results can
and column sections (as be obtained.
explained in para 6) will ensure
deflection of the frames within All above calculations can be
permissible limits. done by STAAD. Pro
Programme output, using excel
1.2.5 As per Clause 7.7.2, of I.S. sheets.
1893(Part-I):2002 to distribute
horizontal lateral force to For latest STAAD. Pro analysis
different lateral force resisting programme, it is not necessary to
elements (joints), following calculate and apply seismic forces
procedure is done: manually, but only by providing
seismic parameters, STAAD
1) Find joint displacements of Programme itself calculate and
each joint by applying a unit

31
apply seismic forces both for static per Clause 5 & 6 of I.S.875:1987
and dynamic analysis. (Part III)

However, the designer should be 1.3.3 Design wind speed is to be


alert to check the correctness of calculated . Clause 5.3 of
the seismic analysis done I.S.875:1987 (Part III)
automatically by computer by Vz = Vb K1 K2 K3
verifying the result parameters like
base shear, fundamental time Where,
period, Sa/g, seismic wt of
building and deflections. Vz = Design wind speed at any
height Z in m/sec.
1.3. WIND ANALYSIS:
Vb Basic wind speed .. Fig.1 or
1.3.1 As per I.S.875:1987 (Part-V) & Appendix A of
I.S.1893:2002 (Part-I), it is I.S.875:1987 (Part III) map
always an assumption that of wind speed to be
earthquake is not likely to occur attached.
simultaneously with wind or
maximum flood or maximum sea K1 Probability factor .. C1
weaves. No.5.3.1 of I.S.875:1987
(Part III)
While designing, in the load
combinations, dead load and K2 Terrain, Height & Structure
imposed loads should be size factor .. C1 No.5.3.2 of
combined with either earthquake I.S.875:1987 (Part III)
load or wind load.
K3 Topography factor
There are various types of Cl.No.5.3.3 of
structures or their components I.S.875:1987 (Part III).
such as some tall buildings,
chimneys, towers, long span 1.3.4 After calculating design wind
bridges etc. which require speed (Vz), design wind pressure
investigation of wind induced is to be calculated as per
oscillations. Cl.No.5.4 of I.S.875:1987 (Part
III).
A large majority of structures
met with in practice do not Pz = 0.6 Vz2
however, suffer wind induced
oscillations, and do not require to Where,
be examined for dynamic effects
of wind. These structures are to Pz design wind pressure in
be analysed by static method. N/Sq.M. at height Z.

1.3.2 Static method of wind load Vz design wind velocity in


estimation which implied a m/s at height z.
steady wind speed, has proved to
be satisfactory for normal, short 1.3.5 The wind load on a building
and heavy structures. shall be calculated for

Analysis for wind forces by


static approach is to be done as

32
a) Building as a whole .. C1 direction only Dead and live
No.6.3 of I.S. : 875:1987 load forces are acting and
(Part III) vice versa.

F = Cf Ae Pd (ii) Horizontal deflection of all


joints of frame at particular
Where, floor level, is same.

F = Force acting in a direction (iii) The individual frames share


specified in respective tables the storey horizontal force in
given in I.S.: 875 (Part-3)- proportion to its stiffness.
1987
1.3.7 Para 7.1 of the IS 875 (Part-
Cf Force co-efficient for the 3):1987 stipulates that flexible
building .. Table 23 slender structure and structural
I.S.875:1987 (Part III) elements shall be investigated to
ascertain the importance of wind
Ae Effective frontal area of the induced oscillations or excitations
building along and across the direction of
Pd Design wind pressure wind.

b) Individual structure elements In general the following guide lines


as roofs and walls or may be used for examining the
cladding units as per clause problem of wind induced
No.6.2.1 of I.S.875: 1987 oscillations.
(Part III).
a) Building and closed structures
F = (Cpe Cpi ) A Pd with height to minimum lateral
dimension ratio more than 5 and
Where,
b) Buildings and closed structures
Cpe External pressure whose natural frequency in the first
coefficient mode is less than 1 Hz.

Cpi Internal pressure coefficient Any structure or building which


does not satisfy either of the above
A Surface area of structure two criteria shall be examined for
element or cladding unit dynamic effects of wind. For the
modal analysis (on similar lines of
Pd design wind pressure modal seismic analysis) will be
carried out. If the wind induced
1.3.6 After calculating the wind force, oscillations are significant, analytical
static wind analysis is done on methods like use of wind tunnel
following assumptions similar modeling will have to be carried out.
for earthquake analysis:
2 PREPARATION OF STAAD. PRO
(i) The wind force act at a time MODEL OF BUIDLING.
only along one direction i.e.
when dead load, live load 2.1 After study of Architectural
and wind forces are assumed drawings and field data and with the
to act on a frame along X help of R.C.C. layouts, STAAD. Pro
direction then, along Z Building Model can be prepared.

33
The computer programme has two 7) Member release Command ;
methods of input data for preparing
STAAD Pro Model. Simply supported ends of beams are
released for moments by this
a) Graphical Environment command.
b) By analytical input of data.
8) Members Offset Command :
Designer may use either of the above
methods or combination of both to By this command position of beam
prepare space frame building model. always from column center is fixed.
Following steps are followed :
By above Commands Building
a) Analytical input of data : Geometry Model is prepared on
STAAD Pro.
1) Write joint co-ordinates of each
joint by command Joint Co- 2.2 LOADING :
ordinates create nodes.
STAAD. Pro Building Geometry so
2) These nodes are joined to each prepared is loaded by applying
other to form a column, beam selfweight, wall loads, slab, lift
skeleton by command Member loads, water tank loads etc. and
incidences. Imposed loads, wind, seismic loads
by creating different load cases.
The space frame Geometry is so (Load 1, Load 2, Load 3 etc.)
formed.
2.3 Load combination cases are
3) Then column/beam sizes like prepared by use of above primary
width, depth are given by the load cases by command Load
computer programme command Combination.
Members property Indian.
2.4 Next command is Perform
4) Material Information is given by analysis and Load List, last
command Define Material. command is FINISH.
The information like E (Modulus
of elasticity of concrete), Poisson
ratio, density, Alpha value, 3 ANALYSIS BY STAAD PRO
Damping value for R.C.C. are
given. 3.1 Programme : Checking of Input
data:
5) Constant Command :
After preparation of STAAD Pro
This command is used for fixing building Model, its input data shall
column orientations by Beta be checked thoroughly by various
angle. commands available in STAAD Pro
Software for its correctness.
6) Support Command :
3.2 RUNNING OF STAAD.Pro
Supports (Fixed/Pinned) are ANALYSIS PROGRAMME :
given by this command.
By giving command Perform
Analysis programme runs. And it

34
gives results for the various Load (A) The checking of input data is
Combination Cases provided to it. already discussed.

3.2.1 Programme STAAD.Pro to give (B) Checking of displacements


results for various load
combinations with the appropriate (i) Displacement of joint are
load factors as per I.S.:456-2000 printed in meters. For fixed
and I.S.1893:2002 (when so end of a frame the value of
specified in input data) namely : displacement must be zero.

(1) 1.5 [Dead load + Live load] (ii) At hinged end of a frame
horizontal and vertical
(2) 1.2 [Dead load + Live load + displacement must be zero.
Seismic load] for Seismic
analysis. (iii) The maximum horizontal
displacement due to
(3) 1.5 [Dead load + Seismic load] earthquake forces between
for Seismic analysis. successive floors shall not
exceed 0.004 times the
(4) 1.2 [dead load + Live load + difference in levels between
Wind load] for wind analysis. these floors.

(5) 1.5 [Dead load + Wind load] for (iv) Displacement of all joints on
wind analysis. a particular floor should be
equal.
(6) 0.9 Dead load + 1.5
Seismic/Wind load for stability (v) While checking of forces, at
of the structure. every joint following 3
equilibrium equations must
The designer has to decide which be satisfied.
of these load combinations are
required and accordingly give (a) Sum of all vertical forces
the details of horizontal loads. must be zero.

3.2.2 Programme output gives values (b) Sum of all horizontal


of axial force, moment and forces must be zero.
deflections for each member and
R.C.C. Design of beams (i.e. (a) Sum of all moments at
area of reinforcement, details of the joint must be zero.
shear reinforcement, columns,
slabs, footings, shear walls etc.) Designer should personally check
these points and check some joints
3.2.3 OUTPUT RESULTS FROM for his own satisfaction.
COMPUTER
4. DESIGN OF VARIOUS R.C.C.
The results obtained by ELEMENTS OF BUILDING
running Programme STAAD.
Pro should be thoroughly After the analysis is over, the
checked before accepting the designer will undertake the
same in the final design. detailed design of various
members of the building in the
following order of actual

35
construction, to be in tune with required to sustain the load on pile.
construction programme decided The diameter of pile and pattern of
by the Field Engineers. pile cap for twin or triple pile
group shall be so chosen that the
(i) Design of piles and pile adjoining pile caps do not get
caps/open footings overlapped and there is at least
(depending on the site and minimum distance between the
foundation conditions) two adjacent pile caps as stipulated
in the code I.S.2911.
(ii) Design of columns.
The mix of concrete considered for
(iii) Design of beams. (Plinth design shall be always one grade
Level to Terrace Level) below than stipulated for casting.

(iv) Design of slabs. (Plinth 4.2 DESIGN OF OPEN FOOTINGS


Level to Terrace Level)
4.2.1 ISOLATED FOOTINGS :
(v) Design of water tank/s.
(i) Write down the reactions at
4.1 DESIGN OF PILE AND PILE various footing points for
CAP different Load combination.

Piles are required to be provided (ii) The working load for each load
where the strata of adequate combination is then worked
bearing capacity is not available at out by dividing each load by
reasonable depth, and site the appropriate load factor of
conditions dictate that open the particular load
foundation is not feasible and combination.
economical. This is generally the
case in black cotton soils and (iii)The maximum value of all
reclaimed areas. these working loads is taken as
design working load on
For very low bearing capacity footing.
strata, and where pile foundation is
not economical, we may adopt raft (iv) The isolated footings are
foundation. For codal provisions designed manually by using
refer I.S.:2911. the design process as explained
in HANDBOOK FOR R.C.
It is a good design practice to MEMEBRS (Vol.II pages 359
provide minimum two piles or 3 to 380) OR any standard text
piles in triangular pattern and book for R.C.C. Design.
generally not more than 4 piles (in
square pattern) be provided under (v) Normally trapezoidal footing is
a column. provided except where the site
conditions demand otherwise.
For piles, where the subsoil water
is polluted and presence of sulfides (vi) Designer shall check that with
and/chlorides is more than the safe the designed dimensions, the
limits, sacrificial cover shall have isolated footings are not
to be provided. However, the getting overlapped. If they are
same shall be neglected while getting overlapped, suitable
working out the area of concrete

36
combined footings shall be moments across appropriate axes
designed. from the output of relevant X
direction and Z direction frame
4.2.2 COMBINED FOOTINGS : analysis, for the design section under
consideration in STAAD Pro
These are provided software analysis.

(1) At the expansion joint The column design by Limit State


locations and Method for reinforced concrete
structures shall be as per following
(2) When it is noticed that the load combinations :
isolated footings, are getting (I.S.1893 Part I :2002, CL.6.3.1.2)
over lapped or encroaching on
adjoining property. The 1) 1.5 (DL + IL)
working load for combined 2) 1.2 (DL + IL + EL)
footing shall be sum of 3) 1.5 (DL + EL)
working loads of columns 4) 0.9 DL + 1.5 EL
constituting the combined
footing. For manual analysis Similar combinations will be
and design of combined applicable in case of wind analysis
footing, refer any standard text i.e. replacing seismic forces by wind
book. forces.

4.3 SPECIAL TYPES OF The columns shall be designed as


FOOTINGS : uniaxial or biaxial depending upon
whether the moments are acting
For design of pedestal or any across one or both axes of column
other special type of footing like and their relative magnitudes.
strip footing etc., refer standard
text books. Effective length of column member
shall be worked out considering end
4.4..DESIGN CHECKS FOR ALL conditions and used in the
TYPES OF FOOTINGS : calculations.
(I.S.456:2000, Table 28, Cl.E-3)
The design shall be checked for
following : The design of column given by
STAAD-Pro programme may be
(1) Check for single shear, verified for its adequacy OR
double shear. otherwise the column design is done
manually as per HANDBOOK
(2) Check for negative FOR DESIGN R.C. MEMBERS
moment (if active) (Limit State Method) Vol.II as
(3) Check for bearing explained in pages to for
pressure on top of uniaxial columns and for biaxial
footing. columns pages 322 to 337 and for
circular columns pages 342.
4.5 DESIGN OF COLUMN Computer programme ASP2 is
SECTION : also available.

4.5.1 A column is subjected to direct The design section and the


load and moments across its axes. reinforcement shall satisfy all the
Find out design loads and design combinations stated above.

37
While deciding the pattern it should
4.5.2 APPROACH FOR ECONOMIC born in mind that when the C.G. of
DESIGN OF COLUMN : the steel provided is away from the
N.A., it gives higher moment of
In the design of a column, two resistance to the section.
factors are to be keenly watched
namely pu/fckbd and interaction 4.5.6 If the first approximation of steel
factor. reinforcement proves inadequate, try
to increase the diameter and/number
The pu/fckbd factor is a measure of of bars. It shall be ensured that in
compressive force in column and by the pattern selected, the bigger
keeping the value of this factor is diameter bars are always placed near
equal to or less than 0.4, it is seen the corner/faces away from axis of
that the concrete section provided is bending. Each successive trial shall
utilised to the maximum extent. be taken by gradually changing
reinforcement, and the final trial
The interaction factor is a measure should provide just adequate steel
of degree of utilisation of steel reinforcement. The reinforcement
reinforcement provided in the pattern should fulfill the minimum
column section. The value of this spacing criteria. The reinforcement
factor (calculated as per clause 39.6 bars are required to be laterally tied
of I.S.456) as close to 1.00 ensures by providing links of proper shape.
that the external loads and moments 4.5.7 While choosing the reinforcement
are resisted optimally by the pattern, provide adequate number of
proposed concrete section alongwith bars so that it satisfies spacing
the (proposed) steel reinforcement criteria as per I.S.456, Cl.26.5.3.1
pattern. and Cl.26.5.3.2.

4.5.3 Always begin by designing the 4.5.8 A sketch giving the suitable link
top most section of a column and arrangements for column
then proceeding successively to the reinforcement which will create least
lower section. congestion and aid easy flow of
concrete in the steel cage is kept at
4.5.4 Begin the design by choosing page number 59 for guidance.
one bar at each corner i.e. 4 bar
pattern (giving total area of 4.5.9 The number of reinforcement
reinforcement required on the basis bars shall be so chosen that for
of minimum steel criteria) and if this uniaxial column, equal area of steel
first approximation is not safe then on opposite faces is provided and for
modify the diameter of bars and/or biaxial column, equal area area of
reinforcement pattern till you get the steel on opposite faces is provided.
interaction Ratio as close to 1.0.
4.5.10 For requirements of ductility
As far as possible for the next lower detailing refer para 6.6 . (Page 35)
story column section, continue the
same bar diameters and
reinforcement pattern. 4.6 DESIGN OF BEAMS :

4.5.5 CHOOSING PROPER (i) The computer output of


REINFORCEMENT PATTERN STAAD.Pro gives the area of
required steel at supports, at
quarter span (from each end)

38
and at centre of span. The (c) Nominal size of bars (in
Designer has only to choose mm.)
the diameter and numbers of
top and bottom bars such that (iv) As per Designs Circles practice
actual steel area is just more bars at the bottom of beam are
than the design value and taken straight without bending.
there is no congestion of
steel. (v) When there are collinear beams
over a support the extra steel
Non congestion can be over the support (at top
ensured by keeping and/bottom as the case may be)
horizontal distance between shall be maximum required for
the bars as the greatest of the the either of the two.
following :
For collinear beams the extra
(a) The diameter of bar (in steel over support shall be
mm) if the diameters are continued in the adjoining span
Equal. for a length equal to anchorage
length or 25 % of the adjoining
(b) The maximum diameter span whichever is more.
(in mm) of bar if the
For non collinear beams the
diameters are Unequal.
extra steel over support shall be
anchored in supporting column
(c) 5 mm. more than the
for full anchorage length.
nominal maximum size
of coarse aggregate. (vi) The stirrups of shear
reinforcement shall be provided
For ensuring better compaction of with appropriate diameter of
concrete with needle vibrator, it is H.Y.S.D. bars so that there is no
desirable that this minimum clear congestion of reinforcement in
distance be 50 mm. beam and it shall be seen that the
ductility criteria where
(ii) The anchor bars (at top and applicable is also fulfilled.
bottom) shall be minimum 2
Nos. 4.6.1 For requirements of ductility
detailing refer para 6.6 (page 35)
(iii) Where it is not possible to
accommodate all the bars in 4.7 DESIGN OF SLABS :
one layer, provide them in
layers. The vertical distance (i) The slabs may be one way or
between these layers shall two way depending on the panel
not be less than the greatest dimensions. The design moment
of following : coefficients of a particular slab
shall be taken in accordance with
(a) 15 mm. its boundary conditions.

(b) 2/3 of the nominal maximum (ii) Design of slabs is done manually
size (in mm) of coarse by referring to Hand Book for
aggregate. R.C.C. Members (Limit State
Method) Vol. I or any standard
text book.

39
(iii) As per Designs Circles practice the checks as per code are
minimum diameter of bars for included.
slabs shall be 8 mm.
5.3 SLAB : This Programme
(iv) In case of future vertical designs one way and two way
expansion, the R.C.C. layout of slabs as per Limit State
the top floor shall be as per Method design. The basic data
Architects plan. However, the is concrete mix, span/s, clear
slab reinforcement shall be cover to reinforcement bars, slab
maximum of that required for loading and end conditions.
future floor or present terrace.
5.4 ASP2 : The basic input required
4.7.1 DESIGN OF OVER HEAD to run this programme are
WATER TANK/S section dimensions, unsupported
length and effective length in
The design of water tank is both X and Y direction,
carried out as per procedure reinforcement pattern and
given in the Reinforced different load combinations.
Concrete Designers Hand
Book by Reynolds, and The main limitation of this
conforming to I.S.:3370. programme is that it is workable
only with rectangular and square
5. COMPUTER AIDED DESIGN column section.
USING INHOUSE
DEVELOPED SOFTWARE This Programme designs for given
column section, reinforcement
With the availability of high pattern and, load combination and
speed and large memory capacity checks the adequacy of section.
desk top computers in Designs For this programme the X axis is
Circle, much of the analysis is always assumed to be along the
now carried out on these smaller dimension of column. The
computers. programme output gives the results
for the chosen column section and
Following is the list of computer reinforcement pattern the values
programmes available in Designs of [Pu/(fck x b x d)] and
Circle with Users Manual : Interaction Factor Values for each
load combination case under
5.1 FOOT : This programme consideration.
designs isolated footing as per
limit state method of design.
Column size, concrete mix, safe 6. EARTHQUAKE RESISTANT
bearing capacity of the founding DESIGN GUIDE LINES AS
strata and working load on the PER I.S.:4326
column are the basic inputs. All
the checks as per code are 6.1 The Seismic Design Philosophy is
included in the programme. to accept damage to a building
during a earthquake. Hence the
5.2 EC FOOT : This Programme I.S.:1893 code specifies design
designs combined footing along seismic force for a building, only a
the expansion joint. Column fraction of the seismic force that it
details alongwith their will experience if it were to remain
orientation expansion joint Linear elastic during severe
details etc. are basic inputs. All ground motions. Thus the

40
structure in severe seismic zones sections shall not preferably
should be necessarily ductile. exceed three times the width.

6.2 Meaning there by that the 4.4.3 Buildings having plans with
members of reinforced concrete shapes like, L, T, E and Y shall
shall be under reinforced so as to preferably be separated into
cause a tension failure. Also it rectangular parts by providing
should be so designed that the separation sections at appropriate
premature failure due to shear or places.
bond may not occur subject to the
provisions of I.S.:456-1978. Note 1.
Ductile failure will enable
structure to absorb energy during The buildings with small lengths
earthquake to avoid sudden of projections forming L, T, E or
collapse of structure. Y shapes need not be provided
with separation section. In such
6.3 I.S.:4326-1993 deals with cases the length of the projection
earthquake resistant design and may not exceed 15 to 20 percent
construction of design. Some of the total dimension of the
important clauses are as under : building in the direction of the
projection.
Clause 4.4 Building Configuration
Note 2.
4.4.0 In order to minimize torsion and
stress concentration, provisions For buildings with minor asymmetry
given in 4.4.1 to 4.4.3 should be in plan and elevation, separation
complied with as relevant. sections may be omitted.

4.4.1 The building should have a Clause 4.5 Strength in Various


simple rectangular plan and be Directions
symmetrical both with respect to
mass and rigidity so that the The structure shall be designed to
centers of mass and rigidity of have adequate strength against
the building coincide with each earthquake effects along both the
other in which case no separation horizontal axes. The design shall
sections other than expansion also be safe considering the
joints are necessary. For reversible nature of earthquake
provision of expansion joints forces.
reference may be made to
I.S.:3414-1968. Clause 4.6 Foundations

4.4.2 If symmetry of the structure is The structure shall not be founded


not possible in plan, elevation or on such loose soils which will
mass, provision shall be made subside or liquefy during an
for torsional and other effects earthquake, resulting in large
due to earthquake forces in the differential settlements.
structural design or the parts of
different rigidities may be Clause 4.7 Ductility
separated through crumple
sections. The length of such The main structural elements and
building between separation their connection shall be designed
not to have a ductile failure. This

41
will enable the structure to absorb The I.S.:13920 has taken note of
energy during earthquakes to avoid latest developments, experiences
sudden collapse of the structure. gained from the performance of
Providing reinforcing steel in structures which were designed and
masonry at critical sections, as detailed as per I.S.4326, during the
provided in this standard will not recent earthquakes. It covers
only increase strength and stability provisions for earthquake resistant
but also ductility. The important design and detailing of reinforced
sketches from I.S.:13920 are kept at concrete structures in particular. (As
page No.54, 55 and 57 to 62. such it includes provisions of
I.S.:4326 also). Now all ductility
Clause 5 Special Construction detailing shall comply I.S.:13920.
Features
Some important clauses of this code are
Clause 5.1 Separation of as follows :
Adjoining Structures.
Clause 1.1.1
Separation of adjoining structures or
parts of the same structure is Provisions of this code shall be adopted
required for structures having in all monolithic reinforced concrete
different total heights or storey structures located in Seismic Zone
heights and different dynamic III, IV & V.
characteristics. This is to avoid
collision during an earthquake. Clause 5.2
Minimum total gap shall be 25 mm. For all buildings which are more
than 3 storeys in height the
Clause 5.2 Separation or Crumple minimum grade of concrete shall be
Section. M 20.

5.21 In case of framed construction, Clause 5.3


members shall be duplicated on
either side of the separation or Steel reinforcement of grade Fe 415
crumple section. As an alternative, or less only shall be used.
in certain cases, such duplication
may not be provided, it the portions Clause 6 : For flexural members
on either side can act as cantilevers
to take the weight of the building 6.1.1 The factored axial stress on the
and other relevant loads. member under earthquake
loading shall not exceed 0.1 fck.
7 DUCTILE DETAILING AS PER
13920:1993. 6.1.2 The member shall have a width
to depth ratio of more than 0.3.
I.S.:4326, The Code of Practice for
earthquake resistant design and 6.1.3 Width of flexural member not
construction of Building, while less than 200 mm.
commenting on certain special
features for the design and 6.1.4 Depth of member not more than
construction of earthquake resistant 0.25 of the clear span.
buildings, included some details for
achieving ductility in reinforced Clause 6.2 : Longitudinal
concrete buildings. Reinforcement :

42
6.2.1 (a) At least two bars at top and (a) within a joint
two bars at bottom shall be
provided through out the (b) within a distance of 2d from
member length. joint face and

(b) The tension steel ratio on (c) within a quarter length of


any face at any section shall not member where flexural
be less than (min) 0.24 yielding may generally occur
[(square root of fck)/fy] under the effect of
earthquake forces.
6.2.2 The maximum steel ratio on any
face at any section shall not Not more than 50 percent of
exceed (max)=0.025. bars shall be spliced at one
section.
6.2.3 The positive steel at a joint face
must be at least equal to half the 6.3.5 The spacing of hoops over a
negative steel at that face. length of 2d at either end of a
beam shall not exceed.
6.2.4 The steel provided at each of the
top and bottom face of the (a) d/4
member at any section along its and
length shall be at least equal to (b) 8 x dia meter of smallest
one fourth of the maximum bar
negative moment steel provided
at the face of either joint. But not less than 100 mm.

6.2.5 In an external joint both the top The first hoop shall be at a
and bottom bars of the beam distance not exceeding 50
shall be provided with anchorage mm. from the joint face.
length beyond the inner face of Vertical hoops at the same
column equal to development spacing as above shall also
length in tension plus 10 times be provided over a length
the bar diameter minus the equal to 2d on either side of a
allowance for 90 degree bend(s). section where flexural
yielding may occur under the
In an internal joint, both face effect of seismic forces.
bars of the beam shall be taken
continuously through the Elsewhere the beam shall
column. have vertical hoops at a
spacing not exceeding d/2.
6.2.6 The longitudinal bars shall be
spliced, only if hoops are Clause 7: Columns subjected to bending
provided over the entire splice and axial load.
length at a spacing not exceeding
150 mm. 7.1.1 These requirements apply to
columns which have factored
The lap length shall not be less axial force in excess of (0.1 fck)
than the development length in under the effect of earthquake
tension. forces.

Lap splices shall not provided 7.1.2 The minimum dimension of


column shall be 200 mm.

43
However where in frames where overlapping hoops may be
beams have c/c span exceeding 5 provided.
m, or column having
unsupported length exceeds 4 m. Clause 7.4 : Special Confining
the shortest dimension shall not Reinforcement
be less than 300 mm.
7.1.3 The ratio of shortest dimension 7.4.1 This shall be provided over a
to the perpendicular dimension length of (lo) from each joint
shall be preferably NOT less face towards mid span on either
than 0.4. side of any section lo shall not be
less than
Clause 7.2 : Longitudinal
Reinforcement (a) larger lateral dimension of
the member
7.2.1 Lap splices shall be provided
only in the central half of the (b) 1/6 of clear span of the
member length. It should be member and
proportioned as a tension splice.
Hoops hall be provided over the (c) 450 mm.
entire splice length at spacing
not exceeding 150 mm. center to 7.4.2 When a column terminates into a
center. footing or mat special confining
reinforcement shall extend at
Not more than 50 percent of bars least 300 mm into the footing or
shall be spliced at one section. mat.
7.2.2 Any area of a column that 7.4.6 The spacing of hoops used as a
extends more than 100 mm. special confining reinforcement
beyond the confined core due to shall not exceed 1/4 of minimum
Architectural requirements shall member dimension but need not
be detailed in the matter. be less than 75 mm nor more
than 100 mm.
In case the contribution of the
area to strength has been 7.4.7 The minimum area of cross
considered then it will have the section of bar forming circular
minimum longitudinal and hoop or spiral to be used as
transverse reinforcement as per special confining reinforcement
this code. shall not be less than

However if this area has been Ash = 0.09 S Dk fck [(Ag /Ak -1.0 ]
treated as non structural the fy
minimum reinforcement shall be Where
governed by I.S.456 provisions.
Ash = area of the bar cross section
Clause 7.3 : Transverse
Reinforcement S = Pitch of spiral or spacing of
hoops
7.3.2 The spacing of rectangular hoops
shall not be more than 300 mm Dk = diameter of core measured to the
c/c. If the length of any side of outside of spiral or hoop
stirrup, exceeds 300 mm a cross
tie shall be provided or a pair of fck = characteristic compressive strength
of concrete cube.

44
fy = yield stress of (spiral/hoop) steel
Ag = gross area of column cross section
Ak = area of concrete core should not
exceed 300 mm (see figure 7)

7.4.8 The area of cross section Ash of


the bar forming rectangular hoop
to be used as special confining
reinforcement shall not be less
than

Ash = 0.18 Sh.fck [(Ag / Ak -1.0 ]


fy
Where

h = longer dimension of rectangular


hoop.

Ak = Area of concrete core in the


rectangular hoop measured to its
outside dimensions.

Clause 8 : Joints of frames :

8.1 The special confining


reinforcement as required at the
end of column shall be provided
through the joint as well, unless
the joint is confined as specified
by 8.2.

8.2 A joint which has beams framing


into all vertical faces of it and
where each beam width is at
least 3/4 of the column width,
may be provided with half the
special confining reinforcement
required at the end of column.
The spacing of hoops shall not
exceed 150 mm.

Important sketches from


I.S.:13920 are kept at page 53
onwards.

45
CHAPTER-V

DETAILING

1. NOTES TO APPEAR ON 7. For notation of slabs, beams


VARIOUS SCHEDULES and columns and column
orientation refer to R.C.C.
[A] GENERAL (Applicable for layouts of respective floors.
all schedules) :
8. For all R.C.C. elements
1. For general instructions and minimum cover shall be
detailing of reinforcement, provided depending on
refer to SP-34 of bureau of condition of exposure described
Indian Standards I.S.13920 and in 8.2.3 shall be as per Table 16
sketches in this chapter. of I.S.456:2000 (Clause 26.4.2)
and nominal cover to meet
2. Unless otherwise specified in specified period of fire
the respective schedules, the resistance shall be as per Table
minimum concrete mix shall be 16A of I.S.456: 2000, Clause
M 20 (characteristic strength 20 No.26.4.3.
N/sq.mm.) and grade of
concrete depending on [B] R.C.C. LAYOUTS :
exposure condition as per
Clause No.8.2.2 and Table 1. This R.C.C. layout is based on
No.5 of I.S.456:2000. the Architects Drawing No.
Job No. , Dated. .. .
3. Reinforcement shall be high
yield strength deformed bars 2. R.C.C. layout at a particular
(Fe 415) conforming to level indicates (i) beams and
I.S.:1986 with latest slabs at that level, (ii)
amendments. supporting columns below that
level and (iii) walls above that
4. Any deviations from level.
designed sizes, found
necessary on site shall be 3. Any discrepancies noticed
got approved well in advance between these layouts and
before execution from Architects drawings shall be
Superintending Engineer. communicated to office of
. (where designs are
5. Development length of prepared) for clarification
reinforcing bars shall be in before starting execution.
accordance with Clause 26.2.1
of I.S.456:2000. 4. Any change in the location of
beams, orientation of column/s
6. Approval to R.C.C. layouts and other than that shown in the
to the sizes of columns and layouts, shall be got approved
beams above plinth level shall in advance from
be obtained from Architect Superintending Engineer.
prior to the execution.

46
[C] FOOTINGS/PILES AND 2. Reduction in column size shall
PILE CAPS : be effected from the top of the
slab at relevant floor level.
1. For column numbers and their
orientation refer to R.C.C. 3. For any change proposed at
layout at plinth level drawing site, in the size of column
No./. . section and/or their orientation,
approval of Superintending
2. The difference in levels between Engineer shall be obtained
adjoining footings shall not before execution.
exceed than that permitted vide
Clause No.9.7 of I.S.:1904. 4. Larger diameter bars shall be
3. The larger dimension of a provided at corners, unless
footing shall be oriented along otherwise indicated in the
the longer side of a column, sketch.
unless the sketch indicates the
contrary. 5. Arrangement of binders shown
in the sketch is suggestive, any
4. Reinforcement parallel to other alternative arrangement in
breadth of footing shall be laid accordance with the relevant
first. provisions in I.S.:456 and
I.S.:2502 may be adopted.
5. Reinforcing bars shall be bent
up at the edges of footings to [E] BEAMS :
get required development
length. 1. For notation of beams refer
R.C.C. layout at floor
6. The sub-soil and sub-soil water level Drawing No. /
are assumed to be free from .
harmful elements.
2. In case of collinear beams, top
7. Footings/pile and pile caps are reinforcement over a support
designed for (ground + --) for non-seismic region and both
(number of stories for which top and bottom reinforcement
footings are designed). at a support for seismic region
shall be continued in adjacent
8. Footings are designed for safe span for full development
bearing capacity of ---- t/sq.m. length or span/4 of adjoining
span whichever is more.
9. For details of dowel bars and
their arrangement refer to 3. In case of collinear beam and in
schedule of columns from case there is no beam on the
footing to plinth level Drawing other side, the top
No./ . reinforcement over a support
for non-coastal region and both
[D] COLUMNS : top and bottom reinforcement
at a support for coastal region
1. For orientation of columns shall be anchored in the
refer R.C.C. layout at plinth supporting column for full
Drawing No.. /.. . development length. In case of
grid beams it shall be anchored

47
in the supporting beams and 10. Beams at toilet portion shall be
columns. cast 20 cm. below general floor
level.
4. Minimum and maximum
distance between individual 11. Necessary provision for
bars shall be as per Clause reinforcement of chajja, facias,
No.26.3 of I.S.456:2000 with canopy, fins, pardi and brackets
latest amendments. etc. shall be made while casting
of relevant beams.
5. The end of a beam except in a
grid not having either a column [F] SLABS :
support or a collinear beam
shall be considered to be a 1. For notation of slabs refer
discontinuous end. The top and R.C.C. layout at floor
bottom reinforcement at such a level Drawing No. / .
discontinuous end shall be .
terminated in the supporting
beams instead of anchoring for 2. Slabs of toilet portion shall be
full development length. cast at 20 cm. below general
floor level.
6. In case diameter and number of
bars of adjacent collinear 3. Reinforcement in chajjas shall
beams are same then these bars be provided as per the sketch
shall be kept continuous. No.4A of Designs Circles
Technical Note No.7502.
7. If the spacing of stirrups in any
region of a beam (such as 0 to 4. In slab notation, the first figure
D, D to 2d, etc. is not a indicate the imposed live load
submultiple of the depth of the assumed in design. It shall be
beam, then the same spacing ensured by the field engineers
shall be continued in the next that the actual live load on the
region for one more spacing slab does not exceed this
before starting the new spacing specified load.
to be provided in the next
region. [G] WATER TANK :

8. Extra steel at top of support 1. Mix of the concrete for water


between adjacent beams is tank shall be M 20.
shown in any one beam. This
extra steel is to be continued on 2. All dimensions are in cms,
both sides of the support for unless otherwise specifically
required anchorage length or mentioned.
span/4 of respective beam,
whichever is more. 3. Plans and sections are not to
scale.
9. Top of internal plinth beams
shall be 15 cms. below plinth 4. Necessary water proofing
level and top of external plinth treatment, load of which shall
beams shall be 15 cms. below not exceed 100 kg/sq.m. shall
ground level. be given to the tank.

48
5. The drawing shows only beyond the bend for full
structural details Air vents, development length.
over flow pipes, inlets, outlets,
scour pipes, man holes etc. 8. The diameter and position of
have not been shown on the over flow pipe shall be such
drawing. that it will ensure a free board
of 15 cms.
6. Manholes of adequate diameter
shall be provided as per 9. Column reinforcement shall be
requirement/s with extra continued upto top of bottom
trimmer bars below main slab of water tank.
reinforcement of slab as shown
in the drawing. 10. R.C.C. Tank/s of .. Litres
capacity shall rest on columns
7. The horizontal and vertical bars Nos., , , , , and .
of the walls shall be continued

49
2. VARIOUS FORMAT
R.C.C. LAYOUT

50
SCHEDULE OF ISOLATED FOOTINGS (SAFE BEARING CAPACITY 300 KN/sqm)
OVERALL SIZE OVERALL DEPTH DETAILS OF COLUMN
REINFORCEMENT
(in mm) (IN mm)
COLUMN SIZE
(in mm) REINFORCEMENT FROM FOOTING TO TOP

Sr.No. COLUMN NUMBERS AT AT PARALLEL TO PARALLEL TO REMARKS


LENGTH BREADTH COLUMN BREADTH OF LENGTH OF DEPTH
FOOTING MAIN BINDER MIX SKETCH
FACE EDGE FOOTING FOOTING (d) (d)
(L) (B)
(D1) (D2)

NOS. DIA. NOS. DIA. NOS. DIA. DIA. SPACING

1. C-1,2,3,4,31,34 1750 1400 500 300 12 10 10 10 600 230 12 12 8 180 M-20

6 16
2. C-5,8,27,30 1900 1550 600 300 15 10 12 10 600 230 + 8 180 M-20
12 12

4 16
3. C-6,7,28,29 1850 1500 600 300 15 10 12 10 600 230 + 8 180 M-20
8 12

4. C-9,10 1750 1400 500 300 12 10 10 10 600 230 10 12 8 180 M-20

5. C-11,14,21,24 1750 1450 500 300 12 10 12 10 500 230 14 12 8 180 M-20

4 16
6. C-12,13 1700 1450 600 300 14 10 11 10 500 230 + 8 180 M-20
8 12

51
SCHEDULE OF BEAMS AT FIRST FLOOR LEVEL.
SHEAR REINFORCEMENT
MAIN REINFORCEMENT (H.Y.S.D.) EXTRA STEEL OVER SUPPORTS (H.Y.S.D.) (H.Y.S.D.)
OVERALL
TYPE SIZE TOP BOTTOM TOP BOTTOM SPACING OF
Sr. DIAMETER
BEAM Nos. OF STIRRUPS C/C REMARKS
No. OF (in mm)
BEAM BREADTH DEPTH DIA DIA DIA COLUMN Nos. STIRRUPS
Nos. DIA Nos. Nos. Nos.
(B) (D) (in mm) (in mm) 2D TO
(in mm) (in mm) (in mm) 0-2D
(in mm) (in mm) CENTER

1. 1.1,3.1,31.1,33.1 R 230 750 2 16 2 16 8 150 150

1 12 C-5,27
2. 5.1,27.1 R 230 600 2 16 2 16 8 200 200
- - --
- - --
3. 7.1,29.1 R 230 600 2 16 2 16 8 200 200
1 12 C-8,30
4. 9.01,9.1,10.1 R 230 750 2 16 2 16 8 200 200

1 16 C-11,13,21,23
5. 11.1,13.1,21.1,23.1 R 230 450 2 12 3 12 8 200 200
1 16 C-12,14,22,24
6. 15.1 R 230 500 2 12 2 16 8 200 200

7. 16.1 R 230 500 2 12 2 16 8 200 200

2 16 2-16 + 1-12 C-17


8. 17.1 R 230 500 2 12 + 8 200 200
1 12 2 20 C-18
2 20 C-18
9. 18.1 R 230 500 2 12 2 16 8 200 200
2 20 C-19
2 20 C-19
10. 19.1 R 230 500 2 12 2 16 8 200 200
2-16 + 1-12 C-20

52
SCHEDULE OF ONE WAY SLAB AT FIRST FLOOR LEVEL
OVERALL REINFORCEMENT
Sr.No. SLAB NOTATION THICKNESS REMARK
(in mm) MAIN STEEL DISTRIBUTION STEEL

1. 200 S 1.1,200 S 1.2 100 8 mm O @ 200 mm c/c 8 mm O @ 250 mm c/c SUNK SLAB

2. 200 S 1.3,200 S 1.4 120 8 mm O @ 200 mm c/c 8 mm O @ 250 mm c/c

3. 300 S 1.5 (ML) 120 8 mm O @ 150 mm c/c 8 mm O @ 250 mm c/c SLAB AT MID LANDING

4. 75 SC 1.1,75 SC 1.1A, 100 8 mm O @ 150 mm c/c 8 mm O @ 250 mm c/c CANTILEVER SLAB / CHAJJA
75 SC 1.2

5. 300 SF 1.1 200 12 mm O @ 150 mm c/c 8 mm O @ 200 mm c/c STAIR FLIGHT WAIST SLAB

SCHEDULE OF TWO WAY SLAB AT FIRST FLOOR LEVEL


MAIN REINFORCEMENT IN CENTRAL STRIP OF 3/4 SPAN
OVERALL CORNER REINFORCEMENT
MAIN STEEL AT BOTTOM EXTRA STEEL OVER SUPPORTING BEAM DISTRIBUTION STEEL AT TOP AND BOTTOM,
SR.No. SLAB NOTATION THICKNESS IN EDGE STRIPS BOTH WAYS REMARKS
PARALLEL TO PARALLEL TO AT BOTTOM AS PER
PARALLEL TO PARALLEL TO
(in mm) BEAMS Nos. TECH, NOTE No.7502
SHORT SPAN LONG SPAN SHORT SPAN LONG SPAN

200 S 2.1,200 S 2.2,


1. 200 S 2.3,200 S 2.4 120 8mm O @ 200mm c/c 8mm O @ 200mm c/c -- -- -- 8mm O @ 200mm c/c 8mm O @ 200mm c/c
300 S 2.5

2. 150 ST 2.6, 150 ST 2.7 100 8mm O @ 200mm c/c 8mm O @ 200mm c/c -- -- -- 8mm O @ 200mm c/c 8mm O @ 200mm c/c

53
SCHEDULE OF COLUMNS FROM FOOTING TO FIRST FLOOR LEVEL

FOOTING TO FIRST FLOOR LEVEL

REINFORCEMENT (H.Y.S.D.)

SIZE
Sr.No. COLUMN NUMBERS REMARKS
MAIN BINDER
MIX SKETCH

WIDTH DEPTH NOS. DIA DIA SPACING


(mm) (mm) (mm) (mm) (mm)

REFER TOSKETCH No.1


C-1,2,3,4,15,20, FOR DETAILS OF
1. 230 600 12 12 8 180 M-20 DUMMY COLUMN
C-31,32,33,34
AT C-1,4,31,34

6 16
2. C-5,8,27,30 230 600 + 8 180 M-20
12 12

4 16
3. C-6,7,28,29 230 600 + 8 180 M-20
8 12

4. C-9,10 230 600 10 12 8 180 M-20

5. C-11,14,21,24 230 500 14 12 8 180 M-20

54
3. FIELD DATA PROFORMA
STANDARD PROFORMA FOR FURNISHING FIELD DATA
FOR COMMENCING DESIGN OF BUILDING PROJECTS

1. Name of work :

2. Location :
(a) Location with Seismic Zone.
(b) Importance Factor for
structure as per I.S.:1893.
(c) Exposure Condition as per
I.S.456:2000.
(d) Grades of concrete :

3. General description & salient :


features.

4. Architects Plan No.& Job No. :

5. G.R.Number and date of :


administrative approval with
cost (Copy to be attached)

6. Budget Item No. and Page No. :


in Budget Book if it is budgeted.

7. Technical sanction order and its :


date (authority with cost).
(Copy to be attached)

8. Foundation conditions :

(a) Foundation details of existing


building near to the site.

(b) Distance between the nearest


existing building and proposed
building.

(c) Plan showing location/s of trial


pits/trial bores including level
of sub-soil water table.
(give date of observation)

55
(d) Results of chemical tests on sub
soil water for Sulphite, Chloride
contents, Ph value.

(e) Safe bearing capacity of founda-


tion strata including depth in case
of open footing (mention basis
i.e. test results with report etc.)

(f) Details of sub soil exploration :


or tests with results like

(i) Nature of subsoil beneath and


around with respect to Compre-
ssibility and shear strength.

(ii) Penetration test results of


Different Strata.

(iii) In case rock, description of rock


to convey physical characteristics
and strength.

(iv) In case of weathered rock,


description regarding physical
behaviour and expected physical
behaviour.

(g) Tidal effects if any. :

9. Special points about foundations and :


site.

9.1 If open footings are not feasible give :


recommendations about.

(a) Raft : Depth and Safe :


bearing capacity of strata

(b) Piles :

(i) Depth

(ii) Safe bearing pressure


for the hard strata.

(iii)Type-frictional/bearing/-
under reamed.

56
(iv) Dia of pile proposed
(if specific dia is to be provided).

(v) Proposed pile cap level.

(vi) Proposed top level of finished


file.

(vii) Undrained shear strength


of soil.

(viii) Horizontal Modulus of soil.

9.2 Nature of ground e.g. plain, undulating, :


sloping etc. (attach contour plan at 0.5 m.
interval if ground slope exceeds 1:30)

10. Water storage tanks (show requirements :


of present and future extension separately)

(a) Overhead tanks : Type :


(M.S./R.C.C./H.D.P.E./F.R.P.)
capacity (show location on plan)

(b) Underground tank (Location, :


capacity and special requirements
if any)

11. Lift loads :

(i) Capacity of lift (passengers/goods) :

(ii) Load of lift cage :

(iii) Load of motor/gear in the :


machine room.

(iv) Machine room floor live load :

(v) Impact factor :

(vi) Lift pit depth :

(vii) Machine room floor level :


w.r.t. terrace.

(viii) Machine roof level w.r.t. terrace. :

(ix) Whether location sketch indicating :


position of girders for supporting
gears/mortars and erection purpose
provided ?

57
(x) Minimum thickness of machine :
room floor slab required by field
(if any)

(xi) Any other system/load to be :


considered for erection.

(xii) Whether above information is :


given by the officer of the rank at
least Executive Engineer (Electrical)
( Yes / No )

12. Extra ordinary Load :


If any to be considered for Design.

13. Provision to be made in design for :


future extension if any.

(a) Horizontal :
(Details of Extension)
(i) No. of stories as per Architects
Drawing G +

(ii) No. of stories to be constructed


at present . G +

(iii) No. of stories to be Designed for G +

(b) Vertical :

(c) Authority for the above :


(Architects plan, provisions in
A.A. or Tech. Sanctioned estimate
reference to master plan etc.)

(d) Whether structural sections :


assumed in sanctioned estimate
take into account the envisaged
expansion at (a) & (b) above.

(e) Detailed plans of the future :


extension.

14. Special requirements of Architectural :


plans if any.

(a) Restriction on column sizes and :


their orientation with locations
(b) Restriction on sizes of beams and :
their locations.

58
(c) Lift machine room floor clearance :
from general terrace level.

(d) Minimum headway if any, with :


locations.

(e) Any specific or suggested positions :


of expansion joints if required at
particular places.

15. If the Building is to be designed for wind : K1 =


load give value of K1, K2, K3 as per K2 =
I.S.:875(Part 3) to calculate design wind K3 =
speed.

16. Special features of the staircases if any :

(a) Clearance on sides

(b) Restrictions on No. of steps in


a flight

(c) Restrictions on tread widths and :


heights of risers etc.

17. Any other special requirements or :


points such as.

(i) Type of water proofing with its loading

(ii) Exposure to saline and chemical


atmosphere.

Note : The following plans must be supplied


with this proforma.

(i) Index plan


(ii) Site plan showing locations of trial pits.
(iii)Sub surface data including test results.
(iv) Contour plan in case ground slope exceeds 1:30
(v) Architects plan (original and not traced copies )
Marked with location of over head tanks/with
individual capacity.
(vi) Plans and sketches showing special requirements, if any.

Additional Information
(1) Present Position of Tender :

(2) Tentative Programme of construction :

59
4. SKETCHES

60
( Fig.2 of I.S.13920:1993 on Page 3 )

61
( Fig.3 of I.S.13920:1993 on Page 4 )
( Fig.3 of I.S.13920:1993 on Page 4 )

62
ANCHARAGE OF BARS IN AN EXTERNAL BEAM

( Fig.1 of I.S.13920:1993 on Page 3 )

63
( Fig.6 of I.S.13920:1993 on Page 6 )

( Fig.10 of I.S.13920:1993 on Page 9 )

64
( Fig.9 of I.S.13920:1993 on Page 9 )

65
( Fig.7 of I.S.13920:1993 on Page 7 )

66
( Fig.11 of I.S.13920:1993 on Page 10 )

( Fig.12 of I.S.13920:1993 on Page 11 )

67
SPECIAL CONFINING REINFORCEMENT FOR BEAM

( Fig.5 of I.S.13920:1993 on Page 6 )

68
69
COPY OF G.R.DATED 03.11.80.

Preparation of R.C.C. design


for building works, plans &
estimates for Bridges.

Public Works and Housing Department,


Mantralaya, Bombay-400 032.
Govt. Circular No.BDG-1080/80838(394)/Desk-2, 3 rd November, 1980.

Read : Government Circular No.B & C Department


(i) No.BDG-1864/22208/K(I), dated 12.11.1964.
(ii) No.BDG-3869/5340/K, dated 13.07.1970.

1. Instructions about the preparation of R.C.C. Designs for building works have
been issued vide Government references cited above. Similarly, in respect of
bridge works, so far, it was a practice that the Designs Circle used to prepare
detailed plans and estimates, only for major bridges where linear waterway
exceeds 100 (i.e.30 M). Since then there has been a substantial increase in the
construction activities and eventual increases in the workload of Designs Circle.

2. The question of relieving the Designs Circle from some of its routine work load,
was under consideration of Government for some time past. In order to enable
the Designs Circle to devote more time and energy for preparing sophisticated
type of designs in case of more complicated structures and to give guidance to the
field officers on planning and monitoring technique of PERT/CPM for works of
large magnitude Government is now pleased to issue the following orders :

(A) Preparation of Bridge Projects :-

(i) Bridge upto 30 m. linear waterway shall be designed and estimated by the
concerned Road Project Division.

(ii) (a) Only preliminary design indicating the waterway the type
of foundation, the span arrangement and brief project report
will be prepared by the Designs Circle for bridges between 30
m. to 60 m. linear waterway.

(b) Detailed plans and estimates for the above bridges shall be done
by the concerned Road Project Division.

(iii) The Designs Circle will henceforth prepare detailed plans and estimates
only for bridges where linear waterway exceeds 60 m.

70
(B) Designs of Bridges:

The Designs Circle will continue to prepare Type-Designs for various bridge-
components as well as detailed structural designs for bridges as per the
present practice.

(C) Designs of Buildings :

(i) Designs of all load bearing structures shall be prepared by the concerned
field Executive Engineer, irrespective of number of stories and cost of
structure.

(ii) Design of R.C.C. framed structures upto 4 stories (Ground plus 3 upper)
shall be prepared by the Executive Engineer of P.W.Divisions of Zilla
Parishads irrespective of the cost of the structure except in case of
structures requiring wind and seismic analysis.

Sd/-
( S.S.Naik )
Deputy Secretary to Govt.

71

Вам также может понравиться