CONSULTOR - ING.

JAMES LLERENA TORRES MUNICIPALIDAD DISTRITAL DE SOCABAYA

Calendario de Utilizacion de Recursos


Obra : MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD VEHICULAR Y PEATONAL EN LA URBANIZACION LOS SAUCES EN EL DISTRITO DE SOCABAYA, PROVINCIA DE AREQUIPA -
AREQUIPA".
Ubicacion : SOCABAYA - AREQUIPA - AREQUIPA
Costo A : May - 2014 Cliente : MUNICIPALIDAD DISTRITAL DE SOCABAYA
PLAZO DE EJECUCION
TOTAL
Cod Descripcion Unid Cantidad Precio Parcial 30 Dias 30 Dias 30 Dias 30 Dias
120 Dias

MANO DE OBRA
47 00012 CAPATAZ HH 359.91 17.80 6,406.40 1,016.26 2,244.31 2,377.79 768.04 6,406.40
47 00029 TOPOGRAFO HH 34.10 16.16 551.06 551.06 - - - 551.06
47 00013 OPERARIO HH 3,798.58 16.18 61,461.02 12,767.59 29,452.15 13,871.83 5,369.45 61,461.02
47 00014 OFICIAL HH 2,917.09 13.88 40,489.21 2,839.12 17,959.21 15,838.44 3,852.44 40,489.21
47 00007 PEON HH 7,165.01 12.52 89,705.93 21,256.26 43,170.68 13,956.77 11,322.22 89,705.93
MATERIALES
01 00240 PLAN DE SEGURIDAD Y SALUD EN EL TRABAJO UND 1.00 1,500.00 1,500.00 1,500.00 - - - 1,500.00
02 00016 ALAMBRE NEGRO N16 KG 807.78 5.80 4,685.12 106.80 2,907.25 1,246.95 424.12 4,685.12
02 00042 ALAMBRE NEGRO N8 KG 644.27 2.26 1,456.05 - 429.54 1,011.99 14.52 1,456.05
02 00008 CLAVOS DE 2 1/2", 3", 4" KG 695.88 6.00 4,175.28 72.73 1,952.25 2,111.70 38.60 4,175.28
02 00041 CLAVOS PARA MADERA C/C DE 3" KG 38.46 6.00 230.76 - 32.97 197.79 - 230.76
02 00449 CLAVOS PARA MADERA CON CABEZA DE 3" KG 15.11 4.50 68.00 68.00 - - - 68.00
02 00445 CLAVOS PARA MADERA CON CABEZA DE 4" KG 2.50 4.50 11.25 11.25 - - - 11.25
03 00388 ACERO DE REFUERZO FY=4200 GRADO 60 KG 4,251.77 2.98 12,670.27 434.48 11,158.90 - 1,076.89 12,670.27
03 00046 FIERRO CORRUGADO KG 7,783.00 2.60 20,235.80 - 8,406.03 9,293.37 2,536.40 20,235.80
04 00063 ARENA FINA M3 126.41 59.32 7,498.64 - 5,544.06 1,709.96 244.62 7,498.64
04 00043 ARENA GRUESA M3 505.62 38.98 19,709.07 337.55 15,653.05 3,304.04 414.43 19,709.07
04 00223 HUMUS kg 786.00 2.00 1,572.00 - - - 1,572.00 1,572.00
04 00219 TIERRA DE CHACRA M3 52.40 25.00 1,310.00 - - - 1,310.00 1,310.00
05 00396 AGREGADO FINO PARA ASFALTO M3 4.09 55.00 224.95 - - - 224.95 224.95
05 00397 AGREGADO GRUESO PARA ASFALTO M3 9.54 40.00 381.60 - - - 381.60 381.60
05 00034 AGUA M3 463.40 8.47 3,925.00 157.00 1,036.85 1,945.59 785.56 3,925.00
05 00037 MATERIAL BASE SELECCIONADO M3 17.04 33.90 577.66 - - - 577.66 577.66
05 00508 MATERIAL CLASIFICADO PARA BASE m3 23.82 55.00 1,310.10 1,310.10 - - - 1,310.10
05 00044 PIEDRA DE 1/2 M3 23.77 90.00 2,139.30 - 2,139.30 - - 2,139.30
05 00379 PIEDRA DE CHANCADA DE 1/2" a 3/4" M3 605.02 66.10 39,991.82 910.59 31,366.79 6,286.66 1,427.78 39,991.82
05 00446 PIEDRA MEDIANA DE 6" M3 0.30 50.00 15.00 15.00 - - - 15.00
13 00409 ASFAlTO MC - 30 gln 141.73 13.82 1,958.71 - - - 1,958.71 1,958.71
13 00266 ASFALTO RC - 250 GLN 319.11 14.24 4,544.13 - 131.28 560.07 3,852.78 4,544.13
21 00002 CEMENTO PORTLAND TIPO IP (42.5KG) BOL 5,685.74 17.79 101,149.31 2,907.80 72,142.38 22,169.02 3,930.11 101,149.31
29 00241 ARNES DE CUERO Y DOBLE LINEA DE ENGANCHE ESTANDARIZADO
UND 4.00 35.00 140.00 140.00 - - - 140.00
29 00242 BARBIQUEJO CON MENTONERA UND 25.00 15.00 375.00 375.00 - - - 375.00
29 00243 BOTAS DE CUERO PUNTA DE ACERO PAR 30.00 60.00 1,800.00 1,800.00 - - - 1,800.00
29 00244 BOTAS DE JEBE PAR 6.00 25.00 150.00 150.00 - - - 150.00

Pgina 1 de 4
CONSULTOR - ING. JAMES LLERENA TORRES MUNICIPALIDAD DISTRITAL DE SOCABAYA

Calendario de Utilizacion de Recursos


Obra : MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD VEHICULAR Y PEATONAL EN LA URBANIZACION LOS SAUCES EN EL DISTRITO DE SOCABAYA, PROVINCIA DE AREQUIPA -
AREQUIPA".
Ubicacion : SOCABAYA - AREQUIPA - AREQUIPA
Costo A : May - 2014 Cliente : MUNICIPALIDAD DISTRITAL DE SOCABAYA
PLAZO DE EJECUCION
TOTAL
Cod Descripcion Unid Cantidad Precio Parcial 30 Dias 30 Dias 30 Dias 30 Dias
120 Dias
29 00259 CAPACITACION INDUCTIVA EN SEGURIDAD Y SALUD EN OBRA UND 1.00 1,500.00 1,500.00 1,500.00 - - - 1,500.00
29 00258 CARTELES DE SEALIZACION, INFORMACIN Y PREVENCION PARA
UND
OBRA 30.00 75.00 2,250.00 2,250.00 - - - 2,250.00
29 00245 CASCOS ESTANDARIZADO UND 20.00 35.00 700.00 700.00 - - - 700.00
29 00246 CHALECOS REFLECTIVOS UND 20.00 35.00 700.00 700.00 - - - 700.00
29 00254 CINTA PLASTICA DE SEGURIDAD (100 M.) RLL 10.00 25.00 250.00 250.00 - - - 250.00
29 00255 CONOS DE SEGURIDAD UND 20.00 16.00 320.00 320.00 - - - 320.00
29 00247 GAFAS DE PROTECCION OCULAR ESTANDARIZADA UND 50.00 25.00 1,250.00 1,250.00 - - - 1,250.00
29 00447 GIGANTOGRAFIA DE 3.60 X 8.50M. plg 1.00 300.00 300.00 300.00 - - - 300.00
29 00248 GUANTES DE BADANA UND 50.00 10.00 500.00 500.00 - - - 500.00
29 00249 GUANTES DE CUERO DURO PAR 80.00 8.00 640.00 640.00 - - - 640.00
29 00250 GUANTES DE JEBE PAR 30.00 15.00 450.00 450.00 - - - 450.00
29 00395 PLANTON DE LAUREL UND 32.00 21.18 677.76 - - - 677.76 677.76
29 00394 PLANTON DE MIOPORO UND 230.00 25.42 5,846.60 - - - 5,846.60 5,846.60
29 00256 POSTE PARANTE CON BASE DE CEMENTO UND 50.00 35.00 1,750.00 1,750.00 - - - 1,750.00
29 00251 PROTECTORES DE OIDO - TAPONES DE JEBE REUTILIZABLE UND 60.00 12.00 720.00 720.00 - - - 720.00
29 00260 RECURSOS VARIOS PARA EMERGENCIAS UND 1.00 1,000.00 1,000.00 1,000.00 - - - 1,000.00
29 00252 RESPIRADOR CONTRA POLVO ESTANDARIZADO UND 60.00 13.50 810.00 810.00 - - - 810.00
29 00257 ROLLO MALLA FAENA (46 M. RLL 25.00 25.00 625.00 625.00 - - - 625.00
29 00253 ROPA DE TRABAJO DENIN/DRILL UND 20.00 180.00 3,600.00 3,600.00 - - - 3,600.00
29 00026 YESO BOLSA DE 28KG BOL 107.10 9.50 1,017.45 1,017.45 - - - 1,017.45
30 00401 ADITIVO ACELERANTE DE FRAGUA GLN 46.53 21.19 985.97 - 867.00 - 118.97 985.97
30 00403 ADITIVO EPOXICO GLN 4.10 50.85 208.49 - 208.49 - - 208.49
30 00392 OCRE KG 92.96 12.71 1,181.52 - 454.43 727.09 - 1,181.52
30 00520 SELLADOR ELSTICO DE POLIURETANO UND 56.29 15.25 858.42 - 858.42 - - 858.42
30 00062 TECNOPOR DE 1"x 4'x 8' PLN 16.80 16.00 268.80 - 268.80 - - 268.80
30 00393 WATER STOP PVC DE 6" M 86.53 16.95 1,466.68 - 1,466.68 - - 1,466.68
31 00385 CAJA DE CONCRETO PARA AGUA (12" x 12 ") UND 51.00 19.06 972.06 - 972.06 - - 972.06
31 00389 CAJA DE REGISTRO UND 51.00 38.13 1,944.63 - 1,944.63 - - 1,944.63
31 00386 MARCO Y TAPA TERMOPLASTICO CON VISOR P/CAJA DE MEDIDOR
UND
DE A 51.00 38.13 1,944.63 - 1,944.63 - - 1,944.63
31 00390 MARCO Y TAPA TERMOPLASTICO CON VISOR P/CAJA DE DESAGUEUND 51.00 33.18 1,692.18 - 1,692.18 - - 1,692.18
38 00005 HORMIGON M3 1.83 40.00 73.20 45.51 27.69 - - 73.20
38 00521 MATERIAL DE PRESTAMO PARA RELLENO PROTECTOR M3 7.68 30.00 230.40 230.40 - - - 230.40
38 00377 MATERIAL DE PRESTAMO M3 140.86 25.42 3,580.66 905.73 - - 2,674.93 3,580.66
38 00330 MATERIAL DE RELLENO M3 348.29 30.00 10,448.70 10,448.70 - - - 10,448.70
39 00239 AGUA MES 60.57 25.00 1,514.25 1,514.25 - - - 1,514.25
43 00367 MADERA TORNILLO P2 9,481.18 4.40 41,717.19 16,249.78 17,888.27 7,255.65 323.49 41,717.19

Pgina 2 de 4
CONSULTOR - ING. JAMES LLERENA TORRES MUNICIPALIDAD DISTRITAL DE SOCABAYA

Calendario de Utilizacion de Recursos


Obra : MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD VEHICULAR Y PEATONAL EN LA URBANIZACION LOS SAUCES EN EL DISTRITO DE SOCABAYA, PROVINCIA DE AREQUIPA -
AREQUIPA".
Ubicacion : SOCABAYA - AREQUIPA - AREQUIPA
Costo A : May - 2014 Cliente : MUNICIPALIDAD DISTRITAL DE SOCABAYA
PLAZO DE EJECUCION
TOTAL
Cod Descripcion Unid Cantidad Precio Parcial 30 Dias 30 Dias 30 Dias 30 Dias
120 Dias
43 00010 MADERA TORNILLO PARA ENCOFRADO P2 1,233.20 4.80 5,919.36 - 2,792.00 3,127.36 - 5,919.36
43 00035 REGLA DE MADERA P2 2.92 7.50 21.90 21.90 - - - 21.90
43 00448 ROLLIZO DE EUCALIPTO DE 6" X 7.00M. und 3.00 45.00 135.00 135.00 - - - 135.00
44 00380 TRIPLAY DE 4'x8'x 6 mm PLN 332.73 20.85 6,937.42 1,668.01 1,037.60 4,231.81 - 6,937.42
45 00452 ESTACAS DE MADERA und 5.73 3.70 21.20 21.20 - - - 21.20
53 00093 THINER STANDARD GLN 24.15 15.50 374.33 - - - 374.33 374.33
54 00382 DISOLVENTE GLN 14.47 35.59 514.99 - - - 514.99 514.99
54 00405 PINTURA DE TRAFICO GLN 27.31 62.71 1,712.61 - - - 1,712.61 1,712.61
54 00033 PINTURA ESMALTE GLN 103.55 44.07 4,563.45 127.18 - - 4,436.27 4,563.45
59 00398 TUBERIA CORRUGADA HDPE DN=380mm M 14.76 115.22 1,700.65 1,700.65 - - - 1,700.65
61 00015 CALAMINA GALVANIZADA DE 1.83x0.83 UND 112.99 18.70 2,112.91 2,112.91 - - - 2,112.91
72 00387 ACCESORIOS PVC PARA AGUA GLB 51.00 8.48 432.48 - 432.48 - - 432.48
74 00391 TUBERIA PVC SAP 4" X 3 m UND 61.23 5.83 356.97 - 356.97 - - 356.97
EQUIPO
37 00004 HERRAMIENTAS MANUALES %MO 8,034.73 1,630.08 3,812.74 1,878.91 713.00 8,034.73
48 00453 CAMION CISTERNA 4X2 (AGUA) 122 HP 1500 GLN HM 5.88 95.00 558.60 299.92 - - 258.68 558.60
48 00513 CAMION IMPRIMANTE DE 1800 GLS HM 0.90 113.00 101.70 - - - 101.70 101.70
48 00023 CAMION VOLQUETE 15 M3 HM 33.87 150.00 5,080.50 - 4,235.22 - 845.28 5,080.50
48 00047 CIZALLA HM 66.77 3.00 200.31 7.29 174.95 - 18.07 200.31
48 00039 MEZCLADORA DE CONCRETO DE 9 -11P3 HM 536.74 21.00 11,271.54 152.24 7,564.23 3,274.16 280.91 11,271.54
49 00024 CARGADOR FRONTAL HM 15.05 180.00 2,709.00 166.42 2,542.58 - - 2,709.00
49 00459 CARGADOR S/LLANTAS 125 HP 2.5 YD3 HM 118.09 180.00 21,256.20 11,387.51 5,470.34 - 4,398.35 21,256.20
49 00457 COMPACTADOR VIBRATORIO TIPO PLANCHA 7 HP HM 51.47 12.00 617.64 615.09 2.55 - - 617.64
49 00022 COMPRESORA NEUMATICA 87 HP HM 248.37 178.56 44,348.95 44,348.95 - - - 44,348.95
49 00399 MAQUINA TERMOFUSION HM 1.18 35.00 41.30 41.30 - - - 41.30
49 00021 MARTILLO NEUMATICO DE 29 KG HM 487.00 4.00 1,948.00 1,948.00 - - - 1,948.00
49 00451 MIRAS Y JALONES hm 33.91 5.00 169.55 169.55 - - - 169.55
49 00408 MOTONIVELADORA HM 6.73 210.31 1,415.39 842.01 - - 573.38 1,415.39
49 00450 MOVILIZACION Y DESMOVILIZACION DE EQUIPO Y MAQUINARIA GLB 1.00 8,460.66 8,460.66 8,460.66 - - - 8,460.66
49 00274 NIVEL TOPOGRAFICO HM 34.61 9.80 339.18 339.18 - - - 339.18
49 00036 PLANCHA COMPACTADORA VIBRATORIA 8 HP HM 86.79 12.00 1,041.48 910.67 - - 130.81 1,041.48
49 00275 RETROEXCAVADORA HM 224.23 120.00 26,907.60 26,907.60 - - - 26,907.60
49 00410 RODILLO LISO VIBRATORIO AUTOPRIPULSADO 70 - 100HP HM 6.25 151.07 944.19 532.68 - - 411.51 944.19
49 00030 TEODOLITO HM 33.47 9.50 317.97 317.97 - - - 317.97
49 00045 VIBRADOR DE CONCRETO 4 HP 1.35" HM 228.75 10.00 2,287.50 68.88 1,196.73 950.56 71.33 2,287.50

Pgina 3 de 4
CONSULTOR - ING. JAMES LLERENA TORRES MUNICIPALIDAD DISTRITAL DE SOCABAYA

Calendario de Utilizacion de Recursos


Obra : MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD VEHICULAR Y PEATONAL EN LA URBANIZACION LOS SAUCES EN EL DISTRITO DE SOCABAYA, PROVINCIA DE AREQUIPA -
AREQUIPA".
Ubicacion : SOCABAYA - AREQUIPA - AREQUIPA
Costo A : May - 2014 Cliente : MUNICIPALIDAD DISTRITAL DE SOCABAYA
PLAZO DE EJECUCION
TOTAL
Cod Descripcion Unid Cantidad Precio Parcial 30 Dias 30 Dias 30 Dias 30 Dias
120 Dias
COSTO DIRECTO 689,268.29 201,436.26 303,938.67 117,327.51 66,565.85 689,268.29
GASTOS GENERALES 10 % 68,926.83 20,143.63 30,393.87 11,732.75 6,656.58 68,926.83
UTILIDAD 8% 55,141.46 16,114.90 24,315.09 9,386.20 5,325.27 55,141.46
SUB TOTAL 813,336.58 237,694.79 358,647.63 138,446.46 78,547.70 813,336.58
IGV. 18 % 146,400.58 42,785.06 64,556.57 24,920.36 14,138.59 146,400.58
PRESUPUESTO TOTAL 959,737.16 280,479.85 423,204.20 163,366.82 92,686.29 959,737.16
TOTAL ACUMULADO 280,479.85 703,684.05 867,050.87 959,737.16
PORCENTAJE DE AVANCE 29.22% 44.10% 17.02% 9.66%
PORCENTAJE ACUMULADO 29.22% 73.32% 90.34% 100.00%