1. Sinopec to confirm the use of GHHL cranes to lifting the
convection modules F-1200 & F-2200. 2. Sinopec to submit a schedule and plan today and have it ready for discussion tomorrow regarding Sinopec still not loaded the completed pre-dryout convections and add convection modules for F-1500 and F-2500 total #6 modules on the stools to start PRE-DRYOUT (Si issued from 10 days ago), RB HILTON staff idle from one week ago. 3. Sinopec still not take any action to transfer breaching and hot & cold flue gas ducts to intermediate yard to start refractory application (SI issued from 10 days ago regarding area preparation and transfer items to intermediate yard). 4. Regarding final external painting of heaters floors, Sinopec to submit a schedule and plan today and have it ready for discussion tomorrow. 5. Air Intake anchors bolts. 6. Connection Bearings