Академический Документы
Профессиональный Документы
Культура Документы
OME-14 - 00
Province Of Ilocos Norte
Municipality of Marcos
OFFICE OF MUNICIPAL ENGINEER
SUMMARY OF APPROPRIATION
A. CONSTRUCTION OF 15M - THREE SPAN FLAT SLAB BRIDGE #REF! 4,800,000.00
Err:509
C. RIVER FLOOD CONTROL SLOPE PROTECTION Sitio Sadiri, Brgy. Daquioag 1,500,000.00
TOTAL Err:509
Item
Description days
No. 1 2 3 4 5 6 7 8 9 10 11 12
5,252
5,252
5,252
5,252
5,252
5,252
5,252
5,252
5,252
5,252
5,252
5,252
5,252
5,252
5,252
5,252
5,252
5,252
5,252
5,252
A1 Structure Excavation 20
4,413
4,413
4,413
4,413
4,413
4,413
4,413
4,413
4,413
4,413
4,413
4,413
4,413
4,413
4,413
4,413
4,413
4,413
4,413
4,413
4,413
4,413
4,413
4,413
4,413
4,413
4,413
4,413
4,413
4,413
4,413
4,413
4,413
4,413
4,413
4,413
4,413
4,413
4,413
4,413
4,413
4,413
A2 Formworks 42 100%
27,018
27,018
27,018
27,018
27,018
27,018
27,018
27,018
27,018
27,018
27,018
27,018
27,018
27,018
27,018
27,018
27,018
27,018
27,018
27,018
27,018
27,018
27,018
27,018
27,018
27,018
27,018
A3 Reinforcement Works 27
28,049
28,049
28,049
28,049
28,049
28,049
28,049
28,049
28,049
28,049
28,049
28,049
28,049
28,049
28,049
28,049
28,049
28,049
28,049
28,049
28,049
28,049
28,049
28,049
28,049
28,049
28,049
28,049
28,049
28,049
28,049
28,049
28,049
28,049
28,049
28,049
28,049
28,049
28,049
28,049
28,049
28,049
A4 Concrete Works 42 90%
8,708
8,708
26,779
B1 Excavation Works 1
26,779
26,779
26,779
26,779
26,779
26,779
26,779
26,779
26,779
26,779
26,779
26,779
26,779
26,779
26,779
B3 RUBBLE MASONRY 16 70%
2,946
2,946
2,946
2,946
2,946
2,946
2,946
2,946
2,946
2,946
C1 EXCAVATION WORKS 10
21,160
21,160
21,160
21,160
21,160
C2 CONCRETE Canal (Double) 5 50%
10,502
10,502
D1 EXCAVATION WORKS 1
30,438
30,438
30,438
30,438
D2 CONCRETE WORKS 4 30%
22,725
22,725
D3 RUBBLE MASONRY WORKS 1
18,933
18,933
18,933
18,933
D4 REINFORCEMENT WORKS 4 20%
9,608
9,608
9,608
9,608
9,608
9,608
D5 Formworks 6
10%
17,416
17,416
17,416
17,416
17,416
17,416
17,416
17,416
17,416
17,416
E1 Excavation Works 5 0%
SUB TOTAL 131,142 263,343 226,659 272,818 209,116 285,821 238,061 417,134 494,540 389,043 173,311 191,264
4% 12% 19% 27% 34% 42% 49% 62% 77% 89% 94% 100%
CASH FLOW
PROJECT NAME: REHABILITATION OF SMALL WATER IMPOUNDING PROJECT with CANALIZATION
PROJECT LOCATION: Brgy. TABUCBUC, Marcos, Ilocos Norte
CONTRACT DURATION: 84 C.D.
W E E K S
CATEGORY 1 2 3 4 5 6 7 8 9 10 11 12
PERIODIC ACCOMPLISHMENT 3.98% 8.00% 6.88% 8.29% 6.35% 8.68% 7.23% 12.67% 15.02% 11.82% 5.26% 5.81%
PERIODIC CASH FLOW (Php) 131,142.33 263,343.01 226,659.37 272,817.95 209,116.12 285,821.07 238,060.93 417,133.82 494,539.83 389,043.08 173,310.94 191,263.55
ACCUMULATED ACCOMPLISHMENTS 3.98% 11.98% 18.87% 27.15% 33.51% 42.19% 49.42% 62.09% 77.11% 88.93% 94.19% 100.00%
ACCUMULATED CASH FLOW (Php) 131,142.33 394,485.33 621,144.70 893,962.65 1,103,078.77 1,388,899.84 1,626,960.77 2,044,094.59 2,538,634.42 2,927,677.49 3,100,988.44 3,292,251.98
Category WEEKS
1 2 3 4 5 6 7 8 9 10 11 12
PROJECT ENGINEER
CONSTRUCTION FOREMAN
CARPENTER
MASON
LABORER/HELPER
STEELMAN
.
Local Government Unit OME - 007 - 1
Marcos, Ilocos Norte
Contract Reference Number
Standard Form Number: SF-INFR-41 Name of the Contract
Revised on: August 11,2004 Location of the Contract
WEEK
Category
1 2 3 4 5 6 7 8 9 10 11 12
BACKHOE
CONCRETE VIBRATOR
BAR CUTTER
TOTAL 96.99% -
BREAKDOWN OF ESTIMATED EXPENDITURES % OF TOTAL AMOUNT
I. ESTIMATED COST
A. DIRECT COST
1 Mobilization & Demobilization
2 Materials 52.81%
3 Labor (including Fringe Benefits) 20.60%
4 Equipment Expenses 5.00%
B. INDIRECT COST
1 Overhead, Contigencies, Miscellaneous (12% of A1 to A4) 9.05%
2 Contractor's Profit (10% of A1 to A4) 7.54%
3 Value Added Tax (VAT) (12% of DC, CP & OCM) 4.60%
4 Comprehensive ALL-RISK Insurance
84 days
3RD Quarter 2016
IMPOUNDING
45.00 m
10.00 m
2.00 m
TECHNICAL PERSONNEL REQUIRED
Description No.
1
1
4
12
3
105,042.00
185,360.70
729,491.07
1,178,048.59
2,197,942.36
17,416.48
428,468.88
445,885.36
29,463.00
105,797.79
135,260.79
21,003.28
121,751.36
45,449.88
75,732.72
57,645.00
321,582.24
87,082.38
87,082.38
99,000.00
99,000.00
3,286,753.13
AMOUNT
1,742,664.00
679,700.00
165,124.00
298,618.56
248,848.80
151,797.77
3,286,753.13
13,246.87
-
13,246.87
Php3,300,000.00
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)
ENGR. WARNER A. MACUSI RANDOLPH PRUDENCE R. INES EVELYN I. VILLANUEVA HON. ARSENIO A. AGUSTIN
Municipal Engineer Municipal Planning & Development Officer OIC MBO / MCR / HRMO Designate Municipal Mayor
Project Title: REHABILITATION
OF SMALL WATER IMPOUNDING PROJECT with CANALIZATION
Location: Brgy. TABUCBUC, Marcos, Ilocos Norte
DETAILED ESTIMATE
SUB TOTAL
Duration
Description No. of Units
Day/Hr.
EQUIPMENT
SUB TOTAL
Duration
Description No.
Day/Hr.
SUB TOTAL
TOTAL DIRECT COST
Contractor's Profit 10.00% of Direct Cost
Overhead, Contingencies, & Miscellaneous 12.00% of Direct Cost
TOTAL INDIRECT COST
TOTAL ( Direct Cost + Indirect Cost )
Value Added Tax ( VAT ) 5.00% of Direct & Indirect Cost
TOTAL ITEM COST (PhP)
COST PER
Prepared by: Approved by:
SUB TOTAL -
-
-
SUB TOTAL -
Rate
Amount
Day/hr
500.00 10,000.00
300.00 72,000.00
-
-
DETAILED ESTIMATE
Description: Formworks
Unit: Board Foot
Quantity: 360.00 bd ft
Item Duration: 42 days
Lumber 360.00 bd ft
Assorted CWN 36.00 kgs
SUB TOTAL
Duration
Description No. of Units
Day/Hr.
EQUIPMENT
SUB TOTAL
Duration
Description No.
Day/Hr.
SUB TOTAL
TOTAL DIRECT COST
Contractor's Profit 10.00% of Direct Cost
Overhead, Contingencies, & Miscellaneous 12.00% of Direct Cost
TOTAL INDIRECT COST
TOTAL ( Direct Cost + Indirect Cost )
Value Added Tax ( VAT ) 5.00% of Direct & Indirect Cost
TOTAL ITEM COST (PhP)
COST PER
Prepared by: Approved by:
850.00 8,500.00
62.00 22,320.00
130.00 4,680.00
-
-
SUB TOTAL -
Rate
Amount
Day/hr
500.00 21,000.00
400.00 50,400.00
300.00 37,800.00
-
DETAILED ESTIMATE
SUB TOTAL
Duration
Description No. of Units
Day/Hr.
EQUIPMENT
SUB TOTAL
Duration
Description No.
Day/Hr.
SUB TOTAL
TOTAL DIRECT COST
Contractor's Profit 10.00% of Direct Cost
Overhead, Contingencies, & Miscellaneous 12.00% of Direct Cost
TOTAL INDIRECT COST
TOTAL ( Direct Cost + Indirect Cost )
Value Added Tax ( VAT ) 5.00% of Direct & Indirect Cost
TOTAL ITEM COST (PhP)
COST PER
Prepared by: Approved by:
E DETAILED ESTIM
Fine Aggregates
130.00 21,060.00 Course Aggregates
TAILED ESTIMATE
cu m
days
DETAILED ESTIMATE
SUB TOTAL
Duration
Description No. of Units
Day/Hr.
EQUIPMENT
SUB TOTAL
Duration
Description No.
Day/Hr.
SUB TOTAL
TOTAL DIRECT COST
Contractor's Profit 10.00% of Direct Cost
Overhead, Contingencies, & Miscellaneous 12.00% of Direct Cost
TOTAL INDIRECT COST
TOTAL ( Direct Cost + Indirect Cost )
Value Added Tax ( VAT ) 5.00% of Direct & Indirect Cost
TOTAL ITEM COST (PhP)
COST PER
Prepared by: Approved by:
Item No.:
Description:
Unit:
Quantity:
Item Duration:
-
-
-
SUB TOTAL -
12,296.00 12,296.00
500.00 500.00
400.00 800.00
Laborer(s)
DETAILED ESTIMATE
Sand 44.00 cu m
BOULDERS 123.00 L.M.
SUB TOTAL
Duration
Description No. of Units
Day/Hr.
EQUIPMENT
SUB TOTAL
Duration
Description No.
Day/Hr.
SUB TOTAL
TOTAL DIRECT COST
Contractor's Profit 10.00% of Direct Cost
Overhead, Contingencies, & Miscellaneous 12.00% of Direct Cost
TOTAL INDIRECT COST
TOTAL ( Direct Cost + Indirect Cost )
Value Added Tax ( VAT ) 5.00% of Direct & Indirect Cost
TOTAL ITEM COST (PhP)
COST PER
Prepared by: Approved by:
320.00 137,920.00
550.00 24,200.00
920.00 113,160.00
SUB TOTAL -
Rate
Amount
Day/hr
500.00 8,000.00
400.00 12,800.00
300.00 38,400.00
DETAILED ESTIMATE
SUB TOTAL
Duration
Description No. of Units
Day/Hr.
EQUIPMENT
SUB TOTAL
Duration
Description No.
Day/Hr.
SUB TOTAL
TOTAL DIRECT COST
Contractor's Profit 10.00% of Direct Cost
Overhead, Contingencies, & Miscellaneous 12.00% of Direct Cost
TOTAL INDIRECT COST
TOTAL ( Direct Cost + Indirect Cost )
Value Added Tax ( VAT ) 5.00% of Direct & Indirect Cost
E DETAILED ESTIM
- Cement
MATERIALS
- Fine Aggregates
- Course Aggregates
SUB TOTAL -
SUB TOTAL -
Rate
Amount Description
Day/hr
TAILED ESTIMATE
cu m
days
105,797.79
7,197.13
Approved by:
DETAILED ESTIMATE
SUB TOTAL
Duration
Description No. of Units
Day/Hr.
EQUIPMENT
SUB TOTAL
Duration
Description No.
Day/Hr.
SUB TOTAL
TOTAL DIRECT COST
Contractor's Profit 10.00% of Direct Cost
Overhead, Contingencies, & Miscellaneous 12.00% of Direct Cost
TOTAL INDIRECT COST
TOTAL ( Direct Cost + Indirect Cost )
Value Added Tax ( VAT ) 5.00% of Direct & Indirect Cost
E DETAILED ESTIM
- Cement
MATERIALS
- Fine Aggregates
- Course Aggregates
SUB TOTAL -
TAILED ESTIMATE
VERSION DAM
cu m
days
121,751.36
6,211.80
Approved by:
DETAILED ESTIMATE
SUB TOTAL
Duration
Description No. of Units
Day/Hr.
EQUIPMENT
SUB TOTAL
Duration
Description No.
Day/Hr.
SUB TOTAL
TOTAL DIRECT COST
Contractor's Profit 10.00% of Direct Cost
Overhead, Contingencies, & Miscellaneous 12.00% of Direct Cost
TOTAL INDIRECT COST
TOTAL ( Direct Cost + Indirect Cost )
Value Added Tax ( VAT ) 5.00% of Direct & Indirect Cost
E DETAILED ESTIM
TAILED ESTIMATE
MATERIALS
24.00 pcs 300.00 7,200.00
57.00 pcs 420.00 23,940.00
30.00 kgs 130.00 3,900.00
75,732.72
88.09
Approved by: Prepared by:
DETAILED ESTIMATE
SUB TOTAL
SUB TOTAL
Rate
Description No. Duration Day/Hr.
Day/hr
SUB TOTAL
TOTAL DIRECT COST
Contractor's Profit 10.00% of Direct Cost
Overhead, Contingencies, & Miscellaneous 12.00% of Direct Cost
TOTAL INDIRECT COST
TOTAL ( Direct Cost + Indirect Cost )
Value Added Tax ( VAT ) 5.00% of Direct & Indirect Cost
Amount
8,500.00
18,600.00
2,600.00
29,700.00
Amount
-
-
Amount
2,700.00
7,200.00
5,400.00
-
15,300.00
45,000.00
4,500.00
5,400.00
9,900.00
54,900.00
2,745.00
57,645.00
192.15
O A. AGUSTIN
Project Title: REHABILITATION
OF SMALL WATER IMPOUNDING PROJECT with CANALIZATION
Location: Brgy. TABUCBUC, Marcos, Ilocos Norte
DETAILED ESTIMATE
SUB TOTAL
Duration
Description No. of Units
Day/Hr.
EQUIPMENT
SUB TOTAL
Duration
Description No.
Day/Hr.
SUB TOTAL
TOTAL DIRECT COST
Contractor's Profit 10.00% of Direct Cost
Overhead, Contingencies, & Miscellaneous 12.00% of Direct Cost
TOTAL INDIRECT COST
TOTAL ( Direct Cost + Indirect Cost )
Value Added Tax ( VAT ) 5.00% of Direct & Indirect Cost
TOTAL ITEM COST (PhP)
COST PER
Prepared by: Approved by:
-
-
-
SUB TOTAL -
12,296.00 61,480.00
500.00 2,500.00
400.00 4,000.00
Duration
Description (Capacity/Production rate) No. of Units Unit Rate
Day/Hr.
EQUIPMENT
Duration Rate
Description Number
Day/Hr. day/hr
LABOR
meters
meters
meters
Amount
Amount
84,480.00
84,480.00
Amount
2,250.00
1,750.00
2,800.00
6,800.00
91,280.00
8,215.20
7,302.40
12,815.71
119,613.31
332.81
Republic of the Philippines
Province of Ilocos Norte
Municipality of Marcos
OFFICE OF THE MUNICIPAL ENGINEER
BILL OF MATERIALS AND DETAILED ESTIMATES
LOCATION Ballesteros Rd., Sitio Bituin, Brgy. Valdez, Marcos, Ilocos Norte
DETAILED ESTIMATE
Duration
Description (Capacity/Production rate) No. of Units Unit Rate
Day/Hr.
EQUIPMENT
Duration Rate
Description Number
Day/Hr. day/hr
LABOR
DETAILED ESTIMATE
Amount
26,000.00
78,000.00
104,000.00
36,000.00
6,500.00
6,500.00
1,400.00
258,400.00
Amount
Amount
9,450.00
36,750.00
29,400.00
75,600.00
334,000.00
30,060.00
26,720.00
46,893.60
437,673.60
136.77
Republic of the Philippines
Province of Ilocos Norte
Municipality of Marcos
OFFICE OF THE MUNICIPAL ENGINEER
BILL OF MATERIALS AND DETAILED ESTIMATES
LOCATION Ballesteros Rd., Sitio Bituin, Brgy. Valdez, Marcos, Ilocos Norte
DETAILED ESTIMATE
LENGTH
Pay Item No. ITEM DESCRIPTION WIDTH
DEPTH
Duration
Description (Capacity/Production rate) No. of Units Unit Rate
Day/Hr.
EQUIPMENT
Duration Rate
Description Number
Day/Hr. day/hr
LABOR
DETAILED ESTIMATE
meters
meters
meters
Amount
744,426.87
270,005.25
177,376.79
180.00
1,191,988.91
Amount
36,679.04
36,679.04
Amount
33,011.14
102,701.32
184,862.38
320,574.84
1,549,242.79
139,431.85
123,939.42
217,513.69
2,030,127.75
110.70
Republic of the Philippines
Province of Ilocos Norte
Municipality of Marcos
OFFICE OF THE MUNICIPAL ENGINEER
BILL OF MATERIALS AND DETAILED ESTIMATES
LOCATION Ballesteros Rd., Sitio Bituin, Brgy. Valdez, Marcos, Ilocos Norte
DETAILED ESTIMATE
Duration
Description (Capacity/Production rate) No. of Units Unit Rate
Day/Hr.
EQUIPMENT
Duration Rate
Description Number
Day/Hr. day/hr
LABOR
OCM - 9%
CP - 8%
TAXES - 12%
DETAILED ESTIMATE
Amount
596,087.38
105,757.44
63,454.46
765,299.28
Amount
55,500.00
55,500.00
111,000.00
Amount
16,650.00
64,750.00
145,040.00
226,440.00
1,102,739.28
99,246.53
88,219.14
154,824.59
1,445,029.55
7,514.99
Republic of the Philippines
Province of Ilocos Norte
Municipality of Marcos
OFFICE OF THE MUNICIPAL ENGINEER
BILL OF MATERIALS AND DETAILED ESTIMATES
LOCATION Ballesteros Rd., Sitio Bituin, Brgy. Valdez, Marcos, Ilocos Norte
DETAILED ESTIMATE
LENGTH 60.00
Pay Item No. ITEM DESCRIPTION WIDTH 0.40
DEPTH 3.00
Duration
Description (Capacity/Production rate) No. of Units Unit Rate
Day/Hr.
EQUIPMENT
Duration Rate
Description Number
Day/Hr. day/hr
LABOR
DETAILED ESTIMATE
Amount
269,960.40
15,965.40
47,896.20
264,154.80
597,976.80
Amount
51,000.00
51,000.00
Amount
15,300.00
47,600.00
114,240.00
177,140.00
826,116.80
74,350.51
66,089.34
115,986.80
1,082,543.45
3,729.31
Republic of the Philippines
Province of Ilocos Norte
Municipality of Marcos
OFFICE OF THE MUNICIPAL ENGINEER
BILL OF MATERIALS AND DETAILED ESTIMATES
LOCATION Ballesteros Rd., Sitio Bituin, Brgy. Valdez, Marcos, Ilocos Norte
DETAILED ESTIMATE
LENGTH 15.00
Pay Item No. ITEM DESCRIPTION WIDTH 6.00
DEPTH 1.30
Duration
Description (Capacity/Production rate) No. of Units Unit Rate
Day/Hr.
EQUIPMENT
Duration Rate
Description Number
Day/Hr. day/hr
LABOR
DETAILED ESTIMATE
Amount
162,000.00
162,000.00
Amount
16,896.00
16,896.00
Amount
4,500.00
3,500.00
5,600.00
13,600.00
192,496.00
17,324.64
15,399.68
27,026.44
252,246.76
467.12
Republic of the Philippines
Province of Ilocos Norte
Municipality of Marcos
OFFICE OF THE MUNICIPAL ENGINEER
BILL OF MATERIALS AND DETAILED ESTIMATES
LOCATION Ballesteros Rd., Sitio Bituin, Brgy. Valdez, Marcos, Ilocos Norte
DETAILED ESTIMATE
LENGTH 60.00 - meters
Pay Item No. ITEM DESCRIPTION WIDTH 6.00 - meters
THICKNESS 0.30 - meters
Duration
Description (Capacity/Production rate) No. of Units Unit Rate Amount
Day/Hr.
EQUIPMENT
Duration Rate
Description Number Amount
Day/Hr. day/hr
1. PROJECT ENGINEER 1 3 500.00 1,500.00
LABOR
Duration
Description (Capacity/Production rate) No. of Units Unit Rate
Day/Hr.
Equipment assumed output /day
EQUIPMENT
Duration Rate
Description Number
Day/Hr. day/hr
1. PROJECT ENGINEER 1 3 500.00
LABOR
DETAILED ESTIMATE
meters
meters
meters
Amount
83,700.00
9,900.00
16,500.00
5,472.00
736.00
23,700.00
140,008.00
Amount
4,500.00
4,500.00
9,000.00
Amount
1,500.00
1,200.00
3,150.00
10,080.00
15,930.00
164,938.00
14,844.42
13,195.04
23,157.30
216,134.76
7,204.49
Republic of the Philippines
Province of Ilocos Norte
Municipality of Marcos
OFFICE OF THE MUNICIPAL ENGINEER
BILL OF MATERIALS AND DETAILED ESTIMATES
LOCATION Sitio Hermano, Caburtunga 925 meters 5.80 meters 5,365.00 sq.m.
Sitio Balbalay, ESCODA 925 meters 5.80 meters 5,365.00 sq.m.
Sitio 2, TABUCBUC 1,150 meters 4.80 meters 5,520.00 sq.m.
Sitio BagongBario, SANTIA 1,150 meters 4.80 meters 5,520.00 sq.m.
Brgy. DAQUIOAG 1,150 meters 4.80 meters 5,520.00 sq.m.
Brgy. IMELDA 1,150 meters 4.80 meters 5,520.00 sq.m.
Sitio Danao, MABUTI 460 meters 4.80 meters 2,208.00 sq.m.
Sitio Cabuaan, MABUTI 345 meters 4.80 meters 1,656.00 sq.m.
Brgy. VALDEZ, Ballesteros - meters 4.80 meters - sq.m.
Sitio Cabalayangan, FORT 460 meters 4.80 meters 2,208.00 sq.m.
Sitio Casapangan-Calumbuy 1,150 meters 4.80 meters 5,520.00 sq.m.
Brgy. LYDIA, Municipal Cem 460 meters 4.80 meters 2,208.00 sq.m.
Sitio Cappia, Fortuna 1,150 meters 4.80 meters 5,520.00 sq.m.
TOTAL LENGTH 10,475 meters ### sq.m.
DETAILED ESTIMATE
LENGTH 10,475.00
Pay Item No. ITEM DESCRIPTION
WIDTH 4.95 -
1.
LABOR
Amount
Amount
371,712.00
63,056.00
434,768.00
Amount
8,800.00
12,320.00
21,120.00
455,888.00
41,029.92
36,471.04
26,669.45
560,058.41
10.74
Republic of the Philippines
Province of Ilocos Norte
Municipality of Marcos
OFFICE OF THE MUNICIPAL ENGINEER
BILL OF MATERIALS AND DETAILED ESTIMATES
LOCATION Sitio Hermano, Caburtunga 925 meters 5.60 meters 777.00 cu.m.
Sitio Balbalay, ESCODA 925 meters 5.60 meters 777.00 cu.m.
Sitio 2, TABUCBUC 1,150 meters 4.60 meters 793.50 cu.m.
Sitio BagongBario, SANTI 1,150 meters 4.60 meters 793.50 cu.m.
Brgy. DAQUIOAG 1,150 meters 4.60 meters 793.50 cu.m.
Brgy. IMELDA 1,150 meters 4.60 meters 793.50 cu.m.
Sitio Danao, MABUTI 460 meters 4.60 meters 317.40 cu.m.
Sitio Cabuaan, MABUTI 345 meters 4.60 meters 238.05 cu.m.
Brgy. VALDEZ, Ballesteros - meters 4.60 meters - cu.m.
Sitio Cabalayangan, FORT 460 meters 4.60 meters 317.40 cu.m.
Sitio Casapangan-Calumbu 1,150 meters 4.60 meters 793.50 cu.m.
Brgy. LYDIA, Municipal Ce 460 meters 4.60 meters 317.40 cu.m.
Sitio Cappia, Fortuna 1,150 meters 4.60 meters 793.50 cu.m.
TOTAL LENGTH 10,475 meters 7,505.25 cu.m.
DETAILED ESTIMATE
LENGTH 10,475.00 -
Pay Item No. ITEM DESCRIPTION WIDTH 4.75 -
THICKNESS 0.15 -
Amount
3,377,700.00
3,377,700.00
Amount
317,472.90
42,216.96
40,455.68
400,145.54
Amount
7,600.00
10,640.00
18,240.00
3,796,085.54
341,647.70
303,686.84
222,071.00
4,663,491.09
621.36
Republic of the Philippines
Province of Ilocos Norte
Municipality of Marcos
OFFICE OF THE MUNICIPAL ENGINEER
BILL OF MATERIALS AND DETAILED ESTIMATES
LOCATION Sitio Hermano, Caburtungan 925 meters 5.30 meters 980.50 cu.m.
Sitio Balbalay, ESCODA 925 meters 5.30 meters 980.50 cu.m.
Sitio 2, TABUCBUC 1,150 meters 4.30 meters 989.00 cu.m.
Sitio BagongBario, SANTIA 1,150 meters 4.30 meters 989.00 cu.m.
Brgy. DAQUIOAG 1,150 meters 4.30 meters 989.00 cu.m.
Brgy. IMELDA 1,150 meters 4.30 meters 989.00 cu.m.
Sitio Danao, MABUTI 460 meters 4.30 meters 395.60 cu.m.
Sitio Cabuaan, MABUTI 345 meters 4.30 meters 296.70 cu.m.
Brgy. VALDEZ, Ballesteros - meters 4.30 meters - cu.m.
Sitio Cabalayangan, FORTU 460 meters 4.30 meters 395.60 cu.m.
Sitio Casapangan-Calumbuy 1,150 meters 4.30 meters 989.00 cu.m.
Brgy. LYDIA, Municipal Cem 460 meters 4.30 meters 395.60 cu.m.
Sitio Cappia, Fortuna 1,150 meters 4.30 meters 989.00 cu.m.
TOTAL LENGTH 10,475 meters 9,378.50 cu.m.
DETAILED ESTIMATE
LENGTH 10,475.00 -
Pay Item No. ITEM DESCRIPTION WIDTH 4.45 -
THICKNESS 0.20 -
Amount
4,220,325.00
4,220,325.00
Amount
401,018.40
52,771.20
50,569.60
504,359.20
Amount
9,600.00
13,440.00
23,040.00
4,747,724.20
427,295.18
379,817.94
277,741.87
5,832,579.18
621.91
Republic of the Philippines
Province of Ilocos Norte
Municipality of Marcos
OFFICE OF THE MUNICIPAL ENGINEER
BILL OF MATERIALS AND DETAILED ESTIMATES
Sitio Hermano, Caburtungan,
LOCATIO Sta Rosa, PACIFICO 925 meters 5.00 meters 693.75 cu.m.
DETAILED ESTIMATE
LENGTH 10,475.00
Pay Item
No.
ITEM DESCRIPTION WIDTH 4.15
THICKNESS 0.15
3,702,013.61
3,682,002.72
3,682,002.72
3,682,002.72
3,682,002.72
1,472,801.09
1,104,600.82
1,472,801.09
3,682,002.72
1,472,801.09
3,682,002.72
35,019,047.65
ETAILED ESTIMATE
meters
meters
meters
Amount
18,900,000.00
2,165,900.00
3,609,650.00
1,074,735.00
160,122.46
158,000.00
26,068,407.46
Amount
838,792.50
896,583.33
184,368.33
43,423.33
1,963,167.50
Amount
14,583.33
153,125.00
306,250.00
473,958.33
28,505,533.29
2,565,498.00
2,280,442.66
1,667,573.70
35,019,047.65
5,336.24
Republic of the Philippines
Province of Ilocos Norte
Municipality of Marcos
OFFICE OF THE MUNICIPAL ENGINEER
BILL OF MATERIALS AND DETAILED ESTIMATES
#N/A Sitio Sadiri, Brgy. Daquioag
DETAILED ESTIMATE
LENGTH 1,150.00
Pay Item No. ITEM DESCRIPTION WIDTH 6.00
DEPTH 0.60
DETAILED ESTIMATE
LENGTH 350.00 #N/A
Pay Item No. ITEM DESCRIPTION
WIDTH #REF! -
DETAILED ESTIMATE
meters
meters
Amount
Amount
16,896.00
9,008.00
25,904.00
Amount
400.00
560.00
960.00
26,864.00
2,417.76
2,149.12
3,771.71
35,202.59
#REF!
Republic of the Philippines
Province of Ilocos Norte
Municipality of Marcos
OFFICE OF THE MUNICIPAL ENGINEER
BILL OF MATERIALS AND DETAILED ESTIMATES
LOCATION Sitio Bituen-Calumbuyan, Valdez 350 meters
DETAILED ESTIMATE
LENGTH 350.00 #N/A
Pay Item No. ITEM DESCRIPTION WIDTH #REF! -
THICKNESS 0.15 -
DETAILED ESTIMATE
meters
meters
meters
Amount
#REF!
#REF!
Amount
#N/A
11,770.32
#N/A
Amount
400.00
560.00
960.00
#N/A
#N/A
#N/A
#N/A
#N/A
#N/A
Republic of the Philippines
Province of Ilocos Norte
Municipality of Marcos
OFFICE OF THE MUNICIPAL ENGINEER
BILL OF MATERIALS AND DETAILED ESTIMATES
DETAILED ESTIMATE
LENGTH 350.00 #N/A
Pay Item No. ITEM DESCRIPTION WIDTH #REF! -
THICKNESS 0.15 -
DETAILED ESTIMATE
meters
meters
meters
Amount
#REF!
#REF!
Amount
#N/A
#N/A
Amount
400.00
560.00
960.00
#N/A
#N/A
#N/A
#N/A
#N/A
#N/A
Republic of the Philippines
Province of Ilocos Norte
Municipality of Marcos
OFFICE OF THE MUNICIPAL ENGINEER
BILL OF MATERIALS AND DETAILED ESTIMATES
DETAILED ESTIMATE
LENGTH 200.00 #REF! meters
Pay Item No. ITEM DESCRIPTION WIDTH #REF! meters
THICKNESS meters
d 311 PORTLAND CEMENT CONCRETE PAVEMENT AREA #REF! cu.m.
DETAILED ESTIMATE
LENGTH 100.00
Pay Item No. ITEM DESCRIPTION WIDTH 6.00
DEPTH 0.80
OCM - 9%
27,804.04
CP - 8% 24,714.70
TAXES - 12% 43,374.30
Engr. WARNER A. MACUSI #REF! TOTAL ADJUSTED COST = 404,826.79
Municipal Engineer Municipal Mayor UNIT COST 7,813.30
Republic of the Philippines
Province of Ilocos Norte
Municipality of Marcos
OFFICE OF THE MUNICIPAL ENGINEER
BILL OF MATERIALS AND DETAILED ESTIMATES
#N/A Sitio Namnama, Brgy. Imelda
DETAILED ESTIMATE
LENGTH 16.00
Pay Item No. ITEM DESCRIPTION WIDTH 0.50
DEPTH 3.00
5.00 Kms.
45.00 Km. per Hour
35.00 Km. per hour
6.67 minutes
8.57 minutes
Manuevering, Loading,Spot
17.00 minutes
32.24 minutes
13.00
10.00 cu.m.
130.00 cu.m
4.00 Kms.
35.00 Km. per Hour
30.00 Km. per hour
6.86 minutes
8.00 minutes
Manuevering, Loading,Spot
20.00 minutes
34.86 minutes
12.00
5.00 cu.m.
60.00 cu.m
Project Title: REHABILITATION
OF SMALL WATER IMPOUNDING PROJECT with CANALIZATION
Location: Brgy. TABUCBUC, Marcos, Ilocos Norte
DETAILED ESTIMATE
SUB TOTAL
Duration
Description No. of Units
Day/Hr.
EQUIPMENT
SUB TOTAL
Duration
Description No.
Day/Hr.
LABOR
SUB TOTAL
TOTAL DIRECT COST
Contractor's Profit 0.00% of Direct Cost
Overhead, Contingencies, & Miscellaneous 0.00% of Direct Cost
TOTAL INDIRECT COST
TOTAL ( Direct Cost + Indirect Cost )
Value Added Tax ( VAT ) 0.00% of Direct & Indirect Cost
TOTAL ITEM COST (PhP)
COST PER
Prepared by: Approved by:
6,600.00 99,000.00
-
-
SUB TOTAL -
Rate
Amount
Day/hr
- -
- -
SUB TOTAL -
TOTAL DIRECT COST 99,000.00
of Direct Cost -
of Direct Cost -
TOTAL INDIRECT COST -
Cost + Indirect Cost ) 99,000.00
of Direct & Indirect Cost -
99,000.00
6,600.00
cu.m
Excavation Works
Equipment Units Days Rate/Day
Backhoe (0.80) = 1.00 ### 11,621.00 11,621.00
Dumptruck (3.00) = 1.00 ### 10,141.00 10,141.00
21,762.00
Labor
Foreman = 1.00 ### 450.00 450.00
Backhoe Operator = 1.00 ### 350.00 350.00
Dumptruck Driver = 1.00 ### 350.00 350.00
Helper(s) = 2.00 1.00 250.00 500.00
1,650.00
Labor
Foreman 1.00 3.00 450.00 1,350.00
Mason 2.00 3.00 350.00 2,100.00
Laborer 4.00 3.00 250.00 3,000.00
6,450.00
31,644.00
Bare Rental
No. Name & Capacity Description
Hourly Rate Daily Rate
1 Air Compressor 86-125 cfm/42Hp 358.00 2,864.00
2 Asphalt Batching Plant 1,139.63 9,117.04
3 Asphalt Distributor 10 ft wide 936.00 7,488.00
4 Asphalt Paver/Finisher PF-180 1,349.00 10,792.00
5 Backhoe SE 130 LC-2, 0.80 cu.m. 1,537.00 12,296.00
6 Backhoe, Wheel Type PW60-3, 0.28 cu.m. 840.00 6,720.00
7 Backhoe with Pavement Breaker 2,074.95 16,599.60
8 Bulldozer D65A-8/155Hp 2,299.00 18,392.00
9 Clampshell 315.00 2,520.00
10 Chain Saw 120.00 960.00
11 Concrete Paver/Finisher GP-2500 Slipform 6,237.00 49,896.00
12 Concrete Batching Plant 30 cu.m. 1,208.03 9,664.24
13 Crawler Crane 46-50T 1,956.00 15,648.00
14 Crawler Crane 36-40T 1,729.00 13,832.00
15 Concrete Vibrator 148.88 1,191.04
16 Concrete Mixer 1.5-2 Bagger 190.00 1,520.00
17 Concrete Mixer 1-Bagger 172.00 1,376.00
18 Concrete Screeder 545.00 4,360.00
19 Concrete Saw 167.38 1,339.04
20 Dump Truck (Cap. 10-11 cu.m.) 1,352.00 10,816.00
21 Payloader 1.5 cu.m. 1,733.00 13,864.00
22 Plate Compactor 123.00 984.00
23 Rebar Bender 351.50 2,812.00
24 Rebar Cutter 219.75 1,758.00
25 Road Grader 135Hp / GD511R-1 2,088.64 16,709.10
26 Road Roller, Vibratory Single Smooth Drum, CA252D 1,319.28 10,554.24
27 Transit Mixer 5-6 cu.m. 958.62 7,668.96
28 Water Truck (1000 Gal.) 632.12 5,056.96
29 Cargo Truck (5T) 696.63 5,573.05
30 TM Crane, 35T Capacity 1,487.63 11,901.05
31 Cutting Outfit (Gas Type) 44.38 355.00
32 Kneading Machine 115.63 925.05
33 Applicator 21.88 175.05
34 Low Bed (Prime Mover 25T Cap) 430.06 3,440.50
Prices of Construction Materials
(Based on Regional Price Monitoring Report - 2nd Quarter CY 13)
Hauling
No. Description Unit Unit Price Total Price Remarks
Cost
1 Portland Cement bag 285.00 1.57 286.57
2 Fine Aggregates cu.m. 476.20 69.88 546.08
3 Coarse Aggregates cu.m. 571.40 69.88 641.28
4 Agg. Subbase Course cu.m. 390.00 69.88 459.88
5 Embankment Materials cu.m. 300.00 69.88 369.88
6 RSB, Grade 40 kg. 55.00 0.04 55.04
7 RSB, Grade 60 kg. 60.00 0.04 60.04
8 Plain Round Rebar,10mm dia.x6m pcs 171.10 0.04 171.14
9 Tie Wire, #16 kg. 85.70 85.70
10 Boulders (Rock Class "A") cu.m. 560.00 179.99 739.99
11 PVC Pipe, 2" l.m. 97.00 97.00
12 RCPC, 910mm pc. 2,170.00 2,170.00
13 Form Lumber, Coco bd.ft. 28.00 28.00
14 Good Lumber, False Work bd.ft. 75.00 75.00
15 Marine Plywood, 4'x8'x1/2" pc. 857.10 857.10
16 Ordinary Plywood, 4'x8'x1/2" pc. 809.50 809.50
17 CW Nails, Assorted kg. 80.50 80.50
18 Tarpauline (Printed), 4'x8' pc. 630.00 630.00
19 Filter Cloth sq.m. 160.00 160.00
Field Office (rental), including electric and
20 mo. 6,200.00 6,200.00
water bills
25 Warning Sign 3mm thk.Triangle 600mm pc 4,972.00 4,972.00
26 75mm G.I Pipe pc 2,400.00 2,400.00
27 5mm Bolt & Knot pc 20.00 20.00
28 Chevron Directional Sign E39(450mmx610m pc 4,500.00 4,500.00
29 Informative Sign (457mmx1219mmx3mm S pc 7,150.00 7,150.00
30 Safety Shoes m.d 2.77 2.77
31 Safety Helmet m.d 0.25 0.25
32 Safety Gloves m.d 7.67 7.67
33 Acetylene/Oxygen set 3,000.00 3,000.00
35 Thermoplastic White bag 2,700.00 2,700.00
36 Glass Beads bag 800.00 800.00
37 Primer ltr 130.00 130.00
38 Rope (Cotton 1/4" x 30m.) l.m. 150 150.00
39 LPG kg. 53.45 53.45
40 Calsumie kg. 24 24.00
41 Curing Compound lit. 100.00 100.00
42 Asphalt Sealant lit. 75.00 75.00
43 Steel Forms l.m. 45.00 45.00
44 Concrete Saw(Diamond Blade 14") pcs 575.00 575.00
45 Pipe Sleeve, 1-1/2" dia. l.m. 131.25 131.25
46 Grease or Tar lit. 210.00 210.00
Summary of Labor Rates
No. Designation Hourly Rate Daily Rate
Certified by:
Certified by:
ENGR. WARNER A. MACUSI
Municipal Engineer Wednesday, February 18, 2015
3 Certificate Recommnded for Payment by:
PROJECT TITLE: 0
LOCATION: BRGY. MABUTI, MARCOS, ILOCOS NORTE
DETAILED ENGINEERING DOCUMENTS
Road Sections
SLOPE PROTECTION
RCDG BRIDGE
1 Approprition Ordinance
PURCHASE REQUEST