Вы находитесь на странице: 1из 153

Republic of the Philippines

OME-14 - 00
Province Of Ilocos Norte
Municipality of Marcos
OFFICE OF MUNICIPAL ENGINEER

SUMMARY OF APPROPRIATION
A. CONSTRUCTION OF 15M - THREE SPAN FLAT SLAB BRIDGE #REF! 4,800,000.00

B. UPGRADING and IMPROVEMENT of ROADS

LOCATION: SITIO & BARANGAY LENGTH ROAD WIDTH AMOUNT

Sitio Hermano, Caburtungan, Sta Rosa, PACIFICO 925.00 M 5.00 M 5,000,000.00

Sitio Balbalay, ESCODA 925.00 M 5.00 M 5,000,000.00

Sitio 2, TABUCBUC 1,150.00 M 4.00 M 5,000,000.00

Sitio BagongBario, SANTIAGO 1,150.00 M 4.00 M 5,000,000.00

Brgy. DAQUIOAG 1,150.00 M 4.00 M 5,000,000.00

Brgy. IMELDA 1,150.00 M 4.00 M 5,000,000.00

Sitio Danao, MABUTI 460.00 M 4.00 M 2,000,000.00

Sitio Cappia, Fortuna 1,150.00 M 4.00 M 5,000,000.00

Err:509

C. RIVER FLOOD CONTROL SLOPE PROTECTION Sitio Sadiri, Brgy. Daquioag 1,500,000.00

D. Err:509 Brgy. VALDEZ Err:509

TOTAL Err:509

Prepared by: Approved by:

Engr. WARNER A. MACUSI Hon. ARSENIO A. AGUSTIN


Municipal Engineer Municipal Mayor
Local Government Unit OME - 005 - 1
Marcos, Ilocos Norte Contract Reference Number
Name of the Contract

Standard Form Number: SF-INFR-41 Location of the Contract

Revised on: August 11,2004

CONSTRUCTION SCHEDULE & S-CURVE


PROJECT NAME: REHABILITATION OF SMALL WATER IMPOUNDING PROJECT with CANALIZATION
PROJECT LOCATION: Brgy. TABUCBUC, Marcos, Ilocos Norte
CONTRACT DURATION: 84 C.D.

Item
Description days
No. 1 2 3 4 5 6 7 8 9 10 11 12

A. CONSTRUCTION OF REINFORCE CONCRETE DRAINAGE CANAL

5,252

5,252

5,252

5,252

5,252

5,252

5,252

5,252

5,252

5,252

5,252

5,252

5,252

5,252

5,252

5,252

5,252

5,252

5,252

5,252
A1 Structure Excavation 20

4,413

4,413

4,413

4,413

4,413

4,413

4,413

4,413

4,413

4,413

4,413

4,413

4,413

4,413

4,413

4,413

4,413

4,413

4,413

4,413

4,413

4,413

4,413

4,413

4,413

4,413

4,413

4,413

4,413

4,413

4,413

4,413

4,413

4,413

4,413

4,413

4,413

4,413

4,413

4,413

4,413

4,413
A2 Formworks 42 100%

27,018

27,018

27,018

27,018

27,018

27,018

27,018

27,018

27,018

27,018

27,018

27,018

27,018

27,018

27,018

27,018

27,018

27,018

27,018

27,018

27,018

27,018

27,018

27,018

27,018

27,018

27,018
A3 Reinforcement Works 27

28,049

28,049

28,049

28,049

28,049

28,049

28,049

28,049

28,049

28,049

28,049

28,049

28,049

28,049

28,049

28,049

28,049

28,049

28,049

28,049

28,049

28,049

28,049

28,049

28,049

28,049

28,049

28,049

28,049

28,049

28,049

28,049

28,049

28,049

28,049

28,049

28,049

28,049

28,049

28,049

28,049

28,049
A4 Concrete Works 42 90%

B RUBBLE MASONRY WORKS (Slope Protection-Impounding Area) 80%

8,708

8,708

26,779
B1 Excavation Works 1

26,779

26,779

26,779

26,779

26,779

26,779

26,779

26,779

26,779

26,779

26,779

26,779

26,779

26,779

26,779
B3 RUBBLE MASONRY 16 70%

C. REHABILITATION OF MASONRY CANAL (to Rectangular Concrete Canal) 60%

2,946

2,946

2,946

2,946

2,946

2,946

2,946

2,946

2,946

2,946
C1 EXCAVATION WORKS 10

21,160

21,160

21,160

21,160

21,160
C2 CONCRETE Canal (Double) 5 50%

D. REINFORCED CONCRETE SMALL DIVERSION DAM 40%

10,502

10,502
D1 EXCAVATION WORKS 1

30,438

30,438

30,438

30,438
D2 CONCRETE WORKS 4 30%

22,725

22,725
D3 RUBBLE MASONRY WORKS 1

18,933

18,933

18,933

18,933
D4 REINFORCEMENT WORKS 4 20%

9,608

9,608

9,608

9,608

9,608

9,608
D5 Formworks 6

10%

E. DREDGING OF WATER IMPOUNDING AREA


17,416

17,416

17,416

17,416

17,416

17,416

17,416

17,416

17,416

17,416

17,416
E1 Excavation Works 5 0%

SUB TOTAL 131,142 263,343 226,659 272,818 209,116 285,821 238,061 417,134 494,540 389,043 173,311 191,264

4% 12% 19% 27% 34% 42% 49% 62% 77% 89% 94% 100%

TOTAL 621,144.70 767,755.14 1,149,734.58 753,617.57


PREPARED BY: APPROVED BY: 3,292,251.98

ENGR. WARNER A. MACUSI HON. ARSENIO A. AGUSTIN


MUNICIPAL ENGINEER MUNICIPAL MAYOR
Local Government Unit OME - 008 - 1
Marcos, Ilocos Norte Contract Reference Number
Name of the Contract
Standard Form Number: SF-INFR-41 Location of the Contract
Revised on: August 11,2004

CASH FLOW
PROJECT NAME: REHABILITATION OF SMALL WATER IMPOUNDING PROJECT with CANALIZATION
PROJECT LOCATION: Brgy. TABUCBUC, Marcos, Ilocos Norte
CONTRACT DURATION: 84 C.D.

W E E K S

CATEGORY 1 2 3 4 5 6 7 8 9 10 11 12

FIRST QUARTER SECOND QUARTER THIRD QUARTER FOURTH QUARTER

PERIODIC ACCOMPLISHMENT 3.98% 8.00% 6.88% 8.29% 6.35% 8.68% 7.23% 12.67% 15.02% 11.82% 5.26% 5.81%

PERIODIC CASH FLOW (Php) 131,142.33 263,343.01 226,659.37 272,817.95 209,116.12 285,821.07 238,060.93 417,133.82 494,539.83 389,043.08 173,310.94 191,263.55

ACCUMULATED ACCOMPLISHMENTS 3.98% 11.98% 18.87% 27.15% 33.51% 42.19% 49.42% 62.09% 77.11% 88.93% 94.19% 100.00%

ACCUMULATED CASH FLOW (Php) 131,142.33 394,485.33 621,144.70 893,962.65 1,103,078.77 1,388,899.84 1,626,960.77 2,044,094.59 2,538,634.42 2,927,677.49 3,100,988.44 3,292,251.98

QUARTERLY 621,144.70 767,755.14 1,149,734.58 753,617.57

Contractor's Name: Contract Name: 3,292,251.98

PREPARED BY: APPROVED BY:

ENGR. WARNER A. MACUSI HON. ARSENIO A. AGUSTIN


MUNICIPAL ENGINEER MUNICIPAL MAYOR
Local Government Unit OME - 006 - 1
Marcos, Ilocos Norte Contract Reference Number
Name of the Contract
Standard Form Number: SF-INFR-41 Location of the Contract
Revised on: August 11,2004

MANPOWER UTILIZATION SCHEDULE


PROJECT NAME: REHABILITATION OF SMALL WATER IMPOUNDING PROJECT with CANALIZATION
PROJECT LOCATION: Brgy. TABUCBUC, Marcos, Ilocos Norte
CONTRACT DURATION: 84 C.D.

Category WEEKS
1 2 3 4 5 6 7 8 9 10 11 12

PROJECT ENGINEER

CONSTRUCTION FOREMAN

HEAVY EQUIPMENT OPTR

LIGHT EQUIPMENT OPTR

CARPENTER

MASON

LABORER/HELPER

STEELMAN

Contractor's Name: Contract Name:

PREPARED BY: APPROVED BY:

ENGR. WARNER A. MACUSI HON. ARSENIO A. AGUSTIN


MUNICIPAL ENGINEER MUNICIPAL MAYOR

.
Local Government Unit OME - 007 - 1
Marcos, Ilocos Norte
Contract Reference Number
Standard Form Number: SF-INFR-41 Name of the Contract
Revised on: August 11,2004 Location of the Contract

EQUIPMENT UTILIZATION SCHEDULE


PROJECT NAME: REHABILITATION OF SMALL WATER IMPOUNDING PROJECT with CANALIZATION
PROJECT LOCATION: Brgy. TABUCBUC, Marcos, Ilocos Norte
CONTRACT DURATION: 84 C.D.

WEEK
Category
1 2 3 4 5 6 7 8 9 10 11 12

BACKHOE

CONCRETE MIXER-ONE BAG

CONCRETE VIBRATOR

BAR CUTTER

Contractor's Name: Contract Name:

PREPARED BY: APPROVED BY:

ENGR. WARNER A. MACUSI HON. ARSENIO A. AGUSTIN


MUNICIPAL ENGINEER MUNICIPAL MAYOR
Republic of the Philippines
Province Of Ilocos Norte OME - 0
1
Municipality of Marcos
OFFICE OF MUNICIPAL ENGINEER
INDIVIDUAL PROGRAM OF WORK
NAME / LOCATION OF PROJECT APPROPRIATION: Php3,300,000.
Source of Fund: DA-BUB
LGU
REHABILITATION OF SMALL WATER
IMPOUNDING PROJECT with CANALIZATION
Calendar Days to Complete:
Brgy. TABUCBUC, Marcos, Ilocos Norte Desirable Starting Date: 3RD Quarter 201
PROJECT CATEGORY PROJECT DESCRIPTION CANAL
LENGTH = 1,060.00
IRRIGATION FASCILITIES WIDTH = 0.40
DEPTH = 0.60
MINIMUM EQUIPMENT REQUIREMENTS TECHNICAL PERSONNEL REQUIRED
Description No. Description
BACKHOE 1 PROJECT ENGINEER
CONCRETE MIXER - ONE BAGGER 1 FOREMAN
CARPENTER
LABORER
STEELMAN

ESTIMATED COST OF PROPOSED WORK


ITEM DESCRIPTION % UNIT QUANTITY DIRECT COST UNIT COST
A. CONSTRUCTION OF REINFORCE CONCRETE DRAINAGE CANAL 2,197,942.36

A1 Structure Excavation 3.20% cu.m 116.00 82,000.00 905.53


A2 Formworks 5.64% bd ft 360.00 144,700.00 514.89
A3 Reinforcement Works 22.19% kgs 5,207.66 569,470.00 140.08
A4 Concrete Works 35.84% cu m 167.90 919,632.00 7,016.37

B RUBBLE MASONRY WORKS (Slope Protection-Impounding Area) 445,885.36

B1 Excavation Works 0.53% cu m 80.00 13,596.00 217.71


B3 RUBBLE MASONRY 13.04% cu.m. 123.00 334,480.00 3,483.49

C. REHABILITATION OF MASONRY CANAL (to Rectangular Concrete Canal) 135,260.79

C1 EXCAVATION WORKS 0.90% cu m 30.00 23,000.00 982.10

C2 CONCRETE Canal (Double) 3.22% cu m 14.70 82,590.00 7,197.13

D. REINFORCED CONCRETE SMALL DIVERSION DAM 263,937.24

D1 EXCAVATION WORKS 0.64% cu m 11.00 16,396.00 1,909.39

D2 CONCRETE WORKS 3.70% cu m 19.60 95,044.00 6,211.80

D3 RUBBLE MASONRY WORKS 1.38% cu m 27.20 35,480.00 1,670.95


D4 REINFORCEMENT WORKS 2.30% kgs 859.74 59,120.00 88.09

D5 Formworks 1.75% bd ft 300.00 45,000.00 192.15

E. DREDGING OF WATER IMPOUNDING AREA


87,082.38

E1 Excavation Works 2.65% cu m 600.00 67,980.00 145.14

F. TOPOGRAPHIC SURVEY AND MAP 99,000.00

F1 SURVEYING and MAPPING 3.01% has. 15.00 99,000.00 6,600.00

TOTAL 96.99% -
BREAKDOWN OF ESTIMATED EXPENDITURES % OF TOTAL AMOUNT
I. ESTIMATED COST
A. DIRECT COST
1 Mobilization & Demobilization
2 Materials 52.81%
3 Labor (including Fringe Benefits) 20.60%
4 Equipment Expenses 5.00%
B. INDIRECT COST
1 Overhead, Contigencies, Miscellaneous (12% of A1 to A4) 9.05%
2 Contractor's Profit (10% of A1 to A4) 7.54%
3 Value Added Tax (VAT) (12% of DC, CP & OCM) 4.60%
4 Comprehensive ALL-RISK Insurance

SUB-TOTAL ( CONTRACTED COST ) 99.60% 3


II. ESTIMATED GOVERNMENT EXPENDITURES
1 Engineering and Administrative Overhead
LGU Administrative Cost ( PROJECT MONITORING HONORARIA)
0.40%
2 TOW / Site Acquisition
3 Services of Heavy Equipment and Aggregate Materials
4 Admin Cost (3.5% of Allocated fund retain of DA RFU I) 0.00%
SUB-TOTAL 0.40%
III. CONTINGENCIES / RESERVES
1 Physical (up to 5% of estimated Contract Cost)
2 Price Escalation ( up to 12% of the Estimated Cost)

TOTAL ESTIMATED PROJECT COST 100.00% Php3,3


Prepared by: Approved by:

Engr. WARNER A. MACUSI Hon. ARSENIO A. AGUSTIN


Municipal Engineer Municipal Mayor
Republic of the Philippines
Province Of Ilocos Norte OME - 001-
1
Municipality of Marcos
OF MUNICIPAL ENGINEER
DUAL PROGRAM OF WORK
Php3,300,000.00
3,000,000.00
300,000.00

84 days
3RD Quarter 2016
IMPOUNDING
45.00 m
10.00 m
2.00 m
TECHNICAL PERSONNEL REQUIRED
Description No.
1
1
4
12
3

TED COST OF PROPOSED WORK


ADJUSTED COST

105,042.00
185,360.70
729,491.07
1,178,048.59
2,197,942.36

17,416.48
428,468.88

445,885.36

29,463.00

105,797.79

135,260.79

21,003.28

121,751.36

45,449.88
75,732.72

57,645.00

321,582.24

87,082.38

87,082.38

99,000.00

99,000.00
3,286,753.13
AMOUNT

1,742,664.00
679,700.00
165,124.00

298,618.56
248,848.80
151,797.77

3,286,753.13

13,246.87

-
13,246.87

Php3,300,000.00

Hon. ARSENIO A. AGUSTIN


Municipal Mayor
OME - 004 - 1

APPROVED BUDGET FOR THE CONTRACT


PROJECT NAME: REHABILITATION OF SMALL WATER IMPOUNDING PROJECT with CANALIZATION SOURCE OF FUND DEPT. of AGRI. = 3,000,000.00
PROJECT LOCATION: Brgy. TABUCBUC, Marcos, Ilocos Norte LGU- Counterpart= 300,000.00
CONTRACT DURATION: 84 C.D. TOTAL FUND = 3,300,000.00

MARK UPS in percent TOTAL MARK UPS TOTAL


ITEM ESTIMATED
DESCRIPTION QUANTITY UNITS VAT INDIRECT TOTAL COST UNIT COST
NO. DIRECT COST
OCM PROFIT % VALUE COST

(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)

A. CONSTRUCTION OF REINFORCE CONCRETE DRAINAGE CANAL


A1 Structure Excavation 116.00 cu.m 82,000.00 12.0% 10.0% 22.0% 18,040.00 5,002.00 23,042.00 105,042.00 905.53
A2 Formworks 360.00 bd ft 144,700.00 12.0% 10.0% 22.0% 31,834.00 8,826.70 40,660.70 185,360.70 514.89
A3 Reinforcement Works 5,207.66 kgs 569,470.00 12.0% 10.0% 22.0% 125,283.40 34,737.67 160,021.07 729,491.07 140.08
A4 Concrete Works 167.90 cu m 919,632.00 12.0% 10.0% 22.0% 202,319.04 56,097.55 258,416.59 1,178,048.59 7,016.37

B RUBBLE MASONRY WORKS (Slope Protection-Impounding Area)


B1 Excavation Works 80.00 cu m 13,596.00 12.0% 10.0% 22.0% 2,991.12 829.36 3,820.48 17,416.48 217.71
B3 RUBBLE MASONRY 123.00 cu.m. 334,480.00 12.0% 10.0% 22.0% 73,585.60 20,403.28 93,988.88 428,468.88 3,483.49

C. REHABILITATION OF MASONRY CANAL (to Rectangular Concrete Canal)


C1 EXCAVATION WORKS 30.00 cu m 23,000.00 12.0% 10.0% 22.0% 5,060.00 1,403.00 6,463.00 29,463.00 982.10
C2 CONCRETE Canal (Double) 14.70 cu m 82,590.00 12.0% 10.0% 22.0% 18,169.80 5,037.99 23,207.79 105,797.79 7,197.13

D. REINFORCED CONCRETE SMALL DIVERSION DAM


D1 EXCAVATION WORKS 11.00 cu m 16,396.00 12.0% 10.0% 22.0% 3,607.12 1,000.16 4,607.28 21,003.28 1,909.39
D2 CONCRETE WORKS 19.60 cu m 95,044.00 12.0% 10.0% 22.0% 20,909.68 5,797.68 26,707.36 121,751.36 6,211.80
D3 RUBBLE MASONRY WORKS 27.20 cu m 35,480.00 12.0% 10.0% 22.0% 7,805.60 2,164.28 9,969.88 45,449.88 1,670.95
D4 REINFORCEMENT WORKS 859.74 kgs 59,120.00 12.0% 10.0% 22.0% 13,006.40 3,606.32 16,612.72 75,732.72 88.09
D5 Formworks 300.00 bd ft 45,000.00 12.0% 10.0% 22.0% 9,900.00 2,745.00 12,645.00 57,645.00 192.15

E. DREDGING OF WATER IMPOUNDING AREA


E1 Excavation Works 600.00 cu m 67,980.00 12.0% 10.0% 22.0% 14,955.60 4,146.78 19,102.38 87,082.38 145.14
2,488,488.00 699,265.13 3,187,753.13

APPROVED BUDGET FOR THE CONTRACT PHP 3,187,753.13

Prepared by: Approved by:

ENGR. WARNER A. MACUSI RANDOLPH PRUDENCE R. INES EVELYN I. VILLANUEVA HON. ARSENIO A. AGUSTIN
Municipal Engineer Municipal Planning & Development Officer OIC MBO / MCR / HRMO Designate Municipal Mayor
Project Title: REHABILITATION
OF SMALL WATER IMPOUNDING PROJECT with CANALIZATION
Location: Brgy. TABUCBUC, Marcos, Ilocos Norte

DETAILED ESTIMATE

Item No.: REINFORCED CONCRETE CANAL

Description: Structure Excavation


Unit: cubic meter
Quantity: 116.00 cu.m
Item Duration: 20 days

Description Quantity Unit


MATERIALS

SUB TOTAL
Duration
Description No. of Units
Day/Hr.
EQUIPMENT

SUB TOTAL
Duration
Description No.
Day/Hr.

Construction Foreman 1.00 20.00


Laborer(s) 12.00 20.00
LABOR

SUB TOTAL
TOTAL DIRECT COST
Contractor's Profit 10.00% of Direct Cost
Overhead, Contingencies, & Miscellaneous 12.00% of Direct Cost
TOTAL INDIRECT COST
TOTAL ( Direct Cost + Indirect Cost )
Value Added Tax ( VAT ) 5.00% of Direct & Indirect Cost
TOTAL ITEM COST (PhP)
COST PER
Prepared by: Approved by:

ENGR. WARNER A. MACUSI HON. ARSENIO A. AGUSTIN


Municipal Engineer Municipal Mayor
OME - 002 - 0
CT with CANALIZATION

Unit Cost Amount

SUB TOTAL -

Unit Rate Amount

-
-

SUB TOTAL -
Rate
Amount
Day/hr

500.00 10,000.00
300.00 72,000.00
-
-

SUB TOTAL 82,000.00


TOTAL DIRECT COST 82,000.00
of Direct Cost 8,200.00
of Direct Cost 9,840.00
TOTAL INDIRECT COST 18,040.00
Cost + Indirect Cost ) 100,040.00
of Direct & Indirect Cost 5,002.00
105,042.00
905.53

HON. ARSENIO A. AGUSTIN


Municipal Mayor
Project Title: REHABILITATION
OF SMALL WATER IMPOUNDING PROJECT with CANALIZATION
Location: Brgy. TABUCBUC, Marcos, Ilocos Norte

DETAILED ESTIMATE

Item No.: REINFORCED CONCRETE CANAL

Description: Formworks
Unit: Board Foot
Quantity: 360.00 bd ft
Item Duration: 42 days

Description Quantity Unit

Ordinary Plywood - 1/2" X 4' X 8' 10.00 pcs


MATERIALS

Lumber 360.00 bd ft
Assorted CWN 36.00 kgs

SUB TOTAL
Duration
Description No. of Units
Day/Hr.
EQUIPMENT

SUB TOTAL
Duration
Description No.
Day/Hr.

Construction Foreman 1.00 42.00


Carpenter 3.00 42.00
LABOR

Laborer(s) 3.00 42.00

SUB TOTAL
TOTAL DIRECT COST
Contractor's Profit 10.00% of Direct Cost
Overhead, Contingencies, & Miscellaneous 12.00% of Direct Cost
TOTAL INDIRECT COST
TOTAL ( Direct Cost + Indirect Cost )
Value Added Tax ( VAT ) 5.00% of Direct & Indirect Cost
TOTAL ITEM COST (PhP)
COST PER
Prepared by: Approved by:

ENGR. WARNER A. MACUSI HON. ARSENIO A. AGUSTIN


Municipal Engineer Municipal Mayor
OME - 002 - 0
CT with CANALIZATION

Unit Cost Amount

850.00 8,500.00
62.00 22,320.00
130.00 4,680.00

SUB TOTAL 35,500.00

Unit Rate Amount

-
-

SUB TOTAL -
Rate
Amount
Day/hr

500.00 21,000.00
400.00 50,400.00
300.00 37,800.00
-

SUB TOTAL 109,200.00


TOTAL DIRECT COST 144,700.00
of Direct Cost 14,470.00
of Direct Cost 17,364.00
TOTAL INDIRECT COST 31,834.00
Cost + Indirect Cost ) 176,534.00
of Direct & Indirect Cost 8,826.70
185,360.70
514.89

HON. ARSENIO A. AGUSTIN


Municipal Mayor
Project Title: REHABILITATION
OF SMALL WATER IMPOUNDING PROJECT with CANALIZATION
Location: Brgy. TABUCBUC, Marcos, Ilocos Norte

DETAILED ESTIMATE

Item No.: REINFORCED CONCRETE CANAL

Description: Reinforcement Works


Unit: kilograms
Quantity: 5,207.66 kgs
Item Duration: 27 days

Description Quantity Unit

10mm dia. RSB x 6.0m 2399.00 pcs


MATERIALS

#16 G.I. Tie Wire 162.00 kgs

SUB TOTAL
Duration
Description No. of Units
Day/Hr.
EQUIPMENT

Minor tools 1.00 1.00

SUB TOTAL
Duration
Description No.
Day/Hr.

Construction Foreman 1.00 27.00


Steelman 4.00 27.00
LABOR

Laborer(s) 4.00 27.00

SUB TOTAL
TOTAL DIRECT COST
Contractor's Profit 10.00% of Direct Cost
Overhead, Contingencies, & Miscellaneous 12.00% of Direct Cost
TOTAL INDIRECT COST
TOTAL ( Direct Cost + Indirect Cost )
Value Added Tax ( VAT ) 5.00% of Direct & Indirect Cost
TOTAL ITEM COST (PhP)
COST PER
Prepared by: Approved by:

ENGR. WARNER A. MACUSI HON. ARSENIO A. AGUSTIN


Municipal Engineer Municipal Mayor
OME - 002 - 0
CT with CANALIZATION Project Title: REHABILITATION
OF SMALL WATER IMPOUNDING PRO
Location: Brgy. TABUCBUC, Marcos, Ilocos Norte

E DETAILED ESTIM

Item No.: REINFORCED CONCRETE CANAL


Description: Concrete Works
Unit: cubic meter
Quantity: 167.90
Item Duration: 42

Unit Cost Amount Description

190.00 455,810.00 Cement


MATERIALS

Fine Aggregates
130.00 21,060.00 Course Aggregates

SUB TOTAL 476,870.00

Unit Rate Amount Description


EQUIPMENT

lot 3,500.00 One Bagger Concrete Mixer

SUB TOTAL 3,500.00


Rate
Amount Description
Day/hr

500.00 13,500.00 Construction Foreman


400.00 43,200.00 Mason
LABOR

300.00 32,400.00 Laborer(s)


-

SUB TOTAL 89,100.00


TOTAL DIRECT COST 569,470.00
of Direct Cost 56,947.00 Contractor's Profit
of Direct Cost 68,336.40 Overhead, Contingencies, & Miscellaneous
TOTAL INDIRECT COST 125,283.40
Cost + Indirect Cost ) 694,753.40 TOTAL ( Dir
of Direct & Indirect Cost 34,737.67 Value Added Tax ( VAT )
729,491.07 TOTAL ITEM COST (PhP)
140.08 COST PER
Prepared by:

HON. ARSENIO A. AGUSTIN ENGR. WARNER A. MACUSI


Municipal Mayor Municipal Engineer
OME - 002 - 0
TER IMPOUNDING PROJECT with CANALIZATION
s Norte

TAILED ESTIMATE

cu m
days

Quantity Unit Unit Cost Amount

1512.00 bags 320.00 483,840.00


84.00 cu m 550.00 46,200.00
168.00 cu m 550.00 92,400.00

SUB TOTAL 622,440.00


Duration
No. of Units Unit Rate Amount
Day/Hr.

1.00 42.00 1,376.00 57,792.00


-

SUB TOTAL 57,792.00


Duration Rate
No. Amount
Day/Hr. Day/hr

1.00 42.00 500.00 21,000.00


4.00 42.00 400.00 67,200.00
12.00 42.00 300.00 151,200.00
-

SUB TOTAL 239,400.00


TOTAL DIRECT COST 919,632.00
10.00% of Direct Cost 91,963.20
12.00% of Direct Cost 110,355.84
TOTAL INDIRECT COST 202,319.04
TOTAL ( Direct Cost + Indirect Cost ) 1,121,951.04
5.00% of Direct & Indirect Cost 56,097.55
1,178,048.59
7,016.37
Approved by:

HON. ARSENIO A. AGUSTIN


Municipal Mayor
Project Title: REHABILITATION
OF SMALL WATER IMPOUNDING PROJECT with CANALIZATION
Location: Brgy. TABUCBUC, Marcos, Ilocos Norte

DETAILED ESTIMATE

Item No.: RUBBLE MASONRY WORKS (Slope Protection-Impounding Area)


Description: Excavation Works
Unit: cubic meter
Quantity: 80.00 cu m
Item Duration: 1 days

Description Quantity Unit


MATERIALS

SUB TOTAL
Duration
Description No. of Units
Day/Hr.
EQUIPMENT

Backhoe (0.80 cu. m) 1.00 1.00

SUB TOTAL
Duration
Description No.
Day/Hr.

Construction Foreman 1.00 1.00


Helper(s) 2.00 1.00
LABOR

SUB TOTAL
TOTAL DIRECT COST
Contractor's Profit 10.00% of Direct Cost
Overhead, Contingencies, & Miscellaneous 12.00% of Direct Cost
TOTAL INDIRECT COST
TOTAL ( Direct Cost + Indirect Cost )
Value Added Tax ( VAT ) 5.00% of Direct & Indirect Cost
TOTAL ITEM COST (PhP)
COST PER
Prepared by: Approved by:

ENGR. WARNER A. MACUSI HON. ARSENIO A. AGUSTIN


Municipal Engineer Municipal Mayor
OME - 002 - 0
CT with CANALIZATION

Item No.:
Description:
Unit:
Quantity:
Item Duration:

Unit Cost Amount

-
-
-

SUB TOTAL -

Unit Rate Amount

12,296.00 12,296.00

SUB TOTAL 12,296.00


Rate
Amount
Day/hr

500.00 500.00
400.00 800.00
Laborer(s)

SUB TOTAL 1,300.00


TOTAL DIRECT COST 13,596.00
of Direct Cost 1,359.60
of Direct Cost 1,631.52
TOTAL INDIRECT COST 2,991.12
Cost + Indirect Cost ) 16,587.12
of Direct & Indirect Cost 829.36
17,416.48
217.71
Prepared by:

HON. ARSENIO A. AGUSTIN ENGR. WARNER A. MACUSI


Municipal Mayor Municipal Engineer
Project Title: REHABILITATION
OF SMALL WATER IMPOUNDING PROJECT with CANALIZATION
Location: Brgy. TABUCBUC, Marcos, Ilocos Norte

DETAILED ESTIMATE

Item No.: RUBBLE MASONRY WORKS (Slope Protection-Impounding Area)


Description: RUBBLE MASONRY
Unit: Cubic meters
Quantity: 123.00 cu.m.
Item Duration: 16 days

Description Quantity Unit

Cement 431.00 bags


MATERIALS

Sand 44.00 cu m
BOULDERS 123.00 L.M.

SUB TOTAL
Duration
Description No. of Units
Day/Hr.
EQUIPMENT

SUB TOTAL
Duration
Description No.
Day/Hr.

Construction Foreman 1.00 16.00


Mason 2.00 16.00
LABOR

Laborer(s) 8.00 16.00

SUB TOTAL
TOTAL DIRECT COST
Contractor's Profit 10.00% of Direct Cost
Overhead, Contingencies, & Miscellaneous 12.00% of Direct Cost
TOTAL INDIRECT COST
TOTAL ( Direct Cost + Indirect Cost )
Value Added Tax ( VAT ) 5.00% of Direct & Indirect Cost
TOTAL ITEM COST (PhP)
COST PER
Prepared by: Approved by:

ENGR. WARNER A. MACUSI HON. ARSENIO A. AGUSTIN


Municipal Engineer Municipal Mayor
OME - 002 - 0
CT with CANALIZATION

Unit Cost Amount

320.00 137,920.00
550.00 24,200.00
920.00 113,160.00

SUB TOTAL 275,280.00

Unit Rate Amount

SUB TOTAL -
Rate
Amount
Day/hr

500.00 8,000.00
400.00 12,800.00
300.00 38,400.00

SUB TOTAL 59,200.00


TOTAL DIRECT COST 334,480.00
of Direct Cost 33,448.00
of Direct Cost 40,137.60
TOTAL INDIRECT COST 73,585.60
Cost + Indirect Cost ) 408,065.60
of Direct & Indirect Cost 20,403.28
428,468.88
3,483.49

HON. ARSENIO A. AGUSTIN


Municipal Mayor
Project Title: REHABILITATION
OF SMALL WATER IMPOUNDING PROJECT with CANALIZATION
Location: Brgy. TABUCBUC, Marcos, Ilocos Norte

DETAILED ESTIMATE

Item No.: REHABILITATION OF MASONRY CANAL (to Rectangular Concrete Canal)


Description: EXCAVATION WORKS
Unit: cubic meter
Quantity: 30.00 cu m
Item Duration: 10 days

Description Quantity Unit


MATERIALS

SUB TOTAL
Duration
Description No. of Units
Day/Hr.
EQUIPMENT

SUB TOTAL
Duration
Description No.
Day/Hr.

Construction Foreman 1.00 10.00


LABOR

Helper(s) 6.00 10.00

SUB TOTAL
TOTAL DIRECT COST
Contractor's Profit 10.00% of Direct Cost
Overhead, Contingencies, & Miscellaneous 12.00% of Direct Cost
TOTAL INDIRECT COST
TOTAL ( Direct Cost + Indirect Cost )
Value Added Tax ( VAT ) 5.00% of Direct & Indirect Cost

TOTAL ITEM COST (PhP)


COST PER
Prepared by: Approved by:

ENGR. WARNER A. MACUSI HON. ARSENIO A. AGUSTIN


Municipal Engineer Municipal Mayor
OME - 002 - 0
CT with CANALIZATION Project Title: REHABILITATION
OF SMALL WATER IMPOUNDING PRO
Location: Brgy. TABUCBUC, Marcos, Ilocos Norte

E DETAILED ESTIM

Item No.: REHABILITATION OF MASONRY CANAL (to Rectangular Con


Description: CONCRETE Canal (Double)
Unit: cubic meter
Quantity: 14.70
Item Duration: 5

Unit Cost Amount Description

- Cement
MATERIALS

- Fine Aggregates
- Course Aggregates

SUB TOTAL -

Unit Rate Amount Description


EQUIPMENT

- One Bagger Concrete Mixer

SUB TOTAL -
Rate
Amount Description
Day/hr

500.00 5,000.00 Construction Foreman


Mason
LABOR

300.00 18,000.00 Laborer(s)

SUB TOTAL 23,000.00


TOTAL DIRECT COST 23,000.00
of Direct Cost 2,300.00 Contractor's Profit
of Direct Cost 2,760.00 Overhead, Contingencies, & Miscellaneous
TOTAL INDIRECT COST 5,060.00
Cost + Indirect Cost ) 28,060.00 TOTAL ( Dir
of Direct & Indirect Cost 1,403.00 Value Added Tax ( VAT )

29,463.00 TOTAL ITEM COST (PhP)


982.10 COST PER
Prepared by:

HON. ARSENIO A. AGUSTIN ENGR. WARNER A. MACUSI


Municipal Mayor Municipal Engineer
OME - 002 - 0
TER IMPOUNDING PROJECT with CANALIZATION
s Norte

TAILED ESTIMATE

AL (to Rectangular Concrete Canal)

cu m
days

Quantity Unit Unit Cost Amount

133.00 bags 320.00 42,560.00


8.00 cu m 550.00 4,400.00
15.00 cu m 550.00 8,250.00

SUB TOTAL 55,210.00


Duration
No. of Units Unit Rate Amount
Day/Hr.

1.00 5.00 1,376.00 6,880.00

SUB TOTAL 6,880.00


Duration Rate
No. Amount
Day/Hr. Day/hr

1.00 5.00 500.00 2,500.00


3.00 5.00 400.00 6,000.00
8.00 5.00 300.00 12,000.00
-

SUB TOTAL 20,500.00


TOTAL DIRECT COST 82,590.00
10.00% of Direct Cost 8,259.00
12.00% of Direct Cost 9,910.80
TOTAL INDIRECT COST 18,169.80
TOTAL ( Direct Cost + Indirect Cost ) 100,759.80
5.00% of Direct & Indirect Cost 5,037.99

105,797.79
7,197.13
Approved by:

HON. ARSENIO A. AGUSTIN


Municipal Mayor
Project Title: REHABILITATION
OF SMALL WATER IMPOUNDING PROJECT with CANALIZATION
Location: Brgy. TABUCBUC, Marcos, Ilocos Norte

DETAILED ESTIMATE

Item No.: REINFORCED CONCRETE SMALL DIVERSION DAM


Description: EXCAVATION WORKS
Unit: cubic meter
Quantity: 11.00 cu m
Item Duration: 1 day

Description Quantity Unit


MATERIALS

SUB TOTAL
Duration
Description No. of Units
Day/Hr.
EQUIPMENT

Backhoe (0.80 cu. m) 1.00 1.00

SUB TOTAL
Duration
Description No.
Day/Hr.

Construction Foreman 1.00 1.00


LABOR

Helper(s) 6.00 2.00

SUB TOTAL
TOTAL DIRECT COST
Contractor's Profit 10.00% of Direct Cost
Overhead, Contingencies, & Miscellaneous 12.00% of Direct Cost
TOTAL INDIRECT COST
TOTAL ( Direct Cost + Indirect Cost )
Value Added Tax ( VAT ) 5.00% of Direct & Indirect Cost

TOTAL ITEM COST (PhP)


COST PER
Prepared by: Approved by:

ENGR. WARNER A. MACUSI HON. ARSENIO A. AGUSTIN


Municipal Engineer Municipal Mayor
OME - 002 - 0
CT with CANALIZATION Project Title: REHABILITATION
OF SMALL WATER IMPOUNDING PRO
Location: Brgy. TABUCBUC, Marcos, Ilocos Norte

E DETAILED ESTIM

Item No.: REINFORCED CONCRETE SMALL DIVERSION DAM


Description: CONCRETE WORKS
Unit: cubic meter
Quantity: 19.60
Item Duration: 4

Unit Cost Amount Description

- Cement
MATERIALS

- Fine Aggregates
- Course Aggregates

SUB TOTAL -

Unit Rate Amount Description


EQUIPMENT

12,296.00 12,296.00 One Bagger Concrete Mixer

SUB TOTAL 12,296.00


Rate
Amount Description
Day/hr

500.00 500.00 Construction Foreman


Mason
LABOR

300.00 3,600.00 Laborer(s)

SUB TOTAL 4,100.00


TOTAL DIRECT COST 16,396.00
of Direct Cost 1,639.60 Contractor's Profit
of Direct Cost 1,967.52 Overhead, Contingencies, & Miscellaneous
TOTAL INDIRECT COST 3,607.12
Cost + Indirect Cost ) 20,003.12 TOTAL ( Dir
of Direct & Indirect Cost 1,000.16 Value Added Tax ( VAT )

21,003.28 TOTAL ITEM COST (PhP)


1,909.39 COST PER
Prepared by:

HON. ARSENIO A. AGUSTIN ENGR. WARNER A. MACUSI


Municipal Mayor Municipal Engineer
OME - 002 - 0
TER IMPOUNDING PROJECT with CANALIZATION
s Norte

TAILED ESTIMATE

VERSION DAM

cu m
days

Quantity Unit Unit Cost Amount

177.00 bags 320.00 56,640.00


10.00 cu m 550.00 5,500.00
20.00 cu m 550.00 11,000.00

SUB TOTAL 73,140.00


Duration
No. of Units Unit Rate Amount
Day/Hr.

1.00 4.00 1,376.00 5,504.00

SUB TOTAL 5,504.00


Duration Rate
No. Amount
Day/Hr. Day/hr

1.00 4.00 500.00 2,000.00


3.00 4.00 400.00 4,800.00
8.00 4.00 300.00 9,600.00
-

SUB TOTAL 16,400.00


TOTAL DIRECT COST 95,044.00
10.00% of Direct Cost 9,504.40
12.00% of Direct Cost 11,405.28
TOTAL INDIRECT COST 20,909.68
TOTAL ( Direct Cost + Indirect Cost ) 115,953.68
5.00% of Direct & Indirect Cost 5,797.68

121,751.36
6,211.80
Approved by:

HON. ARSENIO A. AGUSTIN


Municipal Mayor
Project Title: REHABILITATION
OF SMALL WATER IMPOUNDING PROJECT with CANALIZATION
Location: Brgy. TABUCBUC, Marcos, Ilocos Norte

DETAILED ESTIMATE

Item No.: REINFORCED CONCRETE SMALL DIVERSION DAM


Description: RUBBLE MASONRY WORKS
Unit: cubic meter
Quantity: 27.20 cu m
Item Duration: 1 days

Description Quantity Unit

Cement 14.00 bags


MATERIALS

Fine Aggregates 2.00 cu m


BOULDERS 27.20 pcs

SUB TOTAL
Duration
Description No. of Units
Day/Hr.
EQUIPMENT

One Bagger Concrete Mixer 1.00 1.00

SUB TOTAL
Duration
Description No.
Day/Hr.

Construction Foreman 1.00 1.00


Mason 3.00 1.00
LABOR

Laborer(s) 6.00 1.00

SUB TOTAL
TOTAL DIRECT COST
Contractor's Profit 10.00% of Direct Cost
Overhead, Contingencies, & Miscellaneous 12.00% of Direct Cost
TOTAL INDIRECT COST
TOTAL ( Direct Cost + Indirect Cost )
Value Added Tax ( VAT ) 5.00% of Direct & Indirect Cost

TOTAL ITEM COST (PhP)


COST PER
Prepared by: Approved by:

ENGR. WARNER A. MACUSI HON. ARSENIO A. AGUSTIN


Municipal Engineer Municipal Mayor
OME - 002 - 0
CT with CANALIZATION Project Title: REHABILITATION
OF SMALL WATER IMPOUNDING PRO
Location: Brgy. TABUCBUC, Marcos, Ilocos Norte

E DETAILED ESTIM

Item No.: REINFORCED CONCRETE SMALL DIVERSION DAM


Description: REINFORCEMENT WORKS
Unit: kilograms
Quantity: 859.74
Item Duration: 4

Unit Cost Amount Description

320.00 4,480.00 10mm dia. RSB x 6.0m


MATERIALS

550.00 1,100.00 12mm dia. RSB x 6.0m


920.00 25,024.00 16mm dia. RSB x 6.0m
#16 G.I. Tie Wire

SUB TOTAL 30,604.00

Unit Rate Amount Description


EQUIPMENT

1,376.00 1,376.00 MINOR TOOLS

SUB TOTAL 1,376.00


Rate
Amount Description
Day/hr

500.00 500.00 Construction Foreman


400.00 1,200.00 Steelman
LABOR

300.00 1,800.00 Laborer(s)


-

SUB TOTAL 3,500.00


TOTAL DIRECT COST 35,480.00
of Direct Cost 3,548.00 Contractor's Profit
of Direct Cost 4,257.60 Overhead, Contingencies, & Miscellaneous
TOTAL INDIRECT COST 7,805.60
Cost + Indirect Cost ) 43,285.60 TOTAL ( Dir
of Direct & Indirect Cost 2,164.28 Value Added Tax ( VAT )

45,449.88 TOTAL ITEM COST (PhP)


1,670.95 COST PER
Prepared by:

HON. ARSENIO A. AGUSTIN ENGR. WARNER A. MACUSI


Municipal Mayor Municipal Engineer
OME - 002 - 0
TER IMPOUNDING PROJECT with CANALIZATION Project Title:
s Norte Location:

TAILED ESTIMATE

VERSION DAM Item No.:


Description:
Unit:
kgs Quantity:
days Item Duration:

Quantity Unit Unit Cost Amount

52.00 pcs 190.00 9,880.00

MATERIALS
24.00 pcs 300.00 7,200.00
57.00 pcs 420.00 23,940.00
30.00 kgs 130.00 3,900.00

SUB TOTAL 44,920.00


Duration
No. of Units Unit Rate Amount
Day/Hr.
EQUIPMENT

1.00 LOT 4,000.00

SUB TOTAL 4,000.00


Duration Rate
No. Amount
Day/Hr. Day/hr

1.00 4.00 450.00 1,800.00


3.00 4.00 400.00 4,800.00
LABOR

3.00 4.00 300.00 3,600.00


-

SUB TOTAL 10,200.00


TOTAL DIRECT COST 59,120.00
10.00% of Direct Cost 5,912.00
12.00% of Direct Cost 7,094.40
TOTAL INDIRECT COST 13,006.40
TOTAL ( Direct Cost + Indirect Cost ) 72,126.40
5.00% of Direct & Indirect Cost 3,606.32

75,732.72
88.09
Approved by: Prepared by:

HON. ARSENIO A. AGUSTIN


Municipal Mayor
REHABILITATION OF SMALL WATER IMPOUNDING PROJECT with CANALIZATION
Brgy. TABUCBUC, Marcos, Ilocos Norte

DETAILED ESTIMATE

REINFORCED CONCRETE SMALL DIVERSION DAM


Formworks
Board Foot
300.00 bd ft
6 days

Description Quantity Unit Unit Cost

Ordinary Plywood - 1/2" X 4' X 8' 10.00 pcs 850.00


Lumber 300.00 bd ft 62.00
Assorted CWN 20.00 kgs 130.00

SUB TOTAL

Description No. of Units Duration Day/Hr. Unit Rate

SUB TOTAL
Rate
Description No. Duration Day/Hr.
Day/hr

Construction Foreman 1.00 6.00 450.00


Carpenter 3.00 6.00 400.00
Laborer(s) 3.00 6.00 300.00

SUB TOTAL
TOTAL DIRECT COST
Contractor's Profit 10.00% of Direct Cost
Overhead, Contingencies, & Miscellaneous 12.00% of Direct Cost
TOTAL INDIRECT COST
TOTAL ( Direct Cost + Indirect Cost )
Value Added Tax ( VAT ) 5.00% of Direct & Indirect Cost

TOTAL ITEM COST (PhP)


COST PER
Approved by:

ENGR. WARNER A. MACUSI HON. ARSENIO A. AGUSTIN


Municipal Engineer Municipal Mayor
OME - 002 - 0
NALIZATION

Amount

8,500.00
18,600.00
2,600.00

29,700.00

Amount

-
-

Amount

2,700.00
7,200.00
5,400.00
-

15,300.00
45,000.00
4,500.00
5,400.00
9,900.00
54,900.00
2,745.00

57,645.00
192.15

O A. AGUSTIN
Project Title: REHABILITATION
OF SMALL WATER IMPOUNDING PROJECT with CANALIZATION
Location: Brgy. TABUCBUC, Marcos, Ilocos Norte

DETAILED ESTIMATE

Item No.: DREDGING OF WATER IMPOUNDING AREA


Description: Excavation Works
Unit: cubic meter
Quantity: 600.00 cu m
Item Duration: 5 days

Description Quantity Unit


MATERIALS

SUB TOTAL
Duration
Description No. of Units
Day/Hr.
EQUIPMENT

Backhoe (0.80 cu. m) 1.00 5.00

SUB TOTAL
Duration
Description No.
Day/Hr.

Construction Foreman 1.00 5.00


Helper(s) 2.00 5.00
LABOR

SUB TOTAL
TOTAL DIRECT COST
Contractor's Profit 10.00% of Direct Cost
Overhead, Contingencies, & Miscellaneous 12.00% of Direct Cost
TOTAL INDIRECT COST
TOTAL ( Direct Cost + Indirect Cost )
Value Added Tax ( VAT ) 5.00% of Direct & Indirect Cost
TOTAL ITEM COST (PhP)
COST PER
Prepared by: Approved by:

ENGR. WARNER A. MACUSI HON. ARSENIO A. AGUSTIN


Municipal Engineer Municipal Mayor
OME - 002 - 0
CT with CANALIZATION

Unit Cost Amount

-
-
-

SUB TOTAL -

Unit Rate Amount

12,296.00 61,480.00

SUB TOTAL 61,480.00


Rate
Amount
Day/hr

500.00 2,500.00
400.00 4,000.00

SUB TOTAL 6,500.00


TOTAL DIRECT COST 67,980.00
of Direct Cost 6,798.00
of Direct Cost 8,157.60
TOTAL INDIRECT COST 14,955.60
Cost + Indirect Cost ) 82,935.60
of Direct & Indirect Cost 4,146.78
87,082.38
145.14

HON. ARSENIO A. AGUSTIN


Municipal Mayor
Republic of the Philippines
OME-14 - 001
Province of Ilocos Norte
Municipality of Marcos
OFFICE OF THE MUNICIPAL ENGINEER
BILL OF MATERIALS AND DETAILED ESTIMATES
LOCATION Ballesteros Rd., Sitio Bituin, Brgy. Valdez, Marcos, Ilocos Norte
DETAILED ESTIMATE BRIDGE WINGWALL
LENGTH 15.00 3.00
Pay Item No. ITEM DESCRIPTION WIDTH 4.00 0.20
DEPTH 2.80 3.00

a 103 STRUCTURE EXCAVATION AREA 359.40 cu.m.

Description Quantity Unit Unit Cost


MATERIALS

Material Direct Cost

Duration
Description (Capacity/Production rate) No. of Units Unit Rate
Day/Hr.
EQUIPMENT

Equipment assumed output /day


1. Backhoe 60.00 1 5 16,896.00

Equipment Direct Cost

Duration Rate
Description Number
Day/Hr. day/hr
LABOR

1. CONSTRUCTION FOREMAN 1 5 450.00


2. SKILLED CONSTRUCTION WORKER 1 5 350.00
3. LABORERS 2 5 280.00

Labor Direct Cost

Total Direct Cost


Submitted By: Approved by: PLUS INDIRECT COST
OCM - 9%
CP - 8%
TAXES - 12%

Engr. WARNER A. MACUSI HON. SALVADOR S. PILLOS TOTAL ADJUSTED COST =


Municipal Engineer Municipal Mayor UNIT COST
Republic of the Philippines
OME-14 - 001
Province of Ilocos Norte
Municipality of Marcos
CE OF THE MUNICIPAL ENGINEER
ATERIALS AND DETAILED ESTIMATES

meters
meters
meters

Amount

Amount

84,480.00

84,480.00

Amount

2,250.00
1,750.00
2,800.00

6,800.00

91,280.00

8,215.20
7,302.40
12,815.71
119,613.31
332.81
Republic of the Philippines
Province of Ilocos Norte
Municipality of Marcos
OFFICE OF THE MUNICIPAL ENGINEER
BILL OF MATERIALS AND DETAILED ESTIMATES
LOCATION Ballesteros Rd., Sitio Bituin, Brgy. Valdez, Marcos, Ilocos Norte
DETAILED ESTIMATE

Pay Item No. ITEM DESCRIPTION

a 900 FORMWORKS VOLUME 3,200.00 bd.ft.

Description Quantity Unit Unit Cost


1. 2" X 2" X 12' Form Lumber 100 400 bd.ft. 65.00
MATERIALS

2. 2" X 3" X 12' Form Lumber 200 1,200 bd.ft. 65.00


3. 2" X 4" X 12' Form Lumber 200 1,600 bd.ft. 65.00
4. Plywood 1/2" 40 pcs 900.00
5. CWN 4" 5 keg 1,300.00
6. CWN 3" 5 keg 1,300.00
7 CWN 2" / 1-1/2" 1 keg 1,400.00
Material Direct Cost

Duration
Description (Capacity/Production rate) No. of Units Unit Rate
Day/Hr.
EQUIPMENT

Equipment assumed output /day

Equipment Direct Cost

Duration Rate
Description Number
Day/Hr. day/hr
LABOR

1. CONSTRUCTION FOREMAN 1 21 450.00


2. SKILLED CARPENTER 5 21 350.00
3. LABORERS 5 21 280.00

Labor Direct Cost

Total Direct Cost


Submitted By: Approved by: PLUS INDIRECT COST
OCM - 9%
CP - 8%
TAXES - 12%

Engr. WARNER A. MACUSI HON. SALVADOR S. PILLOS TOTAL ADJUSTED COST =


Municipal Engineer Municipal Mayor UNIT COST
Republic of the Philippines
Province of Ilocos Norte
Municipality of Marcos
CE OF THE MUNICIPAL ENGINEER
ATERIALS AND DETAILED ESTIMATES

DETAILED ESTIMATE

Amount
26,000.00
78,000.00
104,000.00
36,000.00
6,500.00
6,500.00

1,400.00
258,400.00

Amount

Amount

9,450.00
36,750.00
29,400.00

75,600.00

334,000.00

30,060.00
26,720.00
46,893.60
437,673.60
136.77
Republic of the Philippines
Province of Ilocos Norte
Municipality of Marcos
OFFICE OF THE MUNICIPAL ENGINEER
BILL OF MATERIALS AND DETAILED ESTIMATES
LOCATION Ballesteros Rd., Sitio Bituin, Brgy. Valdez, Marcos, Ilocos Norte
DETAILED ESTIMATE
LENGTH
Pay Item No. ITEM DESCRIPTION WIDTH
DEPTH

a 901 REINFORCING STEEL BARS WEIGHT 18,339.52 kgs

Description Quantity Unit Unit Cost


MATERIALS

1. 20 mm x 6.0 RSB 11,453 kgs 65.00


2. 16 mm x 6.0 RSB 4,154 kgs 65.00
3. 12 mm x 6.0 RSB 2,729 kgs 65.00
4. #16 Tie Wire 4 rolls 45.00

Material Direct Cost

Duration
Description (Capacity/Production rate) No. of Units Unit Rate
Day/Hr.
EQUIPMENT

Equipment assumed output /day


1. Bar Cutter 250.00 1 73 500.00

Equipment Direct Cost

Duration Rate
Description Number
Day/Hr. day/hr
LABOR

1. CONSTRUCTION FOREMAN 1 73 450.00


2. STEELMAN 4 73 350.00
3. LABORERS 9 73 280.00

Labor Direct Cost

Total Direct Cost


Submitted By: Approved by: PLUS INDIRECT COST
OCM - 9%
CP - 8%
TAXES - 12%

Engr. WARNER A. MACUSI HON. SALVADOR S. PILLOS TOTAL ADJUSTED COST =


Municipal Engineer Municipal Mayor UNIT COST
Republic of the Philippines
Province of Ilocos Norte
Municipality of Marcos
CE OF THE MUNICIPAL ENGINEER
ATERIALS AND DETAILED ESTIMATES

DETAILED ESTIMATE
meters
meters
meters

Amount
744,426.87
270,005.25
177,376.79
180.00

1,191,988.91

Amount

36,679.04

36,679.04

Amount

33,011.14
102,701.32
184,862.38

320,574.84

1,549,242.79

139,431.85
123,939.42
217,513.69
2,030,127.75
110.70
Republic of the Philippines
Province of Ilocos Norte
Municipality of Marcos
OFFICE OF THE MUNICIPAL ENGINEER
BILL OF MATERIALS AND DETAILED ESTIMATES
LOCATION Ballesteros Rd., Sitio Bituin, Brgy. Valdez, Marcos, Ilocos Norte
DETAILED ESTIMATE

Pay Item No. ITEM DESCRIPTION

a 902 CONCRETE ( 3000 psi ) VOLUME 192.29 cu.m.

Description Quantity Unit Unit Cost


1. Portland Cement 1,923 bags 310.00
MATERIALS

2. Screened Gravel 3/4" 192 cu.m. 550.00


3. Screened Clean Sand 115 cu.m. 550.00

Material Direct Cost

Duration
Description (Capacity/Production rate) No. of Units Unit Rate
Day/Hr.
EQUIPMENT

Equipment assumed output /day


1. CONCRETE MIXER - ONE BAGGER 1 37 1,500.00
CONCRETE VIBRATOR 1 37 1,500.00

Equipment Direct Cost

Duration Rate
Description Number
Day/Hr. day/hr
LABOR

1. CONSTRUCTION FOREMAN 1 37 450.00


2. MASON 5 37 350.00
3. LABORERS 14 37 280.00

Labor Direct Cost

Total Direct Cost


Submitted By: Approved by: PLUS INDIRECT COST

OCM - 9%

CP - 8%
TAXES - 12%

Engr. WARNER A. MACUSI HON. SALVADOR S. PILLOS TOTAL ADJUSTED COST =


Municipal Engineer Municipal Mayor UNIT COST
Republic of the Philippines
Province of Ilocos Norte
Municipality of Marcos
CE OF THE MUNICIPAL ENGINEER
ATERIALS AND DETAILED ESTIMATES

DETAILED ESTIMATE

Amount
596,087.38
105,757.44
63,454.46

765,299.28

Amount

55,500.00
55,500.00

111,000.00

Amount

16,650.00
64,750.00
145,040.00

226,440.00

1,102,739.28

99,246.53
88,219.14
154,824.59
1,445,029.55
7,514.99
Republic of the Philippines
Province of Ilocos Norte
Municipality of Marcos
OFFICE OF THE MUNICIPAL ENGINEER
BILL OF MATERIALS AND DETAILED ESTIMATES
LOCATION Ballesteros Rd., Sitio Bituin, Brgy. Valdez, Marcos, Ilocos Norte
DETAILED ESTIMATE
LENGTH 60.00
Pay Item No. ITEM DESCRIPTION WIDTH 0.40
DEPTH 3.00

a 904 RUBBLE MASONRY VOLUME 290.28 cu.m.

Description Quantity Unit Unit Cost


1. Portland Cement 871 bags 310.00
MATERIALS

2. Screened Gravel 3/4" 29 cu.m. 550.00


3. Screened Clean Sand 87 cu.m. 550.00
4. BOULDERS 290 cu.m. 910.00

Material Direct Cost

Duration
Description (Capacity/Production rate) No. of Units Unit Rate
Day/Hr.
EQUIPMENT

Equipment assumed output /day


1. CONCRETE MIXER - ONE BAGGER 11.00 1 34 1,500.00

Equipment Direct Cost

Duration Rate
Description Number
Day/Hr. day/hr
LABOR

1. CONSTRUCTION FOREMAN 1 34 450.00


2. MASON 4 34 350.00
3. LABORERS 12 34 280.00

Labor Direct Cost

Total Direct Cost


Submitted By: Approved by: PLUS INDIRECT COST
OCM - 9%
CP - 8%
TAXES - 12%

Engr. WARNER A. MACUSI HON. SALVADOR S. PILLOS TOTAL ADJUSTED COST =


Municipal Engineer Municipal Mayor UNIT COST
Republic of the Philippines
Province of Ilocos Norte
Municipality of Marcos
CE OF THE MUNICIPAL ENGINEER
ATERIALS AND DETAILED ESTIMATES

DETAILED ESTIMATE

Amount
269,960.40
15,965.40
47,896.20
264,154.80

597,976.80

Amount

51,000.00

51,000.00

Amount

15,300.00
47,600.00
114,240.00

177,140.00

826,116.80

74,350.51
66,089.34
115,986.80
1,082,543.45
3,729.31
Republic of the Philippines
Province of Ilocos Norte
Municipality of Marcos
OFFICE OF THE MUNICIPAL ENGINEER
BILL OF MATERIALS AND DETAILED ESTIMATES
LOCATION Ballesteros Rd., Sitio Bituin, Brgy. Valdez, Marcos, Ilocos Norte
DETAILED ESTIMATE
LENGTH 15.00
Pay Item No. ITEM DESCRIPTION WIDTH 6.00
DEPTH 1.30

a 905 EMBANKMENT/BACKFILLING VOLUME 540.00 cu.m.

Description Quantity Unit Unit Cost


1. EMBANKMENT MATERIALS 540 cu.m. 300.00
MATERIALS

Material Direct Cost

Duration
Description (Capacity/Production rate) No. of Units Unit Rate
Day/Hr.
EQUIPMENT

Equipment assumed output /day


1. ROAD GRADER 400.00 1 1 16,896.00

Equipment Direct Cost

Duration Rate
Description Number
Day/Hr. day/hr
LABOR

1. CONSTRUCTION FOREMAN 1 10 450.00


2. SKILLED LABORER 1 10 350.00
3. LABORERS 2 10 280.00

Labor Direct Cost

Total Direct Cost


Submitted By: Approved by: PLUS INDIRECT COST
OCM - 9%
CP - 8%
TAXES - 12%

Engr. WARNER A. MACUSI HON. SALVADOR S. PILLOS TOTAL ADJUSTED COST =


Municipal Engineer Municipal Mayor UNIT COST
Republic of the Philippines
Province of Ilocos Norte
Municipality of Marcos
CE OF THE MUNICIPAL ENGINEER
ATERIALS AND DETAILED ESTIMATES

DETAILED ESTIMATE

Amount
162,000.00

162,000.00

Amount

16,896.00

16,896.00

Amount

4,500.00
3,500.00
5,600.00

13,600.00

192,496.00

17,324.64
15,399.68
27,026.44
252,246.76
467.12
Republic of the Philippines
Province of Ilocos Norte
Municipality of Marcos
OFFICE OF THE MUNICIPAL ENGINEER
BILL OF MATERIALS AND DETAILED ESTIMATES
LOCATION Ballesteros Rd., Sitio Bituin, Brgy. Valdez, Marcos, Ilocos Norte
DETAILED ESTIMATE
LENGTH 60.00 - meters
Pay Item No. ITEM DESCRIPTION WIDTH 6.00 - meters
THICKNESS 0.30 - meters

a 200 AGGREGATE SUB-BASE COARSE AREA 108.00 cu.m.

Description Quantity Unit Unit Cost Amount


MATERIALS

Aggregate Sub-Base Coarse 108.00 cu.m. 450.00 48,600.00

Material Direct Cost 48,600.00

Duration
Description (Capacity/Production rate) No. of Units Unit Rate Amount
Day/Hr.
EQUIPMENT

Equipment assumed output /day


1. ROAD GRADER 400.00 1 1 16,896.00 16,896.00

Equipment Direct Cost 16,896.00

Duration Rate
Description Number Amount
Day/Hr. day/hr
1. PROJECT ENGINEER 1 3 500.00 1,500.00
LABOR

2. CONSTRUCTION FOREMAN 1 3 400.00 1,200.00


3. LABORERS 2 3 280.00 1,680.00

Labor Direct Cost 4,380.00

Total Direct Cost 69,876.00


Submitted By: Approved by: PLUS INDIRECT COST
OCM 9% 6,288.84
CP 8% 5,590.08
TAXES 12% 9,810.59
Engr. WARNER A. MACUSI HON. SALVADOR S. PILLOS TOTAL ADJUSTED COST 91,565.51
Municipal Engineer Municipal Mayor UNIT COST 847.83
Republic of the Philippines
Province of Ilocos Norte
Municipality of Marcos
OFFICE OF THE MUNICIPAL ENGINEER
BILL OF MATERIALS AND DETAILED ESTIMATES
LOCATION Ballesteros Rd., Sitio Bituin, Brgy. Valdez, Marcos, Ilocos Norte
DETAILED ESTIMATE
LENGTH 50.00 meters
Pay Item No. ITEM DESCRIPTION WIDTH 4.00 meters
THICKNESS 0.15 meters

a 311 PORTLAND CEMENT CONCRETE PAVEMENT AREA 30.00 cu.m.

Description Quantity Unit Unit Cost


1. Portland Cement 270 bags 310.00
MATERIALS

2. Fine Sand 18 cu. m 550.00


3. Coarse Aggregate 3/4" 30 cu. m 550.00
4. RSB, Dowels/Spikes 76 kgs 72.00
5. Asphalt Sealant 6 li 115.00
6. Channel Bars - 2" x 6" x 2.0mm 12 pcs 1,975.00

Material Direct Cost

Duration
Description (Capacity/Production rate) No. of Units Unit Rate
Day/Hr.
Equipment assumed output /day
EQUIPMENT

1. Concrete Vibrator 1 3 1,500.00


2. Concrete Mixer - One bagger 1 3 1,500.00

Equipment Direct Cost

Duration Rate
Description Number
Day/Hr. day/hr
1. PROJECT ENGINEER 1 3 500.00
LABOR

2. CONSTRUCTION FOREMAN 1 3 400.00


3. MASON 3 3 350.00
4. LABORERS 12 3 280.00

Labor Direct Cost

Total Direct Cost


Submitted By: Approved by: PLUS INDIRECT COST
OCM - 9%
CP - 8%
TAXES - 12%

Engr. WARNER A. MACUSI HON. SALVADOR S. PILLOS TOTAL ADJUSTED COST =


Municipal Engineer Municipal Mayor UNIT COST
Republic of the Philippines
Province of Ilocos Norte
Municipality of Marcos
CE OF THE MUNICIPAL ENGINEER
ATERIALS AND DETAILED ESTIMATES

DETAILED ESTIMATE
meters
meters
meters

Amount
83,700.00
9,900.00
16,500.00
5,472.00
736.00
23,700.00

140,008.00

Amount

4,500.00
4,500.00

9,000.00

Amount

1,500.00
1,200.00
3,150.00
10,080.00

15,930.00

164,938.00

14,844.42
13,195.04
23,157.30
216,134.76
7,204.49
Republic of the Philippines
Province of Ilocos Norte
Municipality of Marcos
OFFICE OF THE MUNICIPAL ENGINEER
BILL OF MATERIALS AND DETAILED ESTIMATES
LOCATION Sitio Hermano, Caburtunga 925 meters 5.80 meters 5,365.00 sq.m.
Sitio Balbalay, ESCODA 925 meters 5.80 meters 5,365.00 sq.m.
Sitio 2, TABUCBUC 1,150 meters 4.80 meters 5,520.00 sq.m.
Sitio BagongBario, SANTIA 1,150 meters 4.80 meters 5,520.00 sq.m.
Brgy. DAQUIOAG 1,150 meters 4.80 meters 5,520.00 sq.m.
Brgy. IMELDA 1,150 meters 4.80 meters 5,520.00 sq.m.
Sitio Danao, MABUTI 460 meters 4.80 meters 2,208.00 sq.m.
Sitio Cabuaan, MABUTI 345 meters 4.80 meters 1,656.00 sq.m.
Brgy. VALDEZ, Ballesteros - meters 4.80 meters - sq.m.
Sitio Cabalayangan, FORT 460 meters 4.80 meters 2,208.00 sq.m.
Sitio Casapangan-Calumbuy 1,150 meters 4.80 meters 5,520.00 sq.m.
Brgy. LYDIA, Municipal Cem 460 meters 4.80 meters 2,208.00 sq.m.
Sitio Cappia, Fortuna 1,150 meters 4.80 meters 5,520.00 sq.m.
TOTAL LENGTH 10,475 meters ### sq.m.

DETAILED ESTIMATE
LENGTH 10,475.00
Pay Item No. ITEM DESCRIPTION
WIDTH 4.95 -

D 105 SUB-GRADE PREPARATION AREA 52,130.00 sq.m.

Description Quantity Unit Unit Cost


MATERIALS

Material Direct Cost =


Duration
Description (Capacity/Production rate) No. of Units Unit Rate
Day/Hr.
Equipment assumed output /day
EQUIPMENT

1. Road Grader 300.00 2,400.00 1 22 16,896.00


2. Water Truck w/ Pump 8,000.00 1 7 9,008.00

Equipment Direct Cost


Duration Rate
Description Number
Day/Hr. day/hr

1.
LABOR

CONSTRUCTION FOREMAN 1 22 400.00


2. LABORERS 2 22 280.00
Labor Direct Cost

Total Direct Cost


Submitted By: Approved by: PLUS INDIRECT COST
OCM - 9%
CP - 8%
TAXES - 5%

Engr. WARNER A. MACUSI HON. SALVADOR S, PILLOS TOTAL ADJUSTED COST =


Municipal Engineer Municipal Mayor UNIT COST
Republic of the Philippines
Province of Ilocos Norte
Municipality of Marcos
OF THE MUNICIPAL ENGINEER
TERIALS AND DETAILED ESTIMATES
57,638.85
57,638.85
59,304.09
59,304.09
59,304.09
59,304.09
23,721.64
17,791.23
-
23,721.64
59,304.09
23,721.64
59,304.09
560,058.41
DETAILED ESTIMATE
meters
meters

Amount

Amount

371,712.00
63,056.00

434,768.00
Amount

8,800.00
12,320.00
21,120.00

455,888.00

41,029.92
36,471.04
26,669.45
560,058.41
10.74
Republic of the Philippines
Province of Ilocos Norte
Municipality of Marcos
OFFICE OF THE MUNICIPAL ENGINEER
BILL OF MATERIALS AND DETAILED ESTIMATES
LOCATION Sitio Hermano, Caburtunga 925 meters 5.60 meters 777.00 cu.m.
Sitio Balbalay, ESCODA 925 meters 5.60 meters 777.00 cu.m.
Sitio 2, TABUCBUC 1,150 meters 4.60 meters 793.50 cu.m.
Sitio BagongBario, SANTI 1,150 meters 4.60 meters 793.50 cu.m.
Brgy. DAQUIOAG 1,150 meters 4.60 meters 793.50 cu.m.
Brgy. IMELDA 1,150 meters 4.60 meters 793.50 cu.m.
Sitio Danao, MABUTI 460 meters 4.60 meters 317.40 cu.m.
Sitio Cabuaan, MABUTI 345 meters 4.60 meters 238.05 cu.m.
Brgy. VALDEZ, Ballesteros - meters 4.60 meters - cu.m.
Sitio Cabalayangan, FORT 460 meters 4.60 meters 317.40 cu.m.
Sitio Casapangan-Calumbu 1,150 meters 4.60 meters 793.50 cu.m.
Brgy. LYDIA, Municipal Ce 460 meters 4.60 meters 317.40 cu.m.
Sitio Cappia, Fortuna 1,150 meters 4.60 meters 793.50 cu.m.
TOTAL LENGTH 10,475 meters 7,505.25 cu.m.

DETAILED ESTIMATE
LENGTH 10,475.00 -
Pay Item No. ITEM DESCRIPTION WIDTH 4.75 -
THICKNESS 0.15 -

D 200 AGGREGATE SUB-BASE COARSE AREA 7,505.25 cu.m.

Description Quantity Unit Unit Cost


MATERIALS

Aggregate Sub-Base Coarse 7,506.00 cu.m. 450.00

Material Direct Cost


Duration
Description (Capacity/Production rate) No. of Units Unit Rate
Day/Hr.
Equipment assumed output /day
EQUIPMENT

1. ROAD GRADER 400.00 1 19 16,709.10


2. VIBRATORY COMPACTOR 1,920.00 1 4 10,554.24
3. WATER TRUCK with PUMP 1,000.00 1 8 5,056.96

Equipment Direct Cost


Duration Rate
Description Number
Day/Hr. day/hr
LABOR

2. CONSTRUCTION FOREMAN 1 19 400.00


3. LABORERS 2 19 280.00
LABOR Labor Direct Cost

Total Direct Cost


Submitted By: Approved by: PLUS INDIRECT COST
OCM 9%
CP 8%
TAXES 5%

Engr. WARNER A. MACUSI HON. SALVADOR S, PILLOS TOTAL ADJUSTED COST


Municipal Engineer Municipal Mayor UNIT COST
Republic of the Philippines
Province of Ilocos Norte
Municipality of Marcos
E OF THE MUNICIPAL ENGINEER
ATERIALS AND DETAILED ESTIMATES
482,799.72
482,799.72
493,052.22
493,052.22
493,052.22
493,052.22
197,220.89
147,915.67
-
197,220.89
493,052.22
197,220.89
493,052.22
4,663,491.09
DETAILED ESTIMATE
meters
meters
meters

Amount

3,377,700.00

3,377,700.00
Amount

317,472.90
42,216.96
40,455.68

400,145.54

Amount

7,600.00
10,640.00
18,240.00

3,796,085.54

341,647.70
303,686.84
222,071.00
4,663,491.09
621.36
Republic of the Philippines
Province of Ilocos Norte
Municipality of Marcos
OFFICE OF THE MUNICIPAL ENGINEER
BILL OF MATERIALS AND DETAILED ESTIMATES
LOCATION Sitio Hermano, Caburtungan 925 meters 5.30 meters 980.50 cu.m.
Sitio Balbalay, ESCODA 925 meters 5.30 meters 980.50 cu.m.
Sitio 2, TABUCBUC 1,150 meters 4.30 meters 989.00 cu.m.
Sitio BagongBario, SANTIA 1,150 meters 4.30 meters 989.00 cu.m.
Brgy. DAQUIOAG 1,150 meters 4.30 meters 989.00 cu.m.
Brgy. IMELDA 1,150 meters 4.30 meters 989.00 cu.m.
Sitio Danao, MABUTI 460 meters 4.30 meters 395.60 cu.m.
Sitio Cabuaan, MABUTI 345 meters 4.30 meters 296.70 cu.m.
Brgy. VALDEZ, Ballesteros - meters 4.30 meters - cu.m.
Sitio Cabalayangan, FORTU 460 meters 4.30 meters 395.60 cu.m.
Sitio Casapangan-Calumbuy 1,150 meters 4.30 meters 989.00 cu.m.
Brgy. LYDIA, Municipal Cem 460 meters 4.30 meters 395.60 cu.m.
Sitio Cappia, Fortuna 1,150 meters 4.30 meters 989.00 cu.m.
TOTAL LENGTH 10,475 meters 9,378.50 cu.m.

DETAILED ESTIMATE
LENGTH 10,475.00 -
Pay Item No. ITEM DESCRIPTION WIDTH 4.45 -
THICKNESS 0.20 -

D 201 AGGREGATE BASE COARSE AREA 9,378.50 cu.m.

Description Quantity Unit Unit Cost


MATERIALS

Aggregate Sub-Base Coarse 9,378.50 cu.m. 450.00

Material Direct Cost


Duration
Description (Capacity/Production rate) No. of Units Unit Rate
Day/Hr.
Equipment assumed output /day
EQUIPMENT

1. ROAD GRADER 400.00 1 24 16,709.10


2. VIBRATORY COMPACTOR 1,920.00 1 5 10,554.24
3. WATER TRUCK with PUMP 1,000.00 1 10 5,056.96

Equipment Direct Cost


Duration Rate
Description Number
Day/Hr. day/hr
LABOR

1. CONSTRUCTION FOREMAN 1 24 400.00


2. LABORERS 2 24 280.00

Labor Direct Cost


Total Direct Cost
Submitted By: Approved by: PLUS INDIRECT COST
OCM - 9%
CP - 8%
TAXES - 5%

Engr. WARNER A. MACUSI HON. SALVADOR S, PILLOS TOTAL ADJUSTED COST =


Municipal Engineer Municipal Mayor UNIT COST
Republic of the Philippines
Province of Ilocos Norte
Municipality of Marcos
E OF THE MUNICIPAL ENGINEER
TERIALS AND DETAILED ESTIMATES
609,782.36
609,782.36
615,068.59
615,068.59
615,068.59
615,068.59
246,027.44
184,520.58
-
246,027.44
615,068.59
246,027.44
615,068.59
5,832,579.18
DETAILED ESTIMATE
meters
meters
meters

Amount

4,220,325.00

4,220,325.00
Amount

401,018.40
52,771.20
50,569.60

504,359.20

Amount

9,600.00
13,440.00

23,040.00
4,747,724.20

427,295.18
379,817.94
277,741.87
5,832,579.18
621.91
Republic of the Philippines
Province of Ilocos Norte
Municipality of Marcos
OFFICE OF THE MUNICIPAL ENGINEER
BILL OF MATERIALS AND DETAILED ESTIMATES
Sitio Hermano, Caburtungan,
LOCATIO Sta Rosa, PACIFICO 925 meters 5.00 meters 693.75 cu.m.

Sitio Balbalay, ESCODA 925 meters 5.00 meters 693.75 cu.m.


Sitio 2, TABUCBUC 1,150 meters 4.00 meters 690.00 cu.m.
Sitio BagongBario, SANTIAGO 1,150 meters 4.00 meters 690.00 cu.m.
Brgy. DAQUIOAG 1,150 meters 4.00 meters 690.00 cu.m.
Brgy. IMELDA 1,150 meters 4.00 meters 690.00 cu.m.
Sitio Danao, MABUTI 460 meters 4.00 meters 276.00 cu.m.
Sitio Cabuaan, MABUTI 345 meters 4.00 meters 207.00 cu.m.
Sitio Cabalayangan, FORTUNA 460 meters 4.00 meters 276.00 cu.m.
Sitio Casapangan-Calumbuyan, L 1,150 meters 4.00 meters 690.00 cu.m.
Brgy. LYDIA, Municipal Cemetery 460 meters 4.00 meters 276.00 cu.m.
Sitio Cappia, Fortuna 1,150 meters 4.00 meters 690.00 cu.m.
TOTAL LENGTH 10,475 meters 6,562.50 cu.m.

DETAILED ESTIMATE
LENGTH 10,475.00
Pay Item
No.
ITEM DESCRIPTION WIDTH 4.15
THICKNESS 0.15

D 311 PORTLAND CEMENT CONCRETE PAVEMENT AREA 6,562.50 cu.m.

Description Quantity Unit Unit Cost


1. Portland Cement 59,063 bags 320.00
MATERIALS

2. Fine Sand 3,938 cu. m 550.00


3. Coarse Aggregate 3/4" 6,563 cu. m 550.00
4. RSB, Dowels/Spikes 16,534 kgs 65.00
5. Asphalt Sealant 1,392 li 115.00
6. Channel Bars - 2" x 6" x 2.0mm 80 pcs 1,975.00

Material Direct Cost


Duration
Description (Capacity/Production rate) No. of Units Unit Rate
Day/Hr.
Equipment assumed output /day
EQUIPMENT

1. Transit Mixer 60.00 3 36 7,668.96


2. Backhoe 60.00 2 36 12,296.00
3. Water Truck w/ Pump 60.00 1 36 5,056.96
4. Concrete Vibrator 60.00 1 36 1,191.04

Equipment Direct Cost


Duration Rate
Description Number
Day/Hr. day/hr
LABOR

1. CONSTRUCTION FOREMAN 1 36 400.00


2. MASON 12 36 350.00
LABOR
3. LABORERS 30 36 280.00

Labor Direct Cost

Total Direct Cost


Submitted By: Approved by: PLUS INDIRECT COST
OCM - 9%
CP - 8%
TAXES - 5%

Engr. WARNER A. MACUSI HON. SALVADOR S, PILLOS TOTAL ADJUSTED COST =


Municipal Engineer Municipal Mayor UNIT COST
Republic of the Philippines
Province of Ilocos Norte
Municipality of Marcos
OF THE MUNICIPAL ENGINEER
ERIALS AND DETAILED ESTIMATES
3,702,013.61

3,702,013.61
3,682,002.72
3,682,002.72
3,682,002.72
3,682,002.72
1,472,801.09
1,104,600.82
1,472,801.09
3,682,002.72
1,472,801.09
3,682,002.72
35,019,047.65

ETAILED ESTIMATE
meters
meters
meters

Amount
18,900,000.00
2,165,900.00
3,609,650.00
1,074,735.00
160,122.46
158,000.00

26,068,407.46

Amount

838,792.50
896,583.33
184,368.33
43,423.33

1,963,167.50

Amount

14,583.33
153,125.00
306,250.00

473,958.33

28,505,533.29

2,565,498.00
2,280,442.66
1,667,573.70
35,019,047.65
5,336.24
Republic of the Philippines
Province of Ilocos Norte
Municipality of Marcos
OFFICE OF THE MUNICIPAL ENGINEER
BILL OF MATERIALS AND DETAILED ESTIMATES
#N/A Sitio Sadiri, Brgy. Daquioag
DETAILED ESTIMATE
LENGTH 1,150.00
Pay Item No. ITEM DESCRIPTION WIDTH 6.00
DEPTH 0.60

b 905 EMBANKMENT/BACKFILLING VOLUME 4,140.00 cu.m.

Description Quantity Unit Unit Cost Amount


1. EMBANKMENT MATERIALS 4,140 cu.m. 400.00 1,656,000.00
MATERIALS

Material Direct Cost 1,656,000.00


Duration
Description (Capacity/Production rate) No. of Units Unit Rate Amount
Day/Hr.
EQUIPMENT

Equipment assumed output /day


1. ROAD GRADER 400.00 1 1 16,896.00 16,896.00

Equipment Direct Cost 16,896.00


Duration Rate
Description Number Amount
Day/Hr. day/hr
LABOR

1. SKILLED LABORER 1 1 350.00 350.00


2. LABORERS 2 1 280.00 560.00

Labor Direct Cost 910.00


Total Direct Cost 1,673,806.00
Submitted By: Approved by: PLUS INDIRECT COST
OCM - 9% 150,642.54
CP - 8% 133,904.48
TAXES - 5% 235,002.36
Engr. WARNER A. MACUSI HON. ARSENIO A. AGUSTIN TOTAL ADJUSTED COST = 2,193,355.38
Municipal Engineer Municipal Mayor UNIT COST 529.80
Republic of the Philippines OME-002-0
Province of Ilocos Norte
Municipality of Marcos
OFFICE OF THE MUNICIPAL ENGINEER
BILL OF MATERIALS AND DETAILED ESTIMATES
LOCATION Sitio Sadiri, Brgy. Daquioag
DETAILED ESTIMATE
LENGTH 60.00 #N/A
Pay Item No. ITEM DESCRIPTION WIDTH 2.50 meters Average
DEPTH 1.00 meters Average
c104 EXCAVATION WORKS AREA 150.00 cu.m.

Description Quantity Unit Unit Cost Amount


MATERIALS

Material Direct Cost = -


Duration
Description (Capacity/Production rate) No. of Units Unit Rate Amount
Day/Hr.
Equipment assumed output /day
EQUIPMENT

1. BACKHOE 200.00 1 3 16,896.00 50,688.00

Equipment Direct Cost 50,688.00


Duration Rate
Description Number Amount
Day/Hr. day/hr
1. PROJECT ENGINEER 1 3 500.00 1,500.00
2.
LABOR

CONSTRUCTION FOREMAN 1 3 400.00 1,200.00


3. LABORERS 2 3 280.00 1,680.00

Labor Direct Cost 4,380.00

Total Direct Cost 55,068.00


Submitted By: Approved by: PLUS INDIRECT COST
OCM - 9% 4,956.12
CP - 8% 4,405.44
TAXES - 12% 7,731.55
Engr. WARNER A. MACUSI #REF! TOTAL ADJUSTED COST = 72,161.11
Municipal Engineer Municipal Mayor UNIT COST 481.07
Republic of the Philippines OME-002-0
Province of Ilocos Norte
Municipality of Marcos
OFFICE OF THE MUNICIPAL ENGINEER
BILL OF MATERIALS AND DETAILED ESTIMATES
LOCATION Sitio Sadiri, Brgy. Daquioag
DETAILED ESTIMATE
LENGTH #N/A
Pay Item No. ITEM DESCRIPTION DEPTH meters
THICKNESS meters

c507 GABION MATTRESS with RUBBLE MASONRY VOLUME 680.00 cu.m.

Description Quantity Unit Unit Cost Amount


Wiremesh 85 rolls 2,250.00 191,250.00
MATERIALS

BOULDERS 680 cu.m. 910.00 618,800.00


FINE SAND 7 cu.m. 550.00 3,740.00
GRAVEL 3/4 11 cu.m. 550.00 6,233.33
PORTLAND CEMENT 68 bags 310.00 21,080.00

Material Direct Cost 841,103.33


Duration
Description (Capacity/Production rate) No. of Units Unit Rate Amount
Day/Hr.
Equipment assumed output /day
EQUIPMENT

1. CONCRETE MIXER - ONE BAGGER 12.00 1 8 1,550.00 12,400.00

Equipment Direct Cost 12,400.00


Duration Rate
Description Number Amount
Day/Hr. day/hr
1. PROJECT ENGINEER 1 31 500.00 15,500.00
LABOR

2. CONSTRUCTION FOREMAN 1 31 400.00 12,400.00


3. SKILLED MASON 4 31 280.00 34,720.00
4. LABORERS 12 31 280.00 104,160.00

Labor Direct Cost 166,780.00

Total Direct Cost 1,020,283.33


Submitted By: Approved by: PLUS INDIRECT COST
OCM 9% 91,825.50
CP 8% 81,622.67
TAXES #N/A 143,247.78
Engr. WARNER A. MACUSI HON. ARSENIO A. AGUSTIN TOTAL ADJUSTED COST 1,336,979.28
Municipal Engineer Municipal Mayor UNIT COST 1,966.15
Republic of the Philippines
Province of Ilocos Norte
Municipality of Marcos
OFFICE OF THE MUNICIPAL ENGINEER
BILL OF MATERIALS AND DETAILED ESTIMATES

LOCATION Sitio Bituen-Calumbuyan, Valdez 350 meters

DETAILED ESTIMATE
LENGTH 350.00 #N/A
Pay Item No. ITEM DESCRIPTION
WIDTH #REF! -

D 105 SUB-GRADE PREPARATION AREA #REF! sq.m.

Description Quantity Unit Unit Cost


MATERIALS

Material Direct Cost =


Duration
Description (Capacity/Production rate) No. of Units Unit Rate
Day/Hr.
Equipment assumed output /day
EQUIPMENT

1. Road Grader 300.00 2,400.00 1 1 16,896.00


2. VIBRATORY COMPACTOR 2,400.00 1 1 #N/A
2. Water Truck w/ Pump 1,000.00 1 1 9,008.00

Equipment Direct Cost


Duration Rate
Description Number
Day/Hr. day/hr
LABOR

1. CONSTRUCTION FOREMAN 1 1 400.00


2. LABORERS 2 1 280.00

Labor Direct Cost

Total Direct Cost


Submitted By: Approved by: PLUS INDIRECT COST
OCM - 9%
CP - 8%
TAXES - 12%

Engr. WARNER A. MACUSI #REF! TOTAL ADJUSTED COST =


Municipal Engineer Municipal Mayor UNIT COST
Republic of the Philippines
Province of Ilocos Norte
Municipality of Marcos
E OF THE MUNICIPAL ENGINEER
ATERIALS AND DETAILED ESTIMATES

DETAILED ESTIMATE
meters
meters

Amount

Amount

16,896.00

9,008.00

25,904.00

Amount

400.00
560.00

960.00

26,864.00

2,417.76
2,149.12
3,771.71
35,202.59
#REF!
Republic of the Philippines
Province of Ilocos Norte
Municipality of Marcos
OFFICE OF THE MUNICIPAL ENGINEER
BILL OF MATERIALS AND DETAILED ESTIMATES
LOCATION Sitio Bituen-Calumbuyan, Valdez 350 meters

DETAILED ESTIMATE
LENGTH 350.00 #N/A
Pay Item No. ITEM DESCRIPTION WIDTH #REF! -
THICKNESS 0.15 -

D 200 AGGREGATE SUB-BASE COARSE VOLUME #REF! cu.m.

Description Quantity Unit Unit Cost


MATERIALS

Aggregate Sub-Base Coarse #REF! cu.m. 400.00

Material Direct Cost


Duration
Description (Capacity/Production rate) No. of Units Unit Rate
Day/Hr.
Equipment assumed output /day
EQUIPMENT

1. ROAD GRADER 400.00 1 1 #N/A


2. VIBRATORY COMPACTOR 576.00 1 1 11,770.32
3. WATER TRUCK with PUMP 1,000.00 1 1 #N/A

Equipment Direct Cost


Duration Rate
Description Number
Day/Hr. day/hr
LABOR

2. CONSTRUCTION FOREMAN 1 1 400.00


3. LABORERS 2 1 280.00

Labor Direct Cost

Total Direct Cost


Submitted By: Approved by: PLUS INDIRECT COST
OCM 9%
CP 8%
TAXES 5%

Engr. WARNER A. MACUSI HON. ARSENIO A. AGUSTIN TOTAL ADJUSTED COST


Municipal Engineer Municipal Mayor UNIT COST
Republic of the Philippines
Province of Ilocos Norte
Municipality of Marcos
CE OF THE MUNICIPAL ENGINEER
MATERIALS AND DETAILED ESTIMATES

DETAILED ESTIMATE
meters
meters
meters

Amount

#REF!

#REF!

Amount

#N/A
11,770.32

#N/A
Amount

400.00
560.00

960.00

#N/A

#N/A
#N/A
#N/A
#N/A
#N/A
Republic of the Philippines
Province of Ilocos Norte
Municipality of Marcos
OFFICE OF THE MUNICIPAL ENGINEER
BILL OF MATERIALS AND DETAILED ESTIMATES

LOCATION Sitio Bituen-Calumbuyan, Valdez 350 meters

DETAILED ESTIMATE
LENGTH 350.00 #N/A
Pay Item No. ITEM DESCRIPTION WIDTH #REF! -
THICKNESS 0.15 -

D 201 AGGREGATE BASE COARSE VOLUME #REF! cu.m.

Description Quantity Unit Unit Cost


MATERIALS

Aggregate Sub-Base Coarse #REF! cu.m. 400.00

Material Direct Cost


Duration
Description (Capacity/Production rate) No. of Units Unit Rate
Day/Hr.
Equipment assumed output /day
EQUIPMENT

1. ROAD GRADER 400.00 1 1 #N/A


2. VIBRATORY COMPACTOR 576.00 1 1
3. WATER TRUCK with PUMP 1,000.00 1 1

Equipment Direct Cost


Duration Rate
Description Number
Day/Hr. day/hr
LABOR

1. CONSTRUCTION FOREMAN 1 1 400.00


2. LABORERS 2 1 280.00

Labor Direct Cost

Total Direct Cost


Submitted By: Approved by: PLUS INDIRECT COST
OCM - 9%
CP - 8%
TAXES - 5%

Engr. WARNER A. MACUSI #REF! TOTAL ADJUSTED COST =


Municipal Engineer Municipal Mayor UNIT COST
Republic of the Philippines
Province of Ilocos Norte
Municipality of Marcos
CE OF THE MUNICIPAL ENGINEER
ATERIALS AND DETAILED ESTIMATES

DETAILED ESTIMATE
meters
meters
meters

Amount

#REF!

#REF!

Amount

#N/A

#N/A
Amount

400.00
560.00

960.00

#N/A

#N/A
#N/A
#N/A
#N/A
#N/A
Republic of the Philippines
Province of Ilocos Norte
Municipality of Marcos
OFFICE OF THE MUNICIPAL ENGINEER
BILL OF MATERIALS AND DETAILED ESTIMATES

LOCATION Sitio Bituen-Calumbuyan, Valdez 180 meters

DETAILED ESTIMATE
LENGTH 200.00 #REF! meters
Pay Item No. ITEM DESCRIPTION WIDTH #REF! meters
THICKNESS meters
d 311 PORTLAND CEMENT CONCRETE PAVEMENT AREA #REF! cu.m.

Description Quantity Unit Unit Cost Amount


1. Portland Cement #REF! bags 310.00 #REF!
MATERIALS

2. Fine Sand #REF! cu. m 550.00 #REF!


3. Coarse Aggregate 3/4" #REF! cu. m 550.00 #REF!
4. RSB, Dowels/Spikes #REF! kgs 72.00 #REF!
5. Asphalt Sealant #REF! li 115.00 #REF!
6. Channel Bars - 2" x 6" x 2.0mm 12 pcs 1,975.00 23,700.00

Material Direct Cost #REF!


Duration
Description (Capacity/Production rate) No. of Units Unit Rate Amount
Day/Hr.
Equipment assumed output /day
EQUIPMENT

1. Concrete Vibrator 1 6 1,500.00 9,000.00


2. Concrete Mixer - One bagger 1 6 1,500.00 9,000.00

Equipment Direct Cost 18,000.00


Duration Rate
Description Number Amount
Day/Hr. day/hr
1. PROJECT ENGINEER 1 6 500.00 3,000.00
LABOR

2. CONSTRUCTION FOREMAN 1 6 400.00 2,400.00


3. MASON 3 6 350.00 6,300.00
4. LABORERS 8 6 280.00 13,440.00

Labor Direct Cost 25,140.00

Total Direct Cost #REF!


Submitted By: Approved by: PLUS INDIRECT COST
OCM - 9% #REF!
CP - 8% #REF!
TAXES - 12% #REF!
Engr. WARNER A. MACUSI #REF! TOTAL ADJUSTED COST = #REF!
Municipal Engineer Municipal Mayor UNIT COST #REF!
Republic of the Philippines
Province of Ilocos Norte
Municipality of Marcos
OFFICE OF THE MUNICIPAL ENGINEER
BILL OF MATERIALS AND DETAILED ESTIMATES
#N/A Sitio Bituen-Calumbuyan, Valdez

DETAILED ESTIMATE
LENGTH 100.00
Pay Item No. ITEM DESCRIPTION WIDTH 6.00
DEPTH 0.80

d 905 EMBANKMENT/BACKFILLING VOLUME 480.00 cu.m.

Description Quantity Unit Unit Cost Amount


1. EMBANKMENT MATERIALS 480 cu.m. 300.00 144,000.00
MATERIALS

Material Direct Cost 144,000.00


Duration
Description (Capacity/Production rate) No. of Units Unit Rate Amount
Day/Hr.
EQUIPMENT

Equipment assumed output /day


1. ROAD GRADER 400.00 1 1 #N/A #N/A

Equipment Direct Cost #N/A


Duration Rate
Description Number Amount
Day/Hr. day/hr
1.
LABOR

CONSTRUCTION FOREMAN 1 1 450.00 450.00


2. SKILLED LABORER 1 1 350.00 350.00
3. LABORERS 2 1 280.00 560.00

Labor Direct Cost 1,360.00


Total Direct Cost #N/A
Submitted By: Approved by: PLUS INDIRECT COST
OCM - 9% #N/A
CP - 8% #N/A
TAXES - 12% #N/A
Engr. WARNER A. MACUSI #REF! TOTAL ADJUSTED COST = #N/A
Municipal Engineer Municipal Mayor UNIT COST #N/A
Republic of the Philippines
OME-14 - 001
Province of Ilocos Norte
Municipality of Marcos
OFFICE OF THE MUNICIPAL ENGINEER
BILL OF MATERIALS AND DETAILED ESTIMATES
#N/A Sitio Namnama, Brgy. Imelda
DETAILED ESTIMATE BRIDGE WINGWALL
LENGTH 15.00 3.00 meters
Pay Item No. ITEM DESCRIPTION WIDTH 4.00 0.20 meters
DEPTH 2.80 3.00 meters

d 103 STRUCTURE EXCAVATION AREA 159.40 cu.m.

Description Quantity Unit Unit Cost Amount


MATERIALS

Material Direct Cost -


Duration
Description (Capacity/Production rate) No. of Units Unit Rate Amount
Day/Hr.
EQUIPMENT

Equipment assumed output /day


1. Backhoe 60.00 1 2 9,646.16 19,292.32

Equipment Direct Cost 19,292.32


Duration Rate
Description Number Amount
Day/Hr. day/hr
LABOR

1. CONSTRUCTION FOREMAN 1 2 450.00 900.00


2. SKILLED CONSTRUCTION WORKER 1 2 350.00 700.00
3. LABORERS 2 2 280.00 1,120.00

Labor Direct Cost 2,720.00


Total Direct Cost 22,012.32
Submitted By: Approved by: PLUS INDIRECT COST
OCM - 9% 1,981.11
CP - 8% 1,760.99
TAXES - 12% 3,090.53
Engr. WARNER A. MACUSI #REF! TOTAL ADJUSTED COST = 28,844.94
Municipal Engineer Municipal Mayor UNIT COST 180.96
Republic of the Philippines
Province of Ilocos Norte
Municipality of Marcos
OFFICE OF THE MUNICIPAL ENGINEER
BILL OF MATERIALS AND DETAILED ESTIMATES
#N/A Sitio Namnama, Brgy. Imelda
DETAILED ESTIMATE
LENGTH #REF! #N/A meters
Pay Item No. ITEM DESCRIPTION WIDTH 6.00 - meters
THICKNESS 0.20 - meters

d 200 AGGREGATE SUB-BASE COARSE AREA #REF! cu.m.

Description Quantity Unit Unit Cost Amount


MATERIALS

Aggregate Sub-Base Coarse #REF! cu.m. 350.00 #REF!

Material Direct Cost #REF!


Duration
Description (Capacity/Production rate) No. of Units Unit Rate Amount
Day/Hr.
EQUIPMENT

Equipment assumed output /day


1. ROAD GRADER 400.00 1 1 #N/A #N/A

Equipment Direct Cost #N/A


Duration Rate
Description Number Amount
Day/Hr. day/hr
1. PROJECT ENGINEER 1 1 500.00 500.00
LABOR

2. CONSTRUCTION FOREMAN 1 1 400.00 400.00


3. LABORERS 2 1 280.00 560.00

Labor Direct Cost 1,460.00


Total Direct Cost #N/A
Submitted By: Approved by: PLUS INDIRECT COST
OCM 9% #N/A
CP 8% #N/A
TAXES 12% #N/A
Engr. WARNER A. MACUSI HON. ARSENIO A. AGUSTIN TOTAL ADJUSTED COST #N/A
Municipal Engineer Municipal Mayor UNIT COST #N/A
Republic of the Philippines
Province of Ilocos Norte
Municipality of Marcos
OFFICE OF THE MUNICIPAL ENGINEER
BILL OF MATERIALS AND DETAILED ESTIMATES
#N/A Sitio Namnama, Brgy. Imelda
DETAILED ESTIMATE

Pay Item No. ITEM DESCRIPTION

d 900 FORMWORKS VOLUME 780.00 bd.ft.

Description Quantity Unit Unit Cost Amount


1. 2" X 2" X 12' Form Lumber 20 80 bd.ft. 60.00 4,800.00
MATERIALS

2. 2" X 3" X 12' Form Lumber 50 300 bd.ft. 60.00 18,000.00


3. 2" X 4" X 12' Form Lumber 50 400 bd.ft. 60.00 24,000.00
4. Plywood 1/2" 16 pcs 900.00 14,400.00
5. CWN 4" 2 keg 1,300.00 2,600.00
6. CWN 3" 2 keg 1,300.00 2,600.00
7 CWN 2" / 1-1/2" 1 keg 1,400.00 1,400.00
Material Direct Cost 67,800.00
Duration
Description (Capacity/Production rate) No. of Units Unit Rate Amount
Day/Hr.
EQUIPMENT

Equipment assumed output /day

Equipment Direct Cost -


Duration Rate
Description Number Amount
Day/Hr. day/hr
LABOR

1. CONSTRUCTION FOREMAN 1 4 450.00 1,800.00


2. SKILLED CARPENTER 5 4 350.00 7,000.00
3. LABORERS 5 4 280.00 5,600.00

Labor Direct Cost 14,400.00


Total Direct Cost 82,200.00
Submitted By: Approved by: PLUS INDIRECT COST
OCM - 9% 7,398.00
CP - 8% 6,576.00
TAXES - 12% 11,540.88
Engr. WARNER A. MACUSI #REF! TOTAL ADJUSTED COST = 107,714.88
Municipal Engineer Municipal Mayor UNIT COST 138.10
Republic of the Philippines
Province of Ilocos Norte
Municipality of Marcos
OFFICE OF THE MUNICIPAL ENGINEER
BILL OF MATERIALS AND DETAILED ESTIMATES
#N/A Sitio Namnama, Brgy. Imelda
DETAILED ESTIMATE
LENGTH 6.00 6.00 meters
Pay Item No. ITEM DESCRIPTION WIDTH 3.00 3.00 meters
DEPTH 3.00 3.00 meters

d 901 REINFORCING STEEL BARS WEIGHT #REF! kgs

Description Quantity Unit Unit Cost Amount


MATERIALS

1. 20 mm x 6.0 RSB #REF! kgs 58.00 #REF!


2. 16 mm x 6.0 RSB #REF! kgs 58.00 #REF!
3. 12 mm x 6.0 RSB #REF! kgs 58.00 #REF!
4. #16 Tie Wire 4 rolls 4,200.00 16,800.00

Material Direct Cost #REF!


Duration
Description (Capacity/Production rate) No. of Units Unit Rate Amount
Day/Hr.
EQUIPMENT

Equipment assumed output /day


1. Bar Cutter 250.00 1 12 500.00 6,000.00

Equipment Direct Cost 6,000.00


Duration Rate
Description Number Amount
Day/Hr. day/hr
1.
LABOR

CONSTRUCTION FOREMAN 1 12 450.00 5,400.00


2. STEELMAN 4 12 350.00 16,800.00
3. LABORERS 9 12 280.00 30,240.00

Labor Direct Cost 52,440.00


Total Direct Cost #REF!
Submitted By: Approved by: PLUS INDIRECT COST
OCM - 9% #REF!
CP - 8% #REF!
TAXES - 12% #REF!
Engr. WARNER A. MACUSI #REF! TOTAL ADJUSTED COST = #REF!
Municipal Engineer Municipal Mayor UNIT COST #REF!
Republic of the Philippines
Province of Ilocos Norte
Municipality of Marcos
OFFICE OF THE MUNICIPAL ENGINEER
BILL OF MATERIALS AND DETAILED ESTIMATES
#N/A Sitio Namnama, Brgy. Imelda
DETAILED ESTIMATE

Pay Item No. ITEM DESCRIPTION

d 902 CONCRETE ( 3000 psi ) VOLUME 51.81 cu.m.

Description Quantity Unit Unit Cost Amount


1. Portland Cement 518 bags 310.00 160,618.75
MATERIALS

2. Screened Gravel 3/4" 52 cu.m. 550.00 28,496.88


3. Screened Clean Sand 31 cu.m. 550.00 17,098.13

Material Direct Cost 206,213.75


Duration
Description (Capacity/Production rate) No. of Units Unit Rate Amount
Day/Hr.
EQUIPMENT

Equipment assumed output /day


1. CONCRETE MIXER - ONE BAGGER 1 12 1,500.00 18,000.00
CONCRETE VIBRATOR 1 12 1,500.00 18,000.00

Equipment Direct Cost 36,000.00


Duration Rate
Description Number Amount
Day/Hr. day/hr
LABOR

1. CONSTRUCTION FOREMAN 1 12 450.00 5,400.00


2. MASON 5 12 350.00 21,000.00
3. LABORERS 12 12 280.00 40,320.00

Labor Direct Cost 66,720.00


Total Direct Cost 308,933.75
Submitted By: Approved by: PLUS INDIRECT COST

OCM - 9%
27,804.04
CP - 8% 24,714.70
TAXES - 12% 43,374.30
Engr. WARNER A. MACUSI #REF! TOTAL ADJUSTED COST = 404,826.79
Municipal Engineer Municipal Mayor UNIT COST 7,813.30
Republic of the Philippines
Province of Ilocos Norte
Municipality of Marcos
OFFICE OF THE MUNICIPAL ENGINEER
BILL OF MATERIALS AND DETAILED ESTIMATES
#N/A Sitio Namnama, Brgy. Imelda
DETAILED ESTIMATE
LENGTH 16.00
Pay Item No. ITEM DESCRIPTION WIDTH 0.50
DEPTH 3.00

d 904 RUBBLE MASONRY VOLUME 33.60 cu.m.

Description Quantity Unit Unit Cost Amount


1. Portland Cement 101 bags 310.00 31,248.00
MATERIALS

2. Screened Gravel 3/4" 3 cu.m. 550.00 1,848.00


3. Screened Clean Sand 10 cu.m. 550.00 5,544.00
4. BOULDERS 34 cu.m. 910.00 30,576.00

Material Direct Cost 69,216.00


Duration
Description (Capacity/Production rate) No. of Units Unit Rate Amount
Day/Hr.
EQUIPMENT

Equipment assumed output /day


1. CONCRETE MIXER - ONE BAGGER 11.00 1 4 1,500.00 6,000.00

Equipment Direct Cost 6,000.00


Duration Rate
Description Number Amount
Day/Hr. day/hr
LABOR

1. CONSTRUCTION FOREMAN 1 4 450.00 1,800.00


2. MASON 4 4 350.00 5,600.00
3. LABORERS 12 4 280.00 13,440.00

Labor Direct Cost 20,840.00


Total Direct Cost 96,056.00
Submitted By: Approved by: PLUS INDIRECT COST
OCM - 9% 8,645.04
CP - 8% 7,684.48
TAXES - 12% 13,486.26
Engr. WARNER A. MACUSI #REF! TOTAL ADJUSTED COST = 125,871.78
Municipal Engineer Municipal Mayor UNIT COST 3,746.18
Equipment Capabilty
Output
Item Description Equipment Unit
Min. Max
100 Clearing and Grubbing Bulldozer 3200 4000 sq.m./day
Excavation Bulldozer 200 cu.m./day
102
Compaction Road Roller 240 320 cu.m./day
Embankment Payloader 240 320 cu.m./day
104 Compaction Road Roller 240 320 cu.m./day
Quarrying Bulldozer 400 cu.m./day
Sub-grade Preparation Grader 2400 sq.m./day
105 Road Roller 1600 sq.m./day
Compaction Road Roller 240 320 cu.m./day
Agg. Sub-Base Course Grader 2400 sq.m./day
200/201 Road Roller 240 320 cu.m./day
Water Truck 8000 sq.m./day

STANDARD EQUIPMENT CAPABILITY ESTIMATES

Bulldozer Clearing 500 sq.m./hr 4000 sq.m./day


Stripping 200 sq.m./hr 1600 sq.m./day
Quarrying 50 sq.m./hr 400 sq.m./day
Excavation 25 sq.m./hr 200 sq.m./day
Pushing 3 cu.m./hr 24 cu.m./day
Grader Sub-grading 300 sq.m./hr 2400 sq.m./day
Spreading 50 cu.m./hr 400 cu.m./day
Pay Loader Loading 30 cu.m./hr 240 cu.m./day
Crane Shovel Loading 35 cu.m./hr 280 cu.m./day
Backhoe Loading 30 cu.m./hr 240 cu.m./day
Sheep Foot Roller Static Rolling (12 passes-15 cm 45 cu.m./hr 360 cu.m./day
Vibratory Rolling (4 passes-15 cm li 135 cu.m./hr 280 cu.m./day
No. 3 Road Static Rolling (6 passes-15 cm
24 cu.m./hr 192 cu.m./day
Roller lift)
Tractor-drawn Vibratory Rolling (6 passes 2 cu.m./hr cu.m./day
240 1920
Roller (1-D) cm lift) cu.m./hr cu.m./day
Static Rolling 96 passes-20 cm
Tander Roller 24 cu.m./hr 192 cu.m./day
lift)
5-T Dump truck Hauling Common Borrow 3.5 cu.m./hr 28 cu.m./day
Hauling SEBC (Selected borrow,
5 cu.m./trip
basecourse)
Hauling Concrete batch class A 3 batch/trip
2 DT Hauling Common Borrow 2.5 cu.m./trip
Hauling SEBC (Selected borrow, cu.m./trip
2
basecourse) cu.m./trip
Hauling Concrete batch class A 2 batch/trip
1-Bagger Mixer Mixing concrete 3 cu.m./hr 24 cu.m./day
165 Conc. Mixer Mixing concrete 9 cu.m./hr 72 cu.m./day
Water Truck Watering 1000 sq.m./hr 8000 sq.m./day
Rock Crusher Crushing mixed sand and gravel 30 cu.m./hr 240 cu.m./day
Conc. Vibrator Vibrating concrete mix 40 cu.m./hr 320 cu.m./day
Percussion Drilling hard rock 0.75 f/hr
Drilling loose rock 1 f/hr
Drilling lime stone 1.25 f/hr
Drilling sticky clay 1.6 f/hr
Drilling loose clay 2.5 f/hr
Bar Cutter 444 kg./day
TIME AND MOTION STUDY
Item 102 (2): Surplus Excavation
Item 103 (3): Structure Excavation
Item 103 (6): Pipe Culvert & Drain Excavation

Dump Trucks Dump Trucks


Average Distance of Overhaul 1.00 Kms. Average Distance of Overhau
Speed Empty 25.00 Km. per Hour Speed Empty
Speed Loaded 20.00 Km. per hour Speed Loaded
Time of Travel Empty 2.40 minutes Time of Travel Empty
Time of Travel Loaded 3.00 minutes Time of Travel Loaded
Manuevering, Loading,Spot Manuevering, Loading,Spot
and Unloading Time 17.00 minutes and Unloading Time
Total Time 22.40 minutes Total Time
No of Trips per DT/day 19.00 No of Trips per DT/day
Capacity of DT 10.00 cu.m. Capacity of DT
Volume hauled per DT/day 190.00 cu.m Volume hauled per DT/day

Dump Trucks Dump Trucks


Average Distance of Overhaul 2.00 Kms. Average Distance of Overhau
Speed Empty 25.00 Km. per Hour Speed Empty
Speed Loaded 20.00 Km. per hour Speed Loaded
Time of Travel Empty 4.80 minutes Time of Travel Empty
Time of Travel Loaded 6.00 minutes Time of Travel Loaded
Manuevering, Loading,Spot Manuevering, Loading,Spot
and Unloading Time 17.00 minutes and Unloading Time
Total Time 27.80 minutes Total Time
No of Trips per DT/day 16.00 No of Trips per DT/day
Capacity of DT 10.00 cu.m. Capacity of DT
Volume hauled per DT/day 160.00 cu.m Volume hauled per DT/day

Dump Trucks Transit Mixer


Average Distance of Overhaul 3.00 Kms. Average Distance of Overhau
Speed Empty 25.00 Km. per Hour Speed Empty
Speed Loaded 20.00 Km. per hour Speed Loaded
Time of Travel Empty 7.20 minutes Time of Travel Empty
Time of Travel Loaded 9.00 minutes Time of Travel Loaded
Manuevering, Loading,Spot Manuevering, Loading,Spot
and Unloading Time 17.00 minutes and Unloading Time
Total Time 33.20 minutes Total Time
No of Trips per DT/day 13.00 No of Trips per TM/day
Capacity of DT 10.00 cu.m. Capacity of Transit Mixer
Volume hauled per DT/day 130.00 cu.m Volume hauled per TM/day

Average Speed of Dump Truck (Kilometer per hour)


Haul dist. Good Poor Haul dist. Good Poor
Km. Maintained Maintained Km. Maintained Maintained
Road Road Road Road
0.3 18 13 11 46 30.5
0.4 19 14 12 47 31
0.5 20 15 13 48 31.5
0.6 21 16 14 49 32
0.7 22 17 15 50 32.5
0.8 23 18 16 51 33
0.9 24 19 17 52 33.5
1 25 20 18 53 34
2 27 21 19 54 34.5
3 30 22 20 55 35
4 32 23 21 55 35
5 35 25 22 55 35
6 37 26 23 same speed same speed
7 39 27 24 to all to all
8 41 28 24 succeeding succeeding
9 43 29 26 haul distance haul distance
10 45 30 27
4.00 Kms.
30.00 Km. per Hour
25.00 Km. per hour
8.00 minutes
9.60 minutes
Manuevering, Loading,Spot
17.00 minutes
34.60 minutes
12.00
10.00 cu.m.
120.00 cu.m

5.00 Kms.
45.00 Km. per Hour
35.00 Km. per hour
6.67 minutes
8.57 minutes
Manuevering, Loading,Spot
17.00 minutes
32.24 minutes
13.00
10.00 cu.m.
130.00 cu.m

4.00 Kms.
35.00 Km. per Hour
30.00 Km. per hour
6.86 minutes
8.00 minutes
Manuevering, Loading,Spot
20.00 minutes
34.86 minutes
12.00
5.00 cu.m.
60.00 cu.m
Project Title: REHABILITATION
OF SMALL WATER IMPOUNDING PROJECT with CANALIZATION
Location: Brgy. TABUCBUC, Marcos, Ilocos Norte

DETAILED ESTIMATE

Item No.: TOPOGRAPHIC SURVEY AND MAP


Description: SURVEYING and MAPPING
Unit: hectares
Quantity: 15.00 has.
Item Duration: 11 days

Description Quantity Unit

Topographic Surveying of Project Site with 15.00 has


MATERIALS

Autocadd drafted TOPOGRAPHIC MAP

SUB TOTAL
Duration
Description No. of Units
Day/Hr.
EQUIPMENT

SUB TOTAL
Duration
Description No.
Day/Hr.
LABOR

SUB TOTAL
TOTAL DIRECT COST
Contractor's Profit 0.00% of Direct Cost
Overhead, Contingencies, & Miscellaneous 0.00% of Direct Cost
TOTAL INDIRECT COST
TOTAL ( Direct Cost + Indirect Cost )
Value Added Tax ( VAT ) 0.00% of Direct & Indirect Cost
TOTAL ITEM COST (PhP)
COST PER
Prepared by: Approved by:

ENGR. WARNER A. MACUSI HON. ARSENIO A. AGUSTIN


Municipal Engineer Municipal Mayor
OME - 002 - 0
CT with CANALIZATION

Unit Cost Amount

6,600.00 99,000.00
-
-

SUB TOTAL 99,000.00

Unit Rate Amount

SUB TOTAL -
Rate
Amount
Day/hr

- -
- -

SUB TOTAL -
TOTAL DIRECT COST 99,000.00
of Direct Cost -
of Direct Cost -
TOTAL INDIRECT COST -
Cost + Indirect Cost ) 99,000.00
of Direct & Indirect Cost -
99,000.00
6,600.00

HON. ARSENIO A. AGUSTIN


Municipal Mayor
Concrete Works MAIN CANAL SC-1 HEIGHT 0.8
Length= 200 860 WIDTH 0.6
WIDTH = 0.4 0.3
THICK = 0.125 0.1
DEPTH= 0.75 0.55
Cross-Sectional Area= 47.5 120.4 THICK 0.15
Volume= 167.90 cu.m

CEMENT = 1,512.00 bags 320.00 483,840.00


SAND = 84.00 cu.m 550.00 46,200.00
GRAVEL = 168.00 cu.m 550.00 92,400.00
622,440.00

unit day rate


ONE BAGGER MIXER = 1.00 42.00 1,376.00 57,792.00
57,792.00
Formworks
FOREMAN = 1.00 42.00 -
CARPENTER = 4.00 42.00 -
LABORER(s) = 8.00 42.00 -
-
Concrete
FOREMAN = 1.00 42.00 450.00 18,900.00
MASON = 4.00 42.00 400.00 67,200.00
LABORER(s) = 12.00 42.00 300.00 151,200.00
237,300.00

TOTAL DIRECT COST 917,532.00


OCM 12.00% 110,103.84
PROFIT 10.00% 91,753.20

TOTAL INDIRECT COST = 201,857.04


(13,246.87) VAT 5.00% 55,969.45

TOTAL ADJUSTED COST 1,175,358.49


UNIT COST 7,000.35

MAIN CANAL (60X40) 200 2,073.53 208.62% 414,706.11


SECONDARY (40X30) 860 2,073.53 20.52% 1,783,236.26
Length 1060 229.14%

2,216,908.85 2,200,000.00 2,197,942.36


(16,908.85) 2,130,297.88

cu.m

REINFORCED CONCRETE PIPE CULVERT


No. of pcs= 8.00 pcs. Volume = 25.5

Excavation Works
Equipment Units Days Rate/Day
Backhoe (0.80) = 1.00 ### 11,621.00 11,621.00
Dumptruck (3.00) = 1.00 ### 10,141.00 10,141.00
21,762.00
Labor
Foreman = 1.00 ### 450.00 450.00
Backhoe Operator = 1.00 ### 350.00 350.00
Dumptruck Driver = 1.00 ### 350.00 350.00
Helper(s) = 2.00 1.00 250.00 500.00
1,650.00

TOTAL DIRECT COST 23,412.00


12.00% 2,809.44
10.00% 2,341.20

TOTAL INDIRECT COST = 5,150.64


5.00% 1,428.13

TOTAL ADJUSTED COST 29,990.77


UNIT COST 1,176.11
R.C. Pipe Laying
Materials
Cement = 15.00 bags 310.00 4,650.00
Sand = 2.00 cu.m 550.00 1,100.00
910mm dia. RC Pipe = 8.00 L.M. 4,000.00 32,000.00
37,750.00

Labor
Foreman 1.00 3.00 450.00 1,350.00
Mason 2.00 3.00 350.00 2,100.00
Laborer 4.00 3.00 250.00 3,000.00
6,450.00

TOTAL DIRECT COST 44,200.00


OCM 12.00% 5,304.00
PROFIT 10.00% 4,420.00

TOTAL INDIRECT COST = 9,724.00


VAT 5.00% 2,696.20

TOTAL ADJUSTED COST 56,620.20


UNIT COST 7,077.53
Reinforcement WorksMAIN C. LENGTH= LM
Longitudinal Bars (10mm) 200 860
No. of Long. Bars = 7 5 KGS
No. of pcs. Per Long. Bar = 35 149
REQUIRED = 245 745 kgs
kgs 3.696 3.696
BAR WEIGHT. 905.52 2,753.52
Transverse Bars (12mm)
T.length of Transverse Bars = 2.00 1.50 SPACING =
Total No. of pcs in one 6m = 3.00 4.00
Spacing= 0.20 0.20
REQUIRED cut bars= 1000.00 4300.00
reqd qty = 334.00 1075.00 kgs
BAR WEIGHT. ### 3,973.20
#16 G.I. Tie Wire
Total No. of Cross = 7007 21505
Total No. = 162.00 kgs. 5,207.66 kgs

10mm RSB = 2399.00 pcs 160.00 383,840.00

#16 GI Tie Wire = 162.00 pcs 115.00 18,630.00


402,470.00
unit day rate
Bar Cutter = 1.00 18.00 1,758.00 31,644.00

31,644.00

Foreman = 1.00 27.00 450.00 12,150.00


Steelman = 4.00 27.00 400.00 43,200.00
Laborer = 4.00 27.00 300.00 32,400.00
87,750.00
TOTAL DIRECT COST 521,864.00
OCM 12.00% 62,623.68
4,585,293.89 PROFIT 10.00% 52,186.40
451,090.74
TOTAL INDIRECT COST 114,810.08
VAT 5.00% 31,833.70

TOTAL ADJUSTED COST 668,507.78


UNIT COST 128.37
Formworks 360.00 BD.FT Structure Excavation
MAIN
Ordinary Plywood1/2" = 10.00 pcs 850.00 8,500.00 DEPTH = 0.20
Lumber = 360.00 bd.ft 62.00 22,320.00 WIDHT = 0.75
Assorted CWN = 36.00 kgs 130.00 4,680.00 LENGTH = 200.00
35,500.00 Volume = 30.00
TOTAL VOLUME = 116.00
Foreman = 1.00 42.00 450.00 18,900.00
Carpenter = 3.00 42.00 400.00 50,400.00 Foreman = 1.00
Laborer(s) = 3.00 42.00 300.00 37,800.00 Laborer = 12.00
107,100.00

TOTAL DIRECT COST 142,600.00


OCM 12.00% 17,112.00
PROFIT 10.00% 14,260.00

TOTAL INDIRECT COST 31,372.00 TOTAL INDIRECT COST


VAT 5.00% 8,698.60

TOTAL ADJUSTED COST 182,670.60 TOTAL ADJUSTED COST


UNIT COST 507.42

LUMBER - 2X2X12 30 pcs 120 bd.ft


LUMBER - 2X3X12 40 pcs 240 bd.ft
360
SC-1
0.2 sq.m
0.5
860
86.00 cu.m

20.00 450.0 9,000.00


20.00 300.0 72,000.00
81,000.00

TOTAL DIRECT COST 81,000.00


OCM 12.00% 9,720.00
PROFIT 10.00% 8,100.00

TOTAL INDIRECT COST 17,820.00


VAT 5.00% 4,941.00

TOTAL ADJUSTED COST ###


UNIT COST 3,458.70
2009 ACEL RATES
(Minimum Operation = 8 hrs. per day)

Bare Rental
No. Name & Capacity Description
Hourly Rate Daily Rate
1 Air Compressor 86-125 cfm/42Hp 358.00 2,864.00
2 Asphalt Batching Plant 1,139.63 9,117.04
3 Asphalt Distributor 10 ft wide 936.00 7,488.00
4 Asphalt Paver/Finisher PF-180 1,349.00 10,792.00
5 Backhoe SE 130 LC-2, 0.80 cu.m. 1,537.00 12,296.00
6 Backhoe, Wheel Type PW60-3, 0.28 cu.m. 840.00 6,720.00
7 Backhoe with Pavement Breaker 2,074.95 16,599.60
8 Bulldozer D65A-8/155Hp 2,299.00 18,392.00
9 Clampshell 315.00 2,520.00
10 Chain Saw 120.00 960.00
11 Concrete Paver/Finisher GP-2500 Slipform 6,237.00 49,896.00
12 Concrete Batching Plant 30 cu.m. 1,208.03 9,664.24
13 Crawler Crane 46-50T 1,956.00 15,648.00
14 Crawler Crane 36-40T 1,729.00 13,832.00
15 Concrete Vibrator 148.88 1,191.04
16 Concrete Mixer 1.5-2 Bagger 190.00 1,520.00
17 Concrete Mixer 1-Bagger 172.00 1,376.00
18 Concrete Screeder 545.00 4,360.00
19 Concrete Saw 167.38 1,339.04
20 Dump Truck (Cap. 10-11 cu.m.) 1,352.00 10,816.00
21 Payloader 1.5 cu.m. 1,733.00 13,864.00
22 Plate Compactor 123.00 984.00
23 Rebar Bender 351.50 2,812.00
24 Rebar Cutter 219.75 1,758.00
25 Road Grader 135Hp / GD511R-1 2,088.64 16,709.10
26 Road Roller, Vibratory Single Smooth Drum, CA252D 1,319.28 10,554.24
27 Transit Mixer 5-6 cu.m. 958.62 7,668.96
28 Water Truck (1000 Gal.) 632.12 5,056.96
29 Cargo Truck (5T) 696.63 5,573.05
30 TM Crane, 35T Capacity 1,487.63 11,901.05
31 Cutting Outfit (Gas Type) 44.38 355.00
32 Kneading Machine 115.63 925.05
33 Applicator 21.88 175.05
34 Low Bed (Prime Mover 25T Cap) 430.06 3,440.50
Prices of Construction Materials
(Based on Regional Price Monitoring Report - 2nd Quarter CY 13)

Hauling
No. Description Unit Unit Price Total Price Remarks
Cost
1 Portland Cement bag 285.00 1.57 286.57
2 Fine Aggregates cu.m. 476.20 69.88 546.08
3 Coarse Aggregates cu.m. 571.40 69.88 641.28
4 Agg. Subbase Course cu.m. 390.00 69.88 459.88
5 Embankment Materials cu.m. 300.00 69.88 369.88
6 RSB, Grade 40 kg. 55.00 0.04 55.04
7 RSB, Grade 60 kg. 60.00 0.04 60.04
8 Plain Round Rebar,10mm dia.x6m pcs 171.10 0.04 171.14
9 Tie Wire, #16 kg. 85.70 85.70
10 Boulders (Rock Class "A") cu.m. 560.00 179.99 739.99
11 PVC Pipe, 2" l.m. 97.00 97.00
12 RCPC, 910mm pc. 2,170.00 2,170.00
13 Form Lumber, Coco bd.ft. 28.00 28.00
14 Good Lumber, False Work bd.ft. 75.00 75.00
15 Marine Plywood, 4'x8'x1/2" pc. 857.10 857.10
16 Ordinary Plywood, 4'x8'x1/2" pc. 809.50 809.50
17 CW Nails, Assorted kg. 80.50 80.50
18 Tarpauline (Printed), 4'x8' pc. 630.00 630.00
19 Filter Cloth sq.m. 160.00 160.00
Field Office (rental), including electric and
20 mo. 6,200.00 6,200.00
water bills
25 Warning Sign 3mm thk.Triangle 600mm pc 4,972.00 4,972.00
26 75mm G.I Pipe pc 2,400.00 2,400.00
27 5mm Bolt & Knot pc 20.00 20.00
28 Chevron Directional Sign E39(450mmx610m pc 4,500.00 4,500.00
29 Informative Sign (457mmx1219mmx3mm S pc 7,150.00 7,150.00
30 Safety Shoes m.d 2.77 2.77
31 Safety Helmet m.d 0.25 0.25
32 Safety Gloves m.d 7.67 7.67
33 Acetylene/Oxygen set 3,000.00 3,000.00
35 Thermoplastic White bag 2,700.00 2,700.00
36 Glass Beads bag 800.00 800.00
37 Primer ltr 130.00 130.00
38 Rope (Cotton 1/4" x 30m.) l.m. 150 150.00
39 LPG kg. 53.45 53.45
40 Calsumie kg. 24 24.00
41 Curing Compound lit. 100.00 100.00
42 Asphalt Sealant lit. 75.00 75.00
43 Steel Forms l.m. 45.00 45.00
44 Concrete Saw(Diamond Blade 14") pcs 575.00 575.00
45 Pipe Sleeve, 1-1/2" dia. l.m. 131.25 131.25
46 Grease or Tar lit. 210.00 210.00
Summary of Labor Rates
No. Designation Hourly Rate Daily Rate

1 Foreman 65.55 524.36

2 Highly Skilled Laborer 54.36 434.88

3 Skilled Laborer 47.62 380.99

4 Semi-Skilled Laborer 43.56 348.48

5 Part-time Safety Practitioner 75.00 600.00

6 First Aider 55.00 440.00

7 Unskilled Laborer 36.75 293.96


Republic of the Philippines
Province of Ilocos Norte
Municipality of Marcos
OFFICE OF THE MUNICIPAL ENGINEER
BILL OF MATERIALS AND DETAILED ESTIMATES
#N/A Sitio Danao, Brgy. Mabuti
DETAILED ESTIMATE

Pay Item No. ITEM DESCRIPTION

SPL 1 VOLUME 3,200.00 bd.ft.

Description Quantity Unit Unit Cost Amount


1. BOULDERS 100 400 bd.ft. 58.00 23,200.00
MATERIALS

2. Portland Cement 200 1,200 bd.ft. 58.00 69,600.00


3. 2" X 4" X 12' Form Lumber 200 1,600 bd.ft. 58.00 92,800.00
Plywood 1/2" 20 pcs 650.00 13,000.00
CWN 4" 3 keg 1,050.00 3,150.00
CWN 3" 3 keg 1,150.00 3,450.00
CWN 2" / 1-1/2" 1 keg 1,200.00 1,200.00
Material Direct Cost 206,400.00
Duration
Description (Capacity/Production rate) No. of Units Unit Rate Amount
Day/Hr.
EQUIPMENT

Equipment assumed output /day

Equipment Direct Cost -


Duration Rate
Description Number Amount
Day/Hr. day/hr
LABOR

1. CONSTRUCTION FOREMAN 1 18.000 450.00 8,100.00


2. SKILLED CARPENTER 5 18.000 350.00 31,500.00
3. LABORERS 4 18.000 280.00 20,160.00

Labor Direct Cost 59,760.00


Total Direct Cost 266,160.00
Submitted By: Approved by: PLUS INDIRECT COST
OCM - #N/A #N/A
CP - #VALUE!
TAXES - #N/A
Engr. WARNER A. MACUSI #REF! TOTAL ADJUSTED COST = #N/A
Municipal Engineer Municipal Mayor UNIT COST #N/A
CERTIFICATE OF PAYMENT
Project : CONSTRUCTION OF 9.0M - ONE SPAN
RCDG BRIDGE COP No. 2015-02-01
Description : ROADS and BRIDGES Period Ending: ###

Location: Brgy. MABUTI Source of Fund: RA 7171 - Municipal Share


Marcos, Ilocos Norte Duration: 84CD
Date Started: January 19, 2015 Remarks : FIRST- PROGRESS BILLING
Contractor: BADOC BUILDERS and SUPPLY Target Date of Completion Monday, April 13, 2015
1 I Certify that this certificate is correct and that payment for the same has been received:

Certified by:

ENGR. ERNESTO P. PAGALING Wednesday, February 18, 2015


2 I certify that I have checked the amount covered in this certificate , that the work was actually
accomplished and performed , that the work , quantities and amounts are wholly consistent
with the requirements of all Contract Documents.

Certified by:
ENGR. WARNER A. MACUSI
Municipal Engineer Wednesday, February 18, 2015
3 Certificate Recommnded for Payment by:

RANDOLPH PRUDENCE R. INES


MPDC Wednesday, February 18, 2015
4 Certificate Approved for Payment :

HON. ARSENIO A. AGUSTIN


Municipal Mayor Wednesday, February 18, 2015
5 VALUE OF ACCOMPLISHMENT :

5.1 TOTAL ADVANCE PAYMENT :


a) Previous Recoupment
b) Balance on Advance Payment
5:2 ORIGINAL CONTRACT AMOUNT : Php 3,123,576.56
Add/Less : Approved Charge Order(Additive/Deductive)
a) C.O Nos. To ______________________________
b) Liquidated Damages
5.3 TOTAL CONTRACT AMOUNT 3,123,576.56
5.4 PERCENTAGE OF ACCOMPLISHMENT TO DATE #REF!
5.5 TOTAL AMOUNT OF ACCOMPLISHMENT TO DATE #REF!
5.6 LESS :
a) Recoupment of Down Payment -
b)Previous Payments : CO Nos.____,_____to________
C) 10% Retention #REF!
5.7 VALUE OF ACCOMPLISHMENT : #REF!
a) Witholding Tax (2%) #REF!
b) Value Added Tax (5%) #REF!
c) Gravel /Boulder Fees:
5.8 AMOUNT DUE THIS CERTIFICATE :
Add :Unpaid Previous Certificate :
C.O.P Nos.: _______________ to _____________
5.9 NET AMOUNT DUE PAYABLE #REF!
5.10 CONTRACT BALANCE AFTER THIS CERTIFICATE #REF!
5.11 CONTRACT BALANCE BEFORE THIS CERTIFICATE 3,123,576.56

6 ATTACHMENTS : * Test Results of Items for payment


* Accomplishment Report ( By Contractor ) * Change Order/Variation Order ( if any )
* Accomlishment Evaluation ( By LGU) *Progress photographs ( By Contractor & LGU)
PRE-POSTING REQUIREMENTS CHECKLISTS
INFRASTRUCTURE PROJECTS

PROJECT TITLE: 0
LOCATION: BRGY. MABUTI, MARCOS, ILOCOS NORTE
DETAILED ENGINEERING DOCUMENTS

1 Program of Works COMPLETED

2 Detail Materials Cost Estimates COMPLETED

3 Plans and Detailed Drawings COMPLETED

Road Sections

SLOPE PROTECTION

RCDG BRIDGE

4 Approved Budget for the Contract Err:509 COMPLETED

5 Construction Schedule & S-Curve COMPLETED

6 Manpower Utilization Schedule

7 Equipment Utilization Schedule

8 Cash Flow COMPLETED

9 Construction Specifications COMPLETED

10 Approprition Amount ###

RESOLUTION FROM SANGUNIANG BAYAN

1 Approprition Ordinance

PURCHASE REQUEST

1 Prepared Purchase Request ###

ACCOMPLISHING THE FORMS

1 Estimated Cost 967,689.00


CONSTRUCTION OF RCDG BRIDGE &
2 Purpose CONCRETING OF FMR at PACIFICO & LYDIA
Direct Shares of LGU from the FY 2010
3 Source of Fund from the Virginia Tobacco Excise Tax;

4 Availability of Fund (Budget Officer NATIFLORDELIZA S. GUIRA

5 Signature of Requesting WARNER A. MACUSI - Municipal Engineer

6 Signature for Availability of Fund IMELDA C. MANUEL - Municipal Treasurer

7 Signature of Approving Officer SALVADOR S. PILLOS - Municipal Mayor

Submit to the Office of the BAC


1 Secretariat Received by: DATE:
Prepared by:

ENGR. WARNER A. MACUSI


MUNICPAL ENGINEER
0.26% 54.00 10,800.51 -
12,568.10 61,469,771.35 -
47.40 4,669.81 -
1,200.00 1,996,068.14 -
1.00 85.63 -
1.00 -
TO DATE ACCOMPLISHMENTS - -

UN ACCOMPLISHED AS OF #VALUE! #VALUE!

LIQUIDATED DAMAGE AMOUNT


PER DAY OF DELAY 0.10% #VALUE!
0.56% - -
42.62% - -
12.42% - -
6.76% - -
0.17% - -
0.17% - -
62.69% - -

Вам также может понравиться