OBRA : "REHABILITACIN Y MEJORAMIENTO CARRETERA VECINAL ALTO CUUMBUZA-PUERTO BERMDEZ, DISTRITO DE ALTO BIAVO-CAMPANILLA, PROVINCIAS DE BELLAVISTA- MARISCAL CCERES-

L CCERES- SAN MARTN"


CLIENTE : GOBIERNO REGIONAL DE SAN MARTN - PROYECTO ESPECIAL HUALLAGA CENTRAL Y BAJO MAYO
UBICACIN : DIST. DE ALTO BIAVO-CAMPANILLA, PROV. DE BELLAVISTA- MARISCAL CCERES, REGION SAN MARTN.
CONTRATISTA : CONSORCIO VIAL CAMPANILLA
1/40
SUPERVISION : CONSORCIO VIAL SUPERVISOR CUUMBUZA
METRADOS VALORIZADOS MENSUALES
CONTRATO PRINCIPAL DEDUCTIVO DE OBRA N 01
CONTRACTUAL METRADOS VALORIZADOS
METRADO VAL 01 VAL 02 VAL 03 VAL 04 VAL 05 VAL 06 VAL 07 VAL 08 VAL 09 VAL 10 VAL 11 VAL 12 VAL 13 TOTAL METRADOS DEDUCIDOS
Cdigo Descripcin de la Partida Unid. TOTAL Agosto 2015 Setiembre 2015 Octubre 2015 Noviembre 2015 Diciembre 2015 Enero 2016 Febrero 2016 Marzo 2016 Abril 2016 Mayo 2016 Junio 2016 Julio 2016 Agosto 2016 EJECUTADO Dedc-01 Dedc-02 T O TAL
1 TRABAJOS PRELIMINARES 0.00
1.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 0.50 0.50 1.00 0.00
1.02 TRAZO Y REPLANTEO KM 19.06 7.62 0.00 0.38 2.00 1.00 3.00 3.00 1.97 18.97 0.09 0.00 0.09
2 MOVIMIENTO DE TIERRAS 0.00 0.00 0.00
2.01 DESBROCE Y LIMPIEZA EN ZONAS NO BOSCOSAS HA 3.69 1.50 0.50 1.69 -0.03 3.66 0.03 0.00 0.03
2.02 EXCAVACION PARA EXPLANACIONES EN MATERIAL COMUN m3 100,065.38 16,821.88 19,826.25 46,351.28 675.43 2,718.08 13,672.47 -704.32 99,361.06 107.90 596.42 704.32
2.03 REMOCION DE MATERIAL SATURADO m3 1,290.85 846.65 61.20 383.00 0.00 1,290.85 0.00
2.04 TERRAPLENES m3 18,948.94 840.72 2,317.18 5,159.00 617.95 1,486.38 8,527.71 -381.25 18,567.69 97.10 284.15 381.25
2.05 PEDRAPLEN m3 1,290.85 846.65 61.20 383.00 0.00 1,290.85 0.00
2.06 PERFILADO Y COMPACTADO DE SUBRASANTE m2 72,871.49 0.00 17,257.27 26,613.93 1,592.03 5,626.95 11,293.55 10,487.76 -752.35 72,119.14 374.01 378.34 752.35
3 AFIRMADOS 0.00 0.00 0.00
3.01 CAPA ANTICONTAMINANTE m3 13,815.50 3,375.28 3,911.30 708.90 1,435.68 2,222.57 2,161.77 -177.17 13,638.33 135.84 41.33 177.17
3.02 AFIRMADO m3 25,915.55 9,703.71 268.92 3,301.68 936.74 2,691.35 7,433.90 1,245.97 25,582.27 255.66 77.62 333.28
4 DRENAJE 0.00 0.00 0.00
4.01 ALCANTARILLAS TMC 0.00 0.00 0.00
04.01.01 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS m3 2,435.25 145.76 142.53 106.20 102.03 662.75 1,275.98 2,435.25 0.00
04.01.02 TUB. CORRUG. DE ACERO GALVAN. CIRCULAR = 0.91 m m 136.89 7.29 -7.29 10.53 0.00 118.26 8.10 136.89 0.00
04.01.03 TUB. CORRUG. DE ACERO GALVAN. CIRCULAR = 1.52 m m 97.20 26.73 7.29 41.31 21.87 0.00 97.20 0.00
04.01.04 TUB. CORRUG. DE ACERO GALVAN. CIRCULAR DE = 1.83 m m 14.58 7.29 0.00 0.00 7.29 0.00 14.58 0.00
04.01.05 ENCOFRADO Y DESENCOFRADO CABEZALES m2 689.26 155.03 55.57 0.00 403.77 74.89 689.26 0.00
04.01.06 ACERO DE REFUERZO F'Y = 4200 KG/CM2 kg 3,717.58 882.80 150.46 0.00 2,137.56 546.76 3,717.58 0.00
04.01.07 CONCRETO F'C=175 KG/CM2. - CABEZALES m3 106.42 26.06 0.00 0.00 69.18 11.18 106.42 0.00
04.01.08 RELLENO CON MATERIAL PROPIO PARA ESTRUCTURAS m3 832.46 175.60 53.92 83.74 467.34 51.86 832.46 0.00
04.01.09 MAMPOSTERIA CON PIEDRA EMBOQUILLADA m3 185.61 0.00 0.00 0.00 185.61 185.61 0.00
4.02 CUNETAS 0.00 0.00 0.00
04.02.01 EXCAVACION MANUAL EN OBRAS DE ARTE m3 6,292.62 948.03 -948.03 1,384.95 1,990.70 251.60 1,319.00 324.80 1,021.57 6,292.62 0.00
04.02.02 ENCOFRADO Y DESENCOFRADO m2 7,206.69 75.53 1,510.60 2,265.90 302.12 1,510.60 371.99 1,169.95 7,206.69 0.00
04.02.03 CONCRETO F'C=140 KG/CM2. m3 1,582.93 16.59 331.80 497.70 66.36 331.80 81.71 256.97 1,582.93 0.00
04.02.04 JUNTA ASFALTICA m 7,219.74 7,219.74 7,219.74 0.00
5 TRANSPORTE 0.00 0.00 0.00
5.01 TRANSPORTE DE MAT. EXCEDENTE DE CORTE HASTA 1 KM m3km 38,732.34 1,000.00 16,441.87 20,032.38 49.61 69.13 1,139.35 -98.57 38,633.77 10.68 87.89 98.57
5.02 TRANSPORTE DE MAT. EXCEDETE DE CORTE D > 1. KM. m3km 15,557.39 6,807.25 8,678.84 0.00 14.25 57.05 -26.66 15,530.73 2.94 23.72 26.66
5.03 TRANSPORTE DE MAT. SATURADO HASTA 1 KM m3km 999.56 637.62 361.94 0.00 999.56 0.00
5.04 TRANSPORTE DE MAT. SATURADO D > 1 KM m3km 281.59 281.59 0.00 0.00 281.59 0.00
5.05 TRANSP. DE MAT. PARA RELL. CON EXCED. DE CORTE HASTA 1 KM m3km 6,900.38 843.55 4,299.36 1,757.47 0.00 6,900.38 0.00
5.06 TRANSP. DE MAT. PARA RELL. CON EXCED. DE CORTE D > 1 KM m3km 17,610.50 142.66 15,957.69 1,510.15 0.00 17,610.50 0.00
5.07 TRANSPORTE DE MAT. ANTICONTAMINANTE HASTA 1 KM m3km 13,815.52 3,375.28 3,911.30 4,050.00 1,000.00 739.47 739.47 -428.20 13,387.32 242.62 185.58 428.20
5.08 TRANSPORTE DE MAT. ANTICONTAMINANTE D > 1KM m3km 264,338.66 16,376.40 57,438.81 77,274.00 19,080.00 47,084.73 47,084.72 -6,709.02 257,629.64 1,725.98 4,983.04 6,709.02
5.09 TRANSPORTE DE MAT. PARA AFIRMADO HASTA 1 KM. m3km 25,915.56 9,703.71 268.92 7,301.68 4,755.00 1,000.00 2,020.38 56.15 25,105.84 297.89 511.83 809.72
5.10 TRANSPORTE DE MAT. PARA AFIRMADO > 1 KM. m3km 723,897.30 192,811.88 7,389.90 161,321.36 132,569.40 27,880.00 141,347.33 40,302.68 703,622.55 6,258.68 14,016.07 20,274.75
6 SEALIZACION Y SEGURIDAD VIAL 0.00 0.00 0.00
6.01 SEALES PREVENTIVAS und 137.00 137.00 137.00 0.00
6.02 SEALES REGLAMENTARIAS und 46.00 46.00 46.00 0.00
6.03 SEAL INFORMATIVA m2 54.49 54.49 54.49 0.00
6.04 ESTRUCTURA DE SOPORTE DE SEALES INFORMATIVAS m 290.88 290.88 290.88 0.00
6.05 CIMENTACION Y MONTAJE DE SEAL INFORMATIVA und 60.00 60.00 60.00 0.00
6.06 HITOS KILOMETRICOS und 20.00 20.00 20.00 0.00
7 PLAN DE MANEJO AMBIENTAL 0.00 0.00 0.00
7.01 PROGRAMA DE MITIGACION AMBIENTAL 0.00 0.00 0.00
07.01.01 CONFORMACION DE DEPOSITOS DE MATERIAL EXCEDENTE m3 55,899.08 17,441.87 20,032.38 15,000.00 3,424.83 55,899.08 0.00
07.01.02 ESTABILIZACION DE TALUDES CON REVEGETACION ha 2.50 2.50 2.50
7.02 PROGRAMA DE MONITOREO AMBIENTAL 0.00 0.00 0.00
07.02.01 MONITOREO DE LA CALIDAD DEL AGUA und 3.00 1.00 2.00 3.00 0.00
07.02.02 MONITOREO DE LA CALIDAD DEL AIRE und 3.00 1.00 2.00 3.00 0.00
07.02.03 MONITOREO DE LA CALIDAD DE RUIDO und 3.00 1.00 2.00 3.00 0.00
7.03 PROGRAMA DE MANEJO DE RESIDUOS 0.00 0.00 0.00
07.03.01 ADQUISICION DE CONTENEDORES und 12.00 6.00 3.00 3.00 12.00 0.00
07.03.02 LETRINA SANITARIA PORTATIL und 3.00 1.00 1.00 1.00 3.00 0.00
7.04 PROGRAMA DE CIERRE Y ABANDONO 0.00 0.00 0.00
07.04.01 READECUACION AMBIENTAL DE CAMPAMENTOS HA 0.25 0.25 0.25 0.00
07.04.02 READECUACION AMBIENTAL DE CANTERAS HA 0.50 0.50 0.50 0.00
07.04.03 READECUACION AMBIENTAL DE BOTADEROS Y DME HA 0.50 0.12 0.38 0.50 0.00
07.04.04 SEALIZACION AMBIENTAL und 6.00 6.00 0.00 6.00 0.00

ADICIONAL DE OBRA N 01
CONTRACTUAL METRADOS VALORIZADOS
METRADO VAL 01 VAL 02 VAL 03 TOTAL
Cdigo Descripcin de la Partida Unid. TOTAL Agosto 2015 Setiembre 2015 Octubre 2015 Noviembre 2015 Diciembre 2015 Enero 2016 Febrero 2016 Marzo 2016 Abril 2016 Mayo 2016 Junio 2016 Julio 2016 Agosto 2016 EJECUTADO
2 MOVIMIENTO DE TIERRAS
2.03 REMOCION DE MATERIAL SATURADO m3 10,058.31 2,106.20 573.55 7,378.56 10,058.31
2.05 PEDRAPLEN m3 10,058.31 2,106.20 573.55 7,378.56 10,058.31
5 TRANSPORTE 0.00
5.03 TRANSPORTE DE MAT. SATURADO HASTA 1 KM m3km 5,274.74 765.83 720.72 3,788.19 5,274.74
5.04 TRANSPORTE DE MAT. SATURADO D > 1 KM m3km 411.99 19.35 61.13 331.51 411.99
7 PLAN DE MANEJO AMBIENTAL 0.00
7.01 PROGRAMA DE MITIGACION AMBIENTAL 0.00
07.01.01 CONFORMACION DE DEPOSITOS DE MATERIAL EXCEDENTE m3 10,058.31 2,106.20 573.55 7,378.56 10,058.31
OBRA : "REHABILITACIN Y MEJORAMIENTO CARRETERA VECINAL ALTO CUUMBUZA-PUERTO BERMDEZ, DISTRITO DE ALTO BIAVO-CAMPANILLA, PROVINCIAS DE BELLAVISTA- MARISCAL CCERES- SAN MARTN"
CLIENTE : GOBIERNO REGIONAL DE SAN MARTN - PROYECTO ESPECIAL HUALLAGA CENTRAL Y BAJO MAYO
UBICACIN : DIST. DE ALTO BIAVO-CAMPANILLA, PROV. DE BELLAVISTA- MARISCAL CCERES, REGION SAN MARTN.
CONTRATISTA : CONSORCIO VIAL CAMPANILLA
SUPERVISION : CONSORCIO VIAL SUPERVISOR CUUMBUZA

VALORIZACIONES
2/40
MENSUALES
CONTRATO PRINCIPAL DEDUCTIVOS DE OBRA N 01 Y N 02
VALORIZACION N01 VALORIZACION N02 VALORIZACION N03 VALORIZACION N04 VALORIZACION N05 VALORIZACION N06 VALORIZACION N07 VALORIZACION N08 VALORIZACION N09 VALORIZACION N10 VALORIZACION N11 VALORIZACION N12 VALORIZACION N13 TOTAL VALORIZACION DEDUCTIVOS DE OBRA
PRESUPUESTO CONTRACTUAL
Agosto 2015 Setiembre 2015 Octubre 2015 Noviembre 2015 Diciembre 2015 Enero 2016 Febrero 2016 Marzo 2016 Abril 2016 Mayo 2016 Junio 2016 Julio 2016 Agosto 2016 DEDUCTIVO 01 DEDUCTIVO 02 TOTAL DEDUCTIVOS
P.U. PARCIAL
Cdigo Descripcin de la Partida Unid. METRADO
S/. S/. Metrado Parcial S/. Metrado Parcial S/. Metrado Parcial S/. Metrado Parcial S/. Metrado Parcial S/. Metrado Parcial S/. Metrado Parcial S/. Metrado Parcial S/. Metrado Parcial S/. Metrado Parcial S/. Metrado Parcial S/. Metrado Parcial S/. Metrado Parcial S/. Metrado Parcial S/. Metrado Parcial S/. Metrado Parcial S/. Metrado Parcial S/.
1 TRABAJOS PRELIMINARES
1.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 32,063.68 32,063.68 0.50 16,031.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.50 16,031.84 1.00 32,063.68 0.00 0.00 0.00 0.00 0.00 0.00
1.02 TRAZO Y REPLANTEO KM 19.06 1,045.20 19,921.51 7.62 7,964.42 0.00 0.00 0.38 397.18 2.00 2,090.40 1.00 1,045.20 3.00 3,135.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.00 3,135.60 1.97 2,059.04 18.97 19,827.44 0.09 94.07 0.00 0.00 0.09 94.07
2 MOVIMIENTO DE TIERRAS 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2.01 DESBROCE Y LIMPIEZA EN ZONAS NO BOSCOSAS HA 3.69 3,530.42 13,027.25 1.50 5,295.63 0.00 0.00 0.50 1,765.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.69 5,966.41 0.00 0.00 0.00 0.00 -0.03 -105.91 3.66 12,921.34 0.03 105.91 0.00 0.00 0.03 105.91
2.02 EXCAVACION PARA EXPLANACIONES EN MATERIAL COMUN m3 100,065.38 4.56 456,298.13 16,821.88 76,707.75 19,826.25 90,407.70 46,351.28 211,361.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 675.43 3,079.96 2,718.08 12,394.44 13,672.47 62,346.44 0.00 0.00 0.00 0.00 -704.32 -3,211.68 99,361.06 453,086.45 107.90 492.02 596.42 2,719.66 704.32 3,211.69
2.03 REMOCION DE MATERIAL SATURADO m3 1,290.85 4.56 5,886.28 0.00 0.00 0.00 0.00 846.65 3,860.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 61.20 279.07 0.00 0.00 383.00 1,746.48 0.00 0.00 0.00 0.00 0.00 0.00 1,290.85 5,886.27 0.00 0.00 0.00 0.00 0.00 0.00
2.04 TERRAPLENES m3 18,948.94 7.14 135,295.43 840.72 6,002.74 2,317.18 16,544.68 5,159.00 36,835.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 617.95 4,412.16 1,486.38 10,612.75 8,527.71 60,887.82 0.00 0.00 0.00 0.00 -381.25 -2,722.13 18,567.69 132,573.28 97.10 693.29 284.15 2,028.85 381.25 2,722.14
2.05 PEDRAPLEN m3 1,290.85 67.88 87,622.90 0.00 0.00 0.00 0.00 846.65 57,470.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 61.20 4,154.26 0.00 0.00 383.00 25,998.04 0.00 0.00 0.00 0.00 0.00 0.00 1,290.85 87,622.90 0.00 0.00 0.00 0.00 0.00 0.00
2.06 PERFILADO Y COMPACTADO DE SUBRASANTE m2 72,871.49 1.59 115,865.67 0.00 0.00 17,257.27 27,439.06 26,613.93 42,316.15 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,592.03 2,531.33 5,626.95 8,946.85 11,293.55 17,956.74 10,487.76 16,675.54 0.00 0.00 -752.35 -1,196.24 72,119.14 114,669.43 374.01 594.68 378.34 601.56 752.35 1,196.24
3 AFIRMADOS 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
3.01 CAPA ANTICONTAMINANTE m3 13,815.50 21.79 301,039.75 0.00 0.00 3,375.28 73,547.35 3,911.30 85,227.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 708.90 15,446.93 1,435.68 31,283.47 2,222.57 48,429.80 2,161.77 47,104.97 0.00 0.00 -177.17 -3,860.53 13,638.33 297,179.22 135.84 2,959.95 41.33 900.58 177.17 3,860.52
3.02 AFIRMADO m3 25,915.55 21.55 558,480.10 0.00 0.00 0.00 0.00 0.00 0.00 9,703.71 209,114.95 268.92 5,795.23 3,301.68 71,151.20 0.00 0.00 936.74 20,186.75 2,691.35 57,998.59 0.00 0.00 0.00 0.00 7,433.90 160,200.55 1,245.97 26,850.65 25,582.27 551,297.92 255.66 5,509.47 77.62 1,672.71 333.28 7,182.18
4 DRENAJE 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4.01 ALCANTARILLAS TMC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.01.01 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS m3 2,435.25 8.26 20,115.17 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 145.76 1,203.98 142.53 1,177.30 106.20 877.21 0.00 0.00 0.00 0.00 102.03 842.77 662.75 5,474.32 1,275.98 10,539.59 2,435.25 20,115.17 0.00 0.00 0.00 0.00 0.00 0.00
04.01.02 TUB. CORRUG. DE ACERO GALVAN. CIRCULAR = 0.91 m m 136.89 405.25 55,474.67 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7.29 2,954.27 -7.29 -2,954.27 10.53 4,267.28 0.00 0.00 0.00 0.00 0.00 0.00 118.26 47,924.87 8.10 3,282.53 136.89 55,474.68 0.00 0.00 0.00 0.00 0.00 0.00
04.01.03 TUB. CORRUG. DE ACERO GALVAN. CIRCULAR = 1.52 m m 97.20 830.17 80,692.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 26.73 22,190.44 0.00 0.00 7.29 6,051.94 0.00 0.00 0.00 0.00 41.31 34,294.32 21.87 18,155.82 0.00 0.00 97.20 80,692.52 0.00 0.00 0.00 0.00 0.00 0.00
04.01.04 TUB. CORRUG. DE ACERO GALVAN CIRCULAR = 1.83 m m 14.58 1,115.28 16,260.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7.29 8,130.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7.29 8,130.39 0.00 0.00 14.58 16,260.78 0.00 0.00 0.00 0.00 0.00 0.00
04.01.05 ENCOFRADO Y DESENCOFRADO CABEZALES m2 689.26 59.07 40,714.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 155.03 9,157.62 55.57 3,282.52 0.00 0.00 0.00 0.00 0.00 0.00 403.77 23,850.69 74.89 4,423.75 689.26 40,714.58 0.00 0.00 0.00 0.00 0.00 0.00
04.01.06 ACERO DE REFUERZO F'Y = 4200 KG/CM2 kg 3,717.58 4.67 17,361.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 882.80 4,122.68 150.46 702.65 0.00 0.00 0.00 0.00 0.00 0.00 2,137.56 9,982.41 546.76 2,553.37 3,717.58 17,361.11 0.00 0.00 0.00 0.00 0.00 0.00
04.01.07 CONCRETO F'C=175 KG/CM2. - CABEZALES m3 106.42 497.98 52,995.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 26.06 12,977.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 69.18 34,450.26 11.18 5,567.42 106.42 52,995.04 0.00 0.00 0.00 0.00 0.00 0.00
04.01.08 RELLENO CON MATERIAL PROPIO PARA ESTRUCTURAS m3 832.46 31.82 26,488.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 175.60 5,587.59 53.92 1,715.73 0.00 0.00 0.00 0.00 83.74 2,664.61 467.34 14,870.76 51.86 1,650.19 832.46 26,488.88 0.00 0.00 0.00 0.00 0.00 0.00
04.01.09 MAMPOSTERIA CON PIEDRA EMBOQUILLADA m3 185.61 469.79 87,197.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 185.61 87,197.72 185.61 87,197.72 0.00 0.00 0.00 0.00 0.00 0.00
4.02 CUNETAS 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.02.01 EXCAVACION MANUAL EN OBRAS DE ARTE m3 6,292.62 32.83 206,586.71 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 948.03 31,123.82 -948.03 -31,123.82 1,384.95 45,467.91 1,990.70 65,354.68 251.60 8,260.03 1,319.00 43,302.77 324.80 10,663.18 1,021.57 33,538.14 6,292.62 206,586.71 0.00 0.00 0.00 0.00 0.00 0.00
04.02.02 ENCOFRADO Y DESENCOFRADO m2 7,206.69 35.75 257,639.17 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 75.53 2,700.20 1,510.60 54,003.95 2,265.90 81,005.93 302.12 10,800.79 1,510.60 54,003.95 371.99 13,298.64 1,169.95 41,825.71 7,206.69 257,639.17 0.00 0.00 0.00 0.00 0.00 0.00
04.02.03 CONCRETO F'C=140 KG/CM2. m3 1,582.93 453.30 717,542.17 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 16.59 7,520.25 331.80 150,404.94 497.70 225,607.41 66.36 30,080.99 331.80 150,404.94 81.71 37,039.14 256.97 116,484.50 1,582.93 717,542.17 0.00 0.00 0.00 0.00 0.00 0.00
04.02.04 JUNTA ASFALTICA m 7,219.74 4.98 35,954.31 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,219.74 35,954.31 7,219.74 35,954.31 0.00 0.00 0.00 0.00 0.00 0.00
5 TRANSPORTE 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5.01 TRANSPORTE DE MAT. EXCEDENTE DE CORTE HASTA 1 KM m3km 38,732.34 6.26 242,464.45 1,000.00 6,260.00 16,441.87 102,926.11 20,032.38 125,402.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 49.61 310.56 69.13 432.75 1,139.35 7,132.33 0.00 0.00 0.00 0.00 -98.57 -617.05 38,633.77 241,847.40 10.68 66.86 87.89 550.19 98.57 617.05
5.02 TRANSPORTE DE MAT. EXCEDETE DE CORTE D > 1. KM. m3km 15,557.39 1.46 22,713.79 0.00 0.00 6,807.25 9,938.59 8,678.84 12,671.11 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 14.25 20.81 57.05 83.30 0.00 0.00 0.00 0.00 -26.66 -38.92 15,530.73 22,674.89 2.94 4.29 23.72 34.63 26.66 38.92
5.03 TRANSPORTE DE MAT. SATURADO HASTA 1 KM m3km 999.56 6.26 6,257.25 0.00 0.00 0.00 0.00 637.62 3,991.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 361.94 2,265.74 0.00 0.00 0.00 0.00 0.00 0.00 999.56 6,257.24 0.00 0.00 0.00 0.00 0.00 0.00
5.04 TRANSPORTE DE MAT. SATURADO D > 1 KM m3km 281.59 1.46 411.12 0.00 0.00 0.00 0.00 281.59 411.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 281.59 411.12 0.00 0.00 0.00 0.00 0.00 0.00
5.05 TRANSP. DE MAT. PARA RELL. CON EXCED. DE CORTE HASTA 1 KM m3km 6,900.38 6.26 43,196.38 843.55 5,280.62 0.00 0.00 4,299.36 26,913.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,757.47 11,001.76 0.00 0.00 0.00 0.00 0.00 0.00 6,900.38 43,196.37 0.00 0.00 0.00 0.00 0.00 0.00
5.06 TRANSP. DE MAT. PARA RELL. CON EXCED. DE CORTE D > 1 KM m3km 17,610.50 1.46 25,711.33 142.66 208.28 0.00 0.00 15,957.69 23,298.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,510.15 2,204.82 0.00 0.00 0.00 0.00 0.00 0.00 17,610.50 25,711.33 0.00 0.00 0.00 0.00 0.00 0.00
5.07 TRANSPORTE DE MAT. ANTICONTAMINANTE HASTA 1 KM m3km 13,815.52 6.26 86,485.16 0.00 0.00 3,375.28 21,129.25 3,911.30 24,484.74 0.00 0.00 0.00 0.00 0.00 0.00 4,050.00 25,353.00 0.00 0.00 1,000.00 6,260.00 739.47 4,629.08 739.47 4,629.08 0.00 0.00 -428.20 -2,680.51 13,387.32 83,804.64 242.62 1,518.80 185.58 1,161.73 428.20 2,680.53
5.08 TRANSPORTE DE MAT. ANTICONTAMINANTE D > 1KM m3km 264,338.66 1.46 385,934.44 0.00 0.00 16,376.40 23,909.54 57,438.81 83,860.66 0.00 0.00 0.00 0.00 0.00 0.00 77,274.00 112,820.04 0.00 0.00 19,080.00 27,856.80 47,084.73 68,743.71 47,084.72 68,743.69 0.00 0.00 -6,709.02 -9,795.15 257,629.64 376,139.29 1,725.98 2,519.93 4,983.04 7,275.24 6,709.02 9,795.17
5.09 TRANSPORTE DE MAT. PARA AFIRMADO HASTA 1 KM. m3km 25,915.56 6.26 162,231.41 0.00 0.00 0.00 0.00 0.00 0.00 9,703.71 60,745.22 268.92 1,683.44 7,301.68 45,708.52 4,755.00 29,766.30 0.00 0.00 1,000.00 6,260.00 0.00 0.00 0.00 0.00 2,020.38 12,647.58 56.15 351.50 25,105.84 157,162.56 297.89 1,864.79 511.83 3,204.06 809.72 5,068.85
5.10 TRANSPORTE DE MAT. PARA AFIRMADO > 1 KM. m3km 723,897.30 1.46 1,056,890.06 0.00 0.00 0.00 0.00 0.00 0.00 192,811.88 281,505.34 7,389.90 10,789.25 161,321.36 235,529.19 132,569.40 193,551.32 0.00 0.00 27,880.00 40,704.80 0.00 0.00 0.00 0.00 141,347.33 206,367.10 40,302.68 58,841.91 703,622.55 1,027,288.91 6,258.68 9,137.67 14,016.07 20,463.46 20,274.75 29,601.14
6 SEALIZACION Y SEGURIDAD VIAL 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6.01 SEALES PREVENTIVAS und 137.00 468.46 64,179.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 137.00 64,179.02 137.00 64,179.02 0.00 0.00 0.00 0.00 0.00 0.00
6.02 SEALES REGLAMENTARIAS und 46.00 403.08 18,541.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 46.00 18,541.68 46.00 18,541.68 0.00 0.00 0.00 0.00 0.00 0.00
6.03 SEAL INFORMATIVA m2 54.49 438.77 23,908.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 54.49 23,908.58 54.49 23,908.58 0.00 0.00 0.00 0.00 0.00 0.00
6.04 ESTRUCTURA DE SOPORTE DE SEALES INFORMATIVAS m 290.88 105.50 30,687.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 290.88 30,687.84 290.88 30,687.84 0.00 0.00 0.00 0.00 0.00 0.00
6.05 CIMENTACION Y MONTAJE DE SEAL INFORMATIVA und 60.00 624.25 37,455.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 60.00 37,455.00 60.00 37,455.00 0.00 0.00 0.00 0.00 0.00 0.00
6.06 HITOS KILOMETRICOS und 20.00 146.15 2,923.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 20.00 2,923.00 20.00 2,923.00 0.00 0.00 0.00 0.00 0.00 0.00
7 PLAN DE MANEJO AMBIENTAL 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7.01 PROGRAMA DE MITIGACION AMBIENTAL 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.01.01 CONFORMACION DE DEPOSITOS DE MATERIAL EXCEDENTE m3 55,899.08 1.19 66,519.91 0.00 0.00 17,441.87 20,755.83 20,032.38 23,838.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 15,000.00 17,850.00 0.00 0.00 0.00 0.00 3,424.83 4,075.55 55,899.08 66,519.91 0.00 0.00 0.00 0.00 0.00 0.00
07.01.02 ESTABILIZACION DE TALUDES CON REVEGETACION ha 2.50 4,580.73 11,451.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.50 11,451.83 2.50 11,451.83 0.00 0.00 0.00 0.00 0.00 0.00
7.02 PROGRAMA DE MONITOREO AMBIENTAL 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.02.01 MONITOREO DE LA CALIDAD DEL AGUA und 3.00 1,500.00 4,500.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 1,500.00 2.00 3,000.00 3.00 4,500.00 0.00 0.00 0.00 0.00 0.00 0.00
07.02.02 MONITOREO DE LA CALIDAD DEL AIRE und 3.00 2,000.00 6,000.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 2,000.00 2.00 4,000.00 3.00 6,000.00 0.00 0.00 0.00 0.00 0.00 0.00
07.02.03 MONITOREO DE LA CALIDAD DE RUIDO und 3.00 500.00 1,500.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 500.00 2.00 1,000.00 3.00 1,500.00 0.00 0.00 0.00 0.00 0.00 0.00
7.03 PROGRAMA DE MANEJO DE RESIDUOS 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.03.01 ADQUISICION DE CONTENEDORES und 12.00 1,080.00 12,960.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.00 6,480.00 3.00 3,240.00 3.00 3,240.00 12.00 12,960.00 0.00 0.00 0.00 0.00 0.00 0.00
07.03.02 LETRINA SANITARIA PORTATIL und 3.00 2,000.00 6,000.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 2,000.00 1.00 2,000.00 1.00 2,000.00 3.00 6,000.00 0.00 0.00 0.00 0.00 0.00 0.00
7.04 PROGRAMA DE CIERRE Y ABANDONO 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.04.01 READECUACION AMBIENTAL DE CAMPAMENTOS HA 0.25 13,243.57 3,310.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.25 3,310.89 0.25 3,310.89 0.00 0.00 0.00 0.00 0.00 0.00
07.04.02 READECUACION AMBIENTAL DE CANTERAS HA 0.50 7,843.57 3,921.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.50 3,921.79 0.50 3,921.79 0.00 0.00 0.00 0.00 0.00 0.00
07.04.03 READECUACION AMBIENTAL DE BOTADEROS Y DME HA 0.50 7,843.57 3,921.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.12 941.23 0.38 2,980.56 0.50 3,921.79 0.00 0.00 0.00 0.00 0.00 0.00
07.04.04 SEALIZACION AMBIENTAL und 6.00 600.00 3,600.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.00 3,600.00 0.00 0.00 0.00 0.00 6.00 3,600.00 0.00 0.00 0.00 0.00 0.00 0.00

COSTO DIRECTO 5,674,200.24 123,751.28 386,598.11 764,106.77 553,455.91 19,313.12 421,127.41 370,655.57 317,175.15 574,739.28 386,384.28 386,384.28 434,746.64 616,372.54 639,599.79 5,608,025.85 25,561.73 40,612.67 66,174.41
GASTOS GENERALES 10.12% 574,268.47 12,524.49 39,126.41 77,332.91 56,013.58 1,954.62 42,621.02 37,512.92 32,100.33 58,167.61 39,104.77 39,104.77 43,999.38 62,381.18 64,731.94 567,571.16 2,587.02 4,110.28 6,697.30
UTILIDAD 0.00% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
SUB TOTAL 6,248,468.71 136,275.77 425,724.52 841,439.68 609,469.49 21,267.74 463,748.43 408,168.49 349,275.48 632,906.89 425,489.05 425,489.05 478,746.02 678,753.72 704,331.73 6,175,597.01 28,148.75 44,722.95 72,871.71

I.G.V. 0.00% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
TOTAL 6,248,468.71 136,275.77 425,724.52 841,439.68 609,469.49 21,267.74 463,748.43 408,168.49 349,275.48 632,906.89 425,489.05 478,746.02 678,753.72 704,331.73 6,175,597.01 28,148.75 44,722.95 72,871.71
0.00

ADICIONAL DE OBRA N 01
VALORIZACION N01 VALORIZACION N02 VALORIZACION N3 TOTAL PRESUPUESTO
Agosto 2015 Setiembre 2015 Octubre 2015 Noviembre 2015 Diciembre 2015 Enero 2016 Febrero 2016 Marzo 2016 Abril 2016 Mayo 2016 Junio 2016 Julio 2016 Agosto 2016 ADICIONAL DE OBRA N 01
P.U. PARCIAL
Cdigo Descripcin de la Partida Unid. METRADO
S/. S/. Metrado Parcial S/. Metrado Parcial S/. Metrado Parcial S/. Metrado Parcial S/. Metrado Parcial S/. Metrado Parcial S/. Metrado Parcial S/. Metrado Parcial S/. Metrado Parcial S/. Metrado Parcial S/. Metrado Parcial S/. Metrado Parcial S/. Metrado Parcial S/. Metrado Parcial S/.
2 MOVIMIENTO DE TIERRAS 0.00
2.03 REMOCION DE MATERIAL SATURADO m3 10,058.31 4.56 45,865.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,106.20 9,604.27 573.55 2,615.39 7,378.56 33,646.23 0.00 0.00 0.00 0.00 0.00 0.00 10,058.31 45,865.89
2.05 PEDRAPLEN m3 10,058.31 67.88 682,758.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,106.20 142,968.86 573.55 38,932.57 7,378.56 500,856.65 0.00 0.00 0.00 0.00 0.00 0.00 10,058.31 682,758.08
5 TRANSPORTE 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5.03 TRANSPORTE DE MAT. SATURADO HASTA 1 KM m3km 5,274.74 6.26 33,019.87 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 765.83 4,794.10 720.72 4,511.71 3,788.19 23,714.07 0.00 0.00 0.00 0.00 0.00 0.00 5,274.74 33,019.87
5.04 TRANSPORTE DE MAT. SATURADO D > 1 KM m3km 411.99 1.46 601.51 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 19.35 28.25 61.13 89.25 331.51 484.00 0.00 0.00 0.00 0.00 0.00 0.00 411.99 601.51
7 PLAN DE MANEJO AMBIENTAL 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7.01 PROGRAMA DE MITIGACION AMBIENTAL 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.01.01 CONFORMACION DE DEPOSITOS DE MATERIAL EXCEDENTE m3 10,058.31 1.19 11,969.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,106.20 2,506.38 573.55 682.52 7,378.56 8,780.49 0.00 0.00 0.00 0.00 0.00 0.00 10,058.31 11,969.39

COSTO DIRECTO 774,214.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 159,901.86 46,831.44 567,481.44 0.00 0.00 0.00 774,214.74
GASTOS GENERALES 8.08% 62,588.76 0.00 0.00 0.00 0.00 0.00 0.00 0.00 12,926.72 3,785.93 45,876.11 0.00 0.00 0.00 62,588.76
UTILIDAD 0.00% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
SUB TOTAL 836,803.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 172,828.58 50,617.37 613,357.55 0.00 0.00 0.00 836,803.50

I.G.V. 0.00% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
TOTAL 836,803.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 172,828.58 50,617.37 613,357.55 0.00 0.00 0.00 836,803.50
OBRA : "REHABILITACIN Y MEJORAMIENTO CARRETERA VECINAL ALTO CUUMBUZA-PUERTO BERMDEZ, DISTRITO DE ALTO BIAVO-CAMPANILLA, PROVINCIAS DE BELLAVISTA- MARISCAL CCERES- SAN MARTN"
CLIENTE : GOBIERNO REGIONAL DE SAN MARTN - PROYECTO ESPECIAL HUALLAGA CENTRAL Y BAJO MAYO
UBICACIN : DIST. DE ALTO BIAVO-CAMPANILLA, PROV. DE BELLAVISTA- MARISCAL CCERES, REGION SAN MARTN.
CONTRATISTA : CONSORCIO VIAL CAMPANILLA
SUPERVISION : CONSORCIO VIAL SUPERVISOR CUUMBUZA

CLCULO DEL COEFICIENTE DE REAJUSTE

CONTRATO PRINCIPAL 0.16

FORMULA: K = 0.150*(Jr / Jo) + 0.057*(Cr / Co) + 0.056*(Dr / Do) + 0.554*(Mr / Mo) + 0.183*(GGUr / GGUo)

Agosto-2014 (BASE) Agosto 2015 Setiembre 2015 Octubre 2015 Noviembre 2015
SIMBOLO DESCRIPCION I.U. % COEF.
I.U. K I.U. K I.U. K I.U. K I.U.
J MANO DE OBRA INC. LEYES SOCIALES 47 100.000% 0.150 523.70 0.150 544.59 0.156 544.59 0.156 544.59 0.156 544.59
C CEMENTO PORTLAND TIPO I 21 100.000% 0.057 458.79 0.057 459.40 0.057 459.40 0.057 459.40 0.057 459.40
D DLAR 29 (30) 100.000% 0.056 390.72 0.056 450.46 0.065 447.20 0.064 450.53 0.065 462.65
M MAQUINARIA Y EQUIPO IMPORTADO 49 100.000% 0.554 250.83 0.554 290.40 0.641 288.48 0.637 291.08 0.643 298.83
GGU INDICE GENERAL DE PRECIOS AL CONSUMIDOR 39 100.000% 0.183 402.37 0.183 418.64 0.190 418.76 0.190 419.35 0.191 420.80
COEFICIENTE DE REAJUSTE ( K ) = 1.000 1.109 1.104 1.112

ADICIONAL DE OBRA N 01 20.89


4%
FORMULA: K = 0.471*(Mr / Mo) + 0.454*(Mr / Mo) + 0.075*(Ir / Io)

Agosto-2014 (BASE) Agosto 2015 Setiembre 2015 Octubre 2015 Noviembre 2015
SIMBOLO DESCRIPCION I.U. % COEF.
I.U. K I.U. K I.U. K I.U. K I.U.
M MANO DE OBRA INC. LEYES SOCIALES 47 100.000% 0.471 523.70 0.471 0.000 0.000 0.000
M MAQUINARIA Y EQUIPO IMPORTADO 49 100.000% 0.454 250.83 0.454 0.000 0.000 0.000
I INDICE GENERAL DE PRECIOS AL CONSUMIDOR 39 100.000% 0.075 402.37 0.075 0.000 0.000 0.000
COEFICIENTE DE REAJUSTE ( K ) = 1.000 0.000 0.000 0.000

3de40
"

JUSTE

Noviembre 2015 Diciembre 2015 Enero 2016 Febrero 2016 Marzo 2016 Abril 2016 Mayo 2016 Junio 2016 Julio 2016 Agosto 2016
K I.U. K I.U. K I.U. K I.U. K I.U. K I.U. K I.U. K I.U. K I.U.
0.156 544.59 0.156 544.12 0.156 544.12 0.156 544.12 0.156 544.12 0.156 544.12 0.156 544.12 0.156 562.24 0.161 562.24
0.057 459.40 0.057 460.88 0.057 462.57 0.057 462.57 0.057 462.57 0.057 462.57 0.057 462.57 0.057 459.08 0.057 457.28
0.066 468.04 0.067 473.88 0.068 484.19 0.069 471.04 0.068 458.22 0.066 465.00 0.067 464.38 0.067 463.54 0.066 467.56
0.660 302.95 0.669 308.01 0.680 313.96 0.693 305.19 0.674 295.61 0.653 298.57 0.659 297.17 0.656 295.65 0.653 298.91
0.191 422.67 0.192 424.25 0.193 424.99 0.193 427.53 0.194 427.58 0.194 428.47 0.195 429.07 0.195 429.42 0.195 430.96
1.130 1.141 1.154 1.168 1.149 1.126 1.134 1.131 1.132

Noviembre 2015 Diciembre 2015 Enero 2016 Febrero 2016 Marzo 2016 Abril 2016 Mayo 2016 Junio 2016 Julio 2016 Agosto 2016
K I.U. K I.U. K I.U. K I.U. K I.U. K I.U. K I.U. K I.U. K I.U.
0.000 0.000 0.000 0.000 544.12 0.489 544.12 0.489 544.12 0.489 0.000 0.000
0.000 0.000 0.000 0.000 305.19 0.552 295.61 0.535 298.57 0.540 0.000 0.000
0.000 0.000 0.000 0.000 427.53 0.080 427.58 0.080 428.47 0.080 0.000 0.000
0.000 0.000 0.000 0.000 1.121 1.104 1.109 0.000 0.000

4de40
Agosto 2016 Septiembre 2016
K I.U. K
0.161 562.24 0.161
0.057 459.93 0.057
0.067 474.82 0.068
0.660 303.08 0.669
0.196 431.85 0.196
1.141 1.151

Agosto 2016
K
0.000
0.000
0.000
0.000

5de40
OBRA : "REHABILITACIN Y MEJORAMIENTO CARRETERA VECINAL ALTO CUUMBUZA-PUERTO BERMDEZ, DISTRITO DE ALTO BIAVO-CAMPANILLA, PROVINCIAS DE BELLAVISTA- MARISCAL CCERES- SAN MARTN"
CLIENTE : GOBIERNO REGIONAL DE SAN MARTN - PROYECTO ESPECIAL HUALLAGA CENTRAL Y BAJO MAYO
UBICACIN : DIST. DE ALTO BIAVO-CAMPANILLA, PROV. DE BELLAVISTA- MARISCAL CCERES, REGION SAN MARTN.
CONTRATISTA : CONSORCIO VIAL CAMPANILLA
SUPERVISION : CONSORCIO VIAL SUPERVISOR CUUMBUZA

DETERMINACIN DEL REAJUSTE


CONTRATO PRINCIPAL

AVANCE PROGRAMADO AVANCE REAL REINTEGRO PROGRAMADO REINTEGRO REAL REINTEGRO A RECONOCER
VALORIZACION
FACTOR
MENSUAL MES DE DE
ACUMULADO MENSUAL K (REAL) MENSUAL ACUMULADO MENSUAL ACUMULADO
(A) ACUMULADO REAJUSTE REAJUSTE MENSUAL ACUMULADO
N MES (APA) (V) (K-1) A x (K-1) (SRP) V x (K-1) (SRR)
CAO N 06

FORM1 FORM1 FORM1


1 Aug-15 2,315.65 2,315.65 136,275.77 136,275.77 Sep-15 1.104 0.104 240.83 240.83 14,172.68 14,172.68 14,172.68 14,172.68
2 Sep-15 130,845.06 133,160.71 425,724.52 562,000.29 Oct-15 1.112 0.112 14,654.65 14,895.48 47,681.15 61,853.83 47,681.15 61,853.83
3 Oct-15 351,112.51 484,273.22 841,439.68 1,403,439.97 Nov-15 1.130 0.130 45,644.63 60,540.11 109,387.16 171,240.99 109,387.16 171,240.99
4 Nov-15 360,902.35 845,175.57 609,469.49 2,012,909.46 Dec-15 1.141 0.141 50,887.23 111,427.34 85,935.20 257,176.19 85,935.20 257,176.19
5 Dec-15 447,662.36 1,292,837.93 21,267.74 2,034,177.20 Jan-16 1.154 0.154 68,940.00 180,367.34 3,275.23 260,451.42 3,275.23 260,451.42
6 Jan-16 817,456.75 2,110,294.68 463,748.43 2,497,925.63 Feb-16 1.168 0.168 137,332.73 317,700.07 77,909.74 338,361.16 77,909.74 338,361.16
7 Feb-16 984,372.55 3,094,667.23 408,168.49 2,906,094.12 Mar-16 1.149 0.149 146,671.51 464,371.58 60,817.11 399,178.27 60,817.11 399,178.27
8 Mar-16 679,690.12 3,774,357.35 349,275.48 3,255,369.60 Apr-16 1.126 0.126 85,640.96 550,012.54 44,008.71 443,186.98 44,008.71 443,186.98
9 Apr-16 540,096.23 4,314,453.58 632,906.89 3,888,276.49 May-16 1.134 0.134 72,372.89 622,385.43 84,809.52 527,996.50 84,809.52 527,996.50
10 May-16 679,262.01 4,993,715.59 425,489.05 4,313,765.54 Jun-16 1.131 0.131 88,983.32 711,368.75 55,739.07 583,735.57 55,739.07 583,735.57
11 Jun-16 570,739.50 5,564,455.09 478,746.02 4,792,511.56 Jul-16 1.132 0.132 75,337.61 786,706.36 63,194.47 646,930.04 63,194.47 646,930.04
12 Jul-16 657,549.24 6,222,004.33 678,753.72 5,471,265.28 Aug-16 1.141 0.141 92,714.44 879,420.80 95,704.27 742,634.31 95,704.27 742,634.31
13 Aug-16 26,464.38 6,248,468.71 704,331.73 6,175,597.01 Sep-16 1.151 0.151 3,996.12 883,416.92 106,354.09 848,988.40 106,354.09 848,988.40
6,248,468.71 6,175,597.01
84,809.52 94,388.93 816,015.84
32,972.56
ADICIONAL DE OBRA N 01
AVANCE PROGRAMADO AVANCE REAL FACTOR REINTEGRO PROGRAMADO REINTEGRO REAL REINTEGRO A RECONOCER
VALORIZACION MES DE DE
MENSUAL ACUMULADO MENSUAL K (REAL) MENSUAL ACUMULADO MENSUAL ACUMULADO
ACUMULADO REAJUSTE REAJUSTE MENSUAL ACUMULADO
N MES (A) (APA) (V) (K-1) A x (K-1) (SRP) V x (K-1) (SRR)
FORM1 FORM1 FORM1
Aug-15 - - - - - - - - -
Sep-15 - - - - - - - -
Oct-15 - - - - - - - -
Nov-15 - - - - - - - -
Dec-15 - - - - - - - -
Jan-16 - - - - - - - -
Feb-16 - - - - - - - -
1 Mar-16 94,200.69 94,200.69 172,828.58 172,828.58 Apr-16 1.104 0.104 9,796.87 9,796.87 17,974.17 17,974.17 17,974.17 17,974.17
2 Apr-16 492,723.50 586,924.19 50,617.37 223,445.95 May-16 1.109 0.109 53,706.86 63,503.73 5,517.29 23,491.46 5,517.29 23,491.46
3 May-16 249,879.31 836,803.50 613,357.55 836,803.50 Jun-16 1.115 0.115 28,736.12 92,239.85 70,536.12 94,027.58 70,536.12 94,027.58
DISTRITO DE ALTO BIAVO-CAMPANILLA, PROVINCIAS DE BELLAVISTA- MARISCAL CCERES- SAN MARTN"

CIN DEL REAJUSTE

ESTADO DE
LA OBRA

ADELANTADA
ADELANTADA
ADELANTADA
ADELANTADA
ADELANTADA
ADELANTADA
ATRASADA
ATRASADA
ATRASADA
ATRASADA
ATRASADA
ATRASADA
ATRASADA

ESTADO DE
LA OBRA

ADELANTADA
ADELANTADA
ADELANTADA
ADELANTADA
ADELANTADA
ADELANTADA
ADELANTADA
ADELANTADA
ATRASADA
ADELANTADA
OBRA : "REHABILITACIN Y MEJORAMIENTO CARRETERA VECINAL ALTO CUUMBUZA-PUERTO
BERMDEZ, DISTRITO DE ALTO BIAVO-CAMPANILLA, PROVINCIAS DE BELLAVISTA- MARISCAL
CCERES- SAN MARTN"
CLIENTE : GOBIERNO REGIONAL DE SAN MARTN - PROYECTO ESPECIAL HUALLAGA CENTRAL Y BAJO MAYO
UBICACIN : DIST. DE ALTO BIAVO-CAMPANILLA, PROV. DE BELLAVISTA- MARISCAL CCERES, REGION SAN MARTN.
CONTRATISTA : CONSORCIO VIAL CAMPANILLA
SUPERVISION : CONSORCIO VIAL SUPERVISOR CUUMBUZA

AMORTIZACIN DEL ADELANTO DIRECTO

DATOS DEL ADELANTO DIRECTO

ADELANTO OTORGADO SIN IGV


MONTO DEL
COMPROBANTE MONTO ADELANTO (S/.) CONTRATO
N FECHA DE PAGO PRINCIPAL (SIN IGV)
DE PAGO SIN I.G.V.

1 12-Aug-2015 1,249,693.74 6,248,468.71

TOTAL DEL ADELANTO DIRECTO (sin IGV) : S/. 1,249,693.74 20.00%

FRMULAS :
A1 A2

AM = V x ( ------- ) + V x ( ------- )

C1 C2
DONDE :
AM : Amorizacin Mensual del Adelanto Directo
V : Monto en S/. de la valorizacin mensual
A : Monto parcial del Adelanto directo concedido al Contratista 1,249,693.74
C : Monto del contrato Principal 6,248,468.71

AMORTIZACIN DEL ADELANTO DIRECTO


VALORIZACION AMORTIZACION (S/.) SALDO POR
MONTO VAL SIN IGV
SIN I.G.V. AMORTIZAR
N PERIODO (S/.)
V VxA/C SIN I.G.V
1 Aug-15 136,275.77 27,255.15 1,222,438.59
2 Sep-15 425,724.52 85,144.90 1,137,293.69
3 Oct-15 841,439.68 168,287.94 969,005.75
4 Nov-15 609,469.49 121,893.90 847,111.85
5 Dec-15 21,267.74 4,253.55 842,858.30
6 Jan-16 463,748.43 92,749.69 750,108.61
7 Feb-16 408,168.49 81,633.70 668,474.91
8 Mar-16 349,275.48 69,855.10 598,619.81
9 Apr-16 632,906.89 126,581.38 472,038.43
10 May-16 425,489.05 85,097.81 386,940.62
11 Jun-16 478,746.02 95,749.20 291,191.42
12 Jul-16 678,753.72 291,191.42 0.00

TOTAL AMORTIZACIN S/. 5,471,265.28 1,249,693.74


OBRA
: "REHABILITACIN Y MEJORAMIENTO CARRETERA VECINAL ALTO CUUMBUZA-PUERTO BERMDEZ, DISTRITO DE
ALTO BIAVO-CAMPANILLA, PROVINCIAS DE BELLAVISTA- MARISCAL CCERES- SAN MARTN"

CLIENTE : GOBIERNO REGIONAL DE SAN MARTN - PROYECTO ESPECIAL HUALLAGA CENTRAL Y BAJO MAYO
UBICACIN : DIST. DE ALTO BIAVO-CAMPANILLA, PROV. DE BELLAVISTA- MARISCAL CCERES, REGION SAN MARTN.
CONTRATISTA : CONSORCIO VIAL CAMPANILLA
SUPERVISION : CONSORCIO VIAL SUPERVISOR CUUMBUZA

CLCULO DE LA DEDUCCIN QUE NO CORRESPONDE


POR EL ADELANTO DIRECTO

FORMULA GENERAL

De = ( V x A / C ) x ( Kr / Ka - 1 ) = AM x ( Kr / Ka - 1 )
donde :

De = Deduccion del reajuste que no corresponde del componente


en soles de la valorizacion mensual
A= Monto del Adelanto sujeto a deduccion =
C= Monto del contrato Principal
Kr = Factor de Reajuste del mes respectivo
Ka = Factor de Reajuste al mes que se otorgo el adelanto (Agosto 2015) = 1.109

VALORIZACION COEFICIENTE DE
REAJUSTE AMORTIZACION
MONTO VAL. sin IGV S/. Kr
N PERIODO
FORM.01 FORM.01 FORM.01

1 Aug-15 136,275.77 1.104 27,255.15


2 Sep-15 425,724.52 1.112 85,144.90
3 Oct-15 841,439.68 1.130 168,287.94
4 Nov-15 609,469.49 1.141 121,893.90
5 Dec-15 21,267.74 1.154 4,253.55
6 Jan-16 463,748.43 1.168 92,749.69
7 Feb-16 408,168.49 1.149 81,633.70
8 Mar-16 349,275.48 1.126 69,855.10
9 Apr-16 632,906.89 1.134 126,581.38
10 May-16 425,489.05 1.131 85,097.81
11 Jun-16 478,746.02 1.132 95,749.20
12 Jul-16 678,753.72 1.141 291,191.42

TOTAL DEDUCCION S/. 5,471,265.28


RAMIENTO CARRETERA VECINAL ALTO CUUMBUZA-PUERTO BERMDEZ, DISTRITO DE
ROVINCIAS DE BELLAVISTA- MARISCAL CCERES- SAN MARTN"

SAN MARTN - PROYECTO ESPECIAL HUALLAGA CENTRAL Y BAJO MAYO


PANILLA, PROV. DE BELLAVISTA- MARISCAL CCERES, REGION SAN MARTN.

E LA DEDUCCIN QUE NO CORRESPONDE


POR EL ADELANTO DIRECTO

x A / C ) x ( Kr / Ka - 1 ) = AM x ( Kr / Ka - 1 )
datos :

S/. 1,249,693.74
S/. 6,248,468.71

DEDUCCION
De
S/.
- 122.88
230.33
3,186.70
3,517.23
172.60
4,934.38
2,944.41
1,070.82
2,853.50
1,688.14
1,985.78
8,402.28

30,863.29
OBRA : "REHABILITACIN Y MEJORAMIENTO CARRETERA VECINAL ALTO CUUMBUZA-PUERTO BERMDEZ, DISTRITOS DE ALTO BIAVO-CAMPANILLA, PROVINCIAS DE BELLAVISTA- MARISCAL CCERES- SAN MARTN"

METRADOS VALORIZADOS MENSUALES 12/40

CONTRATO PRINCIPAL
METRADOS VALORIZADOS
VAL 01 VAL 02 VAL 03 VAL 04 VAL 05 VAL 06 VAL 07 VAL 08 VAL 09 VAL 10 VAL 11 VAL 12 VAL 13 TOTAL
Cdigo Descripcin de la Partida
Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 EJECUTADO
1 TRABAJOS PRELIMINARES
1.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO 0.50 0.50 1.00
1.02 TRAZO Y REPLANTEO 7.62 0.00 0.38 2.00 1.00 3.00 3.00 1.97 18.97
2 MOVIMIENTO DE TIERRAS 0.00 0.00
2.01 DESBROCE Y LIMPIEZA EN ZONAS NO BOSCOSAS 1.50 0.50 1.69 -0.03 3.66
2.02 EXCAVACION PARA EXPLANACIONES EN MATERIAL COMUN 16,821.88 19,826.25 46,351.28 675.43 2,718.08 13,672.47 -107.90 99,957.48
2.03 REMOCION DE MATERIAL SATURADO 846.65 61.20 383.00 0.00 1,290.85
2.04 TERRAPLENES 840.72 2,317.18 5,159.00 617.95 1,486.38 8,527.71 -97.10 18,851.84
2.05 PEDRAPLEN 846.65 61.20 383.00 0.00 1,290.85
2.06 PERFILADO Y COMPACTADO DE SUBRASANTE 0.00 17,257.27 26,613.93 1,592.03 5,626.95 11,293.55 10,487.76 -374.01 72,497.48
3 AFIRMADOS 0.00 0.00
3.01 CAPA ANTICONTAMINANTE 3,375.28 3,911.30 708.90 1,435.68 2,222.57 2,161.77 -135.84 13,679.66
3.02 AFIRMADO 9,703.71 268.92 3,301.68 936.74 2,691.35 7,433.90 1,323.59 25,659.89
4 DRENAJE 0.00 0.00
4.01 ALCANTARILLAS TMC 0.00 0.00
04.01.01 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS 145.76 142.53 106.20 102.03 662.75 1,275.98 2,435.25
04.01.02 TUB CORRUGADA DE ACERO GALVANIZADO CIRCULAR DE = 0.91 m 7.29 -7.29 10.53 0.00 118.26 8.10 136.89
04.01.03 TUB CORRUGADA DE ACERO GALVANIZADO CIRCULAR DE = 1.52 m 26.73 7.29 41.31 21.87 0.00 97.20
04.01.04 TUB CORRUGADA DE ACERO GALVANIZADO CIRCULAR DE = 1.83 m 7.29 0.00 0.00 7.29 0.00 14.58
04.01.05 ENCOFRADO Y DESENCOFRADO CABEZALES 155.03 55.57 0.00 403.77 74.89 689.26
04.01.06 ACERO DE REFUERZO F'Y = 4200 KG/CM2 882.80 150.46 0.00 2,137.56 546.76 3,717.58
04.01.07 CONCRETO F'C=175 KG/CM2. - CABEZALES 26.06 0.00 0.00 69.18 11.18 106.42
04.01.08 RELLENO CON MATERIAL PROPIO PARA ESTRUCTURAS 175.60 53.92 83.74 467.34 51.86 832.46
04.01.09 MAMPOSTERIA CON PIEDRA EMBOQUILLADA 0.00 0.00 0.00 185.61 185.61
4.02 CUNETAS 0.00 0.00
04.02.01 EXCAVACION MANUAL EN OBRAS DE ARTE 948.03 -948.03 1,384.95 1,990.70 251.60 1,319.00 324.80 1,021.57 6,292.62
04.02.02 ENCOFRADO Y DESENCOFRADO 75.53 1,510.60 2,265.90 302.12 1,510.60 371.99 1,169.95 7,206.69
04.02.03 CONCRETO F'C=140 KG/CM2. 16.59 331.80 497.70 66.36 331.80 81.71 256.97 1,582.93
04.02.04 JUNTA ASFALTICA 7,219.74 7,219.74
5 TRANSPORTE 0.00 0.00
5.01 TRANSPORTE DE MAT. EXCEDENTE DE CORTE HASTA 1 KM 1,000.00 16,441.87 20,032.38 49.61 69.13 1,139.35 -10.68 38,721.66
5.02 TRANSPORTE DE MAT. EXCEDETE DE CORTE D > 1. KM. 6,807.25 8,678.84 0.00 14.25 57.05 -2.94 15,554.45
5.03 TRANSPORTE DE MAT. SATURADO HASTA 1 KM 637.62 361.94 0.00 999.56
5.04 TRANSPORTE DE MAT. SATURADO D > 1 KM 281.59 0.00 0.00 281.59
5.05 TRANSP. DE MAT. PARA RELL. CON EXCEDENTE DE CORTE HASTA 1 KM 843.55 4,299.36 1,757.47 0.00 6,900.38
5.06 TRANSP. DE MAT. PARA RELL. CON EXCEDENTE DE CORTE D > 1 KM 142.66 15,957.69 1,510.15 0.00 17,610.50
5.07 TRANSPORTE DE MAT. ANTICONTAMINANTE HASTA 1 KM 3,375.28 3,911.30 4,050.00 1,000.00 739.47 739.47 -242.62 13,572.90
5.08 TRANSPORTE DE MAT. ANTICONTAMINANTE D > 1KM 16,376.40 57,438.81 77,274.00 19,080.00 47,084.73 47,084.72 -1,725.98 262,612.68
5.09 TRANSPORTE DE MAT. PARA AFIRMADO HASTA 1 KM. 9,703.71 268.92 7,301.68 4,755.00 1,000.00 2,020.38 567.98 25,617.67
5.10 TRANSPORTE DE MAT. PARA AFIRMADO > 1 KM. 192,811.88 7,389.90 161,321.36 132,569.40 27,880.00 141,347.33 54,318.75 717,638.62
OBRA : "REHABILITACIN Y MEJORAMIENTO CARRETERA VECINAL ALTO CUUMBUZA-PUERTO BERMDEZ, DISTRITOS DE ALTO BIAVO-CAMPANILLA, PROVINCIAS DE BELLAVISTA- MARISCAL CCERES- SAN MARTN"

METRADOS VALORIZADOS MENSUALES 13/40

CONTRATO PRINCIPAL
METRADOS VALORIZADOS
VAL 01 VAL 02 VAL 03 VAL 04 VAL 05 VAL 06 VAL 07 VAL 08 VAL 09 VAL 10 VAL 11 VAL 12 VAL 13 TOTAL
Cdigo Descripcin de la Partida
Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 EJECUTADO
6 SEALIZACION Y SEGURIDAD VIAL 0.00 0.00
6.01 SEALES PREVENTIVAS 137.00 137.00
6.02 SEALES REGLAMENTARIAS 46.00 46.00
6.03 SEAL INFORMATIVA 54.49 54.49
6.04 ESTRUCTURA DE SOPORTE DE SEALES INFORMATIVAS 290.88 290.88
6.05 CIMENTACION Y MONTAJE DE SEAL INFORMATIVA 60.00 60.00
6.06 HITOS KILOMETRICOS 20.00 20.00
7 PLAN DE MANEJO AMBIENTAL 0.00 0.00
7.01 PROGRAMA DE MITIGACION AMBIENTAL 0.00 0.00
07.01.01 CONFORMACION DE DEPOSITOS DE MATERIAL EXCEDENTE 17,441.87 20,032.38 15,000.00 3,424.83 55,899.08
07.01.02 ESTABILIZACION DE TALUDES CON REVEGETACION 2.50 2.50
7.02 PROGRAMA DE MONITOREO AMBIENTAL 0.00 0.00
07.02.01 MONITOREO DE LA CALIDAD DEL AGUA 1.00 2.00 3.00
07.02.02 MONITOREO DE LA CALIDAD DEL AIRE 1.00 2.00 3.00
07.02.03 MONITOREO DE LA CALIDAD DE RUIDO 1.00 2.00 3.00
7.03 PROGRAMA DE MANEJO DE RESIDUOS 0.00 0.00
07.03.01 ADQUISICION DE CONTENEDORES 6.00 3.00 3.00 12.00
07.03.02 LETRINA SANITARIA PORTATIL 1.00 1.00 1.00 3.00
7.04 PROGRAMA DE CIERRE Y ABANDONO 0.00 0.00
07.04.01 READECUACION AMBIENTAL DE CAMPAMENTOS 0.25 0.25
07.04.02 READECUACION AMBIENTAL DE CANTERAS 0.50 0.50
07.04.03 READECUACION AMBIENTAL DE BOTADEROS Y DME 0.12 0.38 0.50
07.04.04 SEALIZACION AMBIENTAL 6.00 0.00 6.00

ADICIONAL DE OBRA N 01
METRADOS VALORIZADOS
VAL 01 VAL 02 VAL 03 TOTAL
Cdigo Descripcin de la Partida
Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 EJECUTADO
2 MOVIMIENTO DE TIERRAS
2.03 REMOCION DE MATERIAL SATURADO 2,106.20 573.55 7,378.56 10,058.31
2.05 PEDRAPLEN 2,106.20 573.55 7,378.56 10,058.31
5 TRANSPORTE 0.00
5.03 TRANSPORTE DE MAT. SATURADO HASTA 1 KM 765.83 720.72 3,788.19 5,274.74
5.04 TRANSPORTE DE MAT. SATURADO D > 1 KM 19.35 61.13 331.51 411.99
7 PLAN DE MANEJO AMBIENTAL 0.00
7.01 PROGRAMA DE MITIGACION AMBIENTAL 0.00
07.01.01 CONFORMACION DE DEPOSITOS DE MATERIAL EXCEDENTE 2,106.20 573.55 7,378.56 10,058.31
14/40

METRADOS
DEDUCIDOS

DEDUCTIVO 01
0.00
0.00
0.09
0.00
0.03
107.90
0.00
97.10
0.00
374.01
0.00
135.84
255.66
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
10.68
2.94
0.00
0.00
0.00
0.00
242.62
1,725.98
297.89
6,258.68
15/40

METRADOS
DEDUCIDOS

DEDUCTIVO 01
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

METRADOS
DEDUCIDOS

DEDUCTIVO 01

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
METRADOS VALORIZADOS MENSUALES
CONTRATO PRINCIPAL
CONTRACTUAL
METRADOS VALORIZADOS
METRADO TOTAL 16/40
Cdigo Descripcin de la Partida Unid. TOTAL EJECUTADO
1 TRABAJOS PRELIMINARES
1.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 1.00 100.00%
1.02 TRAZO Y REPLANTEO KM 19.06 18.97 99.53%
2 MOVIMIENTO DE TIERRAS 0.00
2.01 DESBROCE Y LIMPIEZA EN ZONAS NO BOSCOSAS HA 3.69 3.66 99.19%
2.02 EXCAVACION PARA EXPLANACIONES EN MATERIAL COMUN m3 100,065.38 99,361.06 99.30%
2.03 REMOCION DE MATERIAL SATURADO m3 1,290.85 1,290.85 100.00%
2.04 TERRAPLENES m3 18,948.94 18,567.69 97.99%
2.05 PEDRAPLEN m3 1,290.85 1,290.85 100.00%
2.06 PERFILADO Y COMPACTADO DE SUBRASANTE m2 72,871.49 72,119.14 98.97%
3 AFIRMADOS 0.00
3.01 CAPA ANTICONTAMINANTE m3 13,815.50 13,638.33 98.72%
3.02 AFIRMADO m3 25,915.55 25,582.27 98.71%
4 DRENAJE 0.00
4.01 ALCANTARILLAS TMC 0.00
04.01.01 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS m3 2,435.25 2,435.25 100.00%
04.01.02 TUB. CORRUG. DE ACERO GALVAN. CIRCULAR = 0.91 m m 136.89 136.89 100.00%
04.01.03 TUB. CORRUG. DE ACERO GALVAN. CIRCULAR = 1.52 m m 97.20 97.20 100.00%
04.01.04 TUB. CORRUG. DE ACERO GALVAN. CIRCULAR DE = 1.83 m m 14.58 14.58 100.00%
04.01.05 ENCOFRADO Y DESENCOFRADO CABEZALES m2 689.26 689.26 100.00%
04.01.06 ACERO DE REFUERZO F'Y = 4200 KG/CM2 kg 3,717.58 3,717.58 100.00%
04.01.07 CONCRETO F'C=175 KG/CM2. - CABEZALES m3 106.42 106.42 100.00%
04.01.08 RELLENO CON MATERIAL PROPIO PARA ESTRUCTURAS m3 832.46 832.46 100.00%
04.01.09 MAMPOSTERIA CON PIEDRA EMBOQUILLADA m3 185.61 185.61 100.00%
4.02 CUNETAS 0.00
04.02.01 EXCAVACION MANUAL EN OBRAS DE ARTE m3 6,292.62 6,292.62 100.00%
04.02.02 ENCOFRADO Y DESENCOFRADO m2 7,206.69 7,206.69 100.00%
04.02.03 CONCRETO F'C=140 KG/CM2. m3 1,582.93 1,582.93 100.00%
04.02.04 JUNTA ASFALTICA m 7,219.74 7,219.74 100.00%
5 TRANSPORTE 0.00
5.01 TRANSPORTE DE MAT. EXCEDENTE DE CORTE HASTA 1 KM m3km 38,732.34 38,633.77 99.75%
5.02 TRANSPORTE DE MAT. EXCEDETE DE CORTE D > 1. KM. m3km 15,557.39 15,530.73 99.83%
5.03 TRANSPORTE DE MAT. SATURADO HASTA 1 KM m3km 999.56 999.56 100.00%
5.04 TRANSPORTE DE MAT. SATURADO D > 1 KM m3km 281.59 281.59 100.00%
5.05 TRANSP. DE MAT. PARA RELL. CON EXCED. DE CORTE HASTA 1 KM m3km 6,900.38 6,900.38 100.00%
5.06 TRANSP. DE MAT. PARA RELL. CON EXCED. DE CORTE D > 1 KM m3km 17,610.50 17,610.50 100.00%
5.07 TRANSPORTE DE MAT. ANTICONTAMINANTE HASTA 1 KM m3km 13,815.52 13,387.32 96.90%
5.08 TRANSPORTE DE MAT. ANTICONTAMINANTE D > 1KM m3km 264,338.66 257,629.64 97.46%
5.09 TRANSPORTE DE MAT. PARA AFIRMADO HASTA 1 KM. m3km 25,915.56 25,105.84 96.88%
5.10 TRANSPORTE DE MAT. PARA AFIRMADO > 1 KM. m3km 723,897.30 703,622.55 97.20%
6 SEALIZACION Y SEGURIDAD VIAL 0.00
6.01 SEALES PREVENTIVAS und 137.00 137.00 100.00%
6.02 SEALES REGLAMENTARIAS und 46.00 46.00 100.00%
6.03 SEAL INFORMATIVA m2 54.49 54.49 100.00%
6.04 ESTRUCTURA DE SOPORTE DE SEALES INFORMATIVAS m 290.88 290.88 100.00%
6.05 CIMENTACION Y MONTAJE DE SEAL INFORMATIVA und 60.00 60.00 100.00%
6.06 HITOS KILOMETRICOS und 20.00 20.00 100.00%
7 PLAN DE MANEJO AMBIENTAL 0.00
7.01 PROGRAMA DE MITIGACION AMBIENTAL 0.00
07.01.01 CONFORMACION DE DEPOSITOS DE MATERIAL EXCEDENTE m3 55,899.08 55,899.08 100.00%
07.01.02 ESTABILIZACION DE TALUDES CON REVEGETACION ha 2.50 2.50 100.00%
7.02 PROGRAMA DE MONITOREO AMBIENTAL 0.00
07.02.01 MONITOREO DE LA CALIDAD DEL AGUA und 3.00 3.00 100.00%
07.02.02 MONITOREO DE LA CALIDAD DEL AIRE und 3.00 3.00 100.00%
07.02.03 MONITOREO DE LA CALIDAD DE RUIDO und 3.00 3.00 100.00%
7.03 PROGRAMA DE MANEJO DE RESIDUOS 0.00
07.03.01 ADQUISICION DE CONTENEDORES und 12.00 12.00 100.00%
07.03.02 LETRINA SANITARIA PORTATIL und 3.00 3.00 100.00%
7.04 PROGRAMA DE CIERRE Y ABANDONO 0.00
07.04.01 READECUACION AMBIENTAL DE CAMPAMENTOS HA 0.25 0.25 100.00%
07.04.02 READECUACION AMBIENTAL DE CANTERAS HA 0.50 0.50 100.00%
07.04.03 READECUACION AMBIENTAL DE BOTADEROS Y DME HA 0.50 0.50 100.00%
07.04.04 SEALIZACION AMBIENTAL und 6.00 6.00 100.00%
METRADOS TOTALES Y EJECUTADOS VALORIZADOS
CONTRATO PRINCIPAL

TOTAL VALORIZACION PRESUPUESTO


CONTRACTUAL
Cdigo Descripcin de la Partida Unid. METRADO
Metrado Parcial
17/40 S/.
1 TRABAJOS PRELIMINARES
1.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 1.00 100.00% 32,063.68
1.02 TRAZO Y REPLANTEO KM 19.06 18.97 99.53% 19,827.44
2 MOVIMIENTO DE TIERRAS 0.00 0.00
2.01 DESBROCE Y LIMPIEZA EN ZONAS NO BOSCOSAS HA 3.69 3.66 99.19% 12,921.34
2.02 EXCAVACION PARA EXPLANACIONES EN MATERIAL COMUN m3 100,065.38 99,361.06 99.30% 453,086.43
2.03 REMOCION DE MATERIAL SATURADO m3 1,290.85 1,290.85 100.00% 5,886.27
2.04 TERRAPLENES m3 18,948.94 18,567.69 97.99% 132,573.28
2.05 PEDRAPLEN m3 1,290.85 1,290.85 100.00% 87,622.90
2.06 PERFILADO Y COMPACTADO DE SUBRASANTE m2 72,871.49 72,119.14 98.97% 114,669.43
3 AFIRMADOS 0.00 0.00
3.01 CAPA ANTICONTAMINANTE m3 13,815.50 13,638.33 98.72% 297,179.22
3.02 AFIRMADO m3 25,915.55 25,582.27 98.71% 551,297.92
4 DRENAJE 0.00 0.00
4.01 ALCANTARILLAS TMC 0.00 0.00
04.01.01 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS m3 2,435.25 2,435.25 100.00% 20,115.17
04.01.02 TUB. CORRUG. DE ACERO GALVAN. CIRCULAR = 0.91 m m 136.89 136.89 100.00% 55,474.68
04.01.03 TUB. CORRUG. DE ACERO GALVAN. CIRCULAR = 1.52 m m 97.20 97.20 100.00% 80,692.52
04.01.04 TUB. CORRUG. DE ACERO GALVAN CIRCULAR = 1.83 m m 14.58 14.58 100.00% 16,260.78
04.01.05 ENCOFRADO Y DESENCOFRADO CABEZALES m2 689.26 689.26 100.00% 40,714.58
04.01.06 ACERO DE REFUERZO F'Y = 4200 KG/CM2 kg 3,717.58 3,717.58 100.00% 17,361.11
04.01.07 CONCRETO F'C=175 KG/CM2. - CABEZALES m3 106.42 106.42 100.00% 52,995.04
04.01.08 RELLENO CON MATERIAL PROPIO PARA ESTRUCTURAS m3 832.46 832.46 100.00% 26,488.88
04.01.09 MAMPOSTERIA CON PIEDRA EMBOQUILLADA m3 185.61 185.61 100.00% 87,197.72
4.02 CUNETAS 0.00 0.00
04.02.01 EXCAVACION MANUAL EN OBRAS DE ARTE m3 6,292.62 6,292.62 100.00% 206,586.71
04.02.02 ENCOFRADO Y DESENCOFRADO m2 7,206.69 7,206.69 100.00% 257,639.17
04.02.03 CONCRETO F'C=140 KG/CM2. m3 1,582.93 1,582.93 100.00% 717,542.17
04.02.04 JUNTA ASFALTICA m 7,219.74 7,219.74 100.00% 35,954.31
5 TRANSPORTE 0.00 0.00
5.01 TRANSPORTE DE MAT. EXCEDENTE DE CORTE HASTA 1 KM m3km 38,732.34 38,633.77 99.75% 241,847.40
5.02 TRANSPORTE DE MAT. EXCEDETE DE CORTE D > 1. KM. m3km 15,557.39 15,530.73 99.83% 22,674.89
5.03 TRANSPORTE DE MAT. SATURADO HASTA 1 KM m3km 999.56 999.56 100.00% 6,257.24
5.04 TRANSPORTE DE MAT. SATURADO D > 1 KM m3km 281.59 281.59 100.00% 411.12
5.05 TRANSP. DE MAT. PARA RELL. CON EXCED. DE CORTE HASTA 1 KM m3km 6,900.38 6,900.38 100.00% 43,196.37
5.06 TRANSP. DE MAT. PARA RELL. CON EXCED. DE CORTE D > 1 KM m3km 17,610.50 17,610.50 100.00% 25,711.33
5.07 TRANSPORTE DE MAT. ANTICONTAMINANTE HASTA 1 KM m3km 13,815.52 13,387.32 96.90% 83,804.62
5.08 TRANSPORTE DE MAT. ANTICONTAMINANTE D > 1KM m3km 264,338.66 257,629.64 97.46% 376,139.27
5.09 TRANSPORTE DE MAT. PARA AFIRMADO HASTA 1 KM. m3km 25,915.56 25,105.84 96.88% 157,162.56
5.10 TRANSPORTE DE MAT. PARA AFIRMADO > 1 KM. m3km 723,897.30 703,622.55 97.20% 1,027,288.91
6 SEALIZACION Y SEGURIDAD VIAL 0.00 0.00
6.01 SEALES PREVENTIVAS und 137.00 137.00 100.00% 64,179.02
6.02 SEALES REGLAMENTARIAS und 46.00 46.00 100.00% 18,541.68
6.03 SEAL INFORMATIVA m2 54.49 54.49 100.00% 23,908.58
6.04 ESTRUCTURA DE SOPORTE DE SEALES INFORMATIVAS m 290.88 290.88 100.00% 30,687.84
6.05 CIMENTACION Y MONTAJE DE SEAL INFORMATIVA und 60.00 60.00 100.00% 37,455.00
6.06 HITOS KILOMETRICOS und 20.00 20.00 100.00% 2,923.00
7 PLAN DE MANEJO AMBIENTAL 0.00 0.00
7.01 PROGRAMA DE MITIGACION AMBIENTAL 0.00 0.00
07.01.01 CONFORMACION DE DEPOSITOS DE MATERIAL EXCEDENTE m3 55,899.08 55,899.08 100.00% 66,519.91
07.01.02 ESTABILIZACION DE TALUDES CON REVEGETACION ha 2.50 2.50 100.00% 11,451.83
7.02 PROGRAMA DE MONITOREO AMBIENTAL 0.00 0.00
07.02.01 MONITOREO DE LA CALIDAD DEL AGUA und 3.00 3.00 100.00% 4,500.00
07.02.02 MONITOREO DE LA CALIDAD DEL AIRE und 3.00 3.00 100.00% 6,000.00
07.02.03 MONITOREO DE LA CALIDAD DE RUIDO und 3.00 3.00 100.00% 1,500.00
7.03 PROGRAMA DE MANEJO DE RESIDUOS 0.00 0.00
07.03.01 ADQUISICION DE CONTENEDORES und 12.00 12.00 100.00% 12,960.00
07.03.02 LETRINA SANITARIA PORTATIL und 3.00 3.00 100.00% 6,000.00
METRADOS TOTALES Y EJECUTADOS VALORIZADOS
CONTRATO PRINCIPAL

TOTAL VALORIZACION PRESUPUESTO


CONTRACTUAL
Cdigo Descripcin de la Partida Unid. METRADO
Metrado Parcial
18/40 S/.
7.04 PROGRAMA DE CIERRE Y ABANDONO 0.00 0.00
07.04.01 READECUACION AMBIENTAL DE CAMPAMENTOS HA 0.25 0.25 100.00% 3,310.89
07.04.02 READECUACION AMBIENTAL DE CANTERAS HA 0.50 0.50 100.00% 3,921.79
07.04.03 READECUACION AMBIENTAL DE BOTADEROS Y DME HA 0.50 0.50 100.00% 3,921.79
07.04.04 SEALIZACION AMBIENTAL und 6.00 6.00 100.00% 3,600.00
OBRA : "REHABILITACIN Y MEJORAMIENTO CARRETERA VECINAL ALTO CUUMBUZA-PUERTO BERMDEZ, DISTRITO DE ALTO BIAVO-CAMPANILLA, PROVINCIAS DE BELLAVISTA- MARISCAL CCERES- SAN MARTN"
CLIENTE : GOBIERNO REGIONAL DE SAN MARTN - PROYECTO ESPECIAL HUALLAGA CENTRAL Y BAJO MAYO
UBICACIN : DIST. DE ALTO BIAVO-CAMPANILLA, PROV. DE BELLAVISTA- MARISCAL CCERES, REGION SAN MARTN.
CONTRATISTA : CONSORCIO VIAL CAMPANILLA
SUPERVISION : CONSORCIO VIAL SUPERVISOR CUUMBUZA

VALORIZACIONES MENSUALES
19/40
CONTRATO PRINCIPAL
VALORIZ. N01 VALORIZ. N02 VALORIZ. N03 VALORIZ. N04
P.U. PARCIAL Aug-15 Sep-15 Oct-15 Nov-15
Cdigo Descripcin de la Partida Unid. METRADO
S/. S/. Metrado Parcial S/. Metrado Parcial S/. Metrado Parcial S/. Metrado
1 TRABAJOS PRELIMINARES
1.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 32,063.68 32,063.68 0.50 16,031.84 0.00 0.00 0.00 0.00 0.00
1.02 TRAZO Y REPLANTEO KM 19.06 1,045.20 19,921.51 7.62 7,964.42 0.00 0.00 0.38 397.18 2.00
2 MOVIMIENTO DE TIERRAS 0.00 0.00 0.00 0.00 0.00
2.01 DESBROCE Y LIMPIEZA EN ZONAS NO BOSCOSAS HA 3.69 3,530.42 13,027.25 1.50 5,295.63 0.00 0.00 0.50 1,765.21 0.00
2.02 EXCAVACION PARA EXPLANACIONES EN MATERIAL COMUN m3 100,065.38 4.56 456,298.13 16,821.88 76,707.75 19,826.25 90,407.70 46,351.28 211,361.84 0.00
2.03 REMOCION DE MATERIAL SATURADO m3 1,290.85 4.56 5,886.28 0.00 0.00 0.00 0.00 846.65 3,860.72 0.00
2.04 TERRAPLENES m3 18,948.94 7.14 135,295.43 840.72 6,002.74 2,317.18 16,544.68 5,159.00 36,835.26 0.00
2.05 PEDRAPLEN m3 1,290.85 67.88 87,622.90 0.00 0.00 0.00 0.00 846.65 57,470.60 0.00
2.06 PERFILADO Y COMPACTADO DE SUBRASANTE m2 72,871.49 1.59 115,865.67 0.00 0.00 17,257.27 27,439.06 26,613.93 42,316.15 0.00
3 AFIRMADOS 0.00 0.00 0.00 0.00 0.00
3.01 CAPA ANTICONTAMINANTE m3 13,815.50 21.79 301,039.75 0.00 0.00 3,375.28 73,547.35 3,911.30 85,227.23 0.00
3.02 AFIRMADO m3 25,915.55 21.55 558,480.10 0.00 0.00 0.00 0.00 0.00 0.00 9,703.71
4 DRENAJE 0.00 0.00 0.00 0.00 0.00
4.01 ALCANTARILLAS TMC 0.00 0.00 0.00 0.00 0.00
04.01.01 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS m3 2,435.25 8.26 20,115.17 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.01.02 TUB. CORRUGADA DE ACERO GALVAN. CIRCULAR DE = 0.91 m m 136.89 405.25 55,474.67 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.01.03 TUB. CORRUGADA DE ACERO GALVAN. CIRCULAR DE = 1.52 m m 97.20 830.17 80,692.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.01.04 TUB. CORRUGADA DE ACERO GALVAN. CIRCULAR DE = 1.83 m m 14.58 1,115.28 16,260.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.01.05 ENCOFRADO Y DESENCOFRADO CABEZALES m2 689.26 59.07 40,714.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.01.06 ACERO DE REFUERZO F'Y = 4200 KG/CM2 kg 3,717.58 4.67 17,361.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.01.07 CONCRETO F'C=175 KG/CM2. - CABEZALES m3 106.42 497.98 52,995.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.01.08 RELLENO CON MATERIAL PROPIO PARA ESTRUCTURAS m3 832.46 31.82 26,488.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.01.09 MAMPOSTERIA CON PIEDRA EMBOQUILLADA m3 185.61 469.79 87,197.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4.02 CUNETAS 0.00 0.00 0.00 0.00 0.00
04.02.01 EXCAVACION MANUAL EN OBRAS DE ARTE m3 6,292.62 32.83 206,586.71 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.02.02 ENCOFRADO Y DESENCOFRADO m2 7,206.69 35.75 257,639.17 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.02.03 CONCRETO F'C=140 KG/CM2. m3 1,582.93 453.30 717,542.17 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.02.04 JUNTA ASFALTICA m 7,219.74 4.98 35,954.31 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5 TRANSPORTE 0.00 0.00 0.00 0.00 0.00
5.01 TRANSPORTE DE MAT. EXCEDENTE DE CORTE HASTA 1 KM m3km 38,732.34 6.26 242,464.45 1,000.00 6,260.00 16,441.87 102,926.11 20,032.38 125,402.70 0.00
5.02 TRANSPORTE DE MAT. EXCEDETE DE CORTE D > 1. KM. m3km 15,557.39 1.46 22,713.79 0.00 0.00 6,807.25 9,938.59 8,678.84 12,671.11 0.00
5.03 TRANSPORTE DE MAT. SATURADO HASTA 1 KM m3km 999.56 6.26 6,257.25 0.00 0.00 0.00 0.00 637.62 3,991.50 0.00
5.04 TRANSPORTE DE MAT. SATURADO D > 1 KM m3km 281.59 1.46 411.12 0.00 0.00 0.00 0.00 281.59 411.12 0.00
5.05 TRANSP. DE MAT. PARA RELL. CON EXCED. DE CORTE HASTA 1 KM m3km 6,900.38 6.26 43,196.38 843.55 5,280.62 0.00 0.00 4,299.36 26,913.99 0.00
5.06 TRANSP. DE MAT. PARA RELL. CON EXCED. DE CORTE D > 1 KM m3km 17,610.50 1.46 25,711.33 142.66 208.28 0.00 0.00 15,957.69 23,298.23 0.00
5.07 TRANSPORTE DE MAT. ANTICONTAMINANTE HASTA 1 KM m3km 13,815.52 6.26 86,485.16 0.00 0.00 3,375.28 21,129.25 3,911.30 24,484.74 0.00
5.08 TRANSPORTE DE MAT. ANTICONTAMINANTE D > 1KM m3km 264,338.66 1.46 385,934.44 0.00 0.00 16,376.40 23,909.54 57,438.81 83,860.66 0.00
5.09 TRANSPORTE DE MAT. PARA AFIRMADO HASTA 1 KM. m3km 25,915.56 6.26 162,231.41 0.00 0.00 0.00 0.00 0.00 0.00 9,703.71
5.10 TRANSPORTE DE MAT. PARA AFIRMADO > 1 KM. m3km 723,897.30 1.46 1,056,890.06 0.00 0.00 0.00 0.00 0.00 0.00 192,811.88

19de40
OBRA : "REHABILITACIN Y MEJORAMIENTO CARRETERA VECINAL ALTO CUUMBUZA-PUERTO BERMDEZ, DISTRITO DE ALTO BIAVO-CAMPANILLA, PROVINCIAS DE BELLAVISTA- MARISCAL CCERES- SAN MARTN"
CLIENTE : GOBIERNO REGIONAL DE SAN MARTN - PROYECTO ESPECIAL HUALLAGA CENTRAL Y BAJO MAYO
UBICACIN : DIST. DE ALTO BIAVO-CAMPANILLA, PROV. DE BELLAVISTA- MARISCAL CCERES, REGION SAN MARTN.
CONTRATISTA : CONSORCIO VIAL CAMPANILLA
SUPERVISION : CONSORCIO VIAL SUPERVISOR CUUMBUZA

VALORIZACIONES MENSUALES
20/40
CONTRATO PRINCIPAL
VALORIZ. N01 VALORIZ. N02 VALORIZ. N03 VALORIZ. N04
P.U. PARCIAL Aug-15 Sep-15 Oct-15 Nov-15
Cdigo Descripcin de la Partida Unid. METRADO
S/. S/. Metrado Parcial S/. Metrado Parcial S/. Metrado Parcial S/. Metrado
6 SEALIZACION Y SEGURIDAD VIAL 0.00 0.00 0.00 0.00 0.00
6.01 SEALES PREVENTIVAS und 137.00 468.46 64,179.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6.02 SEALES REGLAMENTARIAS und 46.00 403.08 18,541.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6.03 SEAL INFORMATIVA m2 54.49 438.77 23,908.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6.04 ESTRUCTURA DE SOPORTE DE SEALES INFORMATIVAS m 290.88 105.50 30,687.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6.05 CIMENTACION Y MONTAJE DE SEAL INFORMATIVA und 60.00 624.25 37,455.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6.06 HITOS KILOMETRICOS und 20.00 146.15 2,923.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7 PLAN DE MANEJO AMBIENTAL 0.00 0.00 0.00 0.00 0.00
7.01 PROGRAMA DE MITIGACION AMBIENTAL 0.00 0.00 0.00 0.00 0.00
07.01.01 CONFORMACION DE DEPOSITOS DE MATERIAL EXCEDENTE m3 55,899.08 1.19 66,519.91 0.00 0.00 17,441.87 20,755.83 20,032.38 23,838.53 0.00
07.01.02 ESTABILIZACION DE TALUDES CON REVEGETACION ha 2.50 4,580.73 11,451.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7.02 PROGRAMA DE MONITOREO AMBIENTAL 0.00 0.00 0.00 0.00 0.00
07.02.01 MONITOREO DE LA CALIDAD DEL AGUA und 3.00 1,500.00 4,500.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.02.02 MONITOREO DE LA CALIDAD DEL AIRE und 3.00 2,000.00 6,000.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.02.03 MONITOREO DE LA CALIDAD DE RUIDO und 3.00 500.00 1,500.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7.03 PROGRAMA DE MANEJO DE RESIDUOS 0.00 0.00 0.00 0.00 0.00
07.03.01 ADQUISICION DE CONTENEDORES und 12.00 1,080.00 12,960.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.03.02 LETRINA SANITARIA PORTATIL und 3.00 2,000.00 6,000.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7.04 PROGRAMA DE CIERRE Y ABANDONO 0.00 0.00 0.00 0.00 0.00
07.04.01 READECUACION AMBIENTAL DE CAMPAMENTOS HA 0.25 13,243.57 3,310.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.04.02 READECUACION AMBIENTAL DE CANTERAS HA 0.50 7,843.57 3,921.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.04.03 READECUACION AMBIENTAL DE BOTADEROS Y DME HA 0.50 7,843.57 3,921.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.04.04 SEALIZACION AMBIENTAL und 6.00 600.00 3,600.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

COSTO DIRECTO 5,674,200.24 123,751.28 386,598.11 764,106.77


GASTOS GENERALES 10.12% 574,268.47 12,524.49 39,126.41 77,332.91
UTILIDAD 0.00% 0.00 0.00 0.00 0.00
SUB TOTAL 6,248,468.71 136,275.77 425,724.52 841,439.68

I.G.V. 0.00% 0.00 0.00 0.00 0.00


TOTAL 6,248,468.71 136,275.77 425,724.52 841,439.68

20de40
OBRA : "REHABILITACIN Y MEJORAMIENTO CARRETERA VECINAL ALTO CUUMBUZA-PUERTO BERMDEZ, DISTRITO DE ALTO BIAVO-CAMPANILLA, PROVINCIAS DE BELLAVISTA- MARISCAL CCERES- SAN MARTN"
CLIENTE : GOBIERNO REGIONAL DE SAN MARTN - PROYECTO ESPECIAL HUALLAGA CENTRAL Y BAJO MAYO
UBICACIN : DIST. DE ALTO BIAVO-CAMPANILLA, PROV. DE BELLAVISTA- MARISCAL CCERES, REGION SAN MARTN.
CONTRATISTA : CONSORCIO VIAL CAMPANILLA
SUPERVISION : CONSORCIO VIAL SUPERVISOR CUUMBUZA

VALORIZACIONES MENSUALES
21/40
CONTRATO PRINCIPAL
VALORIZ. N01 VALORIZ. N02 VALORIZ. N03 VALORIZ. N04
P.U. PARCIAL Aug-15 Sep-15 Oct-15 Nov-15
Cdigo Descripcin de la Partida Unid. METRADO
S/. S/. Metrado Parcial S/. Metrado Parcial S/. Metrado Parcial S/. Metrado
ADICIONAL DE OBRA N 01

P.U. PARCIAL Aug-15 Sep-15 Oct-15 Nov-15


Cdigo Descripcin de la Partida Unid. METRADO
S/. S/. Metrado Parcial S/. Metrado Parcial S/. Metrado Parcial S/. Metrado
2 MOVIMIENTO DE TIERRAS 0.00
2.03 REMOCION DE MATERIAL SATURADO m3 10,058.31 4.56 45,865.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2.05 PEDRAPLEN m3 10,058.31 67.88 682,758.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5 TRANSPORTE 0.00 0.00 0.00 0.00 0.00
5.03 TRANSPORTE DE MAT. SATURADO HASTA 1 KM m3km 5,274.74 6.26 33,019.87 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5.04 TRANSPORTE DE MAT. SATURADO D > 1 KM m3km 411.99 1.46 601.51 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7 PLAN DE MANEJO AMBIENTAL 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7.01 PROGRAMA DE MITIGACION AMBIENTAL 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.01.01 CONFORMACION DE DEPOSITOS DE MATERIAL EXCEDENTE m3 10,058.31 1.19 11,969.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00

COSTO DIRECTO 774,214.74 0.00 0.00 0.00


GASTOS GENERALES 8.08% 62,588.76 0.00 0.00 0.00
UTILIDAD 0.00% 0.00 0.00 0.00 0.00
SUB TOTAL 836,803.50 0.00 0.00 0.00

I.G.V. 0.00% 0.00 0.00 0.00 0.00


TOTAL 836,803.50 0.00 0.00 0.00

21de40
UZA-PUERTO
OBRA
BERMDEZ, DISTRITO
: "REHABILITACIN
DE ALTO BIAVO-CAMPANILLA,
Y MEJORAMIENTO CARRETERA
PROVINCIAS VECINAL
DE BELLAVISTA-
ALTO CUUMBUZA-PUERTO
MARISCAL CCERES-BERMDEZ,
SAN MARTN"
DISTRITO DE ALTO BIAVO-CAMPANILLA, PROVINCIAS DE BELLAVISTA- MARISCAL CCERES- SAN MARTN"
CLIENTE : GOBIERNO REGIONAL DE SAN MARTN - PROYECTO ESPECIAL HUALLAGA CENTRAL Y BAJO MAYO
UBICACIN : DIST. DE ALTO BIAVO-CAMPANILLA, PROV. DE BELLAVISTA- MARISCAL CCERES, REGION SAN MARTN.
CONTRATISTA : CONSORCIO VIAL CAMPANILLA
SUPERVISION : CONSORCIO VIAL SUPERVISOR CUUMBUZA

VALORIZACIONES MENSUALES
22/40
CONTRATO PRINCIPAL
VALORIZ.
RESUM. N04
VALORIZ VALORIZ. N05 VALORIZ. N06 VALORIZ. N07
P.U. PARCIAL Nov-15
JIH Dec-15 Jan-16 Feb-16
Cdigo Descripcin de la Partida Unid. METRADO
S/. S/. Parcial S/. Metrado Parcial S/. Metrado Parcial S/. Metrado Parcial S/.
1 TRABAJOS PRELIMINARES
1.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 32,063.68 32,063.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00
1.02 TRAZO Y REPLANTEO KM 19.06 1,045.20 19,921.51 2,090.40 1.00 1,045.20 3.00 3,135.60 0.00 0.00
2 MOVIMIENTO DE TIERRAS 0.00 0.00 0.00 0.00
2.01 DESBROCE Y LIMPIEZA EN ZONAS NO BOSCOSAS HA 3.69 3,530.42 13,027.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2.02 EXCAVACION PARA EXPLANACIONES EN MATERIAL COMUN m3 100,065.38 4.56 456,298.13 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2.03 REMOCION DE MATERIAL SATURADO m3 1,290.85 4.56 5,886.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2.04 TERRAPLENES m3 18,948.94 7.14 135,295.43 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2.05 PEDRAPLEN m3 1,290.85 67.88 87,622.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2.06 PERFILADO Y COMPACTADO DE SUBRASANTE m2 72,871.49 1.59 115,865.67 0.00 0.00 0.00 0.00 0.00 0.00 0.00
3 AFIRMADOS 0.00 0.00 0.00 0.00
3.01 CAPA ANTICONTAMINANTE m3 13,815.50 21.79 301,039.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00
3.02 AFIRMADO m3 25,915.55 21.55 558,480.10 209,114.95 268.92 5,795.23 3,301.68 71,151.20 0.00 0.00
4 DRENAJE 0.00 0.00 0.00 0.00
4.01 ALCANTARILLAS TMC 0.00 0.00 0.00 0.00
04.01.01 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS m3 2,435.25 8.26 20,115.17 0.00 0.00 0.00 145.76 1,203.98 142.53 1,177.30
04.01.02 TUB. CORRUGADA DE ACERO GALVAN. CIRCULAR DE = 0.91 m m 136.89 405.25 55,474.67 0.00 0.00 0.00 7.29 2,954.27 -7.29 -2,954.27
04.01.03 TUB. CORRUGADA DE ACERO GALVAN. CIRCULAR DE = 1.52 m m 97.20 830.17 80,692.52 0.00 0.00 0.00 26.73 22,190.44 0.00 0.00
04.01.04 TUB. CORRUGADA DE ACERO GALVAN. CIRCULAR DE = 1.83 m m 14.58 1,115.28 16,260.78 0.00 0.00 0.00 7.29 8,130.39 0.00 0.00
04.01.05 ENCOFRADO Y DESENCOFRADO CABEZALES m2 689.26 59.07 40,714.59 0.00 0.00 0.00 0.00 0.00 155.03 9,157.62
04.01.06 ACERO DE REFUERZO F'Y = 4200 KG/CM2 kg 3,717.58 4.67 17,361.10 0.00 0.00 0.00 0.00 0.00 882.80 4,122.68
04.01.07 CONCRETO F'C=175 KG/CM2. - CABEZALES m3 106.42 497.98 52,995.03 0.00 0.00 0.00 0.00 0.00 26.06 12,977.36
04.01.08 RELLENO CON MATERIAL PROPIO PARA ESTRUCTURAS m3 832.46 31.82 26,488.88 0.00 0.00 0.00 0.00 0.00 175.60 5,587.59
04.01.09 MAMPOSTERIA CON PIEDRA EMBOQUILLADA m3 185.61 469.79 87,197.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4.02 CUNETAS 0.00 0.00 0.00 0.00
04.02.01 EXCAVACION MANUAL EN OBRAS DE ARTE m3 6,292.62 32.83 206,586.71 0.00 0.00 0.00 948.03 31,123.82 -948.03 -31,123.82
04.02.02 ENCOFRADO Y DESENCOFRADO m2 7,206.69 35.75 257,639.17 0.00 0.00 0.00 0.00 0.00 75.53 2,700.20
04.02.03 CONCRETO F'C=140 KG/CM2. m3 1,582.93 453.30 717,542.17 0.00 0.00 0.00 0.00 0.00 16.59 7,520.25
04.02.04 JUNTA ASFALTICA m 7,219.74 4.98 35,954.31 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5 TRANSPORTE 0.00 0.00 0.00 0.00
5.01 TRANSPORTE DE MAT. EXCEDENTE DE CORTE HASTA 1 KM m3km 38,732.34 6.26 242,464.45 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5.02 TRANSPORTE DE MAT. EXCEDETE DE CORTE D > 1. KM. m3km 15,557.39 1.46 22,713.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5.03 TRANSPORTE DE MAT. SATURADO HASTA 1 KM m3km 999.56 6.26 6,257.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5.04 TRANSPORTE DE MAT. SATURADO D > 1 KM m3km 281.59 1.46 411.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5.05 TRANSP. DE MAT. PARA RELL. CON EXCED. DE CORTE HASTA 1 KM m3km 6,900.38 6.26 43,196.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5.06 TRANSP. DE MAT. PARA RELL. CON EXCED. DE CORTE D > 1 KM m3km 17,610.50 1.46 25,711.33 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5.07 TRANSPORTE DE MAT. ANTICONTAMINANTE HASTA 1 KM m3km 13,815.52 6.26 86,485.16 0.00 0.00 0.00 0.00 0.00 4,050.00 25,353.00
5.08 TRANSPORTE DE MAT. ANTICONTAMINANTE D > 1KM m3km 264,338.66 1.46 385,934.44 0.00 0.00 0.00 0.00 0.00 77,274.00 112,820.04
5.09 TRANSPORTE DE MAT. PARA AFIRMADO HASTA 1 KM. m3km 25,915.56 6.26 162,231.41 60,745.22 268.92 1,683.44 7,301.68 45,708.52 4,755.00 29,766.30
5.10 TRANSPORTE DE MAT. PARA AFIRMADO > 1 KM. m3km 723,897.30 1.46 1,056,890.06 281,505.34 7,389.90 10,789.25 161,321.36 235,529.19 132,569.40 193,551.32

22de40
UZA-PUERTO
OBRA
BERMDEZ, DISTRITO
: "REHABILITACIN
DE ALTO BIAVO-CAMPANILLA,
Y MEJORAMIENTO CARRETERA
PROVINCIAS VECINAL
DE BELLAVISTA-
ALTO CUUMBUZA-PUERTO
MARISCAL CCERES-BERMDEZ,
SAN MARTN"
DISTRITO DE ALTO BIAVO-CAMPANILLA, PROVINCIAS DE BELLAVISTA- MARISCAL CCERES- SAN MARTN"
CLIENTE : GOBIERNO REGIONAL DE SAN MARTN - PROYECTO ESPECIAL HUALLAGA CENTRAL Y BAJO MAYO
UBICACIN : DIST. DE ALTO BIAVO-CAMPANILLA, PROV. DE BELLAVISTA- MARISCAL CCERES, REGION SAN MARTN.
CONTRATISTA : CONSORCIO VIAL CAMPANILLA
SUPERVISION : CONSORCIO VIAL SUPERVISOR CUUMBUZA

VALORIZACIONES MENSUALES
23/40
CONTRATO PRINCIPAL
VALORIZ.
RESUM. N04
VALORIZ VALORIZ. N05 VALORIZ. N06 VALORIZ. N07
P.U. PARCIAL Nov-15
JIH Dec-15 Jan-16 Feb-16
Cdigo Descripcin de la Partida Unid. METRADO
S/. S/. Parcial S/. Metrado Parcial S/. Metrado Parcial S/. Metrado Parcial S/.
6 SEALIZACION Y SEGURIDAD VIAL 0.00 0.00 0.00 0.00
6.01 SEALES PREVENTIVAS und 137.00 468.46 64,179.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6.02 SEALES REGLAMENTARIAS und 46.00 403.08 18,541.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6.03 SEAL INFORMATIVA m2 54.49 438.77 23,908.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6.04 ESTRUCTURA DE SOPORTE DE SEALES INFORMATIVAS m 290.88 105.50 30,687.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6.05 CIMENTACION Y MONTAJE DE SEAL INFORMATIVA und 60.00 624.25 37,455.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6.06 HITOS KILOMETRICOS und 20.00 146.15 2,923.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7 PLAN DE MANEJO AMBIENTAL 0.00 0.00 0.00 0.00
7.01 PROGRAMA DE MITIGACION AMBIENTAL 0.00 0.00 0.00 0.00
07.01.01 CONFORMACION DE DEPOSITOS DE MATERIAL EXCEDENTE m3 55,899.08 1.19 66,519.91 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.01.02 ESTABILIZACION DE TALUDES CON REVEGETACION ha 2.50 4,580.73 11,451.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7.02 PROGRAMA DE MONITOREO AMBIENTAL 0.00 0.00 0.00 0.00
07.02.01 MONITOREO DE LA CALIDAD DEL AGUA und 3.00 1,500.00 4,500.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.02.02 MONITOREO DE LA CALIDAD DEL AIRE und 3.00 2,000.00 6,000.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.02.03 MONITOREO DE LA CALIDAD DE RUIDO und 3.00 500.00 1,500.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7.03 PROGRAMA DE MANEJO DE RESIDUOS 0.00 0.00 0.00 0.00
07.03.01 ADQUISICION DE CONTENEDORES und 12.00 1,080.00 12,960.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.03.02 LETRINA SANITARIA PORTATIL und 3.00 2,000.00 6,000.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7.04 PROGRAMA DE CIERRE Y ABANDONO 0.00 0.00 0.00 0.00
07.04.01 READECUACION AMBIENTAL DE CAMPAMENTOS HA 0.25 13,243.57 3,310.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.04.02 READECUACION AMBIENTAL DE CANTERAS HA 0.50 7,843.57 3,921.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.04.03 READECUACION AMBIENTAL DE BOTADEROS Y DME HA 0.50 7,843.57 3,921.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.04.04 SEALIZACION AMBIENTAL und 6.00 600.00 3,600.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

COSTO DIRECTO 5,674,200.24 553,455.91 19,313.12 421,127.41 370,655.57


GASTOS GENERALES 10.12% 574,268.47 56,013.58 1,954.62 42,621.02 37,512.92
UTILIDAD 0.00% 0.00 0.00 0.00 0.00 0.00
SUB TOTAL 6,248,468.71
### 609,469.49 21,267.74 463,748.43 408,168.49

I.G.V. 0.00% 0.00 0.00 0.00 0.00 0.00


TOTAL 6,248,468.71 609,469.49 21,267.74 463,748.43 408,168.49

23de40
UZA-PUERTO
OBRA
BERMDEZ, DISTRITO
: "REHABILITACIN
DE ALTO BIAVO-CAMPANILLA,
Y MEJORAMIENTO CARRETERA
PROVINCIAS VECINAL
DE BELLAVISTA-
ALTO CUUMBUZA-PUERTO
MARISCAL CCERES-BERMDEZ,
SAN MARTN"
DISTRITO DE ALTO BIAVO-CAMPANILLA, PROVINCIAS DE BELLAVISTA- MARISCAL CCERES- SAN MARTN"
CLIENTE : GOBIERNO REGIONAL DE SAN MARTN - PROYECTO ESPECIAL HUALLAGA CENTRAL Y BAJO MAYO
UBICACIN : DIST. DE ALTO BIAVO-CAMPANILLA, PROV. DE BELLAVISTA- MARISCAL CCERES, REGION SAN MARTN.
CONTRATISTA : CONSORCIO VIAL CAMPANILLA
SUPERVISION : CONSORCIO VIAL SUPERVISOR CUUMBUZA

VALORIZACIONES MENSUALES
24/40
CONTRATO PRINCIPAL
VALORIZ.
RESUM. N04
VALORIZ VALORIZ. N05 VALORIZ. N06 VALORIZ. N07
P.U. PARCIAL Nov-15
JIH Dec-15 Jan-16 Feb-16
Cdigo Descripcin de la Partida Unid. METRADO
S/. S/. Parcial S/. Metrado Parcial S/. Metrado Parcial S/. Metrado Parcial S/.
ADICIONAL DE OBRA N 01

P.U. PARCIAL Nov-15 Dec-15 Jan-16 Feb-16


Cdigo Descripcin de la Partida Unid. METRADO
S/. S/. Parcial S/. Metrado Parcial S/. Metrado Parcial S/. Metrado Parcial S/.
2 MOVIMIENTO DE TIERRAS 0.00
2.03 REMOCION DE MATERIAL SATURADO m3 10,058.31 4.56 45,865.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2.05 PEDRAPLEN m3 10,058.31 67.88 682,758.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5 TRANSPORTE 0.00 0.00 0.00 0.00
5.03 TRANSPORTE DE MAT. SATURADO HASTA 1 KM m3km 5,274.74 6.26 33,019.87 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5.04 TRANSPORTE DE MAT. SATURADO D > 1 KM m3km 411.99 1.46 601.51 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7 PLAN DE MANEJO AMBIENTAL 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7.01 PROGRAMA DE MITIGACION AMBIENTAL 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.01.01 CONFORMACION DE DEPOSITOS DE MATERIAL EXCEDENTE m3 10,058.31 1.19 11,969.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00

COSTO DIRECTO 774,214.74 0.00 0.00 0.00 0.00


GASTOS GENERALES 8.08% 62,588.76 0.00 0.00 0.00 0.00
UTILIDAD 0.00% 0.00 0.00 0.00 0.00 0.00
SUB TOTAL 836,803.50 0.00 0.00 0.00 0.00

I.G.V. 0.00% 0.00 0.00 0.00 0.00 0.00


TOTAL ###
836,803.50 0.00 0.00 0.00 0.00

24de40
OBRA : "REHABILITACIN Y MEJORAMIENTO CARRETERA VECINAL ALTO CUUMBUZA-PUERTO BERMDEZ, DISTRITO DE ALTO BIAVO-CAMPANILLA, PROVINCIAS DE BELLAVISTA- MARISCAL CCERES- SAN MARTN"
CLIENTE : GOBIERNO REGIONAL DE SAN MARTN - PROYECTO ESPECIAL HUALLAGA CENTRAL Y BAJO MAYO
UBICACIN : DIST. DE ALTO BIAVO-CAMPANILLA, PROV. DE BELLAVISTA- MARISCAL CCERES, REGION SAN MARTN.
CONTRATISTA : CONSORCIO VIAL CAMPANILLA
SUPERVISION : CONSORCIO VIAL SUPERVISOR CUUMBUZA

VALORIZACIONES MENSUALES
25/40
CONTRATO PRINCIPAL
VALORIZ. N08
RESUM. VALORIZ VALORIZ. N09 VALORIZ. N10 VALORIZ. N11
P.U. PARCIAL JIH Mar-16 Apr-16 May-16 Jun-16
Cdigo Descripcin de la Partida Unid. METRADO
S/. S/. Metrado Parcial S/. Metrado Parcial S/. Metrado Parcial S/. Metrado
1 TRABAJOS PRELIMINARES
1.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 32,063.68 32,063.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00
1.02 TRAZO Y REPLANTEO KM 19.06 1,045.20 19,921.51 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2 MOVIMIENTO DE TIERRAS 0.00 0.00 0.00 0.00 0.00
2.01 DESBROCE Y LIMPIEZA EN ZONAS NO BOSCOSAS HA 3.69 3,530.42 13,027.25 0.00 0.00 0.00 0.00 1.69 5,966.41 0.00
2.02 EXCAVACION PARA EXPLANACIONES EN MATERIAL COMUN m3 100,065.38 4.56 456,298.13 675.43 3,079.96 2,718.08 12,394.44 13,672.47 62,346.44 0.00
2.03 REMOCION DE MATERIAL SATURADO m3 1,290.85 4.56 5,886.28 61.20 279.07 0.00 0.00 383.00 1,746.48 0.00
2.04 TERRAPLENES m3 18,948.94 7.14 135,295.43 617.95 4,412.16 1,486.38 10,612.75 8,527.71 60,887.82 0.00
2.05 PEDRAPLEN m3 1,290.85 67.88 87,622.90 61.20 4,154.26 0.00 0.00 383.00 25,998.04 0.00
2.06 PERFILADO Y COMPACTADO DE SUBRASANTE m2 72,871.49 1.59 115,865.67 1,592.03 2,531.33 5,626.95 8,946.85 11,293.55 17,956.74 10,487.76
3 AFIRMADOS 0.00 0.00 0.00 0.00 0.00
3.01 CAPA ANTICONTAMINANTE m3 13,815.50 21.79 301,039.75 708.90 15,446.93 1,435.68 31,283.47 2,222.57 48,429.80 2,161.77
3.02 AFIRMADO m3 25,915.55 21.55 558,480.10 936.74 20,186.75 2,691.35 57,998.59 0.00 0.00 0.00
4 DRENAJE 0.00 0.00 0.00 0.00 0.00
4.01 ALCANTARILLAS TMC 0.00 0.00 0.00 0.00 0.00
04.01.01 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS m3 2,435.25 8.26 20,115.17 106.20 877.21 0.00 0.00 0.00 0.00 102.03
04.01.02 TUB. CORRUGADA DE ACERO GALVAN. CIRCULAR DE = 0.91 m m 136.89 405.25 55,474.67 10.53 4,267.28 0.00 0.00 0.00 0.00 0.00
04.01.03 TUB. CORRUGADA DE ACERO GALVAN. CIRCULAR DE = 1.52 m m 97.20 830.17 80,692.52 7.29 6,051.94 0.00 0.00 0.00 0.00 41.31
04.01.04 TUB. CORRUGADA DE ACERO GALVAN. CIRCULAR DE = 1.83 m m 14.58 1,115.28 16,260.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.01.05 ENCOFRADO Y DESENCOFRADO CABEZALES m2 689.26 59.07 40,714.59 55.57 3,282.52 0.00 0.00 0.00 0.00 0.00
04.01.06 ACERO DE REFUERZO F'Y = 4200 KG/CM2 kg 3,717.58 4.67 17,361.10 150.46 702.65 0.00 0.00 0.00 0.00 0.00
04.01.07 CONCRETO F'C=175 KG/CM2. - CABEZALES m3 106.42 497.98 52,995.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.01.08 RELLENO CON MATERIAL PROPIO PARA ESTRUCTURAS m3 832.46 31.82 26,488.88 53.92 1,715.73 0.00 0.00 0.00 0.00 83.74
04.01.09 MAMPOSTERIA CON PIEDRA EMBOQUILLADA m3 185.61 469.79 87,197.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4.02 CUNETAS 0.00 0.00 0.00 0.00 0.00
04.02.01 EXCAVACION MANUAL EN OBRAS DE ARTE m3 6,292.62 32.83 206,586.71 1,384.95 45,467.91 1,990.70 65,354.68 251.60 8,260.03 1,319.00
04.02.02 ENCOFRADO Y DESENCOFRADO m2 7,206.69 35.75 257,639.17 1,510.60 54,003.95 2,265.90 81,005.93 302.12 10,800.79 1,510.60
04.02.03 CONCRETO F'C=140 KG/CM2. m3 1,582.93 453.30 717,542.17 331.80 150,404.94 497.70 225,607.41 66.36 30,080.99 331.80
04.02.04 JUNTA ASFALTICA m 7,219.74 4.98 35,954.31 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5 TRANSPORTE 0.00 0.00 0.00 0.00 0.00
5.01 TRANSPORTE DE MAT. EXCEDENTE DE CORTE HASTA 1 KM m3km 38,732.34 6.26 242,464.45 49.61 310.56 69.13 432.75 1,139.35 7,132.33 0.00
5.02 TRANSPORTE DE MAT. EXCEDETE DE CORTE D > 1. KM. m3km 15,557.39 1.46 22,713.79 0.00 0.00 14.25 20.81 57.05 83.30 0.00
5.03 TRANSPORTE DE MAT. SATURADO HASTA 1 KM m3km 999.56 6.26 6,257.25 0.00 0.00 0.00 0.00 361.94 2,265.74 0.00
5.04 TRANSPORTE DE MAT. SATURADO D > 1 KM m3km 281.59 1.46 411.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5.05 TRANSP. DE MAT. PARA RELL. CON EXCED. DE CORTE HASTA 1 KM m3km 6,900.38 6.26 43,196.38 0.00 0.00 0.00 0.00 1,757.47 11,001.76 0.00
5.06 TRANSP. DE MAT. PARA RELL. CON EXCED. DE CORTE D > 1 KM m3km 17,610.50 1.46 25,711.33 0.00 0.00 0.00 0.00 1,510.15 2,204.82 0.00
5.07 TRANSPORTE DE MAT. ANTICONTAMINANTE HASTA 1 KM m3km 13,815.52 6.26 86,485.16 0.00 0.00 1,000.00 6,260.00 739.47 4,629.08 739.47
5.08 TRANSPORTE DE MAT. ANTICONTAMINANTE D > 1KM m3km 264,338.66 1.46 385,934.44 0.00 0.00 19,080.00 27,856.80 47,084.73 68,743.71 47,084.72
5.09 TRANSPORTE DE MAT. PARA AFIRMADO HASTA 1 KM. m3km 25,915.56 6.26 162,231.41 0.00 0.00 1,000.00 6,260.00 0.00 0.00 0.00
5.10 TRANSPORTE DE MAT. PARA AFIRMADO > 1 KM. m3km 723,897.30 1.46 1,056,890.06 0.00 0.00 27,880.00 40,704.80 0.00 0.00 0.00

25de40
OBRA : "REHABILITACIN Y MEJORAMIENTO CARRETERA VECINAL ALTO CUUMBUZA-PUERTO BERMDEZ, DISTRITO DE ALTO BIAVO-CAMPANILLA, PROVINCIAS DE BELLAVISTA- MARISCAL CCERES- SAN MARTN"
CLIENTE : GOBIERNO REGIONAL DE SAN MARTN - PROYECTO ESPECIAL HUALLAGA CENTRAL Y BAJO MAYO
UBICACIN : DIST. DE ALTO BIAVO-CAMPANILLA, PROV. DE BELLAVISTA- MARISCAL CCERES, REGION SAN MARTN.
CONTRATISTA : CONSORCIO VIAL CAMPANILLA
SUPERVISION : CONSORCIO VIAL SUPERVISOR CUUMBUZA

VALORIZACIONES MENSUALES
26/40
CONTRATO PRINCIPAL
VALORIZ. N08
RESUM. VALORIZ VALORIZ. N09 VALORIZ. N10 VALORIZ. N11
P.U. PARCIAL JIH Mar-16 Apr-16 May-16 Jun-16
Cdigo Descripcin de la Partida Unid. METRADO
S/. S/. Metrado Parcial S/. Metrado Parcial S/. Metrado Parcial S/. Metrado
6 SEALIZACION Y SEGURIDAD VIAL 0.00 0.00 0.00 0.00 0.00
6.01 SEALES PREVENTIVAS und 137.00 468.46 64,179.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6.02 SEALES REGLAMENTARIAS und 46.00 403.08 18,541.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6.03 SEAL INFORMATIVA m2 54.49 438.77 23,908.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6.04 ESTRUCTURA DE SOPORTE DE SEALES INFORMATIVAS m 290.88 105.50 30,687.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6.05 CIMENTACION Y MONTAJE DE SEAL INFORMATIVA und 60.00 624.25 37,455.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6.06 HITOS KILOMETRICOS und 20.00 146.15 2,923.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7 PLAN DE MANEJO AMBIENTAL 0.00 0.00 0.00 0.00 0.00
7.01 PROGRAMA DE MITIGACION AMBIENTAL 0.00 0.00 0.00 0.00 0.00
07.01.01 CONFORMACION DE DEPOSITOS DE MATERIAL EXCEDENTE m3 55,899.08 1.19 66,519.91 0.00 0.00 0.00 0.00 15,000.00 17,850.00 0.00
07.01.02 ESTABILIZACION DE TALUDES CON REVEGETACION ha 2.50 4,580.73 11,451.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7.02 PROGRAMA DE MONITOREO AMBIENTAL 0.00 0.00 0.00 0.00 0.00
07.02.01 MONITOREO DE LA CALIDAD DEL AGUA und 3.00 1,500.00 4,500.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.02.02 MONITOREO DE LA CALIDAD DEL AIRE und 3.00 2,000.00 6,000.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.02.03 MONITOREO DE LA CALIDAD DE RUIDO und 3.00 500.00 1,500.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7.03 PROGRAMA DE MANEJO DE RESIDUOS 0.00 0.00 0.00 0.00 0.00
07.03.01 ADQUISICION DE CONTENEDORES und 12.00 1,080.00 12,960.00 0.00 0.00 0.00 0.00 0.00 0.00 6.00
07.03.02 LETRINA SANITARIA PORTATIL und 3.00 2,000.00 6,000.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00
7.04 PROGRAMA DE CIERRE Y ABANDONO 0.00 0.00 0.00 0.00 0.00
07.04.01 READECUACION AMBIENTAL DE CAMPAMENTOS HA 0.25 13,243.57 3,310.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.04.02 READECUACION AMBIENTAL DE CANTERAS HA 0.50 7,843.57 3,921.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.04.03 READECUACION AMBIENTAL DE BOTADEROS Y DME HA 0.50 7,843.57 3,921.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.04.04 SEALIZACION AMBIENTAL und 6.00 600.00 3,600.00 0.00 0.00 0.00 0.00 0.00 0.00 6.00

COSTO DIRECTO 5,674,200.24 317,175.15 574,739.28 386,384.28 386,384.28


GASTOS GENERALES 10.12% 574,268.47 32,100.33 58,167.61 39,104.77 39,104.77
UTILIDAD 0.00% 0.00 0.00 0.00 0.00
SUB TOTAL 6,248,468.71
### 349,275.48 632,906.89 425,489.05 425,489.05

I.G.V. 0.00% 0.00 0.00 0.00 0.00


TOTAL 6,248,468.71 349,275.48 632,906.89 425,489.05
0.00

26de40
OBRA : "REHABILITACIN Y MEJORAMIENTO CARRETERA VECINAL ALTO CUUMBUZA-PUERTO BERMDEZ, DISTRITO DE ALTO BIAVO-CAMPANILLA, PROVINCIAS DE BELLAVISTA- MARISCAL CCERES- SAN MARTN"
CLIENTE : GOBIERNO REGIONAL DE SAN MARTN - PROYECTO ESPECIAL HUALLAGA CENTRAL Y BAJO MAYO
UBICACIN : DIST. DE ALTO BIAVO-CAMPANILLA, PROV. DE BELLAVISTA- MARISCAL CCERES, REGION SAN MARTN.
CONTRATISTA : CONSORCIO VIAL CAMPANILLA
SUPERVISION : CONSORCIO VIAL SUPERVISOR CUUMBUZA

VALORIZACIONES MENSUALES
27/40
CONTRATO PRINCIPAL
VALORIZ. N08
RESUM. VALORIZ VALORIZ. N09 VALORIZ. N10 VALORIZ. N11
P.U. PARCIAL JIH Mar-16 Apr-16 May-16 Jun-16
Cdigo Descripcin de la Partida Unid. METRADO
S/. S/. Metrado Parcial S/. Metrado Parcial S/. Metrado Parcial S/. Metrado
ADICIONAL DE OBRA N 01
VALORIZACION N01 VALORIZACION N02 VALORIZACION N3

P.U. PARCIAL Mar-16 Apr-16 May-16 Jun-16


Cdigo Descripcin de la Partida Unid. METRADO
S/. S/. Metrado Parcial S/. Metrado Parcial S/. Metrado Parcial S/. Metrado
2 MOVIMIENTO DE TIERRAS 0.00
2.03 REMOCION DE MATERIAL SATURADO m3 10,058.31 4.56 45,865.89 2,106.20 9,604.27 573.55 2,615.39 7,378.56 33,646.23 0.00
2.05 PEDRAPLEN m3 10,058.31 67.88 682,758.08 2,106.20 142,968.86 573.55 38,932.57 7,378.56 500,856.65 0.00
5 TRANSPORTE 0.00 0.00 0.00 0.00 0.00
5.03 TRANSPORTE DE MAT. SATURADO HASTA 1 KM m3km 5,274.74 6.26 33,019.87 765.83 4,794.10 720.72 4,511.71 3,788.19 23,714.07 0.00
5.04 TRANSPORTE DE MAT. SATURADO D > 1 KM m3km 411.99 1.46 601.51 19.35 28.25 61.13 89.25 331.51 484.00 0.00
7 PLAN DE MANEJO AMBIENTAL 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7.01 PROGRAMA DE MITIGACION AMBIENTAL 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.01.01 CONFORMACION DE DEPOSITOS DE MATERIAL EXCEDENTE m3 10,058.31 1.19 11,969.39 2,106.20 2,506.38 573.55 682.52 7,378.56 8,780.49 0.00

COSTO DIRECTO 774,214.74 159,901.86 46,831.44 567,481.44


GASTOS GENERALES 8.08% 62,588.76 12,926.72 3,785.93 45,876.11
UTILIDAD 0.00% 0.00 0.00 0.00 0.00
SUB TOTAL 836,803.50 172,828.58 50,617.37 613,357.55

I.G.V. 0.00% 0.00 0.00 0.00 0.00


TOTAL ###
836,803.50 172,828.58 50,617.37 613,357.55

27de40
OBRA : "REHABILITACIN Y MEJORAMIENTO CARRETERA VECINAL ALTO CUUMBUZA-PUERTO BERMDEZ, DISTRITO DE ALTO BIAVO-CAMPANILLA, PROVINCIAS DE BELLAVISTA- MARISCAL CCERES- SAN MARTN"
CLIENTE : GOBIERNO REGIONAL DE SAN MARTN - PROYECTO ESPECIAL HUALLAGA CENTRAL Y BAJO MAYO
UBICACIN : DIST. DE ALTO BIAVO-CAMPANILLA, PROV. DE BELLAVISTA- MARISCAL CCERES, REGION SAN MARTN.
CONTRATISTA : CONSORCIO VIAL CAMPANILLA
SUPERVISION : CONSORCIO VIAL SUPERVISOR CUUMBUZA

VALORIZACIONES MENSUALES
28/40
CONTRATO PRINCIPAL
VALORIZ.
RESUM. N11
VALORIZ VALORIZ. N12 VALORIZ. N13 TOTAL VALORIZADO
Jun-16
JIH Jul-16 Aug-16 ACUMULADO
P.U. PARCIAL
Cdigo Descripcin de la Partida Unid. METRADO
S/. S/. Parcial S/. Metrado Parcial S/. Metrado Parcial S/. Metrado Parcial S/.
1 TRABAJOS PRELIMINARES
1.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 32,063.68 32,063.68 0.00 0.00 0.00 0.50 16,031.84 1.00 32,063.68
1.02 TRAZO Y REPLANTEO KM 19.06 1,045.20 19,921.51 0.00 3.00 3,135.60 1.97 2,059.04 18.97 19,827.44
2 MOVIMIENTO DE TIERRAS 0.00 0.00 0.00 0.00 0.00
2.01 DESBROCE Y LIMPIEZA EN ZONAS NO BOSCOSAS HA 3.69 3,530.42 13,027.25 0.00 0.00 0.00 -0.03 -105.91 3.66 12,921.34
2.02 EXCAVACION PARA EXPLANACIONES EN MATERIAL COMUN m3 100,065.38 4.56 456,298.13 0.00 0.00 0.00 -704.32 -3,211.70 99,361.06 453,086.43
2.03 REMOCION DE MATERIAL SATURADO m3 1,290.85 4.56 5,886.28 0.00 0.00 0.00 0.00 0.00 1,290.85 5,886.27
2.04 TERRAPLENES m3 18,948.94 7.14 135,295.43 0.00 0.00 0.00 -381.25 -2,722.13 18,567.69 132,573.28
2.05 PEDRAPLEN m3 1,290.85 67.88 87,622.90 0.00 0.00 0.00 0.00 0.00 1,290.85 87,622.90
2.06 PERFILADO Y COMPACTADO DE SUBRASANTE m2 72,871.49 1.59 115,865.67 16,675.54 0.00 0.00 -752.35 -1,196.24 72,119.14 114,669.43
3 AFIRMADOS 0.00 0.00 0.00 0.00 0.00
3.01 CAPA ANTICONTAMINANTE m3 13,815.50 21.79 301,039.75 47,104.97 0.00 0.00 -177.17 -3,860.53 13,638.33 297,179.22
3.02 AFIRMADO m3 25,915.55 21.55 558,480.10 0.00 7,433.90 160,200.55 1,245.97 26,850.65 25,582.27 551,297.92
4 DRENAJE 0.00 0.00 0.00 0.00 0.00
4.01 ALCANTARILLAS TMC 0.00 0.00 0.00 0.00 0.00
04.01.01 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS m3 2,435.25 8.26 20,115.17 842.77 662.75 5,474.32 1,275.98 10,539.59 2,435.25 20,115.17
04.01.02 TUB. CORRUGADA DE ACERO GALVAN. CIRCULAR DE = 0.91 m m 136.89 405.25 55,474.67 0.00 118.26 47,924.87 8.10 3,282.53 136.89 55,474.68
04.01.03 TUB. CORRUGADA DE ACERO GALVAN. CIRCULAR DE = 1.52 m m 97.20 830.17 80,692.52 34,294.32 21.87 18,155.82 0.00 0.00 97.20 80,692.52
04.01.04 TUB. CORRUGADA DE ACERO GALVAN. CIRCULAR DE = 1.83 m m 14.58 1,115.28 16,260.78 0.00 7.29 8,130.39 0.00 0.00 14.58 16,260.78
04.01.05 ENCOFRADO Y DESENCOFRADO CABEZALES m2 689.26 59.07 40,714.59 0.00 403.77 23,850.69 74.89 4,423.75 689.26 40,714.58
04.01.06 ACERO DE REFUERZO F'Y = 4200 KG/CM2 kg 3,717.58 4.67 17,361.10 0.00 2,137.56 9,982.41 546.76 2,553.37 3,717.58 17,361.11
04.01.07 CONCRETO F'C=175 KG/CM2. - CABEZALES m3 106.42 497.98 52,995.03 0.00 69.18 34,450.26 11.18 5,567.42 106.42 52,995.04
04.01.08 RELLENO CON MATERIAL PROPIO PARA ESTRUCTURAS m3 832.46 31.82 26,488.88 2,664.61 467.34 14,870.76 51.86 1,650.19 832.46 26,488.88
04.01.09 MAMPOSTERIA CON PIEDRA EMBOQUILLADA m3 185.61 469.79 87,197.72 0.00 0.00 0.00 185.61 87,197.72 185.61 87,197.72
4.02 CUNETAS 0.00 0.00 0.00 0.00 0.00
04.02.01 EXCAVACION MANUAL EN OBRAS DE ARTE m3 6,292.62 32.83 206,586.71 43,302.77 324.80 10,663.18 1,021.57 33,538.14 6,292.62 206,586.71
04.02.02 ENCOFRADO Y DESENCOFRADO m2 7,206.69 35.75 257,639.17 54,003.95 371.99 13,298.64 1,169.95 41,825.71 7,206.69 257,639.17
04.02.03 CONCRETO F'C=140 KG/CM2. m3 1,582.93 453.30 717,542.17 150,404.94 81.71 37,039.14 256.97 116,484.50 1,582.93 717,542.17
04.02.04 JUNTA ASFALTICA m 7,219.74 4.98 35,954.31 0.00 0.00 0.00 7,219.74 35,954.31 7,219.74 35,954.31
5 TRANSPORTE 0.00 0.00 0.00 0.00 0.00
5.01 TRANSPORTE DE MAT. EXCEDENTE DE CORTE HASTA 1 KM m3km 38,732.34 6.26 242,464.45 0.00 0.00 0.00 -98.57 -617.05 38,633.77 241,847.40
5.02 TRANSPORTE DE MAT. EXCEDETE DE CORTE D > 1. KM. m3km 15,557.39 1.46 22,713.79 0.00 0.00 0.00 -26.66 -38.92 15,530.73 22,674.89
5.03 TRANSPORTE DE MAT. SATURADO HASTA 1 KM m3km 999.56 6.26 6,257.25 0.00 0.00 0.00 0.00 0.00 999.56 6,257.24
5.04 TRANSPORTE DE MAT. SATURADO D > 1 KM m3km 281.59 1.46 411.12 0.00 0.00 0.00 0.00 0.00 281.59 411.12
5.05 TRANSP. DE MAT. PARA RELL. CON EXCED. DE CORTE HASTA 1 KM m3km 6,900.38 6.26 43,196.38 0.00 0.00 0.00 0.00 0.00 6,900.38 43,196.37
5.06 TRANSP. DE MAT. PARA RELL. CON EXCED. DE CORTE D > 1 KM m3km 17,610.50 1.46 25,711.33 0.00 0.00 0.00 0.00 0.00 17,610.50 25,711.33
5.07 TRANSPORTE DE MAT. ANTICONTAMINANTE HASTA 1 KM m3km 13,815.52 6.26 86,485.16 4,629.08 0.00 0.00 -428.20 -2,680.53 13,387.32 83,804.62
5.08 TRANSPORTE DE MAT. ANTICONTAMINANTE D > 1KM m3km 264,338.66 1.46 385,934.44 68,743.69 0.00 0.00 -6,709.02 -9,795.17 257,629.64 376,139.27
5.09 TRANSPORTE DE MAT. PARA AFIRMADO HASTA 1 KM. m3km 25,915.56 6.26 162,231.41 0.00 2,020.38 12,647.58 56.15 351.50 25,105.84 157,162.56
5.10 TRANSPORTE DE MAT. PARA AFIRMADO > 1 KM. m3km 723,897.30 1.46 1,056,890.06 0.00 141,347.33 206,367.10 40,302.68 58,841.91 703,622.55 1,027,288.91

28de40
OBRA : "REHABILITACIN Y MEJORAMIENTO CARRETERA VECINAL ALTO CUUMBUZA-PUERTO BERMDEZ, DISTRITO DE ALTO BIAVO-CAMPANILLA, PROVINCIAS DE BELLAVISTA- MARISCAL CCERES- SAN MARTN"
CLIENTE : GOBIERNO REGIONAL DE SAN MARTN - PROYECTO ESPECIAL HUALLAGA CENTRAL Y BAJO MAYO
UBICACIN : DIST. DE ALTO BIAVO-CAMPANILLA, PROV. DE BELLAVISTA- MARISCAL CCERES, REGION SAN MARTN.
CONTRATISTA : CONSORCIO VIAL CAMPANILLA
SUPERVISION : CONSORCIO VIAL SUPERVISOR CUUMBUZA

VALORIZACIONES MENSUALES
29/40
CONTRATO PRINCIPAL
VALORIZ.
RESUM. N11
VALORIZ VALORIZ. N12 VALORIZ. N13 TOTAL VALORIZADO
Jun-16
JIH Jul-16 Aug-16 ACUMULADO
P.U. PARCIAL
Cdigo Descripcin de la Partida Unid. METRADO
S/. S/. Parcial S/. Metrado Parcial S/. Metrado Parcial S/. Metrado Parcial S/.
6 SEALIZACION Y SEGURIDAD VIAL 0.00 0.00 0.00 0.00 0.00
6.01 SEALES PREVENTIVAS und 137.00 468.46 64,179.02 0.00 0.00 0.00 137.00 64,179.02 137.00 64,179.02
6.02 SEALES REGLAMENTARIAS und 46.00 403.08 18,541.68 0.00 0.00 0.00 46.00 18,541.68 46.00 18,541.68
6.03 SEAL INFORMATIVA m2 54.49 438.77 23,908.58 0.00 0.00 0.00 54.49 23,908.58 54.49 23,908.58
6.04 ESTRUCTURA DE SOPORTE DE SEALES INFORMATIVAS m 290.88 105.50 30,687.84 0.00 0.00 0.00 290.88 30,687.84 290.88 30,687.84
6.05 CIMENTACION Y MONTAJE DE SEAL INFORMATIVA und 60.00 624.25 37,455.00 0.00 0.00 0.00 60.00 37,455.00 60.00 37,455.00
6.06 HITOS KILOMETRICOS und 20.00 146.15 2,923.00 0.00 0.00 0.00 20.00 2,923.00 20.00 2,923.00
7 PLAN DE MANEJO AMBIENTAL 0.00 0.00 0.00 0.00 0.00
7.01 PROGRAMA DE MITIGACION AMBIENTAL 0.00 0.00 0.00 0.00 0.00
07.01.01 CONFORMACION DE DEPOSITOS DE MATERIAL EXCEDENTE m3 55,899.08 1.19 66,519.91 0.00 0.00 0.00 3,424.83 4,075.55 55,899.08 66,519.91
07.01.02 ESTABILIZACION DE TALUDES CON REVEGETACION ha 2.50 4,580.73 11,451.83 0.00 0.00 0.00 2.50 11,451.83 2.50 11,451.83
7.02 PROGRAMA DE MONITOREO AMBIENTAL 0.00 0.00 0.00 0.00 0.00
07.02.01 MONITOREO DE LA CALIDAD DEL AGUA und 3.00 1,500.00 4,500.00 0.00 1.00 1,500.00 2.00 3,000.00 3.00 4,500.00
07.02.02 MONITOREO DE LA CALIDAD DEL AIRE und 3.00 2,000.00 6,000.00 0.00 1.00 2,000.00 2.00 4,000.00 3.00 6,000.00
07.02.03 MONITOREO DE LA CALIDAD DE RUIDO und 3.00 500.00 1,500.00 0.00 1.00 500.00 2.00 1,000.00 3.00 1,500.00
7.03 PROGRAMA DE MANEJO DE RESIDUOS 0.00 0.00 0.00 0.00 0.00
07.03.01 ADQUISICION DE CONTENEDORES und 12.00 1,080.00 12,960.00 6,480.00 3.00 3,240.00 3.00 3,240.00 12.00 12,960.00
07.03.02 LETRINA SANITARIA PORTATIL und 3.00 2,000.00 6,000.00 2,000.00 1.00 2,000.00 1.00 2,000.00 3.00 6,000.00
7.04 PROGRAMA DE CIERRE Y ABANDONO 0.00 0.00 0.00 0.00 0.00
07.04.01 READECUACION AMBIENTAL DE CAMPAMENTOS HA 0.25 13,243.57 3,310.89 0.00 0.00DE
LA CANTIDAD 0.00 0.25 3,310.89 0.25 3,310.89
07.04.02 READECUACION AMBIENTAL DE CANTERAS HA 0.50 7,843.57 3,921.79 425,489.090.00
0.00 NO 0.00 0.50 3,921.79 0.50 3,921.79
CORRESPONDE
07.04.03 READECUACION AMBIENTAL DE BOTADEROS Y DME HA 0.50 7,843.57 3,921.79 0.00 0.12 941.23 0.38 2,980.56 0.50 3,921.79
07.04.04 SEALIZACION AMBIENTAL und 6.00 600.00 3,600.00 3,600.00 0.00 0.00 0.00 0.00 6.00 3,600.00

COSTO DIRECTO 5,674,200.24 434,746.64 616,372.54 639,599.74 5,608,025.79


GASTOS GENERALES 10.12% 574,268.47 43,999.38 62,381.18 64,731.96 567,571.16
UTILIDAD 0.00% 0.00 0.00 0.00 0.00 0.00
SUB TOTAL 6,248,468.71
### 478,746.02 678,753.72 704,331.70 6,175,596.95

I.G.V. 0.00% 0.00 0.00 0.00 0.00 0.00


TOTAL 6,248,468.71 478,746.02 678,753.72 704,331.70 6,175,596.95

29de40
OBRA : "REHABILITACIN Y MEJORAMIENTO CARRETERA VECINAL ALTO CUUMBUZA-PUERTO BERMDEZ, DISTRITO DE ALTO BIAVO-CAMPANILLA, PROVINCIAS DE BELLAVISTA- MARISCAL CCERES- SAN MARTN"
CLIENTE : GOBIERNO REGIONAL DE SAN MARTN - PROYECTO ESPECIAL HUALLAGA CENTRAL Y BAJO MAYO
UBICACIN : DIST. DE ALTO BIAVO-CAMPANILLA, PROV. DE BELLAVISTA- MARISCAL CCERES, REGION SAN MARTN.
CONTRATISTA : CONSORCIO VIAL CAMPANILLA
SUPERVISION : CONSORCIO VIAL SUPERVISOR CUUMBUZA

VALORIZACIONES MENSUALES
30/40
CONTRATO PRINCIPAL
VALORIZ.
RESUM. N11
VALORIZ VALORIZ. N12 VALORIZ. N13 TOTAL VALORIZADO
Jun-16
JIH Jul-16 Aug-16 ACUMULADO
P.U. PARCIAL
Cdigo Descripcin de la Partida Unid. METRADO
S/. S/. Parcial S/. Metrado Parcial S/. Metrado Parcial S/. Metrado Parcial S/.
ADICIONAL DE OBRA N 01
TOTAL VALORIZADO
Jun-16 Jul-16 Aug-16 ACUMULADO
P.U. PARCIAL
Cdigo Descripcin de la Partida Unid. METRADO
S/. S/. Parcial S/. Metrado Parcial S/. Metrado Parcial S/. Metrado Parcial S/.
2 MOVIMIENTO DE TIERRAS 0.00
2.03 REMOCION DE MATERIAL SATURADO m3 10,058.31 4.56 45,865.89 0.00 0.00 0.00 0.00 0.00 10,058.31 45,865.89
2.05 PEDRAPLEN m3 10,058.31 67.88 682,758.08 0.00 0.00 0.00 0.00 0.00 10,058.31 682,758.08
5 TRANSPORTE 0.00 0.00 0.00 0.00 0.00
5.03 TRANSPORTE DE MAT. SATURADO HASTA 1 KM m3km 5,274.74 6.26 33,019.87 0.00 0.00 0.00 0.00 0.00 5,274.74 33,019.87
5.04 TRANSPORTE DE MAT. SATURADO D > 1 KM m3km 411.99 1.46 601.51 0.00 0.00 0.00 0.00 0.00 411.99 601.51
7 PLAN DE MANEJO AMBIENTAL 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7.01 PROGRAMA DE MITIGACION AMBIENTAL 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.01.01 CONFORMACION DE DEPOSITOS DE MATERIAL EXCEDENTE m3 10,058.31 1.19 11,969.39 0.00 0.00 0.00 0.00 0.00 10,058.31 11,969.39

COSTO DIRECTO 774,214.74 0.00 0.00 0.00 774,214.74


GASTOS GENERALES 8.08% 62,588.76 0.00 0.00 0.00 62,588.76
UTILIDAD 0.00% 0.00 0.00 0.00 0.00 0.00
SUB TOTAL 836,803.50 0.00 0.00 0.00 836,803.50

I.G.V. 0.00% 0.00 0.00 0.00 0.00 0.00


TOTAL ###
836,803.50 0.00 0.00 0.00 836,803.50

30de40
OBRA : "REHABILITACIN Y MEJORAMIENTO CARRETERA VECINAL ALTO CUUMBUZA-PUERTO BERMDEZ, DISTRITO DE ALTO BIAVO-CAMPANILLA, PROVINCIAS DE BELLAVISTA- MARISCAL CCERES- SAN MARTN"
CLIENTE : GOBIERNO REGIONAL DE SAN MARTN - PROYECTO ESPECIAL HUALLAGA CENTRAL Y BAJO MAYO
UBICACIN : DIST. DE ALTO BIAVO-CAMPANILLA, PROV. DE BELLAVISTA- MARISCAL CCERES, REGION SAN MARTN.
CONTRATISTA : CONSORCIO VIAL CAMPANILLA
SUPERVISION : CONSORCIO VIAL SUPERVISOR CUUMBUZA

VALORIZACIONES MENSUALES
31/40
CONTRATO PRINCIPAL
RESUM. VALORIZ
P.U. PARCIAL JIH DEDUCTIVO 01
Cdigo Descripcin de la Partida Unid. METRADO
S/. S/. Metrado Parcial S/.
1 TRABAJOS PRELIMINARES
1.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 32,063.68 32,063.68 0.00 0.00
1.02 TRAZO Y REPLANTEO KM 19.06 1,045.20 19,921.51 0.09 94.07
2 MOVIMIENTO DE TIERRAS 0.00 0.00 0.00
2.01 DESBROCE Y LIMPIEZA EN ZONAS NO BOSCOSAS HA 3.69 3,530.42 13,027.25 0.03 105.91
2.02 EXCAVACION PARA EXPLANACIONES EN MATERIAL COMUN m3 100,065.38 4.56 456,298.13 704.32 3,211.70
2.03 REMOCION DE MATERIAL SATURADO m3 1,290.85 4.56 5,886.28 0.00 0.00
2.04 TERRAPLENES m3 18,948.94 7.14 135,295.43 381.25 2,722.14
2.05 PEDRAPLEN m3 1,290.85 67.88 87,622.90 0.00 0.00
2.06 PERFILADO Y COMPACTADO DE SUBRASANTE m2 72,871.49 1.59 115,865.67 752.35 1,196.24
3 AFIRMADOS 0.00 0.00 0.00
3.01 CAPA ANTICONTAMINANTE m3 13,815.50 21.79 301,039.75 177.17 3,860.53
3.02 AFIRMADO m3 25,915.55 21.55 558,480.10 333.28 7,182.18
4 DRENAJE 0.00 0.00 0.00
4.01 ALCANTARILLAS TMC 0.00 0.00 0.00
04.01.01 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS m3 2,435.25 8.26 20,115.17 0.00 0.00
04.01.02 TUB. CORRUGADA DE ACERO GALVAN. CIRCULAR DE = 0.91 m m 136.89 405.25 55,474.67 0.00 0.00
04.01.03 TUB. CORRUGADA DE ACERO GALVAN. CIRCULAR DE = 1.52 m m 97.20 830.17 80,692.52 0.00 0.00
04.01.04 TUB. CORRUGADA DE ACERO GALVAN. CIRCULAR DE = 1.83 m m 14.58 1,115.28 16,260.78 0.00 0.00
04.01.05 ENCOFRADO Y DESENCOFRADO CABEZALES m2 689.26 59.07 40,714.59 0.00 0.00
04.01.06 ACERO DE REFUERZO F'Y = 4200 KG/CM2 kg 3,717.58 4.67 17,361.10 0.00 0.00
04.01.07 CONCRETO F'C=175 KG/CM2. - CABEZALES m3 106.42 497.98 52,995.03 0.00 0.00
04.01.08 RELLENO CON MATERIAL PROPIO PARA ESTRUCTURAS m3 832.46 31.82 26,488.88 0.00 0.00
04.01.09 MAMPOSTERIA CON PIEDRA EMBOQUILLADA m3 185.61 469.79 87,197.72 0.00 0.00
4.02 CUNETAS 0.00 0.00 0.00
04.02.01 EXCAVACION MANUAL EN OBRAS DE ARTE m3 6,292.62 32.83 206,586.71 0.00 0.00
04.02.02 ENCOFRADO Y DESENCOFRADO m2 7,206.69 35.75 257,639.17 0.00 0.00
04.02.03 CONCRETO F'C=140 KG/CM2. m3 1,582.93 453.30 717,542.17 0.00 0.00
04.02.04 JUNTA ASFALTICA m 7,219.74 4.98 35,954.31 0.00 0.00
5 TRANSPORTE 0.00 0.00 0.00
5.01 TRANSPORTE DE MAT. EXCEDENTE DE CORTE HASTA 1 KM m3km 38,732.34 6.26 242,464.45 98.57 617.05
5.02 TRANSPORTE DE MAT. EXCEDETE DE CORTE D > 1. KM. m3km 15,557.39 1.46 22,713.79 26.66 38.92
5.03 TRANSPORTE DE MAT. SATURADO HASTA 1 KM m3km 999.56 6.26 6,257.25 0.00 0.00
5.04 TRANSPORTE DE MAT. SATURADO D > 1 KM m3km 281.59 1.46 411.12 0.00 0.00
5.05 TRANSP. DE MAT. PARA RELL. CON EXCED. DE CORTE HASTA 1 KM m3km 6,900.38 6.26 43,196.38 0.00 0.00
5.06 TRANSP. DE MAT. PARA RELL. CON EXCED. DE CORTE D > 1 KM m3km 17,610.50 1.46 25,711.33 0.00 0.00
5.07 TRANSPORTE DE MAT. ANTICONTAMINANTE HASTA 1 KM m3km 13,815.52 6.26 86,485.16 428.20 2,680.53
5.08 TRANSPORTE DE MAT. ANTICONTAMINANTE D > 1KM m3km 264,338.66 1.46 385,934.44 6,709.02 9,795.17
5.09 TRANSPORTE DE MAT. PARA AFIRMADO HASTA 1 KM. m3km 25,915.56 6.26 162,231.41 809.72 5,068.85
5.10 TRANSPORTE DE MAT. PARA AFIRMADO > 1 KM. m3km 723,897.30 1.46 1,056,890.06 20,274.75 29,601.14

31de40
OBRA : "REHABILITACIN Y MEJORAMIENTO CARRETERA VECINAL ALTO CUUMBUZA-PUERTO BERMDEZ, DISTRITO DE ALTO BIAVO-CAMPANILLA, PROVINCIAS DE BELLAVISTA- MARISCAL CCERES- SAN MARTN"
CLIENTE : GOBIERNO REGIONAL DE SAN MARTN - PROYECTO ESPECIAL HUALLAGA CENTRAL Y BAJO MAYO
UBICACIN : DIST. DE ALTO BIAVO-CAMPANILLA, PROV. DE BELLAVISTA- MARISCAL CCERES, REGION SAN MARTN.
CONTRATISTA : CONSORCIO VIAL CAMPANILLA
SUPERVISION : CONSORCIO VIAL SUPERVISOR CUUMBUZA

VALORIZACIONES MENSUALES
32/40
CONTRATO PRINCIPAL
RESUM. VALORIZ
P.U. PARCIAL JIH DEDUCTIVO 01
Cdigo Descripcin de la Partida Unid. METRADO
S/. S/. Metrado Parcial S/.
6 SEALIZACION Y SEGURIDAD VIAL 0.00 0.00 0.00
6.01 SEALES PREVENTIVAS und 137.00 468.46 64,179.02 0.00 0.00
6.02 SEALES REGLAMENTARIAS und 46.00 403.08 18,541.68 0.00 0.00
6.03 SEAL INFORMATIVA m2 54.49 438.77 23,908.58 0.00 0.00
6.04 ESTRUCTURA DE SOPORTE DE SEALES INFORMATIVAS m 290.88 105.50 30,687.84 0.00 0.00
6.05 CIMENTACION Y MONTAJE DE SEAL INFORMATIVA und 60.00 624.25 37,455.00 0.00 0.00
6.06 HITOS KILOMETRICOS und 20.00 146.15 2,923.00 0.00 0.00
7 PLAN DE MANEJO AMBIENTAL 0.00 0.00 0.00
7.01 PROGRAMA DE MITIGACION AMBIENTAL 0.00 0.00 0.00
07.01.01 CONFORMACION DE DEPOSITOS DE MATERIAL EXCEDENTE m3 55,899.08 1.19 66,519.91 0.00 0.00
07.01.02 ESTABILIZACION DE TALUDES CON REVEGETACION ha 2.50 4,580.73 11,451.83 0.00 0.00
7.02 PROGRAMA DE MONITOREO AMBIENTAL 0.00 0.00 0.00
07.02.01 MONITOREO DE LA CALIDAD DEL AGUA und 3.00 1,500.00 4,500.00 0.00 0.00
07.02.02 MONITOREO DE LA CALIDAD DEL AIRE und 3.00 2,000.00 6,000.00 0.00 0.00
07.02.03 MONITOREO DE LA CALIDAD DE RUIDO und 3.00 500.00 1,500.00 0.00 0.00
7.03 PROGRAMA DE MANEJO DE RESIDUOS 0.00 0.00 0.00
07.03.01 ADQUISICION DE CONTENEDORES und 12.00 1,080.00 12,960.00 0.00 0.00
07.03.02 LETRINA SANITARIA PORTATIL und 3.00 2,000.00 6,000.00 0.00 0.00
7.04 PROGRAMA DE CIERRE Y ABANDONO 0.00 0.00 0.00
07.04.01 READECUACION AMBIENTAL DE CAMPAMENTOS HA 0.25 13,243.57 3,310.89 0.00 0.00
07.04.02 READECUACION AMBIENTAL DE CANTERAS HA 0.50 7,843.57 3,921.79 0.00 0.00
07.04.03 READECUACION AMBIENTAL DE BOTADEROS Y DME HA 0.50 7,843.57 3,921.79 0.00 0.00
07.04.04 SEALIZACION AMBIENTAL und 6.00 600.00 3,600.00 0.00 0.00

COSTO DIRECTO 5,674,200.24 66,174.43


GASTOS GENERALES 10.12% 574,268.47 6,697.31
UTILIDAD 0.00% 0.00 0.00
SUB TOTAL 6,248,468.71
### 72,871.74

I.G.V. 0.00% 0.00 0.00


TOTAL 6,248,468.71 72,871.74

32de40
OBRA : "REHABILITACIN Y MEJORAMIENTO CARRETERA VECINAL ALTO CUUMBUZA-PUERTO BERMDEZ, DISTRITO DE ALTO BIAVO-CAMPANILLA, PROVINCIAS DE BELLAVISTA- MARISCAL CCERES- SAN MARTN"
CLIENTE : GOBIERNO REGIONAL DE SAN MARTN - PROYECTO ESPECIAL HUALLAGA CENTRAL Y BAJO MAYO
UBICACIN : DIST. DE ALTO BIAVO-CAMPANILLA, PROV. DE BELLAVISTA- MARISCAL CCERES, REGION SAN MARTN.
CONTRATISTA : CONSORCIO VIAL CAMPANILLA
SUPERVISION : CONSORCIO VIAL SUPERVISOR CUUMBUZA

VALORIZACIONES MENSUALES
33/40
CONTRATO PRINCIPAL
RESUM. VALORIZ
P.U. PARCIAL JIH DEDUCTIVO 01
Cdigo Descripcin de la Partida Unid. METRADO
S/. S/. Metrado Parcial S/.
ADICIONAL DE OBRA N 01

P.U. PARCIAL DEDUCTIVO 01


Cdigo Descripcin de la Partida Unid. METRADO
S/. S/. Metrado Parcial S/.
2 MOVIMIENTO DE TIERRAS 0.00
2.03 REMOCION DE MATERIAL SATURADO m3 10,058.31 4.56 45,865.89 0.00 0.00
2.05 PEDRAPLEN m3 10,058.31 67.88 682,758.08 0.00 0.00
5 TRANSPORTE 0.00 0.00 0.00
5.03 TRANSPORTE DE MAT. SATURADO HASTA 1 KM m3km 5,274.74 6.26 33,019.87 0.00 0.00
5.04 TRANSPORTE DE MAT. SATURADO D > 1 KM m3km 411.99 1.46 601.51 0.00 0.00
7 PLAN DE MANEJO AMBIENTAL 0.00 0.00 0.00
7.01 PROGRAMA DE MITIGACION AMBIENTAL 0.00 0.00 0.00
07.01.01 CONFORMACION DE DEPOSITOS DE MATERIAL EXCEDENTE m3 10,058.31 1.19 11,969.39 0.00 0.00

COSTO DIRECTO 774,214.74 0.00


GASTOS GENERALES 8.08% 62,588.76 0.00
UTILIDAD 0.00% 0.00 0.00
SUB TOTAL 836,803.50 0.00

I.G.V. 0.00% 0.00 0.00


TOTAL ###
836,803.50 0.00

33de40
OBRA : "REHABILITACIN Y MEJORAMIENTO CARRETERA VECINAL ALTO CUUMBUZA-PUERTO BERMDEZ, DISTRITO DE ALTO BIAVO-CAMPANILLA, PROVINCIAS DE BELLAVISTA- MARISCAL CCERES- SAN MARTN"
CLIENTE : GOBIERNO REGIONAL DE SAN MARTN - PROYECTO ESPECIAL HUALLAGA CENTRAL Y BAJO MAYO
UBICACIN : DIST. DE ALTO BIAVO-CAMPANILLA, PROV. DE BELLAVISTA- MARISCAL CCERES, REGION SAN MARTN.
CONTRATISTA : CONSORCIO VIAL CAMPANILLA
SUPERVISION : CONSORCIO VIAL SUPERVISOR CUUMBUZA

CLCULO DEL COEFICIENTE DE REAJUSTE

CONTRATO PRINCIPAL

FORMULA: K = 0.150*(Jr / Jo) + 0.057*(Cr / Co) + 0.056*(Dr / Do) + 0.554*(Mr / Mo) + 0.183*(GGUr / GGUo)
Porque se calcula este mes Porque se calcula este mes
Agosto-2014 (BASE) Jul-15 Calculo Aug-15 Calculo Sep-15 Calculo Oct-15 Calculo Nov-15 Calculo Dec-15 Calculo Jan-16 Calculo Feb-16 Calculo Mar-16 Calculo Apr-16 Calculo May-16 Calculo Jun-16 Calculo Jul-16 Calculo Aug-16 Calculo Sep-16 Calculo
SIMBOLO DESCRIPCION I.U. % COEF.
I.U. K I.U. K Veificacion I.U. K Veificacion I.U. K Veificacion I.U. K Veificacion I.U. K Veificacion I.U. K Veificacion I.U. K Veificacion I.U. K Veificacion I.U. K Veificacion I.U. K Veificacion I.U. K Veificacion I.U. K Veificacion I.U. K Veificacion I.U. K Veificacion I.U. K Veificacion
J MANO DE OBRA INC. LEYES SOCIALES 47 100.000% 0.150 523.70 0.150 523.15 0.150 0.150 544.59 0.156 0.156 544.59 0.156 0.156 544.59 0.156 0.156 544.59 0.156 0.156 544.59 0.156 0.156 544.12 0.156 0.156 544.12 0.156 0.156 544.12 0.156 0.156 544.12 0.156 0.156 544.12 0.156 0.156 544.12 0.156 0.156 562.24 0.161 0.161 562.24 0.161 0.161 562.24 0.161 0.161
C CEMENTO PORTLAND TIPO I 21 100.000% 0.057 458.79 0.057 459.40 0.057 0.057 459.40 0.057 0.057 459.40 0.057 0.057 459.40 0.057 0.057 459.40 0.057 0.057 459.40 0.057 0.057 460.88 0.057 0.057 462.57 0.057 0.057 462.57 0.057 0.057 462.57 0.057 0.057 462.57 0.057 0.057 462.57 0.057 0.057 459.08 0.057 0.057 457.28 0.057 0.057 459.93 0.057 0.057
D DLAR 29 (30) 100.000% 0.056 390.72 0.056 442.52 0.063 0.063 450.46 0.065 0.065 447.20 0.064 0.064 450.53 0.065 0.065 462.65 0.066 0.066 468.04 0.067 0.067 473.88 0.068 0.068 484.19 0.069 0.069 471.04 0.068 0.068 458.22 0.066 0.066 465.00 0.067 0.067 464.38 0.067 0.067 463.54 0.066 0.066 467.56 0.067 0.067 474.82 0.068 0.068
M MAQUINARIA Y EQUIPO IMPORTADO 49 100.000% 0.554 250.83 0.554 285.08 0.630 0.630 290.40 0.641 0.641 288.48 0.637 0.637 291.08 0.643 0.643 298.83 0.660 0.660 302.95 0.669 0.669 308.01 0.680 0.680 313.96 0.693 0.693 305.19 0.674 0.674 295.61 0.653 0.653 298.57 0.659 0.659 297.17 0.656 0.656 295.65 0.653 0.653 298.91 0.660 0.660 303.08 0.669 0.669
GGU INDICE GENERAL DE PRECIOS AL CONSUMIDOR 39 100.000% 0.183 402.37 0.183 417.07 0.190 0.190 418.64 0.190 0.190 418.76 0.190 0.190 419.35 0.191 0.191 420.80 0.191 0.191 422.67 0.192 0.192 424.25 0.193 0.193 424.99 0.193 0.193 427.53 0.194 0.194 427.58 0.194 0.194 428.47 0.195 0.195 429.07 0.195 0.195 429.42 0.195 0.195 430.96 0.196 0.196 431.85 0.196 0.196
COEFICIENTE DE REAJUSTE ( K ) = 1.000 1.090 1.090 1.109 1.109 1.104 1.104 1.112 1.112 1.130 1.130 1.141 1.141 1.154 1.154 1.168 1.168 1.149 1.149 1.126 1.126 1.134 1.134 1.131 1.131 1.132 1.132 1.141 1.141 1.151 1.151
COEFICIENTE DE REAJUSTE ( K-Real ) = Valores 1.000 1.090 1.109 1.104 1.112 1.130 1.141 1.154 1.168 1.149 1.126 1.134 1.131 1.132 1.141 1.151

ADICIONAL DE OBRA N 01

FORMULA: K = 0.471*(Mr / Mo) + 0.454*(Mr / Mo) + 0.075*(Ir / Io)

Agosto-2014 (BASE) Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16
SIMBOLO DESCRIPCION I.U. % COEF.
I.U. K I.U. K I.U. K I.U. K I.U. K I.U. K I.U. K I.U. K I.U. K I.U. K I.U. K I.U. K I.U. K I.U. K I.U. K I.U. K
M MANO DE OBRA INC. LEYES SOCIALES 47 100.000% 0.471 523.70 0.471 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 544.12 0.489 0.489 544.12 0.489 0.489 544.12 0.489 0.489 0.000 0.000 0.000 0.000
M MAQUINARIA Y EQUIPO IMPORTADO 49 100.000% 0.454 250.83 0.454 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 305.19 0.552 0.552 295.61 0.535 0.535 298.57 0.540 0.540 0.000 0.000 0.000 0.000
I INDICE GENERAL DE PRECIOS AL CONSUMIDOR 39 100.000% 0.075 402.37 0.075 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 427.53 0.080 0.080 427.58 0.080 0.080 428.47 0.080 0.080 0.000 0.000 0.000 0.000
COEFICIENTE DE REAJUSTE ( K ) = 1.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 1.121 1.121 1.104 1.104 1.109 1.109 0.000 0.000 0.000 0.000
COEFICIENTE DE REAJUSTE ( K ) = 1.000 1.104 1.109 1.107 1.107 0.000 0.000 0.000
OBRA : "REHABILITACIN Y MEJORAMIENTO CARRETERA VECINAL ALTO CUUMBUZA-PUERTO BERMDEZ, DISTRITO DE ALTO BIAVO-CAMPANILLA, PROVINCIAS DE BELLAVISTA- MARISCAL CCERES- SAN MARTN"

CLIENTE : GOBIERNO REGIONAL DE SAN MARTN - PROYECTO ESPECIAL HUALLAGA CENTRAL Y BAJO MAYO
UBICACIN : DIST. DE ALTO BIAVO-CAMPANILLA, PROV. DE BELLAVISTA- MARISCAL CCERES, REGION SAN MARTN.
CONTRATISTA : CONSORCIO VIAL CAMPANILLA
SUPERVISION : CONSORCIO VIAL SUPERVISOR CUUMBUZA

DETERMINACIN DEL REAJUSTE


CONTRATO PRINCIPAL

AVANCE PROGRAMADO AVANCE REAL REINTEGRO PROGRAMADO REINTEGRO REAL REINTEGRO A RECONOCER
VALORIZACION
FACTOR
MENSUAL MES DE DE
ACUMULADO MENSUAL K (REAL) MENSUAL ACUMULADO MENSUAL ACUMULADO
(A) ACUMULADO REAJUSTE REAJUSTE MENSUAL ACUMULADO
N MES (APA) (V) (K-1) A x (K-1) (SRP) V x (K-1) (SRR)
CAO N 05

FORM1 FORM1 FORM1


1 Aug-15 2,315.65 2,315.65 136,275.77 136,275.77 Sep-15 1.109 0.109 252.41 252.41 14,854.06 14,854.06 14,854.06 14,854.06
2 Sep-15 130,845.06 133,160.71 425,724.52 562,000.29 Oct-15 1.104 0.104 13,607.89 13,860.30 44,275.35 59,129.41 44,275.35 59,129.41
3 Oct-15 351,112.51 484,273.22 841,439.68 1,403,439.97 Nov-15 1.112 0.112 39,324.60 53,184.90 94,241.24 153,370.65 94,241.24 153,370.65
4 Nov-15 360,902.35 845,175.57 609,469.49 2,012,909.46 Dec-15 1.130 0.130 46,917.31 100,102.21 79,231.03 232,601.68 79,231.03 232,601.68
5 Dec-15 447,662.36 1,292,837.93 21,267.74 2,034,177.20 Jan-16 1.141 0.141 63,120.39 163,222.60 2,998.75 235,600.43 2,998.75 235,600.43
6 Jan-16 817,456.75 2,110,294.68 463,748.43 2,497,925.63 Feb-16 1.154 0.154 125,888.34 289,110.94 71,417.26 307,017.69 71,417.26 307,017.69
7 Feb-16 984,372.55 3,094,667.23 408,168.49 2,906,094.12 Mar-16 1.168 0.168 165,374.59 454,485.53 68,572.31 375,590.00 68,572.31 375,590.00
8 Mar-16 679,690.12 3,774,357.35 349,275.48 3,255,369.60 Apr-16 1.149 0.149 101,273.83 555,759.36 52,042.05 427,632.05 52,042.05 427,632.05
9 Apr-16 540,096.23 4,314,453.58 632,906.89 3,888,276.49 May-16 1.126 0.126 68,052.12 623,811.48 79,746.27 507,378.32 79,746.27 507,378.32
10 May-16 679,262.01 4,993,715.59 425,489.05 4,313,765.54 Jun-16 1.134 0.134 91,021.11 714,832.59 57,015.53 564,393.85 57,015.53 564,393.85
11 Jun-16 570,739.50 5,564,455.09 478,746.02 4,792,511.56 Jul-16 1.131 0.131 74,766.87 789,599.46 62,715.73 627,109.58 62,715.73 627,109.58
12 Jul-16 657,549.24 6,222,004.33 678,753.72 5,471,265.28 Aug-16 1.132 0.132 86,796.50 876,395.96 89,595.49 716,705.07 89,595.49 716,705.07
13 Aug-16 26,464.38 6,248,468.71 749,054.65 6,220,319.93 Sep-16 1.141 0.141 3,731.48 880,127.44 105,616.71 822,321.78 105,616.71 822,321.78
6,248,468.71 6,220,319.93

0.104 240.83 240.83 14,172.68 14,172.68 14,172.68 14,172.68


515,556.50 0.112 14,654.65 14,895.48 47,681.15 61,853.83 47,681.15 61,853.83
0.13 45,644.63 60,540.11 109,387.16 171,240.99 109,387.16 171,240.99
0.141 50,887.23 111,427.34 85,935.20 257,176.19 85,935.20 257,176.19
0.154 68,940.00 180,367.34 3,275.23 260,451.42 3,275.23 260,451.42
0.168 137,332.73 317,700.07 77,909.74 338,361.16 77,909.74 338,361.16
0.149 146,671.51 464,371.58 60,817.11 399,178.27 60,817.11 399,178.27
0.126 85,640.96 550,012.54 44,008.71 443,186.98 44,008.71 443,186.98
0.134 72,372.89 622,385.43 84,809.52 527,996.50 84,809.52 527,996.50
0.131 88,983.32 711,368.75 55,739.07 583,735.57 55,739.07 583,735.57
0.132 75,337.61 786,706.36 63,194.47 646,930.04 63,194.47 646,930.04
0.141 92,714.44 879,420.80 95,704.27 742,634.31 95,704.27 742,634.31
0.151 3,996.12 883,416.92 113,107.25 855,741.56 113,107.25 855,741.56

3,289.48 33,419.78 33,419.78


HOJA NUEVA NUEVO CALCULO
883,152.28 880,127.44 -3,024.84
848,251.02 822,321.78 -25,929.24
447,521.91 822,321.78 374,799.87
ADICIONAL DE OBRA N 01
AVANCE PROGRAMADO AVANCE REAL FACTOR REINTEGRO PROGRAMADO REINTEGRO REAL REINTEGRO A RECONOCER
VALORIZACION MES DE DE
MENSUAL ACUMULADO MENSUAL REAJUSTE REAJUSTE MENSUAL ACUMULADO MENSUAL ACUMULADO
ACUMULADO MENSUAL ACUMULADO
N MES (A) (APA) (V) (K-1) A x (K-1) (SRP) V x (K-1) (SRR)
FORM1 FORM1 FORM1
Aug-15 - - - - - - - - -
Sep-15 - - - - - - - -
Oct-15 - - - - - - - -
Nov-15 - - - - - - - -
Dec-15 - - - - - - - -
Jan-16 - - - - - - - -
Feb-16 - - - - - - - -
1 Mar-16 94,200.69 94,200.69 172,828.58 172,828.58 Apr-16 1.121 0.121 11,398.28 11,398.28 20,912.26 20,912.26 20,912.26 20,912.26
2 Apr-16 492,723.50 586,924.19 50,617.37 223,445.95 May-16 1.104 0.104 51,243.24 62,641.52 5,264.21 26,176.47 5,264.21 26,176.47
3 May-16 249,879.31 836,803.50 613,357.55 836,803.50 Jun-16 1.109 0.109 27,236.84 89,878.36 66,855.97 93,032.44 66,855.97 93,032.44
Jun-16

NOTA VERIFICAR EL MES DE ESTA VALORIZACIN


ITO DE ALTO BIAVO-CAMPANILLA, PROVINCIAS DE BELLAVISTA- MARISCAL CCERES- SAN MARTN"

ACIN DEL REAJUSTE

ESTADO DE
LA OBRA

ADELANTADA
ADELANTADA
ADELANTADA
ADELANTADA
ADELANTADA
ADELANTADA
ATRASADA
ATRASADA
ATRASADA
ATRASADA
ATRASADA
ATRASADA
ATRASADA

ADELANTADA
ADELANTADA
ADELANTADA
ADELANTADA
ADELANTADA
ADELANTADA
ATRASADA
ATRASADA
ATRASADA
ATRASADA
ATRASADA
ATRASADA
ATRASADA
ESTADO DE
LA OBRA

ADELANTADA
ADELANTADA
ADELANTADA
ADELANTADA
ADELANTADA
ADELANTADA
ADELANTADA
ADELANTADA
ATRASADA
ADELANTADA
OBRA : "REHABILITACIN Y MEJORAMIENTO CARRETERA VECINAL ALTO CUUMBUZA-PUERTO
BERMDEZ, DISTRITO DE ALTO BIAVO-CAMPANILLA, PROVINCIAS DE BELLAVISTA- MARISCAL
CCERES- SAN MARTN"
CLIENTE : GOBIERNO REGIONAL DE SAN MARTN - PROYECTO ESPECIAL HUALLAGA CENTRAL Y BAJO MAYO
UBICACIN : DIST. DE ALTO BIAVO-CAMPANILLA, PROV. DE BELLAVISTA- MARISCAL CCERES, REGION SAN MARTN.
CONTRATISTA : CONSORCIO VIAL CAMPANILLA
SUPERVISION : CONSORCIO VIAL SUPERVISOR CUUMBUZA

AMORTIZACIN DEL ADELANTO DIRECTO

DATOS DEL ADELANTO DIRECTO

ADELANTO OTORGADO SIN IGV


MONTO DEL
COMPROBANTE MONTO ADELANTO (S/.) CONTRATO
N FECHA DE PAGO PRINCIPAL (SIN IGV)
DE PAGO SIN I.G.V.

1 12-Aug-2015 1,249,693.74 6,248,468.71

TOTAL DEL ADELANTO DIRECTO (sin IGV) : S/. 1,249,693.74 20.00%

FRMULAS :
A1 A2

AM = V x ( ------- ) + V x ( ------- )

C1 C2

DONDE :
AM : Amorizacin Mensual del Adelanto Directo
V : Monto en S/. de la valorizacin mensual
A : Monto parcial del Adelanto directo concedido al Contratista 1,249,693.74
C : Monto del contrato Principal 6,248,468.71

AMORTIZACIN DEL ADELANTO DIRECTO

VALORIZACION AMORTIZACION (S/.) SALDO POR


MONTO VAL SIN IGV
SIN I.G.V. AMORTIZAR
N PERIODO (S/.)
V V xA/ C SIN I.G.V
1 Aug-15 136,275.77 27,255.15 1,222,438.59
2 Sep-15 425,724.52 85,144.90 1,137,293.69
3 Oct-15 841,439.68 168,287.94 969,005.75
4 Nov-15 609,469.49 121,893.90 847,111.85
5 Dec-15 21,267.74 4,253.55 842,858.30
6 Jan-16 463,748.43 92,749.69 750,108.61
7 Feb-16 408,168.49 81,633.70 668,474.91
8 Mar-16 349,275.48 69,855.10 598,619.81
9 Apr-16 632,906.89 126,581.38 472,038.43
10 May-16 425,489.05 85,097.81 386,940.62
11 Jun-16 478,746.02 95,749.20 291,191.42
12 Jul-16 678,753.72 291,191.42 0.00

TOTAL AMORTIZACIN S/. 5,471,265.28 1,249,693.74


OBRA
: "REHABILITACIN Y MEJORAMIENTO CARRETERA VECINAL ALTO CUUMBUZA-PUERTO BERMDEZ, DISTRITO DE
ALTO BIAVO-CAMPANILLA, PROVINCIAS DE BELLAVISTA- MARISCAL CCERES- SAN MARTN"

CLIENTE : GOBIERNO REGIONAL DE SAN MARTN - PROYECTO ESPECIAL HUALLAGA CENTRAL Y BAJO MAYO
UBICACIN : DIST. DE ALTO BIAVO-CAMPANILLA, PROV. DE BELLAVISTA- MARISCAL CCERES, REGION SAN MARTN.
CONTRATISTA : CONSORCIO VIAL CAMPANILLA
SUPERVISION : CONSORCIO VIAL SUPERVISOR CUUMBUZA

CLCULO DE LA DEDUCCIN QUE NO CORRESPONDE


POR EL ADELANTO DIRECTO

FORMULA GENERAL

De = ( V x A / C ) x ( Kr / Ka - 1 ) = AM x ( Kr / Ka - 1 )
donde : datos :

De = Deduccion del reajuste que no corresponde del componente


en soles de la valorizacion mensual
A= Monto del Adelanto sujeto a deduccion = S/. 1,249,693.74
C= Monto del contrato Principal S/. 6,248,468.71
Kr = Factor de Reajuste del mes respectivo
Ka = Factor de Reajuste al mes que se otorgo el adelanto (Agosto 2015) = 1.109

VALORIZACION COEFICIENTE DE DEDUCCION


REAJUSTE AMORTIZACION
MONTO VAL. sin IGV S/. Kr De
N PERIODO
FORM.01 FORM.01 FORM.01 S/.
1 Aug-15 136,275.77 1.104 27,255.15 - 122.88
2 Sep-15 425,724.52 1.112 85,144.90 230.33
3 Oct-15 841,439.68 1.130 168,287.94 3,186.70
4 Nov-15 609,469.49 1.141 121,893.90 3,517.23
5 Dec-15 21,267.74 1.154 4,253.55 172.60
6 Jan-16 463,748.43 1.168 92,749.69 4,934.38
7 Feb-16 408,168.49 1.149 81,633.70 2,944.41
8 Mar-16 349,275.48 1.126 69,855.10 1,070.82
9 Apr-16 632,906.89 1.134 126,581.38 2,853.50
10 May-16 425,489.05 1.131 85,097.81 1,688.14
11 Jun-16 478,746.02 1.132 95,749.20 1,985.78
12 Jul-16 678,753.72 1.141 291,191.42 8,402.28

TOTAL DEDUCCION S/. 5,471,265.28 30,863.29