Вы находитесь на странице: 1из 4

Using Configuration Management to Mitigate the Impact of

Design and Construction Contract Changes

Michael Steinberg Frank Otero


PACO Group, Inc.

Abstract manufacturing of weapons and aircraft.


Subsequently, the nuclear industry adopted
Changes are and will continue to be an CM to track equipment changes affecting
inevitable part of the design and construction operational safety, and today CM is actively
of any project. Even the best design plans and used in many industries, including the
most detailed contract specifications are no software development industry to manage
guarantee a particular project will not version control through tracking software
experience numerous changes. This is modifications. In 1995, CM was formalized
particularly true when the scope involves a as an ISO 10007 quality management process
large-scale, multi-contract, multi-phased [1].
complex project. Most projects, whether
public or private, domestic or international, 2. Definition of Configuration
experience schedule slippage and cost Management
overruns
The application of a formalized Over the years, numerous organizations
Configuration Management methodology and industries developed various CM
during the planning, design, construction, definitions. The Project Management Institute
maintenance, and operations phases of defines CM as a subsystem of the overall
complex projects can mitigate schedule project management information system [that]
slippage and cost overruns. The decision to includes the process for submitting proposed
apply Configuration Management to a changes, tracking systems for reviewing and
construction project can make the difference approving proposed changes, defining
between a successful project verses a failure; approval levels for authorizing changes, and
turning a profit verses taking a loss; and a providing a method to validate approved
satisfied client verses a disgruntled one. changes. [2] The American National
The optimal adaptation of Configuration Standards Institute, defines CM as A
Management entails the integration of a management process for establishing and
specialized software solution. Using a maintaining consistency of a products
software driven process guarantees performance, functional, and physical
repeatability, enforcement of standards, and attributes with its requirements, design, and
provides customized business rules governing operational information throughout its life. [3]
the steps required to track, manage, and A common thread running between these
approve (or deny) change. definitions is the consensus that CM is a
process accommodating change and
1. Origins of Configuration perpetually documenting how a system is
Management configured.
Due to the unique attributes of the
In the 1950s, Configuration Management construction industry, the application of CM
(CM) principles were first documented and assumes a slightly different meaning. In the
adopted by the United States Department of management of large multi-contract projects,
Defense (DoD). The DoD focus on CM CM is applied to the design, construction,
started when concerns over life safety issues maintenance, and operations phases to control
were raised during the design and
and document all changes to project baseline time an unsanctioned change is recognized and
drawings and specifications. dealt with, a project manager is often forced to
As construction projects grow larger and enter a reactive mode and perform damage
more complex, the necessity for CM increases. control.
This concept is particularly true with todays If a formal CM system were in-place, the
evolving project delivery approaches where causal chain of events permitting the non-
the owners contractual relationship and sanctioned change to grow and overwhelm a
involvement requires a reengineering of project would have been documented,
project control strategies. The need for reviewed, and curtailed before ever causing a
accurate and readily attainable status, trending, problem. So, it comes as no surprise that
exception reporting, and other key projects performed without a formal CM
performance measures is crucial to project strategy are often the victims of change.
success.
4. Embracing Change
3. Defining and Recognizing Change
Change, in and of itself, is not inherently
CM is the process of managing the good or bad. The manner in which change is
inevitable change occurring during every managed can either result in a huge problem or
phase of the project lifecycle. In this context, a great success story.
change refers to any measurable deviation CM pundits embrace change as a means of
from the project scope mutually agreed upon expanding project scope and business. Non-
by the contractor and client. The larger and practitioners of CM often see mid-project
more complex the project, the greater the scope changes as problems to be dealt with
likelihood and impact of change. Change, in rather than opportunities for growth.
turn, is the primary reason for schedule Accommodating change in a graceful and
slippage and cost overruns. controlled manner can increase profit margins
To the untrained eye, budget overruns and and bolster client relations, while being ill-
schedule slippage occurring during a project prepared for change (or failing to recognize it)
often come as a surprise to the unsuspecting can result in the perception of disorganization,
project manager and client. CM practitioners, poor management, or even negligence.
however, are quick to point out that these
events are not unforeseeable at all. Non- 5. Cost of Mismanaging Change
practitioners of CM simply lack the proper
tools to recognize and manage seemingly At first glance, the initial and recurring
trivial scope changes before they become expenses associated with selecting, purchasing,
unmanageable and impact a projects schedule implementing, and enforcing a formalized
and budget. CM system appear costly. However, these
And it is not the changes that non- expenses are trivial when compared to the
practitioners of CM see so much as the affects costs incurred from not using CM.
they have on a project. These individuals A case study performed by the Los
spend a great deal of time analyzing a Angeles County Metropolitan Transit
projects history to unearth the cause of a Authority in 1990 compared the relative
schedule slippage or budget overrun. construction costs of two similar railroad
To the non-practitioner, seemingly trivial segments in their $5.3 billion Rapid Transit
changes often go unnoticed, or even worse, are Program, one performed using CM principles
ignored because of their presumably and one without. The study concluded the
inconsequential nature. Unfortunately, these railway segment constructed using CM
types of changes are given their due achieved a 60% reduction in administrative
recognition only after having grown large costs, saving over $10 million; enabled
enough to negatively impact the project information request responses in minutes
schedule, budget, and client relations. By the rather than days; realized a 90% reduction in
contractor claims due to improved change Document Management
order processing times; and shifted the project Under the principles of CM, all documents
focus from data gathering to training, analysis, generated within a project are closely managed,
and management [4]. tracked, and archived. This process includes
tracking and archiving all document changes,
6. Configuration Management versions, and approval communications. This
Methodology level of detail is necessary to avoid the
inclusion of ad-hoc document changes without
CM can be expressed as four distinct core following a formal document approval process.
areas: CM planning, document management, Managed documents include schedules,
baseline management, and change diagrams, drawings, plans, specifications,
management [5]. In practice each of these training material, manuals, requests for
areas is dependent upon (and linked to) the information, change requests, and all written
remaining three. daily project correspondences.

Configuration Management Planning Baseline Management


CM planning involves determining what Establishing and maintaining baseline
needs to be controlled; when those controls states for a project is a fundamental CM
take effect; how changes are managed; and the precept. Baseline management involves the
level of effort required to perform CM. This capture and archive of the exact state of a
information is documented in a CM Plan, project during key points of the project
which contains the processes and procedures lifecycle. Document management plays a key
describing how the configuration of the new role in managing a projects baseline states.
system is controlled [6]. The CM Plan is the Every version of every document is
nucleus of effective CM enforcement, archived, and the relationship between
containing the business rules governing documents is captured. This level of detail
document management, baseline management, permits the re-visitation of any phase of a
and change management. projects history for change validation,
The CM Plan contains a workflow clearly auditing, and lessons learned purposes.
describing the roles, responsibilities, and Effective baseline management provides
authority levels of all participating members the contractor and client with a virtual paper
engaged on a project. Participating members trail of all documents and written
include all project staff, third-party consultants, communications from project conception
contractors, and client staff. This workflow through close-out. This comprehensive
provides the foundation for all formal archive enables the contractor and client to
communication and decisions made during a review all supporting documentation and
project. communications that existed at a particular
Strict adherence to the communication and time. Each project baseline is a virtual
decision pipeline within a CM enforced snapshot in time of every step of a projects
project eliminates the potential for history.
miscommunication, misrouted information,
and improper decision making. All Change Management
communications are shared with appropriate Change management is the process of
senior members involved within the project, approving (or denying) changes impacting
resulting in complete visibility, accountability, project scope, schedule, and budget. CM
and tracking. All decisions flow through a planning provides the rules governing change
formal documented process of disclosure, management, while document management
review, and acceptance by the contractor and and baseline management provide the detailed
client. This decision process avoids ad-hoc project history substantiating change
decision making (i.e. changes) impacting the management.
project schedule and budget.
7. Implementing Configuration implications of failing to perform CM are
Management immeasurable. The cost of implementing and
maintaining a CM solution will pay for itself
Due to the complexity and level of effort several times over during the course of any
required to perform CM on complex project. Although formal CM
construction projects, a software solution is implementations in the construction industry
the only practical approach. A capable CM are currently uncommon, the industry needs to
solution must contain a minimal set of core look no further than other private and public
functionality to achieve effectiveness. sectors successfully using and enjoying the
At the highest level, the CM system must benefits of CM for decades.
be configured with the clients business rules Similar to the recent industry acceptance
(described in the CM Plan) for governing and mandatory requirement for using risk
intra-project communication, document management in the construction industry, CM
storage and retention, and change management. has the potential for being adopted as the next
Document management functionality must industry-wide standard.
contain the ability to store electronic and
scanned documents, and link those documents 9. References
to specific projects, personnel, schedules, and
other documents and correspondences. [1] International Organization for
A detailed search and retrieval function is Standardization, ISO:10007:2003, Quality
essential to view a project baseline from a management systems Guidelines for
particular point in time. Viewing a time- configuration management, 2003.
specific baseline involves extracting particular [2] Project Management Institute, A Guide to
archived versions of documents, the Project Management Body of Knowledge,
correspondences, schedules, budgetary items, Third Edition (PMBOK Guide), p. 90, 2004.
project staff, and links relating each of these [3] ANSI/EDI 649-1998, National Consensus
aforementioned items to each other. This level Standard for Configuration Management,
of search and cross-linking is necessary to 1998.
perform audits either during a project and after [4] Los Angeles Metropolitan Transit
its completion. Authority, Rapid Transit Program, Intra-
Finally, user-level and group-level Agency Study, 1990.
permissions and robust security are essential [5] PACO Technologies, Inc., ccsNet
when multiple agencies, contractors, and Configuration Management Methodology,
subcontractors require access to the CM 2004.
system. [6] Mitretek Systems, Inc., Intelligent
Transportation Systems Joint Program Office,
8. Conclusion United States Department of Transportation,
A Guide to Management for Intelligent
When considering the benefits of Transportation Systems, p. 5, 2002.
performing CM on a large or complex
construction project, the financial and business

Вам также может понравиться