SECTION 4

BILL OF QUANTITIES
General Description of work : Infrastructure Development and Upgradation Works in Industrial Area Ghironghi/Malanpur, District Bhind (M.P.)
Probable Amount of Contract :
(Rs. In Figure) : Rs. 38,84,76,338/-
(Rs. In Words) : Rupees Thirty Eight Crores Eighty Four Lakhs Seventy Six Thousand Three Hundred and Thirty Eight Only/-

Amount
S. No. Particulars of Item of Work Quantity Unit Rate
(in figure)
I II III IV V VI
1 Clearing and Grubbing Road Land. (Clearing and grubbing road land including uprooting
rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of
stumps of trees cut earlier and disposal of unserviceable materials and stacking of
serviceable material to be used or auctioned up to a lead of 1000 metres including
15.51 Hect. 35090.00 544,175
removal and disposal of top organic soil not exceeding 150 mm in thickness.) - In area of
light jungle

2 Dismantling of Flexible Pavements (Dismantling of flexible pavements and disposal of


dismantled materials up to a lead of 1000 metres, stacking serviceable and unserviceable
materials separately) By Mechanical Means - 925.56 Cum 237.00 219,357
Bituminous course

3 Dismantling of Flexible Pavements (Dismantling of flexible pavements and disposal of


dismantled materials up to a lead of 1000 metres, stacking serviceable and unserviceable
materials separately) By Mechanical Means - 3567.80 Cum 237.00 845,568
Granular course
4 Dismantling Kerb Stone (Dismantling kerb stone by manual means and disposal of
dismantled material with all lifts and up to a lead of 1000 metre)
16447.38 metre 12.00 197,368

Page - 72
Amount
S. No. Particulars of Item of Work Quantity Unit Rate
(in figure)
5 Excavation in Soil using Hydraulic Excavator and Tippers with disposal upto 1000
metres. (Excavation for roadwork in soil with hudraulic excavator of 0.9 cum bucket
capacity including cutting and loading in tippers, trimming bottom and side slopes, in
accordance with requirements of lines, grades and cross sections, and transporting to the 17813.18 Cum 50.00 890,658
embankment location within all lifts and lead upto 1000m)

6 Scarifying existing bituminous surface to a depth of 50 mm by mechanical means


(Scarifying the existing bituminous road surface to a depth of 50 mm and disposal of
scarified material with in all lifts and lead upto 1000 meters.) 132495.00 Sqm 4.00 529,980

7 Embankment Construction with Material Obtained from Borrow Pits (Construction of


embankment with approved material CBR>5 obtained from borrow pits with all lifts and
leads, transporting to site, spreading, grading to required slope and compacting to meet 14915.38 Cum 154.00 2,296,968
requirement of table 300-2)

8 Embankment Construction with Material Deposited from Roadway Cutting


(Construction of embankment with approved materials CBR>5 deposited at site from
roadway cutting and excavation from drain and foundation of other structures graded and 11403.99 Cum 73.00 832,491
compacted to meet requirement of table 300-2)

9 Plant Mix Method (Construction of granular sub-base by providing close graded Material,
mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site,
spreading in uniform layers with motor grader on prepared surface and compacting with
vibratory power roller to achieve the desired density, complete as per clause 401) - 19992.63 Cum 989.00 19,772,713
for grading-I Material

Page - 73
Amount
S. No. Particulars of Item of Work Quantity Unit Rate
(in figure)
10 Wet Mix Macadam (Providing, laying, spreading and compacting graded stone aggregate
to wet mix macadam specification including premixing the Material with water at OMC in
mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers
with paver in sub- base / base course on well prepared surface and compacting with 35481.10 Cum 1330.00 47,189,865
vibratory roller to achieve the desired density.) and as per clause of section 400.

11 Construction of Median and Island with Soil Taken from Borrow Areas (Construction
of median and island above road level with approved material brought from borrow pits,
spread, sloped and compacted as per clause 407) 11850.28 Cum 177.00 2,097,499

12 Construction of Shoulders with approved material / selected soil i/c excavation all lifts &
leads i/c grading to required slope & camber and compacting using vibratory roller of 80 to
100 kN static weight to meet requirement as per relevant clause of 400. 28914.13 Cum 223.00 6,447,849
Hard Shoulders (CBR value > 12)

13 Prime Coat (Providing and applying primer coat with bitumen emulsion on prepared
surface of granular Base including clearing of road surface and spraying primer at the rate
of 0.75 kg/sqm using mechanical means.) 166469.02 Sqm 35.00 5,826,416

14 Providing and applying tack coat with bitumen emulsion using emulsion pressure
distributor on the prepared bituminous/granular surface cleaned with mechanical broom
and as per relevant clauses of section-503. {@ 0.25 kg per sqm (normal bituminous 166469.02 Sqm 12.00 1,997,628
surfaces)}

15 Providing and applying tack coat with bitumen emulsion using emulsion pressure
distributor on the prepared bituminous/granular surface cleaned with mechanical broom
and as per relevant clauses of section-503. {@ 0.30 kg per sqm (dry & hungry
166469.02 Sqm 15.00 2,497,035
bituminous surfaces/granular surfaces treated with primer)}

Page - 74
Amount
S. No. Particulars of Item of Work Quantity Unit Rate
(in figure)
16 Dense Graded Bituminous Macadam (Providing and laying dense bituminous macadam
using crushed aggregates of specified grading, premixed with bituminous binder @ 4.0 to
4.5% by weight of total mix and filler, transporting the hot mix to work site, laying with a
hydrostatic paver finisher with sensor control to the required grade, level and alignment,
rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired
compaction as per MoRTH specification clause No. 507 complete in all respects.) 9988.15 Cum 7415.00 74,062,168
Using 100-120 TPH Batch mix Plant and Paver Finisher
Hydraustatic with Sensor control. {for Grading II (19 mm nominal size)}

17 Bituminous Concrete (Providing and laying bituminous concrete using crushed


aggregates of specified grading, premixed with bituminous binder @ 5.4 to 5.6% of mix
and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with
sensor control to the required grade, level and alignment, rolling with smooth wheeled,
vibratory and tandem rollers to achieve the desired compaction as per MoRTH
specification clause No. 509 complete in all respects) {Using 100-120 TPH Batch mix 6658.77 Cum 8493.00 56,552,933
Plant and Paver Finisher Hydraustatic with Sensor control.} - [for Grading II (30-45 mm
thickness ) with 60/70 bitumen (VG-30)]

18 Dry Lean Cement Concrete Sub-base (Construction of dry lean cement concrete Sub-
base over a prepared sub-grade with coarse and fine aggregate conforming to IS: 383, the
size of coarse aggregate not exceeding 25 mm, aggregate cement ratio not to exceed
15:1, aggregate gradation after blending to be as per table 600-1, cement content not to
be less than 150 kg/ cum, optimum moisture content to be determined during trial length
construction, concrete strength not to be less than 10 Mpa at 7 days, mixed in a batching
plant, transported to site, laid with a paver with electronic sensor, compacting with 8-10 2876.12 Cum 2383.00 6,853,802
tonnes vibratory roller, finishing and curing)

Page - 75
Amount
S. No. Particulars of Item of Work Quantity Unit Rate
(in figure)
19 Cement Concrete Pavement (Construction of un-reinforced, dowel jointed, plain cement
concrete pavement M-40 grade concrete over a prepared sub base with cement, coarse
and fine aggregate conforming to IS 383, maximum size of coarse aggregate not
exceeding 25 mm, mixed in a batching and mixing plant as per approved mix design,
transported to site, laid with a fixed form or slip form paver, spread, compacted and
finished in a continuous operation including provision of contraction, expansion,
construction and longitudinal joints, joint filler, separation membrane, sealant primer, joint
sealant, debonding strip, admixtures as approved, curing compound, finishing to lines and 5752.25 Cum 5847.00 33,633,385
grades as per drawing as per IRC-15 2011 and as per relevant clauses of section 602 of
specifications complete but excluding cost of steel in dowel bar and tie rods etc.)

20 The cost of steel in dowel bar and tie rod including craddle, laps etc. complete required as
per design. (Mild steel) 41.64 tonne 61068.70 2,543,064

21 The cost of steel in dowel bar and tie rod including craddle, laps etc. complete required as
per design. (Tor steel)
3.49 tonne 63561.30 221,777

22 Cast in Situ Cement Concrete M20 kerb (Construction of cement concrete kerb with top
and bottom width 115 and 165 mm respectively, 250 mm high in M 20 grade PCC on M-10
grade foundation 150 mm thick, foundation having 50 mm projection beyond kerb stone,
kerb stone laid with kerb laying machine, foundation concrete laid manually, all complete
and as per clause 408) Using Concrete Batching and Mixing 19687.38 metre 236.00 4,646,222
Plant

23 Painting Two Coats on New Concrete Surfaces (Painting two coats after filling the
surface with synthetic enamel paint in all shades on new plastered concrete surfaces)
Kerb 7185.89 Sqm 51.00 366,481

Page - 76
Amount
S. No. Particulars of Item of Work Quantity Unit Rate
(in figure)
24 Road Marking with Hot Applied Thermoplastic Compound with Reflectorising Glass
Beads on Bituminous Surface (Providing and laying of hot applied thermoplastic
compound 2.5 mm thick including reflectorising glass beads @ 250 gms per sqm area,
thickness of 2.5 mm is exclusive of surface applied glass beads as per IRC:35. The 9950.33 Sqm 636.00 6,328,407
finished surface to be level, uniform and free from streaks and holes)

25 Providing and laying Plain/Reinforced cement concrete in open foundation including form
work shuttering etc. complete as per drawing and technical specifications and as per
relevant clauses of sections 1500, 1700 & 2100 with. {PCC Grade M15 (Side Slope)} 191.25 Cum 4502.00 861,008

26 Dismantling of Structures (Dismantling of existing structures like culverts, bridges,


retaining walls and other structure comprising of masonry, cement concrete, wood work,
steel work, including T&P and scaffolding wherever necessary, sorting the dismantled
material, disposal of unserviceable material and stacking the serviceable material with all
lifts and lead upto 1000 metres) Dismantling 255.00 Cum 230.00 58,650
Stone Masonry - (Rubble stone masonry in Cement mortar)

27 Excavation for Structures (Earth work in excavation of foundation of structures as per


drawing and technical specification, including setting out, construction of shoring and
bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and
44366.19 Cum 50.00 2,218,309
backfilling with approved material.) as per relevant clauses of section 300 & 2100 in

28 Providing and laying Plain/Reinforced cement concrete in open foundation including form
work shuttering etc. complete as per drawing and technical specifications and as per
relevant clauses of sections 1500, 1700 & 2100 with. (PCC Grade M15) 2844.00 Cum 4502.00 12,803,688

Page - 77
Amount
S. No. Particulars of Item of Work Quantity Unit Rate
(in figure)
29 Providing and laying Plain/Reinforced cement concrete in open foundation including form
work shuttering etc. complete as per drawing and technical specifications and as per
relevant clauses of sections 1500, 1700 & 2100 with. (RCC Grade M20) - (With 6393.56 Cum 5070.00 32,415,362
Batching Plant, Transit Mixer and Concrete Pump)

30 Supplying, fitting and placing un-coated HYSD bar reinforcement in foundation complete
as per drawing and technical specifications and as per relevant clauses of sections 1600.
272.51 tonne 75306.00 20,521,777

31 Furnishing and Placing Reinforced/Prestressed cement concrete in super-structure as per


drawing and Technical Specification and as per relevant clauses of sections 1500,1700
and 2300 in Using Batching Plant, Transit Mixer and Concrete Pump. (i) For 133.00 Cum 5720.00 760,760
solid slab super-structure, 20-30% of (a+b+c) (a) Height upto 5m

32 Supplying, fitting and placing HYSD bar reinforcement in super-structure complete as per
drawing and technical specifications as per relevant clauses of section 1600 8.13 tonne 76480.00 621,683

33 Excavation for Structures (Earth work in excavation of foundation of structures as per


drawing and technical specification, including setting out, construction of shoring and
bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and
backfilling with approved material.) as per relevant clauses of section 300 & 2100 in 1617.97 Cum 50.00 80,898

34 Providing P.C.C. M-15 Nominal mix for hume pipe culverts in foundation and sub
structure etc. as per drawing and as per relevant clauses of section 1500, 1700, 2100 and 480.53 Cum 4695.00 2,256,074
2900

35 Providing and laying Plain/Reinforced cement concrete in open foundation including form
work shuttering etc. complete as per drawing and technical specifications and as per
relevant clauses of sections 1500, 1700 & 2100 with. (PCC Grade M15) 27.14 Cum 4502.00 122,206

Page - 78
Amount
S. No. Particulars of Item of Work Quantity Unit Rate
(in figure)
36 Providing and laying Plain/Reinforced cement concrete in open foundation including form
work shuttering etc. complete as per drawing and technical specifications and as per
relevant clauses of sections 1500, 1700 & 2100 with. (PCC Grade M20) 154.34 Cum 4998.00 771,368

37 Providing and laying Plain/Reinforced cement concrete in sub-structure or complete RCC


Box section as per drawing and technical specifications and as per relevant clauses of
sections 1500, 1700 & 2200 in (Height above average ground level) (PCC Grade M20) 159.55 Cum 5220.00 832,861

38 Providing and laying Plain/Reinforced cement concrete in sub-structure or complete RCC


Box section as per drawing and technical specifications and as per relevant clauses of
sections 1500, 1700 & 2200 in (Height above average ground level) (RCC Grade M30) 14.13 Cum 5859.00 82,776

39 Supplying, fitting and placing un-coated HYSD bar reinforcement in foundation complete
as per drawing and technical specifications and as per relevant clauses of sections 1600 0.376 tonne 75306.00 28,315
(Reinforcement @ 5kg/sqm)

40 Supplying, fitting and placing HYSD bar reinforcement in sub-structure complete as per
drawing and technical specifications and as per relevant clauses of sections 1600
1.35 tonne 75415.00 101,937

41 Providing and laying Reinforced / Prestressed cement concrete in superstructure as per


drawing and Technical Specification and as per relevant clauses of sections 1500, 1700
and 2300 in (M30) Solid slab Super structure 28.5 Cum 6392.00 182,172

42 a) Supplying, fitting and placing HYSD bar reinforcement complete in superstructure


complete as per drawing and technical specifications as per relevant clauses of section
1600 of specifications 2.00 tonne 76480.00 152,578

Page - 79
Amount
S. No. Particulars of Item of Work Quantity Unit Rate
(in figure)
43 Providing weep holes in Brick masonry/Plain/Reinforced concrete abutment, wing
wall/return wall with 100 mm dia AC pipe, extending through the full width of the structure
with slope of 1V :20H towards water face. Complete as per drawing and Technical 64.432 metre 122.00 7,861
specifications and as per clause 2706 of specifications.

44 Providing and laying of Filter media with granular materials/stone crushed aggregates
satisfying the requirements laid down in clause 2504.2.2. of MORTH specifications to a
thickness of not less than 600 mm with smaller size towards the soil and bigger size
towards the wall and provided over the entire surface behind abutment, wing wall and
39.64 Cum 1127.00 44,677
return wall to the full height compacted to a firm condition complete as per drawing and
technical specification.

45 Providing and fixing in position bituminous paper bearing for slabs as per approved
drawing and confirming to IS:1398. 16 Sqm 48.00 768

46 (ii) Filler joint - Providing & fixing 20 mm thick & 25cm deep compressible fibre board in
expansion joint complete as per drawing & Technical Specification and as per relevant 40 metre 418.00 16,720
clauses of section 2600

47 Providing PCC M15 Grade leveling course below approach slab complete as per drawing
and Technical specification and as per relevant clauses of section 1700. 19.74 Cum 4268.00 84,250

48 Providing and laying Reinforced cement concrete approach slab in M-25 grade concrete
including reinforcement and formwork complete as per drawing and Technical specification
and as per relevant clauses of section 1500, 1600, 1700 and clause 2704 of 39.71 Cum 9257.00 367,605
specifications.

49 Providing and laying Cement concrete wearing coat M-30 grade including reinforcement
complete as per drawing and Technical Specifications and as per relevant clauses of
sections 1500, 1700 and Clause 2702 of specifications. 17.1 Cum 11107.00 189,930

Page - 80
Amount
S. No. Particulars of Item of Work Quantity Unit Rate
(in figure)
50 Providing Drainage Spouts complete as per drawing and Technical specification and as
per clause 2705 of specifications. 2 each 911.00 1,822

51 Back filling behind abutment, wing wall and return wall complete as per drawing and
Technical specification and as per relevant clauses 305 of specifications and as per
appendix 6 of IRC-78. (Granular material) 219.63 Cum 739.00 162,308

52 Laying Reinforced Cement Concrete Pipe NP4/prestressed concrete pipe on first


class bedding in single row. (Providing and Laying Reinforced cement concrete pipe
NP4/prestressed concrete pipe for culverts on first class bedding of granular material (cost
of bedding included) in single row including fixing collar with cement mortar 1:2 but
excluding excavation, protection works, backfilling, concrete and masonry works in head 125.00 metre 8818.00 1,102,250
walls and parapets.) 1200 mm dia

53 Laying Reinforced Cement Concrete Pipe NP4/prestressed concrete pipe on first


class bedding in double row. (Providing and Laying Reinforced cement concrete pipe
NP4/prestressed concrete pipe for culverts on first class bedding of granular material (cost
of bedding included) in double row including fixing collar with cement mortar 1:2 but
excluding excavation, protection works, backfilling, concrete and masonry works in head 82.50 metre 17754.00 1,464,705
walls and parapets.) 1200 mm dia

54 Reinforced Cement Concrete Crash Barrier (Provision of an Reinforced cement concrete


crash barrier at the edges of the road, approaches to bridge structures and medians,
constructed with M-20 grade concrete with HYSD reinforcement conforming to IRC:21 and
dowel bars 25 mm dia, 450 mm long at expansion joints filled with pre-moulded asphalt
filler board, keyed to the structure on which it is built and installed as per design given in
the enclosure to MOST circular No. RW/NH - 33022/1/94-DO III dated 24 June 1994 as 22.8 Rmt 3467.00 79,048
per dimensions in the approved drawing and at locations directed by the Engineer, all as
specified)

Page - 81
Amount
S. No. Particulars of Item of Work Quantity Unit Rate
(in figure)
55 Dismantling of Structures (Dismantling of existing structures like culverts, bridges,
retaining walls and other structure comprising of masonry, cement concrete, wood work,
steel work, including T&P and scaffolding wherever necessary, sorting the dismantled
material, disposal of unserviceable material and stacking the serviceable material with all
222.274 Cum 230.00 51,123
lifts and lead upto 1000 metres) (Dismantling Stone Masonry) - (Rubble stone masonry
in cement mortar. )

56 Dismantling of Structures (Dismantling of existing structures like culverts, bridges,


retaining walls and other structure comprising of masonry, cement concrete, wood work,
steel work, including T&P and scaffolding wherever necessary, sorting the dismantled
material, disposal of unserviceable material and stacking the serviceable material with all
lifts and lead upto 1000 metres) Removing all type of hume pipes and stacking within a 102.50 metre 278.00 28,495
lead upto 1000 metres including earthwork and dismantling of masonry works. - (Above
900mm dia.)

57 Rewiring in existing surface / concealed rigid steel / PVC non metalic conduit with PVC
insulated cable FR with copper multi strand conductor ISI marked and other materials as
required including replacement of worn-out / damaged / missing material, painting etc.
complete as per specification. This shall include all work, arrangement required for wiring
10020.00 Metre 25.00 250,500
but shall exclude switch, ceiling rose fitting etc. { 2 WIRE SUB-MAIN (2 x 2.5 Sq mm) }

Page - 82
Amount
S. No. Particulars of Item of Work Quantity Unit Rate
(in figure)
58 Supplying, fixing, testing & commissioning wall / floor mounted LT Panel primer coated
with two coat of enamel paint & provided with required gasket for dust / vermin proof with
degree of protection IP 42 suitable for 415 v 3 phase, 50 Hz, 4 wire system fabricated out
of CRCA sheet upto 2 mm thick (1.6 mm for doors) with frame work of angle iron / channel
/ bolted type construction duly compartmentalised for incomer, bus section, outgoings,
cable alleys & CT, PT Ampere Meter, Volt Meter, selector switches, Frequency Meter,
phase indicating lamps, energy Meter complete including cost of busbar supports
detachable gland plates, 2 earthing terminals, internal wiring and fixing of separately
supplied MCBs, MCCBs, panel mounted Changeover switch / SFUs, etc. as required but 5.00 Each 150000.00 750,000
including cost of busbar strips, Ampere Meter, Volt Meter, Selector switch as per approved
design & specification and including supplying and fixing LT Panel accessories of
approved make as required

59 Primer coat over new steel and other metallic surface with red oxide / zinc chromide paint
complete with supply of material labour etc. including preparation of surface. per sq
2351.15 14.00 32,916
Metre

60 Primer coat with aluminium paint, brushing complete with material and labour including per sq
preparation of surface 4702.30 Metre 19.00 89,344

61 Dismantling of existing underground cable safely with its accessories and refilling the
trench to ground level including recoiling of dismantalled cable. 22200 Metre 4.00 88,800

62 Dismantling of existing water tight fitting / M.V. Lamp fitting with extension bracket, clamp
from pole or wall with making the site clear. 150 Each 6.00 900

63 Earthing with G.I. Earth pipe 4.5 Metre long and 40 mm dia with masonary enclosure in
cement mortar, cover plate having locking arrangement on the top etc. (but without
charcoal or coke and salt) complete as required 113 Each 1598.00 180,574

Page - 83
Amount
S. No. Particulars of Item of Work Quantity Unit Rate
(in figure)
64 Add Extra for using salt and charcoal / coke for pipe earth electrode as required including
excavation and refilling. (Excavation 2.5 cum by manual labour) 113 Each 429.00 48,477

65 Supplying and laying 6 SWG G.I. wire at 0.5 Metre below ground level as conductor earth
electrode including soldering etc. as required. 25930 Metre 13.00 337,090

66 Supply of XLPE Insulated power cable (conforming IS-7098) 1100 Volt grade/Heavy duty
power cable conforming to IS 1554-1964) 1100 Volts grade, 2 core / 3 1/2 core /4 core ISI
MARKED with Aluminium Stranded / solid conductor { ARMOURED 4 CORE (16 Sq. 38700 Metre 188.00 7,275,600
mm. (XLPE) }

67 Supplying and fixing cramping type Alum, lugs as per I.S.S. Specificationsuitable for
following size of cable with Alu. / Copper solid / stranded conductor evently cramped with
high / pressure tool and connected to switch gear / Bus / M.C.C.B. / M.C.B. etc. as 6136 Each 4.00 24,544
required complete. For Conductor Size- (6 mm to 16 Sq. mm)

68 Supplying and installing Double wall corrugated pipes (DWC) of HDPE (IS 14930 Part II -
marked) for cable laid under ground with necessary connecting sockets / couplings, tees of
same material and at required depth upto 90 cm. below road/ground surface, including
excavation, back filling with excavated material with ramming and making the surface 23750 Metre 160.00 3,800,000
good. (50.00mm O.D)

69 Laying of one number PVC insulated and PVC sheathed power cable of 1.1kV grade of
size not exceeding 25 Sq.mm in the existing RCC Hume/Stone/Ware/G.I. pipe as required. 38700 Metre 10.00 387,000

70 Supply of steel tubular pole swaged type as per IS: 2713-1980 complete with baseplate
and top canopy (410 SP-44 - 10.00 metre (A) Double Arm)
120 Each 11488.00 1,378,560

Page - 84
Amount
S. No. Particulars of Item of Work Quantity Unit Rate
(in figure)
71 Supply of steel tubular pole swaged type as per IS: 2713-1980 complete with baseplate
and top canopy (410 SP-40 (Bend type) 10.00 metre (B) Single Arm)
62 Each 9357.00 580,134

72 Supplying and erection of water tight terminal box of 14 SWG M.S. Sheet 4 mm thick box
of required size to erect the suitable kit kat / MCB / Switch with Top & bottom folded fitted
with rubber ring to make it water tight with pole clamp made from 40 x 3 mm M.S. flat iron
with 2 Nos. Nut and Bolts duly painted with 2 coat of Red Oxide paint and 2 coat of
aluminium silver paint erected with cable gland but excluding the cost of the Kit Kat / 767 Each 323.00 247,741
MCB / Switch complete as per specification. - (30 x 20 x 15 Cms.)

73 Installing iron clad weather proof cut outs on existing pole or surface board/boxes with
necessary materials complete including fixing and connection etc. excluding cost of
cutouts as required: (15/16 Amps. 250 volts) 767 Each 24.00 18,408

74 Erection of steel tubular or steel rail pole or H-Beam of length exceeding 8 metres but not
exceeding 10 metres in cement concrete 1:3:6 (1 cement : 3 coarse sand : 6 graded stone
aggregate 40 mm nominal size) foundation, base padding & muffing including excavation
182 Each 1106.00 201,292
and refilling etc. as required. (4.55 bags of cement/cmt.)

75 Dismantling poles / street light standards / struts embedded in cement concrete foundation
etc. as required. 150 Each 285.00 42,750

Page - 85
Amount
S. No. Particulars of Item of Work Quantity Unit Rate
(in figure)
76 Providing and erecting 16mt High Mast Lighting system with 6 No. Metal hallide flood light fitting 400
Watt each complete with control gear and lamps with integral Power tool, weight 550 kg. comprising
of 2 sections of hot dipped galvanized materials as per BSEN ISO 1461 thickness 3 mm & 4 mm, dia
150 mm & 460 mm for top and bottom respectively, stress fitting arrangement on site with 500 mm
overlap dynamic loading to withstand max wind pressure as per IS 875 part III, parameters for
structural & foundation design must be taken from Wind Tunnel test. Lightning protection of GI single
spike 1200mm at top and at base inside compartment with double internal lock with adequate size of
MCB erected on PVC board complete with base plate of 25 mm thick 670 mm dia. and foundation
bolts having 8 nos. bolts of 30 mm dia. 850 mm long (E 6.8 grade) Anchor plate 590 PCD, 670 x 670
x 8 mm including accessories viz. (1) Lantern carriage of 50 NB ERW class-B, PI pipe covered with
PVC sleeve suitable to carry 500 kg. load and upto 8 fittings symmetrically. (2) Trailing Copper cable
5 x 2.5 sq. mm, EPR insulated PCP Sheatehed (3) Double Drum Winch having gear 53:1, oil bath
(SAE90/140) arrangement (4) 2 nos. Stainless steel wire ropes 6 mm dia. (7/19) breaking load
capacity 2400 kg. x 2, (5) Integral power tool 3-phase, 1 HP 2m/min single speed . torque limiter upto 3 Each 315000.00 945,000
500 kg adjustable (6) Twin door aviation light of type of BJAOL 2 with two numbers 100W lamps (7)
Feeder pillar fabricated out of 14 SWG CRCA sheet and comprise of incoming 32 A TPN switch,
HRC fuses, single dial timer, suitable size of contactors for lighting and power tool, 2 nos. outgoing,
reversing switch for motor.

77 Designing & casting of Open raft shallow footing foundation with M-20 cement concrete
suitable for 16 mtrs. High Mast considering the safe soil bearing capacity at site as 10
T/sqm at 2 mtrs. Depth including excavation, foundation nut bolts in an approved manner. 3 Each 47000.00 141,000

78 Providing and laying in position cement concrete of specified grade excluding the cost of
centering and shuttering - All work up to plinth level: (0.4 x 0.4 x 0.5) x 670 {With 20 mm
nominal size graded stone aggregate} M 10 53.60 Cum 2900.00 155,440

Page - 86
Amount
S. No. Particulars of Item of Work Quantity Unit Rate
(in figure)
79 Centering and shuttering including strutting, propping etc. and removal of form work for:-
(0.4 x 0.5 ) x 4 x 670 {Foundations, footings, bases for columns.} 536.00 Sqm 127.00 68,072

80 12mm thick cement plaster of mix 1:6 (0.4 x 0.5) x 4 + (0.4 x


0.4) x 670 - {1:6 (1 Cement : 6 Sand)} 108.00 Sqm 80.00 8,640

81 Demolishing cement concrete manually / by mechanical means 1:3:6 or richer mix -


(0.4 x 0.4 x 0.9) x 670 {1:3:6 or richer mix} 96.48 Cum 397.00 38,303

82 LED BASED OUTDOOR LIGHTING: Heavy Duty IP 65 LED Light / Lamp as Flood /
Road / Street light type luminaire with System wattage of 90 W (Phillips make / Crompton 672.00 Each 18000.00 12,096,000
make)
83 Earthwork in excavation for pipe trench in all kinds of rocks in areas including dressing,
stacking of useful material and disposal of unserviceable one upto 50 m lead and lift upto
1.5 m. (b) Hard rock requiring blasting 247.50 Cum 311.00 76,973

84 Earthwork in excavation for pipe trench in all kinds of rocks in areas including dressing,
stacking of useful material and disposal of unserviceable one upto 50 m lead and lift upto
1.5 m. (c) Hard rock requiring chiseling / where blasting is prohibited 247.50 Cum 331.00 81,923

85 Filling with moorum for pipe bedding or over the pipe including supply of moorum
495.00 Cum 170.00 84,150

86 Providing, laying and jointing following socket & spigot centrifugally cast (Spun) Ductile
Iron pressure pipes with inside cement mortar lining (class K-7) conforming to IS
8329/2000 with suitable Rubber Gasket (Push on) joints as per IS: 5382/85 including (200 550.00 Rmt 1808.00 994,400
mm dia)

87 Providing and Laying Ductile Iron Double Socket 90 0 Bends conforming to IS-9523/2000
having dimension as per table 15 of IS-9523/2000 in the following nominal diameter/sizes
with external bitumen coating and internal cement mortar lining. (200 mm) 2 Each 3107.00 6,214

Page - 87
Amount
S. No. Particulars of Item of Work Quantity Unit Rate
(in figure)
88 Providing & fixing of following Cast iron double flanged sluice valves as per IS:14846-2000
fitted with cast iron cap including jointing & testing with cost of jointing material such as
bolts, nuts, rubber insertions etc. all complete (200mm dia (PN-1.0)) 1 Each 9540.00 9,540

89 Constructing masonry chamber 90 x 90 x 100 cm inside with brick of crushing strength not
less than 25 kg/sqcm and water absorption not more than 20% class designation brick
work in cement mortar 1:4 (1 cement : 4 sand) 160 mm bottom diameter and 180 mm
deep (inside) with chained lid and RCC top slab 1:2:4 mix (1 cement : 2 sand : 4 graded
stone aggregate 20 mm nominal size) necessary excavation foundation complete 1:5:10 (1
cement : 5 fine sand : 10 graded stone mortar 1:3 (1 cement : 3 sand) 12 mm thick 2 Each 6148.00 12,296
finisged with a floating coat of neat cement complete as per standard design. (With
Modular bricks)

90 Providing & laying in position following cast iron plain ended standard specials confirming
to IS 5531/1988 (Reaffirmed 2002) {Cast Iron Blank end cap (200mm) Class 10} 1 Each 952.00 952

91 Earth work in excavation of foundation of structures as per drawing and technical


specification, including setting out, construction of shoring and bracing, removal of stumps
and other deleterious matter, dressing of sides and bottom and backfilling with approved
material etc. and as per relevant clauses of section 300 & 2100 in In all types of 65.38 Cum 50.00 3,269
soils

92 Providing and laying Plain/Reinforced cement concrete in open foundation including form
work shuttering etc. complete as per drawing and technical specifications and as per
relevant clauses of sections 1500, 1700 & 2100 with. - (PCC Grade M15) 3.85 Cum 4,502.00 17,313

93 Providing and laying Plain/Reinforced cement concrete in open foundation including form
work shuttering etc. complete as per drawing and technical specifications and as per
relevant clauses of sections 1500, 1700 & 2100 with. - (PCC Grade M20) 38.46 Cum 4,998.00 192,208

Page - 88
Amount
S. No. Particulars of Item of Work Quantity Unit Rate
(in figure)
94 Painting Two Coats on New Concrete Surfaces (Painting two coats after filling the
surface with synthetic enamel paint in all shades on new plastered concrete surfaces) 124.60 Sqm 51.00 6,355

95 Construction of Median and Island with Soil Taken from Borrow Areas (Construction
of median and island above road level with approved material brought from borrow pits,
spread, sloped and compacted as per clause 407) 328.42 Cum 177.00 58,130

96 Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in


over areas foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan)
including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out
the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 110.25 Cum 107.00 11,797
m. - (All kinds of soil)

97 Earth work in excavation by mechanical means (Hydraulic excavator) / manual means over
areas (exceeding 30cm in depth. 1.5m in width as well as 10 sqm on plan) including
disposal of excavated earth, lead upto 50m and lift upto 1.5m, disposed earth to be 154.35 Cum 171.00 26,394
levelled and neatly dressed. - (Ordinary rock)

98 Providing and laying in position cement concrete of specified grade excluding the cost of
centering and shuttering - All work up to plinth level : With 40mm nominal size graded 11.03 Cum 3362.00 37,066
stone aggregate. (M15)
99 Reinforced cement concrete work in walls (any thickness), including attached pilasters,
buttresses, plinth and string courses, fillets, columns, pillars, posts and struts suspended
floor roof slab, beams, etc. up to floor two level excluding cost of centering, shuttering,
finishing and reinforcement : M 20 Nomial mix (with 20mm nominal size graded stone 137.44 Cum 4321.00 593,861
aggregate)

100 Reinforcement for R.C.C. work including straightening, cutting, bending, placing in position
and binding including cost of binding wire up to floor two level including all wastage etc.
complete. Thermo-Mechanically Treated bars. (TMT) 20615.40 kg 42.00 865,847

Page - 89
Amount
S. No. Particulars of Item of Work Quantity Unit Rate
(in figure)
101 Centering and shuttering including strutting, propping etc. and removal of form for :
Foundations, footings, bases of columns, etc. for mass concrete up to plinth level. 170.88 Sqm 127.00 21,702

102 Walls (any thickness) including attached pilasters butteresse s, plinth beams and string
courses etc. up to plinth level. 43.20 Sqm 193.00 8,338

103 Suspended floors, roofs, landings, balconies and access platform. Shelves (Cast in situ)
Lintels, beams, beams, girders, bressumers and cantilevers, Columns, Pillars, Posts and
Struts Walls in super structure. 540.40 Sqm 199.00 107,540

104 Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations
etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming
and watering, lead up to 50 m and lift upto 1.5 m. 154.34 Cum 49.00 7,563

105 Supplying and filling in plinth with Hard muram/ Hard copra under floors including,
watering, ramming consolidating and dressing complete 38.56 Cum 337.00 12,995

106 Brick work with M.S. bricks of class designation 40 in superstructure above plinth level up
to floor II level in all shapes and sizes in : Cement mortar 1:6 (1 cement : 6 sand) 28.44 Cum 3599.00 102,356

107 Extra for brick work in superstructure above floor II level for each additional floor or part
28.44 Cum 35.99 1,024
thereof.

108 12 mm cement plaster of mix : 1:6 (1 cement: 6 sand) 133.76 Sqm 80.00 10,701

109 20 mm cement plaster of mix : 1:4 (1 cement: 4 sand) 305.28 Sqm 129.00 39,381

Page - 90
Amount
S. No. Particulars of Item of Work Quantity Unit Rate
(in figure)
110 Finishing walls with Deluxe Multi surface paint system for interiors and exteriors using
primer as per manufacturers specifications : Two or more coats applied @ 1.25 ltr/10 sqm.
Over and including one coat of Special primer applied @ 0.75 ltr / 10 sqm. 439.04 Sqm 71.00 31,172

Total Amount (Rs. In Figure) 388,476,338

Total Amount (Rs. In Words) : Rupees Thirty Eight Crores Eighty Four Lakhs Seventy Six Thousand Three Hundred and Thirty Eight Only/-

Page - 91
SECTION 4
BILL OF QUANTITIES
ustrial Area Ghironghi/Malanpur, District Bhind (M.P.)

ree Hundred and Thirty Eight Only/-

Amount (in
Remarks
words)
VII VIII

Five Lakhs Forty Four


Thousand One Hundred and
Seventy Five

Two Lakhs Nineteen


Thousand Three Hundred
and Fifty Seven

Eight Lakhs Forty Five


Thousand Five Hundred and
Sixty Eight

One Lakh Ninty Seven


Thousand Three Hundred
and Sixty Eight

Page - 92
Amount (in
Remarks
words)

Eight Lakhs Ninty Thousand


Six Hundred and Fifty Eight

Five Lakhs Twenty Nine


Thousand Nine Hundred and
Eighty

Twenty Two Lakhs Ninty Six


Thousand Nine Hundred and
Sixty Eight

Eight Lakhs Thirty Two


Thousand Four Hundred and
Ninty One

One Crore Ninty Seven


Lakhs Seventy Two
Thousand Seven Hundred
and Thirteen

Page - 93
Amount (in
Remarks
words)

Four Crores Seventy One


Lakhs Eighty Nine Thousand
Eight Hundred and Sixty Five

Twenty Lakhs Ninty Seven


Thousand Four Hundred and
Ninty Nine

Sixty Four Lakhs Forty


Seven Thousand Eight
Hundred and Forty Nine

Fifty Eight Lakhs Twenty Six


Thousand Four Hundred and
Sixteen

Nineteen Lakhs Ninty Seven


Thousand Six Hundred and
Twenty Eight

Twenty Four Lakhs Ninty


Seven Thousand and Thirty
Five

Page - 94
Amount (in
Remarks
words)

Seven Crores Forty Lakhs


Sixty Two Thousand One
Hundred and Sixty Eight

Five Crores Sixty Five Lakhs


Fifty Two Thousand Nine
Hundred and Thirty Three

Sixty Eight Lakhs Fifty Three


Thousand Eight Hundred
and Two

Page - 95
Amount (in
Remarks
words)

Three Crores Thirty Six


Lakhs Thirty Three
Thousand Three Hundred
and Eighty Five

Twenty Five Lakhs Forty


Three Thousand and Sixty
Four

Two Lakhs Twenty One


Thousand Seven Hundred
and Seventy Seven

Forty Six Lakhs Forty Six


Thousand Two Hundred and
Twenty Two

Three Lakhs Sixty Six


Thousand Four Hundred and
Eighty One

Page - 96
Amount (in
Remarks
words)

Sixty Three Lakhs Twenty


Eight Thousand Four
Hundred and Seven

Eight Lakhs Sixty One


Thousand and Eight

Fifty Eight Thousand Six


Hundred and Fifty

Twenty Two Lakhs Eighteen


Thousand Three Hundred
and Nine

One Crore Twenty Eight


Lakhs Three Thousand Six
Hundred and Eighty Eight

Page - 97
Amount (in
Remarks
words)

Three Crores Twenty Four


Lakhs Fifteen Thousand
Three Hundred and Sixty
Two

Two Crores Five Lakhs


Twenty One Thousand
Seven Hundred and Seventy
Seven

Seven Lakhs Sixty Thousand


Seven Hundred and Sixty

Six Lakhs Twenty One


Thousand Six Hundred and
Eighty Three

Eighty Thousand Eight


Hundred and Ninty Eight

Twenty Two Lakhs Fifty Six


Thousand and Seventy Four

One Lakh Twenty Two


Thousand Two Hundred and
Six

Page - 98
Amount (in
Remarks
words)

Seven Lakhs Seventy One


Thousand Three Hundred
and Sixty Eight

Eight Lakhs Thirty Two


Thousand Eight Hundred
and Sixty One

Eight Two Thousand Seven


Hundred and Seventy Six

Twenty Eight Thousand


Three Hundred and Fifteen

One Lakh One Thousand


Nine Hundred and Thirty
Seven

One Lakh Eighty Two


Thousand One Hundred and
Seventy Two

One Lakh Fifty Two


Thousand Five Hundred and
Seventy Eight

Page - 99
Amount (in
Remarks
words)

Seven Thousand Eight


Hundred and Sixty One

Forty Four Thousand Six


Hundred and Seventy Seven

Seven Hundred and Sixty


Eight

Sixteen Thousand Seven


Hundred and Twenty

Eighty Four Thousand Two


Hundred and Fifty

Three Lakhs Sixty Seven


Thousand Six Hundred and
Five

One Lakh Eighty Nine


Thousand Nine Hundred and
Thirty

Page - 100
Amount (in
Remarks
words)

One Thousand Eight


Hundred and Twenty Two

One Lakh Sixty Two


Thousand Three Hundred
and Eight

Eleven Lakhs Two Thousand


Two Hundred and Fifty

Fourteen Lakhs Sixty Four


Thousand Seven Hundred
and Five

Seventy Nine Thousand and


Forty Eight

Page - 101
Amount (in
Remarks
words)

Fifty One Thousand One


Hundred and Twenty Three

Twenty Eight Thousand Four


Hundred and Ninty Five

Two Lakhs Fifty Thousand


and Five Hundred

Page - 102
Amount (in
Remarks
words)

Seven Lakhs and Fifty


Thousand

Thirty Two Thousand Nine


Hundred and Sixteen

Eighty Nine Thousand Three


Hundred and Forty Four

Eighty Eight Thousand and


Eight Hundred

Nine Hundred

One Lakh Eighty Thousand


Five Hundred and Seventy
Four

Page - 103
Amount (in
Remarks
words)

Forty Eight Thousand Four


Hundred and Seventy Seven

Three Lakhs Thirty Seven


Thousand and Ninty

Seventy Two Lakhs Seventy


Five Thousand and Six
Hundred

Twenty Four Thousand Five


Hundred and Forty Four

Thirty Eight Lakhs

Three Lakhs and Eighty


Seven Thousand

Thirteen Lakhs Seventy


Eight Thousand Five
Hundred and Sixty

Page - 104
Amount (in
Remarks
words)

Five Lakhs Eighty Thousand


One Hundred and Thirty
Four

Two Lakhs Forty Seven


Thousand Seven Hundred
and Forty One

Eighteen Thousand Four


Hundred and Eight

Two Lakhs One Thousand


Two Hundred and Ninty Two

Forty Two Thousand Seven


Hundred and Fifty

Page - 105
Amount (in
Remarks
words)

Nine Lakhs and Forty Five


Thousand

One Lakh and Forty One


Thousand

One Lakh Fifty Five


Thousand Four Hundred and
Forty

Page - 106
Amount (in
Remarks
words)

Sixty Eight Thousand and


Seventy Two

Eight Thousand Six Hundred


and Forty

Thirty Eight Thousand Three


Hundred and Three

One Crore Twenty Lakhs


and Ninty Six Thousand

Seventy Six Thousand Nine


Hundred and Seventy Three

Eighty One Thousand Nine


Hundred and Twenty Three

Eighty Four Thousand One


Hundred and Fifty

Nine Lakhs Ninty Four


Thousand and Four Hundred

Six Thousand Two Hundred


and Fourteen

Page - 107
Amount (in
Remarks
words)

Nine Thousand Five


Hundred and Forty

Twelve Thousand Two


Hundred and Ninty Six

Nine Hundred and Fifty Two

Three Thousand Two


Hundred and Sixty Nine

Seventeen Thousand Three


Hundred and Thirteen

One Lakh Ninty Two


Thousand Two Hundred and
Eight

Page - 108
Amount (in
Remarks
words)

Six Thousand Three


Hundred and Fifty Five

Fifty Eight Thousand One


Hundred and Thirty

Eleven Thousand Seven


Hundred and Ninty Seven

Twenty Six Thousand Three


Hundred and Ninty Four

Thirty Seven Thousand and


Sixty Six

Five Lakhs Ninty Three


Thousand Eight Hundred
and Sixty One

Eight Lakhs Sixty Five


Thousand Eight Hundred
and Forty Seven

Page - 109
Amount (in
Remarks
words)

Twenty One Thousand


Seven Hundred and Two

Eight Thousand Three


Hundred and Thirty Eight

One Lakh Seven Thousand


Five Hundred and Forty

Seven Thousand Five


Hundred and Sixty Three

Twelve Thousand Nine


Hundred and Ninty Five

One Lakh Two Thousand


Three Hundred and Fifty Six

One Thousand and Twenty


Four
Ten Thousand Seven
Hundred and One

Thirty Eight Thousand Three


Hundred and Eighty One

Page - 110
Amount (in
Remarks
words)

Thirty One Thousand One


Hundred and Seventy Two

Thousand Three Hundred and Thirty Eight Only/-

Executive Engineer

..

..