a Footing
F1: 3.07 X 2.840 X .350 ( 2 No's)
CUM 6.10 5091.00 31055.10
F2: 4.2 X 1.8 X .350 (2 No's)
CUM 5.29 5091.00 26941.57
b Column
C1 (2.1 X .23 X .23) 8 No's CUM 0.89 5091.00 4520.81
C2 (2.1 X .23 X .6) 4 No's CUM 1.16 5091.00 5900.47
C Plinth Beam
PB1 (1.41 X .23 X .3) 4 No's CUM 0.78 5091.00 3950.62
PB2 (1.18 X .23 X .3) 4 No's CUM 0.65 5091.00 3303.04
PB3 (1.8 X .23 X .3) 2 No's CUM 0.50 5091.00 2525.14
PB4 (3.37 X .23 X .3) 2 No's CUM 0.93 5091.00 4734.63
(MP PWD, SOR, Reinforcement for R.C.C. work
1.08.2014) I.NO.
5.16.4 PAGE N0.68 including straightening, cutting,
bending, placing in position and
binding including cost of binding wire
up to floor two level including all
4 wastage etc complete. Hot Rolled
Deformed Bars.
a FOOTING
F1 KG 166.80 62.90 10491.72
F2 KG 285.57 62.90 17962.48
b COLUMN
C1 (2.1 X .23 X .23) 8 No's KG 145.56 62.90 9155.72
C2 (2.1 X .23 X .6) 4 No's KG 103.90 62.90 6535.31
C Plinth Beam
PB1 (1.41 X .23 X .3) 4 No's KG 20.00 62.90 1258.00
PB2 (1.18 X .23 X .3) 4 No's KG 16.77 62.90 1054.52
PB3 (1.8 X .23 X .3) 2 No's KG 19.10 62.90 1201.39
PB4 (3.37 X .23 X .3) 2 No's KG 35.91 62.90 2258.74
(MP PWD, SOR, Centering and shuttering including
1.08.2014) I.NO.
5.9.1 PAGE N0.66 strutting, propping etc. and removal
of form for: Foundations, footings,
5 bases of columns, etc. for concrete
upto plinth.
a Footing
F1 = 3.070 X 3.040 X .350 (2 NO'S)
SQM 8.554 174.00 1488.40
F2 = 4.2 X 1.8 X .350 (2 NO)
SQM 8.400 174.00 1461.60
b COLUMN
C1 (2.1 X .23 X .23) 8 No's SQM 9.568 174.00 1664.83
C2 (2.1 X .23 X .6) 4 No's SQM 8.632 174.00 1501.97
C Plinth Beam
PB1 (1.41 X .23 X .3) 4 No's SQM 5.978 174.00 1040.17
PB2 (1.18 X .23 X .3) 4 No's SQM 5.000 174.00 870.00
PB3 (1.8 X .23 X .3) 2 No's SQM 3.816 174.00 663.98
PB4 (3.37 X .23 X .3) 2 No's SQM 7.144 174.00 1243.06
(MP PWD, SOR, Filling available excavated earth
1.08.2014)
I.NO.2.25 PAGE (excluding hard rock/Ordinary rock) in
N0.26 Trenches, plinth, sides of foundat
ions etc. in layers not 10
exceeding 20cm in depth,
consolidating each deposited layer by
ramming and watering, lead up to 50 m
6 and lift upto 1.5 m.
M 15 - Grade concrete
a COLUMN
C1 (5.85 X .23 X .23) 8 No's CUM 2.47 5202 12848.94
C2 (5.85 X .23 X .6) 4 No's CUM 3.22 5202 16750.44
b SLAB
S1 (3.23 X 3 X .15) 2 No's CUM 2.907 5202 15122.21
S2 (3.9 X 5.1 X .15) 1 No's CUM 2.983 5202 15517.57
S3 (2.33 X 2.1 X .15) 2 No's CUM 1.467 5202 7631.33
S4 (3 X 4.2 X .15) 1 No's CUM 1.89 5202 9831.78
C BEAM
B1 (1.41 X .23 X .3) 4 No's CUM 0.62 5202 3230.44
B2 (1.18 X .23 X .3) 4 No's CUM 0.87 5202 4515.34
B3 (1.8 X .23 X .3) 2 No's CUM 0.50 5202 2580.19
B4 (3.37 X .23 X .3) 2 No's CUM 0.93 5202 4837.86
(MP PWD, SOR, Centering and shuttering including
1.08.2014)
I.NO.5.9.3 PAGE strutting, propping etc. and removal of
N0.66 form for : Suspended floors, roofs,
4 landings, balconies and access
platform.
a COLUMN
C1 (5.85 X .23 X .23) 8 No's SQM 43.056 264.00 11366.78
C2 (5.85 X .23 X .6) 4 No's SQM 38.840 264.00 10253.76
b SLAB
S1 (3.23 X 3) 2 No's SQM 19.380 264.00 5116.32
S2 (3.9 X 5.1 ) 1 No's SQM 19.81 264.00 5229.84
S3 (2.33 X 2.1) 2 No's SQM 9.79 264.00 2583.50
S4 (3 X 4.2) 1 No's SQM 12.60 264.00 3326.40
C BEAM
B1 (1.41 X .23 X .3) 4 No's SQM 5.970 264.00 1576.08
B2 (1.18 X .23 X .3) 4 No's SQM 5.000 264.00 1320.00
B3 (1.8 X .23 X .3) 2 No's SQM 3.816 264.00 1007.42
B4 (3.37 X .23 X .3) 2 No's SQM 7.140 264.00 1884.96
d LINTEL
L1 (1.8 X .23 ) 3 No's SQM 1.242 264.00 327.89
L2 (1.05 X .23 ) 2 No's SQM 0.483 264.00 127.51
L3 (1 X .23 ) 2 No's SQM 0.460 264.00 121.44
L4 (.9 X .23 ) 2 No's SQM 0.414 264.00 109.30
(MP PWD, SOR, Reinforcement for R.C.C. work
1.08.2014) I.NO.
5.16.4 PAGE N0.68 including straightening, cutting,
bending, placing in position and
binding including cost of binding wire
up to floor two level including all
wastage etc complete. Hot Rolled
5
Deformed Bars.
b COLUMN
C1 (5.85 X .23 X .23) 8 No's KG 289.44 62.90 18205.78
C2 ( 5.85 X .23 X .6) 4 No's KG 181.00 62.90 11384.90
C Beam
B1 (1.41 X .23 X .3) 4 No's KG 20.00 62.90 1258.00
B2 (1.18 X .23 X .3) 4 No's KG 16.77 62.90 1054.52
B3 (1.8 X .23 X .3) 2 No's KG 12.78 62.90 803.86
B4 (3.37 X .23 X .3) 2 No's KG 23.94 62.90 1505.83
D SLAB
S1 (3.23 X 3) 2 No's KG 155.70 62.90 9793.53
S2 (3.9 X 5.1 ) 1 No's KG 163.20 62.90 10265.28
S3 (2.33 X 2.1) 2 No's KG 79.38 62.90 4993.00
S4 (3 X 4.2) 1 No's KG 88.84 62.90 5588.04
E LINTEL
L1 (1.8 X .23 ) 3 No's KG 9.99 62.90 628.37
L2 (1.05 X .23 ) 2 No's KG 3.88 62.90 244.05
L3 (1 X .23 ) 2 No's KG 3.70 62.90 232.73
L4 (.9 X .23 ) 2 No's KG 3.33 62.90 209.46
(MP PWD, SOR, Brick work with well brunt chimney
1.08.2014) I.NO.
6.4.2, PAGE N0.85 bricks in bulls patent trench kiln,
crushing strength not less than 25 kg/
sqcm and water absorption not more
than 20% in superstructure above
plinth level and upto two floor level i/c
6
curing complete
cement
Mortar 1:6 (1 cement: 6 sand)
Ceiling
a (1.41 X 1.18) 2 No's SQM 65.83 34.00 2238.22
b (2.54 X 3.74) 1 No's SQM 9.49 34.00 322.66
Wall (Internal)
a (7.94 X 2.6) - (2.98 )2 No's SQM 35.32 34.00 1200.88
b (10.34 X 2.6) - (8.64) 1 No's SQM 18.24 34.00 620.30
(MP PWD, SOR, Providing and laying vitrified floor tiles
1.08.2014)
I.NO.11.53.2 PAGE in different sizes with water
N0.205 absorption's less than 0.08% and
conforming to IS : 15622 of approved
make in all colours and shades, laid on
20mm thick cement mortar 1:4 (1
cement : 4 sand) including grouting the
11 joints with white cement and matching SQM 15.62 894.00 13964.28
pigments etc., complete. Size of Tile
600 x 600 x 9-10 mm
(MP PWD, SOR, Providing and fixing factory made ISI
1.08.2014)
I.NO.10.10.1, PAGE marked steel door, windows,
N0.179 ventilators side/ top/ centre hung with
beading and all members such as
F7D, F4B, K11 B and K12 B etc.
complete of standard rolled steel
sections, joints mitred and flash butt
welded and sash bars tenoned and
riveted, including providing and fixing
of hinges, pivots including priming coat
of approved steel primer, but excluding
the cost of other fittings, complete all
as per approved design (sectional
weight of only steel members shall be
measured for payment. Fixing
12 with 15 X 3 mm lugs 10 cm long
embedded in cement concrete block
15 x 10 x 10 cm of cement concrete
1:3:6 (1 cement: 3 sand: 6 graded
stone aggregate 20 nominal size)
Area of
slab more than 50 Sq m
(As per market rate) All allied and miscellenous work for
completion of entrance gate work as
21 per engineer-in-charge
Job 10000.00
Sub - Total Amount 2606603.62
Total in lakhs 26.07
Chapter 1 Site Development
Summary Of Cost
A.1 Site development (land levelling/filling) and Boundary wall
Qty. Amount IN
S.No. Schedule Item UNITS
PHYSICAL LACS(Rs)
A.1.1 Site Development 15.71 Hect. 238.04
A.1.2 Entrance Gate 1.00 Nos 26.03
Total 264.07
Chapter 1 Site Development
(PWD, SOR,
R&B, Cutting of trees including cutting of trunks, Branches and
1.1 6.6.2016) removal Cutting of trees,
2.1 including cutting of trunks, branches and removal of stumps,
roots, stacking of serviceable material with all lifts and up to a
lead of 1000 mtrs and earth filling in the depression/pit.
(i) Girth from 300 mm to 600 mm nos 25.00 214 5350.00
1.3 Plot Filling
a Footing
F1: 3.07 X 2.840 X .350 ( 2 No's) CUM 6.10 5091.00 31055.10
F2: 4.2 X 1.8 X .350 (2 No's) CUM 5.29 5091.00 26941.57
b Column
C1 (2.1 X .23 X .23) 8 No's CUM 0.89 5091.00 4520.81
C2 (2.1 X .23 X .6) 4 No's CUM 1.16 5091.00 5900.47
C Plinth Beam
PB1 (1.41 X .23 X .3) 4 No's CUM 0.78 5091.00 3950.62
PB2 (1.18 X .23 X .3) 4 No's CUM 0.65 5091.00 3303.04
PB3 (1.8 X .23 X .3) 2 No's CUM 0.50 5091.00 2525.14
PB4 (3.37 X .23 X .3) 2 No's CUM 0.93 5091.00 4734.63
(MP PWD, Reinforcement for R.C.C. work including straightening, cutting, bending, placing in position
SOR,
1.08.2014) and binding including cost of binding wire up to floor two level including all wastage etc
4 I.NO. 5.16.4 complete. Hot Rolled Deformed Bars.
PAGE N0.68
a FOOTING
F1 KG 166.80 62.90 10491.72
F2 KG 285.57 62.90 17962.48
b COLUMN
C1 (2.1 X .23 X .23) 8 No's KG 145.56 62.90 9155.72
C2 (2.1 X .23 X .6) 4 No's KG 103.90 62.90 6535.31
C Plinth Beam
PB1 (1.41 X .23 X .3) 4 No's KG 20.00 62.90 1258.00
PB2 (1.18 X .23 X .3) 4 No's KG 16.77 62.90 1054.52
PB3 (1.8 X .23 X .3) 2 No's KG 19.10 62.90 1201.39
PB4 (3.37 X .23 X .3) 2 No's KG 35.91 62.90 2258.74
(MP PWD, Centering and shuttering including strutting, propping etc. and removal of form for: Foundations,
SOR,
1.08.2014) footings, bases of columns, etc. for concrete upto plinth.
5 I.NO. 5.9.1
PAGE N0.66
a Footing
F1 = 3.070 X 3.040 X .350 (2 NO'S) SQM 8.554 174.00 1488.40
F2 = 4.2 X 1.8 X .350 (2 NO) SQM 8.400 174.00 1461.60
b COLUMN
C1 (2.1 X .23 X .23) 8 No's SQM 9.568 174.00 1664.83
C2 (2.1 X .23 X .6) 4 No's SQM 8.632 174.00 1501.97
C Plinth Beam
PB1 (1.41 X .23 X .3) 4 No's SQM 5.978 174.00 1040.17
PB2 (1.18 X .23 X .3) 4 No's SQM 5.000 174.00 870.00
PB3 (1.8 X .23 X .3) 2 No's SQM 3.816 174.00 663.98
PB4 (3.37 X .23 X .3) 2 No's SQM 7.144 174.00 1243.06
(MP PWD, Filling available excavated earth (excluding hard rock/Ordinary rock) in Trenches, plinth, sides of
SOR,
1.08.2014) foundat ions etc. in layers not 10 exceeding 20cm in depth, consolidating each deposited
6 I.NO.2.25 layer by ramming and watering, lead up to 50 m and lift upto 1.5 m.
PAGE N0.26
a COLUMN
C1 (5.85 X .23 X .23) 8 No's CUM 2.47 5202 12848.94
C2 (5.85 X .23 X .6) 4 No's CUM 3.22 5202 16750.44
b SLAB
S1 (3.23 X 3 X .15) 2 No's CUM 2.907 5202 15122.21
S2 (3.9 X 5.1 X .15) 1 No's CUM 2.983 5202 15517.57
S3 (2.33 X 2.1 X .15) 2 No's CUM 1.467 5202 7631.33
S4 (3 X 4.2 X .15) 1 No's CUM 1.89 5202 9831.78
C BEAM
B1 (1.41 X .23 X .3) 4 No's CUM 0.62 5202 3230.44
B2 (1.18 X .23 X .3) 4 No's CUM 0.87 5202 4515.34
B3 (1.8 X .23 X .3) 2 No's CUM 0.50 5202 2580.19
B4 (3.37 X .23 X .3) 2 No's CUM 0.93 5202 4837.86
(MP PWD, Centering and shuttering including strutting, propping etc. and removal of form for : Suspended
SOR,
1.08.2014) floors, roofs, landings, balconies and access platform.
4 I.NO.5.9.3
PAGE N0.66
a COLUMN
C1 (5.85 X .23 X .23) 8 No's SQM 43.056 264.00 11366.78
C2 (5.85 X .23 X .6) 4 No's SQM 38.840 264.00 10253.76
b SLAB
S1 (3.23 X 3) 2 No's SQM 19.380 264.00 5116.32
S2 (3.9 X 5.1 ) 1 No's SQM 19.81 264.00 5229.84
S3 (2.33 X 2.1) 2 No's SQM 9.79 264.00 2583.50
S4 (3 X 4.2) 1 No's SQM 12.60 264.00 3326.40
C BEAM
B1 (1.41 X .23 X .3) 4 No's SQM 5.970 264.00 1576.08
B2 (1.18 X .23 X .3) 4 No's SQM 5.000 264.00 1320.00
B3 (1.8 X .23 X .3) 2 No's SQM 3.816 264.00 1007.42
B4 (3.37 X .23 X .3) 2 No's SQM 7.140 264.00 1884.96
d LINTEL
L1 (1.8 X .23 ) 3 No's SQM 1.242 264.00 327.89
L2 (1.05 X .23 ) 2 No's SQM 0.483 264.00 127.51
L3 (1 X .23 ) 2 No's SQM 0.460 264.00 121.44
L4 (.9 X .23 ) 2 No's SQM 0.414 264.00 109.30
(MP PWD, Reinforcement for R.C.C. work including straightening, cutting, bending, placing in position
SOR,
1.08.2014) and binding including cost of binding wire up to floor two level including all wastage etc
5 I.NO. 5.16.4 complete. Hot Rolled Deformed Bars.
PAGE N0.68
b COLUMN
C1 (5.85 X .23 X .23) 8 No's KG 289.44 62.90 18205.78
C2 ( 5.85 X .23 X .6) 4 No's KG 181.00 62.90 11384.90
C Beam
B1 (1.41 X .23 X .3) 4 No's KG 20.00 62.90 1258.00
B2 (1.18 X .23 X .3) 4 No's KG 16.77 62.90 1054.52
B3 (1.8 X .23 X .3) 2 No's KG 12.78 62.90 803.86
B4 (3.37 X .23 X .3) 2 No's KG 23.94 62.90 1505.83
D SLAB
S1 (3.23 X 3) 2 No's KG 155.70 62.90 9793.53
S2 (3.9 X 5.1 ) 1 No's KG 163.20 62.90 10265.28
S3 (2.33 X 2.1) 2 No's KG 79.38 62.90 4993.00
S4 (3 X 4.2) 1 No's KG 88.84 62.90 5588.04
E LINTEL
L1 (1.8 X .23 ) 3 No's KG 9.99 62.90 628.37
L2 (1.05 X .23 ) 2 No's KG 3.88 62.90 244.05
L3 (1 X .23 ) 2 No's KG 3.70 62.90 232.73
L4 (.9 X .23 ) 2 No's KG 3.33 62.90 209.46
(MP PWD, Brick work with well brunt chimney bricks in bulls patent trench kiln, crushing strength not less than
SOR,
1.08.2014) 25 kg/ sqcm and water absorption not more than 20% in superstructure above plinth level and
6 I.NO. 6.4.2, upto two floor level i/c curing complete
PAGE N0.85 cement Mortar 1:6 (1 cement: 6 sand)
a (7.94 X5.85 X .23) - (2.985 X 2.1 X .23) 2 No's CUM 20.00 5255.00 105078.98
b 10.34 X 8.25 X .23) - (8.64 X 2.1 X .23) 1 No's CUM 17.63 5255.00 92645.65
7 (MP PWD, 12mm cement plaster of mix : 1:4 (1 cement :4 sand)
SOR,
1.08.2014) Ceiling
a I.NO.13.1.1 (1.41 X 1.18) 2 No's
PAGE N0.244 SQM 3.33 123.00 409.22
b (2.54 X 3.74) 1 No's SQM 9.49 123.00 1167.27
Wall (Internal)
a (7.94 X 2.6) - (2.98 )2 No's SQM 35.32 123.00 4344.36
b (10.34 X 2.6) - (8.64) 1 No's SQM 18.24 123.00 2244.01
(MP PWD, 20 mm cement plaster of mix (1:4) (1
SOR,
1.08.2014) cement: 4 sand)
8 I.NO.13.3.1
PAGE N0.244
Chapter 1 Site Development
Ceiling
a (1.41 X 1.18) 2 No's SQM 65.83 34.00 2238.22
b (2.54 X 3.74) 1 No's SQM 9.49 34.00 322.66
Wall (Internal)
a (7.94 X 2.6) - (2.98 )2 No's SQM 35.32 34.00 1200.88
b (10.34 X 2.6) - (8.64) 1 No's SQM 18.24 34.00 620.30
(MP PWD, Providing and laying vitrified floor tiles in different sizes with water absorption's less than 0.08%
SOR,
1.08.2014) and conforming to IS : 15622 of approved make in all colours and shades, laid on 20mm thick
I.NO.11.53.2 cement mortar 1:4 (1 cement : 4 sand) including grouting the joints with white cement and
11 PAGE N0.205 matching pigments etc., complete. Size of Tile 600 x 600 x 9-10 mm SQM 15.62 894.00 13964.28
(MP PWD, Providing and fixing factory made ISI marked steel door, windows, ventilators side/ top/ centre
SOR,
1.08.2014) hung with beading and all members such as F7D, F4B, K11 B and K12 B etc. complete of standard
I.NO.10.10.1, rolled steel sections, joints mitred and flash butt welded and sash bars tenoned and riveted,
PAGE N0.179 including providing and fixing of hinges, pivots including priming coat of approved steel primer, but
excluding the cost of other fittings, complete all as per approved design (sectional weight of only
steel members shall be measured for payment. Fixing with 15 X 3 mm lugs 10 cm long
12 embedded in cement concrete block 15 x 10 x 10 cm of cement concrete 1:3:6 (1 cement: 3 sand:
6 graded stone aggregate 20 nominal size)
(MP PWD, Designing, Fabricating, testing, installing and fixing in position curtain wall with Aluminium
SOR,
1.08.2014) Composite panel Cladding, with open grooves for linear as well as curvilinear portions of the
I.NO.8.7.1, building, for all heights and all levels etc including:
PAGE N0.114
a) Structural analysis and designand preparation of shop drawings for pressure equalisation or rain
screen principle as required, proper drainage of water to make it watertight including checking af
all the structural and functional design.
15 b) Providing, fabricating and supplying and fixing panels of aluminium composite panel cladding in sqm 400.00 3800.00 1520000.00
pan shape in metallic colours of apoved shades. The aluminium acomposite panel cladding sheet
shal be coil coated, with Kynar 500 based PVDF/ Lumiflon based fluoropolymer resin coating of
approved colour and shade on face # 1 and polymer (service) coating on face # 2 as specified
using stainless steel screws, nuts, bolys, washers, cleats, weathersilicone sealant, backer rods etc.
Chapter 1 Site Development
(As per Providing and erecting overhead signs with a corrosion ressistant 2mm thk aluminium alloy sheet
market reflectorised with high intensity retro- reflective sheeting vide clause 801.3/ High intensity prisamtic
rate) grade sheeting as per ASTM D 4956 with vertical and lateral clearance given in clause 802.2 and
802.3 duly painted on back side with two coats of grey stove enamel paint and installed as per
clause 802.7 over a designed support system of structural steel work trestles and trusses of
sections and type as per structural designs requirement and approved plans ,including painting
with one coat of epoxy primer & two coats of epoxy finish paint.The nut bolts of boards with angle
iron post/ supporting structure after fixing at site has to be electrically welded. Retroreflective
sheeting should be with seven years written warrenty from the manufracture & authorised
16 distibuter/ convertor for satisfactory field performance durability & stipulated retro- reflective SQM 4.50 5670.00 25515.00
sheeting. this certificate in orginal should be submitted to the Engineer in charge bt the contractor/
supplier.
(MP PWD, a) Providing and laying gang saw cut 18 mm thick, mirror polished machine cut granite stone of
SOR,
1.08.2014) required size and shape of approved shade, colour and texture in flooring laid over 20 mm thick
I.NO.11.29.2.2, base of cement mortar 1:4 (1 cement: 4 sand) including grouting the joints with white cement
17
PAGE N0.202 mixed with matching pigment, epoxy touch ups etc. complete as per direction of Engineer in SQM 40.00 3695.00 147800.00
charge. All shades/ colour other than black.
Area of slab more than 50 Sq m
(MP PWD, Providing edge moulding to 18 mm thick marble stone counters, Vanities, window sills etc.
SOR,
1.08.2014) including machine polishing to edge to give high gloss etc. complete as per design approved by
18 I.NO.11.36.2, the engineer in charge. Granite Work. RMT 40.00 269 10760.00
PAGE N0.203
(MP PWD, Finishing with Epoxy paint (two or more coats) at all locations prepared and applied as per
SOR,
1.08.2014) manufacturer's specifications including appropriate priming coat, preparation of surface, etc.
20 I.NO.13.60.1, complete. On steel work SQM 126.00 109 13734.00
PAGE N0.251
(As per market All allied and miscellenous work for completion of entrance gate work as per engineer-in-charge
21 rate)
Job 10000.00
Sub - Total Amount 2603448.01
Total in lakhs 26.03
Chapter 1 Site Development
0.00 72 0
M 20 CONCRETE GRADE
COLUMN 0 1.2 0.23 0.3 0.00 cum
top BEAM 1 0 0.075 0.23 0.00 cum
SUB TOTAL 0.00 cum 5202 0
MP.PWD,
Centering and shuttering including strutting,
BW-
propping etc and removal of form work for
1.8.2014
7 , SOR,
FOUNDATION , Footings, Bases of columns
4.3.1
FOR FOUNDATION OF COLUMNS
0 3.6 0.3 0.00 sqm 169 0
( 4 x 0.9)=3.6m
for column (230+300)x2/1000=1.06m 0 1.06 1.2 0.00 sqm 169 0
Centering and shuttering including strutting,
MP.PWD,
propping etc and removal of form work for
BW-
7 1.8.2014
Retaining walls, return walls, walls (any thickness)
, SOR,
including attached pilasters, buttresses, plinth and
4.3.2
string courses fillets etc.
PLINTH BEAM 1 0 0.9 0.00 sqm
TOP BEAM 1 0 0.15 0.00 sqm
SUB TOTAL 0.00 sqm 267 0
MP.PWD,
Centering and shuttering including strutting,
BW-
propping etc and removal of form work for
8 1.8.2014
Columns,
, SOR,
piers, abutments, pillars, posts and struts.
4.3.3
COLUMN 0 1.06 1.2 0.00 sqm 356 0
MP.PWD, Brick work with Fly ash Lime Bricks (Falg Bricks)
BW- conforming to IS: 12894-2002, in super structure
9 1.8.2014 above plinth level upto floor 2 level, having 50 1 0 0.23 1.2 0.00 cum 5230 0
, SOR, kg/cm2 average compressive strength, in cement
6.7.3.1 Mortar 1:4
MP.PWD, Structural steel work riveted, bolted or welded in
BW- built up - sections, trusses and framed work,
10 1.8.2014 including cutting,hoisting, fixing in position and 310.00 KG 68.7 21297
, SOR, applying a priming coat of approved steel primer
10.2 all complete.
FOR BARBED WIRE FENCING ( 45 X 45 X5, 1.5M =
0 5.1 kg/nos 0.00 KG 68.7 0
5.1 KG , @1nos EVERY Collumn)
MP.PWD,
BW- 12 mm cement plaster of mix.
11 1.8.2014 1 0 1.805 0.00 sqm 123 0
, SOR, (1:4) (1 cement :4 sand)
13.1.1
Chapter 1 Site Development
(MP
PWD,
SOR, Painting with synthetic enamel paint of approved brand
15 1.08.201 and manufacture to give an even shade: 6 2 12.00 SQM 53 636
4) Two or more coats on new work
P/252,
I/13.68
TOTAL 21933