Demonstrations Required for Civil

1. Operation Theatre
a. Modular Walls
b. Ceilings
c. Doors/Ironmongeries
d. Sanitary Fixtures
2. Ceilings
a. ACT-01 - QRI
b. ACT-02 - QRI
c. ACT-03 - QRI
d. ACT-04 - QRI
e. ACT-23/ 27/ 28 WH 4F
f. Wooden ceiling tiles
3. Flooring
a. Epoxy terrazzo BMC Qatar
b. Kitchen flooring (U-crete) BMC Qatar
c. Raised flooring HDEC at QRI
d. Polyurethane flooring (ie. loading dock) BMC Qatar
e. Others (Linoleum IMAR)
4. Wall panels
a. Resin panels -
b. TV panels
c. Decorative panels
d. Back painted glass (ie. in Conference rooms)
e. Bed-head unit panels
f. Lab casework panels
g. Acoustic wall panels (ie. Conference rooms)
h. Others
5. Stretched fabric ceilings HMC to witness removal of barisol
6. Grease/oil interceptors by mech team
7. Sanitary items (fixtures, flush valve) by mech team
8. Manholes, cleanouts AH GF North
9. Foldable / Operable Partition (ie. installation, removal)
10.Solid surface material - corian (ie. access hatch, columns) PMR GF
Lobby
11.Internal tensile structures (ie. faade) HMC to inform tensile
measurement result & maintenance recommendation.
12.Blind curtains (ie. supports) HMC to see access at WH 3F
13.Door/Ironmongeries (ie. lockset/gasket replacement)
a. Obermatic doors
b. Panic doors
14.External tensile structures (ie. parking area, area between QRI & ACC)
15.Building Maintenance Unit Specialize contractor only, WH GF West
16.Faade glass (punch window/spider glass/UCW) HMC to witness
actual removal
17.AH Roof Access Opening
Comments on Civil/Arch Demonstration

1. Glass/Faade
a. kindly provide details/specifications of all sealants used for
structural sealant for the glass (Dow corning 995 black color), for
ACP weather sealant (Dow corning 791 Grey color)
b. HMC to witness actual replacement of the damaged glass on site
(2 types) Noted, we will inform you once we replace the firemans
access glass maybe after 2 weeks from now.

2. Tensile Structure we are waiting for tensile measurement result


from our specialist including their maintenance recommendation.
We will update you accordingly.
a. HMC to be advised on the result of the tensile measurement
done by contractor b. Hyundai to provide maintenance
recommendation and maintenance history of the system

3. Door/Ironmongeries
a. kindly arrange demo on obermatic doors, exit doors (panic bars)
and sliding doors we will coordinate with your Engineers to include
this items in upcoming demonstration.

4. Motorized Blinds
a. kindly arrange demo on the access of motors on 3rd floor its
available at anytime to view & inspect at WH 3F

5. Stretched Fabric
a. HMC to witness actual removal and fixing of stretched fabric
ceiling due to replacement of busted light we will inform you once
our new lighting materials will arrive on site. we are waiting
expected delivery from supplier up to now.