CSCEC/HOISTING/01
REQUESTED BY
DATE TIME
REQUESTED BY SIGNATURE
DESIGNATION
COMPANY NAME/
COMPANY CHOP
HOISTING/MACHINERY
CONTACT NO
NO
APPROVED BY CSCEM
AUTHORITY CONSTRUCTION MANAGER EQUIPMENT MANAGER
NAME
DATE&TIME
APPROVED/NOT
APPROVED
SIGNATURE/COMPANY
CHOP
1. All subcontractors is required to submit their requisition form 48 hours in advance prior to usage of any
machineries or hoisting facilities.
2. CSCEC reserved the right to reduce or re-schedule of any machineries or hoisting facilities of any
machineries or hoisting facilities to accommodate the site requirement
3. CSCEC reserved the right to penalty or remove of any Site Personal from due to non-compliance of
safety regulation and non-compliance on site.
4. Charging of usage for any machineries or hoisting facilities is discretion of CSCEC or subject to
contractual obligation as stipulated in the contract.