SCAFFOLDINGS

Lumber Kiln Dried S4S


2x2 board ft @ 52.00 per bd ft
2x3 board ft @ 55.00 per bd ft

I. COLUMNS
GRADE LINE - ROOF LEVEL
Height of Column= 3.2 m
Number of Columns= 13
Total Length = 41.6 m
Vertical Support 2" x 3" = 291.2 bd ft
Cost for Vertical Support = 16,016.00
Horizontal Support 2" x 2" = 873.6 bd ft
Cost for Horizontal Support = 45,427.20
Diagonal Braces 2" x 2" = 486.72 bd ft
Cost for Diagonal Braces = 25,309.44
Total Cost For 3 LEVELS = 260,257.92

II. TIE BEAMS


GRADE LINE
Total Length of Beams = 271.125 m
Vertical Support 2" x 3" = 1084.5 bd ft
Cost for Vertical Support = 59,647.50
Horizontal Support 2" x 2" = 1274.2875 bd ft
Cost for Horizontal Support = 66,262.95
Total Cost of Scaffoldings = 125,910.45

III. BEAMS
2ND LEVEL - 3RD LEVEL
Total Length of Beams = 271.125 m
Vertical Support 2" x 3" = 1626.75 bd ft
Cost for Vertical Support = 89,471.25
Horizontal Support 2" x 2" = 1274.2875 bd ft
Cost for Horizontal Support = 66,262.95
Total Cost of For 2 Levels = 155,734.20

ROOF LEVEL
Total Length of Beams = 288.075 m
Vertical Support 2" x 3" = 1728.45 bd ft
Cost for Vertical Support = 95,064.75
Horizontal Support 2" x 2" = 1353.9525 bd ft
Cost for Horizontal Support = 70,405.53
Total Cost of For 2 Levels = 165,470.28

IV. SLABS
2ND LEVEL - 3RD LEVEL
Total Area = 412.62 mm^2
Flooring Support 2" x 3" = 3754.842 bd ft
Total Cost For 2 Levels = 206,516.31
COLUMN BEAM FLOORNG
VERTICAL HOR. BRACE VERTICAL HOR.
4.7 21 11.7 4 4.7 6.1
7 31.67 17.5 6 7 9.1