REVISED PROGRAMME OF WORK

Construction of HLB at Km 4/0-2 on road from Shankarampe- narayankhed road (via) Bujrampally in Medak district.

As per agreement As per revised milestone


Earthwork Earthwork
VCC/VRCC VCC/VRCC
Mile Earthwork VCC/VRCC for Earthwork VCC/VRCC for
for for
S.No. Stone/peri for for formation for for formation
foundatio GSb in WMM in DBM & BC foundatio WMM in DBM & BC
od Foundatio Superstru of Financial Foundatio Superstru of GSb in Cums Financial
ns & sub- Cums Cums in Cum ns & sub- Cums in Cum
ns in ctures in embankm ns in ctures in embankm
structures structures
Cums Cums ent in Cums Cums ent in
in Cums in Cums
Cums Cums

1st
Milestone
1 3 months 1088 cum 951 cums - 4172 cums- - - Rs.6550000
(0 to 90
days)
2nd Mile 0 0 0 0 0 0 0 0
stone 6
months
2 - - 659 cums - 524 cums 335 cums 108 cums Rs.8331954
(91 days
to 180
days )

3 Revised 1088 cums 410 cums - 4172 cums' - - - Rs.3814120


1stM/s 0
to 60 days
Revised
4 2stM/s 60 - 541 cums 300 cums - 524 cums - - Rs.6625561
to 120
days

Revised
5 3rd M/s - - 359 cums - - 335 cums 108 cums Rs.6377986
120 to
180 days
5 1088 951 659 4172 524 335 108 1088 959 659 4172 524 335 108
5 Total ECV = Rs.16817667
5 Total TCV= Rs.14881954 Total TCV Deduting T.P( -) 11.51 % Less of Rs.=Rs. 14881954.00

Contractor Assistant Executive Engineer (R&B) Dy. Executive Engineer (R&B), Executive Engineer (R&B),
Section shankarampet A Subdivision Medak Division Medak