ACTUAL TIMELINE FOR DISCONECTION-CONECTING FLOATING HOSE FPSO

DATE TIME

06.00hrs 12.00hrs
2/2/2017
12.00hrs 21.00hrs

06.00hrs 12.00hrs
3/2/2017
12.30hrs - 18.30hrs

06.00hrs 12.00hrs
4/2/2017
13.00hrs - 18.00hrs

06.00hrs 12.00hrs

5/2/2017 13.00hrs - 18.00hrs

19.00hrs - 21.00hrs

06.00hrs 14.00hrs
6/2/2017
15.00hrs - 22.00hrs
ONECTION-CONECTING FLOATING HOSE FPSO LAM SON ONSHORE TEST 2017

JOB
Disconnecting 12 section from tanker end on deck OSV. Transfer hose sections to FPSO main deck for
inspection and testing

Hydraulic test; Vacuum test floating hose.

Hydraulic test and Vacuum test, Electric test floating hose

Assembly of floating hose on OSV (12 floating hose). Completed

Disconnecting 12 hose sections from FPSO end on OSV. Transfer hose sections to FPSO main deck for
inspection and testing

Inspection for repair and testing. Hydraulic test; Vacuum test and electric test

Repair floating hose on OSV, - Hydraulic test; Vacuum test

Hydraulic test; Vacuum test for 3 section. Completed

Hydraulic test; Vacuum test for 1 section. Completed. Electric test 12 section. Completed

Reconnection of floating hose on OSV (12 sections) to FPSO end. Completed

String leak test to 15 bar. Completed.


Reconnection whole floating hose with FPSO system. Completed