UC 2016 Prague
EETC 2016 Prague
May 23, 2016
0
Contents
Contents : Accents
1
1. Project location
2
1. Project location
3
1. Project location
Slovenian and
Austrian parts of
corridors
4
1. Project location
5
1. Project location
6
2. Project data
Layout
7
2. Project data
Longitudinal section
8
2. Project data
Length: 27.1 km
In Tunnel 20.5 km (75%)
Length with service tunnels : 43.6 km
Length of tunnels with serv.tun. 37.0 km (85 %)
Clearance: GC
Axle load: 255 KN or 80 KN/m,(categ. D4)
Tracks: 60 E1, mostly slab track
Electrification : direct current 3kV
Telecommunication system: ERTMS/ETCS level 2
9
2. Project data
10
2. Project data
Tunnel cross sections
11
2. Project data
Bridges : viaduct1
12
2. Project data
Bridges : viaduct2
13
3. Alternatives
TBM option
as longest tunnels
14
3. Alternatives
HPP Plave IIDoblar II
Construction JV :
Primorje 36.7%
SCT 25,8%
SELI 14,3 %
JaEGER 14,3%
MONTI 7%
15
4. Ventilation and safety concept
Risk distribution :
16
4. Ventilation and safety concept
17
4. Ventilation and safety concept
18
5. Muck deposits
Muck deposits :
Volumes of muck calculated on thebasis of project documentation.
Checking required of :
19
5. Muck deposits
Main design project development level in 03.2016
Muck deposits :
Bekovec
Ankaranski Bonifiki,
20
5. Muck deposits
Main design project development level in 03.2016
In the sense of distribution and transport of excavated material to be stored
questionable is the volume of material estimated as :
Tunnels cross Tunnel lenght Excavated Factor of Loosed material
seciton (m2) (m) material (m3) looseness (m3)
Material type Storage location Excavated material Faktor of looseness Loosed material (m3)
(m3)
Flysch Salonit Anhovo (2 shours 2.100.000 1.5 2.730.000
by train from Divaca)
Limestone rnotie yard (for mDivaca 1.310.000 1.5 1.972.000
1 hour by lorry)
Total 3.410.000 1.5 4.672.000
21
6. Project division
22
7. Cost Breakdown
Brutto (1.400.000.000,00)
23
8. Project development
Concession type :
DBFOMT
24
8. Project development
DBFOM
25
8. Project development
Time for Concession Length (km) Investment Public Contract type
design and period (years) volume funds
no Project construction
1 CTRL Channel 1996- 90 109 GBP 5.8 mlrd. GBP 2.01 DBFM
tunnel rail link, UK 2003/2007 mlrd.
55
6 Perpignan- Figueras, 2005-2009 50 45 1.1 mlrd 540 mil+ DBFM
HS rail France/Spain 62 mil.
27
9. Conclusion
Time schedule :
07.-09.2016
10.-12.2016 Adoption of project documentation
03.2017 Start of tender phase
http://www.drugitir.si/en
28