Вы находитесь на странице: 1из 32

Sr.

No Broad Classification
1
2
3
4

6
7

9
10
11
12
13
14
15
16
17

Civil Foundation Work


Civil Foundation Work
Activities Predesscor
Civil Foundation Drawing Approval
Foundation Bolts
Civil Job Order PO
Earthing Mat Design Calculations
Earthing Mat Design Layout Approval
Earthing Mat Material Supply PO
Earthing Mat Erection Job Work PO
VCB Switch Board PO
VCB Switch Board Drawing Approval
VCB Switch Board Delivery at Site
VCB Switch Board Commissioing Job Work PO
Structure Material PO for VCB Trench
Structure Material delivery at Site
Structure Material for VCB Trench Fabrication Job Work PO
VCB Switch Board Layout Approved Drawing

HT Route Finaization from New Substation to Old Substation


Structure Designing and Layout Drawing Finalization for New Route
Structure Material PO
Structure Material Fabrication Job Work PO
Structure Material Delivery at Site
HT Cable Laying Job Work PO
HT Cable Material Supply PO
HT Cable delivery at Site
HT Termination Kit Material Supply PO
HT Termination Kit delivery at Site
C&R Panel-1&2 PO
C&R Panel-1&2 Drawing Approval
C&R Panel-1&2 Delivery at Site
C&R Panel-1&2 Commissioning Job Work PO
C&R Panel-1&2 Layout Approved Drawing

ACDB Panel-1&2 PO
ACDB Panel-1&2 Drawing Approval
ACDB Panel-1&2 Delivery at Site
ACDB Panel-1&2 Commissioning Job Work PO
ACDB Panel-1&2 Layout Apporved Drawing

Busduct-1&2 PO
Busduct-1&2 Drawing Approval
Busduct-1&2 Delivery at the Site
Busduct 1&2Commissioning Job Work PO
Busduct 1&2Laying Approved Drawing
Lighting Arrestor Strcuture Supply PO
Lighting Arrestor Structure Structure Drawing Apporval
Lighting Arrestor Structure Deliavery at Site
Lighting Arrestor Structure Erection Job Work PO
Lighting Arrestor Layout Approved Drawing
CT (R Phase,Y Phase,B Phase) Strcuture Supply PO
CT (R Phase,Y Phase,B Phase) Structure Drawing Approval
CT (R Phase,Y Phase,B Phase) Structure Deliavery at Site
CT (R Phase,Y Phase,B Phase) Structure Erection Job Work PO
CT (R Phase,Y Phase,B Phase) Layout Approved Drawing
SF6 Breaker Structure Supply PO
SF6 Breaker Structure Drawing Approval
SF6 Breaker Structure Delivery at the Site
SF6 Breaker Structure Commissioning Job Work PO
PT (R Phase,Y Phase,B Phase) Strcuture Supply PO
PT (R Phase,Y Phase,B Phase) Structure Drawing Apporval
PT (R Phase,Y Phase,B Phase) Structure Deliavery at Site
PT (R Phase,Y Phase,B Phase) Structure Erection Job Work PO
PT (R Phase,Y Phase,B Phase) Layout Approved Drawing
1250A Isolator Structure Supply PO
1250A Isolator Structure Drawing Approval
1250A Isolator Structure Delivery at the Site
1250A Isolator Structure Commissioning Job Work PO
1250A Isolator Structure Supply PO
1250A Isolator Structure Drawing Approval
1250A Isolator Structure Delivery at the Site
1250A Isolator Structure Commissioning Job Work PO
1250A Isolator Structure Supply PO
1250A Isolator Structure Drawing Approval
1250A Isolator Structure Delivery at the Site
1250A Isolator Structure Commissioning Job Work PO
1250A Isolator Structure Supply PO
1250A Isolator Structure Drawing Approval
1250A Isolator Structure Delivery at the Site
1250A Isolator Structure Commissioning Job Work PO
FG+FP Column Structure Supply PO
FG+FP Column Structure Drawing Approval
FG+FP Column Structure Delivery at the Site
FG+FP Column Structure Commissioning Job Work PO
FG+FP Column Structure Supply PO
FG+FP Column Structure Drawing Approval
FG+FP Column Structure Delivery at the Site
FG+FP Column Structure Commissioning Job Work PO
FB Beam Structure Supply PO
FB Beam Structure Drawing Approval
FB Beam Structure Delivery at the Site
FB Beam Structure Commissioning Job Work PO
FG+FP Column Structure Supply PO
FG+FP Column Structure Drawing Approval
FG+FP Column Structure Delivery at the Site
FG+FP Column Structure Commissioning Job Work PO
FF+FP Column Structure Supply PO
FF+FP Column Structure Drawing Approval
FF+FP Column Structure Delivery at the Site
FF+FP Column Structure Commissioning Job Work PO
FB Beam Structure Supply PO
FB Beam Structure Drawing Approval
FB Beam Structure Delivery at the Site
FB Beam Structure Commissioning Job Work PO
0.2 ACSR Conductor Supply PO
0.2 ACSR Conductor GTP Approval
0.2 ACSR Conductor Delivery at Site
0.2 ACSR Conductor Termination Job Work PO
Silicone Polymer Suspension Insulator Supply PO
Silicone Polymer Suspension Insulator GTP Approval
Silcione Polyme Suspension Insulator Conductor Delivery at Site
Silicone Polymer Suspension Insulator Installation PO
1250A Isolator Structure Supply PO
1250A Isolator Structure Drawing Approval
1250A Isolator Structure Delivery at the Site
1250A Isolator Structure Commissioning Job Work PO
3150A Isolator Structure Supply PO
3150A Isolator Structure Drawing Approval
3150A Isolator Structure Delivery at the Site
3150A Isolator Structure Commissioning Job Work PO
3150A Isolator Structure Supply PO
3150A Isolator Structure Drawing Approval
3150A Isolator Structure Delivery at the Site
3150A Isolator Structure Commissioning Job Work PO
Dead End Tower Foundation Drawing Approval
Finalization of Rerouting Plan of Dead End Tower
Dead End Tower Foundation Job Work PO
Dead End Tower Foundation Work Material Supply PO
Dead End Tower Foundation Work Material delivery at Site
Grid Isolation Permission Approval (2-3 Days)
Activities Deptt.
VCB Room Foundation Work Civil Deptt.
Earthing Wire Structure Foundation Work.
Transformer-1 Foundation and Rail Work (Bay-1)
Lighting Arresstor (R Phase) Foundation Work Bay-1
Lighting Arresstor (Y Phase) Foundation Work Bay-1
Lighting Arresstor (B Phase) Foundation Work Bay-1
CT (R Phase) Foundation Work Bay-1
CT (Y Phase) Foundation Work Bay-1
CT (B Phase) Foundation Work Bay-1
SF6 Breaker Foundation Work Bay-1
PT (R Phase) Foundation Work Bay-1
PT (Y Phase) Foundation Work Bay-1
PT (B Phase) Foundation Work Bay-1
1250A Isolator Foundation Work Bay-1 (Bay-1 Incomer)
Bus Post-1 Insualtor Foundation Work Bay-1
Bus Post-2 Insualtor Foundation Work Bay-1
Transformer-1 Foundation and Rail Work (Bay-1)
Transformer-2 Foundation and Rail Work (Bay-2)
Lighting Arresstor (R Phase) Foundation Work Bay-2
Lighting Arresstor (Y Phase) Foundation Work Bay-2
Lighting Arresstor (B Phase) Foundation Work Bay-2
CT (R Phase) Foundation Work Bay-2
CT (Y Phase) Foundation Work Bay-2
CT (B Phase) Foundation Work Bay-2
SF6 Breaker Foundation Work Bay-2
PT (R Phase) Foundation Work Bay-2
PT (Y Phase) Foundation Work Bay-2
PT (B Phase) Foundation Work Bay-2
1250A Isolator Foundation Work Bay-2 (Bay-2 Incomer)
Bus Post-3 Insualtor Foundation Work Bay-2
Bus Post-4 Insualtor Foundation Work Bay-2
FH+FP Column Foundation Work
FH+FP Column Foundation Work
FH+FP Column Foundation Work
FF+FP Column Foundation Work
FG+FP Column Foundation Work
FG+FP Column Foundation Work
FG+FP Column Foundation Work
PT (R Phase) Main ABT Meter Foundation Work
PT (Y Phase) Main ABT Meter Foundation Work
PT (B Phase) Main ABT Meter Foundation Work
CT (R Phase) Main ABT Meter Foundation Work
CT (Y Phase) Main ABT Meter Foundation Work
CT (B Phase) Main ABT Meter Foundation Work
PT (R Phase) Check ABT Meter Foundation Work
PT (Y Phase) Check ABT Meter Foundation Work
PT (B Phase) Check ABT Meter Foundation Work
CT (R Phase) Check ABT Meter Foundation Work
CT (Y Phase) Check ABT Meter Foundation Work
CT (B Phase) Check ABT Meter Foundation Work
Metering Room Foundation Work
FH+FP Column Foundation Work
FH+FP Column Foundation Work
1250A Isolator Foundation Work (Metering Area Incomer)
Bus Post Insulator-5 Foundation Work
3150A Pass-1 Isolator Foundation Work
ABB Pass-1 Foundation Work
FG+FP Column Foundation Work (Pass Area)
FG+FP Column Foundation Work (Pass Area)
FG+FP Column Foundation Work (Pass Area)
Wave Trap (R Phase) Foundation Work (Line-1)
Wave Trap (B Phase) Foundation Work (Line-1)
Coupling Capacitor (R Phase) Foundation Work (Line-1)
Coupling Capacitor (B Phase) Foundation Work (Line-1)
Lighting Arresstor (R Phase) Foundation Work (Line-1)
Lighting Arresstor (Y Phase) Foundation Work (Line-1)
Lighting Arresstor (B Phase) Foundation Work (Line-1)
3150A Pass-2 Isolator Foundation Work
ABB Pass-2 Foundation Work
Wave Trap (R Phase) Foundation Work (Line-2)
Wave Trap (B Phase) Foundation Work (Line-2)
Coupling Capacitor (R Phase) Foundation Work (Line-2)
Coupling Capacitor (B Phase) Foundation Work (Line-2)
Lighting Arresstor (R Phase) Foundation Work (Line-2)
Lighting Arresstor (Y Phase) Foundation Work (Line-2)
Lighting Arresstor (B Phase) Foundation Work (Line-2)
Bus Post Insulator-6 Foundation Work
Bus Post Insulator-7 Foundation Work
FH+FP Column Foundation Work
FH+FP Column Foundation Work
Bus PT Isolator 1250A Foundation Work
Bus PT (R Phase) Foundation Work
Bus PT (Y Phase) Foundation Work
Bus PT (B Phase) Foundation Work
LILO Room Foundation Work
Placing of Transformer-2 at the Foundation Work

Earthing Mat Erection


Earthing Mat Erection

VCB SwitchBoard Commissioing Work

HT Cable 6 Run 3Cx240 SQMM from Old Substation to New Substation


via Temporary Path to be Laid and Terminated.

C&R Panel-1&2 Commissioning Work

RTCC Panel-2 Commissioning Work

ACDB Panel-1&2 Commissioning Work


Transformer-2 Commissioning Work (Testing/Assembling)

Busduct-2 Commissioning Work from Transformer-2 to Incomer-2 VCB

Lighting Arresstor (R Phase) Structure Erection Bay-2


Lighting Arresstor (Y Phase) Structure Erection Bay-2
Lighting Arresstor (B Phase) Structure Erection Bay-2

CT (R Phase) Structure Erection Bay-2


CT (Y Phase) Structure Erection Bay-2
CT (B Phase) Structure Erection Bay-2

SF6 Breaker Structure Erection Bay-2

PT (R Phase) Structure Erection Bay-2


PT (Y Phase) Structure Erection Bay-2
PT (B Phase) Structure Erection Bay-2

1250A Isolator-1 Structure Erection Bay-2 (Bay-2 Incomer)

1250A Isolator-2 Structure Erection Bay-1 (Bay-1 Incomer)

1250A Isolator-3 Structure Erection Bay Incomer


(Bay Incomer-2)

1250A Isolator-4 Structure Erection Bay Incomer


(Bay Incomer-1)

FG+FP Column Erection Work

FG+FP Column Erection Work

FB Beam Erection Work

FG+FP Column Erection Work


FF+FP Column Erection Work

FB Beam Erection Work

0.2 ACSR Single Bus System Installation Work

Silicone Polymer Suspension Insulator Installation Work

1250A Isolator-5 Structure Erection Metering (Metering Incomer)

3150A Isolator-1 Structure Erection (Pass-1)

3150A Isolator-1 Structure Erection (Pass-2)

Dead End Tower Foundation Work

Isolating JSW Substation from Grid.


Disconnecting Control Wiring of LILO Panel
Disconnecting Control Wiring of ACDB Panel to be removed.
Disconnecting Control Wiring of 110VDC Battery Charger to be removed.
Disconnecting Control Wiring of 4VDC Battery Charger to be removed.
Disconnecting Control Wiring of Bus PT
Disconnecting Control Wire of Bus PT Isolator
Disconnecting Control Wire of Pass-1
Disconnecting Control Wire of Pass-2
Disconnecting Control Wiring of Transformer-1
Disconnecting Control Wiring of RTCC Panel
Disconnecting Control Wiring of C&R Panel-1
Shifting and Installation of LILO Panel
Shifting and Installation of 110VDC Battery Charger Panel
Shifting and Installation of 4VDC Battery Charger Panel
Disconnecting Control Wiring of CT R Phase
Disconnecting Control Wiring of CT Y Phase
Disconnecting Control Wiring of CT B Phase
Disconnecting Control Wiring of SF6 Breaker
Disconnecting Control Wiring of PT R Phase
Disconnecting Control Wiring of PT Y Phase
Disconnecting Control Wiring of PT B Phase
Disconnecting Control Wiring of Isolator
Disconnecting Control Wiring of Main Meter CT R Phase
Disconnecting Control Wiring of Main Meter CT Y Phase
Disconnecting Control Wiring of Main Meter CT B Phase
Disconnecting Control Wiring of Main Meter PT R Phase
Disconnecting Control Wiring of Main Meter PT Y Phase
Disconnecting Control Wiring of Main Meter PT B Phase
Disconnecting Control Wiring of Check Meter CT R Phase
Disconnecting Control Wiring of Check Meter CT Y Phase
Disconnecting Control Wiring of Check Meter CT B Phase
Disconnecting Control Wiring of Check Meter PT R Phase
Disconnecting Control Wiring of Check Meter PT Y Phase
Disconnecting Control Wiring of Check Meter PT B Phase
Disconnecting Control Wiring of Main Energy Meter (Apex)
Disconnecting Control Wiring of Check Energy Meter (Apex)
Shifting & Installation of Pass Gantry FG+FP "3 Columns" and FA Beam "2"
Shifting & Installation of Lighting Arrester Structure Only.
Shifting & Installation of Coupling Capacitor with Structure
Shifiting & Installation of Wave Trap with Structure.
Shifting & Installation of Pass Hybrid System-1
Shifting & Installation of Pass Hybrid System-2
Shifting & Installation of FH+FP Column with FB Beam
Shifting & Installation of Twin Bus Line
Shifting & Installation of Bus PT Isolator with Structure
Dismantalling of Bus PT from Structure
Shifting & Installation of Bus PT Structure
Dismantalling of Main Meter R Phase CT
Dismantalling of Main Meter Y Phase CT
Dismantalling of Main Meter B Phase CT
Dismantalling of Main Meter R Phase PT
Dismantalling of Main Meter Y Phase PT
Dismantalling of Main Meter B Phase PT
Dismantalling of Check Meter R Phase CT
Dismantalling of Check Meter Y Phase CT
Dismantalling of Check Meter B Phase CT
Dismantalling of Check Meter R Phase PT
Dismantalling of Check Meter Y Phase PT
Dismantalling of Check Meter B Phase PT
Shifting & Installation of of Main Meter R Phase CT Structure
Shifting & Installation of of Main Meter Y Phase CT Structure
Shifting & Installation of of Main Meter B Phase CT Structure
Shifitng & Instalallation of Main Meter R Phase PT Structure
Shifitng & Installation of Main Meter Y Phase PT Structure
Shifitng & Installation of Main Meter B Phase PT Structure
Shifting & Installationof of Check Meter R Phase CT Structure
Shifting & Installation of of Check Meter Y Phase CT Structure
Shifting & Installation of of Check Meter B Phase CT Structure
Shifitng & Installation of Check Meter R Phase PT Structure
Shifitng & Installation of Check Meter Y Phase PT Structure
Shifitng & Installation of Check Meter B Phase PT Structure
Shifting & Installtion of FG+FP "4" Column Structure with "2" FB Beam
Shifting & Installtion of Bus Post Insulator Strcuture All 7 Nos.
Dismantalling of R Phase PT
Dismantalling of Y Phase PT
Dismantalling of B Phase PT
Shifitng & Installation of R Phase PT Structure
Shifitng & Installation of Y Phase PT Structure
Shifitng & Installtion of B Phase PT Structure
Shifting & Installation of R Phase CT with Structure
Shifting & Installation of Y Phase CT with Structure
Shifting & Installtion of B Phase CT with Structure
Shifting & Installation of R Phase Lighting Arrester
Shifting & Installtion of Y Phase Lighting Arrester
Shifting & Installation of B Phase Lighting Arrester
Shifting & Installation of 40 MVA Transformer
Control Wiring of 110VDC Battery Charger Panel
Control Wiring of 4VDC Battery Charger Panel
Power Circuit Wiring from ACDB Panel to ABB Hybrid Pass-1
Power Circuit Wiring from ACDB Panel to ABB Hybrid Pass-2
Power Circuit Wiring from ACDB Panel to Bus PT Isolator
Control Wiring of ABB Hybrid Pass-1
Control Wiring of ABB Hybrid Pass-2
Control Wiring of Bus PT Isolator
Control Wiring of Bus PT
Power Circuit Wiring of 3150 Isolator Pass-1
Power Circuit Wiring of 3150 Isolator Pass-2
Power Circuit Wiring of 1250 Isolator Metering Incomer
Control Circuit Wiring of 3150 Isolator Pass-1
Control Circuit Wiring of 3150 Isolator Pass-2
Control Circuit Wiring of 1250 Isolator Metering Incomer
Control Circuit Wiring of PLCC Panel with W.T and C.C
Power Circuit Wiring of Main Meter R Phase CT
Power Circuit Wiring of Main Meter Y Phase CT
Power Circuit Wiring of Main Meter B Phase CT
Power Circuit Wiring of Main Meter R Phase PT
Power Circuit Wiring of Main Meter Y Phase PT
Power Circuit Wiring of Main Meter B Phase PT
Power Circuit Wiring of Check Meter R Phase CT
Power Circuit Wiring of Check Meter Y Phase CT
Power Circuit Wiring of Check Meter B Phase CT
Power Circuit Wiring of Check Meter R Phase PT
Power Circuit Wiring of Check Meter Y Phase PT
Power Circuit Wiring of Check Meter B Phase PT
Control Circuit Wiring of ABT Check Meter
Control Circuit Wiring of ABT Main Meter
Power Circuit Wring of 1250 A Isolator at Point of Supply
Power Circuit Wring of 1250 A Isolator at Bay Inomer
Power Circuit Wring of 1250 A Isolator at Bay-1
Power Circuit Wring of 1250 A Isolator at Bay-2
Control Circuit Wring of 1250 A Isolator at Point of Supply
Control Circuit Wring of 1250 A Isolator at Bay Inomer
Control Circuit Wring of 1250 A Isolator at Bay-1
Control Circuit Wring of 1250 A Isolator at Bay-2
Power Circuit Wiring of SF6 Breaker Bay-1
Power Circuit Wiring of SF6 Breaker Bay-2
Control Circuit Wiring of SF6 Breaker Bay-1
Control Circuit Wiring of SF6 Breaker Bay-2
Power Circuit Wiring of R Phase CT
Power Circuit Wiring of Y Phase CT
Power Circuit Wiring of B Phase CT
Power Circuit Wiring of R Phase PT
Power Circuit Wiring of Y Phase PT
Power Circuit Wiring of B Phase PT
Control Circuit Wiring of 40MVA Transformer
Online Offline
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes

Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes

Вам также может понравиться