Академический Документы
Профессиональный Документы
Культура Документы
by fjspsv, 2011
01. Which of the following management objectives are not provided by documented work
authorizations?
A. Activities by deliverable.
B. Activities by start date.
C. Costs according to the chart of accounts of the performing organization.
D. Stakeholder reporting relationships.
06. Which of the following risk events is most likely to interfere with attainment of the projects cost
objective?
07. Assuming a life cycle of concept, development, implementation, and final delivery, which phase
typically, has the highest degree of uncertainty?
A. Concept.
Pgina: 1
Fichero: PMP_C03_02_EN.doc
Profesor:
Francisco Javier Sanz Prez
by fjspsv, 2011
B. Development.
C. Implementation.
D. Termination.
09. Which of the following is often reviewed to help ensure that all project work has been identified?
10. Which change record type usually has the highest priority to apply Integrated Change Control
process?
A. Defect repair.
B. Corrective action.
C. Preventive action.
D. Change proposal.
A. Ensures that the projects cost and schedule targets will be met.
B. It is the same as the performance measurement baseline.
C. Enhances understanding within the project team.
D. Documents the major technical alternatives considered.
13. Which of the following is least likely to contribute to developing an effective project team
supportive of quality?
Pgina: 2
Fichero: PMP_C03_02_EN.doc
Profesor:
Francisco Javier Sanz Prez
by fjspsv, 2011
15. Which of the following scheduling practices incorporates a form of risk assessment?
A. Gantt/Bar Charts.
B. Precedence Diagramming Method.
C. Monte Carlo simulation.
D. Critical Path Method.
A. Constrained optimization.
B. Comparative approach.
C. Benefit measurement.
D. Impact analysis.
17. You have created the project charter, but could not get it approved. Your sponsor and his boss
have asked that the project begin immediately. Which of the following is the best thing to do?
18. The engineering department has uncovered a problem with the cost accounting system and has
asked the systems department to analyze what is wrong and fix the problem. You are a project
manager working with the cost accounting system on another project. Management has issued
a change request to the change control board to add the new work to your project. Your existing
project has a cost performance Index (CPI) of 1.2 and a schedule performance Index (SPI) of
1.3 so you have some room to add work without delaying your existing project or going over
budget. However, you cannot see how the new work fits within the project charter for your
existing project. After some analysis, you determine that the new work and existing work do not
overlap and can be done concurrently. They also require different skill sets. Which of the
following is the best thing to do?
A. Re creates the project objectives and develops the project scope statement.
B. Re estimate the project schedule with inputs from the engineering department.
C. Perform scope verification on the new work with the help of the stakeholders.
D. Identify specific changes to the existing work.
19. All technical work is completed on the project. Which of the following remains to be done?
A. Scope verification.
B. Risk response plan.
C. Staffing management plan.
D. Lessons learned.
20. What better describes the difference between Areas of Expertise and Application Areas?
Pgina: 3
Fichero: PMP_C03_02_EN.doc
Profesor:
Francisco Javier Sanz Prez
by fjspsv, 2011
22. Which statement is true about monitoring and control process group?
Pgina: 4
Fichero: PMP_C03_02_EN.doc
Profesor:
Francisco Javier Sanz Prez
by fjspsv, 2011
Pgina: 5
Fichero: PMP_C03_02_EN.doc