Академический Документы
Профессиональный Документы
Культура Документы
TK3
2/1/2017
Kettler-Kilgore-Knight 1
Table of Contents
Summary.2
Introduction... 3
Body
Science.....5
Design Challenges..........6
Data and Calculations.......7
Bridge CAD Drawings...9
Testing and Improvements....9
Building Challenges.10
Bridge Building Process...11
Conclusion and Recommendations........17
Acknowledgements..19
Bibliography.20
Appendices
Appendix A...22
Appendix B...22
Appendix C...23
Summary
Kettler-Kilgore-Knight 2
The purpose of creating this bridge was to analyze the structure of a truss through tied
arch bridge. The goal was to create a bridge that could withstand the greatest amount of weight
while having as small a mass as possible. Before building, rough designs were tested using the
ModelSmart 2D software. In addition, a number of bridges of this type were researched, such as
the Fort Pitt bridge and the Fremont bridge. After a rough idea for the bridge had been gathered,
rough sketches were created to get an idea of how to start the bridge. After a decent design was
created, the production of the bridge began while other parts of the project were completed.
During construction, a number of observations were made that could help future bridge attempts.
Finally, after construction was complete, the Bentley Microstation PowerDraft software model
design was updated to accurately reflect the final bridge. After the completion of the bridge, it
was then broken using a near identical situation to the situation that would occur in the actual
competition to collect data on how the bridge hold up to the stress of added weight.
Introduction
Team TK3 is a group of three juniors from the Macomb Mathematics Science and
Technology Center (MMSTC) located in Warren, Michigan. The members, Thomas Kettler,
Kettler-Kilgore-Knight 3
Tianna Kilgore, and Tyler Knight, all have the initials of TK, thus TK3 since there are three of us
in the group. The members all attend MMSTC because of their love of math, science,
engineering, or computer technology. In addition to MMSTC, all of the group members attend a
home school for the remainder of the day. Two members, Thomas Kettler and Tyler Knight,
attend Lake Shore High School in St. Clair Shores, Michigan, whereas Tianna Kilgore attends
Cousino High School in Warren. The community at MMSTC is one that is very close, since the
junior class in the morning attends all classes together and therefore have formed a very close
Thomas Kettler is a hardworking individual from Lake Shore High School and attends
the Macomb Mathematics Science and Technology Center (MMSTC), as mentioned above.
Thomas loves dogs and is involved in a number of extracurricular activities. Thomas is on the
varsity swimming team at Lake Shore High School. He also is a part of the Science Olympiad
club, and competes once a year in a competition. Thomas is thinking about majoring in civil
Tianna Kilgore is a very intelligent and motivated student from Cousino High School
who also attends the MMSTC, as mentioned above. In addition to school, Tianna is also a part
of the Cousino varsity tennis team and the Warren Consolidated Schools robotics team. She is
also a part of the Warren Student Advisory Committee, which does volunteer and outreach work
for the local community. Tianna loves reading and musicals, such as Hamilton. In the future,
Tianna hopes to attend the University of Michigan and major in nuclear engineering.
Tyler Knight is a student from Lake Shore High School who attends MMSTC as well.
Some of Tylers extracurricular activities include bowling on varsity bowling team, the Science
Olympiad club, robotics, and archery all through Lake Shore. Tyler also attends the Lakefront
Kettler-Kilgore-Knight 4
Environmental Committee meetings once a month as a student liaison from Lake Shore High
School. In the future, Tyler hopes to attend a college in Michigan, some options being Michigan
Tech, Lawrence Tech, and Wayne State. Although he is not sure yet, Tyler hopes to go to school
Body
Science:
A truss through tied arch bridge is a modified version of the tied arch bridge. A tied arch
bridge is also known as a solid ribbed arch because that is what it looks like, a regular arch with
bars from the top of the arch to the base of the road. A truss through tied arch bridge has 4 main
parts; the arch, the ribbings (ties), the trusses beneath the road, and the road itself. The arch
handles the majority of the stress, as it takes energy to stay arched and not return to its original
position, straight. This energy is provided from the force of gravity on the road. It takes most of
Kettler-Kilgore-Knight 5
the force of the mass of the cars on the road, transferred partially through the ribbings placed
periodically throughout the length of the bridge, and partially from the ends where it connects the
the road and the ground or platform. The trusses beneath the road help to distribute the weight of
the cars as well, incase of excess weight, making this bridge very stable.
Figure 1, on the previous page, shows the force diagram for a tied arch bridge. As
shown, the bridge may bow due to the stress. This could harm the road, so a truss beneath the
road could prevent this bowing. The stress is distributed through the ribbing to the arch and
eventually to the ground. A truss would distribute the bowing stress so it would be able to
Figure 2, above, shows the force diagram for a regular truss bridge. While this is not the
main component of the truss through tied arch bridge, it does help prevent it from bowing and
support higher weights on the road. This would be located under the road.
The force diagram of a truss through tied arch bridge would be a combination of the two
force diagrams shown above, with the tied arch bridge on top and the truss part of the bridge
Design Challenges:
Some of the biggest challenges encountered when designing the bridge were the
limitations of the software. While many ideas were formed and rough sketches were made, the
those ideas. These limitations included the detrimental inability to make actual arches, therefore
a variety of straight edges created the illusion of trusses. In addition, there was no way to insert
the string that would be used in the actual design, so vertical balsa wood beams were used
instead. However, this is a very inaccurate representation for how the bridge would actually hold
up under pressure, so the results were not taken too seriously. The ModelSmart software was
also really difficult to use, as the mechanics were easy to learn but extremely inconvenient if any
For the data and calculations, a bridge model was created in the ModelSmart 2D software
(see Appendix C for the actual designs). These bridge designs were then tested under a number
of loads until they broke. From this, a maximum load to bridge weight ratio was calculated and,
in theory, the bridge with the largest maximum load to weight ratio would be designed. However,
the extreme imperfections in the software caused the data to be unhelpful, with the designs
Figure 3, above, shows a sample calculation for calculating the ratio of maximum load to
bridge weight. Line one shows the formula for calculating the ratio, along with the appropriate
method for converting the load from pounds to grams. Line two shows substituted values which
came from the data for bridge number one in the table below. These values were then used to
Table 1, above, shows the data collected from the bridges. The most effective bridge was
bridge 6, which had one of the smallest weights but the largest weight held, was used to help
model our final design. However, during the construction of the actual bridge it came to the
constructors attention that it had no actual trusses, and the balsa wood bridges in the design
could not be transferred to the actual design. Instead, right angle trusses were constructed to try
and replicate the same effect that the bridge had in the preliminary design, and the long balsa
wood beams were replaced with braided string. This should, in theory, help make the bridge
stronger as the string would support more than the balsa wood could before snapping, however it
could not be properly tested until the actual bridge was created.
When the bridge was first designed, a preliminary drawing was first made in Bentley
MicroStation PowerDraft. This preliminary drawing, which can be seen as the first attached
Bentley page, was created using the base of one of our ModelSmart designs and an arch which
complied with MDOT rules. However, after testing our preliminary bridge, it was discovered that
while the current design worked well, it was too short and differed slightly from the instructions
in the MDOt manual. Knowing this, a new, final drawing was made, which can be seen as the
Kettler-Kilgore-Knight 9
second attached Bentley page. This final drawing has the same design as the original, the only
difference being that the the length of the bridge has gone from 18 inches to 20 inches. This
gives the bridges more leverage on the testing station, and makes it so that the length from the
midpoint between the upper and lower arch on the right to the one on the left is 18 inches. This
change was made become of the added support it gave, but also so that it complied with the
After constructing a preliminary bridge model, the next step was to test the bridge. First,
the bridge had to be weighed on a scale so that value could be used for the final ratio. Next, the
bridge was tested using a model Pitsco Tester. The model Pitsco Tester we used was a board
approximately 20 inches long and 5 inches wide which had a support on either end. These
supports were approximately 3 inches high, 5 inches long, and 2 inches wide. The way this
worked was the bridge was laid across the supports, then a block of wood 16 inches long, 2
inches wide, and 1 inch high was put on top of the bridge deck. A length of paracord, which was
connected to the wooden block through a hole in the center, was then fed through the bottom
truss of the bridge. A hook was then added onto that paracord, and a bucket was secured to the
hook. Then, sand was poured into the bucket until the bridge broke. The amount of sand in the
bucket was then measured, and the maximum load to bridge weight ratio was then calculated.
The preliminary bridge design broke under a maximum load of 19,361.8 grams and
weighed 44.5 grams. This gave the preliminary design a maximum load to bridge weight ratio of
435.09 grams to grams. Overall, the group was satisfied with this ratio. In fact, the only thing
that needed to be changed was the length of the bridge. The length of the bridge was increased
from 18 inches to 20 inches so that it created better leverage on the model Pitsco Tester and so
Kettler-Kilgore-Knight 10
that it complied more with the bridge specifications outlined in the MDOT manual. Other than
that, the improvements that needed to be made to the bridge were caused by building challenges
Building Challenges:
Through the building of the bridge, a number of challenges arose that had to be
overcome. First, it was very difficult to bend the wood into a curve because the arches broke very
easily after being soaked, so they had to be gently bent and taped down in an estimated curve to
avoid creating small cracks that would become detrimental later on. We ended up tacking the
arches to a piece of cardboard, however this still left a little room for error. The braided string
was also a challenge because it was difficult to make a tight braid using such a long length of
string. Also it was hard to estimate how much shorter the string would be after braiding, because
the preliminary bridge, there was not enough string to tie the arch down securely. Therefore, we
ended up having to tie the arch down fairly loosely. Finally, the most difficult building challenge
was finding a good way to cut the balsa wood without getting bad cuts or just squishing the wood
together. These imperfections caused our measurements, and the overall bridge, to be off. The
only solution to this issue ended up being going back and redoing parts of the bridge.
Before the bridge was built, a few safety precautions were taken. Some of these
precautions included using caution and not playing with the balsa cutters, using a stick to spread
the glue to prevent any sort of accident glue, and using wax paper and laminated paper to prevent
the bridge from sticking to the table. In addition, the balsa wood was cut carefully to prevent the
wood from accidentally flying off and possibly hitting somebody. While there were not very
Kettler-Kilgore-Knight 11
many actual safety precautions, in the future goggles used when cutting the wood would be a lot
safer than just trying to be careful. The bridge building began with a simple sketch, which has
since been altered many times through further testing of bridges using the ModelSmart software.
All of the wood was cut after being measured multiple times. While the glue was drying, tape
was used to keep the balsa wood together, and to make sure the glue created a tight fit. The first
thing that was built was the base, which started off as a rectangle with trusses going back and
forth to prevent it from collapsing in on itself, but also to support the block where weight would
be added to break the bridge. The base has two parts, the road and the bottom, both being two
Figure 4, above, shows Tianna gluing and taping the trusses to the first rectangle of the
road.
Kettler-Kilgore-Knight 12
Figure 5, above, shows Tyler starting the vertical trusses while Tianna created the other
trussed rectangles. This was done before the rectangles were laminated to each other. This was
the step that caused the most error, and had to be redone multiple times as the vertical trusses
would often slide with the glue and the sizes would vary slightly, throwing everything off in the
end. These vertical trusses, with laminated supports at the corners and in the middle, helped to
connect the bottom part to the road and provided a little support so the road didnt just snap with
Figure 6, above, shows the final design for the base. Tianna is redoing some of the
trusses that didnt dry correctly, causing them to not fit perfectly or even touch the road from the
base. As seen, there are criss-crossed horizontal trusses to prevent the bridge from collapsing on
itself from the sides, and also to support the block that weight would be added to. Due to a lack
of time, some trusses were given a very small piece of balsa wood so they would connect the
bottom to the road and provide some support. This should not have affected the integrity of the
trusses on the base. While this was going on, Tyler was beginning to design in the Bentley
software and Thomas was beginning to create the arches, one of the most important parts of the
bridge.
Figure 7. Arches
Figure 7, above, shows two of the arches used after they were soaked for approximately
45 minutes. The tape ensures that they retain their shape for later use. A total of six arches were
Figure 8, above, shows the arches being connected to the road. The longer strands of tape
made sure that the arches didnt fall over and the glue dried straight. The road was taken off in
order to fix the vertical trusses between the bottom and the road, which was redone many times.
This helped the final bridge as the work could be divided up more easily.
Kettler-Kilgore-Knight 15
Figure 9, above, shows the supports that were used in between the two arches. While the
trusses arent shown, this is the majority of the bridge excluding a few horizontal supports to
make the trusses, and some horizontal beams between the arches to make sure they didnt fall
over. As in the other gluing steps, tape was used to make sure the parts stayed in place while the
Conclusion
In the end, the preliminary bridge tested very well. With a maximum load to bridge
weight ratio of 435.09 grams to grams, our group was satisfied with the results. During the actual
testing of the bridge, we found out that the base was very sturdy but it was the arch that was
weak. This was evident through the way that the middle of the base gave out and the arches bent,
yet the base of the frame remained in tact. Therefore, once improvements are applied, we are
confident that the final bridge will perform better than our preliminary one.
By participating in this project, we learned a number of useful skills. The most important
skill that we could learn was teamwork. Early on we noticed that if all of us were working on the
Kettler-Kilgore-Knight 17
bridge at once, there usually was not enough work to keep all of us occupied. However, once we
noticed this we started dividing the work up so two people would work on the bridge at a time
and the other would work on the CAD drawing in Bentley MicroStation PowerDraft.Finaly, our
group learned that planning is crucial to any task that you do. Without having a solid
ModelSmart design to base our preliminary bridge off of, we would have just been winging it,
which would have resulted in a lot more problems. Luckily, by learning to divide our time
wisely, we were able to come up with a solid idea for building the bridge before we got very far
into building the base of it. This allowed for our measurements to be a little more accurate and
In future projects, namely our final bridge design, there are a number of things we would
do differently. First off, we would like to cut the trusses were more consistently in size and
angle, so that gaps and errors could be avoided. This could be done by simply sharpening our
original cutting tools or purchasing better ones. The arches would also be cut at a more uniform
angle and bent in a more reliable manner. This could be done by bending the soaked wood
around a curved objected and tacking it in place. This would make the arches uniform and
prevent the arch from changing shape while drying. We would also like to use better software
that could accurately create joints and model the string tied design of the bridge. Lastly, we
would like to increase the length of the final bridge from 18 inches to 20 inches to help give the
Acknowledgments
Mr. Greg McMillan helped to oversee the construction of the bridge, and provided us
with the workspace and the tools needed to complete the construction.
Mrs. Rose Cybulski helped to figure out the Model Smart software, and helped with some
researching sources.
Each other, for always doing their part in some way, always contributing to the building
Bibliography
"Beam Bridge." Encyclopdia Britannica. Encyclopdia Britannica, Inc., n.d. Web. 08 Jan.
2017.
"Bridge Basics - A Spotter's Guide to Bridge Design." Bridge Basics - A Spotter's Guide to
"Cantilever Bridge." Encyclopdia Britannica. Encyclopdia Britannica, Inc., n.d. Web. 08 Jan.
2017.
<http://www.lightthebridges.org/bridge/fremont/>.
"How Bridges Work." Explain That Stuff. N.p., 26 Mar. 2016. Web. 08 Jan. 2017.
Lamb, Robert, and Michael Morrissey. "How Bridges Work: The Beam
<http://science.howstuffworks.com/engineering/civil/bridge3.htm>.
Lamb, Robert, and Michael Morrissey. "How Bridges Work: The Suspension
<http://science.howstuffworks.com/engineering/civil/bridge6.htm>.
Kettler-Kilgore-Knight 20
"Suspension Bridge." Encyclopdia Britannica. Encyclopdia Britannica, Inc., n.d. Web. 08 Jan.
2017.
"The Point & Pittsburgh." Point Bridge Realty Advisors LLC. N.p., n.d. Web. 09 Jan. 2017.
<http://point-bridge.com/about-us/pittsburgh-the-point/>.
"Tied-arch Bridge Facts, History and Examples." Tied-arch Bridge - Facts, Design and
<http://www.historyofbridges.com/facts-about-bridges/tied-arch-bridge/>.
"Tied-arch Bridge Facts, History and Examples." Tied-arch Bridge - Facts, Design and
<http://www.historyofbridges.com/facts-about-bridges/tied-arch-bridge/>.
Kettler-Kilgore-Knight 21
Appendices
Appendix A. Schedule
In terms of bridge constructuction, there was no real schedule in place for when the
bridge would be built. This was due to the fact that the bridge was only worked on during any
possible class time. The main idea was having at least two people building while the third
member would do another part, such as modeling in the Bentley software or creating the ideas in
ModelSmart.
Figure 10, above, shows the first possible bridge design made in ModelSmart 2D. It was
not efficient. Also, the loads were not evenly distributed, they were only placed in the center,
Figure 11, above, shows the second possible bridge design done in ModelSmart 2D. It is
not symmetric and is extremely inefficient. Also, the loads were not evenly distributed, they were
Kettler-Kilgore-Knight 24
Figure 12, above, shows the third possible bridge design done in ModelSmart 2D. This
design was more capable of holding weight than the previous two. However, the loads were not
evenly distributed, they were only placed in the center, which may have caused errors.
Figure 13, above, shows the fourth possible bridge design done in ModelSmart 2D. This
design had one of the higher strength-to-weight ratios of the designs. However, only one load
was placed in the center of the bridge, which may have caused errors.
Kettler-Kilgore-Knight 26
Figure 14, above, shows the fifth possible bridge design done in ModelSmart 2D. This
was the lightest design to be created, but also held the least amount of weight. It should be noted
that only one load was placed in the center of the bridge, which may have caused errors.
Kettler-Kilgore-Knight 27
Figure 15, above, shows the sixth possible bridge design done in ModelSmart 2D. This
design had the highest strength-to-weight ratio of them all. However. only one load was placed in
Figure 16, above, shows the seventh possible bridge design done in ModelSmart 2D. This
design was very effective at holding multiple loads of weight, evenly distributed along the length
of the bridge.
Figure 17, above, shows the eighth possible bridge design done in ModelSmart 2D. This