CTR FORM

COST TIME & RESOURCE

PROJECT : DWT Subsea FEED CONTRACT No.: WORK ORDER Nr. :

CONTRACTOR:

CUSTOMER : Tullow Ghana Limited

Planned Start: Planned Finish : Duration :

CTR/Activity No : Title : Date :


Rev :
1010 Project Management
Author :

Objective

To perform the project and interface management activities associated with implementation of the subsea FEED.

Activities Description

Subsea FEED team management


Schedule management and progress reporting
Liaison with Client
Definition of codes and standards
Change control
Weekly reporting and progress meetings
Overseeing development of final FEED documentation and ITT packages

Input Requirements

Output / Deliverables

FEED schedule
Schedule management and progress reporting
Liaison with Client
Definition of codes and standards
Change control
Weekly reporting and progress meetings
Overseeing development of final FEED documentation and ITT packages

Notes, Assumptions, etc

Prepared By (Lead): Checked By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

Agreed By : Approved By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

PROJECT : DWT Subsea FEED CONTRACT No.: WORK ORDER Nr. :

CONTRACTOR:

CUSTOMER : Tullow Ghana Limited

Planned Start: Planned Finish : Duration :

CTR/Activity No : Title : Date :


Rev :
1020 Quality Assurance
Author :

Objective

Quality Assurance for the Subsea FEED

Activities Description

Develop and issue QA Manual for project use during subsea FEED
Develop and Issue QA Plan for subsea FEED

Input Requirements

Output / Deliverables

Subsea FEED QA Manual


QA Plan for FEED
Audit Schedule
Audit Reports
Corrective Action Reports
Follow-up Reports

Notes, Assumptions, etc

Prepared By (Lead): Checked By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

Agreed By : Approved By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

PROJECT : DWT Subsea FEED CONTRACT No.: WORK ORDER Nr. :

CONTRACTOR:

CUSTOMER : Tullow Ghana Limited

Planned Start: Planned Finish : Duration :

CTR/Activity No : Title : Date :


Rev :
1030 Document Control
Author :

Objective

Management of Project Documents

Activities Description

Produce Subsea FEED Document Control Manual


Maintain Document Register
Control and issue outgoing documentation
Receipt and control of incoming documentation

Input Requirements

Key deliverable dates


Deliverables Schedule (CTR 1050)

Output / Deliverables

Master Document Register (MDR)

Notes, Assumptions, etc

Prepared By (Lead): Checked By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

Agreed By : Approved By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

PROJECT : DWT Subsea FEED CONTRACT No.: WORK ORDER Nr. :

CONTRACTOR:

CUSTOMER : Tullow Ghana Limited

Planned Start: Planned Finish : Duration :

CTR/Activity No : Title : Date :


Rev :
1040 FMECA and RAM Studies
Author :

Objective

Define sparing and redundancy philosophy for subsea facilities

Activities Description

Perform a FMECA study to identify, record and understand potential failure modes and uncertainties
Quantify reliability and availability of individual items of equipment
Development of models to quantify reliability, availability and maintainability of each defined system to cover turn-up,
operational and mechanical cases

Input Requirements

Client supplied reliability data


Manufacturers data
OREDA

Output / Deliverables

Report on FMECA studies


Report on RAM studies
Input to project Sparing Philosophy for subsea facilities

Notes, Assumptions, etc


CTR FORM
COST TIME & RESOURCE

Prepared By (Lead): Checked By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .

Agreed By : Approved By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

PROJECT : DWT Subsea FEED CONTRACT No.: WORK ORDER Nr. :

CONTRACTOR:

CUSTOMER : Tullow Ghana Limited

Planned Start: Planned Finish : Duration :

CTR/Activity No : Title : Date :


Rev :
1050 Scheduling
Author :

Objective

Planning services to the overall project plan

Activities Description

Generate and maintain a Level 2 schedule for the overall subsea development from FEED to project completion. The
project schedule shall reflect and integrate Client milestones and planned field activities
Identify a Consents and Approvals schedule
Integrate data from procurement support

Input Requirements

Information from procurement support (CTR 1060)

Output / Deliverables

Level 2 schedule for post-FEED activities

Notes, Assumptions, etc

Prepared By (Lead): Checked By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

Agreed By : Approved By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

PROJECT : DWT Subsea FEED CONTRACT No.: WORK ORDER Nr. :

CONTRACTOR:

CUSTOMER : Tullow Ghana Limited

Planned Start: Planned Finish : Duration :

CTR/Activity No : Title : Date :


Rev :
1060 Procurement Support
Author :

Objective

To establish a subsea Long lead Item (LLI) List for the project (taking into account of, but not limited to, COMPANY
Frame Agreement items)
To develop a post-FEED subsea procurement plan for the project
To develop technical specifications and datasheets for long lead items included (but not limited to) COMPANY Frame
Agreement items.
Support Company in the technical evaluation of offered components under the frame agreement
Assist Company in developing all technical documentation for the frame agreement work order packages including scope
of supply, supplier data requirements list (SDRL) etc in the requisition documentation

Activities Description

Contact with vendors to establish current (and future) expected lead times for equipment and materials supply (outwith
COMPANYs Frame Agreements)
Discuss and agree likely durations for post FEED procurement activities
Develop specifications and data sheets
Assist with technical queries during tendering period
Carry out technical evaluation of tenders
Assist in the development of work order package requisitions, SDRLs.

Input Requirements

Definition of subsea facilities and equipment required

Output / Deliverables

Subsea Long Lead Items (LLI) List


Produce Vendor Bid Lists for the identified LLI
Post-FEED procurement plan for input into the overall project schedule (Level 2)
Specifications,
Technical evaluation criteria,
Requisition and SDRL development

Notes, Assumptions, etc

Company is expecting 3 Frame agreement tenders per frame agreement type. Contractor should anticipate technical
queries and technical evaluation with 3 tenderers.
CTR FORM
COST TIME & RESOURCE

Prepared By (Lead): Checked By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .

Agreed By : Approved By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

PROJECT : DWT Subsea FEED CONTRACT No.: WORK ORDER Nr. :

CONTRACTOR:

CUSTOMER : Tullow Ghana Limited

Planned Start: Planned Finish : Duration :

CTR/Activity No : Title : Date :


Rev :
1070 Cost Estimating
Author :

Objective

To provide a comprehensive life cycle cost report, including abandonment, for the management, engineering,
procurement, installation, testing, pre-commissioning and commissioning of the subsea facilities

Activities Description

Contact with vendors to establish budget estimates as required outside COMPANYs Frame Agreement items
Agree a cost basis with COMPANY
Produce a tabulated cost estimate for CAPEX, OPEX and abandonment costs

Input Requirements

Agreed cost norms


Discussion with vendors as required.

Output / Deliverables

Cost Estimation Basis Report


Field Development Cost Report for subsea equipment and facilities and their installation and pre-commissioning

Notes, Assumptions, etc

Prepared By (Lead): Checked By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .

Agreed By : Approved By :
CTR FORM
COST TIME & RESOURCE

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

PROJECT : DWT Subsea FEED CONTRACT No.: WORK ORDER Nr. :

CONTRACTOR:

CUSTOMER : Tullow Ghana Limited

Planned Start: Planned Finish : Duration :

CTR/Activity No : Title : Date :


Rev :
1080 Risk and Opportunities
Author :

Objective

To identify risks and opportunities for the project


To investigate risk reduction, mitigation and management measures

Activities Description

Subsea presence at formal project Risk Identification and Assessment Workshop


Input into the Risk Register, as required
Input to Risk reduction and mitigation report as required

Input Requirements

Output / Deliverables

Subsea input to Risk Identification Report


Subsea input to Risk Register
Subsea input to possible risk reduction measures and management of risk

Notes, Assumptions, etc

Prepared By (Lead): Checked By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

Agreed By : Approved By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

PROJECT : DWT Subsea FEED CONTRACT No.: WORK ORDER Nr. :

CONTRACTOR:

CUSTOMER : Tullow Ghana Limited

Planned Start: Planned Finish : Duration :

CTR/Activity No : Title : Date :


Rev :
1090 IVB Interface and Support
Author :

Objective

To provide an interface with COMPANYs IVB


To provide technical support in response to COMPANYs IVB queries/comments

Activities Description

Provide a technical interface with COMPANYs IVB during the FEED process
Provide technical responses to COMPANYs IVB queries, reviews and comments

Input Requirements

Queries and comments received from COMPANYs IVB

Output / Deliverables

General discussion with COMPANYs IVB


Formal responses to COMPANYs IVB queries/comments
IVB Approval of Subsea FEED Deliverables

Notes, Assumptions, etc

Prepared By (Lead): Checked By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .

Agreed By : Approved By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

PROJECT : DWT Subsea FEED CONTRACT No.: WORK ORDER Nr. :

CONTRACTOR:

CUSTOMER : Tullow Ghana Limited

Planned Start: Planned Finish : Duration :

CTR/Activity No : Title : Date :


Rev :
2010 Basis of Design
Author :

Objective

To assist with updating of the project Basis of Design

Activities Description

Provision of subsea data and change of data as required as the FEED progresses

Input Requirements

Output / Deliverables

Basis of Design updates

Notes, Assumptions, etc

Prepared By (Lead): Checked By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .

Agreed By : Approved By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

PROJECT : DWT Subsea FEED CONTRACT No.: WORK ORDER Nr. :

CONTRACTOR:

CUSTOMER : Tullow Ghana Limited

Planned Start: Planned Finish : Duration :

CTR/Activity No : Title : Date :


Rev :
2020 Project Philosophies
Author :

Objective

To assist with the development of system design and operation philosophies for the project

Activities Description

Provision of subsea input into the various philosophies to be developed as part of the overall FEED

Input Requirements

Fishing Intensity Studies (if available or relevant)


Basis of Design
All party workshops

Output / Deliverables

Operations Philosophy
Materials Selection Philosophy
Corrosion Mitigation Philosophy
Chemical Injection Philosophy
Metering Philosophy
Pigging Philosophy
Protection Philosophy
Installation Philosophy
Pre-commissioning/Commissioning Philosophy
Inspection, Maintenance and Repair (IMR) Philosophy
Future Tie-In Philosophy

Notes, Assumptions, etc


CTR FORM
COST TIME & RESOURCE

Prepared By (Lead): Checked By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .

Agreed By : Approved By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

PROJECT : DWT Subsea FEED CONTRACT No.: WORK ORDER Nr. :

CONTRACTOR:

CUSTOMER : Tullow Ghana Limited

Planned Start: Planned Finish : Duration :

CTR/Activity No : Title : Date :


Rev :
2030 Interface Engineering
Author :

Objective

To establish subsea interfaces with other FEED disciplines (process, marine, etc.)

Activities Description

Establish areas where subsea equipment and facilities interface with other aspects of the project, for example, the FPSO,
process equipment and requirements, etc., and define the nature of the interface.
Develop an interface Register defining responsibilities for the interface and data required.
Manage the interfaces through FEED to ensure that up-to-date information is included in the design.

Input Requirements

Review meetings with FPSO Design Team


Attendance at all-party workshops
Attendance at Drilling Interface Management meetings

Output / Deliverables

Interface Register
Interface Definition Sheets

Notes, Assumptions, etc

COMPANYs FPSO contractor is likely to be located in the Far East


The interface between Subsea and the FPSO Topsides is very significant, and the subsea FEED contractor and the FPSO
Design Team will need to be aware of this. In particular, the interface applies to CTR Nos. 1050, 2040, 2060, 4010,
4020F to 3020 H, 4020 M, 4060, 4110, 4120, 5110 and 6030

Prepared By (Lead): Checked By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

Agreed By : Approved By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

PROJECT : DWT Subsea FEED CONTRACT No.: WORK ORDER Nr. :

CONTRACTOR:

CUSTOMER : Tullow Ghana Limited

Planned Start: Planned Finish : Duration :

CTR/Activity No : Title : Date :


Rev :
2040 Future Expansion
Author :

Objective

To establish the options for future expansion of the development and quantify level of pre-investment.

Activities Description

Investigate the options available for the subsea architecture for future tie-in of wells.
Define potential requirement for new wells and quantify level of pre-investment recommended

Input Requirements

Client sub-surface team

Output / Deliverables

List of pre-investment CAPEX


Input to Future Tie-Back Philosophy (CTR 2020)
Pre-investment included in cost estimate

Notes, Assumptions, etc

Prepared By (Lead): Checked By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .

Agreed By : Approved By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

PROJECT : DWT Subsea FEED CONTRACT No.: WORK ORDER Nr. :

CONTRACTOR:

CUSTOMER : Tullow Ghana Limited

Planned Start: Planned Finish : Duration :

CTR/Activity No : Title : Date :


Rev :
2050 Materials Philosophy
Author :

Objective

To develop materials selection philosophy for the subsea production system, including manifolds, flowlines and risers.
To develop a Corrosion Management System Specification

Activities Description

Definition of potential materials for use within the subsea architecture selected for the development
Demonstration that the materials recommended will be compatible with those of adjacent components and foreseen
operating conditions, and will comply with the system requirements as a whole.
Development of an overall Corrosion Management Specification for the subsea system

Input Requirements

Basis of Design

Output / Deliverables

Input to Materials Philosophy document (CTR 2020)


Subsea Corrosion Management System Specification

Notes, Assumptions, etc

Prepared By (Lead): Checked By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .

Agreed By : Approved By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

PROJECT : DWT Subsea FEED CONTRACT No.: WORK ORDER Nr. :

CONTRACTOR:

CUSTOMER : Tullow Ghana Limited

Planned Start: Planned Finish : Duration :

CTR/Activity No : Title : Date :


Rev :
2060 System Definition and Optimisation
Author :

Objective

To define the subsea system for the development as a basis for the remaining phases of FEED.

Activities Description

Development of preliminary system schematics (first draft P&IDs and field layout drawings), showing all main elements
of the subsea system, manifolds, flowlines risers, piping, valves, instruments, etc.
Undertake a peer driven constructability/operability workshop, reviewing the arrangements from installation, operation
and maintenance viewpoints.
Issue field architecture GA drawings and schematics as a basis for the remaining phases of FEED.

Input Requirements

Concept selection documentation and drawings.

Output / Deliverables

Preliminary subsea system P&IDs


Field Layout drawings
Development schematics

Notes, Assumptions, etc

Prepared By (Lead): Checked By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

Agreed By : Approved By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

PROJECT : DWT Subsea FEED CONTRACT No.: WORK ORDER Nr. :

CONTRACTOR:

CUSTOMER : Tullow Ghana Limited

Planned Start: Planned Finish : Duration :

CTR/Activity No : Title : Date :


Rev :
3010 Subsea Structure Piping Design
Author :

Objective

To develop preliminary designs for manifold and riser base (if required) pipework

Activities Description

Development of piping and equipment layouts for the subsea manifolds, PLETs and riser bases (if required), to include:
- All pipework required
- Tie-in arrangements
- Remote connector type(s)
- Valve requirements, actuation methods and interfaces for ROV intervention
- Controls instrumentation
- Testing and commissioning requirements
From layouts, the development of a piping MTO and weight estimate for each structure as required.

Input Requirements

System definition and P&IDs


System philosophies

Output / Deliverables

2D and 3D CAD drawings


Piping MTOs for all structures
Piping weight estimates for all structures

Notes, Assumptions, etc

Prepared By (Lead): Checked By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

Agreed By : Approved By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

PROJECT : DWT Subsea FEED CONTRACT No.: WORK ORDER Nr. :

CONTRACTOR:

CUSTOMER : Tullow Ghana Limited

Planned Start: Planned Finish : Duration :

CTR/Activity No : Title : Date :


Rev :
3020 Subsea Structures Structural Design
Author :

Objective

To develop structural designs for manifolds, PLETs and riser bases (if required)

Activities Description

Development of manifold, PLET and riser base (if required) structural layouts, to meet the following criteria:
- Support and protection of the manifold/riser base piping and equipment
- Any protection requirements
- Potential foundations design
- Deployment and installation requirements
- ROV access to operate/override valves
- ROV access to recover/change out key components
From the structural layouts developed, structural steel MTOs and weight estimates will be established for each structure.

Input Requirements

System definition and preliminary P&IDs


System philosophies

Output / Deliverables

2D and 3D CAD drawings


Piping MTOs
Piping weight estimates

Notes, Assumptions, etc

Prepared By (Lead): Checked By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

Agreed By : Approved By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

PROJECT : DWT Subsea FEED CONTRACT No.: WORK ORDER Nr. :

CONTRACTOR:

CUSTOMER : Tullow Ghana Limited

Planned Start: Planned Finish : Duration :

CTR/Activity No : Title : Date :


Rev :
3030 Subsea Structures Foundations Design
Author :

Objective

To define the most suitable foundation system for the manifold, PLET and riser base (if required) structures.

Activities Description

Development of foundations designs for the subsea structures, including:


- Agree seabed soils data for the preliminary design
- Select optimum foundations system (piles, suction piles, gravity base, etc.)
- Potential foundations design
- Foundations deployment and installation requirements (if applicable)
- ROV access
From the above develop a structural steel MTO and weight estimates for the foundations for each structure.

Input Requirements

Seabed soils information (desktop study or survey information)


Manifold structural and piping designs/layouts

Output / Deliverables

Drawings
Technical note on foundations design for all structures
Foundations MTO and weight estimates for all structures

Notes, Assumptions, etc

Prepared By (Lead): Checked By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

Agreed By : Approved By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

PROJECT : DWT Subsea FEED CONTRACT No.: WORK ORDER Nr. :

CONTRACTOR:

CUSTOMER : Tullow Ghana Limited

Planned Start: Planned Finish : Duration :

CTR/Activity No : Title : Date :


Rev :
4010 Flowline Route Selection
Author :

Objective

To select routes for the infield flowlines required for the development.

Activities Description

A flowline routing study will be performed based on the available data. The routing study will take into consideration the
approaches at the FPSO and manifold ends of the flowlines as well as any known seabed features that will require routing
around. In general, however, the shortest route possible will be selected.
The flowline routes will be used as a basis for the scope of work for the engineering route survey, will be used as the
basis of Field Layout drawings and will provide input to the flow assurance studies (CTR 4020).
Flowline routing shall also take into account pipeline stability, the potential to walk over steep inclines, etc, and avoid
these as necessary

Input Requirements

Admiralty Chart(s) of he DWT area


Any Client supplied information on the area

Output / Deliverables

Route Alignment Sheets


Technical note on route selection
Input to Scope of Work for engineering survey
Input to flow assurance studies

Notes, Assumptions, etc

Prepared By (Lead): Checked By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

Agreed By : Approved By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

PROJECT : DWT Subsea FEED CONTRACT No.: WORK ORDER Nr. :

CONTRACTOR:

CUSTOMER : Tullow Ghana Limited

Planned Start: Planned Finish : Duration :

CTR/Activity No : Title : Date :


Rev :
4020A Flow Assurance; Fluids Characterisation
Author :

Objective

To undertake further fluids characterisation studies based on clean DST fluid samples

Activities Description

Analysis of available laboratory report data and selection of fluids for characterisation
Specification of fluid characterisation procedure
Characterisation of fluids

Input Requirements

Fluid analysis reports

Output / Deliverables

Update of fluid characterisation study report

Notes, Assumptions, etc

Prepared By (Lead): Checked By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .

Agreed By : Approved By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

PROJECT : DWT Subsea FEED CONTRACT No.: WORK ORDER Nr. :

CONTRACTOR:

CUSTOMER : Tullow Ghana Limited

Planned Start: Planned Finish : Duration :

CTR/Activity No : Title : Date :


Rev :
4020B Flow Assurance; Flow Assurance Simulation Basis
Author :

Objective

To develop a flow assurance simulation basis

Activities Description

Review of steady state and dynamic flow assurance work undertaken in pre-FEED
Specification of data requirements
Collation of Data
Identify further data requirements
Detail any assumptions made

Input Requirements

Existing available data

Output / Deliverables

Flow Assurance Simulation Basis Report


Agreement with COMPANY as to the simulation basis

Notes, Assumptions, etc

Note: there will be some uncertainty in design. Additional exploration and appraisal drilling in Q2 2011 will provide more
data which may require/cause updates to some of the design cases, and then pre-FEED steady state and dynamic flow
assurance work may require reworking.

Prepared By (Lead): Checked By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

Agreed By : Approved By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

PROJECT : DWT Subsea FEED CONTRACT No.: WORK ORDER Nr. :

CONTRACTOR:

CUSTOMER : Tullow Ghana Limited

Planned Start: Planned Finish : Duration :

CTR/Activity No : Title : Date :

Flow Assurance; Steady State Analysis of Further Field Rev :


4020C Extension
Author :

Objective

To complete steady state PIPESIM analysis in the event that the current full field development is expanded.

Activities Description

Review of pre-FEED steady state analysis


Construction of appropriate PIPESIM models
Undertaking the required simulation runs
Results analysis
Production of steady state report

Input Requirements

Existing available data

Output / Deliverables

Extended Steady State Simulation Report

Notes, Assumptions, etc

Note: there will be some uncertainty in design. Additional exploration and appraisal drilling in Q2 2011 will provide more
data which may require/cause updates to some of the design cases, and then pre-FEED steady state and dynamic flow
assurance work may require reworking

Prepared By (Lead): Checked By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

Agreed By : Approved By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

PROJECT : DWT Subsea FEED CONTRACT No.: WORK ORDER Nr. :

CONTRACTOR:

CUSTOMER : Tullow Ghana Limited

Planned Start: Planned Finish : Duration :

CTR/Activity No : Title : Date :


Rev :
4020D Flow Assurance; Steady State Life of Field Analysis
Author :

Objective

To complete steady state PIPESIM analysis to confirm system performance through field life

Activities Description

Review of pre-FEED steady state analysis


Construction of appropriate PIPESIM models
Development of fluid compositions
Undertaking the required simulation runs
Results analysis
Production of Life of Field Report

Input Requirements

Agreed production rates at various stages through field life


Assessment of water cut and gas leaning sensitivities define appropriate fluids sensitivities

Output / Deliverables

Confirmation of line sizing, thermal insulation, etc.


Steady State Life of Field Report

Notes, Assumptions, etc

Note: there will be some uncertainty in design. Additional exploration and appraisal drilling in Q2 2011 will provide more
data which may require/cause updates to some of the design cases, and then pre-FEED steady state and dynamic flow
assurance work may require reworking

Prepared By (Lead): Checked By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

Agreed By : Approved By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

PROJECT : DWT Subsea FEED CONTRACT No.: WORK ORDER Nr. :

CONTRACTOR:

CUSTOMER : Tullow Ghana Limited

Planned Start: Planned Finish : Duration :

CTR/Activity No : Title : Date :

Flow Assurance; Provision of Data for Life of Field Rev :


4020E Corrosion Analysis
Author :

Objective

To provide data for the analysis of corrosion over life of field

Activities Description

Review of pre-FEED steady state analysis


Extract appropriate data from the steady state life of field analysis to support life of field corrosion assessment
(temperature, pressure, density and superficial velocity profiles)
Production of Report

Input Requirements

Agreed production rates at various stages through field life


Assessment of water cut and gas leaning sensitivities define appropriate fluids sensitivities

Output / Deliverables

Report

Notes, Assumptions, etc

Note: there will be some uncertainty in design. Additional exploration and appraisal drilling in Q2 2011 will provide more
data which may require/cause updates to some of the design cases, and then pre-FEED steady state and dynamic flow
assurance work may require reworking

Prepared By (Lead): Checked By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

Agreed By : Approved By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

PROJECT : DWT Subsea FEED CONTRACT No.: WORK ORDER Nr. :

CONTRACTOR:

CUSTOMER : Tullow Ghana Limited

Planned Start: Planned Finish : Duration :

CTR/Activity No : Title : Date :


Rev :
4020F Flow Assurance; OLGA Model Construction and Review
Author :

Objective

To design, construct, review and approve an OLGA model of the DWT system to allow accurate dynamic and transient
analysis

Activities Description

Review of pre-FEED dynamic flow assurance analysis


Design and construct (or update existing model) an OLGA model of the system
Review the OLGA model

Input Requirements

Agreed subsea architecture


Agreed well designs

Output / Deliverables

Construction of a suitable OLGA model


Approval of model for use

Notes, Assumptions, etc

Note: there will be some uncertainty in design. Additional exploration and appraisal drilling in Q2 2011 will provide more
data which may require/cause updates to some of the design cases, and then pre-FEED steady state and dynamic flow
assurance work may require reworking

Prepared By (Lead): Checked By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

Agreed By : Approved By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

PROJECT : DWT Subsea FEED CONTRACT No.: WORK ORDER Nr. :

CONTRACTOR:

CUSTOMER : Tullow Ghana Limited

Planned Start: Planned Finish : Duration :

CTR/Activity No : Title : Date :

Flow Assurance; Transient Operability and Design Rev :


4020G Assessment
Author :

Objective

To perform dynamic and transient analysis of the system to confirm its satisfactory operation

Activities Description

Specification of operating philosophies and sensitivities


Definition of case matrices
Using OLGA model, investigate the following: Unstable flow and minimum hydraulic turndown; Artificial lift performance
(if required); Shutdown; Pipeline pressurisation (line packing); Settle out; Cooldown (no touch) and minimum thermal
turndown; Ramp up; Ramp down; Sphering and benefits of operational pigging; De-pressurisation; Well restart to
depressurised, pressurised and flowing systems; First gas start up; Typical start-up
Analysis of results
Final report

Input Requirements

Operations philosophy
Sensitivities

Output / Deliverables

Report of Transient Operability and Design Assessment

Notes, Assumptions, etc

Prepared By (Lead): Checked By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

Agreed By : Approved By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

PROJECT : DWT Subsea FEED CONTRACT No.: WORK ORDER Nr. :

CONTRACTOR:

CUSTOMER : Tullow Ghana Limited

Planned Start: Planned Finish : Duration :

CTR/Activity No : Title : Date :

Flow Assurance; Slugging Analysis Rev :


4020H
Author :

Objective

To provide data on potential slug sizes for various potential riser sizes in various flow scenarios
Working in conjunction with the FPSO Design Team, determine the best compromise in terms of FPSO topsides capacity
for managing slugs versus flowline size and wellhead back-pressures later in field life.

Activities Description

Extract liquid surge profiles from the OLGA runs of ramp up and pigging (if applicable) strategies. This is an iterative
process.
Data presentation in report form

Input Requirements

Appropriate OLGA runs

Output / Deliverables

Final Report of Support Data for Slug sizes and recommendations for topsides equipment that is consistent with the FPSO
Design Team conclusions.

Notes, Assumptions, etc

Prepared By (Lead): Checked By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

Agreed By : Approved By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

PROJECT : DWT Subsea FEED CONTRACT No.: WORK ORDER Nr. :

CONTRACTOR:

CUSTOMER : Tullow Ghana Limited

Planned Start: Planned Finish : Duration :

CTR/Activity No : Title : Date :


Rev :
4020I Flow Assurance; Data to Support Flowline Design
Author :

Objective

In conjunction with CTRs 4040/J and 4020 K, to provide data in support of flowline design

Activities Description

Extract data from appropriate steady state and dynamic runs in support of flowline design, including, but not limited to:
maximum and minimum steady state and transient wall temperatures; Operating pressure ranges; Full shut-in conditions
for each system
Data presentation in report form

Input Requirements

Appropriate PIPESIM and OLGA runs

Output / Deliverables

In conjunction with CTRs 4040/J and 4020 K, Report of Support Data for Flowline Design

Notes, Assumptions, etc

Prepared By (Lead): Checked By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .

Agreed By : Approved By :
CTR FORM
COST TIME & RESOURCE

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

PROJECT : DWT Subsea FEED CONTRACT No.: WORK ORDER Nr. :

CONTRACTOR:

CUSTOMER : Tullow Ghana Limited

Planned Start: Planned Finish : Duration :

CTR/Activity No : Title : Date :


Rev :
4020J Flow Assurance; Hydrate and Wax Management Studies
Author :

Objective

In conjunction with CTRs 4040/J and 4020 K, to specify and confirm hydrate and wax management strategies,
particularly under transient conditions

Activities Description

Additional OLGA runs as required to consider refined blowdown and liquids displacement strategies
Additional OLGA runs to track hydrate inhibition during restart and wax deposition
Data presentation in report form

Input Requirements

Appropriate PIPESIM and OLGA runs

Output / Deliverables

In conjunction with CTRs 4040/J and 4020 K, Report of recommended hydrate and wax management strategies for the
development

Notes, Assumptions, etc

Prepared By (Lead): Checked By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .

Agreed By : Approved By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

PROJECT : DWT Subsea FEED CONTRACT No.: WORK ORDER Nr. :

CONTRACTOR:

CUSTOMER : Tullow Ghana Limited

Planned Start: Planned Finish : Duration :

CTR/Activity No : Title : Date :


Rev :
4020K Flow Assurance; Hydrate Remediation Assessment
Author :

Objective

In conjunction with CTRs 4040/J and 4020 K, to size the venting system (if provided) for de-pressurisation on either side
of a hydrate blockage, and to develop an operating strategy for the system

Activities Description

Identification of cases for assessment


Construction of OLGA model(s)
OLGA runs
Results analysis
Case Refinement and report on hydrate remediation

Input Requirements

Appropriate PIPESIM and OLGA runs

Output / Deliverables

In conjunction with CTRs 4040/J and 4020 K, Report of recommended hydrate remediation strategy

Notes, Assumptions, etc

Prepared By (Lead): Checked By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

Agreed By : Approved By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

PROJECT : DWT Subsea FEED CONTRACT No.: WORK ORDER Nr. :

CONTRACTOR:

CUSTOMER : Tullow Ghana Limited

Planned Start: Planned Finish : Duration :

CTR/Activity No : Title : Date :


Rev :
4020L Flow Assurance; Chemical Core and Distribution Sizing
Author :

Objective

To confirm sizing of chemical injection cores in the subsea umbilicals and design of any subsea chemicals distribution
network

Activities Description

Construction of appropriate PIPESIM models


Development of fluid compositions
PIPESIM runs
Analysis of results
Report covering above work

Input Requirements

N/A

Output / Deliverables

Report on chemical injection system


Input data for the specifications for subsea umbilicals and umbilical risers

Notes, Assumptions, etc

Prepared By (Lead): Checked By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

Agreed By : Approved By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

PROJECT : DWT Subsea FEED CONTRACT No.: WORK ORDER Nr. :

CONTRACTOR:

CUSTOMER : Tullow Ghana Limited

Planned Start: Planned Finish : Duration :

CTR/Activity No : Title : Date :


Rev :
4020M Flow Assurance; System Finalisation
Author :

Objective

To confirm system performance on completion of design activities

Activities Description

Finalised set of OLGA runs, simulating finalised chemical inhibition dosing and agreed flowline operating strategies. Runs
will be required for: Steady state; ramp up; Ramp down; Pigging; Shutdown, settle out and cooldown; Pipeline
pressurisation; De-pressurisation; First gas and typical start up; Well restart; Hydrate remediation
Analysis of results
Report covering above work

Input Requirements

System design and operating philosophies

Output / Deliverables

Report on finalised system analysis

Notes, Assumptions, etc

Prepared By (Lead): Checked By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

Agreed By : Approved By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

PROJECT : DWT Subsea FEED CONTRACT No.: WORK ORDER Nr. :

CONTRACTOR:

CUSTOMER : Tullow Ghana Limited

Planned Start: Planned Finish : Duration :

CTR/Activity No : Title : Date :


Rev :
4030 Flowline Mechanical Design
Author :

Objective

To undertake flowline mechanical design

Activities Description

Mechanical design of the infield flowlines will be undertaken using verified software to confirm the following:
- Wall thickness
- On-bottom stability
- External coating definition
- CP requirements
- Anode design and attachment
- Upheaval buckling analysis
- Trenching assessment (insulation)
Design shall be sufficient to allow procurement of linepipe in this phase of the development, if required.

Input Requirements

Preliminary flowline sizing (CTR 4020)


Basis of Design

Output / Deliverables

Flowline Mechanical Design Reports for infield flowlines


Drawings as appropriate

Notes, Assumptions, etc

Prepared By (Lead): Checked By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

Agreed By : Approved By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

PROJECT : DWT Subsea FEED CONTRACT No.: WORK ORDER Nr. :

CONTRACTOR:

CUSTOMER : Tullow Ghana Limited

Planned Start: Planned Finish : Duration :

CTR/Activity No : Title : Date :


Rev :
4040 Flowline Coating Design
Author :

Objective

To define optimum external coating system(s) for the flowlines

Activities Description

Selection of the external coating system(s) for flowlines will be undertaken taking into account:
- Anti-corrosion
- Stability
- Insulation requirements

Input Requirements

Flowline mechanical design (CTR 4030)


Flow Assurance studies (CTR 4020)

Output / Deliverables

Flowline Coating Selection Technical Report


Insulation Coating Selection Technical Note

Notes, Assumptions, etc

Prepared By (Lead): Checked By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

Agreed By : Approved By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

PROJECT : DWT Subsea FEED CONTRACT No.: WORK ORDER Nr. :

CONTRACTOR:

CUSTOMER : Tullow Ghana Limited

Planned Start: Planned Finish : Duration :

CTR/Activity No : Title : Date :


Rev :
4050 Flowline and Well Tie-Ins
Author :

Objective

To define systems for flowline and well tie-ins.

Activities Description

Survey available subsea remote flowline connection systems and select most appropriate for DWT development
Undertake system design for tie-ins between
- Flowlines and manifolds
- Wells and manifold
- Flowlines and riser bases (if required)
The stress analysis work for the spool tie-in design shall be based on a likely envelope, and the spool design shall be
adequate to accommodate the potential locations for trees, manifolds and PLETs within that envelope

Input Requirements

Basis of Design

Output / Deliverables

Subsea Remote Connection Systems Review Technical Note


Recommended remote connection system
Drawings of potential layouts for well tie-ins and for flowline tie-ins, including preliminary jumper/spoolpiece design.

Notes, Assumptions, etc

Prepared By (Lead): Checked By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

Agreed By : Approved By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

PROJECT : DWT Subsea FEED CONTRACT No.: WORK ORDER Nr. :

CONTRACTOR:

CUSTOMER : Tullow Ghana Limited

Planned Start: Planned Finish : Duration :

CTR/Activity No : Title : Date :


Rev :
4060 Pigging Design
Author :

Objective

To design aspects of the flowline system to suit pre-commissioning and operational pigging requirements.

Activities Description

From the established pigging philosophy


- Ensure that piping design for the manifolds facilitates the installation, use and retrieval of a temporary subsea
PLR for all headers
- Ensure that all tie-in spoolpiece designs are suitable for the safe passage of all types of pig envisaged for use in
pre-commissioning and operational requirements
- Ensure that all other aspects of the subsea flowline systems are suitable for envisaged pigging operations
- Interface with FPSO design to ensure that topsides PLR can be installed for pigging operations envisaged

Input Requirements

Basis of Design (CTR 2010)


Pigging Philosophy (CTR 2020)

Output / Deliverables

Pigging Operations Technical Note


Preliminary pigging procedures
Specification for subsea PLR
Input to design drawings of flowline system components

Notes, Assumptions, etc

Prepared By (Lead): Checked By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

Agreed By : Approved By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

PROJECT : DWT Subsea FEED CONTRACT No.: WORK ORDER Nr. :

CONTRACTOR:

CUSTOMER : Tullow Ghana Limited

Planned Start: Planned Finish : Duration :

CTR/Activity No : Title : Date :


Rev :
4110 Riser System Selection
Author :

Objective

To define the optimal configuration for the DWT riser system

Activities Description

Survey available deep water riser systems, establish pros and cons for each system and select most appropriate system
for the DWT development on both technical and economic bases. Riser systems evaluated will include:
- Flexible Risers
- Steel Catenary Risers
- Multi-bore Hybrid risers
- Single Offset Hybrid Risers
- Concentric Offset Hybrid Risers

Input Requirements

Basis of Design
Flow Assurance studies
Field Layout
Operations philosophy

Output / Deliverables

Deep Water Riser Systems Review Technical Note


Recommended riser system

Notes, Assumptions, etc

Prepared By (Lead): Checked By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

Agreed By : Approved By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

PROJECT : DWT Subsea FEED CONTRACT No.: WORK ORDER Nr. :

CONTRACTOR:

CUSTOMER : Tullow Ghana Limited

Planned Start: Planned Finish : Duration :

CTR/Activity No : Title : Date :


Rev :
4120 Riser System Design
Author :

Objective

Design of the DWT riser system

Activities Description

Based on an appropriate riser system selection, the following design analysis work will be undertaken to define the riser
system
- Configuration design, interfacing with the FPSO contractor for details on FPSO size, layout and RAOs.
- Stress analysis of the risers under expected loads induced by the expected FPSO motions, Metocean conditions
and operational conditions.
- Anchor requirements at base of risers (to isolate the flowlines and/or to maintain configuration and limit
transverse motions).
- Wall thickness definition.
- Preliminary fatigue analysis, including effects of VIV.
- Effects of insulation, if required.
- Flex-joint definition, if required
- Top end motions

Input Requirements

Basis of Design
FPSO layout/RAOs, etc.
Flow Assurance studies

Output / Deliverables

Preliminary Riser Design Report

Notes, Assumptions, etc

Prepared By (Lead): Checked By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

Agreed By : Approved By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

PROJECT : DWT Subsea FEED CONTRACT No.: WORK ORDER Nr. :

CONTRACTOR:

CUSTOMER : Tullow Ghana Limited

Planned Start: Planned Finish : Duration :

CTR/Activity No : Title : Date :


Rev :
5010 Chemical Injection Review and System Definition
Author :

Objective

Definition of the subsea components of the DWT chemical injection system

Activities Description

Review with process engineers the requirements for chemical injection into the DWT system, and the optimum locations
for such injection (e.g. at trees, flowlines or at manifolds, or combinations).
Review possible methods for achieving the chemical injection required, i.e. subsea distribution, etc.
Input into manifold system design and system P&IDs

Input Requirements

Basis of Design
Process studies
Flow Assurance studies

Output / Deliverables

Information for use in the subsea control system and umbilical studies

Notes, Assumptions, etc

Prepared By (Lead): Checked By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

Agreed By : Approved By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

PROJECT : DWT Subsea FEED CONTRACT No.: WORK ORDER Nr. :

CONTRACTOR:

CUSTOMER : Tullow Ghana Limited

Planned Start: Planned Finish : Duration :

CTR/Activity No : Title : Date :


Rev :
5110 Subsea Control System (SCS) Definition
Author :

Objective

Review and definition of the SCS

Activities Description

The subsea control system for the DWT development will be a multiplexed electrohydraulic system.
The DWT system philosophies (e.g. operations, availability, reliability, sparing, etc.) will be reviewed to assess the
required performance criteria for the SCS.
The key components of the SCS will be reviewed and defined
Review any new technology that may enhance the SCS or reduce its cost.
Develop a functional design specification for the SCS that will allow procurement to commence on completion of the FEED
phase of the project.

Input Requirements

Basis of Design
Field layout
P&IDs
Chemical Injection report

Output / Deliverables

Subsea Control System Preliminary Design Report


SCS Functional Design Specification

Notes, Assumptions, etc

Prepared By (Lead): Checked By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

Agreed By : Approved By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

PROJECT : DWT Subsea FEED CONTRACT No.: WORK ORDER Nr. :

CONTRACTOR:

CUSTOMER : Tullow Ghana Limited

Planned Start: Planned Finish : Duration :

CTR/Activity No : Title : Date :


Rev :
5210 Subsea Umbilical and Umbilical Riser Definition
Author :

Objective

Review and define requirements for the subsea umbilicals and umbilical riser(s)

Activities Description

Umbilical risers and seabed umbilicals will be required for subsea control, communications and chemical injection supplies
to manifolds and trees.
Review and define requirements for:
- Electrical power transmission
- Electrical or fibre optic signal transmission
- Hydraulic fluid supplies (HP and LP)
- Injection chemical supplies
Compare the use of thermoplastic hose with steel tube cores to supply hydraulic fluids and chemicals for injection.
Consider construction with copper core cables for signal transmission or the use of fibre optic cores.
In collaboration with umbilical supplier(s):
- Establish optimum construction for the seabed umbilicals, complete with proposed cross section.
- Establish optimum construction for the dynamic umbilical risers, complete with proposed cross section, and also
the transition design between dynamic and seabed umbilicals.
- Determine any anchoring/buoyancy requirements for the dynamic umbilical riser section.
- Consider reducing the number of umbilical risers with distribution subsea.
Review any new technology that may enhance the umbilical system or reduce its cost.

Input Requirements

Basis of Design
Field layout
P&IDs
Flow assurance studies (CTR 4020/L)
Chemical Injection report
SCS Definition

Output / Deliverables

Subsea Umbilical and Umbilical Riser Preliminary Design Report


Umbilical and Umbilical Riser Specification
Umbilical and Umbilical Riser Data Sheets

Notes, Assumptions, etc


CTR FORM
COST TIME & RESOURCE

Prepared By (Lead): Checked By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .

Agreed By : Approved By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

PROJECT : DWT Subsea FEED CONTRACT No.: WORK ORDER Nr. :

CONTRACTOR:

CUSTOMER : Tullow Ghana Limited

Planned Start: Planned Finish : Duration :

CTR/Activity No : Title : Date :


Rev :
5310 Review of Multiphase Flowmeter Systems
Author :

Objective

Review and recommend subsea multiphase flowmeter systems.

Activities Description

Gather and collate data on each of the subsea multiphase flowmeter types available, and review their accuracy, reliability
and cost (CAPEX and OPEX), making technical contact with suppliers as required. Establish track record of use in each
case.
Investigate and compare on technical and cost grounds the options to supply a meter and flow control valves at the
manifold or to provide a meter per well.
Produce a Specification and data sheet for the recommended multiphase flowmeter

Input Requirements

Metering philosophy
Operating philosophy
Vendor information packs
Chemical Injection report

Output / Deliverables

Subsea Multiphase Flowmeter Review Technical Note


Subsea Multiphase Flowmeter Specification
Subsea Multiphase Flowmeter Data Sheet

Notes, Assumptions, etc

Prepared By (Lead): Checked By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

Agreed By : Approved By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

PROJECT : DWT Subsea FEED CONTRACT No.: WORK ORDER Nr. :

CONTRACTOR:

CUSTOMER : Tullow Ghana Limited

Planned Start: Planned Finish : Duration :

CTR/Activity No : Title : Date :


Rev :
5320 Review of Sand Detection Systems
Author :

Objective

Review and recommend subsea sand detection systems.

Activities Description

Gather and collate data on the sand detection systems available (both intrusive and non-intrusive to the production
system). Review and compare the systems, their accuracy, reliability and cost (CAPEX and OPEX), making technical
contact with suppliers as required, and make recommendations for the DWT project.
Develop specification and data sheet for the recommended sand detection system

Input Requirements

Basis of Design
Operating philosophy
Vendor information packs

Output / Deliverables

Sand Detection Systems Review Technical Note


Sand Detector System Specification
Sand Detection System Data Sheet

Notes, Assumptions, etc

Prepared By (Lead): Checked By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

Agreed By : Approved By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

PROJECT : DWT Subsea FEED CONTRACT No.: WORK ORDER Nr. :

CONTRACTOR:

CUSTOMER : Tullow Ghana Limited

Planned Start: Planned Finish : Duration :

CTR/Activity No : Title : Date :


Rev :
6010 Survey Specification and Scope of Work
Author :

Objective

To provide a Specification and Scope of Work for engineering survey of the DWT seabed for detailed design purposes.

Activities Description

For detailed design of the DWT subsea facilities to proceed it will be necessary to provide data as to the nature of the
seabed in the area to allow various engineering and design tasks to proceed. The survey specification shall include, but
not be limited to:
- Applicable codes and standards
- Mobilisation and acceptance trials
- Survey vessel requirements
- Survey equipment requirements
- Sampling and in-situ testing requirements
- Data collection and on-board processing
- Interpretation and charting
- Reporting and Documentation requirements
The survey scope of work will include, but may not be limited to, the following:
- Route survey for each infield flowline and umbilical corridor, specifying corridor route, expected termination
locations, survey width and number of passes, PCT test requirements and separation, etc.
- Boreholes to establish details of soils and soils strength for locations where seabed structures will be required,
i.e. the three manifold locations, any location where there may be a riser base or riser anchor.
- Requirements for survey for the FPSO will also be included from the FPSO contractor.

Input Requirements

Field layouts
Expected locations for subsea structures and FPSO
Preliminary flowline routes

Output / Deliverables

Survey Specification
Survey Scope of Work
Survey Corridor Drawings

Notes, Assumptions, etc


CTR FORM
COST TIME & RESOURCE

Prepared By (Lead): Checked By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .

Agreed By : Approved By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

PROJECT : DWT Subsea FEED CONTRACT No.: WORK ORDER Nr. :

CONTRACTOR:

CUSTOMER : Tullow Ghana Limited

Planned Start: Planned Finish : Duration :

CTR/Activity No : Title : Date :


Rev :
6020 Subsea System Functional Design Specification
Author :

Objective

To prepare a Functional Design Specification for the DWT subsea system

Activities Description

The purpose of the document will be to summarise all functional requirements for the subsea facilities based on the FEED
work completed, and to compliment the BOD. Cross reference will be made within this document to other key reports and
specifications generated by the FEED study.

Input Requirements

BOD
Project philosophies
Field layout drawings
Subsea P&IDs

Output / Deliverables

Subsea System Functional Design Specification

Notes, Assumptions, etc

Prepared By (Lead): Checked By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

Agreed By : Approved By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

PROJECT : DWT Subsea FEED CONTRACT No.: WORK ORDER Nr. :

CONTRACTOR:

CUSTOMER : Tullow Ghana Limited

Planned Start: Planned Finish : Duration :

CTR/Activity No : Title : Date :

Flowline and Flowline Related Procurement, Fabrication Rev :


6030 and Installation Specifications
Author :

Objective

To prepare a full suite of specifications for procurement, fabrication and installation of the subsea flowline and related
facilities for inclusion in the ITT for the next phase of the project.

Activities Description

Prepare Specifications covering the procurement, fabrication and installation of subsea flowlines and flowlines related
equipment

Input Requirements

BOD
Project philosophies
Field layout drawings
Subsea P&IDs
Materials selection
Etc.

Output / Deliverables

Specifications covering Procurement, Fabrication and Installation of the Subsea FlowlineFacilities

Notes, Assumptions, etc

Specifications for the flowlines and flowline related equipment required have been listed in the Scope of Work for the
Subsea FEED. Depending on the FEED outcome, these may vary. Certain specifications are covered under specific
equipment CTRs.
CTR FORM
COST TIME & RESOURCE

Prepared By (Lead): Checked By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .

Agreed By : Approved By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

PROJECT : DWT Subsea FEED CONTRACT No.: WORK ORDER Nr. :

CONTRACTOR:

CUSTOMER : Tullow Ghana Limited

Planned Start: Planned Finish : Duration :

CTR/Activity No : Title : Date :


Rev :
6040 Subsea Structures and Structure Related Procurement ,
Fabrication and Installation Specifications Author :

Objective

To prepare functional specifications for the subsea manifolds, PLETs and riser bases (if required) for tenderers for the
next phase of the project

Activities Description

Prepare Specifications covering the procurement, fabrication and installation of subsea manifolds, PLETs and riser bases
(if required) and any structure related related equipment

Input Requirements

BOD
Project philosophies
Subsea P&IDs
Manifold 2D and 3D drawings
Pipework schematics
MTOs

Output / Deliverables

Manifold Design Specification

Notes, Assumptions, etc

Specifications for the subsea structures and structure related equipment required have been listed in the Scope of Work
for the Subsea FEED. The functional specification for the manifold(s), PLETs and riser bases (if required) will be prepared
in conjunction with the 2D and 3D CAD drawings, the MTOs and pipework schematics developed in FEED. Certain
Specifications (e.g. structure fabrication) will cover all structures.
CTR FORM
COST TIME & RESOURCE

Prepared By (Lead): Checked By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .

Agreed By : Approved By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

PROJECT : DWT Subsea FEED CONTRACT No.: WORK ORDER Nr. :

CONTRACTOR:

CUSTOMER : Tullow Ghana Limited

Planned Start: Planned Finish : Duration :

CTR/Activity No : Title : Date :


Rev :
6110 Scopes of Work for EPC/EPIC/Installation Contracts
Author :

Objective

To provide assistance as necessary to determine a contracting strategy for the next phase of the project.
To prepare Scopes of Work for the enquiry packages for the contracts to be let for the next phase of the work.

Activities Description

Assistance will be provided as necessary to develop a contracting strategy for the project, for example, EPC, EPIC, EPCIC
or installation.
As a result of the decision on contracting strategy, Scopes of Work will be developed for each of the contracts that will be
tendered. These Scopes of Work will be taken forward, together with other technical deliverables developed during FEED,
into The ITT packages.

Input Requirements

Contracting strategy
Subsea system architecture details

Output / Deliverables

Scopes of Work for ITT packages

Notes, Assumptions, etc

Prepared By (Lead): Checked By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

Agreed By : Approved By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

PROJECT : DWT Subsea FEED CONTRACT No.: WORK ORDER Nr. :

CONTRACTOR:

CUSTOMER : Tullow Ghana Limited

Planned Start: Planned Finish : Duration :

CTR/Activity No : Title : Date :


Rev :
7010 Subsea Support to HSE - General
Author :

Objective

Subsea contributions to project HSE in general

Activities Description

Assistance will be provided as necessary for the following:


- Contractual obligations for HSE
- Safety Engineering Design Philosophy
- Project HSE Plan
- Project Safety Register
- Development and Upkeep of Safety Action Management System (SAMS)

Input Requirements

Output / Deliverables

Report on HSE obligations


Philosophy documents
Project HSE Plan
Project Safety Register
SAMS

Notes, Assumptions, etc

Prepared By (Lead): Checked By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

Agreed By : Approved By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

PROJECT : DWT Subsea FEED CONTRACT No.: WORK ORDER Nr. :

CONTRACTOR:

CUSTOMER : Tullow Ghana Limited

Planned Start: Planned Finish : Duration :

CTR/Activity No : Title : Date :


Rev :
7020 Safety Engineering
Author :

Objective

Subsea contributions to project safety engineering tasks

Activities Description

Assistance/attendance will be provided as necessary for the following:


- Formal HAZID Workshop
- Formal HAZOP Workshop
- Loss control design
- Hazardous material inventory
-

Input Requirements

Output / Deliverables

HAZID Report
HAZOP Report
HAZOP Action List Responses
Design Report
Hazardous Materials List

Notes, Assumptions, etc

Prepared By (Lead): Checked By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

Agreed By : Approved By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

PROJECT : DWT Subsea FEED CONTRACT No.: WORK ORDER Nr. :

CONTRACTOR:

CUSTOMER : Tullow Ghana Limited

Planned Start: Planned Finish : Duration :

CTR/Activity No : Title : Date :


Rev :
7030 Environmental Engineering
Author :

Objective

Subsea contributions to project environmental engineering tasks

Activities Description

Assistance/attendance will be provided as necessary for the following:


- Environmental studies
- Formal ENVID Workshop
- Environmental protection philosophy
- Environmental emissions and discharges estimations and database

Input Requirements

Output / Deliverables

Environmental study technical note


ENVID report
Philosophy document
Emissions/Discharges database

Notes, Assumptions, etc

Prepared By (Lead): Checked By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .
CTR FORM
COST TIME & RESOURCE

Agreed By : Approved By :

Name: . Name: .

Signature: .. Signature: ...

Date: . Date: .