Housing Requirements
The housing requirement principally pertaining to the necessary rooms to host the datacenter and
the bus operation control center toSheger Mass Transport Service enterprise ITS. The house for
the datacenter shall be designed with the aim of hosting all the necessary, racks, servers,
workstations, routers, switches, UPs, power panel systems, power and telecommunication
equipment and cables.
The design should include raised floor to cover all the cabling system, to avoid
humidity and unnecessary dust, which affect the cables. The room should also
include all the necessary security and danger protection devices such as
humidity sensor, smoke detector, fire extinguisher, CCTVs, Smart card door
lock.
The bus operation control center shall be a well-crafted hall to handle all the bus
ITS. It should host all the necessary displays, computers, and other devices to
control all the bus operation onsite. The design shall also be made with the
aim of hosting operators, furniture, and all the necessary equipment. It should
host all the necessary infrastructures to be integrated and interoperable with
the backend datacenter.
The detailed requirement design shall be presented by supplier/contractor and
approved by the client.
Power system
1. Except where detailed specification is given, all the bus ITS equipment shall
be powered from either,
A single phase (220-240)V AC 50Hz supply or
A three phase 380Vac 50Hz supply.
2. The bus ITS shall include a power distribution subsystem for each power
supply to all components within the related bus ITS equipment. The circuit
breakers shall be properly sized according to the expected loads of the bus
ITS equipment and to meet electrical code requirements.
related electrical power supply is restored, without the need for manual
intervention.
5. The APTS must be able to transfer the connection with the internal power
system, from the primary power source, to the secondary power source,
within 1 mains power cycle (less than 20ms).
6. Additional equipment necessary to eliminate the delay in the transfer of
power sources which may cause the bus ITS equipment to reboot shall be
provided.
7. Each external power supply line shall be terminated at the APTS.
4.1.5.Telecommunications Equipment