Вы находитесь на странице: 1из 17

G.R. No. 170141 April 22, 2008 issued a U.S. visa.

issued a U.S. visa. Just to allow him to board the plane, he pleaded with JAL to closely monitor his movements
when the aircraft stops over in Narita. 17 His pleas were ignored. He was then constrained to go out of the plane. 18
JAPAN AIRLINES, petitioner, In a nutshell, respondent was bumped off the flight.
vs.
JESUS SIMANGAN, respondent. Respondent went to JAL's ground office and waited there for three hours. Meanwhile, the plane took off and he
was left behind.19 Afterwards, he was informed that his travel documents were, indeed, in order. 20 Respondent was
DECISION refunded the cost of his plane ticket less the sum of US$500.00 which was deducted by JAL. 21 Subsequently,
respondent's U.S. visa was cancelled.22
REYES R.T., J.:
Displeased by the turn of events, respondent filed an action for damages against JAL with the Regional Trial Court
(RTC) in Valenzuela City, docketed as Civil Case No. 4195-V-93. He claimed he was not able to donate his kidney
WHEN an airline issues a ticket to a passenger confirmed on a particular flight on a certain date, a contract of to Loreto; and that he suffered terrible embarrassment and mental anguish. 23 He prayed that he be awarded P3
carriage arises, and the passenger has every right to expect that he would fly on that flight and on that date. If he million as moral damages, P1.5 million as exemplary damages and P500,000.00 as attorney's fees.24
does not, then the carrier opens itself to a suit for breach of contract of carriage. 1
JAL denied the material allegations of the complaint. It argued, among others, that its failure to allow respondent
The power to admit or not an alien into the country is a sovereign act which cannot be interfered with even by to fly on his scheduled departure was due to "a need for his travel documents to be authenticated by the United
Japan Airlines (JAL).2 States Embassy"25 because no one from JAL's airport staff had encountered a parole visa before. 26 It posited that
the authentication required additional time; that respondent was advised to take the flight the following day, July
In this petition for review on certiorari,3 petitioner JAL appeals the: (1) Decision 4 dated May 31, 2005 of the 30, 1992. JAL alleged that respondent agreed to be rebooked on July 30, 1992. 27
Court of Appeals (CA) ordering it to pay respondent Jesus Simangan moral and exemplary damages; and (2)
Resolution5 of the same court dated September 28, 2005 denying JAL's motion for reconsideration. JAL also lodged a counterclaim anchored on respondent's alleged wrongful institution of the complaint. It prayed
for litigation expenses, exemplary damages and attorney's fees. 28
The Facts
On September 21, 2000, the RTC presided by Judge Floro P. Alejo rendered its decision in favor of respondent
In 1991, respondent Jesus Simangan decided to donate a kidney to his ailing cousin, Loreto Simangan, in UCLA (plaintiff), disposing as follows:
School of Medicine in Los Angeles, California, U.S.A. Upon request of UCLA, respondent undertook a series of
laboratory tests at the National Kidney Institute in Quezon City to verify whether his blood and tissue type are WHEREFORE, judgment is hereby rendered ordering the defendant to pay the plaintiff the amount of
compatible with Loreto's. 6 Fortunately, said tests proved that respondent's blood and tissue type were well- P1,000,000.00 as moral damages, the amount of P500,000.00 as exemplary damages and the amount of
matched with Loreto's. 7 P250,000.00 as attorney's fees, plus the cost of suit.29

Respondent needed to go to the United States to complete his preliminary work-up and donation surgery. Hence, The RTC explained:
to facilitate respondent's travel to the United States, UCLA wrote a letter to the American Consulate in Manila to
arrange for his visa. In due time, respondent was issued an emergency U.S. visa by the American Embassy in
Manila.8 In summarily and insolently ordering the plaintiff to disembark while the latter was already settled in his
assigned seat, the defendant violated the contract of carriage; that when the plaintiff was ordered out of
the plane under the pretext that the genuineness of his travel documents would be verified it had caused
Having obtained an emergency U.S. visa, respondent purchased a round trip plane ticket from petitioner JAL for him embarrassment and besmirched reputation; and that when the plaintiff was finally not allowed to
US$1,485.00 and was issued the corresponding boarding pass. 9 He was scheduled to a particular flight bound for take the flight, he suffered more wounded feelings and social humiliation for which the plaintiff was
Los Angeles, California, U.S.A. via Narita, Japan. 10 asking to be awarded moral and exemplary damages as well as attorney's fees.

On July 29, 1992, the date of his flight, respondent went to Ninoy Aquino International Airport in the company of The reason given by the defendant that what prompted them to investigate the genuineness of the travel
several relatives and friends.11 He was allowed to check-in at JAL's counter.12 His plane ticket, boarding pass, documents of the plaintiff was that the plaintiff was not then carrying a regular visa but just a letter does
travel authority and personal articles were subjected to rigid immigration and security routines. 13 After passing not appear satisfactory. The defendant is engaged in transporting passengers by plane from country to
through said immigration and security procedures, respondent was allowed by JAL to enter its airplane. 14 country and is therefore conversant with the travel documents. The defendant should not be allowed to
pretend, to the prejudice of the plaintiff not to know that the travel documents of the plaintiff are valid
While inside the airplane, JAL's airline crew suspected respondent of carrying a falsified travel document and documents to allow him entry in the United States.
imputed that he would only use the trip to the United States as a pretext to stay and work in Japan. 15 The
stewardess asked respondent to show his travel documents. Shortly after, the stewardess along with a Japanese and The foregoing act of the defendant in ordering the plaintiff to deplane while already settled in his
a Filipino haughtily ordered him to stand up and leave the plane. 16 Respondent protested, explaining that he was assigned seat clearly demonstrated that the defendant breached its contract of carriage with the plaintiff
as passenger in bad faith and as such the plaintiff is at bar. Questions not taken up during the trial cannot
entitled to moral and exemplary damages as well as to be raised for the first time on appeal. 40 (Underscoring
an award of attorney's fees.30 ours and citations were omitted)

Disagreeing with the RTC judgment, JAL appealed to the CA Citing Ortigas, Jr. v. Lufthansa German Airlines,41 the CA
contending that it is not guilty of breach of contract of carriage, declared that "(i)n contracts of common carriage, inattention
hence, not liable for damages. 31 It posited that it is the one and lack of care on the part of the carrier resulting in the failure
entitled to recover on its counterclaim. 32 of the passenger to be accommodated in the class contracted for
amounts to bad faith or fraud which entitles the passengers to
CA Ruling the award of moral damages in accordance with Article 2220 of
the Civil Code."42
In a Decision33 dated May 31, 2005, the CA affirmed the
decision of the RTC with modification in that it lowered the Nevertheless, the CA modified the damages awarded by the
amount of moral and exemplary damages and deleted the award RTC. It explained:
of attorney's fees. The fallo of the CA decision reads:
Fundamental in the law on damages is that one
WHEREFORE, the appealed Decision is AFFIRMED injured by a breach of a contract, or by a wrongful or
with MODIFICATION. Appellant JAPAN AIR negligent act or omission shall have a fair and just
LINES is ordered to pay appellee JESUS compensation commensurate to the loss sustained as
SIMANGAN the reduced sums, as follows: Five consequence of the defendant's act. Being
Hundred Thousand Pesos (P500,000.00) as moral discretionary on the court, the amount, however,
damages, and Two Hundred Fifty Thousand Pesos should not be palpably and scandalously excessive.
(P250,000.00) as exemplary damages. The award of
attorney's fees is hereby DELETED.34 Here, the trial court's award of P1,000,000.00 as
moral damages appears to be overblown. No other
The CA elucidated that since JAL issued to respondent a round proof of appellee's social standing, profession,
trip plane ticket for a lawful consideration, "there arose a financial capabilities was presented except that he
perfected contract between them."35 It found that respondent was single and a businessman. To Us, the sum of
was "haughtily ejected"36 by JAL and that "he was certainly 500,000.00 is just and fair. For, moral damages are
embarrassed and humiliated"37 when, in the presence of other emphatically not intended to enrich a complainant at
passengers, JAL's airline staff "shouted at him to stand up and the expense of the defendant. They are awarded only
arrogantly asked him to produce his travel papers, without the to enable the injured party to obtain means, diversion
least courtesy every human being is entitled to"; 38 and that "he or amusements that will serve to alleviate the moral
was compelled to deplane on the grounds that his papers were suffering he has undergone, by reason of the
fake."39 defendant's culpable action.

The CA ratiocinated: Moreover, the grant of P500,000.00 as exemplary


damages needs to be reduced to a reasonable level.
The award of exemplary damages is designed to
While the protection of passengers must take precedence over permit the courts to mould behavior that has socially
convenience, the implementation of security measures must be deleterious consequences and its imposition is
attended by basic courtesies. required by public policy to suppress the wanton acts
of the offender. Hence, the sum of P250,000.00 is
In fact, breach of the contract of carriage creates adequate under the circumstances.
against the carrier a presumption of liability, by a
simple proof of injury, relieving the injured passenger The award of P250,000.00 as attorney's fees lacks
of the duty to establish the fault of the carrier or of his factual basis. Appellee was definitely compelled to
employees; and placing on the carrier the burden to litigate in protecting his rights and in seeking relief
prove that it was due to an unforeseen event or to from appellant's misdeeds. Yet, the record is devoid
force majeure. of evidence to show the cost of the services of his
counsel and/or the actual expenses incurred in
That appellee possessed bogus travel documents and prosecuting his action.43 (Citations were omitted)
that he might stay illegally in Japan are allegations
without substantiation. Also, appellant's attempt to When JAL's motion for reconsideration was denied, it resorted
rebook appellee the following day was too late and to the petition at bar.
did not relieve it from liability. The damage had been
done. Besides, its belated theory of novation, i.e., that
appellant's original obligation to carry appellee to Issues
Narita and Los Angeles on July 29, 1992 was
extinguished by novation when appellant and JAL poses the following issues -
appellant agreed that appellee will instead take
appellant's flight to Narita on the following day, July I.
30, 1992, deserves little attention. It is inappropriate
WHETHER OR NOT THE COURT OF APPEALS Basically, there are three (3) issues to resolve here: (1) whether
ERRED IN RULING THAT RESPONDENT WAS or not JAL is guilty of contract of carriage; (2) whether or not
ENTITLED TO MORAL DAMAGES, respondent is entitled to moral and exemplary damages; and (3)
CONSIDERING THAT: whether or not JAL is entitled to its counterclaim for damages.

A. JAL WAS NOT GUILTY OF BREACH Our Ruling


OF CONTRACT.
This Court is not a trier of facts.
B. MORAL DAMAGES MAY BE
AWARDED IN BREACH OF CONTRACT Chiefly, the issues are factual. The RTC findings of facts were
CASES ONLY WHEN THE BREACH IS affirmed by the CA. The CA also gave its nod to the reasoning
ATTENDED BY FRAUD OR BAD of the RTC except as to the awards of damages, which were
FAITH. ASSUMING ARGUENDO THAT reduced, and that of attorney's fees, which was deleted.
JAL WAS GUILTY OF BREACH, JAL
DID NOT ACT FRAUDULENTLY OR IN
BAD FAITH AS TO ENTITLE We are not a trier of facts. We generally rely upon, and are
RESPONDENT TO MORAL DAMAGES. bound by, the conclusions on this matter of the lower courts,
which are better equipped and have better opportunity to assess
the evidence first-hand, including the testimony of the
C. THE LAW DISTINGUISHES A witnesses.45
CONTRACTUAL BREACH EFFECTED
IN GOOD FAITH FROM ONE
ATTENDED BY BAD FAITH. We have repeatedly held that the findings of fact of the CA are
final and conclusive and cannot be reviewed on appeal to the
Supreme Court provided they are based on substantial
II. evidence.46 We have no jurisdiction, as a rule, to reverse their
findings.47 Among the exceptions to this rule are: (a) when the
WHETHER OR NOT THE COURT OF APPEALS conclusion is a finding grounded entirely on speculations,
ERRED IN RULING THAT RESPONDENT WAS surmises or conjectures; (b) when the inference made is
ENTITLED TO EXEMPLARY DAMAGES manifestly mistaken, absurd or impossible; (c) where there is
CONSIDERING THAT: grave abuse of discretion; (d) when the judgment is based on a
misapprehension of facts; (e) when the findings of facts are
A. EXEMPLARY DAMAGES ARE NOT conflicting; (f) when the CA, in making its findings, went
RECOVERABLE IN BREACH OF beyond the issues of the case and the same is contrary to the
CONTRACT OF CARRIAGE UNLESS admissions of both appellant and appellee.48
THE CARRIER IS GUILTY OF
WANTON, FRAUDULENT, RECKLESS, The said exceptions, which are being invoked by JAL, are not
OPPRESSIVE OR MALEVOLENT found here. There is no indication that the findings of the CA
CONDUCT. are contrary to the evidence on record or that vital testimonies
of JAL's witnesses were disregarded. Neither did the CA
B. ASSUMING ARGUENDO THAT JAL commit misapprehension of facts nor did it fail to consider
WAS GUILTY OF BREACH, JAL DID relevant facts. Likewise, there was no grave abuse of discretion
NOT ACT IN A WANTON in the appreciation of facts or mistaken and absurd inferences.
FRAUDULENT, RECKLESS,
OPPRESSIVE OR MALEVOLENT We thus sustain the coherent facts as established by the courts
MANNER AS TO ENTITLE below, there being no sufficient showing that the said courts
RESPONDENT TO EXEMPLARY committed reversible error in reaching their conclusions.
DAMAGES.
JAL is guilty of breach of
III. contract of carriage.

ASSUMING ARGUENDO THAT RESPONDENT That respondent purchased a round trip plane ticket from JAL
WAS ENTITLED TO AN AWARD OF DAMAGES, and was issued the corresponding boarding pass is
WHETHER OR NOT THE COURT OF APPEALS uncontroverted.49 His plane ticket, boarding pass, travel
AWARD OF P750,000 IN DAMAGES WAS authority and personal articles were subjected to rigid
EXCESSIVE AND UNPRECEDENTED. immigration and security procedure. 50 After passing through
said immigration and security procedure, he was allowed by
IV. JAL to enter its airplane to fly to Los Angeles, California,
U.S.A. via Narita, Japan.51 Concisely, there was a contract of
carriage between JAL and respondent.
WHETHER OR NOT THE COURT OF APPEALS
ERRED IN NOT FINDING FOR JAL ON ITS
COUNTERCLAIM.44 (Underscoring Ours)
Nevertheless, JAL made respondent get off the plane on his failure to carry the passenger safely to his destination. 63
scheduled departure on July 29, 1992. He was not allowed by Respondent has complied with these twin requisites.
JAL to fly. JAL thus failed to comply with its obligation under
the contract of carriage. Respondent is entitled to moral and exemplary damages and
attorney's fees plus legal interest.
JAL justifies its action by arguing that there was "a need to
verify the authenticity of respondent's travel document." 52 It With reference to moral damages, JAL alleged that they are not
alleged that no one from its airport staff had encountered a recoverable in actions ex contractu except only when the breach
parole visa before.53 It further contended that respondent agreed is attended by fraud or bad faith. It is contended that it did not
to fly the next day so that it could first verify his travel act fraudulently or in bad faith towards respondent, hence, it
document, hence, there was novation. 54 It maintained that it was may not be held liable for moral damages.
not guilty of breach of contract of carriage as respondent was
not able to travel to the United States due to his own voluntary
desistance.55 As a general rule, moral damages are not recoverable in actions
for damages predicated on a breach of contract for it is not one
of the items enumerated under Article 2219 of the Civil Code. 64
We cannot agree. JAL did not allow respondent to fly. It As an exception, such damages are recoverable: (1) in cases in
informed respondent that there was a need to first check the which the mishap results in the death of a passenger, as
authenticity of his travel documents with the U.S. Embassy. 56 provided in Article 1764, in relation to Article 2206(3) of the
As admitted by JAL, "the flight could not wait for Mr. Civil Code; and (2) in the cases in which the carrier is guilty of
Simangan because it was ready to depart."57 fraud or bad faith, as provided in Article 2220.65

Since JAL definitely declared that the flight could not wait for The acts committed by JAL against respondent amounts to bad
respondent, it gave respondent no choice but to be left behind. faith. As found by the RTC, JAL breached its contract of
The latter was unceremoniously bumped off despite his carriage with respondent in bad faith. JAL personnel summarily
protestations and valid travel documents and notwithstanding and insolently ordered respondent to disembark while the latter
his contract of carriage with JAL. Damage had already been was already settled in his assigned seat. He was ordered out of
done when respondent was offered to fly the next day on July the plane under the alleged reason that the genuineness of his
30, 1992. Said offer did not cure JAL's default. travel documents should be verified.

Considering that respondent was forced to get out of the plane These findings of facts were upheld by the CA, to wit:
and left behind against his will, he could not have freely
consented to be rebooked the next day. In short, he did not
agree to the alleged novation. Since novation implies a waiver x x x he was haughtily ejected by appellant. He was
of the right the creditor had before the novation, such waiver certainly embarrassed and humiliated when, in the
must be express.58 It cannot be supposed, without clear proof, presence of other passengers, the appellant's airline
that respondent had willingly done away with his right to fly on staff shouted at him to stand up and arrogantly asked
July 29, 1992. him to produce his travel papers, without the least
courtesy every human being is entitled to. Then, he
was compelled to deplane on the grounds that his
Moreover, the reason behind the bumping off incident, as found papers were fake. His protestation of having been
by the RTC and CA, was that JAL personnel imputed that issued a U.S. visa coupled with his plea to appellant
respondent would only use the trip to the United States as a to closely monitor his movements when the aircraft
pretext to stay and work in Japan.59 stops over in Narita, were ignored. Worse, he was
made to wait for many hours at the office of appellant
Apart from the fact that respondent's plane ticket, boarding only to be told later that he has valid travel
pass, travel authority and personal articles already passed the documents.66 (Underscoring ours)
rigid immigration and security routines, 60 JAL, as a common
carrier, ought to know the kind of valid travel documents Clearly, JAL is liable for moral damages. It is firmly settled that
respondent carried. As provided in Article 1755 of the New moral damages are recoverable in suits predicated on breach of
Civil Code: "A common carrier is bound to carry the passengers a contract of carriage where it is proved that the carrier was
safely as far as human care and foresight can provide, using the guilty of fraud or bad faith, as in this case. Inattention to and
utmost diligence of very cautious persons, with a due regard for lack of care for the interests of its passengers who are entitled
all the circumstances."61 Thus, We find untenable JAL's defense to its utmost consideration, particularly as to their convenience,
of "verification of respondent's documents" in its breach of amount to bad faith which entitles the passenger to an award of
contract of carriage. moral damages. What the law considers as bad faith which may
furnish the ground for an award of moral damages would be
It bears repeating that the power to admit or not an alien into bad faith in securing the contract and in the execution thereof,
the country is a sovereign act which cannot be interfered with as well as in the enforcement of its terms, or any other kind of
even by JAL.62 deceit.67

In an action for breach of contract of carriage, all that is JAL is also liable for exemplary damages as its above-
required of plaintiff is to prove the existence of such contract mentioned acts constitute wanton, oppressive and malevolent
and its non-performance by the carrier through the latter's acts against respondent. Exemplary damages, which are
awarded by way of example or correction for the public good, damages are awarded and whenever the court deems it just and
may be recovered in contractual obligations, as in this case, if equitable,75 as in this case.
defendant acted in wanton, fraudulent, reckless, oppressive, or
malevolent manner.68 Considering the factual backdrop of this case, attorney's fees in
the amount of P200,000.00 is reasonably modest.
Exemplary damages are designed by our civil law to permit the
courts to reshape behaviour that is socially deleterious in its The above liabilities of JAL in the total amount of P800,000.00
consequence by creating negative incentives or deterrents earn legal interest pursuant to the Court's ruling in Construction
against such behaviour. In requiring compliance with the Development Corporation of the Philippines v. Estrella,76 citing
standard of extraordinary diligence, a standard which is, in fact, Eastern Shipping Lines, Inc. v. Court of Appeals,77 to wit:
that of the highest possible degree of diligence, from common
carriers and in creating a presumption of negligence against
them, the law seeks to compel them to control their employees, Regarding the imposition of legal interest at the rate
to tame their reckless instincts and to force them to take of 6% from the time of the filing of the complaint, we
adequate care of human beings and their property.69 held in Eastern Shipping Lines, Inc. v. Court of
Appeals, that when an obligation, regardless of its
source, i.e., law, contracts, quasi-contracts, delicts or
Neglect or malfeasance of the carrier's employees could give quasi-delicts is breached, the contravenor can be held
ground for an action for damages. Passengers have a right to be liable for payment of interest in the concept of actual
treated by the carrier's employees with kindness, respect, and compensatory damages, subject to the following
courtesy and due consideration and are entitled to be protected rules, to wit -
against personal misconduct, injurious language, indignities and
abuses from such employees.70
1. When the obligation is breached, and it
consists in the payment of a sum of money,
The assessment of P500,000.00 as moral damages and i.e., a loan or forbearance of money, the
P100,000.00 as exemplary damages in respondent's favor is, in interest due should be that which may have
Our view, reasonable and realistic. This award is reasonably been stipulated in writing. Furthermore, the
sufficient to indemnify him for the humiliation and interest due shall itself earn legal interest
embarrassment he suffered. This also serves as an example to from the time it is judicially demanded. In
discourage the repetition of similar oppressive acts. the absence of stipulation, the rate of
interest shall be 12% per annum to be
With respect to attorney's fees, they may be awarded when computed from default, i.e., from judicial or
defendant's act or omission has compelled plaintiff to litigate extrajudicial demand under and subject to
with third persons or to incur expenses to protect his interest. 71 the provisions of Article 1169 of the Civil
The Court, in Construction Development Corporation of the Code.
Philippines v. Estrella,72 citing Traders Royal Bank Employees
Union-Independent v. National Labor Relations Commission,73 2. When an obligation, not constituting a
elucidated thus: loan or forbearance of money, is breached,
an interest on the amount of damages
There are two commonly accepted concepts of awarded may be imposed at the discretion
attorney's fees, the so-called ordinary and of the court at the rate of 6% per annum.
extraordinary. In its ordinary concept, an attorney's No interest, however, shall be adjudged on
fee is the reasonable compensation paid to a lawyer unliquidated claims or damages except
by his client for the legal services he has rendered to when or until the demand can be
the latter. The basis of this compensation is the fact of established with reasonable certainty.
his employment by and his agreement with the client. Accordingly, where the demand is
established with reasonable certainty, the
In its extraordinary concept, an attorney's fee is interest shall begin to run from the time the
an indemnity for damages ordered by the court to claim is made judicially or extrajudicially
be paid by the losing party in a litigation. The basis (Art. 1169, Civil Code) but when such
of this is any of the cases provided by law where such certainty cannot be so reasonably
award can be made, such as those authorized in established at the time the demand is made,
Article 2208, Civil Code, and is payable not to the the interest shall begin to run only from
lawyer but to the client, unless they have agreed the date the judgment of the court is
that the award shall pertain to the lawyer as made (at which time the quantification of
additional compensation or as part thereof.74 damages may be deemed to have been
reasonably ascertained). The actual base
for the computation of legal interest shall,
It was therefore erroneous for the CA to delete the award of in any case, be on the amount finally
attorney's fees on the ground that the record is devoid of adjudged.
evidence to show the cost of the services of respondent's
counsel. The amount is actually discretionary upon the Court so
long as it passes the test of reasonableness. They may be 3. When the judgment of the court
recovered as actual or compensatory damages when exemplary awarding a sum of money becomes final
and executory, the rate of legal interest,
whether the case falls under paragraph 1 public, its bumping off of respondent without a valid reason
or paragraph 2, above, shall be 12% per naturally drew public attention and generated a public issue.
annum from such finality until its
satisfaction, this interim period being The publications involved matters about which the public has
deemed to be by then an equivalent to a the right to be informed because they relate to a public issue.
forbearance of credit.78 (Emphasis This public issue or concern is a legitimate topic of a public
supplied and citations omitted) comment that may be validly published.

Accordingly, in addition to the said total amount of Assuming that respondent, indeed, caused the publication of his
P800,000.00, JAL is liable to pay respondent legal interest. complaint, he may not be held liable for damages for it. The
Pursuant to the above ruling of the Court, the legal interest is constitutional guarantee of freedom of the speech and of the
6% and it shall be reckoned from September 21, 2000 when the press includes fair commentaries on matters of public interest.
RTC rendered its judgment. From the time this Decision This is explained by the Court in Borjal v. Court of Appeals,85 to
becomes final and executory, the interest rate shall be 12% until wit:
its satisfaction.
To reiterate, fair commentaries on matters of public
JAL is not entitled to its counterclaim for damages. interest are privileged and constitute a valid defense
in an action for libel or slander. The doctrine of fair
The counterclaim of JAL in its Answer 79 is a compulsory comment means that while in general every
counterclaim for damages and attorney's fees arising from the discreditable imputation publicly made is deemed
filing of the complaint. There is no mention of any other false, because every man is presumed innocent until
counter claims. his guilt is judicially proved, and every false
imputation is deemed malicious, nevertheless, when
This compulsory counterclaim of JAL arising from the filing of the discreditable imputation is directed against a
the complaint may not be granted inasmuch as the complaint public person in his public capacity, it is not
against it is obviously not malicious or unfounded. It was filed necessarily actionable. In order that such discreditable
by respondent precisely to claim his right to damages against imputation to a public official may be actionable, it
JAL. Well-settled is the rule that the commencement of an must either be a false allegation of fact or a comment
action does not per se make the action wrongful and subject the based on a false supposition. If the comment is an
action to damages, for the law could not have meant to impose expression of opinion, based on established facts,
a penalty on the right to litigate.80 then it is immaterial that the opinion happens to be
mistaken, as long as it might reasonably be inferred
from the facts.86 (Citations omitted and underscoring
We reiterate case law that if damages result from a party's ours)
exercise of a right, it is damnum absque injuria.81 Lawful acts
give rise to no injury. Walang perhuwisyong maaring idulot
ang paggamit sa sariling karapatan. Even though JAL is not a public official, the rule on privileged
commentaries on matters of public interest applies to it. The
privilege applies not only to public officials but extends to a
During the trial, however, JAL presented a witness who great variety of subjects, and includes matters of public
testified that JAL suffered further damages. Allegedly, concern, public men, and candidates for office. 87
respondent caused the publications of his subject complaint
against JAL in the newspaper for which JAL suffered
damages.82 Hence, pursuant to the Borjal case, there must be an actual
malice in order that a discreditable imputation to a public
person in his public capacity or to a public official may be
Although these additional damages allegedly suffered by JAL actionable. To be considered malicious, the libelous statements
were not incorporated in its Answer as they arose subsequent to must be shown to have been written or published with the
its filing, JAL's witness was able to testify on the same before knowledge that they are false or in reckless disregard of
the RTC.83 Hence, although these issues were not raised by the whether they are false or not.88
pleadings, they shall be treated in all respects as if they had
been raised in the pleadings.
Considering that the published articles involve matters of public
interest and that its expressed opinion is not malicious but
As provided in Section 5, Rule 10 of the Rules of Court, based on established facts, the imputations against JAL are not
"(w)hen issues not raised by the pleadings are tried with the actionable. Therefore, JAL may not claim damages for them.
express or implied consent of the parties, they shall be treated
in all respects as if they had been raised in the pleadings."
WHEREFORE, the petition is DENIED. The appealed
Decision of the Court of Appeals is AFFIRMED WITH
Nevertheless, JAL's counterclaim cannot be granted. MODIFICATION. As modified, petitioner Japan Airlines is
ordered to pay respondent Jesus Simangan the following: (1)
JAL is a common carrier. JAL's business is mainly with the P500,000.00 as moral damages; (2) P100,000.00 as exemplary
traveling public. It invites people to avail themselves of the damages; and (3) P200,000.00 as attorney's fees.
comforts and advantages it offers.84 Since JAL deals with the
The total amount adjudged shall earn legal interest at the rate of Upon the completion of MPT's structural works, respondent
6% per annum from the date of judgment of the Regional Trial awarded the P130,000,000 contract for the tower's architectural
Court on September 21, 2000 until the finality of this Decision. works8[8] (project) to petitioner. Thus, on January 31, 1994, the
From the time this Decision becomes final and executory, the parties executed a supplemental agreement. 9[9] The salient
unpaid amount, if any, shall earn legal interest at the rate of portions thereof were:
12% per annum until its satisfaction.
1. the [project] shall cover the scope of work of the
SO ORDERED. detailed construction bid plans and specifications and bid
documents dated 28 September 1993, attached and forming an
integral part hereof as Annex A.
TITAN-IKEDA CONSTRUCTION G.R. No. 158768
& DEVELOPMENT 2. the contract price for the said works shall be P130
CORPORATION, million.
Petitioner,
Present: 3. the payment terms shall be full swapping or full
payment in condominium units. The condominium units
earmarked for the [petitioner] are shown in the attached Annex
PUNO, C.J., Chairperson, B.

SANDOVAL-GUTIERREZ, 4. the [respondent] shall transfer and surrender to


-v e r s u s- [petitioner] the condominium units abovestated in accordance
CORONA, with the following schedule:

AZCUNA and (a) 80% of units upon posting and acceptance by


LEONARDO-DE CASTRO, JJ. [respondent] of the performance bond [and]

(b) 20% or remaining balance upon completion of the


PRIMETOWN PROPERTY project as provided in the construction contract and
GROUP, INC., simultaneous with the posting by [petitioner] of the
Respondent. reglementary guarantee bond.
Promulgated:
5. the contract period shall be fifteen (15) months
reckoned from the release of the condominium certificates of
February 12, 2008 title (CCTs) covering eighty percent (80%) of the units
transferable to [petitioner] as aforesaid[.]

x------------------------------------------- Significantly, the supplemental agreement adopted those


-------x provisions of the construction contract which it did not
specifically discuss or provide for.10[10] Among those carried
DECISION over was the designation of GEMM Construction Corporation
(GEMM) as the project's construction manager.11[11]
CORONA, J.:
Petitioner started working on the project in February 1994.

This petition for review on certiorari 1[1] seeks to set On June 30, 1994, respondent executed a deed of
aside the decision of the Court of Appeals (CA) in CA-G.R. CV sale12[12] (covering 114 condominium units and 20 parking
No. 613532[2] and its resolution3[3] denying reconsideration. slots of the MPT collectively valued by the parties at
P112,416,716.88)13[13] in favor of petitioner pursuant to the
In 1992, respondent Primetown Property Group, Inc. awarded full-swapping payment provision of the supplemental
the contract for the structural works 4[4] of its 32-storey Makati agreement.
Prime Tower (MPT) to petitioner Titan-Ikeda Construction and
Development Corporation.5[5] The parties formalized their Shortly thereafter, petitioner sold some of its units to third
agreement in a construction contract6[6] dated February 4, persons.14[14]
1993.7[7]
In September 1995, respondent engaged the services of
Integratech, Inc. (ITI), an engineering consultancy firm, to

1 8
2 9
3 10
4 11
5 12
6 13
7 14
evaluate the progress of the project. 15[15] In its September 7,
1995 report,16[16] ITI informed respondent that petitioner, at On February 19, 1996, petitioner sent a second letter to
that point, had only accomplished 31.89% of the project (or was respondent demanding P2,023,876.25. This new figure included
11 months and six days behind schedule).17[17] the cost of materials (P244,331.40) petitioner advanced from
December 5, 1995 to January 26, 1996.26[26]
Meanwhile, petitioner and respondent were discussing the On November 22, 1996, petitioner demanded from respondent
possibility of the latters take over of the projects supervision. the delivery of MPT's management certificate 27[27] and the
Despite ongoing negotiations, respondent did not obtain keys to the condominium units and the payment of its
petitioners consent in hiring ITI as the projects construction (respondent's) balance.28[28]
manager. Neither did it inform petitioner of ITIs September 7,
1995 report. Because respondent ignored petitioner's demand, petitioner, on
December 9, 1996, filed a complaint for specific
On October 12, 1995, petitioner sought to confirm performance29[29] in the Housing and Land Use Regulatory
respondent's plan to take over the project.18[18] Its letter stated: Board (HLURB).

The mutual agreement arrived at sometime in the last While the complaint for specific performance was pending in
week of August 1995 for [respondent] to take over the the HLURB, respondent sent a demand letter to petitioner
construction supervision of the balance of the [project] from asking it to reimburse the actual costs incurred in finishing the
[petitioner's] [e]ngineering staff and complete [the] same by project (or P69,785,923.47).30[30] In view of the pendency of
December 31, 1995 as promised by [petitioner's] engineer. the HLURB case, petitioner did not heed respondent's demands.

The [petitioner's] accomplished works as of this date On April 29, 1997, the HLURB rendered a decision in favor of
of [t]ake over is of acceptable quality in materials and petitioner.31[31] It ruled that the instrument executed on June
workmanship. 30, 1994 was a deed of absolute sale because the conveyance of
the condominium units and parking slots was not subject to any
This mutual agreement on the take over should condition.32[32] Thus, it ordered respondent to issue MPTs
not be misconstrued in any other way except that the take management certificate and to deliver the keys to the
over is part of the long range plan of [respondent] that condominium units to petitioner.33[33] Respondent did not
[petitioner], in the spirit of cooperation, agreed to hand over the appeal this decision. Consequently, a writ of execution was
construction supervision to [respondent] as requested. issued upon its finality.34[34]
(emphasis supplied)19[19]
Undaunted by the finality of the HLURB decision, respondent
filed a complaint for collection of sum of money 35[35] against
Engineers Antonio Co, general construction manager of petitioner in the Regional Trial Court (RTC) of Makati City,
respondent, and Luzon Y. Tablante, project manager of Branch 58 on July 2, 1997. It prayed for the reimbursement of
petitioner, signed the letter. the value of the projects unfinished portion amounting to
P66,677,000.36[36]

Integratechs (ITIs) Report During trial, the RTC found that because respondent modified
the MPT's architectural design, petitioner had to adjust the
In its September 7, 1995 report, ITI estimated that petitioner scope of work.37[37] Moreover, respondent belatedly informed
should have accomplished 48.71% of the project as of the petitioner of those modifications. It also failed to deliver the
October 12, 1995 takeover date.20[20] Petitioner repudiated this concrete mix and rebars according to schedule. For this reason,
figure21[21] but qualifiedly admitted that it did not finish the petitioner was not responsible for the project's delay. 38[38] The
project.22[22] Records showed that respondent did not merely trial court thus allowed petitioner to set-off respondent's other
take over the supervision of the project but took full control outstanding liabilities with respondents excess payment in the
thereof.23[23] project.39[39] It concluded that respondent owed petitioner

Petitioner consequently conducted an inventory.24[24] On the 26


basis thereof, petitioner demanded from respondent the 27
payment of its balance amounting to P1,779,744.85.25[25]
28
15 29
16 30
17 31
18 32
19 33
20 34
21 35
22 36
23 37
24 38
25 39
P2,023,876.25.40[40] In addition, because respondent refused to Petitioner moved for reconsideration but it was denied. Hence,
deliver the keys to the condominium units and the management this petition.
certificate to petitioner, the RTC found that petitioner lost rental
income amounting to US$1,665,260.41[41] The dispositive Petitioner contends that the CA erred in giving weight
portion of the RTC decision stated: to ITI's report because the project evaluation was commissioned
only by respondent,47[47] in disregard of industry practice.
WHEREFORE, PREMISES CONSIDERED, judgment is Project evaluations are agreed upon by the parties and
hereby rendered dismissing [respondent's] [c]omplaint for lack conducted by a disinterested third party.48[48]
of merit. On the other hand, finding preponderance of evidence
to sustain [petitioner's] counterclaim, judgment is hereby We grant the petition.
rendered in favor of [petitioner] ordering [respondent] to pay
the former:

1. The unpaid balance of the consideration for Review of Conflicting Factual Findings
[petitioner's] services in [the project] in the amount of
P2,023,867.25 with legal interest from the date of demand until
fully paid; As a general rule, only questions of law may be raised
in a petition for review on certiorari. Factual issues are
2. Compensatory damages in the amount of entertained only in exceptional cases such as where the findings
US$1,665,260 or its peso equivalent at the current foreign of fact of the CA and the trial court are conflicting. 49[49]
exchange rate representing lost rental income due only as of
July 1997 and the accrued lost earnings from then on until the Here, a glaring contradiction exists between the factual findings
date of actual payment, with legal interest from the date of of the RTC and the CA. The trial court found that respondent
demand until fully paid; and contributed to the project's delay because it belatedly
communicated the modifications and failed to deliver the
3. Attorney's fees in the amount of P100,000 as necessary materials on time. The CA, however, found that
acceptance fee, P1,000 appearance fee per hearing and 25% of petitioner incurred delay in the performance of its obligation. It
the total amount awarded to [petitioner]. relied on ITI's report which stated that petitioner had
accomplished only 48.71% of the project as of October 12,
With costs against the [respondent]. 1995.

SO ORDERED.42[42]

Respondent appealed the RTC decision to the CA. 43[43] The January 31, 1994 Supplemental Agreement Was
appellate court found that respondent fully performed its Extinguished
obligation when it executed the June 30, 1994 deed of absolute
sale in favor of petitioner.44[44] Moreover, ITI's report clearly
established that petitioner had completed only 48.71% of the A contract is a meeting of the minds between two
project as of October 12, 1995, the takeover date. Not only did persons whereby one binds himself, with respect to the other, to
it incur delay in the performance of its obligation but petitioner give something or to render some service. 50[50] This case
also failed to finish the project. The CA ruled that respondent involved two contracts entered into by the parties with regard to
was entitled to recover the value of the unfinished portion of the the project.
project under the principle of unjust enrichment. 45[45] Thus:
The parties first entered into a contract for a piece of work 51[51]
WHEREFORE, the appealed decision is when they executed the supplemental agreement. Petitioner as
REVERSED and a new one entered dismissing [petitioner's] contractor bound itself to execute the project for respondent, the
counterclaims of P2,023,867.25 representing unpaid balance for owner/developer, in consideration of a price certain
[its] services in [the project]; US$1,665,260 as accrued lost (P130,000,000). The supplemental agreement was reciprocal in
earnings, and attorney's fees. [Petitioner] is hereby ordered to nature because the obligation of respondent to pay the entire
return to [respondent] the amount of P66,677,000 representing contract price depended on the obligation of petitioner to
the value of unfinished [portion of the project], plus legal complete the project (and vice versa).
interest thereon until fully paid. Upon payment by [petitioner]
of the aforementioned amount, [respondent] is hereby ordered Thereafter, the parties entered into a second contract. They
to deliver the keys and [m]anagement [c]ertificate of the agreed to extinguish the supplemental agreement as evidenced
[Makati Prime Tower] paid to [petitioner] as consideration for by the October 12, 1995 letter-agreement which was duly
the [project].46[46] acknowledged by their respective representatives. 52[52]

46
40 47
41 48
42 49
43 50
44 51
45 52
In this instance, respondent paid part of the contract price under
While the October 12, 1995 letter-agreement stated that the assumption that petitioner would complete the project
respondent was to take over merely the supervision of the within the stipulated period. However, after the supplemental
project, it actually took over the whole project itself. In fact, agreement was extinguished, petitioner ceased working on the
respondent subsequently hired two contractors in petitioner's project. Therefore, the compensation petitioner received in
stead.53[53] Moreover, petitioner's project engineer at site only excess of the cost of its actual accomplishment as of October
monitored the progress of architectural works undertaken in its 12, 1995 was never due. The condominium units and parking
condominium units.54[54] Petitioner never objected to this slots corresponding to the said excess were mistakenly
arrangement; hence, it voluntarily surrendered its participation delivered by respondent and were therefore not due to
in the project. Moreover, it judicially admitted in its answer that petitioner.
respondent took over the entire project, not merely its
supervision, pursuant to its (respondents) long-range plans. 55 Stated simply, respondent erroneously delivered
[55] excess units to petitioner and the latter, pursuant to Article
2154, was obliged to the return them to respondent. 58[58]
Because the parties agreed to extinguish the supplemental Article 2160 of the Civil Code provides:
agreement, they were no longer required to fully perform their
respective obligations. Petitioner was relieved of its obligation Article 2160. He who in good faith accepts an undue payment
to complete the project while respondent was freed of its of a thing certain and determinate shall only be responsible for
obligation to pay the entire contract price. However, the impairment or loss of the same or its accessories and
respondent, by executing the June 30, 1994 deed of absolute accessions insofar as he has thereby been benefited. If he has
sale, was deemed to have paid P112,416,716.88. Nevertheless, alienated it, he shall return the price or assign the action to
because petitioner applied part of what it received to collect the sum.
respondents outstanding liabilities, 56[56] it admitted
overpayment.
Because petitioner acknowledged that it had been overpaid, it One who receives payment by mistake in good faith is, as a
was obliged to return the excess to respondent. Embodying the general rule, only liable to return the thing delivered. 59[59] If he
principle of solutio indebiti, Article 2154 of the Civil Code benefited therefrom, he is also liable for the impairment or loss
provides: of the thing delivered and its accessories and accessions. 60[60]
If he sold the thing delivered, he should either deliver the
Article 2154. If something is received when there is no right to proceeds of the sale or assign the action to collect to the other
demand it and it was unduly delivered through mistake, the party.61[61]
obligation to return it arises.
The situation is, however, complicated by the following facts:
a) the basis of the valuation (P112,416,716.99) of the
condominium units and parking slots covered by the June 30,
For the extra-contractual obligation of solutio indebiti to arise, 1994 deed of sale is unknown;
the following requisites must be proven:
b) the percentage of petitioner's actual accomplishment in the
1. the absence of a right to collect the excess sums and project has not been determined and

2. the payment was made by mistake.57[57] c) the records of this case do not show the actual number of
condominium units and parking slots sold by petitioners.
With regard to the first requisite, because the supplemental Because this Court is not a trier of facts, the determination of
agreement had been extinguished by the mutual agreement of these matters should be remanded to the RTC for reception of
the parties, petitioner became entitled only to the cost of further evidence.
services it actually rendered (i.e., that fraction of the project
cost in proportion to the percentage of its actual The RTC must first determine the percentage of the
accomplishment in the project). It was not entitled to the excess project petitioner actually completed and its proportionate
(or extent of overpayment). cost.62[62] This will be the amount due to petitioner. Thereafter,
based on the stipulated valuation in the June 30, 1994 deed of
On the second requisite, Article 2163 of the Civil sale, the RTC shall determine how many condominium units
Code provides: and parking slots correspond to the amount due to petitioner. It
will only be the management certificate and the keys to these
Article 2163. It is presumed that there was a mistake in the units that petitioner will be entitled to. The remaining units,
payment if something which had never been due or had having been mistakenly delivered by respondent, will therefore
already been paid was delivered; but, he from whom the return be the subject of solutio indebiti.
is claimed may prove that the delivery was made out of
liberality or for any other just cause. (emphasis supplied)

53 58
54 59
55 60
56 61
57 62
What exactly must petitioner give back to respondent? Under Recovery Of Additional Costs Resulting From Changes
Article 2160 in relation to Article 2154, it should return to
respondent the condominium units and parking slots in excess
of the value of its actual accomplishment (i.e., the amount due The supplemental agreement was a contract for a
to it) as of October 12, 1995. If these properties include units stipulated price.68[68] In such contracts, the recovery of
and/or slots already sold to third persons, petitioner shall additional costs (incurred due to changes in plans or
deliver the proceeds of the sale thereof or assign the actions for specifications) is governed by Article 1724 of the Civil Code.
collection to respondent as required by Article 2160.
Delay In The Completion Of The Project Article 1724. The contractor who undertakes to build a structure
or any other work for a stipulated price, in conformity with
plans and specifications agreed upon with the landowner, can
Mora or delay is the failure to perform the obligation neither withdraw from the contract nor demand an increase in
in due time because of dolo (malice) or culpa (negligence).63 the price on account of higher cost of labor or materials, save
[63] A debtor is deemed to have violated his obligation to the when there has been a change in plans and specifications,
creditor from the time the latter makes a demand. Once the provided:
creditor makes a demand, the debtor incurs mora or delay.64[64]
1. such change has been authorized by the proprietor in
The construction contract65[65] provided a procedure for writing; and
protesting delay:
Article XIV 2. the additional price to be paid to the contractor has been
DELAYS AND ABANDONMENT determined in writing by both parties.

15.1. If at any time during the effectivity of this contract, In Powton Conglomerate, Inc. v. Agcolicol, 69[69] we
[PETITIONER] shall incur unreasonable delay or slippages reiterated that a claim for the cost of additional work arising
of more than fifteen percent (15%) of the scheduled work from changes in the scope of work can only be allowed upon
program, [RESPONDENT] should notify [PETITIONER] the:
in writing to accelerate the work and reduce, if not erase,
slippage. If after the lapse of sixty (60) days from receipt of 1. written authority from the developer/owner
such notice, [PETITIONER] fails to rectify the delay or ordering/allowing the changes in work; and
slippage, [RESPONDENT] shall have the right to terminate this
contract except in cases where the same was caused by force 2. written agreement of parties with regard to the increase in
majeure. FORCE MAJEURE as contemplated herein, and in cost (or price) due to the change in work or design
determination of delay includes, but is not limited to, typhoon, modification. 70[70]
flood, earthquake, coup d'etat, rebellion, sedition, transport
strike, stoppage of work, mass public action that prevents Furthermore:
workers from reporting for work, and such other causes beyond
[PETITIONER'S] control.66[66] (emphasis supplied) Compliance with the two requisites of Article 1724, a
specific provision governing additional works, is a condition
xxx xxx xxx precedent of the recovery. The absence of one or the other
bars the recovery of additional costs. Neither the authority for
Respondent never sent petitioner a written demand the changes made nor the additional price to be paid therefor
asking it to accelerate work on the project and reduce, if not may be proved by any other evidence for purposes of
eliminate, slippage. If delay had truly been the reason why recovery.71[71] (emphasis supplied)
respondent took over the project, it would have sent a written
demand as required by the construction contract. Moreover, Petitioner submitted neither one. In addition, petitioners project
according to the October 12, 1995 letter-agreement, respondent coordinator Estellita Garcia testified that respondent never
took over the project for the sole reason that such move was approved any change order.72[72] Thus, under Article 1724 and
part of its (respondent's) long-term plan. pursuant to our ruling in Powton Conglomerate, Inc., petitioner
cannot recover the cost it incurred in effecting the design
Respondent, on the other hand, relied on ITI's modifications. A contractor who fails to secure the owner or
September 7, 1995 report. The construction contract named developer's written authority to changes in the work or written
GEMM, not ITI, as construction manager.67[67] Because assent to the additional cost to be incurred cannot invoke the
petitioner did not consent to the change of the designated principle of unjust enrichment.73[73]
construction manager, ITI's September 7, 1995 report could not Recovery Of Compensatory Damages
bind it.

In view of the foregoing, we hold that petitioner did not incur


delay in the performance of its obligation.
68
63 69
64 70
65 71
66 72
67 73
Indemnification for damages comprehends not only the loss
suffered (actual damages or damnum emergens) but also the 2. the computation of petitioner Titan-Ikeda
claimant's lost profits (compensatory damages or lucrum Construction and Development Corporation's actual liability to
cessans). For compensatory damages to be awarded, it is respondent Primetown Property Group, Inc. or vice-versa, and
necessary to prove the actual amount of the alleged loss by the determination of imposable interests and/or penalties, if any.
preponderance of evidence.74[74]
G.R. No. 73867 February 29, 1988
The RTC awarded compensatory damages based on the rental
pool rates submitted by petitioner 75[75] and on the premise that TELEFAST COMMUNICATIONS/PHILIPPINE
all those units would have been leased had respondent only WIRELESS, INC., petitioner,
finished the project by December 31, 1995. 76[76] However, vs.
other than bare assertions, petitioner submitted no proof that the IGNACIO CASTRO, SR., SOFIA C. CROUCH, IGNACIO
rental pool was in fact able to lease out the units. We thus hold CASTRO JR., AURORA CASTRO, SALVADOR CASTRO,
that the losses sustained by petitioner were merely speculative MARIO CASTRO, CONRADO CASTRO, ESMERALDA
and there was no basis for the award. C. FLORO, AGERICO CASTRO, ROLANDO CASTRO,
VIRGILIO CASTRO AND GLORIA CASTRO, and
HONORABLE INTERMEDIATE APPELLATE COURT,
Remand Of Other Claims respondents.

Since respondent did not repudiate petitioner's other claims


stated in the inventory77[77] in the RTC and CA, it is estopped
from questioning the validity thereof. 78[78] However, because PADILLA, J.:
some of petitioner's claims have been disallowed, we remand
the records of this case to the RTC for the computation of Petition for review on certiorari of the decision * of the
respondent's liability.79[79] Intermediate Appellate Court, dated 11 February 1986, in AC-
G.R. No. CV-70245, entitled "Ignacio Castro, Sr., et al.,
WHEREFORE, the petition is hereby GRANTED. Plaintiffs-Appellees, versus Telefast Communication/Philippine
Wireless, Inc., Defendant-Appellant."
The March 15, 2002 decision and May 29, 2003
resolution of the Court of Appeals in CA-G.R. CV No. 61353
and the August 5, 1998 decision of the Regional Trial Court, The facts of the case are as follows:
Branch 58, Makati City in Civil Case No. 97-1501 are hereby
SET ASIDE. New judgment is entered: On 2 November 1956, Consolacion Bravo-Castro wife of
plaintiff Ignacio Castro, Sr. and mother of the other plaintiffs,
1. ordering petitioner Titan-Ikeda Construction and passed away in Lingayen, Pangasinan. On the same day, her
Development Corporation to return to respondent Primetown daughter Sofia C. Crouch, who was then vacationing in the
Property Group, Inc. the condominium units and parking slots Philippines, addressed a telegram to plaintiff Ignacio Castro, Sr.
corresponding to the payment made in excess of the at 685 Wanda, Scottsburg, Indiana, U.S.A., 47170 announcing
proportionate (project) cost of its actual accomplishment as of Consolacion's death. The telegram was accepted by the
October 12, 1995, subject to its (petitioners) allowable claims defendant in its Dagupan office, for transmission, after payment
as stated in the inventory and of the required fees or charges.
2. dismissing petitioner Titan-Ikeda Construction and
Development Corporations claims for the cost of additional The telegram never reached its addressee. Consolacion was
work (or change order) and damages. interred with only her daughter Sofia in attendance. Neither the
husband nor any of the other children of the deceased, then all
The records of this case are remanded to the Regional residing in the United States, returned for the burial.
Trial Court of Makati City, Branch 58 for:

1. the reception of additional evidence to determine When Sofia returned to the United States, she discovered that
(a) the percentage of the architectural work actually the wire she had caused the defendant to send, had not been
completed by petitioner Titan-Ikeda Construction and received. She and the other plaintiffs thereupon brought action
Development Corporation as of October 12, 1995 on the Makati for damages arising from defendant's breach of contract. The
Prime Tower and case was filed in the Court of First Instance of Pangasinan and
(b) the number of condominium units and parking slots docketed therein as Civil Case No. 15356. The only defense of
sold by petitioner Titan-Ikeda Construction and Development the defendant was that it was unable to transmit the telegram
Corporation to third persons; because of "technical and atmospheric factors beyond its
control." 1 No evidence appears on record that defendant ever
74 made any attempt to advise the plaintiff Sofia C. Crouch as to
why it could not transmit the telegram.
75
76
The Court of First Instance of Pangasinan, after trial, ordered
77 the defendant (now petitioner) to pay the plaintiffs (now private
78 respondents) damages, as follows, with interest at 6% per
79 annum:
1. Sofia C. Crouch, P31.92 and P16,000.00 Art. 1170 of the Civil Code provides that "those who in the
as compensatory damages and P20,000.00 performance of their obligations are guilty of fraud, negligence
as moral damages. or delay, and those who in any manner contravene the tenor
thereof, are liable for damages." Art. 2176 also provides that
2. Ignacio Castro Sr., P20,000.00 as moral "whoever by act or omission causes damage to another, there
damages. being fault or negligence, is obliged to pay for the damage
done."
3. Ignacio Castro Jr., P20,000.00 as moral
damages. In the case at bar, petitioner and private respondent Sofia C.
Crouch entered into a contract whereby, for a fee, petitioner
undertook to send said private respondent's message overseas
4. Aurora Castro, P10,000.00 moral by telegram. This, petitioner did not do, despite performance by
damages. said private respondent of her obligation by paying the required
charges. Petitioner was therefore guilty of contravening its
5. Salvador Castro, P10,000.00 moral obligation to said private respondent and is thus liable for
damages. damages.

6. Mario Castro, P10,000.00 moral This liability is not limited to actual or quantified damages. To
damages. sustain petitioner's contrary position in this regard would result
in an inequitous situation where petitioner will only be held
7. Conrado Castro, P10,000 moral damages. liable for the actual cost of a telegram fixed thirty (30) years
ago.

8. Esmeralda C. Floro, P20,000.00 moral


damages. We find Art. 2217 of the Civil Code applicable to the case at
bar. It states: "Moral damages include physical suffering,
mental anguish, fright, serious anxiety, besmirched reputation,
9. Agerico Castro, P10,000.00 moral wounded feelings, moral shock, social humiliation, and similar
damages. injury. Though incapable of pecuniary computation, moral
damages may be recovered if they are the proximate results of
10. Rolando Castro, P10,000.00 moral the defendant's wrongful act or omission." (Emphasis supplied).
damages.
Here, petitioner's act or omission, which amounted to gross
11. Virgilio Castro, P10,000.00 moral negligence, was precisely the cause of the suffering private
damages. respondents had to undergo.

12. Gloria Castro, P10,000.00 moral As the appellate court properly observed:
damages.
[Who] can seriously dispute the shock, the
Defendant is also ordered to pay P5,000.00 attorney's fees, mental anguish and the sorrow that the
exemplary damages in the amount of P1,000.00 to each of the overseas children must have suffered upon
plaintiffs and costs. 2 learning of the death of their mother after
she had already been interred, without
On appeal by petitioner, the Intermediate Appellate Court being given the opportunity to even make a
affirmed the trial court's decision but eliminated the award of choice on whether they wanted to pay her
P16,000.00 as compensatory damages to Sofia C. Crouch and their last respects? There is no doubt that
the award of P1,000.00 to each of the private respondents as these emotional sufferings were
exemplary damages. The award of P20,000.00 as moral proximately caused by appellant's omission
damages to each of Sofia C. Crouch, Ignacio Castro, Jr. and and substantive law provides for the
Esmeralda C. Floro was also reduced to P120,000. 00 for each. justification for the award of moral
3 damages. 4

Petitioner appeals from the judgment of the appellate court, We also sustain the trial court's award of P16,000.00 as
contending that the award of moral damages should be compensatory damages to Sofia C. Crouch representing the
eliminated as defendant's negligent act was not motivated by expenses she incurred when she came to the Philippines from
"fraud, malice or recklessness." the United States to testify before the trial court. Had petitioner
not been remiss in performing its obligation, there would have
been no need for this suit or for Mrs. Crouch's testimony.
In other words, under petitioner's theory, it can only be held
liable for P 31.92, the fee or charges paid by Sofia C. Crouch
for the telegram that was never sent to the addressee thereof. The award of exemplary damages by the trial court is likewise
justified and, therefore, sustained in the amount of P1,000.00
for each of the private respondents, as a warning to all telegram
Petitioner's contention is without merit.
companies to observe due diligence in transmitting the Construction Contact:
messages of their customers. If at any time during the effectivity of this contract,
[PETITIONER] shall incur unreasonable delay or slippages of
WHEREFORE, the petition is DENIED. The decision appealed more (15%) of the scheduled work program, [RESPONDENT]
from is modified so that petitioner is held liable to private should notify in writing to accelerate the work and reduce, if
respondents in the following amounts: not erase, slippage. If after the lapse of sixty (60) days from
receipt of such notice, [PETITIONER] fails to rectify the delay
or slippage, [RESPONDENT] shall have the right to terminate
(1) P10,000.00 as moral damages, to each this contract except in cases where the same was caused by
of private respondents; force majeure.

(2) P1,000.00 as exemplary damages, to Respondent never sent petitioner a written demand asking it to
each of private respondents; accelerate work on the project and reduce, if not eliminate,
slippage. If delay had truly been the reason why respondent
(3) P16,000.00 as compensatory damages, took over the project, it would have sent a written demand as
to private respondent Sofia C. Crouch; required by the construction contract. Moreover, according to
the October 12, 1995 letter-agreement, respondent took over the
project for the sole reason that such move was part of its
(4) P5,000.00 as attorney's fees; and (respondents) long-term plan.
Because petitioner did not consent to the change of the
(5) Costs of suit. designated construction manager, ITIs September 7, 1995
report could not bind it.
SO ORDERED.
G.R. No. 157318 August 9, 2006

TITAN-IKEDA CONST. vs. PRIMETOWN


544 SCRA 466 (Art. 1169) GENEROSO V. VILLANUEVA and RAUL C.
VILLANUEVA, JR., Petitioners,
Facts: vs.
ESTATE OF GERARDO L. GONZAGA/MA. VILLA
The parties entered into a contract for a piece of work when GONZAGA, in her capacity as Administratrix, Respondents.
they executed the supplemental agreement. Respondent
Primetown Property Group, Inc. awarded the contract for the DECISION
structural works of its 32-storey Makati Prime Tower (MPT) to
petitioner Titan-Ikeda Construction and Development PUNO, J.:
Corporation. Titan-Ikeda as contractor bound itself to execute
the project for respondent, the owner/developer, in
consideration of a price certain P130M. (The supplemental Before us is a petition for review on certiorari assailing the
agreement was reciprocal in nature because the obligation of Decision dated January 16, 2003 1 of the Court of Appeals in
respondent to pay the entire contract price depended on the CA-G.R. CV No. 46865 which affirmed with modification the
obligation of petitioner to complete the project.) Decision dated December 29, 1993 2 of the Regional Trial Court
(RTC) of Bacolod City in Civil Case No. 6552. The RTC-
ITI estimated that petitioner should have accomplished 48.71% Bacolod City declared the Memorandum of Agreement (MOA)
of the project as of the October 12, 1995 takeover date. between petitioners and respondents as rescinded, and ordered
Petitioner repudiated this figure but qualifiedly admitted that it petitioners to pay moral damages and attorneys fees to
did not finish the project. Records showed that respondent did respondents. The Court of Appeals deleted the award for moral
not merely take over the supervision of the project but took full damages.
control thereof.
The antecedent facts are as follows:
Because the parties agreed to extinguish the supplemental
agreement, they were no longer required to fully perform their On January 15, 1990, petitioners Generoso Villanueva and Raul
respective obligations. Petitioner was relieved of its obligation Villanueva, Jr., business entrepreneurs engaged in the operation
to complete the project while respondent was freed of its of transloading stations and sugar trading, and respondent
obligation to pay the entire contract price. Estate of Gerardo L. Gonzaga, represented by its Judicial
Administratrix, respondent Ma. Villa J. Gonzaga, executed a
Issue: MOA 3 which reads:
WON there was delay on the part of petitioner Titan-Ikeda? NO

Held: KNOW ALL MEN BY THESE PRESENTS:


Mora or delay is the failure to perform the obligation in due
time because of dolo (malice) or culpa (negligence). A debtor is This Memorandum made and entered into by and between:
deemed to have violated his obligation to the creditor from the
time the latter makes a demand. Once the creditor makes a THE ESTATE OF GERARDO L. GONZAGA represented in
demand, the debtor incurs mora or delay. the act by its Administratrix, MA. VILLA J. GONZAGA,
Filipino, of legal age, widow and resident of Bacolod City, forfeited in the event the SECOND PARTY withdraws from
hereinafter referred to as the FIRST PARTY, this agreement.

-and- D.) That upon payment of 60% of the purchase price, the
SECOND PARTY may start to introduce improvements in the
RAUL VILLANUEVA, JR. and GENEROSO V. area if they so desire.
VILLANUEVA, Filipinos, of legal age, married and residents
of Bacolod City, hereinafter jointly referred to as the SECOND E.) That upon the release by the Philippine National Bank
PARTY. (PNB) of the lots subject of this agreement, the FIRST PARTY
shall immediately execute a Deed of Sale in favor of the
W I T N E S S E T H: SECOND PARTY. All expenses for documentation and capital
gains shall be borne by the FIRST PARTY, while expenses for
transfer of title to the SECOND PARTY shall be borne by the
1. WHEREAS, the FIRST PARTY is the true and lawful owner latter.
of a parcel of land, Lot No. 1362, covered by TCT No. T-
131872 situated at Brgy. Granada, Bacolod City and known as
Hda. San Dionisio Norte; IN WITNESS WHEREOF, the parties have hereunto set their
hands this 15th day of January, 1990 in this City of Bacolod,
Philippines. [emphases added]
2. WHEREAS, the aforesaid property is presently mortgaged
with the Philippine National Bank (PNB) as collateral for a
loan; As stipulated in the agreement, petitioners introduced
improvements after paying P291,600.00 constituting sixty
(60%) percent of the total purchase price of the lots. Petitioners
3. WHEREAS, the aforesaid property is already subdivided into then requested permission from respondent Administratrix to
sub-lots although separate titles for each lot is not yet issued; use the premises for the next milling season. Respondent
refused on the ground that petitioners cannot use the premises
4. WHEREAS, the herein SECOND PARTY agrees to purchase until full payment of the purchase price. Petitioners informed
portions of the aforesaid property equivalent to 3,240 sq. meters respondent that their immediate use of the premises was
which portions are designated as Lots Nos. 28, 29, 30, 31, 32, absolutely necessary and that any delay will cause them
33, 34, 35, 36, 37, 38 & 39 in phase 11 of the subdivision plan; substantial damages. Respondent remained firm in her refusal,
and demanded that petitioners stop using the lots as a
5. WHEREAS, the SECOND PARTY agrees to purchase the transloading station to service the Victorias Milling Company
aforesaid lots at the price of ONE HUNDRED FIFTY unless they pay the full purchase price. In a letter-reply dated
(P150.00) PESOS per sq. meter or for a total price of FOUR April 5, 1991, petitioners assured respondent of their readiness
HUNDRED EIGHTY SIX THOUSAND (P486,000.00) PESOS to pay the balance but reminded respondent of her obligation to
subject to the following conditions: redeem the lots from mortgage with the Philippine National
Bank (PNB). [4]Petitioners gave respondent ten (10) days
within which to do so. [5]
A.) That the FIRST PARTY shall cause the release of the
aforementioned lots from the Philippine National Bank (PNB)
at the earliest possible time. On April 10, 1991, respondent Administratrix wrote petitioners
informing them that the PNB had agreed to release the lots from
mortgage. She demanded payment of the balance of the
B.) That the SECOND PARTY agrees to pay the amount of purchase price. Enclosed with the demand letter was the PNBs
P486,000.00 as follows: letter of approval dated April 8, 1991, 6 marked as Exhibit "3-
B," which reads -
P100,000.00 - upon the signing of this
Mrs. Ma. Villa J. Gonzaga
agreement.
Judicial Administratrix
P191,600.00 - on or before January 10,
Int. Est. of Gerardo L. Gonzaga
1990.
La Salle Subdivision
P194,400.00 - upon the approval by the
Bacolod City
PNB of the release of the
Dear Mrs. Gonzaga:
lots.
We are pleased to inform you that your request for the partial
C.) That it is hereby agreed that the ONE HUNDRED release of securities, particularly the 3,240 sq. m. agricultural
THOUSAND (P100,000.00) PESOS down payment shall at the land x x x covered by TCT No. T-31113 has been approved by
same time be considered as earnest money which shall be
our Senior Management Credit Committee I on April 1, 1991 (2) Ordering plaintiffs to jointly and severally pay defendants:
subject to the following conditions: P20,000.00 as moral damages; and P15,000.00 as attorneys
fees;
1. The sale be approved by the Court insofar as the interest of
the estate is concerned; (3) Ordering defendants to solidarily pay or refund plaintiffs:
the sum of P100,000.00 paid by the latter as down payment on
2. Payment of two (2) annual amortizations of the restructured the aforesaid Memorandum of Agreement on December 18,
accounts in addition to P50,000.00 to be derived from sale of 1989, with legal interest at 6% per annum from said date up to
lot sought to be released; and until the amount is fully paid or refunded; and another sum
of P191,600.00 paid by the latter to the former in connection
with the said Memorandum of Agreement on January 10, 1990,
3. Such terms and conditions that our Legal Dept. may impose with the same rate of interest at 6% per annum from said date
to protect the interest of the Bank. up to and until the amount is fully paid or refunded; and

Please see us for the preparation of the covering documents. (4) Condemning plaintiffs to pay the cost of suit. [8]
[emphases added]
Petitioners filed a petition for review before the Court of
Very truly yours, Appeals. On January 16, 2003, the Court of Appeals affirmed
the trial courts decision but deleted the award for moral
(signed) damages on the ground that petitioners were not guilty of bad
faith in refusing to pay the balance of the purchase price. 9
CECILIA S. GAYENALO Hence, this petition.

Asst. Manager Petitioners raise the following issues:

In their letter-reply dated April 18, 1991, 7 petitioners demanded 1. Whether x x x respondents failed to comply with their
that respondent show the clean titles to the lots first before they reciprocal obligation of securing the release of the subject lots
pay the balance of the purchase price. Respondent merely from mortgage indebtedness with the Philippine National Bank.
reiterated the demand for payment. Petitioners stood pat on
their demand. 2. Whether x x x the delivery of the titles corresponding to the
twelve (12) lots subject of the Memorandum of Agreement is a
On May 28, 1991, respondent Administratrix executed a Deed precondition to the payment by the petitioners of the balance of
of Rescission rescinding the MOA on two grounds: (1) the consideration.
petitioners failed to pay the balance of the purchase price
despite notice of the lots release from mortgage, and (2) 3. Whether x x x petitioners did incur (sic) delay in the
petitioners violated the MOA by using the lots as a transloading performance of their reciprocal obligation under the
station without permission from the respondents. Memorandum of Agreement.

In their Letter dated June 13, 1991, petitioners, through counsel, 4. Whether x x x there is legal, or even a factual, ground for the
formally demanded the production of the titles to the lots before rescission of the Memorandum of Agreement. 10
they pay the balance of the purchase price. The demand was
ignored. Consequently, on June 19, 1991, petitioners filed a We will resolve first the procedural objections raised by the
complaint against respondents for breach of contract, specific respondents.
performance and damages before the RTC-Bacolod City,
docketed as Civil Case No. 6552. Petitioners alleged that
respondents delayed performance of their obligation by Respondents contend that the petition should be dismissed for
unreasonably failing to secure the release of the lots from late filing, and irregular execution of the affidavit of service
mortgage with the PNB within the earliest possible time, as attached to the petition. Respondents allege that the petition
stipulated in the MOA. Petitioners prayed that respondents be was filed late as there was no evidence to show that petitioners
ordered to produce the clean titles to the lots before they pay motion for extension of time to file the petition has been
the balance of the purchase price. granted by the Court. Petitioners allegedly received a copy of
the assailed Court of Appeals decision on January 28, 2003 but
filed the petition for review on March 12, 2003 only, contrary to
The trial court decided the case in favor of respondents. The Section 2, Rule 45 of the 1997 Rules of Civil Procedure. 11 In
dispositive portion of the decision reads- addition, the Affidavit of Service attached to the petition was
irregularly executed on March 13, 2003, a day after the petition
(1) Declaring the Memorandum of Agreement, Exh. "C" has been filed in Court.
rescinded; consequently ownership and possession of Lots 28 to
39, inclusive, of Phase II of the subdivision plan covered by Respondents contentions are not meritorious. The records show
TCT No. T-31113 are hereby restored to defendants, and that petitioners motion for 30 days extension of time to file the
defendants (sic) are thereby ordered to vacate the premises of petition for review has been granted in our Resolution dated
said lots; March 26, 2003. Petitioners were given thirty (30) days from
the expiration of the original period, or until March 13, 2003, situation that prevents the obligation of the vendor to convey
within which to file the petition for review. Although our title from acquiring an obligatory force. This is entirely
resolution is dated after the extension prayed for has already different from the situation in a contract of sale, where non-
expired, we specifically conditioned the grant of extension upon payment of the price is a negative resolutory condition. The
the timeliness of the filing of the petition and payment by effects in law are not identical. In a contract of sale, the vendor
petitioners of the correct docket and other filing fees. has lost ownership of the thing sold and cannot recover it,
Petitioners did so. The petition for review was posted by unless the contract of sale is rescinded and set aside. In a
registered mail on March 13, 2003, as shown by the date contract to sell, however, the vendor remains the owner for as
appearing on the first page of the original copy of the petition long as the vendee has not complied fully with the condition of
filed with the Court. [12]The Affidavit of Service was thus paying the purchase price. If the vendor should eject the vendee
regularly executed on March 13, 2003, the same day that the for failure to meet the condition precedent, he is enforcing the
petition was posted by registered mail. No reason exists contract and not rescinding it. x x x x Article 1592 speaks of
therefore for the dismissal of the petition on technical grounds, non-payment of the purchase price as a resolutory condition. It
as respondents erroneously contend. does not apply to a contract to sell. As to Article 1191, it is
subordinated to the provisions of Article 1592 when applied to
On the merits of the case, we agree with the petitioners that the sales of immovable property. Neither provision is applicable [to
Court of Appeals erred in ruling that respondents had already a contract to sell]. (emphasis added)
fulfilled their obligation to cause the release of the lots from
mortgage with the PNB at the time they demanded payment of The MOA between petitioners and respondents is a conditional
the balance of the purchase price. The finding of the appellate contract to sell. Ownership over the lots is not to pass to the
court is refuted by Exh. "3-B" and by the testimonial evidence petitioners until full payment of the purchase price. Petitioners
on record. obligation to pay, in turn, is conditioned upon the release of the
lots from mortgage with the PNB to be secured by the
A reading of Exhibit "3-B," 13 which is the PNBs letter of respondents. Although there was no express provision regarding
approval dated April 8, 1991, clearly shows that the approval reserved ownership until full payment of the purchase price, the
was conditional. Three (3) conditions were laid down by the intent of the parties in this regard is evident from the provision
bank before the lots could be finally released from mortgage. that a deed of absolute sale shall be executed only when the lots
The three conditions were: (1) that respondents secure approval have been released from mortgage and the balance paid by
of the sale from the intestate court insofar as the interest of the petitioners. Since ownership has not been transferred, no further
estate is concerned; (2) that respondents pay two annual legal action need have been taken by the respondents, except an
amortizations of their restructured accounts with the PNB plus action to recover possession in case petitioners refuse to
P50,000.00 to be derived from the sale of the lots sought to be voluntarily surrender the lots. 19
released; and (3) that respondents comply with such other terms
and conditions as the PNBs Legal Department may impose. The records show that the lots were finally released from
Cecilia S. Gayenalo, the Assistant Manager of PNB Bacolod mortgage in July 1991. Petitioners have always expressed
City Branch, herself testified that it was in July 1991 that the readiness to pay the balance of the purchase price once that is
final release papers were prepared by the bank because it was achieved. Hence, petitioners should be allowed to pay the
only at that time that respondents complied with the three balance now, if they so desire, since it is established that
conditions. 14 It was therefore premature for respondents to respondents demand for them to pay in April 1991 was
demand payment of the balance of the purchase price from the premature. However, petitioners may not demand production by
petitioners in April 1991 and, failing in that, to "rescind" the the respondents of the titles to the lots as a condition for their
MOA in May 1991. payment. It was not required under the MOA. The MOA merely
states that petitioners shall pay the balance "upon approval by
Moreover, there is no legal basis for the rescission. The remedy the PNB of the release of the lots" from mortgage. Petitioners
of rescission under Art. 1191 of the Civil Code 15 is predicated may not add further conditions now. Obligations arising from
on a breach of faith by the other party that violates the contracts have the force of law between the contracting parties
reciprocity between them. 16 We have held in numerous cases and should be complied with in good faith. 20
that the remedy does not apply to contracts to sell. 17 We
explained the reason in Santos v. Court of Appeals, 18 viz - IN VIEW WHEREOF, the petition is GRANTED. The assailed
Decision dated January 16, 2003 of the Court of Appeals in
x x x [I]n a contract to sell, title remains with the vendor and CA-G.R. CV No. 46865 is REVERSED and SET ASIDE.
does not pass on to the vendee until the purchase price is paid in Petitioners and respondents are restored to
full. Thus, in a contract to sell, the payment of the purchase
price is a positive suspensive condition. Failure to pay the price
agreed upon is not a mere breach, casual or serious, but a

Вам также может понравиться