Академический Документы
Профессиональный Документы
Культура Документы
PARAS, J.:
These are petitions for review on certiorari of the November 28, 1977
decision of the Court of Appeals in CA-G.R. No. 51771-R modifying the
decision of the Court of First Instance of Manila, Branch V, in Civil Case
No. 74958 dated September 21, 1971 as modified by the Order of the
lower court dated December 8, 1971. The Court of Appeals in
modifying the decision of the lower court included an award of an
additional amount of P200,000.00 to the Philippine Bar Association to
be paid jointly and severally by the defendant United Construction Co.
and by the third-party defendants Juan F. Nakpil and Sons and Juan F.
Nakpil.
SO ORDERED.
These petitions arising from the same case filed in the Court of First
Instance of Manila were consolidated by this Court in the resolution of
May 10, 1978 requiring the respective respondents to comment. (Rollo,
L-47851, p. 172).
The facts as found by the lower court (Decision, C.C. No. 74958; Record
on Appeal, pp. 269-348; pp. 520-521; Rollo, L-47851, p. 169) and
affirmed by the Court of Appeals are as follows:
On November 29, 1968, the plaintiff commenced this action for the
recovery of damages arising from the partial collapse of the building
against United Construction, Inc. and its President and General
Manager Juan J. Carlos as defendants. Plaintiff alleges that the collapse
of the building was accused by defects in the construction, the failure
of the contractors to follow plans and specifications and violations by
the defendants of the terms of the contract.
(b) The deviations, if any, made by the defendants from said plans and
specifications and how said deviations contributed to the damage
sustained;
Thus, the issues of this case were divided into technical issues and
non-technical issues. As aforestated the technical issues were referred
to the Commissioner. The non-technical issues were tried by the Court.
The trial court agreed with the findings of the Commissioner except as
to the holding that the owner is charged with full nine supervision of
the construction. The Court sees no legal or contractual basis for such
conclusion. (Record on Appeal, pp. 309-328; Ibid).
Thus, on September 21, 1971, the lower court rendered the assailed
decision which was modified by the Intermediate Appellate Court on
November 28, 1977.
All the parties herein appealed from the decision of the Intermediate
Appellate Court. Hence, these petitions.
After the parties had all filed their comments, We gave due course to
the petitions in Our Resolution of July 21, 1978.
The amicus curiae gave the opinion that the plans and specifications of
the Nakpils were not defective. But the Commissioner, when asked by
Us to comment, reiterated his conclusion that the defects in the plans
and specifications indeed existed.
Using the same authorities availed of by the amicus curiae such as the
Manila Code (Ord. No. 4131) and the 1966 Asep Code, the
Commissioner added that even if it can be proved that the defects in
the construction alone (and not in the plans and design) caused the
damage to the building, still the deficiency in the original design and
jack of specific provisions against torsion in the original plans and the
overload on the ground floor columns (found by an the experts
including the original designer) certainly contributed to the damage
which occurred. (Ibid, p. 174).
The applicable law governing the rights and liabilities of the parties
herein is Article 1723 of the New Civil Code, which provides:
Art. 1723. The engineer or architect who drew up the plans and
specifications for a building is liable for damages if within fifteen years
from the completion of the structure the same should collapse by
reason of a defect in those plans and specifications, or due to the
defects in the ground. The contractor is likewise responsible for the
damage if the edifice fags within the same period on account of
defects in the construction or the use of materials of inferior quality
furnished by him, or due to any violation of the terms of the contract. If
the engineer or architect supervises the construction, he shall be
solidarily liable with the contractor.
The action must be brought within ten years following the collapse of
the building.
The principle embodied in the act of God doctrine strictly requires that
the act must be one occasioned exclusively by the violence of nature
and all human agencies are to be excluded from creating or entering
into the cause of the mischief. When the effect, the cause of which is to
be considered, is found to be in part the result of the participation of
man, whether it be from active intervention or neglect, or failure to act,
the whole occurrence is thereby humanized, as it were, and removed
from the rules applicable to the acts of God. (1 Corpus Juris, pp. 1174-
1175).
Thus it has been held that when the negligence of a person concurs
with an act of God in producing a loss, such person is not exempt from
liability by showing that the immediate cause of the damage was the
act of God. To be exempt from liability for loss because of an act of
God, he must be free from any previous negligence or misconduct by
which that loss or damage may have been occasioned. (Fish & Elective
Co. v. Phil. Motors, 55 Phil. 129; Tucker v. Milan, 49 O.G. 4379;
Limpangco & Sons v. Yangco Steamship Co., 34 Phil. 594, 604; Lasam
v. Smith, 45 Phil. 657).
It is well settled that the findings of facts of the Court of Appeals are
conclusive on the parties and on this court (cases cited in Tolentino vs.
de Jesus, 56 SCRA 67; Cesar vs. Sandiganbayan, January 17, 1985, 134
SCRA 105, 121), unless (1) the conclusion is a finding grounded
entirely on speculation, surmise and conjectures; (2) the inference
made is manifestly mistaken; (3) there is grave abuse of discretion; (4)
the judgment is based on misapprehension of facts; (5) the findings of
fact are conflicting , (6) the Court of Appeals went beyond the issues of
the case and its findings are contrary to the admissions of both
appellant and appellees (Ramos vs. Pepsi-Cola Bottling Co., February 8,
1967, 19 SCRA 289, 291-292; Roque vs. Buan, Oct. 31, 1967, 21 SCRA
648, 651); (7) the findings of facts of the Court of Appeals are contrary
to those of the trial court; (8) said findings of facts are conclusions
without citation of specific evidence on which they are based; (9) the
facts set forth in the petition as well as in the petitioner's main and
reply briefs are not disputed by the respondents (Garcia vs. CA, June
30, 1970, 33 SCRA 622; Alsua-Bett vs. Court of Appeals, July 30, 1979,
92 SCRA 322, 366); (10) the finding of fact of the Court of Appeals is
premised on the supposed absence of evidence and is contradicted by
evidence on record (Salazar vs. Gutierrez, May 29, 1970, 33 SCRA 243,
247; Cited in G.R. No. 66497-98, Sacay v. Sandiganbayan, July 10,
1986).
It is evident that the case at bar does not fall under any of the
exceptions above-mentioned. On the contrary, the records show that
the lower court spared no effort in arriving at the correct appreciation
of facts by the referral of technical issues to a Commissioner chosen by
the parties whose findings and conclusions remained convincingly
unrebutted by the intervenors/amicus curiae who were allowed to
intervene in the Supreme Court.
In any event, the relevant and logical observations of the trial court as
affirmed by the Court of Appeals that "while it is not possible to state
with certainty that the building would not have collapsed were those
defects not present, the fact remains that several buildings in the same
area withstood the earthquake to which the building of the plaintiff was
similarly subjected," cannot be ignored.
The next issue to be resolved is the amount of damages to be awarded
to the PBA for the partial collapse (and eventual complete collapse) of
its building.
The Court of Appeals affirmed the finding of the trial court based on
the report of the Commissioner that the total amount required to repair
the PBA building and to restore it to tenantable condition was
P900,000.00 inasmuch as it was not initially a total loss. However,
while the trial court awarded the PBA said amount as damages, plus
unrealized rental income for one-half year, the Court of Appeals
modified the amount by awarding in favor of PBA an additional sum of
P200,000.00 representing the damage suffered by the PBA building as
a result of another earthquake that occurred on April 7, 1970 (L-47896,
Vol. I, p. 92).
The PBA in its brief insists that the proper award should be
P1,830,000.00 representing the total value of the building (L-47896,
PBA's No. 1 Assignment of Error, p. 19), while both the NAKPILS and
UNITED question the additional award of P200,000.00 in favor of the
PBA (L- 47851, NAKPIL's Brief as Petitioner, p. 6, UNITED's Brief as
Petitioner, p. 25). The PBA further urges that the unrealized rental
income awarded to it should not be limited to a period of one-half year
but should be computed on a continuing basis at the rate of
P178,671.76 a year until the judgment for the principal amount shall
have been satisfied L- 47896, PBA's No. 11 Assignment of Errors, p.
19).
There should be no question that the NAKPILS and UNITED are liable
for the damage resulting from the partial and eventual collapse of the
PBA building as a result of the earthquakes.
We quote with approval the following from the erudite decision penned
by Justice Hugo E. Gutierrez (now an Associate Justice of the Supreme
Court) while still an Associate Justice of the Court of Appeals:
There is no question that an earthquake and other forces of nature
such as cyclones, drought, floods, lightning, and perils of the sea are
acts of God. It does not necessarily follow, however, that specific losses
and suffering resulting from the occurrence of these natural force are
also acts of God. We are not convinced on the basis of the evidence on
record that from the thousands of structures in Manila, God singled out
the blameless PBA building in Intramuros and around six or seven
other buildings in various parts of the city for collapse or severe
damage and that God alone was responsible for the damages and
losses thus suffered.
The findings of the lower Court on the cause of the collapse are more
rational and accurate. Instead of laying the blame solely on the
motions and forces generated by the earthquake, it also examined the
ability of the PBA building, as designed and constructed, to withstand
and successfully weather those forces.
a. Increase the inertia forces that move the building laterally toward
the Manila Fire Department.
3. The embedded 4" diameter cast iron down spout on all exterior
columns reduces the cross-sectional area of each of the columns and
the strength thereof.
2. There are more damages in the front part of the building than
towards the rear, not only in columns but also in slabs.
The Third-party defendants, who are the most concerned with this
portion of the Commissioner's report, voiced opposition to the same on
the grounds that (a) the finding is based on a basic erroneous
conception as to the design concept of the building, to wit, that the
design is essentially that of a heavy rectangular box on stilts with
shear wan at one end; (b) the finding that there were defects and a
deficiency in the design of the building would at best be based on an
approximation and, therefore, rightly belonged to the realm of
speculation, rather than of certainty and could very possibly be
outright error; (c) the Commissioner has failed to back up or support
his finding with extensive, complex and highly specialized
computations and analyzes which he himself emphasizes are
necessary in the determination of such a highly technical question; and
(d) the Commissioner has analyzed the design of the PBA building not
in the light of existing and available earthquake engineering
knowledge at the time of the preparation of the design, but in the light
of recent and current standards.
(2) (a) The deviations, if any, made by the defendants from the
plans and specifications, and how said deviations contributed to the
damage sustained by the building.
These two issues, being interrelated with each other, will be discussed
together.
We now turn to the construction of the PBA Building and the alleged
deficiencies or defects in the construction and violations or deviations
from the plans and specifications. All these may be summarized as
follows:
(10) Column D6 Spirals are too far apart and apparently improperly
spliced,
(11) Column D7 Lateral ties are too far apart, spaced 16" on
centers.
There is no excuse for the cavity or hollow portion in the column A4,
second floor, and although this column did not fail, this is certainly an
evidence on the part of the contractor of poor construction.
The cutting of the spirals in column A5, ground floor is the subject of
great contention between the parties and deserves special
consideration.
The proper placing of the main reinforcements and spirals in column
A5, ground floor, is the responsibility of the general contractor which is
the UCCI. The burden of proof, therefore, that this cutting was done by
others is upon the defendants. Other than a strong allegation and
assertion that it is the plumber or his men who may have done the
cutting (and this was flatly denied by the plumber) no conclusive proof
was presented. The engineering experts for the defendants asserted
that they could have no motivation for cutting the bar because they
can simply replace the spirals by wrapping around a new set of spirals.
This is not quite correct. There is evidence to show that the pouring of
concrete for columns was sometimes done through the beam and
girder reinforcements which were already in place as in the case of
column A4 second floor. If the reinforcement for the girder and column
is to subsequently wrap around the spirals, this would not do for the
elasticity of steel would prevent the making of tight column spirals and
loose or improper spirals would result. The proper way is to produce
correct spirals down from the top of the main column bars, a procedure
which can not be done if either the beam or girder reinforcement is
already in place. The engineering experts for the defendants strongly
assert and apparently believe that the cutting of the spirals did not
materially diminish the strength of the column. This belief together
with the difficulty of slipping the spirals on the top of the column once
the beam reinforcement is in place may be a sufficient motivation for
the cutting of the spirals themselves. The defendants, therefore,
should be held responsible for the consequences arising from the loss
of strength or ductility in column A5 which may have contributed to the
damages sustained by the building.
The lack of proper length of splicing of spirals was also proven in the
visible spirals of the columns where spalling of the concrete cover had
taken place. This lack of proper splicing contributed in a small measure
to the loss of strength.
The effects of all the other proven and visible defects although nor can
certainly be accumulated so that they can contribute to an appreciable
loss in earthquake-resistant strength. The engineering experts for the
defendants submitted an estimate on some of these defects in the
amount of a few percent. If accumulated, therefore, including the effect
of eccentricity in the column the loss in strength due to these minor
defects may run to as much as ten percent.
Relative thereto, the ruling of the Supreme Court in Tucker v. Milan (49
O.G. 4379, 4380) which may be in point in this case reads:
One who negligently creates a dangerous condition cannot escape
liability for the natural and probable consequences thereof, although
the act of a third person, or an act of God for which he is not
responsible, intervenes to precipitate the loss.
SO ORDERED.
The present case comes by direct appeal from a decision of the Court
of First Instance of Manila (Case No. 44572) adjudging the defendant-
appellant, Luzon Stevedoring Corporation, liable in damages to the
plaintiff-appellee Republic of the Philippines.
In the early afternoon of August 17, 1960, barge L-1892, owned by the
Luzon Stevedoring Corporation was being towed down the Pasig river
by tugboats "Bangus" and "Barbero"1 also belonging to the same
corporation, when the barge rammed against one of the wooden piles
of the Nagtahan bailey bridge, smashing the posts and causing the
bridge to list. The river, at the time, was swollen and the current swift,
on account of the heavy downpour of Manila and the surrounding
provinces on August 15 and 16, 1960.
After due trial, the court rendered judgment on June 11, 1963, holding
the defendant liable for the damage caused by its employees and
ordering it to pay to plaintiff the actual cost of the repair of the
Nagtahan bailey bridge which amounted to P192,561.72, with legal
interest thereon from the date of the filing of the complaint.
I The lower court erred in not holding that the herein defendant-
appellant had exercised the diligence required of it in the selection and
supervision of its personnel to prevent damage or injury to
others.1awphl.nt
II The lower court erred in not holding that the ramming of the
Nagtahan bailey bridge by barge L-1892 was caused by force majeure.
III The lower court erred in not holding that the Nagtahan bailey
bridge is an obstruction, if not a menace, to navigation in the Pasig
river.
IV The lower court erred in not blaming the damage sustained by the
Nagtahan bailey bridge to the improper placement of the dolphins.
Taking the aforesaid rules into account, it can be seen that the only
reviewable issues in this appeal are reduced to two:
2) Whether or not it was error for the Court to have permitted the
plaintiff-appellee to introduce additional evidence of damages after
said party had rested its case.
It avails the appellant naught to argue that the dolphins, like the
bridge, were improperly located. Even if true, these circumstances
would merely emphasize the need of even higher degree of care on
appellant's part in the situation involved in the present case. The
appellant, whose barges and tugs travel up and down the river
everyday, could not safely ignore the danger posed by these allegedly
improper constructions that had been erected, and in place, for years.
On the second point: appellant charges the lower court with having
abused its discretion in the admission of plaintiff's additional evidence
after the latter had rested its case. There is an insinuation that the
delay was deliberate to enable the manipulation of evidence to
prejudice defendant-appellant.
DECISION
YNARES-SANTIAGO, J.:
3. And the 4th party complaint is dismissed for lack of cause of action.
No pronouncement as to costs.
SO ORDERED.9
SO ORDERED.10
5.2. RESPONDENTS ARE NOT LIABLE FOR DAMAGES FOR THE INJURY
RESULTING FROM A GUNSHOT WOUND SUFFERED BY THE PETITIONER
FROM THE HANDS OF NO LESS THAN THEIR OWN SECURITY GUARD IN
VIOLATION OF THEIR BUILT-IN CONTRACTUAL OBLIGATION TO
PETITIONER, BEING THEIR LAW STUDENT AT THAT TIME, TO PROVIDE
HIM WITH A SAFE AND SECURE EDUCATIONAL ENVIRONMENT;
xxxx
11.0. Defendants are responsible for ensuring the safety of its students
while the latter are within the University premises. And that should
anything untoward happens to any of its students while they are within
the University's premises shall be the responsibility of the defendants.
In this case, defendants, despite being legally and morally bound,
miserably failed to protect plaintiff from injury and thereafter, to
mitigate and compensate plaintiff for said injury;
Article 1170 of the Civil Code provides that those who are negligent in
the performance of their obligations are liable for damages.
Accordingly, for breach of contract due to negligence in providing a
safe learning environment, respondent FEU is liable to petitioner for
damages. It is essential in the award of damages that the claimant
must have satisfactorily proven during the trial the existence of the
factual basis of the damages and its causal connection to defendant's
acts.18
As regards the award of moral damages, there is no hard and fast rule
in the determination of what would be a fair amount of moral damages
since each case must be governed by its own peculiar
circumstances.22 The testimony of petitioner about his physical
suffering, mental anguish, fright, serious anxiety, and moral shock
resulting from the shooting incident23 justify the award of moral
damages. However, moral damages are in the category of an award
designed to compensate the claimant for actual injury suffered and not
to impose a penalty on the wrongdoer. The award is not meant to
enrich the complainant at the expense of the defendant, but to enable
the injured party to obtain means, diversion, or amusements that will
serve to obviate the moral suffering he has undergone. It is aimed at
the restoration, within the limits of the possible, of the spiritual status
quo ante, and should be proportionate to the suffering inflicted. Trial
courts must then guard against the award of exorbitant damages; they
should exercise balanced restrained and measured objectivity to avoid
suspicion that it was due to passion, prejudice, or corruption on the
part of the trial court.24 We deem it just and reasonable under the
circumstances to award petitioner moral damages in the amount of
P100,000.00.
We note that the trial court held respondent De Jesus solidarily liable
with respondent FEU. In Powton Conglomerate, Inc. v. Agcolicol,26 we
held that:
xxxx
xxxx
xxxx
For these acts of negligence and for having supplied respondent FEU
with an unqualified security guard, which resulted to the latter's breach
of obligation to petitioner, it is proper to hold Galaxy liable to
respondent FEU for such damages equivalent to the above-mentioned
amounts awarded to petitioner.
DECISION
PEREZ, J.:
I.
II.
III.
THE HONORABLE OFFICE OF THE PRESIDENT ERRED IN AFFIRMING THE
DECISION OF THE HOUSING AND LAND USE REGULATORY BOARD
ORDERING PETITIONERS-APPELLANTS TO PAY P10,000.00 AS
ADMINISTRATIVE FINE IN THE ABSENCE OF ANY FACTUAL OR LEGAL
BASIS TO SUPPORT SUCH FINDING.8
On 30 July 2008, the Court of Appeals denied the petition for review for
lack of merit. The appellate court echoed the HLURB Arbiters ruling
that "a buyer for a condominium/subdivision unit/lot unit which has not
been developed in accordance with the approved
condominium/subdivision plan within the time limit for complying with
said developmental requirement may opt for reimbursement under
Section 20 in relation to Section 23 of Presidential Decree (P.D.) 957 x x
x."9 The appellate court supported the HLURB Arbiters conclusion,
which was affirmed by the HLURB Board of Commission and the Office
of the President, that petitioners failure to develop the condominium
project is tantamount to a substantial breach which warrants a refund
of the total amount paid, including interest. The appellate court
pointed out that petitioners failed to prove that the Asian financial
crisis constitutes a fortuitous event which could excuse them from the
performance of their contractual and statutory obligations. The
appellate court also affirmed the award of moral damages in light of
petitioners unjustified refusal to satisfy respondents claim and the
legality of the administrative fine, as provided in Section 20 of
Presidential Decree No. 957.
A.
B.
Lastly, petitioners aver that they should not be ordered to pay moral
damages because they never intended to cause delay, and again
blamed the Asian economic crisis as the direct, proximate and only
cause of their failure to complete the project. Petitioners submit that
moral damages should not be awarded unless so stipulated except
under the instances enumerated in Article 2208 of the New Civil Code.
Lastly, petitioners refuse to pay the administrative fine because the
delay in the project was caused not by their own deceptive intent to
defraud their buyers, but due to unforeseen circumstances beyond
their control.
Three issues are presented for our resolution: 1) whether or not the
Asian financial crisis constitute a fortuitous event which would justify
delay by petitioners in the performance of their contractual obligation;
2) assuming that petitioners are liable, whether or not 12% interest
was correctly imposed on the judgment award, and 3) whether the
award of moral damages, attorneys fees and administrative fine was
proper.
It is apparent that these issues were repeatedly raised by petitioners in
all the legal fora. The rulings were consistent that first, the Asian
financial crisis is not a fortuitous event that would excuse petitioners
from performing their contractual obligation; second, as a result of the
breach committed by petitioners, respondents are entitled to rescind
the contract and to be refunded the amount of amortizations paid
including interest and damages; and third, petitioners are likewise
obligated to pay attorneys fees and the administrative fine.
This petition did not present any justification for us to deviate from the
rulings of the HLURB, the Office of the President and the Court of
Appeals.
The injured party may choose between the fulfillment and the
rescission of the obligation, with payment of damages in either case.
He may also seek rescission, even after he has chosen fulfillment, if
the latter should become impossible.
Also, we cannot generalize that the Asian financial crisis in 1997 was
unforeseeable and beyond the control of a business corporation. It is
unfortunate that petitioner apparently met with considerable difficulty
e.g. increase cost of materials and labor, even before the scheduled
commencement of its real estate project as early as 1995. However, a
real estate enterprise engaged in the pre-selling of condominium units
is concededly a master in projections on commodities and currency
movements and business risks. The fluctuating movement of the
Philippine peso in the foreign exchange market is an everyday
occurrence, and fluctuations in currency exchange rates happen
everyday, thus, not an instance of caso fortuito.16
In said case, the Court ordered the refund of the total amortizations
paid by respondents plus 6% legal interest computed from the date of
demand. The Court also awarded attorneys fees. We follow that ruling
in the case before us.
The resulting modification of the award of legal interest is, also, in line
with our recent ruling in Nacar v. Gallery Frames,17 embodying the
amendment introduced by the Bangko Sentral ng Pilipinas Monetary
Board in BSP-MB Circular No. 799 which pegged the interest rate at 6%
regardless of the source of obligation.
SO ORDERED.
RESOLUTION
PERLAS-BERNABE, J.:
The Facts
<<Reference: http://www.scribd.com/doc/196404620/177921>>
P224,713.58
The interest rate under Promissory Note No. 96-21301 was pegged at
15.25% per annum (p.a.), with penalty charge of 3% per month in case
of default; while the twelve (12) trust receipts uniformly provided for
an interest rate of 14% p.a. and 1% penalty charge. By way of security,
the individual petitioners executed several Continuing
Guaranty/Comprehensive Surety Agreements19 in favor of Allied Bank.
Petitioners failed to settle their obligations under the aforementioned
promissory note and trust receipts, hence, Allied Bank, through
counsel, sent them demand letters,20 all dated December 10, 1998,
seeking payment of the total amount of P51,064,093.62, but to no
avail. Thus, Allied Bank was prompted to file a complaint for collection
of sum of money21 (subject complaint) against petitioners before the
RTC, docketed as Civil Case No. 00-1563. In their second22 Amended
Answer,23 petitioners admitted their indebtedness to Allied Bank but
denied liability for the interests and penalties charged, claiming to
have paid the total sum of P65,073,055.73 by way of interest charges
for the period covering 1992 to 1997.24
They also alleged that the economic reverses suffered by the Philippine
economy in 1998 as well as the devaluation of the peso against the US
dollar contributed greatly to the downfall of the steel industry, directly
affecting the business of Metro Concast and eventually leading to its
cessation. Hence, in order to settle their debts with Allied Bank,
petitioners offered the sale of Metro Concasts remaining assets,
consisting of machineries and equipment, to Allied Bank, which the
latter, however, refused. Instead, Allied Bank advised them to sell the
equipment and apply the proceeds of the sale to their outstanding
obligations. Accordingly, petitioners offered the equipment for sale, but
since there were no takers, the equipment was reduced into ferro scrap
or scrap metal over the years. In 2002, Peakstar Oil Corporation
(Peakstar), represented by one Crisanta Camiling (Camiling), expressed
interest in buying the scrap metal. During the negotiations with
Peakstar, petitioners claimed that Atty. Peter Saw (Atty. Saw), a
member of Allied Banks legal department, acted as the latters agent.
Eventually, with the alleged conformity of Allied Bank, through Atty.
Saw, a Memorandum of Agreement25 dated November 8, 2002 (MoA)
was drawn between Metro Concast, represented by petitioner Jose
Dychiao, and Peakstar, through Camiling, under which Peakstar
obligated itself to purchase the scrap metal for a total consideration of
P34,000,000.00, payable as follows:
(a) their failure to pay their outstanding loan obligations to Allied Bank
must be considered as force majeure ; and
(b) since Allied Bank was the party that accepted the terms and
conditions of payment proposed by Peakstar, petitioners must
therefore be deemed to have settled their obligations to Allied Bank. To
bolster their defense, petitioner Jose Dychiao (Jose Dychiao) testified28
during trial that it was Atty. Saw himself who drafted the MoA and
subsequently received29 the P2,000,000.00 cash and the two (2)
Bankwise post-dated checks worth P1,000,000.00 each from Camiling.
However, Atty. Saw turned over only the two (2) checks and
P1,500,000.00 in cash to the wife of Jose Dychiao.30
Claiming that the subject complaint was falsely and maliciously filed,
petitioners prayed for the award of moral damages in the amount of
P20,000,000.00 in favor of Metro Concast and at least P25,000,000.00
for each individual petitioner, P25,000,000.00 as exemplary damages,
P1,000,000.00 as attorneys fees, P500,000.00 for other litigation
expenses, including costs of suit.
The CA Ruling
It also added that "[i]n the final analysis, the aforesaid checks and
receipts were signed by [Atty.] Saw either as representative of
[petitioners] or as partner of the latters legal counsel, and not in
anyway as representative of [Allied Bank]."36
Article 1231 of the Civil Code states that obligations are extinguished
either by payment or performance, the loss of the thing due, the
condonation or remission of the debt, the confusion or merger of the
rights of creditor and debtor, compensation or novation.