Вы находитесь на странице: 1из 1

346 CHAPTER TWENTY

Estimates familiar with the cost control procedures for construction


contracts.
Invariably, every claim seems to include some form of esti-
mate. An objective review of the source material and methods
upon which the estimate was based will often show weak- Claims Administration
nesses or deviations from accepted industry practice. In any
There are several common forms of settlement of contractor
case, it is extremely difficult to determine the amount of a
claims costs. Principally, these include lump-sum settle-
claim or counterclaim without preparing careful estimates of
ments with or without qualification, and time and materials
the work involved.
settlements. The type of settlement generally favored under
Clean Water Grant Projects is the lump-sum approach. With
Schedules that type of settlement the owner and the contractor reach
an agreement on the total amount of money and time
Another facet of construction that seems to contribute to required to complete the work. This agreement may be
the most controversy is scheduling. Scheduling controver- reached either before or after the work has been completed,
sies arise not only from poor planning, on occasion, but with the advantage that it places a price ceiling on the entire
also from disagreement over construction methods or dispute, and on Clean Water Grant Projects facilitates the
sequences of operations. Often, these disputes occur where grantees application for funding from the administrators of
a project is constructed under multiple prime contracts, the funding.
such as those commonly experienced in a professional con- The most desirable form of a lump-sum settlement is
struction management (PCM) contract. The absence of the so-called no fault settlement, which allows resolution
any contractual relationship between the individual prime of the dispute without determination of fault. With this type
contractors or the architect/engineer has been the root of settlement, in exchange for the issuance of a change order,
cause of numerous disputes. the contractor gives a full accord and satisfaction and a
Scheduling techniques such as CPM or other net- waiver of all claims arising out of the incident.
work scheduling systems and their associated computer- A variation of the no-fault settlement is one wherein the
generated printouts have only served to compound the owner may obtain a unilateral reservation of legal rights that
problem. Often the owner has stacks of computer print- will enable the owner to sue for a portion of the claim settle-
outs that it either does not want or does not know how to ment after full payment has been made to the contractor
read. Yet, somewhere in that stack of paper may well be the upon completion of the project. This type of solution is of
key to success in the defense of claims being made against special value on Clean Water Grant Projects by helping to
it. The question of scheduling methods of operation and solve the contractors cash flow problems related to the claim
the impact of deviating from the anticipated schedule and gives the owner a chance to recover funds that may later
requires a careful analysis to determine the reasonableness be determined to be ineligible for payment by the adminis-
of the originally anticipated schedule in conjunction with trators of the grant funds.
the planned methods of operation. The analysis of every With the time and material settlements, the contractor
schedule-related problem is unique, and every such analy- performs the work and submits documented charges for all
sis should include a review of the anticipated sequence materials, labor, and equipment used on the affected work.
and schedule together with a review of the actual progress This type of settlement has one advantage, namely, the
of the work. The review must include an analysis of any opportunity for the contractor to begin work without prior
delay and impact caused by all parties to the progress of negotiation of costs involved. It has a disadvantage as well.
the project. By this method a contractor can artificially increase the cost
and time required to complete the work and inflate the costs
submitted to the owner for payment.
Costs A similar approach is sometimes referred to as force
It is in the presentation of cost data and their supporting account. This is based upon a contractual agreement whose
documentation that most construction claims are the terms are generally spelled out in the General Conditions of
weakest. A carefully detailed reconstruction of all con- the contract for payment of extra work. It is generally
struction activities and their related costs must be made applied in conditions involving an unexpected condition
and presented so that they can be clearly identified for use that leads to extra work and involves a prearranged formula
in negotiating affirmatively or defensively. Construction- for reimbursing the contractor for the costs of labor, materi-
related organizations are reported to be poor in their cost als, and equipment plus a fixed percentage for overhead
record-keeping systems (or lack of systems) and to lack expenses and profit, and the allowable surcharge that will be
the ability to relate costs to possible claims areas. An permitted to be applied to the billings of its subcontractors
accounting firm is not the answer either, as often those and suppliers. A contractor does not waive its rights to claim
cost items relating to potential claims are not identified by extra costs over and above the amount allowed by force
an accounting firm because most accounting firms are not account, if it can be justified and verified; however, it is

Вам также может понравиться