Вы находитесь на странице: 1из 5

IS 1200 ( Part 1 1

f~u~ ~ft~ f~rf~r ~#f~V ~rtff #V


UTW~T ~f?r~
~~PT 1 tI~-~T7~

( ~Pu i~ui)

Indiali Standard
METHODS OF MEASUREMENT OF BUILDI
AND CIVIL ENGINEERING WORKS
PART 1 EARTHWORK

(hurtI2 Revision)

First Reprint MAY 19~4

UDC 69.003.12:69.021.13:624 13

~ BIS 1992

BUREAU OF INDIAN STANDARDS


MANAK BHAVAN, 9 BAHADUR SHAH ZAFAR MARG
NEW DELHi 110002

December 1992 Price C


,t,. ~

~ ~Y)C ~
~ :...
(7
5 IS ~2OO( Part 1): 1992
sji

Indian Standard
I ~~ETHODS OF ~~4EASUREMENTOF BUILDING
~ ENGINEERING WORKS
PART 1 EARTHWORK

( Fourth Revision)
1 SCOPE 2.6 The following works shall not be measured
separately and allowance for the same shall be
This standard ( Part 1) covers the method of deemed to have been made in the description of
measurement of earthwork in building and civil main item:
engineering works. a) Setting out works, profiles, etc;
2 GENERAL RULES b) Site clearance, such as cleaning grass and
vegetation;
2.1 Clubbing of Items c) Unauthorized battering or benching or
excavation:
Items may be clubbed together provided that the dj Forming (or leaving) dead men and
break-up of the clubbed items is agreed to be on tell tales in borrow pits and their removal
the basis of the detailed description of the items after measurements;
stated in this standard.
e) Forming (or leaving) steps in sides of deep
2.2 Booking of Dimensions excavation and their removal after
measurements;
In booking dimensioms, the order shall be con- f) Excavation for insertion of planking and
sistent and generally in the scquenc~ of length, strutting:
breadth or width and height or depth or g) Unless otherwise specified, removing slips
thickness.
or falls in excavations; and
2.3 Mensurements h) Bailing out or pumping of water in
excavation from rains.
Unless otherwise stated hereinafter all work shall
be measured net in decimal system, as fixed in 2.7 Special pumping other than what is required
for conditions given in 2.4 (a) and included
position as given below:
in 2.6 ( h ) and tube well/well point dewatering
a) Each dimension shall be measured to the where resorted to, shall each be measured
nearest 001 m; separately for all stages of pumping, including
intermediate stages unless otherwise stated, in
b) Areas shall he worked out to the nearest K.W. Hrs, or HP Hr~, against separate specific
001 in2; and provision(s) made for the purpose.
c) Cubical contents shall be worked out to
the nearest 00 I in3. 3 CLASS1FICATION
The materials to be excavated shall be classified
2.4 Work to be Measured Separately as follows unless otherwise specified.
Work executed in the following conditions shall a) Soft/Loose Soil Generally any soil which
be measured separately: yields to the ordinary application of pick
and shovel, or t~ PHA WRA, rake or other
a) Work in or under water, ordinary digging implement; such as vege-
b) Work in or under foul situations, table or organic soil, turf, gravel, sand,
silt, loam, clay peat, etc.
c) Work under tidal conditions, and b) Hard/Dense Soil Generally any soil
d) Work in snow. which requires the close application of
picks, or jumpers or scarifiers to loosen;
2.4.1 The levels of high and low water tides such as stiff clay, gravel, cobblestone,
water bound macadem and soling of roads.
where occurring, shall be stated. NOTE Cobbtestone is the rock fragment usualty
2.5 Bills of Quantities rounded or semi-rounded having maximum
diameter in any one direction between 80 mm and
The bills of quantities shall fully describe the 3O~ mm.
materials and workmanship, and accurately c) Mud A mixture of soil and water in
represent the work to be executed. fluid or weak solid state.
I , ......

15 1200 ( Part 1): 1992 2

d) Soft/Disintegrated Rock (Not Requiring d) Where hard/dense sn~ ..~qff/disinlegrated


Blasting) Rock or boulders which may
rock an~ hard rock are d~ t~~1~asure-
be quarried or split with crowbars. This ment fo tithe total cjutiV~ t~&4~de by
will also include laterite and hard method~ (a) and/or (b) given above. If
conglomerate. possiblq after the removal of th~ hard!
e) Hard Rock ( Requiring Blasting) Any dense soil the levels of the exposed
rock or boulder for the excavation of rocks ace should be taken and the
which blasting is required. quantity oFTh~ hard/dens~ soil removed,
NOTE Boulder is a rock fragment usually worked out from the differ~Th5~ betwe~
rounded by weathering disintegration and exfolia- the original levels and new levels. lf this
tionor abrasion by water or ice, having maximum. is not possible the excavation should be
diameter in any direction of more than 300 mm, completed leavingjell-tales and from the
round lying loose on the surface or embedded in
river bed, soil, talus, slope wash and terrace cross-section of these tell-tales, the area of
material of dissimilar origin. the hard/dense soil excavated should be
worked out and then the volume of the
f) Hard Rock (Blasting Prohibited) Hard
hard/dense soil excavated arrived at.
rock requiring blasting as described
under (e) but where blasting is prohibited Quantity of hard dense soil should then be
deducted from the total quantity of hard
for any reason and excavation has to be rock and soft/disintegrated rock. The
carried out by chiselling, wedging or any quantities of hard rock and soft/disintegrated
other agreed method. rock should then be separated as in (c)
NOTE A broad cassification of soil and rock
for earthwork suitable for conditions generally above by stacking the hard rock separately.
occurring in practice has been provided where e) Where soft/loose soil, hard/dense soil, soft!
necessary, further sub-classification may be done disintegrated rock and hard rock are mixed,
to suit individual cases depending on the
properties of the substrate. the measurements of the entire quantity
shall be made by methods (a) and/or (b)
4 METHOD OF MEASUREMENT OR given above. The separate quantities of
VARIOUS TYPES OF EXCAVATION soft/loose soil and hard/dense soil shall be
worked out from the cross-section based on
4.1 The measurement of earthwork shall be done dead men or tell-tales as mentioned in (d)
in cubic metres, unless otherwise mentioned. The in case of hard/dense soil. The total
measurements to be taken shall be those of the quantity of soft/loose and hard/dense soil
authorized dimensions from which soil has been ahall then be deducted from the total ex-
taken out and shall be measured without cavation to arrive at the total quantity of
allowance for increase in bulk. rock excavated. The quantities of soft/dis-
integrated rock and hard rock excavated
4.2 Excavation in Earthwork Including Rock be worked out separately as in case of (c)
Cutting above.
4.2.1 Wherever it is not possible or convenient
The measurement of excavation in earthwork to take measurements from borrow pits or cutting,
including rock cutting shall be made as follows: excavation shall be worked out from filling
a) Where the excavation is in trenches or (see 4.3).
from borrow pits in fairly uniform ground, 4.2.2 Dressing or trimming sides of excavations
the measurements of cutting trenches or and levelling or grading and ramming of bottoms
borrow pits shall be made. Dead men or shall be described with the item of excavation
tell-tales may be left at suitable intervals except in the case of rough excavation ( see 4.5 ).
to determine the average depth of
excavation. 4.2.3 All excavation shall be measured in
b) Where the ground is not uniform, levels successive stages of 1.5 m stating the commencing
shall be taken berore the start, after site level. This shall not apply toircases where no
clearance and after the completion of the lift is involved as in hillside cutting.
work and the quantity of excavation in 4.2.4 All excavation shall gen~rally be described
cutting computed from these levels. as excavate and get out. Jetting out shall
c) Where soft/disintegrated frock and hard include throwing the excavated earth at least one
rock are mixed the measurement for the metre or 1/3 depth ( see Note ) of excavation
total quantity shall be made by method (a) whichever is more clear of edge of the excavatton.
and/or (b) given above. The hard rock The subsequent disposal of surplus excavated
excavated shall be stacked and measured material shall either be stated as a separate item
in stack. The quantity of the hard rock or included with the item of excavation statitig
excavated shall be arrived at by applying the lead.
pre-accepted deductions (stated as a per- NOTE In special cases sxhere disposal alca is
centage ) for voids. From the total limited or where application of this requirement is
impracticable, the person in-charge may adopt a berm
quantity of the mixture the quantity of of reduced width in any case not less than 600 mm
hard rock excavated thus arrived at shall provided the material being excavated is sufficiently
be deducted to work out the quantity of stable and shoring is designed to carry the additional
the soft/disintegrated rock excavated. loads.

2
IS 1100 ( Part 1): 1992
4.2.5 In case of the following works, authorized 4.6 Surface Excavation
quantities ( calculated on the basis of authorized
working spice ) or those actually excavated, Excavation exceeding 15 in in width as well as
2 ott plan but not exceeding 300 mm in
whichever, are less, shall be measured: 10 in
depth shall be described as surface excavation
and measured in square metres.
a) In work which requires forinwork;
b) In work which will be covered externally 4.7 Excavation Over Area
with a damp proof covering; Excavation exceeding l~5 in in width as well as
c) In work which will be covered externally 10 in2 on plan, and 300 mm in depth shall
with protective masonry work of brick, be described as excavation over areas and
stone, precast concrete, etc; measured in cubic metres.
d) Trenches which are to receive post tension- 4.8 Excavation in Trenches for Foundations and
ed concrete ground beams; for Pipes, Cables, etc
e) Special works like guniting, etc; and Excavation in trenches for foundations and for
pipes, cables, etc, not exceeding I ~5 m in width
f) In work which requires workmen to operate and for shafts, wells, cesspits and the like not
from outside. exceeding 10 m2 on plan shall be so described and
measured in cubic metres.
4.2.5.1 Authorised \vorking space shall be special
in each case. Where authorised working space 4.8.1 The authorized quantities ( calculated on
is not so specified the following shall apply: the basis of authorized width ) or those excavated
whichever are less shall be measured in case of
600 mm measured from the face of sub- excavation for pipes, cables, etc. For the purpose
structure ( including prolecti~e measures, if of calculating the contents, cross-sections shall be
any ) at lowest level, where extra working taken at suitable intervals. The authorised width
space is required. ln addition, for item (d shall be specified in each case. ( Relevant Indian
given in 4.2.5 ( d ) the extra length at each Standards, if any, may be consulted for
end shall be 15 in. guidances ).
4.2.6 Battering and benching shall be specified
4.8.2 Exca ration Trenches for Foundations
and measured along with main item of excavation.
For depth exceeding I in, an allowance of
4.3 Filling 50 mm/in depth for each side of trench shall be
added to the specified width.
4.3.1 Actual measurement of fill shall be calculat-
ed by taking levels of the original ground before 4.9 Post Holes
start of the work after site clearance and after Independent post holes ( or similar holes ), each
compaction of the fill at suitable intervals and not exceeding 05 in3, shall be enumerated and
the quantity of fill computed from these levels. the description shall include return, fill and ram
and removal of surplus spoil.
4.3.2 Deductions shall be made from actual
measurements in all cases of fills except for floors 4.10 Return, Fill and Raw
as in 4.12 to arrive at net measurement of filling Returning, filling and ramming of excavated earth
based on pre-accepted or specified deduction where not described with the item of excavation
stated as percentage ) for voids. shall be measured in cubic metres and shall
tnclude spreading in layers not exceeding 200 mm
4.3.3 If the filling is obtained from the borrow tn depth, watering, well ramming and levelling.
pits it shall be measured from the borrow pits as
excavation ( see 4.2 ). 4.11 Embankments
Forming embankments and filling to make up
4.4 Surface Dressing levels shall be measured in cubic metres and shall
iticlude the formation of slopes. If the material
Tritnniing of natural ground, excavated surface is to be deposited in layers, this shall be described
and filled up area to remove vegetation and/or stating the thickness of such layers. The method
small inequalities not exceeding 150 mm deep of consolidation shall be described. The measure-
shall be described as surface dressing and ment shall be taken in successive stages of l~5 m
measured in square metres. stating commcncing level. In case of special
soils like marine clay, the allowance for change
4.5 Rough Excavation in the original levels due to load of an embank-
ment shall be specified.
Excavation not requiring dressing of sides atid
bottom and reduction to exact levels, such as 4.12 Filling under floors shall be measured in
winning earth from borrow pits, hillside cutting, cubic metres and shall include spreading in
etc, shall be described as rough excavation and layers not exceeding 200 mm in depth watering,
tneasured in cubic metres. well ramming and levelling.

3
IS 1200 ( Part 1): 1992
5 LEAD AND LIFT measured in square metres of face supported,
and grouped; separately in stages of I 5 m.
5.1 Lead
The distance for removal shall be measured over 6.1.1 The description shall include use and waste
the shortest practicable route and not necessarily of all necessary timber work, including wales,
the route actually taken. Distances not exceed- struts and open or close poling boards, their
ing 250 m shall be measured in units of fixing and subsequent removal.
50 in. Distance exceeding 250 in and not 6.1.2 Planking and struttitig to the following shall
exceeding 500 in shall be measured as a
separate item. Leads beyond 500 in shall be measured separately:
be measured in units of 500 nt, that is, there will
be one item for lead exceeding 500 in and n~ot a) Tretiches;
exceeding I 000 in, another item for lead exceed-
ing 1 000 in and not exceeding 1500 in and so b) Areas ( the description shall include use
on up to 5 km. Where the lead exceeds 5 kin, and waste of raking shores ); and
it will be measured in units of I kin, half km and c) Shafts, wells, cesspits, manholes and the
above be reckoned as one and less than half like.
kilometre shall be ignored.

5.1.1 The description of items shall include 6.1.3 Where tightly driven close butt jointed
loading and unloading. sheeting is necessary as in the case of running
sand, the item shall be measured separately and
5.1.2 If spoil heaps requiring re-handling have the packing of cavities behind sheeting with
become consolidated due to passage of time or suitable material shall be included in description
any other reason, it shall be so stated attd such of the item
heaps shall be measured separately.
6.1.4 Planking and strutting required to be left
5.1.3 For the purpose of measurements of lead, permanently in position shall be measured
the area excavated shall be divided into suitable separately.
blocks and for each block the distance from the
centre of the block to centre of placed earth 7 REMOVING TREES AND HEDGES
pertaining to this block shall be taken as lead.
7.1 Clearing of shrubs, brushwood, small trees
5.2 Lift not exceeding 300 mm girth shall be measured in
Lift shall be measured from ground level. square metres, and shall deem to include removal
Excavation up to 15 in depth below ground and disposal. The girth shall be measured at
level and depositing excavated material on the I in above ground level.
ground shall be included in the item of earthwork
for various kinds of soil. Extra lift shall be 7.2 Cutting down hedges and removal of fences
measured in unit of 1 5 m or part thereof. shall be fully described and measured in running
Obvious lifts shall only be measured; that is lifts metres and shall deem to include removal and
inherent in the lead due to ground slope shall not disposal.
be measured (except for lead up to 250 in).
7.3 Cutting down trees of 300 mm girth and over
When earth has to be carried over a bank/ up to 1 000 mm girth shall be enumerated as one
obstruction and dumped beyond it, the lift shall item. The cutting down of trees exceeding
be the difference in level between the centre of 1 000 mm in girth shall be enumerated stating
gravity of the excavated earth and the top of
bank/construction. the girth. The girth shall be measured at one
metre above ground level. The item shall include
lopping of branches and removal and disposal.
6 PLANKING AND STRUTTING

6.1 The plankIng and strutting required to 7.4 Digging out of roots including stacking Thall
uphold the face of excavated earth, ete, shall be be measured separately and enumerated.

Вам также может понравиться