GOVERNMENT OF MAHARASHTRA

WATER RESOURCES DEPARTMENT

COMMON SCHEDULE OF RATES


2016-17
(Applicable from 01-11-2016)
DETAILS OF COMMITTEE FORMED FOR PREPARATION OF
COMMON SCHEDULE OF RATES FOR 2016-17
(Reference--Government Resolution Marathi No.MIS-2212/(343/12)/MI-2 Mantralaya
Mumbai 400032 dated 05/07/2014)

1) C.E.(SP),W.R.D.Pune - President

2) C.E. Kokan Region,W.R.D.Mumbai - Member

3) C.E.(SP),W.R.D.Amarwati - Member

4) C.E. & C.A.(CADA)Aurangabad - Member

5) C.E.(WR),W.R.D.Nagpur - Member

6) C.E.Koyana Project Pune - Member

7) C.E.(Mechanical),W.R.D.Nasik - Member

8) S.E.Thane Irrigation Circle,Thane - Member

9) S.E.Kukadi Irrigation Circle,Pune - Member Secretary


DETAILS OF SUBCOMMITTEE FOR PREPARATION OF
COMMON SCHEDULE OF RATES FOR 2016-17

Sr.No. Component of work Members of subcommittee


(1) Excavation & Embankment CO-ORDINATOR
C.E.(SP), WRD, Pune
MEMBERS
1) C.E., North Maharashtra Region, Nashik
2) C.E., Mechanical, WRD, Nashik
(2) Concrete Work including Centering, CO-ORDINATOR
UCR Masonry, Brick Masonry & C.E.(WR), WRD, Pune
R.C.C. Pipes MEMBERS
1) C.E.(WR), WRD, Aurangabad
2) C.E., Goshikhurd Project, Nagpur
3) C.E.(SP), WRD, Amravati
4) C.E., Tapi, Jalgaon.
(3) Lift Irrigation Scheme CO-ORDINATOR
C.E.( WR), WRD, Nagpur
MEMBERS
1) C.E.(WR), WRD, Pune
2) C.E.(WR), WRD, Aurangabad
3) C.E., Mechanical, WRD, Nashik
(4) Surveying & Investigation CO-ORDINATOR
C.E.(SP), WRD, Amravati
MEMBERS
1) C.E. & C.A., CADA, Aurangabad
2) S.E., T.I.C., Thane
(5) Tunnel Works CO-ORDINATOR
C.E., Hydroelectric Project, Pune
MEMBERS
1) C.E., Konkan Region, WRD, Mumbai
2) C.E.(WR), WRD, Aurangabad
3) C.E.(WR), WRD, Nagpur
(6) Maintenance & Repairs CO-ORDINATOR
C.E. & C.A., CADA, Aurangabad
MEMBERS
1) C.E.(WR), WRD, Aurangabad
2) C.E.(WR), WRD, Nagpur
3) C.E., N.M.R., Nashik
4) C.E., Mechanical, WRD, Nashik
5) C.E.(SP), WRD, Pune
6) S.E. & Director, D.I.R.D., Pune
Sr.No. Component of work Members of subcommittee
(7) Gates- Manufacturing & Repairs CO-ORDINATOR
C.E., Mechanical, WRD, Nashik
MEMBERS
1) C.E., N.M.R., Nashik
2) S.E., Gates Circle, C.D.O., Nashik
3) C.E.(WR), WRD, Aurangabad
4) S.E., Mechanical Circle, Pune

(8) Hydrology C.E.(WR), WRD, Nagpur

(9) Items for Valuation of Structures in C.E.(WR), WRD, Nagpur


affected villages

(10) Marking Blue Line & Red Line C.E.(WR), WRD, Pune

(11) Flow Measuring Devices C.E.(WR), WRD, Nagpur


GOVERNMENT OF MAHARASHTRA

WATER RESOURCES DEPARTMENT

COMMON SCHEDULE OF RATES FOR 2016-17

INDEX
Sr. Particulars Pages
No.
From To

1 SECTION-1 1 2

1.1 General Note 3 6

1.2 Lift Charges 7 8

1.3 Rates of Construction Materials & Labours 9 13

1.4 Lead Charges Statement for Materials 14 30

2 SECTION-2 31 34

Excavation & Embankment -Item 1 to 19 35 40

3 SECTION-3 41 44

Concrete Work including Centering, UCR Masonry, 45 56


Brick Masonry & R.C.C. Pipes -Item 20 to 60

4 SECTION-4 57 60

Maintenance & Repairs-Item 61 to 84 61 64

5 SECTION-5 65 68

Tunnel Works-Item 85 to 98 69 72

6 SECTION-6 73 76

Lift Irrigation Scheme-Item 99 to 131 77 90

7 SECTION-7 91 94

Surveying & Investigation-Item 132 to 152 95 100


Sr. Particulars Pages
No.
From To

8 SECTION-8 101 104

Hydrology-Item 153 to 159 105 106

9 SECTION-9 107 110

Items for Valuation of Structures in affected villages 111 114


Item 160 to 191

10 SECTION-10 115 118

Gates Manufacturing & Repairs-Item 192 to 208 119 134

11 SECTION-11 135 138

Flow Measuring Devices-Item 209 to 212 139 142

12 SECTION-12 143 146

Marking Blue Line & Red Line -Item 213 to 219 147 149
GOVERNMENT OF MAHARASHTRA

WATER RESOURCES DEPARTMENT

COMMON SCHEDULE OF RATES FOR 2016-17

SECTION-1

1.1 General Note

1.2 Lift Charges

1.3 Rates of Construction Materials & Labour

1.4 Lead charges statement for Materials

1
2
2016-17

(1.1)
:-
2016-17 01/11/2016 . 2016-17
.
) , , , . .
1) (VAT) : .
(M.Vat) TDS .
(M.Vat Act) 31
.
2) ,


(Excise Duty) :
.
3) , : .
,
: .
. (

.
4) -1090/-6453/-3, 14/07/1993
.
5) -2009/-108/ 7-, .17/06/2010

. : 1

.
6) . -1008/..28/98/., 19/08/1998
, ,
1
- .
. :
.
, [Cost put to tender] 1
, .

3
7) 2016-17
.

8) , ,
.
.

.

:- .. (1)
(8)
. - -
- .

) : :-

1) (Service provider) .
Cross
payment - . ( consultancy contract, survey
contract) , activities . . Testing
activity, IIIrd party inspection
. - .
- .
.

2) 10 .

3) .
30 . -2 10 : .
30 .

4) ,
2205/(246/2005)/-2, 13/09/2006
, , , ,
(), , , , , , ,
, , , , , , ,
( ),
10
. .629/.
2009-10/2010, 28/01/2010 20 .

4
5) .-2 -3 /
.
6)
- /
-2397/256/97 -2, 27/03/1997
.


.1098/146/99/-2, 17 2000
.

7) : 01/06/2015
.
.
7) : .290/ .

(.290/) .
8) Concrete with batching plant & Transit Mixer
. Batching plant
Mixer
Concrete with Batching plant & Transit Mixer
5 . Specifications .
9) /
( ) 10 .
.
10) (Dewatering) ,
1 .
3 .
11) Section-9 .

* 2016-17 Down load

5
6
COMMON SCHEDULE OF RATES 2016-17
(1.2) Lift charges by Head Load

Lift in m Rate as per CSR 2013-14 Rate as per CSR 2016-17

1.00 4.65 5.60

1.50 5.90 7.10

2.00 6.65 8.00

2.50 8.00 9.60

3.00 9.00 10.80

3.50 10.00 12.00

4.00 11.10 13.30

4.50 12.55 15.05

5.00 13.30 15.95

5.50 14.25 17.10

6.00 15.75 18.90

6.50 17.05 20.45

7.00 17.75 21.30

7.50 18.85 22.60

8.00 20.15 24.20

8.50 20.85 25.00

9.00 22.05 26.45

9.50 23.35 28.00

10.00 24.20 29.05

* These rates are applicable only for manual works & not for work
executed by Machinery.

7
8
GOVERNMENT OF MAHARASHTRA
WATER RESOURCES DEPARTMENT
COMMON SCHEDULE OF RATES FOR 2016-17
(1.3) RATES OF CONSTRUCTION MATERIALS
Sr.
Material Unit Rate in Rs.
No.
1 Acetylene Cum 390.00
2 Admixture Kg 75.00
3 Aldrop 30 cm No. 120.00
4 Bamboo 25 mm Rmt 20.00
5 Binding wire Kg 65.00
6 Black glass No. 89.00
7 Brick No. 6.00
8 Brushes No. 70.00
9 Butt Hinges Iron 125 mm No. 35.00
10 Cement (50 Kg bag) Bag 290.00
11 Coal tar paint Kg 55.00
12 Coaltar epoxy paint Litre 250.00
13 Coir string Kg 42.00
14 Copper plate Kg 572.00
15 Copper water stopper 16 gauge Sqm 9100.00
16 Cotton waste Kg 46.00
17 Curing compound Litre 134.00
18 Delay Detonator No. 20.00
19 Electric Detonator No. 12.00
20 Empty cement bag No. 10.00
21 First Aid Kit No. 250.00
22 Fly Ash Kg 1.00
23 Fuse coil Rmt. 20.00
24 G.P. Electrodes No. 11.00
25 Gelatin Kg 144.00
26 Geru Kg 12.00
27 Goggles No. 154.00
28 Hand gloves Pair 233.00

9
Sr. Material Unit Rate in Rs.
No.
29 Hand screen No. 370.00
30 Handle Iron 125 mm No. 35.00
31 Hook iron & eye oxi 75 mm No. 18.00
32 Hose pipe Oxygen & DA Rmt 82.00
33 J-Bolt (For soldier fixing) No 36.00
34 Kerosene Litre 30.00
35 L.H. Electrodes No. 15.00
36 Latches 250 mm No. 45.00
37 Manila Rope Kg 221.00
38 Metal size 40 mm & above (Including Royalty charges) Cum. 680.00
39 Metal size 40 mm & above (Excluding Royalty Cum. 538.66
charges)
40 Metal size less than 40 mm (Including Royalty Cum 780.00
charges)
41 Metal size less than 40 mm (Excluding Royalty Cum 638.66
charges)
42 Nails 4 cm Kg 68.00
43 Neoprene pad Cu.cm 2.00
44 Non Teak wood Cum 37000.00
45 Nozzle 3/64 No. 849.00
46 Nut bolts Kg 64.00
47 Nut bolts and washer Kg 99.00
48 Nylon Rope Kg 280.00
49 Oil paint Litre 250.00
50 Ordinary Detonator No. 7.00
51 Oxygen Cum 47.00
52 P.V.C. water stopper,310mm wide central bulb type Rmt 235.00
53 Painting brush 4 No. 100.00
54 Pickaxe No. 150.00
55 Plum bob No. 100.00
56 Polyethylene film 200 gauge Kg 238.75
57 Primer Litre 160.00
58 Red oxide Litre 140.00
10
Sr. Material Unit Rate in Rs.
No.
59 Rust cleaner Litre 310.00
60 Safety Helmet No. 250.00
61 Safety shoes Pair 1444.00
62 Sand (Including Royalty charges) Cum. 750.00
63 Sand (Excluding Royalty charges) Cum. 608.66
64 Shalitex super Expansion Pad 12 mm Tk. Sqm 621.25
65 Spirit level - 150 mm No. 120.00

66 Steel MT Rate as per


J.P.C.,
Dt.1/6/2015
67 Stone (Including Royalty charges) Cum. 480.00
68 Stone (Excluding Royalty charges) Cum. 338.66
69 Super plasticizer Kg 106.00
70 Turpentine Litre 70.00

71 Tower bolt Iron 200 mm No. 70.00


72 Tower bolt Iron 250 mm No. 80.00
73 Water 1000 Ltrs 32.00
74 Water proofing compound Kg 58.00
75 Welding cable 600 AMP Rmt 753.00
76 White glass No. 5.00
77 Wire brush No. 80.00
78 Wire mesh 50 X 50 - 13 gauge Sqm 200.00
79 Zink base oil paint Litre 318.00
80 Zink rich Epoxy primer Litre 289.00

11
12
GOVERNMENT OF MAHARASHTRA
WATER RESOURCES DEPARTMENT

COMMON SCHEDULE OF RATES FOR 2016-17


LABOUR RATES

Sr.
Labour Unit Rate in Rs.
No.
1 Barbender day 428.00
2 Bhisti day 428.00
3 CAD operator / Civil Engg. Assistant day 564.00
4 Carpenter day 455.00
5 Civil Engineer day 912.00
6 Electrician day 455.00
7 Fitter day 455.00
8 Fitter for shuttering day 455.00
9 Foreman day 455.00
10 Gas cutter day 428.00
11 Grinder day 428.00
12 Gauge Inspector day 428.00
13 Mason day 455.00
14 Mazdoor (Heavy) day 428.00
15 Mazdoor (Light) day 409.00
16 Measurement clerk day 455.00
17 Mechanic / Operator day 455.00
18 Mistri / Mukadam day 455.00
19 Painter day 455.00
20 Semiskilled Mazdoor day 428.00
21 Skilled Mazdoor day 455.00
22 Surveyor day 628.00
23 Tile Turner day 455.00
24 Tracer day 536.00
25 Unskilled Mazdoor day 409.00
26 Welder day 455.00

13
(1.4) Statement No.1
Average Speed Statement
Including Loading & unloading Charges

Qty of
Qty of Cost of Cost of 6 Hire Add 10 % Cost per
Lead in Av speed Mobile Oil Total of Lead in
No of Trips KM done Diesel 4 Cost of Diesel Mobile Oil Rs Mazdoors @ Charges of Total Cost Over head trip =
Km per hour 168.75 Col.11+12 Km
Km/Litre 290/Litre Rs.409/day Truck Charges Col.7/col.3
Km/Litre
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
N=8/((2*(L/ Col.No.5*57.1 Col. Rs Col. Col.No.11*0. Col.No.13/
L S (2*NL)+6 Col.No.4/4 Col.No.7*290 6*409 Col.11+12 L
S))+1) 7 No.4/168.75 2000/Day No.6+8+9+10 10 col.No.3
1.00 16.00 7.11 20.22 5.06 289.03 0.12 34.75 2454.00 2000 4778 477.78 5255.56 739 1.00
1.50 16.50 6.77 26.31 6.58 376.00 0.16 45.21 2454.00 2000 4875 487.52 5362.73 792 1.50
2.00 17.00 6.48 31.90 7.98 456.00 0.19 54.83 2454.00 2000 4965 496.48 5461.31 843 2.00
2.50 17.25 6.20 37.01 9.25 528.98 0.22 63.60 2454.00 2000 5047 504.66 5551.25 895 2.50
3.00 17.50 5.96 41.74 10.44 596.64 0.25 71.74 2454.00 2000 5122 512.24 5634.61 946 3.00
3.50 17.75 5.74 46.16 11.54 659.76 0.27 79.33 2454.00 2000 5193 519.31 5712.40 996 3.50
4.00 18.00 5.54 50.31 12.58 719.02 0.30 86.45 2454.00 2000 5259 525.95 5785.43 1045 4.00
4.50 18.25 5.36 54.22 13.56 774.94 0.32 93.18 2454.00 2000 5322 532.21 5854.33 1093 4.50
5.00 18.50 5.19 57.93 14.48 827.96 0.34 99.55 2454.00 2000 5382 538.15 5919.67 1140 5.00
6.00 18.75 4.88 64.54 16.13 922.39 0.38 110.91 2454.00 2000 5487 548.73 6036.03 1237 6.00
7.00 19.00 4.61 70.48 17.62 1007.40 0.42 121.13 2454.00 2000 5583 558.25 6140.79 1333 7.00
8.00 19.30 4.37 75.98 19.00 1085.99 0.45 130.58 2454.00 2000 5671 567.06 6237.62 1426 8.00
9.00 19.60 4.17 81.06 20.27 1158.60 0.48 139.31 2454.00 2000 5752 575.19 6327.11 1517 9.00
10.00 20.00 4.00 86.00 21.50 1229.16 0.51 147.79 2454.00 2000 5831 583.09 6414.04 1604 10.00
15.00 25.00 3.64 115.09 28.77 1644.94 0.68 197.79 2454.00 2000 6297 629.67 6926.39 1905 15.00
20.00 25.00 3.08 129.08 32.27 1844.83 0.76 221.82 2454.00 2000 6521 652.07 7172.72 2331 20.00
25.00 25.00 2.67 139.33 34.83 1991.42 0.83 239.45 2454.00 2000 6685 668.49 7353.36 2758 25.00
30.00 25.00 2.35 147.18 36.79 2103.52 0.87 252.93 2454.00 2000 6810 681.04 7491.49 3184 30.00
35.00 30.00 2.40 174.00 43.50 2486.90 1.03 299.02 2454.00 2000 7240 723.99 7963.91 3318 35.00
40.00 30.00 2.18 180.55 45.14 2580.45 1.07 310.27 2454.00 2000 7345 734.47 8079.19 3703 40.00
45.00 30.00 2.00 186.00 46.50 2658.41 1.10 319.64 2454.00 2000 7432 743.20 8175.25 4088 45.00
50.00 30.00 1.85 190.62 47.65 2724.37 1.13 327.58 2454.00 2000 7506 750.59 8256.54 4472 50.00
60.00 30.00 1.60 198.00 49.50 2829.92 1.17 340.27 2454.00 2000 7624 762.42 8386.60 5242 60.00
70.00 30.00 1.41 203.65 50.91 2910.63 1.21 349.97 2454.00 2000 7715 771.46 8486.06 6011 70.00
80.00 30.00 1.26 208.11 52.03 2974.34 1.23 357.63 2454.00 2000 7786 778.60 8564.57 6780 80.00
90.00 30.00 1.14 211.71 52.93 3025.93 1.25 363.83 2454.00 2000 7844 784.38 8628.14 7550 90.00
100.00 30.00 1.04 214.70 53.67 3068.54 1.27 368.96 2454.00 2000 7891 789.15 8680.65 8319 100.00
125.00 40.00 1.10 281.86 70.47 4028.51 1.67 484.39 2454.00 2000 8967 896.69 9863.59 8939 125.00
150.00 40.00 0.94 288.35 72.09 4121.28 1.71 495.54 2454.00 2000 9071 907.08 9977.91 10602 150.00
175.00 40.00 0.82 293.18 73.29 4190.27 1.74 503.83 2454.00 2000 9148 914.81 10062.91 12264 175.00
200.00 40.00 0.73 296.91 74.23 4243.57 1.76 510.24 2454.00 2000 9208 920.78 10128.60 13927 200.00

14
STATEMENT NO.2

Lead Charges
Rate per Steel , Lead in
Lead in Km Metal below Metal 40 Concrete
Trip Murum Earth Sand Rubble Water Cement, Excavated Rock Bricks Km
40 mm mm & above Block
Stone Block
As per col.
Col. No.2 / Col. No.2 / Col. No.2 / Col. No.2 / Col. No.2 / Col. No.2 / Col. No.2 / Col. No.2 /
No.13 of Col. No.2 / pay Col. No.2 / pay Col. No.2 / pay
L pay load pay load pay load pay load pay load pay load pay load pay load L
Statement load factor load factor load factor
factor factor factor factor factor factor factor factor
No.1
1 2 3 4 5 6 7 8 9 10 11 12 13 1
Unit Cum Cum Cum Cum Cum Cum 1000 Liters MT Cum Cum 1000 Unit
Pay Load Pay Load
6.00 4.80 5.00 5.00 4.62 4.25 9.00 7.00 3.00 6.00 2.00
Factor Factor
1.00 739 123.18 153.97 147.81 147.81 159.97 173.90 82.12 105.58 246.35 123.18 369.53 1.00
1.50 792 132.04 165.05 158.44 158.44 171.48 186.41 88.02 113.17 264.07 132.04 396.11 1.50
2.00 843 140.55 175.69 168.66 168.66 182.53 198.42 93.70 120.47 281.10 140.55 421.65 2.00
2.50 895 149.17 186.47 179.01 179.01 193.73 210.60 99.45 127.86 298.35 149.17 447.52 2.50
3.00 946 157.63 197.04 189.16 189.16 204.72 222.54 105.09 135.12 315.27 157.63 472.90 3.00
3.50 996 165.94 207.43 199.13 199.13 215.51 234.27 110.63 142.24 331.88 165.94 497.82 3.50
4.00 1045 174.10 217.62 208.92 208.92 226.10 245.79 116.07 149.23 348.20 174.10 522.30 4.00
4.50 1093 182.11 227.64 218.54 218.54 236.51 257.10 121.41 156.10 364.23 182.11 546.34 4.50
5.00 1140 189.99 237.49 227.99 227.99 246.74 268.22 126.66 162.85 379.98 189.99 569.97 5.00
6.00 1237 206.23 257.79 247.48 247.48 267.83 291.15 137.49 176.77 412.46 206.23 618.69 6.00
7.00 1333 222.20 277.75 266.64 266.64 288.57 313.69 148.13 190.46 444.40 222.20 666.60 7.00
8.00 1426 237.68 297.10 285.22 285.22 308.68 335.55 158.45 203.73 475.36 237.68 713.04 8.00
9.00 1517 252.87 316.09 303.44 303.44 328.40 356.99 168.58 216.74 505.74 252.87 758.61 9.00
10.00 1604 267.25 334.06 320.70 320.70 347.08 377.30 178.17 229.07 534.50 267.25 801.76 10.00
15.00 1905 317.46 396.82 380.95 380.95 412.29 448.18 211.64 272.11 634.92 317.46 952.38 15.00
20.00 2331 388.52 485.65 466.23 466.23 504.57 548.50 259.01 333.02 777.04 388.52 1165.57 20.00
25.00 2758 459.58 574.48 551.50 551.50 596.86 648.83 306.39 393.93 919.17 459.58 1378.75 25.00
30.00 3184 530.65 663.31 636.78 636.78 689.15 749.15 353.76 454.84 1061.29 530.65 1591.94 30.00
35.00 3318 553.05 691.31 663.66 663.66 718.25 780.78 368.70 474.04 1106.10 553.05 1659.15 35.00
40.00 3703 617.16 771.45 740.59 740.59 801.51 871.29 411.44 528.99 1234.32 617.16 1851.48 40.00
45.00 4088 681.27 851.59 817.53 817.53 884.77 961.79 454.18 583.95 1362.54 681.27 2043.81 45.00
50.00 4472 745.38 931.73 894.46 894.46 968.03 1052.30 496.92 638.90 1490.76 745.38 2236.15 50.00
60.00 5242 873.60 1092.01 1048.32 1048.32 1134.55 1233.32 582.40 748.80 1747.21 873.60 2620.81 60.00
70.00 6011 1001.83 1252.28 1202.19 1202.19 1301.07 1414.34 667.88 858.71 2003.65 1001.83 3005.48 70.00
80.00 6780 1130.05 1412.56 1356.06 1356.06 1467.59 1595.36 753.37 968.61 2260.10 1130.05 3390.14 80.00
90.00 7550 1258.27 1572.84 1509.92 1509.92 1634.12 1776.38 838.85 1078.52 2516.54 1258.27 3774.81 90.00
100.00 8319 1386.49 1733.12 1663.79 1663.79 1800.64 1957.40 924.33 1188.42 2772.98 1386.49 4159.48 100.00
125.00 8939 1489.81 1862.27 1787.78 1787.78 1934.82 2103.27 993.21 1276.98 2979.63 1489.81 4469.44 125.00
150.00 10602 1766.92 2208.65 2120.31 2120.31 2294.70 2494.48 1177.95 1514.50 3533.84 1766.92 5300.76 150.00
175.00 12264 2044.03 2555.04 2452.83 2452.83 2654.58 2885.69 1362.69 1752.02 4088.06 2044.03 6132.09 175.00
200.00 13927 2321.14 2901.42 2785.36 2785.36 3014.46 3276.90 1547.42 1989.55 4642.27 2321.14 6963.41 200.00

15
STATEMENT NO.3
LEAD CHARGES STATEMENT FOR 2016-17 (INCLUDING LOADING & UNLOADING CHARGES )

METAL BELOW METAL 40MM Steel , Cement,


LEAD MURUM EARTH SAND RUBBLE Water Excavated Rock Concrete Block Bricks
40MM & ABOVE Stone Block

As per Col No.3 As per Col No.4 As per Col No.5 As per Col No.6 As per Col No.7 As per Col No.8 As per Col No.9 As per Col No.10 As per Col No.11 As per Col No.12 As per Col No.13
L Of Statement Of Statement Of Statement Of Statement Of Statement Of Statement of Statement of Statement of Statement of Statement of Statement
No.2 No.2 No.2 No.2 No.2 No.2 No.2 No.2 No.2 No.2 No.2

KM Cum Cum Cum Cum Cum Cum 1000 Liters MT Cum Cum 1000
1.00 123.18 153.97 147.81 147.81 159.97 173.90 82.12 105.58 246.35 123.18 369.53
1.50 132.04 165.05 158.44 158.44 171.48 186.41 88.02 113.17 264.07 132.04 396.11
2.00 140.55 175.69 168.66 168.66 182.53 198.42 93.70 120.47 281.10 140.55 421.65
2.50 149.17 186.47 179.01 179.01 193.73 210.60 99.45 127.86 298.35 149.17 447.52
3.00 157.63 197.04 189.16 189.16 204.72 222.54 105.09 135.12 315.27 157.63 472.90
3.50 165.94 207.43 199.13 199.13 215.51 234.27 110.63 142.24 331.88 165.94 497.82
4.00 174.10 217.62 208.92 208.92 226.10 245.79 116.07 149.23 348.20 174.10 522.30
4.50 182.11 227.64 218.54 218.54 236.51 257.10 121.41 156.10 364.23 182.11 546.34
5.00 189.99 237.49 227.99 227.99 246.74 268.22 126.66 162.85 379.98 189.99 569.97
6.00 206.23 257.79 247.48 247.48 267.83 291.15 137.49 176.77 412.46 206.23 618.69
7.00 222.20 277.75 266.64 266.64 288.57 313.69 148.13 190.46 444.40 222.20 666.60
8.00 237.68 297.10 285.22 285.22 308.68 335.55 158.45 203.73 475.36 237.68 713.04
9.00 252.87 316.09 303.44 303.44 328.40 356.99 168.58 216.74 505.74 252.87 758.61
10.00 267.25 334.06 320.70 320.70 347.08 377.30 178.17 229.07 534.50 267.25 801.76
11.00 279.88 349.85 335.86 335.86 363.49 395.13 186.59 239.90 559.76 279.88 839.66
12.00 292.51 365.64 351.02 351.02 379.90 412.96 195.01 250.73 585.02 292.51 877.56
13.00 305.14 381.43 366.18 366.18 396.31 430.79 203.43 261.56 610.28 305.14 915.46
14.00 317.77 397.22 381.34 381.34 412.72 448.62 211.85 272.39 635.54 317.77 953.36
15.00 317.46 396.82 380.95 380.95 412.29 448.18 211.64 272.11 634.92 317.46 952.38
16.00 328.79 410.98 394.55 394.55 427.01 464.18 219.19 281.82 657.58 328.79 986.38
17.00 337.17 425.14 408.15 408.15 441.73 480.18 226.74 291.53 680.24 340.12 1020.38
18.00 345.55 439.30 421.75 421.75 456.45 496.18 234.29 301.24 702.90 351.45 1054.38
19.00 353.93 453.46 435.35 435.35 471.17 512.18 241.84 310.95 725.56 362.78 1088.38
20.00 388.52 485.65 466.23 466.23 504.57 548.50 259.01 333.02 777.04 388.52 1165.57
21.00 398.89 498.62 478.68 478.68 518.04 563.15 265.93 341.91 797.79 398.89 1196.69
22.00 409.26 511.59 491.13 491.13 531.51 577.80 272.85 350.80 818.54 409.26 1227.81
23.00 419.63 524.56 503.58 503.58 544.98 592.45 279.77 359.69 839.29 419.63 1258.93
24.00 430.00 537.53 516.03 516.03 558.45 607.10 286.69 368.58 860.04 430.00 1290.05
25.00 459.58 574.48 551.50 551.50 596.86 648.83 306.39 393.93 919.17 459.58 1378.75
26.00 469.23 586.54 563.08 563.08 609.39 662.45 312.82 402.20 938.46 469.23 1407.69
27.00 478.88 598.60 574.66 574.66 621.92 676.07 319.25 410.47 957.75 478.88 1436.63
28.00 488.53 610.66 586.24 586.24 634.45 689.69 325.68 418.74 977.04 488.53 1465.57
29.00 498.18 622.72 597.82 597.82 646.98 703.31 332.11 427.01 996.33 498.18 1494.51
30.00 530.65 663.31 636.78 636.78 689.15 749.15 353.76 454.84 1061.29 530.65 1591.94

16
STATEMENT NO.3
LEAD CHARGES STATEMENT FOR 2016-17 (INCLUDING LOADING & UNLOADING CHARGES )
METAL BELOW METAL 40MM & Steel, Cement,
LEAD MURUM EARTH SAND RUBBLE Water Excavated Rock Concrete Block Bricks
40MM ABOVE Stone Block
31.00 543.25 679.06 651.90 647.54 705.51 766.94 362.16 465.64 1086.49 543.25 1629.73
32.00 555.85 694.81 667.02 658.30 721.87 784.73 370.56 476.44 1111.69 555.85 1667.52
33.00 568.45 710.56 682.14 669.06 738.23 802.52 378.96 487.24 1136.89 568.45 1705.31
34.00 581.05 726.31 697.26 679.82 754.59 820.31 387.36 498.04 1162.09 581.05 1743.10
35.00 553.05 691.31 663.66 663.66 718.25 780.78 368.70 474.04 1106.10 553.05 1659.15
36.00 565.65 707.06 678.78 678.78 734.61 798.57 377.10 484.84 1131.30 565.65 1696.94
37.00 578.25 722.81 693.90 693.90 750.97 816.36 385.50 495.64 1156.50 578.25 1734.73
38.00 590.85 738.56 709.02 709.02 767.33 834.15 393.90 506.44 1181.70 590.85 1772.52
39.00 603.45 754.31 724.14 724.14 783.69 851.94 402.30 517.24 1206.90 603.45 1810.31
40.00 617.16 771.45 740.59 740.59 801.51 871.29 411.44 528.99 1234.32 617.16 1851.48
41.00 629.76 787.20 755.71 755.71 817.87 889.08 419.84 539.79 1259.52 629.76 1889.27
42.00 642.36 802.95 770.83 770.83 834.23 906.87 428.24 550.59 1284.72 642.36 1927.06
43.00 654.96 818.70 785.95 785.95 850.59 924.66 436.64 561.39 1309.92 654.96 1964.85
44.00 667.56 834.45 801.07 801.07 866.95 942.45 445.04 572.19 1335.12 667.56 2002.64
45.00 681.27 851.59 817.53 817.53 884.77 961.79 454.18 583.95 1362.54 681.27 2043.81
46.00 693.87 867.34 832.65 832.65 901.13 979.58 462.58 594.75 1387.74 693.87 2081.60
47.00 706.47 883.09 847.77 847.77 917.49 997.37 470.98 605.55 1412.94 706.47 2119.39
48.00 719.07 898.84 862.89 862.89 933.85 1015.16 479.38 616.35 1438.14 719.07 2157.18
49.00 731.67 914.59 878.01 878.01 950.21 1032.95 487.78 627.15 1463.34 731.67 2194.97
50.00 745.38 931.73 894.46 894.46 968.03 1052.30 496.92 638.90 1490.76 745.38 2236.15
51.00 757.98 947.48 909.58 909.58 984.39 1070.09 505.32 649.70 1515.96 757.98 2273.94
52.00 770.58 963.23 924.70 924.70 1000.75 1087.88 513.72 660.50 1541.16 770.58 2311.73
53.00 783.18 978.98 939.82 939.82 1017.11 1105.67 522.12 671.30 1566.36 783.18 2349.52
54.00 795.78 994.73 954.94 954.94 1033.47 1123.46 530.52 682.10 1591.56 795.78 2387.31
55.00 808.38 1010.48 970.06 970.06 1049.83 1141.25 538.92 692.90 1616.76 808.38 2425.10
56.00 820.98 1026.23 985.18 985.18 1066.19 1159.04 547.32 703.70 1641.96 820.98 2462.89
57.00 833.58 1041.98 1000.30 1000.30 1082.55 1176.83 555.72 714.50 1667.16 833.58 2500.68
58.00 846.18 1057.73 1015.42 1015.42 1098.91 1194.62 564.12 725.30 1692.36 846.18 2538.47
59.00 858.78 1073.48 1030.54 1030.54 1115.27 1212.41 572.52 736.10 1717.56 858.78 2576.26
60.00 873.60 1092.01 1048.32 1048.32 1134.55 1233.32 582.40 748.80 1747.21 873.60 2620.81
61.00 886.20 1107.76 1063.44 1063.44 1150.91 1251.11 590.80 759.60 1772.41 886.20 2658.60
62.00 898.80 1123.51 1078.56 1078.56 1167.27 1268.90 599.20 770.40 1797.61 898.80 2696.39
63.00 911.40 1139.26 1093.68 1093.68 1183.63 1286.69 607.60 781.20 1822.81 911.40 2734.18
64.00 924.00 1155.01 1108.80 1108.80 1199.99 1304.48 616.00 792.00 1848.01 924.00 2771.97
65.00 936.60 1170.76 1123.92 1123.92 1216.35 1322.27 624.40 802.80 1873.21 936.60 2809.76
66.00 949.20 1186.51 1139.04 1139.04 1232.71 1340.06 632.80 813.60 1898.41 949.20 2847.55
67.00 961.80 1202.26 1154.16 1154.16 1249.07 1357.85 641.20 824.40 1923.61 961.80 2885.34
68.00 974.40 1218.01 1169.28 1169.28 1265.43 1375.64 649.60 835.20 1948.81 974.40 2923.13
69.00 987.00 1233.76 1184.40 1184.40 1281.79 1393.43 658.00 846.00 1974.01 987.00 2960.92
70.00 1001.83 1252.28 1202.19 1202.19 1301.07 1414.34 667.88 858.71 2003.65 1001.83 3005.48

17
STATEMENT NO.3

LEAD CHARGES STATEMENT FOR 2016-17 (INCLUDING LOADING & UNLOADING CHARGES )

METAL BELOW METAL 40MM & Steel , Cement,


LEAD MURUM EARTH SAND RUBBLE Water Excavated Rock Concrete Block Bricks
40MM ABOVE Stone Block

71.00 1014.43 1268.03 1217.31 1217.31 1317.43 1432.13 676.28 869.51 2028.85 1014.43 3043.27
72.00 1027.03 1283.78 1232.43 1232.43 1333.79 1449.92 684.68 880.31 2054.05 1027.03 3081.06
73.00 1039.63 1299.53 1247.55 1247.55 1350.15 1467.71 693.08 891.11 2079.25 1039.63 3118.85
74.00 1052.23 1315.28 1262.67 1262.67 1366.51 1485.50 701.48 901.91 2104.45 1052.23 3156.64
75.00 1064.83 1331.03 1277.79 1277.79 1382.87 1503.29 709.88 912.71 2129.65 1064.83 3194.43
76.00 1077.43 1346.78 1292.91 1292.91 1399.23 1521.08 718.28 923.51 2154.85 1077.43 3232.22
77.00 1090.03 1362.53 1308.03 1308.03 1415.59 1538.87 726.68 934.31 2180.05 1090.03 3270.01
78.00 1102.63 1378.28 1323.15 1323.15 1431.95 1556.66 735.08 945.11 2205.25 1102.63 3307.80
79.00 1115.23 1394.03 1338.27 1338.27 1448.31 1574.45 743.48 955.91 2230.45 1115.23 3345.59
80.00 1130.05 1412.56 1356.06 1356.06 1467.59 1595.36 753.37 968.61 2260.10 1130.05 3390.14
81.00 1142.65 1428.31 1371.18 1371.18 1483.95 1613.15 761.77 979.41 2285.30 1142.65 3427.93
82.00 1155.25 1444.06 1386.30 1386.30 1500.31 1630.94 770.17 990.21 2310.50 1155.25 3465.72
83.00 1167.85 1459.81 1401.42 1401.42 1516.67 1648.73 778.57 1001.01 2335.70 1167.85 3503.51
84.00 1180.45 1475.56 1416.54 1416.54 1533.03 1666.52 786.97 1011.81 2360.90 1180.45 3541.30
85.00 1193.05 1491.31 1431.66 1431.66 1549.39 1684.31 795.37 1022.61 2386.10 1193.05 3579.09
86.00 1205.65 1507.06 1446.78 1446.78 1565.75 1702.10 803.77 1033.41 2411.30 1205.65 3616.88
87.00 1218.25 1522.81 1461.90 1461.90 1582.11 1719.89 812.17 1044.21 2436.50 1218.25 3654.67
88.00 1230.85 1538.56 1477.02 1477.02 1598.47 1737.68 820.57 1055.01 2461.70 1230.85 3692.46
89.00 1243.45 1554.31 1492.14 1492.14 1614.83 1755.47 828.97 1065.81 2486.90 1243.45 3730.25
90.00 1258.27 1572.84 1509.92 1509.92 1634.12 1773.26 838.85 1078.52 2516.54 1258.27 3774.81
91.00 1255.73 1569.67 1525.31 1506.87 1630.82 1791.05 837.16 1076.34 2511.46 1255.73 3767.19
92.00 1253.19 1566.50 1540.70 1503.82 1627.52 1808.84 835.47 1074.16 2506.38 1253.19 3759.57
93.00 1250.65 1563.33 1556.09 1500.77 1663.79 1826.63 833.78 1071.98 2501.30 1250.65 3751.95
94.00 1248.11 1560.16 1571.48 1497.72 1660.49 1844.42 832.09 1069.80 2496.22 1248.11 3744.33
95.00 1245.57 1556.99 1586.87 1494.67 1657.19 1862.21 830.40 1067.62 2491.14 1245.57 3736.71
96.00 1243.03 1553.82 1602.26 1491.62 1653.89 1880.00 828.71 1065.44 2486.06 1243.03 3729.09
97.00 1240.49 1550.65 1617.65 1488.57 1650.59 1897.79 827.02 1063.26 2480.98 1240.49 3721.47
98.00 1237.95 1547.48 1633.04 1485.52 1647.29 1915.58 825.33 1061.08 2475.90 1237.95 3713.85
99.00 1235.41 1544.31 1648.43 1482.47 1643.99 1933.37 823.64 1058.90 2470.82 1235.41 3706.23
100.00 1386.49 1733.12 1663.79 1663.79 1800.64 1957.40 924.33 1188.42 2772.98 1386.49 4159.48

18
LEAD CHARGES STATEMENT FOR 2016-17 (INCLUDING LOADING & UNLOADING CHARGES )
METAL BELOW METAL 40MM & Steel , Cement,
LEAD MURUM EARTH SAND RUBBLE Water Excavated Rock Concrete Block Bricks
40MM ABOVE Stone Block

101.00 1397.57 1746.97 1668.75 1668.75 1815.03 1973.05 931.72 1197.92 2795.15 1397.57 4192.73
102.00 1408.65 1760.83 1673.71 1673.71 1829.43 1988.70 939.11 1207.42 2817.32 1408.65 4225.98
103.00 1419.73 1774.68 1678.67 1678.67 1843.82 2004.34 946.50 1216.92 2839.49 1419.73 4259.23
104.00 1430.81 1788.54 1683.63 1683.63 1858.22 2019.99 953.88 1226.42 2861.66 1430.81 4292.48
105.00 1441.89 1802.39 1688.59 1688.59 1872.61 2035.64 961.27 1235.92 2883.82 1441.89 4325.73
106.00 1452.97 1816.25 1693.54 1693.54 1887.01 2051.29 968.66 1245.42 2905.99 1452.97 4358.98
107.00 1464.05 1830.10 1698.50 1698.50 1901.40 2066.94 976.05 1254.92 2928.16 1464.05 4392.23
108.00 1475.13 1843.96 1703.46 1703.46 1915.80 2082.58 983.44 1264.42 2950.33 1475.13 4425.48
109.00 1486.21 1857.81 1708.42 1708.42 1930.19 2098.23 990.83 1273.92 2972.50 1486.21 4458.73
110.00 1497.29 1871.67 1713.38 1713.38 1944.59 2113.88 998.22 1283.42 2994.66 1497.29 4491.98
111.00 1508.37 1885.52 1718.34 1718.34 1958.98 2129.53 1005.61 1292.92 3016.83 1508.37 4525.23
112.00 1519.45 1899.38 1723.30 1723.30 1973.38 2145.18 1013.00 1302.42 3039.00 1519.45 4558.48
113.00 1530.53 1913.23 1728.26 1728.26 1987.77 2160.82 1020.39 1311.92 3061.17 1530.53 4591.73
114.00 1541.61 1927.09 1733.22 1733.22 2002.17 2176.47 1027.77 1321.42 3083.34 1541.61 4624.98
115.00 1552.69 1940.94 1738.18 1738.18 2016.56 2192.12 1035.16 1330.92 3105.50 1552.69 4658.23
116.00 1563.77 1954.80 1743.13 1743.13 2030.96 2207.77 1042.55 1340.42 3127.67 1563.77 4691.48
117.00 1574.85 1968.65 1748.09 1748.09 2045.35 2223.42 1049.94 1349.92 3149.84 1574.85 4724.73
118.00 1585.93 1982.51 1753.05 1753.05 2059.75 2239.06 1057.33 1359.42 3172.01 1585.93 4757.98
119.00 1597.01 1996.36 1758.01 1758.01 2074.14 2254.71 1064.72 1368.92 3194.18 1597.01 4791.23
120.00 1608.09 2010.22 1762.97 1762.97 2088.54 2270.36 1072.11 1378.42 3216.34 1608.09 4824.48
121.00 1619.17 2024.07 1767.93 1767.93 2102.93 2286.01 1079.50 1387.92 3238.51 1619.17 4857.73
122.00 1630.25 2037.93 1772.89 1772.89 2117.33 2301.66 1086.89 1397.42 3260.68 1630.25 4890.98
123.00 1641.33 2051.78 1777.85 1777.85 2131.72 2317.30 1094.28 1406.92 3282.85 1641.33 4924.23
124.00 1652.41 2065.64 1782.81 1782.81 2146.12 2332.95 1101.66 1416.42 3305.02 1652.41 4957.48
125.00 1489.81 1862.27 1787.78 1787.78 1934.82 2103.27 993.21 1276.98 2979.63 1489.81 4469.44
126.00 1500.89 1876.12 1801.07 1801.08 1949.22 2118.91 1000.60 1286.48 3001.79 1500.89 4502.69
127.00 1511.97 1889.98 1814.37 1814.38 1963.61 2134.56 1007.99 1295.98 3023.96 1511.97 4535.94
128.00 1523.05 1903.83 1827.67 1827.68 1978.01 2150.21 1015.38 1305.48 3046.13 1523.05 4569.19
129.00 1534.13 1917.69 1840.97 1840.98 1992.40 2165.86 1022.76 1314.98 3068.30 1534.13 4602.44
130.00 1545.21 1931.54 1854.27 1854.28 2006.80 2181.51 1030.15 1324.48 3090.47 1545.21 4635.69
131.00 1556.29 1945.40 1867.57 1867.58 2021.19 2197.15 1037.54 1333.98 3112.63 1556.29 4668.94
132.00 1567.37 1959.25 1880.87 1880.88 2035.59 2212.80 1044.93 1343.48 3134.80 1567.37 4702.19
133.00 1578.45 1973.11 1894.17 1894.18 2049.98 2228.45 1052.32 1352.98 3156.97 1578.45 4735.44
134.00 1589.53 1986.96 1907.47 1907.48 2064.38 2244.10 1059.71 1362.48 3179.14 1589.53 4768.69
135.00 1600.61 2000.82 1920.77 1920.78 2078.77 2259.75 1067.10 1371.98 3201.31 1600.61 4801.94

19
LEAD CHARGES STATEMENT FOR 2016-17 (INCLUDING LOADING & UNLOADING CHARGES )
METAL BELOW METAL 40MM & Steel , Cement,
LEAD MURUM EARTH SAND RUBBLE Water Excavated Rock Concrete Block Bricks
40MM ABOVE Stone Block
136.00 1611.69 2014.67 1934.06 1934.08 2093.17 2275.39 1074.49 1381.48 3223.47 1611.69 4835.19
137.00 1622.77 2028.53 1947.36 1947.38 2107.56 2291.04 1081.88 1390.98 3245.64 1622.77 4868.44
138.00 1633.85 2042.38 1960.66 1960.68 2121.96 2306.69 1089.27 1400.48 3267.81 1633.85 4901.69
139.00 1644.93 2056.24 1973.96 1973.98 2136.35 2322.34 1096.65 1409.98 3289.98 1644.93 4934.94
140.00 1656.01 2070.09 1987.26 1987.28 2150.75 2337.99 1104.04 1419.48 3312.15 1656.01 4968.19
141.00 1667.09 2083.95 2000.56 2000.58 2165.14 2353.63 1111.43 1428.98 3334.31 1667.09 5001.44
142.00 1678.17 2097.80 2013.86 2013.88 2179.54 2369.28 1118.82 1438.48 3356.48 1678.17 5034.69
143.00 1689.25 2111.66 2027.16 2027.18 2193.93 2384.93 1126.21 1447.98 3378.65 1689.25 5067.94
144.00 1700.33 2125.51 2040.46 2040.48 2208.33 2400.58 1133.60 1457.48 3400.82 1700.33 5101.19
145.00 1711.41 2139.37 2053.76 2053.78 2222.72 2416.23 1140.99 1466.98 3422.99 1711.41 5134.44
146.00 1722.49 2153.22 2067.05 2067.08 2237.12 2431.87 1148.38 1476.48 3445.15 1722.49 5167.69
147.00 1733.57 2167.08 2080.35 2080.38 2251.51 2447.52 1155.77 1485.98 3467.32 1733.57 5200.94
148.00 1744.65 2180.93 2093.65 2093.68 2265.91 2463.17 1163.16 1495.48 3489.49 1744.65 5234.19
149.00 1755.73 2194.79 2106.95 2106.98 2280.30 2478.82 1170.54 1504.98 3511.66 1755.73 5267.44
150.00 1766.92 2208.65 2120.31 2120.31 2294.70 2494.48 1177.95 1514.50 3533.84 1766.92 5300.76
151.00 1778.00 2222.51 2133.60 2133.61 2309.10 2510.12 1185.34 1524.00 3556.01 1778.00 5334.01
152.00 1789.08 2236.36 2146.90 2146.91 2323.49 2525.77 1192.73 1533.50 3578.18 1789.08 5367.26
153.00 1800.16 2250.22 2160.20 2160.21 2337.89 2541.42 1200.11 1543.00 3600.35 1800.16 5400.51
154.00 1811.24 2264.07 2173.50 2173.51 2352.28 2557.07 1207.50 1552.50 3622.51 1811.24 5433.76
155.00 1822.32 2277.93 2186.80 2186.81 2366.68 2572.72 1214.89 1562.00 3644.68 1822.32 5467.01
156.00 1833.40 2291.78 2200.10 2200.11 2381.07 2588.36 1222.28 1571.50 3666.85 1833.40 5500.26
157.00 1844.48 2305.64 2213.40 2213.41 2395.47 2604.01 1229.67 1581.00 3689.02 1844.48 5533.51
158.00 1855.56 2319.49 2226.70 2226.71 2409.86 2619.66 1237.06 1590.50 3711.19 1855.56 5566.76
159.00 1866.64 2333.35 2240.00 2240.01 2424.26 2635.31 1244.45 1600.00 3733.35 1866.64 5600.01
160.00 1877.72 2347.20 2253.30 2253.31 2438.65 2650.96 1251.84 1609.50 3755.52 1877.72 5633.26
161.00 1888.80 2361.06 2266.59 2266.61 2453.05 2666.60 1259.23 1619.00 3777.69 1888.80 5666.51
162.00 1899.88 2374.91 2279.89 2279.91 2467.44 2682.25 1266.62 1628.50 3799.86 1899.88 5699.76
163.00 1910.96 2388.77 2293.19 2293.21 2481.84 2697.90 1274.00 1638.00 3822.03 1910.96 5733.01
164.00 1922.04 2402.62 2306.49 2306.51 2496.23 2713.55 1281.39 1647.50 3844.19 1922.04 5766.26
165.00 1933.12 2416.48 2319.79 2319.81 2510.63 2729.20 1288.78 1657.00 3866.36 1933.12 5799.51
166.00 1944.20 2430.33 2333.09 2333.11 2525.02 2744.84 1296.17 1666.50 3888.53 1944.20 5832.76
167.00 1955.28 2444.19 2346.39 2346.41 2539.42 2760.49 1303.56 1676.00 3910.70 1955.28 5866.01
168.00 1966.36 2458.04 2359.69 2359.71 2553.81 2776.14 1310.95 1685.50 3932.87 1966.36 5899.26
169.00 1977.44 2471.90 2372.99 2373.01 2568.21 2791.79 1318.34 1695.00 3955.03 1977.44 5932.51
170.00 1988.52 2485.75 2386.29 2386.31 2582.60 2807.44 1325.73 1704.50 3977.20 1988.52 5965.76

20
LEAD CHARGES STATEMENT FOR 2016-17 (INCLUDING LOADING & UNLOADING CHARGES )
METAL BELOW METAL 40MM & Steel , Cement,
LEAD MURUM EARTH SAND RUBBLE Water Excavated Rock Concrete Block Bricks
40MM ABOVE Stone Block

171.00 1999.60 2499.61 2399.58 2399.61 2597.00 2823.08 1333.12 1714.00 3999.37 1999.60 5999.01
172.00 2010.68 2513.46 2412.88 2412.91 2611.39 2838.73 1340.51 1723.50 4021.54 2010.68 6032.26
173.00 2021.76 2527.32 2426.18 2426.21 2625.79 2854.38 1347.89 1733.00 4043.71 2021.76 6065.51
174.00 2032.84 2541.17 2439.48 2439.51 2640.18 2870.03 1355.28 1742.50 4065.87 2032.84 6098.76
175.00 2044.03 2555.04 2452.83 2452.83 2654.58 2885.69 1362.69 1752.02 4088.06 2044.03 6132.09
176.00 2055.11 2568.89 2466.13 2466.13 2668.98 2901.34 1370.08 1761.52 4110.23 2055.11 6165.34
177.00 2066.19 2582.75 2479.43 2479.43 2683.37 2916.98 1377.46 1771.02 4132.39 2066.19 6198.59
178.00 2077.27 2596.60 2492.73 2492.73 2697.77 2932.63 1384.85 1780.52 4154.56 2077.27 6231.84
179.00 2088.35 2610.46 2506.03 2506.03 2712.16 2948.28 1392.24 1790.02 4176.73 2088.35 6265.09
180.00 2099.43 2624.31 2519.33 2519.33 2726.56 2963.93 1399.63 1799.52 4198.90 2099.43 6298.34
181.00 2110.51 2638.17 2532.63 2532.63 2740.95 2979.58 1407.02 1809.02 4221.07 2110.51 6331.59
182.00 2121.59 2652.02 2545.93 2545.93 2755.35 2995.22 1414.41 1818.52 4243.23 2121.59 6364.84
183.00 2132.67 2665.88 2559.23 2559.23 2769.74 3010.87 1421.80 1828.02 4265.40 2132.67 6398.09
184.00 2143.75 2679.73 2572.53 2572.53 2784.14 3026.52 1429.19 1837.52 4287.57 2143.75 6431.34
185.00 2154.83 2693.59 2585.82 2585.83 2798.53 3042.17 1436.58 1847.02 4309.74 2154.83 6464.59
186.00 2165.91 2707.44 2599.12 2599.13 2812.93 3057.82 1443.97 1856.52 4331.91 2165.91 6497.84
187.00 2176.99 2721.30 2612.42 2612.43 2827.32 3073.46 1451.35 1866.02 4354.07 2176.99 6531.09
188.00 2188.07 2735.15 2625.72 2625.73 2841.72 3089.11 1458.74 1875.52 4376.24 2188.07 6564.34
189.00 2199.15 2749.01 2639.02 2639.03 2856.11 3104.76 1466.13 1885.02 4398.41 2199.15 6597.59
190.00 2210.23 2762.86 2652.32 2652.33 2870.51 3120.41 1473.52 1894.52 4420.58 2210.23 6630.84
191.00 2221.31 2776.72 2665.62 2665.63 2884.90 3136.06 1480.91 1904.02 4442.75 2221.31 6664.09
192.00 2232.39 2790.57 2678.92 2678.93 2899.30 3151.70 1488.30 1913.52 4464.91 2232.39 6697.34
193.00 2243.47 2804.43 2692.22 2692.23 2913.69 3167.35 1495.69 1923.02 4487.08 2243.47 6730.59
194.00 2254.55 2818.28 2705.52 2705.53 2928.09 3183.00 1503.08 1932.52 4509.25 2254.55 6763.84
195.00 2265.63 2832.14 2718.81 2718.83 2942.48 3198.65 1510.47 1942.02 4531.42 2265.63 6797.09
196.00 2276.71 2845.99 2732.11 2732.13 2956.88 3214.30 1517.86 1951.52 4553.59 2276.71 6830.34
197.00 2287.79 2859.85 2745.41 2745.43 2971.27 3229.94 1525.24 1961.02 4575.75 2287.79 6863.59
198.00 2298.87 2873.70 2758.71 2758.73 2985.67 3245.59 1532.63 1970.52 4597.92 2298.87 6896.84
199.00 2309.95 2887.56 2772.01 2772.03 3000.06 3261.24 1540.02 1980.02 4620.09 2309.95 6930.09
200.00 2321.14 2901.42 2785.36 2785.36 3014.46 3276.90 1547.42 1989.55 4642.27 2321.14 6963.41

21
Statement No.1
Average Speed Statement
Excluding Loading & unloading Charges
Av Qty of Qty of Mobile Cost of
Lead in Hire Charges Add 10 % Over Total of Cost per trip Lead in
speed No of Trips KM done Diesel 4 Cost of Diesel Oil 168.75 Mobile Oil Rs Total Cost
Km of Truck head Charges Col.5+6 = Col.7/col.3 Km
per hour Km/Litre Km/Litre 290/Litre
1 2 3 4 5 6 7 8 9 10 11 12 13 1
N=8/((2* col.No.12/
L S (2*NL)+6 Col.No.4/4 Col.No.5*57.17 Col. No.4/168.75 Col.No.7*290 Rs 2000/Day Col. No.6+8+9 Col.No.10*0.10 Col.10+11 L
(L/S)) +1) col.No.3
1.00 16.00 7.11 20.22 5.06 289.03 0.12 34.75 2000 2324 232.38 2556.16 359 1.00
1.50 16.50 6.77 26.31 6.58 376.00 0.16 45.21 2000 2421 242.12 2663.33 393 1.50
2.00 17.00 6.48 31.90 7.98 456.00 0.19 54.83 2000 2511 251.08 2761.91 426 2.00
2.50 17.25 6.20 37.01 9.25 528.98 0.22 63.60 2000 2593 259.26 2851.85 460 2.50
3.00 17.50 5.96 41.74 10.44 596.64 0.25 71.74 2000 2668 266.84 2935.21 493 3.00
3.50 17.75 5.74 46.16 11.54 659.76 0.27 79.33 2000 2739 273.91 3013.00 525 3.50
4.00 18.00 5.54 50.31 12.58 719.02 0.30 86.45 2000 2805 280.55 3086.03 557 4.00
4.50 18.25 5.36 54.22 13.56 774.94 0.32 93.18 2000 2868 286.81 3154.93 589 4.50
5.00 18.50 5.19 57.93 14.48 827.96 0.34 99.55 2000 2928 292.75 3220.27 620 5.00
6.00 18.75 4.88 64.54 16.13 922.39 0.38 110.91 2000 3033 303.33 3336.63 684 6.00
7.00 19.00 4.61 70.48 17.62 1007.40 0.42 121.13 2000 3129 312.85 3441.39 747 7.00
8.00 19.30 4.37 75.98 19.00 1085.99 0.45 130.58 2000 3217 321.66 3538.22 809 8.00
9.00 19.60 4.17 81.06 20.27 1158.60 0.48 139.31 2000 3298 329.79 3627.71 870 9.00
10.00 20.00 4.00 86.00 21.50 1229.16 0.51 147.79 2000 3377 337.69 3714.64 929 10.00
15.00 25.00 3.64 115.09 28.77 1644.94 0.68 197.79 2000 3843 384.27 4226.99 1162 15.00
20.00 25.00 3.08 129.08 32.27 1844.83 0.76 221.82 2000 4067 406.67 4473.32 1454 20.00
25.00 25.00 2.67 139.33 34.83 1991.42 0.83 239.45 2000 4231 423.09 4653.96 1745 25.00
30.00 25.00 2.35 147.18 36.79 2103.52 0.87 252.93 2000 4356 435.64 4792.09 2037 30.00
35.00 30.00 2.40 174.00 43.50 2486.90 1.03 299.02 2000 4786 478.59 5264.51 2194 35.00
40.00 30.00 2.18 180.55 45.14 2580.45 1.07 310.27 2000 4891 489.07 5379.79 2466 40.00
45.00 30.00 2.00 186.00 46.50 2658.41 1.10 319.64 2000 4978 497.80 5475.85 2738 45.00
50.00 30.00 1.85 190.62 47.65 2724.37 1.13 327.58 2000 5052 505.19 5557.14 3010 50.00
60.00 30.00 1.60 198.00 49.50 2829.92 1.17 340.27 2000 5170 517.02 5687.20 3554 60.00
70.00 30.00 1.41 203.65 50.91 2910.63 1.21 349.97 2000 5261 526.06 5786.66 4099 70.00
80.00 30.00 1.26 208.11 52.03 2974.34 1.23 357.63 2000 5332 533.20 5865.17 4643 80.00
90.00 30.00 1.14 211.71 52.93 3025.93 1.25 363.83 2000 5390 538.98 5928.74 5188 90.00
100.00 30.00 1.04 214.70 53.67 3068.54 1.27 368.96 2000 5437 543.75 5981.25 5732 100.00
125.00 40.00 1.10 281.86 70.47 4028.51 1.67 484.39 2000 6513 651.29 7164.19 6493 125.00
150.00 40.00 0.94 288.35 72.09 4121.28 1.71 495.54 2000 6617 661.68 7278.51 7733 150.00
175.00 40.00 0.82 293.18 73.29 4190.27 1.74 503.83 2000 6694 669.41 7363.51 8974 175.00
200.00 40.00 0.73 296.91 74.23 4243.57 1.76 510.24 2000 6754 675.38 7429.20 10215 200.00

22
Statement No.2
Lead Charges
Lead in Lead in
Rate per Trip Metal below Metal 40 mm Steel, Cement, Concrete
Km Murum Earth Sand Rubble Water Excavated Rock Bricks Km
40 mm & above Stone Block Block
As per col. No. Col. No.2 / Col. No.2 / Col. No.2 / Col. No.2 / Col. No.2 / Col. No.2 / Col. No.2 / Col. No.2 / Col. No.2 /
Col. No.2 / pay Col. No.2 / pay
L 13 of pay load pay load pay load pay load pay load pay load pay load pay load pay load L
load factor load factor
Statement No.1 factor factor factor factor factor factor factor factor factor
1 2 3 4 5 6 7 8 9 10 11 12 13 1
Unit Cum Cum Cum Cum Cum Cum 1000 Liters MT Cum Cum 1000 Unit
Pay Load Pay Load
6.00 4.80 5.00 5.00 4.62 4.25 9.00 7.00 3.00 6.00 2.00
Factor Factor
1.00 359 59.91 74.89 71.89 71.89 77.81 84.58 39.94 51.35 119.82 59.91 179.73 1.00
1.50 393 65.57 81.97 78.69 78.69 85.16 92.58 43.72 56.21 131.15 65.57 196.72 1.50
2.00 426 71.08 88.85 85.29 85.29 92.31 100.35 47.39 60.92 142.16 71.08 213.24 2.00
2.50 460 76.63 95.79 91.96 91.96 99.53 108.19 51.09 65.69 153.27 76.63 229.90 2.50
3.00 493 82.12 102.65 98.54 98.54 106.64 115.93 54.74 70.39 164.23 82.12 246.35 3.00
3.50 525 87.53 109.41 105.03 105.03 113.67 123.57 58.35 75.02 175.05 87.53 262.58 3.50
4.00 557 92.87 116.08 111.44 111.44 120.61 131.11 61.91 79.60 185.73 92.87 278.60 4.00
4.50 589 98.14 122.68 117.77 117.77 127.46 138.55 65.43 84.12 196.28 98.14 294.42 4.50
5.00 620 103.35 129.19 124.02 124.02 134.22 145.91 68.90 88.59 206.71 103.35 310.06 5.00
6.00 684 114.00 142.50 136.80 136.80 148.05 160.94 76.00 97.72 228.00 114.00 342.00 6.00
7.00 747 124.52 155.65 149.43 149.43 161.72 175.80 83.02 106.73 249.05 124.52 373.57 7.00
8.00 809 134.82 168.53 161.79 161.79 175.09 190.34 89.88 115.56 269.64 134.82 404.47 8.00
9.00 870 144.98 181.23 173.98 173.98 188.29 204.68 96.66 124.27 289.97 144.98 434.95 9.00
10.00 929 154.78 193.47 185.73 185.73 201.01 218.51 103.18 132.67 309.55 154.78 464.33 10.00
15.00 1162 193.74 242.17 232.48 232.48 251.61 273.51 129.16 166.06 387.47 193.74 581.21 15.00
20.00 1454 242.30 302.88 290.77 290.77 314.68 342.08 161.54 207.69 484.61 242.30 726.91 20.00
25.00 1745 290.87 363.59 349.05 349.05 377.76 410.64 193.91 249.32 581.74 290.87 872.62 25.00
30.00 2037 339.44 424.30 407.33 407.33 440.83 479.21 226.29 290.95 678.88 339.44 1018.32 30.00
35.00 2194 365.59 456.99 438.71 438.71 474.79 516.13 243.73 313.36 731.18 365.59 1096.77 35.00
40.00 2466 410.96 513.70 493.15 493.15 533.71 580.17 273.97 352.25 821.91 410.96 1232.87 40.00
45.00 2738 456.32 570.40 547.59 547.59 592.62 644.22 304.21 391.13 912.64 456.32 1368.96 45.00
50.00 3010 501.69 627.11 602.02 602.02 651.54 708.26 334.46 430.02 1003.37 501.69 1505.06 50.00
60.00 3554 592.42 740.52 710.90 710.90 769.37 836.35 394.94 507.79 1184.83 592.42 1777.25 60.00
70.00 4099 683.15 853.93 819.78 819.78 887.20 964.44 455.43 585.55 1366.29 683.15 2049.44 70.00
80.00 4643 773.88 967.35 928.65 928.65 1005.04 1092.53 515.92 663.32 1547.75 773.88 2321.63 80.00
90.00 5188 864.61 1080.76 1037.53 1037.53 1122.87 1220.62 576.41 741.09 1729.22 864.61 2593.82 90.00
100.00 5732 955.34 1194.17 1146.41 1146.41 1240.70 1348.71 636.89 818.86 1910.68 955.34 2866.01 100.00
125.00 6493 1082.09 1352.61 1298.51 1298.51 1405.31 1527.66 721.39 927.51 2164.18 1082.09 3246.27 125.00
150.00 7733 1288.90 1611.13 1546.68 1546.68 1673.90 1819.63 859.27 1104.77 2577.80 1288.90 3866.71 150.00
175.00 8974 1495.71 1869.64 1794.86 1794.86 1942.49 2111.60 997.14 1282.04 2991.43 1495.71 4487.14 175.00
200.00 10215 1702.52 2128.16 2043.03 2043.03 2211.07 2403.56 1135.02 1459.31 3405.05 1702.52 5107.57 200.00

23
Statement No.3
LEAD CHARGES STATEMENT FOR 2016-17 (EXCLUDING LOADING & UNLOADING )
METAL BELOW METAL 40MM Steel , Cement,
LEAD MURUM EARTH SAND RUBBLE Water Excavated Rock Concrete Block Bricks
40MM & ABOVE Stone Block

As per Col No.3 As per Col No.4 As per Col No.5 As per Col No.6 As per Col No.7 As per Col No.8 As per Col No.9 As per Col No.10 As per Col No.11 As per Col No.12 As per Col No.13
L Of Statement Of Statement Of Statement Of Statement Of Statement Of Statement of Statement of Statement of Statement of Statement of Statement
No.2 No.2 No.2 No.2 No.2 No.2 No.2 No.2 No.2 No.2 No.2

KM Cum Cum Cum Cum Cum Cum 1000 Liters MT Cum Cum 1000
1.00 59.91 74.89 71.89 71.89 77.81 84.58 39.94 51.35 119.82 59.91 179.73
1.50 65.57 81.97 78.69 78.69 85.16 92.58 43.72 56.21 131.15 65.57 196.72
2.00 71.08 88.85 85.29 85.29 92.31 100.35 47.39 60.92 142.16 71.08 213.24
2.50 76.63 95.79 91.96 91.96 99.53 108.19 51.09 65.69 153.27 76.63 229.90
3.00 82.12 102.65 98.54 98.54 106.64 115.93 54.74 70.39 164.23 82.12 246.35
3.50 87.53 109.41 105.03 105.03 113.67 123.57 58.35 75.02 175.05 87.53 262.58
4.00 92.87 116.08 111.44 111.44 120.61 131.11 61.91 79.60 185.73 92.87 278.60
4.50 98.14 122.68 117.77 117.77 127.46 138.55 65.43 84.12 196.28 98.14 294.42
5.00 103.35 129.19 124.02 124.02 134.22 145.91 68.90 88.59 206.71 103.35 310.06
6.00 114.00 142.50 136.80 136.80 148.05 160.94 76.00 97.72 228.00 114.00 342.00
7.00 124.52 155.65 149.43 149.43 161.72 175.80 83.02 106.73 249.05 124.52 373.57
8.00 134.82 168.53 161.79 161.79 175.09 190.34 89.88 115.56 269.64 134.82 404.47
9.00 144.98 181.23 173.98 173.98 188.29 204.68 96.66 124.27 289.97 144.98 434.95
10.00 154.78 193.47 185.73 185.73 201.01 218.51 103.18 132.67 309.55 154.78 464.33
11.00 162.57 203.21 195.08 195.08 211.13 229.51 108.37 139.34 325.13 162.57 487.71
12.00 170.36 212.95 204.43 204.43 221.25 240.51 113.56 146.02 340.71 170.36 511.08
13.00 178.15 222.69 213.78 213.78 231.37 251.51 118.75 152.70 356.29 178.15 534.46
14.00 185.94 232.43 223.13 223.13 241.48 262.51 123.94 159.38 371.87 185.94 557.83
15.00 193.74 242.17 232.48 232.48 251.61 273.51 129.16 166.06 387.47 193.74 581.21
16.00 203.45 254.31 244.13 244.13 264.22 287.22 135.63 174.38 406.89 203.45 610.35
17.00 213.16 266.45 255.78 255.78 276.83 300.93 142.10 182.70 426.31 213.16 639.49
18.00 222.88 278.59 267.43 267.43 289.44 314.64 148.57 191.02 445.73 222.87 668.63
19.00 232.59 290.73 279.08 279.08 302.05 328.35 155.04 199.34 465.15 232.58 697.77
20.00 242.30 302.88 290.77 290.77 314.68 342.08 161.54 207.69 484.61 242.30 726.91
21.00 252.01 315.02 302.42 302.42 327.29 355.79 168.01 216.01 504.03 252.01 756.05
22.00 261.72 327.16 314.07 314.07 339.90 369.50 174.48 224.33 523.45 261.72 785.19
23.00 271.43 339.30 325.72 325.72 352.51 383.21 180.95 232.65 542.87 271.43 814.33
24.00 281.14 351.44 337.37 337.37 365.12 396.92 187.42 240.97 562.29 281.14 843.47
25.00 290.87 363.59 349.05 349.05 377.76 410.64 193.91 249.32 581.74 290.87 872.62
26.00 300.58 375.73 360.70 360.70 390.37 424.35 200.38 257.64 601.16 300.58 901.76
27.00 310.29 387.87 372.35 372.35 402.98 438.06 206.85 265.96 620.58 310.29 930.90
28.00 320.00 400.01 384.00 384.00 415.59 451.77 213.32 274.28 640.00 320.00 960.04
29.00 329.71 412.15 395.65 395.65 428.20 465.48 219.79 282.60 659.42 329.71 989.18
30.00 339.44 424.30 407.33 407.33 440.83 479.21 226.29 290.95 678.88 339.44 1018.32

24
METAL BELOW METAL 40MM Steel , Cement,
LEAD MURUM EARTH SAND RUBBLE Water Excavated Rock Concrete Block Bricks
40MM & ABOVE Stone Block

31.00 344.67 430.83 413.60 413.60 447.62 486.59 229.77 295.43 689.34 344.67 1034.01
32.00 349.90 437.36 419.87 419.87 454.41 493.97 233.25 299.91 699.80 349.90 1049.70
33.00 355.13 443.89 426.14 426.14 461.20 501.35 236.73 304.39 710.26 355.13 1065.39
34.00 360.36 450.42 432.41 432.41 467.99 508.73 240.21 308.87 720.72 360.36 1081.08
35.00 365.59 456.99 438.71 438.71 474.79 516.13 243.73 313.36 731.18 365.59 1096.77
36.00 374.66 468.33 449.59 449.59 486.57 528.93 249.77 321.13 749.32 374.66 1123.98
37.00 383.73 479.67 460.47 460.47 498.35 541.73 255.81 328.90 767.46 383.73 1151.19
38.00 392.80 491.01 471.35 471.35 510.13 554.53 261.85 336.67 785.60 392.80 1178.40
39.00 401.87 502.35 482.23 482.23 521.91 567.33 267.89 344.44 803.74 401.87 1205.61
40.00 410.96 513.70 493.15 493.15 533.71 580.17 273.97 352.25 821.91 410.96 1232.87
41.00 420.03 525.04 504.03 504.03 545.49 592.97 280.01 360.02 840.05 420.03 1260.08
42.00 429.10 536.38 514.91 514.91 557.27 605.77 286.05 367.79 858.19 429.10 1287.29
43.00 438.17 547.72 525.79 525.79 569.05 618.57 292.09 375.56 876.33 438.17 1314.50
44.00 447.24 559.06 536.67 536.67 580.83 631.37 298.13 383.33 894.47 447.24 1341.71
45.00 456.32 570.40 547.59 547.59 592.62 644.22 304.21 391.13 912.64 456.32 1368.96
46.00 465.39 581.74 558.47 558.47 604.40 657.02 310.25 398.90 930.78 465.39 1396.17
47.00 474.46 593.08 569.35 569.35 616.18 669.82 316.29 406.67 948.92 474.46 1423.38
48.00 483.53 604.42 580.23 580.23 627.96 682.62 322.33 414.44 967.06 483.53 1450.59
49.00 492.60 615.76 591.11 591.11 639.74 695.42 328.37 422.21 985.20 492.60 1477.80
50.00 501.69 627.11 602.02 602.02 651.54 708.26 334.46 430.02 1003.37 501.69 1505.06
51.00 510.76 638.45 612.90 612.90 663.32 721.06 340.50 437.79 1021.51 510.76 1532.27
52.00 519.83 649.79 623.78 623.78 675.10 733.86 346.54 445.56 1039.65 519.83 1559.48
53.00 528.90 661.13 634.66 634.66 686.88 746.66 352.58 453.33 1057.79 528.90 1586.69
54.00 537.97 672.47 645.54 645.54 698.66 759.46 358.62 461.10 1075.93 537.97 1613.90
55.00 547.04 683.81 656.42 656.42 710.44 772.26 364.66 468.87 1094.07 547.04 1641.11
56.00 556.11 695.15 667.30 667.30 722.22 785.06 370.70 476.64 1112.21 556.11 1668.32
57.00 565.18 706.49 678.18 678.18 734.00 797.86 376.74 484.41 1130.35 565.18 1695.53
58.00 574.25 717.83 689.06 689.06 745.78 810.66 382.78 492.18 1148.49 574.25 1722.74
59.00 583.32 729.17 699.82 699.94 757.56 823.46 388.82 499.95 1166.63 583.32 1749.95
60.00 592.42 740.52 710.90 710.90 769.37 836.35 394.94 507.79 1184.83 592.42 1777.25
61.00 601.49 751.86 721.78 721.78 781.15 849.15 400.98 515.56 1202.97 601.49 1804.46
62.00 610.56 763.20 732.66 732.66 792.93 861.95 407.02 523.33 1221.11 610.56 1831.67
63.00 619.63 774.54 743.54 743.54 804.71 874.75 413.06 531.10 1239.25 619.63 1858.88
64.00 628.70 785.88 754.42 754.42 816.49 887.55 419.10 538.87 1257.39 628.70 1886.09
65.00 637.77 797.22 765.30 765.30 828.27 900.35 425.14 546.64 1275.53 637.77 1913.30
66.00 646.84 808.56 776.18 776.18 840.05 913.15 431.18 554.41 1293.67 646.84 1940.51
67.00 655.91 819.90 787.06 787.06 851.83 925.95 437.22 562.18 1311.81 655.91 1967.72
68.00 664.98 831.24 797.94 797.94 863.61 938.75 443.26 569.95 1329.95 664.98 1994.93
69.00 674.05 842.58 808.82 808.82 875.39 951.55 449.30 577.72 1348.09 674.05 2022.14
70.00 683.15 853.93 819.78 819.78 887.20 964.44 455.43 585.55 1366.29 683.15 2049.44

25
METAL BELOW METAL 40MM Steel , Cement,
LEAD MURUM EARTH SAND RUBBLE Water Excavated Rock Concrete Block Bricks
40MM & ABOVE Stone Block

71.00 692.22 865.27 830.66 830.66 898.98 977.24 461.47 593.32 1384.43 692.22 2076.65
72.00 701.29 876.61 841.54 841.54 910.76 990.04 467.51 601.09 1402.57 701.29 2103.86
73.00 710.36 887.95 852.42 852.42 922.54 1002.84 473.55 608.86 1420.71 710.36 2131.07
74.00 719.43 899.29 863.30 863.30 934.32 1015.64 479.59 616.63 1438.85 719.43 2158.28
75.00 728.50 910.63 874.18 874.18 946.10 1028.44 485.63 624.40 1456.99 728.50 2185.49
76.00 737.57 921.97 885.06 885.06 957.88 1041.24 491.67 632.17 1475.13 737.57 2212.70
77.00 746.64 933.31 895.94 895.94 969.66 1054.04 497.71 639.94 1493.27 746.64 2239.91
78.00 755.71 944.65 906.82 906.82 981.44 1066.84 503.75 647.71 1511.41 755.71 2267.12
79.00 764.78 955.99 917.70 917.70 993.22 1079.64 509.79 655.48 1529.55 764.78 2294.33
80.00 773.88 967.35 928.65 928.65 1005.04 1092.53 515.92 663.32 1547.75 773.88 2321.63
81.00 782.95 978.69 939.53 939.53 1016.82 1105.33 521.96 671.09 1565.89 782.95 2348.84
82.00 792.02 990.03 950.41 950.41 1028.60 1118.13 528.00 678.86 1584.03 792.02 2376.05
83.00 801.09 1001.37 961.29 961.29 1040.38 1130.93 534.04 686.63 1602.17 801.09 2403.26
84.00 810.16 1012.71 972.17 972.17 1052.16 1143.73 540.08 694.40 1620.31 810.16 2430.47
85.00 819.23 1024.05 983.05 983.05 1063.94 1156.53 546.12 702.17 1638.45 819.23 2457.68
86.00 828.30 1035.39 993.93 993.93 1075.72 1169.33 552.16 709.94 1656.59 828.30 2484.89
87.00 837.37 1046.73 1004.81 1004.81 1087.50 1182.13 558.20 717.71 1674.73 837.37 2512.10
88.00 846.44 1058.07 1015.69 1015.69 1099.28 1194.93 564.24 725.48 1692.87 846.44 2539.31
89.00 855.51 1069.41 1026.57 1026.57 1111.06 1207.73 570.28 733.25 1711.01 855.51 2566.52
90.00 864.61 1080.76 1037.53 1037.53 1122.87 1220.62 576.41 741.09 1729.22 864.61 2593.82
91.00 873.68 1092.10 1048.41 1048.41 1134.65 1233.42 582.45 748.86 1747.36 873.68 2621.03
92.00 882.75 1103.44 1059.29 1059.29 1146.43 1246.22 588.49 756.63 1765.50 882.75 2648.24
93.00 891.82 1114.78 1070.17 1070.17 1158.21 1259.02 594.53 764.40 1783.64 891.82 2675.45
94.00 900.89 1126.12 1081.05 1081.05 1169.99 1271.82 600.57 772.17 1801.78 900.89 2702.66
95.00 909.96 1137.46 1091.93 1091.93 1181.77 1284.62 606.61 779.94 1819.92 909.96 2729.87
96.00 919.03 1148.80 1102.81 1102.81 1193.55 1297.42 612.65 787.71 1838.06 919.03 2757.08
97.00 928.10 1160.14 1113.69 1113.69 1205.33 1310.22 618.69 795.48 1856.20 928.10 2784.29
98.00 937.17 1171.48 1124.57 1124.57 1217.11 1323.02 624.73 803.25 1874.34 937.17 2811.50
99.00 946.24 1182.82 1135.45 1135.45 1228.89 1335.82 630.77 811.02 1892.48 946.24 2838.71
100.00 955.34 1194.17 1146.41 1146.41 1240.70 1348.71 636.89 818.86 1910.68 955.34 2866.01

26
METAL BELOW METAL 40MM Steel , Cement,
LEAD MURUM EARTH SAND RUBBLE Water Excavated Rock Concrete Block Bricks
40MM & ABOVE Stone Block

101.00 960.41 1200.50 1152.49 1152.49 1247.28 1355.86 640.27 822.24 1920.82 960.41 2881.22
102.00 965.48 1206.83 1158.57 1158.57 1253.86 1363.01 643.65 825.62 1930.96 965.48 2896.43
103.00 970.55 1213.16 1164.65 1164.65 1260.44 1370.16 647.03 832.71 1941.10 970.55 2911.64
104.00 975.62 1219.49 1170.73 1170.73 1267.02 1377.31 650.41 839.80 1951.24 975.62 2926.85
105.00 980.69 1225.82 1176.81 1176.81 1273.60 1384.46 653.79 846.89 1961.38 980.69 2942.06
106.00 985.76 1232.15 1182.89 1182.89 1280.18 1391.61 657.17 853.98 1971.52 985.76 2957.27
107.00 990.83 1238.48 1188.97 1188.97 1286.76 1398.76 660.55 861.07 1981.66 990.83 2972.48
108.00 995.90 1244.81 1195.05 1195.05 1293.34 1405.91 663.93 868.16 1991.80 995.90 2987.69
109.00 1000.97 1251.14 1201.13 1201.13 1299.92 1413.06 667.31 875.25 2001.94 1000.97 3002.90
110.00 1006.04 1257.47 1207.21 1207.21 1306.50 1420.21 670.69 882.34 2012.08 1006.04 3018.11
111.00 1011.11 1263.80 1213.29 1213.29 1313.08 1427.36 674.07 889.43 2022.22 1011.11 3033.32
112.00 1016.18 1270.13 1219.37 1219.37 1319.66 1434.51 677.45 896.52 2032.36 1016.18 3048.53
113.00 1021.25 1276.46 1225.45 1225.45 1326.24 1441.66 680.83 903.61 2042.50 1021.25 3063.74
114.00 1026.32 1282.79 1231.53 1231.53 1332.82 1448.81 684.21 910.70 2052.64 1026.32 3078.95
115.00 1031.39 1289.12 1237.61 1237.61 1339.40 1455.96 687.59 917.79 2062.78 1031.39 3094.16
116.00 1036.46 1295.45 1243.69 1243.69 1345.98 1463.11 690.97 924.88 2072.92 1036.46 3109.37
117.00 1041.53 1301.78 1249.77 1249.77 1352.56 1470.26 694.35 931.97 2083.06 1041.53 3124.58
118.00 1046.60 1308.11 1255.85 1255.85 1359.14 1477.41 697.73 939.06 2093.20 1046.60 3139.79
119.00 1051.67 1314.44 1261.93 1261.93 1365.72 1484.56 701.11 946.15 2103.34 1051.67 3155.00
120.00 1056.74 1320.77 1268.01 1268.01 1372.30 1491.71 704.49 953.24 2113.48 1056.74 3170.21
121.00 1061.81 1327.10 1274.09 1274.09 1378.88 1498.86 707.87 960.33 2123.62 1061.81 3185.42
122.00 1066.88 1333.43 1280.17 1280.17 1385.46 1506.01 711.25 967.42 2133.76 1066.88 3200.63
123.00 1071.95 1339.76 1286.25 1286.25 1392.04 1513.16 714.63 974.51 2143.90 1071.95 3215.84
124.00 1077.02 1346.09 1292.33 1292.33 1398.62 1520.31 718.01 981.60 2154.04 1077.02 3231.05
125.00 1082.09 1352.61 1298.51 1298.51 1405.31 1527.66 721.39 927.51 2164.18 1082.09 3246.27
126.00 1090.36 1362.95 1308.44 1308.44 1416.01 1539.33 726.90 934.60 2180.72 1090.36 3271.08
127.00 1098.63 1373.29 1318.37 1318.36 1426.71 1551.00 732.41 941.69 2197.26 1098.63 3295.89
128.00 1106.90 1383.63 1328.30 1328.29 1437.41 1562.67 737.92 948.78 2213.80 1106.90 3320.70
129.00 1115.17 1393.97 1338.23 1338.21 1448.11 1574.34 743.43 955.87 2230.34 1115.17 3345.51
130.00 1123.44 1404.31 1348.16 1348.14 1458.81 1586.01 748.94 962.96 2246.88 1123.44 3370.32
131.00 1131.71 1414.65 1358.09 1358.07 1469.51 1597.68 754.45 970.05 2263.42 1131.71 3395.13
132.00 1139.98 1424.99 1368.02 1367.99 1480.21 1609.35 759.96 977.14 2279.96 1139.98 3419.94
133.00 1148.25 1435.33 1377.95 1377.92 1490.91 1621.02 765.47 984.23 2296.50 1148.25 3444.75
134.00 1156.52 1445.67 1387.88 1387.84 1501.61 1632.69 770.98 991.32 2313.04 1156.52 3469.56
135.00 1164.79 1456.01 1397.81 1397.77 1512.31 1644.36 776.49 998.41 2329.58 1164.79 3494.37

27
METAL BELOW METAL 40MM Steel , Cement,
LEAD MURUM EARTH SAND RUBBLE Water Excavated Rock Concrete Block Bricks
40MM & ABOVE Stone Block

136.00 1173.06 1466.35 1407.74 1407.70 1523.01 1656.03 782.00 1005.50 2346.12 1173.06 3519.18
137.00 1181.33 1476.69 1417.67 1417.62 1533.71 1667.70 787.51 1012.59 2362.66 1181.33 3543.99
138.00 1189.60 1487.03 1427.60 1427.55 1544.41 1679.37 793.02 1019.68 2379.20 1189.60 3568.80
139.00 1197.87 1497.37 1437.53 1437.47 1555.11 1691.04 798.53 1026.77 2395.74 1197.87 3593.61
140.00 1206.14 1507.71 1447.46 1447.40 1565.81 1702.71 804.04 1033.86 2412.28 1206.14 3618.42
141.00 1214.41 1518.05 1457.39 1457.33 1576.51 1714.38 809.55 1040.95 2428.82 1214.41 3643.23
142.00 1222.68 1528.39 1467.32 1467.25 1587.21 1726.05 815.06 1048.04 2445.36 1222.68 3668.04
143.00 1230.95 1538.73 1477.25 1477.18 1597.91 1737.72 820.57 1055.13 2461.90 1230.95 3692.85
144.00 1239.22 1549.07 1487.18 1487.10 1608.61 1749.39 826.08 1062.22 2478.44 1239.22 3717.66
145.00 1247.49 1559.41 1497.11 1497.03 1619.31 1761.06 831.59 1069.31 2494.98 1247.49 3742.47
146.00 1255.76 1569.75 1507.04 1506.96 1630.01 1772.73 837.10 1076.40 2511.52 1255.76 3767.28
147.00 1264.03 1580.09 1516.97 1516.88 1640.71 1784.40 842.61 1083.49 2528.06 1264.03 3792.09
148.00 1272.30 1590.43 1526.90 1526.81 1651.41 1796.07 848.12 1090.58 2544.60 1272.30 3816.90
149.00 1280.57 1600.77 1536.83 1536.73 1662.11 1807.74 853.63 1097.67 2561.14 1280.57 3841.71
150.00 1288.90 1611.13 1546.68 1546.68 1673.90 1819.63 859.27 1104.77 2577.80 1288.90 3866.71
151.00 1297.17 1621.47 1556.61 1556.61 1684.60 1831.30 864.78 1111.86 2594.34 1297.17 3891.52
152.00 1305.44 1631.81 1566.54 1566.53 1695.30 1842.97 870.29 1118.95 2610.88 1305.44 3916.33
153.00 1313.71 1642.15 1576.47 1576.46 1706.00 1854.64 875.80 1126.04 2627.42 1313.71 3941.14
154.00 1321.98 1652.49 1586.40 1586.39 1716.70 1866.31 881.31 1133.13 2643.96 1321.98 3965.95
155.00 1330.25 1662.83 1596.33 1596.31 1727.40 1877.98 886.82 1140.22 2660.50 1330.25 3990.76
156.00 1338.52 1673.17 1606.26 1606.24 1738.10 1889.65 892.33 1147.31 2677.04 1338.52 4015.57
157.00 1346.79 1683.51 1616.19 1616.16 1748.80 1901.32 897.84 1154.40 2693.58 1346.79 4040.38
158.00 1355.06 1693.85 1626.12 1626.09 1759.50 1912.99 903.35 1161.49 2710.12 1355.06 4065.19
159.00 1363.33 1704.19 1636.05 1636.02 1770.20 1924.66 908.86 1168.58 2726.66 1363.33 4090.00
160.00 1371.60 1714.53 1645.98 1645.94 1780.90 1936.33 914.37 1175.67 2743.20 1371.60 4114.81
161.00 1379.87 1724.87 1655.91 1655.87 1791.60 1948.00 919.88 1182.76 2759.74 1379.87 4139.62
162.00 1388.14 1735.21 1665.84 1665.79 1802.30 1959.67 925.39 1189.85 2776.28 1388.14 4164.43
163.00 1396.41 1745.55 1675.77 1675.72 1813.00 1971.34 930.90 1196.94 2792.82 1396.41 4189.24
164.00 1404.68 1755.89 1685.70 1685.65 1823.70 1983.01 936.41 1204.03 2809.36 1404.68 4214.05
165.00 1412.95 1766.23 1695.63 1695.57 1834.40 1994.68 941.92 1211.12 2825.90 1412.95 4238.86
166.00 1421.22 1776.57 1705.56 1705.50 1845.10 2006.35 947.43 1218.21 2842.44 1421.22 4263.67
167.00 1429.49 1786.91 1715.49 1715.42 1855.80 2018.02 952.94 1225.30 2858.98 1429.49 4288.48
168.00 1437.76 1797.25 1725.42 1725.35 1866.50 2029.69 958.45 1232.39 2875.52 1437.76 4313.29
169.00 1446.03 1807.59 1735.35 1735.28 1877.20 2041.36 963.96 1239.48 2892.06 1446.03 4338.10
170.00 1454.30 1817.93 1745.28 1745.20 1887.90 2053.03 969.47 1246.57 2908.60 1454.30 4362.91

28
METAL BELOW METAL 40MM Steel , Cement,
LEAD MURUM EARTH SAND RUBBLE Water Excavated Rock Concrete Block Bricks
40MM & ABOVE Stone Block
171.00 1462.57 1828.27 1755.21 1755.13 1898.60 2064.70 974.98 1253.66 2925.14 1462.57 4387.72
172.00 1470.84 1838.61 1765.14 1765.05 1909.30 2076.37 980.49 1260.75 2941.68 1470.84 4412.53
173.00 1479.11 1848.95 1775.07 1774.98 1920.00 2088.04 986.00 1267.84 2958.22 1479.11 4437.34
174.00 1487.38 1859.29 1785.00 1784.91 1930.70 2099.71 991.51 1274.93 2974.76 1487.38 4462.15
175.00 1495.71 1869.64 1794.86 1794.86 1942.49 2111.60 997.14 1282.04 2991.43 1495.71 4487.14
176.00 1503.98 1879.98 1804.79 1804.78 1953.19 2123.27 1002.65 1289.13 3007.97 1503.98 4511.95
177.00 1512.25 1890.32 1814.72 1814.71 1963.89 2134.94 1008.16 1296.22 3024.51 1512.25 4536.76
178.00 1520.52 1900.66 1824.65 1824.63 1974.59 2146.61 1013.67 1303.31 3041.05 1520.52 4561.57
179.00 1528.79 1911.00 1834.58 1834.56 1985.29 2158.28 1019.18 1310.40 3057.59 1528.79 4586.38
180.00 1537.06 1921.34 1844.51 1844.49 1995.99 2169.95 1024.69 1317.49 3074.13 1537.06 4611.19
181.00 1545.33 1931.68 1854.44 1854.41 2006.69 2181.62 1030.20 1324.58 3090.67 1545.33 4636.00
182.00 1553.60 1942.02 1864.37 1864.34 2017.39 2193.29 1035.71 1331.67 3107.21 1553.60 4660.81
183.00 1561.87 1952.36 1874.30 1874.26 2028.09 2204.96 1041.22 1338.76 3123.75 1561.87 4685.62
184.00 1570.14 1962.70 1884.23 1884.19 2038.79 2216.63 1046.73 1345.85 3140.29 1570.14 4710.43
185.00 1578.41 1973.04 1894.16 1894.12 2049.49 2228.30 1052.24 1352.94 3156.83 1578.41 4735.24
186.00 1586.68 1983.38 1904.09 1904.04 2060.19 2239.97 1057.75 1360.03 3173.37 1586.68 4760.05
187.00 1594.95 1993.72 1914.02 1913.97 2070.89 2251.64 1063.26 1367.12 3189.91 1594.95 4784.86
188.00 1603.22 2004.06 1923.95 1923.89 2081.59 2263.31 1068.77 1374.21 3206.45 1603.22 4809.67
189.00 1611.49 2014.40 1933.88 1933.82 2092.29 2274.98 1074.28 1381.30 3222.99 1611.49 4834.48
190.00 1619.76 2024.74 1943.81 1943.75 2102.99 2286.65 1079.79 1388.39 3239.53 1619.76 4859.29
191.00 1628.03 2035.08 1953.74 1953.67 2113.69 2298.32 1085.30 1395.48 3256.07 1628.03 4884.10
192.00 1636.30 2045.42 1963.67 1963.60 2124.39 2309.99 1090.81 1402.57 3272.61 1636.30 4908.91
193.00 1644.57 2055.76 1973.60 1973.52 2135.09 2321.66 1096.32 1409.66 3289.15 1644.57 4933.72
194.00 1652.84 2066.10 1983.53 1983.45 2145.79 2333.33 1101.83 1416.75 3305.69 1652.84 4958.53
195.00 1661.11 2076.44 1993.46 1993.38 2156.49 2345.00 1107.34 1423.84 3322.23 1661.11 4983.34
196.00 1669.38 2086.78 2003.39 2003.30 2167.19 2356.67 1112.85 1430.93 3338.77 1669.38 5008.15
197.00 1677.65 2097.12 2013.32 2013.23 2177.89 2368.34 1118.36 1438.02 3355.31 1677.65 5032.96
198.00 1685.92 2107.46 2023.25 2023.15 2188.59 2380.01 1123.87 1445.11 3371.85 1685.92 5057.77
199.00 1694.19 2117.80 2033.18 2033.08 2199.29 2391.68 1129.38 1452.20 3388.39 1694.19 5082.58
200.00 1702.52 2128.16 2043.03 2043.03 2211.07 2403.56 1135.02 1459.31 3405.05 1702.52 5107.57

29
30
SECTION-2

EXCAVATION AND EMBANKMENT

ITEM NO 1 TO 19

31
32
33
34
GOVERNMENT OF MAHARASHTRA
COMMON SCHEDULE OF RATES FOR 2016-17
EXCAVATION & EMBANKMENT
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No.
Completed Item Labour
1 2 3 4 5

1 Item No.1 :-
Excavation in all kinds of soil including Cum. 60.15 9.05
boulders upto 0.6 m diameter ( 0.113 cum)
for canal, seating of embankment, filter
drains / catch water drains etc., and placing
the excavated stuff neatly in dump area or
for formation of service road / embankment
as directed including cost of all materials,
machinery, labour, dressing bed and sides
to required level and profile etc., complete
with lead upto 1 km and 6m lift.

2 Item No.2 :-
Excavation in hard murum including Cum. 73.35 12.25
boulders upto 0.6 m diameter (0.113 cum)
for canal, seating of embankment, filter drain
/ catch water drains etc., and placing the
excavated material neatly in dump area or
for formation of service road as directed
including cost of all materials, machinery,
labour, dressing bed and sides to required
level and profile etc., complete with lead upto
1 km and 6m lift.

3 Item No.3 :-
Excavation in soft rock without blasting Cum. 89.80 15.60
including boulders upto 0.6 m diameter
(0.113 cum) for canal, seating of
embankment, filter drain / catch water drains
etc., and placing the excavated soft rock
neatly in dump area or for formation of
service road as directed including cost of all
materials, machinery, labour, dressing bed
and sides to required level and profile etc.,
complete with lead upto 1 km and 6m lift.

4 Item No.4 :-
Excavation in hard rock of all toughness by Cum. 321.80 73.00
blasting including boulders above 0.6 m
dia.(0.113Cum) minimising damage to side
slopes of excavation in water prism area by
adopting any one or combination of line
drilling / pre-splitting / smooth blasting
techniques and placing the excavated rock
neatly in approved dump area as directed
including cost of all materials, machinery,
labour, levelling bed etc., complete with lead
upto 1 km and lift upto 6 m.

35
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No.
Completed Item Labour
1 2 3 4 5

5 Item No.5 :-
Excavation in hard rock of all toughness Cum. 482.70 109.50
including boulders above 0.6 m dia.
(0.113Cum) for canals cut-off trench of
embankment filter / catch water drains and
other appurtenant structures by control
blasting methods including control of
vibrations by use of delay detonators and
control of fly rocks by muffling arrangements
and adopting only jack hammers for drilling
holes and minimising damage to side slopes
of canal in water prism area by adopting any
one or combination of line drilling / pre-
splitting / smooth blasting techniques
including cost of all materials, machinery,
labour, placing excavated rock neatly
approved dump area as directed etc.,
complete with lead upto 1 km & lift upto 6 m.
6 Item No.6 :-
Excavation in hard rock of all toughness by Cum. 502.40 28.50
breaker including boulders above 0.6 m dia.
(0.113Cum) minimising damage to side
slopes of excavation and placing the
excavated rock neatly in approved dump
area as directed including cost of all
materials, machinery, labour, levelling bed
etc., complete with lead upto 1 km and lift
upto 6 m.
7 Item No.7 :-
Watering the embankment in proper layers Cum. 11.80 ---
by tankers including a lead of water upto
1 km and all lifts etc. complete

8 Item No.8 :-
Compaction of bankwork with vibratory Cum. 22.65 ---
Compactor to 95 % of Proctor density
including watering with a lead upto 1.00 Km.

9 Item No.9 :-
Providing cut off trench filling using Cum. 45.60 1.70
selected impervious soil directly available
from material of excavation including cost of
all materials, machinery, labour, all other
operations such as collection of soil,
spreading soil in layer of specified thickness,
sorting out, breaking clods, levelling,
sectioning edges / sides, watering,
compacting each layer to density control of
not less than 95 percent or as stipulated
using power roller etc., complete with lead
upto1 km for water and 6m lift.

36
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No.
Completed Item Labour
1 2 3 4 5

10 Item No.10 :-
Providing hearting embankment using Cum. 45.60 1.70
selected impervious material available
directly from excavation in layers
including cost of all materials, machinery,
labour, all other operations such as
collection of material, spreading soil in
layer of specified thickness, sorting out,
breaking clods, levelling, sectioning edges
/ sides, watering, compacting each layer to
density control of not less than 95 percent
or as stipulated using vibratory compactor
etc., complete with lead upto1 km for
watering and 6m lift.

11 Item No.11 :-
Providing casing embankment using Cum. 55.10 2.30
selected pervious material available
directly from excavation in layers
including cost of all materials, machinery,
labour, all other operations such as
collection of material, spreading material in
layer of specified thickness, sorting out,
breaking clods, levelling, sectioning edges
/ sides, watering, compacting each layer to
density control of not less than 95 percent
or as stipulated using vibratory compactor
etc., complete with lead upto1 km for
watering and 6m lift.
12 Item No.12 :-
Providing cut off trench filling using Cum. 108.75 1.80
selected impervious soil from approved
borrow areas including cost of all
materials, machinery, labour, all other
operations such as collection of soil,
spreading soil in layer of specified
thickness, sorting out, breaking clods,
levelling, sectioning edges / sides,
watering, compacting each layer to density
control of not less than 95 percent or as
stipulated using power roller etc., complete
with lead upto1 km and 6m lifts.

37
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No.
Completed Item Labour
1 2 3 4 5

13 Item No.13 :-
Providing hearting embankment using Cum. 99.30 1.75
selected impervious soil from approved
borrow areas in layers including cost of all
materials, machinery, labour, all other
operations such as collection of soil, spreading
soil in layer of specified thickness, sorting out,
breaking clods, levelling, sectioning edges /
sides, watering, compacting each layer to
density control of not less than 95 percent or as
stipulated using power roller etc., complete with
lead upto1 km and 6m lift.
14 Item No.14 :-
Providing casing embankment using Cum. 119.45 2.35
selected pervious material from approved
borrow areas in layers including cost of all
materials, machinery, labour, all other
operations such as collection of soil, spreading
soil in layer of specified thickness, sorting out,
breaking clods, levelling, sectioning edges /
sides, watering, compacting each layer to
density control of not less than 95 percent or as
stipulated using vibratory compactor etc.,
complete with lead upto1 km and 6m lift.

15 Item No.15 :-
Providing cohesive non-swelling (CNS) Cum. 162.00 37.10
material lining to canals using selected
material from approved borrow area including
cost of all materials, machinery, labour,
spreading soil in layers of thickness not more
than 150 mm including providing 20 cm or so
(perpendicular to side slope) of extra pride
,removing pride just prior to the placement of
lining, breaking clods, watering, compacting to
density control of not less than 95 percent or as
stipulated, dressing to required profile etc.,
complete with lead upto1 km and 6m lift.

16 Item No.16 :-
Providing and constructing 300 mm thick dry Sqm. 216.15 44.35
rubble stone pitching with pin headers at
2 per sqm using stones and stone chips from
approved source including cost of all materials,
labour, hand packing / wedging stone chips,
finishing etc., complete with lead upto 50 m and
all lifts excluding royalty of material.

38
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No.
Completed Item Labour
1 2 3 4 5

17 Item No.17 :-
Providing and constructing 450 mm thick dry Sqm. 295.20 66.40
rubble stone pitching with pin headers at 2
per sqm using stones and stone chips from
approved source including cost of all materials,
labour, hand packing / wedging stone chips,
finishing etc., complete with lead upto 50 m and
all lifts excluding royalty of material.

18 Item No.18 :-
Providing and constructing dry rubble rock-toe Cum. 551.40 133.00
using rubble and stone chips from approved
source including cost of all materials,
machinery, labour, hand packing rubble and
stone chips, finishing top and sides to required
slopes etc., complete with lead upto 50 m and
all lifts excluding royalty of material.

19 Item No.19 :-
Providing and constructing longitudinal and Cum. 873.50 175.85
cross graded filter drains using sand and 20mm
down approved clean, hard, graded aggregates
satisfying specified filter criteria in layers of
specified thickness including cost of all
materials, machinery, labour, laying to required
slopes, compaction etc., complete as per
specifications and approved drawings with lead
upto 50 m and all lifts.

39
40
SECTION 3
CONCRETE WORK INCLUDING
CENTERING, UCR MASONRY, BRICK MASONRY AND
R.C.C. PIPES

ITEM NO 20 TO 60

41
42
43
44
2016-17

(General Notes)

1.0
.


5% (Total Basic rate worked out in the CSR)
.

2.0 6 .
.
177.75/ .
.

3.0
.
-2 1.50 .

4.0
. .
.

5.0 .

45
GOVERNMENT OF MAHARASHTRA
COMMON SCHEDULE OF RATES FOR 2016-17
CONCRETE WORKS

Rate for 2016-17


Sr. (Rate in Rs.)
Item Unit
No.
Completed Item Labour

1 2 3 4 5
DAM AND ALLIED WORKS
FOUNDATION AND BEDDING
20 Item No.20 :-
Providing and laying in situ cement concrete of grade
M-10 of trap/ granite / quartzite / graded metal for
foundation and bedding with Batching Plant and
Transit Mixer including compacting, curing, etc.
complete with an initial lead of 50 m. and lift of 1.5 m.

(A) M-10 (20 MSA) Cum 3515.80


(B) M-10 (40 MSA) Cum 3515.80
(C) M-10 (80 MSA)
Cum 3455.60
21 Item No.21 :-
Providing and laying in situ cement concrete of grade
M-15 of trap / granite / gneiss / quartzite / graded
metal for foundation and bedding with Batching
Plant & Transit Mixer, compacting, curing etc.
complete with an initial lead of 50 m. and lift of 1.5 m.

(A) M-15 (20 MSA) Cum 3876.55


(B) M-15 (40 MSA) Cum 3726.15
(C) M-15 (80 MSA)
Cum 3624.95
SUB AND SUPER STRUCTURE
22 Item No.22 :-
Providing and laying in situ cement concrete of grade
M-15 of trap / granite / gneiss / quartzite / graded
metal for PCC with or without surface
reinforcement/RCC concreting requiring heavy or
special type of shuttering for works of gallery,
sluice, spillway crest, spillway down stream face,
energy dissipating structures, intake structures,
training walls, piers, abutments etc. with Batching
Plant and Transit mixer with shuttering and
scaffolding, compacting, curing etc. complete with
an initial lead of 50 m. and lift of 1.5 m.

(A) M-15 (20 MSA) Cum 4458.70


(B) M-15 (40 MSA) Cum 4267.50
(C) M-15 (80 MSA) Cum 4243.00

46
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No.
Completed Item Labour
1 2 3 4 5

23 Item No.23 :-
Providing and laying in situ cement concrete of grade
M-20 of trap / granite / gneiss / quartzite / graded
metal for RCC works of gallery, sluice, spillway
crest, spillway down stream face, energy
dissipating structures, intake structures, training
walls, piers, abutments, slab etc. with Batching
Plant and Transit mixer including shuttering and
scaffolding, compacting, curing etc. complete with
an initial lead of 50 m. and lift of 1.5 m.

(A) M-20 (20 MSA) Cum 4771.10


(B) M-20 (40 MSA) Cum 4594.65

24 Item No.24 :-
Providing and laying in situ cement concrete of grade
M-25 of trap / granite / gneiss / quartzite / graded
metal for RCC works of gallery, sluice, spillway
crest, spillway down stream face, energy
dissipating structures, intake structures, training
walls, piers, abutments, slab etc. with Batching
Plant and Transit mixer including shuttering and
scaffolding, compacting, curing etc. complete with
an initial lead of 50 m. and lift of 1.5 m.
(A) M-25 (20 MSA) Cum 5103.00

CANAL AND ALLIED WORKS

25 Item No.25 :-
Providing and laying in situ M-15 (20 MSA)(28 days
cube compressive strength not less than
15N/sqmm) grade cement concrete with clean,
hard, graded aggregates for canal lining for side
and bed including cost of all materials,
machinery, labour, cleaning with batching plant
and transit mixer placing in position, finishing with
all slope of canal including scaffolding, formwork,
compaction, curing, by cutting grooves, filling with
sealing compound and providing porous plugs,
preparation of sub grade excluding royalty of
materials etc. with initial lead of 50 m and lift of 1.5 m

A) For Bed Lining Cum 4954.85


B) For Side Lining Cum 5209.10

47
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No.
Completed Item Labour
1 2 3 4 5

26 Item No.26 :-
Providing and laying in situ mechanised lining in
M-15 (20 MSA)(28 days cube compressive strength
not less than 15N/sqmm) grade cement concrete
with clean, hard, graded aggregates for canal side
and bed using vibrating cylindrical type mechanical
paver including cost of all materials, machinery,
labour, cleaning with batching plant and transit mixer
placing in position, finishing with all slope of canal
including scaffolding, formwork, compaction, curing,
by cutting grooves, filling with sealing compound and
providing porous plugs, preparation of sub grade
excluding royalty of materials etc. with initial lead of
50 m and lift of 1.5 m

A) For Bed Lining Cum 5160.90


B) For Side Lining Cum 5415.20

27 Item No.27 A :-
Providing & laying chip masonry back filling behind Cum 1551.95
concrete lining in C.M. 1:8 including striking joints,
curing, scaffolding etc. complete but excluding
pointing, excluding royalty of material. (35% mortar)

Item No.27 B :-
Providing, laying, erecting and dismantling M.S. Sqm 64.55
plates form work for side lining (for steeper slopes
only) (to be used with prior approval of C.E.)

28 Item No.28 :-
Providing and laying polythene film of 031 properly
manufactured from 100% virgin granules confirming
to I.S. 2508-1984 with 1.5 to 2.5 m. package in rolls
as per specifications.
A) 200 microns Sqm 48.50
B) 400 microns Sqm 95.15
C) 600 microns Sqm 148.45

29 Item No.29 :-
Providing and laying 40 and 45 cm. thick UCR Cum 2185.75
masonry in C.M. 1:5 for side lining of the canal
including raking joints, scaffolding and curing etc.
complete excluding pointing, excluding royalty of
material with lead upto 50 m. and lift upto 1.5 m.
(35% mortar)

48
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No.
Completed Item Labour
1 2 3 4 5

30 Item No.30 :-
Providing and laying cement plaster 6 mm thick in Sqm 89.15
C.M. 1:3 single coat without neru finish to concrete
surface in all position including scaffolding, curing,
including etc. complete.

CANAL STRUCTURES

31 Item No.31 :-
Providing and laying in situ cement concrete of grade
M-10 of trap/ granite / quartzite / graded metal for
foundation and bedding with Batching Plant and
Transit Mixer including shuttering, compacting,
curing, etc. complete with an initial lead of 50 m. and
lift of 1.5 m.
(A) M-10 (20 MSA) Cum 4037.65
(B) M-10 (40 MSA) Cum 4037.65
(C) M-10 (80 MSA) Cum 3977.50

32 Item No.32 :-
Providing and laying in situ cement concrete of grade
M-15 of trap / granite / gneiss / quartzite / graded
metal for foundation and bedding by Batching Plant
and Transit Mixer, shuttering, scaffolding,
compacting, curing etc. complete with an initial lead
of 50 m. and lift of 1.5 m.

(A) M-15 (20 MSA) Cum 4398.45


(B) M-15 (40 MSA) Cum 4248.00
(C) M-15 (80 MSA) Cum 4146.80

33 Item No.33 :-
Providing and laying in situ cement concrete of grade
M-15 of trap / granite / gneiss / quartzite / graded
metal for RCC works of retaining walls, piers,
abutments, etc. with Batching Plant and Transit
mixer including shuttering, scaffolding,
compacting, curing etc. complete with an initial lead
of 50 m. and lift of 1.5 m.
(A) M-15 (20 MSA)
i) For Abutment, wing walls, returns, transition walls Cum 4973.35
ii) For Piers Cum 5083.00
(B) M-15 (40 MSA)
i) For Abutment, wing walls, returns, transition walls Cum 4782.10
ii) For Piers Cum 4891.80
(C) M-15 (80 MSA)
i)For Abutment, wing walls, returns, transition walls Cum 4689.30
ii) For Piers Cum 4798.95

49
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No.
Completed Item Labour
1 2 3 4 5

34 Item No.34 :-
Providing and laying in situ cement concrete of
grade M-20 of trap / granite / gneiss / quartzite /
graded metal for RCC works of abutment, wing
walls, returns, transition walls, columns, beams
and slabs, diaphragm walls, Road slabs trough
(Box Culvert) trough for aqueduct, wearing coat,
etc. with Batching Plant and Transit mixer
including shuttering, scaffolding compacting,
curing etc. complete with an initial lead of 50 m. and
lift of 1.5 m.

(A) 20 MSA
i) For Abutment, wing walls, returns, transition walls Cum 5285.70
ii) Piers Cum 5395.40
iii) Columns Cum 6930.90
iv) Beams and slabs for building Cum 7192.10
v) Road Slab,kerb,super passage/slab culvert etc. Cum 7010.95
vi) Trough resting on ground Cum 6477.05
vii) Trough for aqueduct Cum 7716.45
viii) Wearing Coat and other required concrete Cum 4188.95
(B) 40 MSA
i) Abutment/retaining walls/wing walls/Transition walls Cum 5109.30
ii) Pier Cum 5218.95

35 Item No.35 :-
Providing and laying in situ cement concrete of
grade M-25 of trap / granite / gneiss / quartzite /
graded metal for RCC works of columns, beams
and slabs, diaphram walls, Road slabs trough
(Box Culvert) trough for aqueduct, wearing coat,
etc. with Batching Plant and Transit mixer
including shuttering, scaffolding compacting,
curing etc. complete with an initial lead of 50 m. and
lift of 1.5 m.

(A) 20 MSA
i) Columns Cum 7262.80
ii) Beams and slabs for building Cum 7524.05
iii)Road Slab,kerb,super passage/slab culvert etc. Cum 7342.90
iv) Trough resting on ground Cum 6809.00
v) Trough for aqueduct Cum 8048.40
vi) Wearing Coat Cum 4520.90

50
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No.
Completed Item Labour
1 2 3 4 5

36 Item No.36 :-
Providing and laying in situ cement concrete of
grade M-30 for trough of aqueduct etc. of trap /
granite / gneiss / quartzite / graded metal with
Batching Plant and Transit mixer including
shuttering, scaffolding including compacting,
curing etc. complete with an initial lead of 50 m.
and lift of 1.5 m.
(A) M-30 (20 MSA) for trough of aqueduct Cum 8509.10
(B) M-30 (20 MSA) for slab Cum 7984.75

37 Item No.37 :-
Providing and laying expansion / construction joint
with 18 SWG copper plate and shalitex
expansion pad below and above the copper plate
including sealing the joint with shalitex sealing
compound etc. complete including 50*50*5 mm
angle frame with stainless steel bolts etc. (For
all slab thickness ).

A) 60 cm wide copper plate Sqm 13462.55


B) 37.50 cm wide copper plate Sqm 15480.25

38 Item No.38 :-
Providing and laying expansion / construction joint Sqm 1181.15
with shalitex super expansion pad (jute fiber)
12 mm thick including sealing the joint with
shalitex sealing compound etc. complete (For slab
thickness of 30 cm.).
39 Item No.39 :-
Providing and fixing G.I. sheet 24 gauge and 22.5 Rmt 184.95
cm. wide for the construction joint in R.C.C.
trough wall including cutting 15 cm. overlap,
riveting the joints and fixing in position etc.
complete.

40 Item No.40 :-
Cutting, bending, hooking, laying in position and MT 6597.70
tying M.S. bars for reinforcement of R.C.C. work
as per detailed drawing etc. complete.
Ferro Cement (Items to be implemented with
prior permission of Chief Engineer)

41 Item No.41 :-
Providing and Fixing and errecting, welding 8 mm Sqm 921.35
MS bar @200 mm C/c both ways for ferro cement
walling situ welded mesh of size 100x100x2.30
mm and chiken mesh 3 layers.

51
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No.
Completed Item Labour
1 2 3 4 5

42 Item No.42 :-
Providing and casting Ferro cement wall in C.M.
1:3 including curing etc complete.
A) 30 mm thick wall Sqm 388.65
B) 40 mm thick wall Sqm 511.65

c) 50 mm thick wall Sqm 633.25

CENTERING ITEMS
43 Item No.43 A :-
Providing, erecting and laying steel shuttering Sqm 343.60
formwork and making surface suitable for
concreting including dismantling etc. complete for
abutments, piers, wings, returns etc.

Item No.43 B :-
For RCC Solid/Deck slab/Box Cells/ Trough of Sqm 388.30
Aqueduct etc.
Item No.43 C :- For curved surface Sqm 412.30

44 Item No.44 A :-
Providing and erecting steel props centering up to Sqm 204.15
3.00 m height including bracing, strengthening and
dismantling etc. complete.
Item No.44 B :-
Rate for centering for every Additional 1.00 m Sqm 70.30
height

U.C.R.S. MASONRY
45 Item No.45 :-
Providing U.C.R. masonry in C.M. 1:5 in
foundation upto 0.5 m above G.L. with 50 m. lead
and lift upto 1.5 m. including striking joints, curing,
excluding royalty of material etc. complete.

A) Thickness of wall upto 1 m. (30% mortar) Cum 1739.55


B) Walls of water retaining structures thinner than Cum 1786.45
1.0 m. and walls of structures thicker than 1.0 m.
other than dams and water retaining structures.
(35% mortar).

C) For dams and water retaining structures (45% Cum 2007.60


mortar) .

52
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No.
Completed Item Labour
1 2 3 4 5

46 Item No.46 :-
Providing U.C.R. masonry in C.M.1:6 in foundation
upto plinth with 50 m. lead and lift upto 1.5 m.
including striking joints, curing excluding royalty of
material etc. complete.

(A) : (30% mortar). Cum 1646.60


(B) : (35% mortar) Cum 1676.90
(C) : (45% mortar). Cum 1864.85

47 Item No.47 :-
Providing U.C.R. masonry in C.M.1:5 in
superstructure with 50 m. lead and lift upto 1.5 m.
including striking joints and excluding royalty of
material etc. complete.
A) Thickness of walls upto 1 m. (30% mortar) Cum 1756.50
B) Walls of water retaining structures thinner than Cum 1800.10
1.0 m. and walls and structures thicker than 1.0 m.
other than dams and water retaining structures.
(35% mortar)
C) For dams & water retaining structures (45% Cum 2021.30
mortar)

48 Item No.48 :-
Providing khandki facing to the face of masonry
with pointing in C.M.1:2 including finishing to the
required shape & slope with necessary scaffolding,
curing and excluding royalty of material etc.
complete with lead of 50m. (It is assumed that the
Khandkis are of the size 20cm x 20cm. No mortar
for jointing is taken into account, only face pointing
of joint is considered)
(A) with khandki facing on one side Sqm 1322.50
B) with khandki facing on both side. Sqm 1268.80
I
49 tem No.49 :-
Providing and laying dry stone rubble masonry Cum 799.00
excluding pointing and royalty of material.

50 Item No.50 :-
Providing pointing with cement mortar for stone
masonry including racking joints, scaffolding,
curing excluding royalty of material etc. complete.
(A) In Cement mortar 1:3 Sqm 39.85
(B) In Cement Mortar 1:2 Sqm 45.20

53
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No.
Completed Item Labour
1 2 3 4 5

51 Item No.51 :-
Providing and constructing coarse rubble masonry Cum 3602.90
II sort in C.M. 1:4.5 for super structure with lead
upto 50m. and lift upto 1.5m. including striking
joints, curing excluding royalty of material etc.
complete excluding cement pointing etc. complete.
30% mortar.

52 Item No.52 :-
Cutting rectangular grooves of size 10 cm. x 10 Rmt 917.05
cm. in stone masonry including clearing pointing
etc. to facilitate smooth working of needles etc.
complete.

53 Item No.53 :-
Providing and laying rough dressed cut stone Cum 4535.15
coping 23 cm. thick in C.M.1:5 excluding cement
pointing but including watering with lead 50 m. and
lift upto 1.5 m., excluding royalty of material etc.
complete.
54 Item No.54 :-
Providing coalgrout U.C.R. masonry in C.M.1:3 Cum 2818.75
(43% mortar) proper packing rubble and of the
required shape and quality with the coalgrout at
required pressure with 50 m. lead and lift upto 1.5
m. including scaffolding, watering and excluding
royalty of material etc. complete. (Excluding
formwork and staging)

BRICK MASONRY
55 Item No.55 :-
Providing B.B. masonry with conventional I.S. type
bricks for super structure including striking joints,
watering, scaffolding with lead upto 50 m. and lift
upto 1.5 m., including cost of material and
excluding royalty of material.

A) in C. M. 1:5 Cum 4470.20

56 Item No.56 :-
Providing B.B. masonry with conventional I.S. type Sqm 624.75
bricks in cement mortar 1:5 in super structure
upto floor level including mild steel reinforcement
of 2 bars of 6 mm dia. placed by every 3rd course
properly bent, bounded at ends, scaffolding,
watering etc. complete with lead upto 50 m. and lift
upto 1.5 m. including cost of material and
excluding royalty of material.

54
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No.
Completed Item Labour
1 2 3 4 5
PIPE LAYING
57 Item No.57 :-
Laying and jointing R.C.C. pipe of NP2 class or
IRC standard in C.M.1:2 proportion by volume
including cost of all materials (excluding pipes
and collars), labour, aligning pipes, batching
and mixing mortar, packing joints with hemp
and mortar, finishing, curing etc. complete with
lead up to 50 m and all leads.

(A) 1200 mm dia. Rmt 411.00


(B) 900 mm dia. Rmt 292.70
(C) 600 mm dia. Rmt 208.45
(D) 450 mm dia. Rmt 159.90
(E) 300 mm dia. Rmt 138.05

58 Item No.58 :-
Laying and jointing R.C.C. pipe of NP3 class or
IRC standard in C.M.1:2 proportion by volume
including cost of all materials (excluding pipes
and collars), labour, aligning pipes, batching
and mixing mortar, packing joints with hemp
and mortar, finishing, curing etc. complete with
lead up to 50 m and all leads.

(A) 1200 mm dia. Rmt 475.95


(B) 900 mm dia. Rmt 341.40

59 Item No.59 :-
Laying and jointing R.C.C. pipe of P1 class of Rmt 341.40
900 mm dia or IRC standard in C.M.1:2
proportion by volume including cost of all
materials (excluding pipes and collars), labour,
aligning pipes, batching and mixing mortar,
packing joints with hemp and mortar, finishing,
curing etc. complete with lead up to 50 m and
all leads.

60 Item No.60 :-
Providing and laying in situ cement concrete of Cum 7529.90
grade M-20 of trap / granite / gneiss / quartzite /
graded metal for Staunch wall with Batching
Plant and Transit Mixer including shuttering,
scaffolding compacting, curing etc. complete
with an initial lead of 50 m. and lift of 1.5 m.

55
56
SECTION-4

MAINTENANCE AND REPAIRS

ITEM NO 61 TO 84

57
58
59
60
GOVERNMENT OF MAHARASHTRA
COMMON SCHEDULE OF RATES FOR 2016-17
MAINTAINANCE & REPAIRS

Rate for 2016-17


Sr. (Rate in Rs.)
Item Unit
No.
Completed Item Labour
1 2 3 4 5

61 Item No.61 :-
Dismantling stone masonry cement mortar Cum. 153.60 153.60
including stacking the material as directed with
15 m. lead and 1.5 mtr. Lift etc complete.

62 Item No.62 :-
Dismantling the old lime concrete or cement Cum. 185.05 185.05
concrete including stacking the material as
directed with 15 m. lead and 1.5 mtr. lift etc
complete.

63 Item No.63 :-
Dismantling R.C.C. works and removing the Cum. 277.60 277.60
stuff to a distance of 15 m and 1.50 mtr. lift
including stacking etc. complete as directed

64 Item No.64 :-
Cleaning cutting thorny shrubs bushes, grass Sqm. 1.75 1.75
as directed with 15m lead and lift up to 1.5m.
65 Item No.65 :-
Cutting down trees including cutting trunks &
branches and stacking the material as directed
with 15 mtr. lead and lift up to 1.5 mtr. etc.
complete including up roofing and refilling the
pit with material as directed (excluding extra
material required for refilling)

(a) Girth between 30 cm to 60 cm No. 188.45

(b) Girth between 60 cm to 90 cm No. 223.65

(c) Girth between 90 cm to 1.50 mtr. No. 400.00

(d) Girth between 1.50 mtr to 3.00 mtr. No. 576.10

(e) Girth between 3.00 mtr to 4.50 mtr. No. 928.35

66 Item No.66 :-
Numbering road and canal sites trees No. 12.20
including painting etc. complete

67 Item No.67 :-
Removing dry silt from the canal bed and Cum. 41.65
stacking as directed with 15 mtr. lead and 1.50
mtr. lift etc. complete.

61
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No.
Completed Item Labour

1 2 3 4 5

68 Item No.68 :-
Removing wet silt from canal bed with 15.00 Cum. 61.30
mtr. lead and 1.50 mtr. including depositing the
excavated stuff as directed.

69 Item No.69 :-
Removing old paint from steel and other Sqm. 31.15
surface with flame, cleaning and making the
surface even including scaffolding etc.
complete.

70 Item No.70 :-
Providing and applying Primer Red Oxide Sqm. 195.00
Paint in two coats including surface
preparation, chipping the welding, cleaning
spatters, dust etc. complete.

71 Item No.71 :-
Providing and applying anticorrosive coal tar Sqm. 259.50
black paint IS 290-1961 in two coats including
surface preparation, chipping the welding,
cleaning spatters, dust etc. complete.

72 Item No.72 :-
Providing and applying anticorrosive H.D. Sqm. 262.10
black paint for upstream side in two coats
including surface preparation, chipping the
welding, cleaning spatters, dust etc. complete.

73 Item No.73 :-
Providing and applying two coats of flat oil Sqm. 74.00
paint of approved colour and shade to
internal/external plastered surfaces including
scaffolding if necessary clearing and preparing
surfaces excluding primer paint.

74 Item No.74 :-
Providing and applying two coats of flat oil Sqm. 71.25
paint of approved colour to the old structural
steel work and iron work previously painted
including scaffolding if necessary clearing &
preparing surface excluding primer coat etc.
complete.

62
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No.
Completed Item Labour

1 2 3 4 5

75 Item No.75 :-
Providing and applying two coats of lead/zinc Sqm. 94.80
base oil paint / bituminous paint of approved
colour and shade to wood work/fiber boards
previously painted including scaffolding if
necessary, preparing surface excluding
primary coat etc. complete.

76 Item No.76 :-
Providing and applying coal tar in one coat on Sqm. 19.45
previously painted wood work including
preparing the surface scaffolding etc. complete

77 Item No.77 :-
Applying geru wash and white wash to canal No. 43.40
road side Km stones / Boundary stones / Ch.
Stones / bottom of trees, etc.

78 Item No.78 :-
Removing M.S. Needles from the K.T. Weir No. 111.00
opening before onset of the monsoon for
passing the flood water through the K.T. Weir
openings including conveying the same up to
the river banks, stacking the same as directed
with all leads and lifts etc. complete.

79 Item No.79 :-
Transportation of M.S. Needles from the river No. 35.00
bank to the store shed / safe place or from
store shed / safe place to river bank by
Bullock cart including loading unloading and
stacking as directed with all leads and lifts etc.
complete.(Lead Half km)

80 Item No.80 :-
Providing, supplying and applying 1 coat of red Sqm. 136.50
oxide to the steel structure as a primary coat
including cleaning, scrubbing for preparing the
surface to apply paint with lead up to 15 mt.
and lift up to 1.50 mt.etc complete for one
needle.

81 Item No.81 :-
Fixing of M.S. Needles in weir openings after Needle 402.70
offset of the monsoon for storage of Water
from post monsoon river flow and making it
water tight by using wooden pegs, Dungry
cloth & empty cement bags etc. with all leads
& lifts and including all material and labour etc.
complete.

63
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No.
Completed Item Labour
1 2 3 4 5

82 Item No.82 :-
Cleaning by redrilling the vertical porous drain
pipes including removing of leaching material,
grout material if any inside of the V.P.D. etc
complete with all leads and lifts.
(Vertical upward drilling)
a) From 0 to 5 m. Rmt. 5831.55
b) From 5 to 10 m. Rmt. 6415.00
c) From 10 to 15 m. Rmt. 6998.00
d) From 15 to 20 m. Rmt. 7289.00

83 Item No.83 :-
Providing and applying single coat of epoxy Sqm. 406.15
primer (4.42 sqm/kg) (Resin : Hardner 2:1) on
old U C R masonry / concrete surface etc.
complete.

84 Item No.84 :-
Providing & applying of Epoxy Mortar layers to Kg. 186.20
Monolith joint of Masonry Dam with all lead &
lift etc. complete.

64
SECTION-5

TUNNEL WORKS

ITEM NO 85 TO 98

65
66
67
68
GOVERNMENT OF MAHARASHTRA
COMMON SCHEDULE OF RATES FOR 2016-17
TUNNEL & ALLIED WORKS

Rate for 2016-17


Sr. (Rate in Rs.)
Item Unit
No.
Completed Item Labour

1 2 3 4 5

85 Item No.85 :-
Excavation of tunnel in all type of rock through Cum. 1770.00
itself / adit by drilling and smooth control
perimeter blasting, mucking, disposing muck in
muck yard, lighting, ventilation inside tunnel
with initial lead of 1Km (From Average face to
Dump yard including length of Adit)etc.
Complete.
86 Item No.86 :-
Excavation of tunnel in all type of rock through Cum. 2435.00
shaft by drilling and smooth control perimeter
blasting, mucking, disposing muck in muck
yard, lighting, ventilation inside tunnel with
initial lead of 1Km (From Average face to
Dump yard) and Initial lift of 50m etc.
Complete.

87 Item No.87 :-
Excavation of shaft in all type of rock by Cum. 2055.00
drilling and smooth control perimeter blasting,
mucking, disposing muck in muck yard,
lighting, ventilation inside shaft with initial lead
of 500m (From top of shaft to Dump yard) and
Initial lift of 25m etc. Complete.

88 Item No.88 :-
Providing and fixing steel rock bolts of various Kg. 177.00
lengths with resin bond cement capsule
anchorage including drilling holes, inserting
grout capsule, driving bolt, fixing 10mm thick
plate and nuts and tightening the same by
torque wrench after hardening of cement grout,
cost of all materials, machinery, labour,
ventilation, lighting, drainage and other
ancillary operations etc complete with lead upto
1km and all lifts.

89 Item No.89 :-
Providing and fixing steel rock bolts of various Kg. 144.00
lengths with mechanical/wedge type anchorage
including drilling holes, providing tapered steel
wedge, plate and nuts and tightening the same
by torque wrench after hardening of cement
grout, cost of all materials, machinery, labour,
ventilation, lighting, drainage & other ancillary
operations etc complete with lead upto 1km
and all lifts.

69
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No.
Completed Item Labour

1 2 3 4 5

90 Item No.90 (A) :-


Providing and fixing steel Anchor (25mm Dia.) Kg. 113.00
with resin bond cement capsule anchorage
including drilling holes, inserting grout capsule,
driving anchor, cost of all materials, machinery,
labour, ventilation, lighting, drainage and other
ancillary operations etc complete with lead upto
1km and all lifts.

Item No.90 (B) :-


Providing and fixing steel Anchor (32 mm dia.) Kg. 82.00
with resin bond cement capsule anchorage
including drilling holes, inserting grout capsule,
driving anchor, cost of all materials, machinery,
labour, ventilation, lighting, drainage and other
ancillary operations etc.

91 Item No.91 :-
Providing fabricating and fixing in position MT 82643.00
permanent structural steel supports as per
details including cost of all materials,
machinery, labour, cutting, bending, welding,
grinding, lighting, ventilation, drainage and all
other ancillary operations etc. complete with
initial lead upto 1 Km and all lifts.

92 Item No.92 :-
Providing fabricating and placing in position MT 53688.00
reinforcement steel for tunnel RCC works
including cleaning, straightening, cutting,
bending, hooking, lapping, welding joints
wherever required, tying with binding wire
including cost of all materials, labour,
machinery, ventilation, lighting, drainage etc.,
complete with initial lead upto 1 km and all lift.

93 Item No.93 :-
Drilling 32mm diameter grout holes in Rmt. 544.00
concrete/rock by per cusion drilling using jack
hammer as directed to specified depth for
consolidation / contact grouting including cost
of all materials, machinery, labour, cleaning
holes, ventilation, lightening, drainage and all
other ancillary operations etc., complete.

70
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No.
Completed Item Labour

1 2 3 4 5

94 Item No.94 :-
Grouting cement slurry in grout holes under MT 10590.00
specified pressure for consolidation / contact
grouting including cost of all materials,
machinery, labour, re drilling wherever
necessary ventilation, lightening, drainage and
other ancillary operations etc., complete with
lead upto 1 Km and all lifts.

95 Item No.95 :-
Providing and applying M-28 plain Wet
shotcrete 50mm thick in layers as directed
including admixtures, scaffolding, necessary
machinery, labours, ventilation, lighting,
drainage and all other ancillary operations etc.
complete with lead upto 1Km & all lifts. (By
non robotic machine.)(Excluding Royalty)

Sqm. 490.00

Cum. 12740.00

96 Item No.96 :-
Providing and applying M-28 plain Wet
shotcrete 50mm thick in layers as directed
including admixtures, scaffolding, necessary
machinery, labours, ventilation, lighting,
drainage and all other ancillary operations etc.
complete with lead upto 1Km & all lifts. (By
robotic machine.) (Excluding Royalty)

Sqm. 473.00
Cum. 12298.00

97 Item No.97 :-
Providing & laying in situ vibrated M-20 grade Cum. 6150.00
cement concrete using 20mm clean, hard,
graded aggregates crushed from tunnel muck
for Side and arch lining including cost of all
materials, machinery, labour, formwork,
batching, mixing, conveying upto placing point
in agitator car, placing in position, laying,
vibrating, finishing, curing, ventilation, lighting,
draining and all other ancillary operations etc.,
complete with lead upto 1Km and all lifts. for
Tunnel . (Excluding Royalty)

71
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No.
Completed Item Labour

1 2 3 4 5

98 Item No.98 :-
Providing & laying in situ vibrated M-20 grade Cum. 6062.00
cement concrete using 20mm clean, hard,
graded aggregates crushed from tunnel muck
for Invert (Kerb and bed) lining including cost
of all materials , machinery, labour, formwork,
batching, mixing, conveying upto placing point
in agitator car, placing in position, laying,
vibrating, finishing, curing, ventilation, lighting,
draining and all other ancillary operations etc.,
complete with lead upto 1Km and all lifts. for
Tunnel . (Excluding Royalty)

72
SECTION-6

LIFT IRRIGATION SCHEME

ITEM NO 99 TO 131

73
74
75
76
GOVERNMENT OF MAHARASHTRA
COMMON SCHEDULE OF RATES FOR 2016-17
LIFT IRRIGATION SCHEME

Rate for 2016-17


Sr. (Rate in Rs.)
Item Unit
No.
Completed Item Labour

1 2 3 4 5

99 Item No.99 :-
Excavation for deep trenches for laying rising Cum 70.90 11.60
main in Earth, Soil of all types, sand, gravel
and soft murum including trimming to correct
line, level and to specified widths including
removing the excavated material and stacking
or spreading the same upto a distance of 15
meters and lifts of 1.5 m as directed, preparing
the bed for foundation and necessary safety
precautions , keep the trench undisturbed till
pipe laying & fixing necessary specials etc
complete as per detailed specifications.
(Payable measurements with vertical
excavation)

100 Item No.100 :-


Excavation for deep trenches for laying rising Cum 86.70 15.40
main in Hard murum, soft bhisa, hard man and
boulder including trimming to correct line and
level and to specified width, including removing
the excavated material and stacking or
spreading the same upto a distance of 15
meters and lifts of 1.5 m as directed, preparing
the bed for foundation and necessary safety
precautions , keep the trench undisturbed till
pipe laying & fixing necessary specials etc
complete as per detailed specifications.
(Payable measurements with vertical
excavation)

101 Item No.101 :-


Excavation for deep trenches for laying rising Cum 105.10 20.60
main in Soft Rock by crow bar and shavel
including trimming to correct line and level and
to specified width including trimming and
levelling the bed by chiselling, removing the
excavated material and stacking the same upto
a distance of 15 meters and lifts of 1.5 m as
directed, and safety precautions to keep the
trench undisturbed till pipe laying & fixing
necessary specials etc complete as per detailed
specifications.
(Payable measurements with vertical
excavation)

77
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No.
Completed Item Labour

1 2 3 4 5

102 Item No.102 :-


Excavation for deep trenches for laying rising Cum 384.20 283.70
main in Hard Rock of any toughness by
blasting to correct line and level and to specified
width including trimming and levelling the bed
as directed, removing the excavated material
and sorting, stacking the same upto a distance
of 15 meters and lifts of 1.5 m as directed,
preparing the bed for foundation and keep the
trench undisturbed till pipe laying & fixing
necessary specials etc complete as per detailed
specifications. (Payable measurements with
vertical excavation)

103 Item No.103 :-


Murum bedding in trenches with murum of Cum. 139.00 98.00
approved quality in layers not exceeding 150
mm to 200 mm, each layer shall be
consolidated by watering and ramming as
directed etc complete. (Without royalty)

104 Item No.104 :-


Providing and filling in sand boxing in trenches Cum. 774.10
with sand of approved quality including watering
and compaction as directed etc complete.

105 Item No.105 :-


Back filling the trenches in layers not Cum. 144.20 144.20
exceeding 300 mm, each layer shall be
consolidated by watering and ramming without
disturbing the pipe line with excavated stuff as
directed including breaking of clods of soil etc
complete. ( The backfilling on the two sides of
the pipeline should be carried out
simultaneously.) (Without royalty)

106 Item No.106 :-


Manufacturing, Providing and Supplying spirally Kg. 65.25 12.90
welded / ERW / SAW / fabricated M.S. pipes
(Commercial Quality) made out of MS plate
conforming to IS 2062:1992 including
procurement of plates, gas cutting to required
size, rolling, tack welding, assembling in
suitable lengths to form pipes, all continuous
spiral/circumferencial and longitudinal welding
to form a pipe on automatic welding machine

78
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No.
Completed Item Labour

1 2 3 4 5

using electrodes having weldmark E7018 (Low


Hydrogen electrodes) and forming 'V' edge on
both ends of pipes, VAT and Excise Duty on
materials required, third party inspection
charges insurance, ,lowering and laying to
correct position on prepared bedding or on
pedestals or chairs, field hydraulic testing at
specified test pressure as per IS 5822: 1994
sec 11,field welding to join pipes after laying,
Radiographic ( 5%) and ultrasonic ( 10%)
testing of welds including all equipments
submitting report, expert personnel required for
testing, interpreting and submitting report along
with develop film where applicable, all incidental
charges etc complete as per IS - 3589:2001 and
as per specifications (No negative Tolerance in
thickness is permissible).
107 Item No.107 :-
Lowering, laying in position to correct line & Kg. 6.00 3.70
level including M.S. pipes with / without any out
coating on prepared bedding or on pedestals or
chairs or upon prepared formation including
loading, unloading, hoisting, marginal cutting
wherever required, assembling and tack
welding, and transportation upto 500 m etc.
completed as specified with all lead & lift etc.
complete including field hydraulic testing at
specified pressure and as per procedure
mentioned in section 11 of IS 5822: 1994. (item
to be used only in situations where pipes are
already procured )
108 Item No.108 :-
Manufacturing, Providing and Supplying tapers Kg. 68.80 15.50
made out of MS plate conforming to IS
2062:1992 including procurement of plates, gas
cutting to required size and shape, rolling, tack
welding, full welding on either automatic welding
machine or manually and forming 'V' edge on
both ends for welding it to pipe, including
fabrication & full welding of stiffeners as per
design requirements, including VAT & ED on all
materials required , third party inspection
charges, insurance, lowering & laying to correct
position etc, complete as per IS - 3589 and IS -
5504 as applicable and as per detailed
specifications. Cost of longitudinal welding
and " V " edging required for circumferencial
welding required to connect
(Item contd. on next page)

79
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No.
Completed Item Labour

1 2 3 4 5

MS special to Rising main /delivery pipes is


inclusive in the rate however circumferencial
welding for connecting the M.S. special to
Rising main shall be paid seperately on running
meter basis.
(No negative Tolerance in thickness is
permissible).

109 Item No.109 :-


Manufacturing, Providing and Supplying "Y" Kg. 79.50 19.30
connection with Crotch plate made out of MS
plate conforming to IS 2062:1992 including
procurement of plates, gas cutting to required
size and shape, rolling, tack welding, full
welding on either automatic welding machine or
manually and forming 'V' edge on all the three
ends for welding it to pipe, including fabrication
and full welding of crotch plate and stiffeners as
per design requirements, including VAT & ED
on all materials required, third party inspection
charges, insurance ,lowering & laying to correct
position etc, complete as per IS - 3589 and IS -
5504 as applicable as per detailed
specifications. Cost of welding of crotch plate is
included in the rate. Cost of longitudinal welding
and " V " edging required for circumferencial
welding required to connect MS special to
Rising main /delivery pipe is inclusive in the rate
however circumferencial welding required for
connecting Y-piece to Rising main / manifold
pipe shall be paid seperately on running meter
basis. (No negative Tolerance in thickness is
permissible).

110 Item No.110 :-


Manufacturing, Providing and Supplying "Y " Kg. 70.40 16.75
and "T" branches with coller plate made out of
MS plate conforming to IS 2062:1992 including
procurement of plates, gas cutting to required
size and shape, rolling, tack welding, full
welding on either automatic welding machine or
manually and forming 'V' edge on both ends for
welding it to pipe, including fabrication & full
welding of coller plate and stiffeners as per
design requirements, including VAT & ED on all
materials required, third party inspection
charges, insurance , (Item contd. on next page)

80
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No.
Completed Item Labour

1 2 3 4 5

lowering & laying to correct position etc,


complete as per IS - 3589 and IS - 5504 as
applicable as per detailed specifications. Cost of
"V" edging, machining and welding of collar
plate in "Y" and "T" connection is included in the
rate. Cost of longitudinal welding and "V"
edging required for circumferencial welding
required to connect MS special to Rising main /
delivery pipes is inclusive in the rate however
circumferencial welding required to connect Y/T
to Rising main or manifold shall be paid
seperately on running meter basis. (No
negative Tolerance in thickness is permissible)

111 Item No.111 :-


Manufacturing, Providing and Supplying Kg 70.40 15.50
manhole covers made out of MS plate
conforming to IS 2062:1992 including
procurement of plates, gas cutting to required
size and shape, rolling, tack welding and full
welding on either automatic welding machine or
manually and forming 'V' edge on both ends,
including fabrication and full welding of
stiffeners as per design requirements, including
VAT & ED on all materials required, insurance,
,lowering & laying to correct position etc,
complete as per IS - 3589 and IS - 5504 as
applicable and as per detailed specifications.
Cost of longitudinal welding and 'V' edging
required for circumferencial welding required to
connect MS special to Rising main /delivery
pipes is inclusive in the rate however
circumferencial welding required for connecting
man hole to Rising main shall be paid
seperately on running meter basis. Cost of
washers , nuts, bolts, etc. required for fixing
manhole cover is included in the rate. (No
negative Tolerance in thickness is permissible).
112 Item No.112 :-
Manufacturing, Providing and Supplying M S Kg 70.40 15.50
bends made out of MS plate conforming to IS
2062:1992 including procurement of plates,
gas cutting to required size and shape, rolling,
tack welding, full welding on either automatic
welding machine or manually and forming 'V'
edge on both ends for welding it to pipe,
including fabrication & full welding of stiffeners
as per design requirements, including VAT &
ED on all materials required, insurance, (Item
contd. on next page)

81
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No.
Completed Item Labour

1 2 3 4 5

,lowering & laying to correct position etc,


complete as per IS - 3589 and IS - 5504 as
applicable as per detailed specifications. Cost
of longitudinal welding and " V " edging required
for circumferencial welding required to connect
MS special to Rising main /delivery pipes is
inclusive in the rate however circumferencial
welding required for connecting M.S. special to
Rising Main shall be paid seperately on running
meter basis.
(No negative Tolerance in thickness is
permissible).
113 Item No.113 :-
Manufacturing, Providing and Supplying short Kg 65.80 12.20
pipes, cants made out of MS plate conforming
to IS 2062:1992 including procurement of
plates, gas cutting to required size and shape,
rolling, tack welding, full welding on either
automatic welding machine or manually and
forming 'V' edge on both ends for welding it to
pipe, including fabrication and full welding of
stiffeners as per design requirements, including
VAT & ED on all materials required, insurance
,lowering & laying to correct position etc,
complete as per IS - 3589 and IS - 5504 as
applicable as per detailed specifications. Cost of
longitudinal welding and " V " edging required
for circumferencial welding required to connect
MS special to Rising main /delivery pipes is
inclusive in the rate however circumferencial
welding required for connecting M.S. special to
Rising Main shall be paid seperately on running
meter basis. (No negative Tolerance in
thickness is permissible).
114 Item No.114 :-
Radiographic testing of welded butt joints in Rmt. 1360.75 555.30
Rising main as per Procedure given in IS
4853:1982 including cost of all materials,
equipments & expert personnel required for
testing, developing, interpreting and submitting
report along with developed films, including all
incidental charges, transportation to site and
local transportation on site etc. complete.

82
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No.
Completed Item Labour

1 2 3 4 5

115 Item No.115 :-


Ultrasonic testing of field welded joints as Rmt. 314.90 164.20
per Procedure laid down in IS 4260:1986
including actual testing, interpreting and
submitting test report in detail including cost of
all materials, equipments & expert personnel
required for testing, developing, interpreting and
submitting report, including all incidental
charges, transportation to site and local
transportation on site etc. complete.

116 Item No.116 :-


Cleaning the surface of rising main pipe by Sqm. 68.60 16.40
Sand Blasting to expose fresh metal surface
ready for painting including removal of all rust,
oil, grease, etc. as per specification including
all material, labour and equipments etc
complete.

117 Item No.117 :-


Providing & applying Liquid epoxy coating Sqm. 567.80 120.00
system to the external surface of Rising Main
Pipes as per Annex-B of IS 3589:2001,
preferably by airless spray with one coat of
Zinc rich epoxy primer( 90 % zink (DFT 40
micron , coverage 9 Sqm / lit) and two coats of
coal tar epoxy paint (DFT 120 X 2 micron
coverage 5 Sqm / Lit / coat) including cleaning
the surface to the satisfaction of Engineer in
charge by sand blasting / chemical cleaning /
scraping removing oil, grease, other foreign
materials including all necessary material ,
labour with all leads and lifts etc. complete.

118 Item No.118 :-


Providing & applying Liquid epoxy coating Sqm. 697.00 120.00
system to the interior surface of Rising Main
Pipes as per Annex - B of IS 3589:2001,
preferably by airless spray with one coat of
Zinc rich epoxy primer (90% zink, DFT 40
micron , coverage 9 Sqm / lit) and three coats
of coal tar epoxy paint (DFT 120 X 3 micron
coverage 5 Sqm/Lit/coat) including cleaning the
surface to the satisfaction of Engineer in charge
by sand blasting / chemical cleaning / scraping
removing oil, grease, other foreign materials
including all necessary material, labour with all
leads and lifts etc. complete.

83
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No.
Completed Item Labour

1 2 3 4 5

119 Item No.119 :-


Providing and applying external 25 mm thick Sqm. 515.40 43.00
cement mortar coating in CM 1 : 3 (cement
consumption 15.94 kg/sqm) pneumatically
under pressure of 2.1 to 2.8 kg /Sq cm, with
weld mesh 50 x 50 x 2.54 mm (13 gauge), after
duly cleaning the surface by wire brushing,
degreasing etc., including necessary
admixtures (200 ml / bag of cement), curing,
rehandling the pipe from fabrication shop to
guniting place and from guniting place to laying
location etc. complete with all leads & lifts.
120 Item No.120 :-
Providing inner cement mortar lining of
specified thickness in proportion 1:1.5 using
mechanical spinning machine, including all
necessary labour, material, plants and
equipments, local handling etc. complete as
per procedure laid down in IS 3589:2001.

a For 9 mm thick inner mortar lining Sqm. 309.80 42.30


b For 12 mm thick inner mortar lining Sqm. 388.00 31.75

121 Item No.121 :-


Supplying, fixing and commissioning C.I.
Tamper proof double orifice type Kinetic Air
Valve manufactured by ISO:9001 certified
manufacturing company, body and seat ring of
bronze, conforming to IS: 14845, of specified
diameter with all fixtures including all taxes,
third party inspection, transportation, loading,
unloading, etc. complete.

P. N. 1.0
Air valve with all accessories
a 80 mm diameter No. 19254.00 ---
b 100 mm diameter No. 22527.00 ---
c 150 mm diameter No. 41467.00 ---
d 200 mm diameter No. 44654.00 ---
P. N. 1.6
Air valve with all accessories
a 80 mm diameter No. 20334.00 ---
b 100 mm diameter No. 25120.00 ---
c 150 mm diameter No. 42061.00 ---
d 200 mm diameter No. 45454.00 ---

84
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No.
Completed Item Labour

1 2 3 4 5

122 Item No.122 :-


Supplying, fixing and commissioning C.I. Scour
Valve (sluice valve) manufactured by
ISO:9001 certified manufacturing company,
body and seat ring of bronze, conforming to IS:
14846 of specified diameter and to withstand
specified pressure with all accessories true to
line and perfect linking with pipes on either side
including lifting and placing in position, cleaning
ends, inserting gaskets into correct position,
jointing pipes and valve to form water tight joint,
including all taxes, third party inspection,
transportation, loading, unloading, etc.
complete.

P. N. 1.0
Scour valve with all accessories
a 100 mm diameter No. 8363.00 ---
b 150 mm diameter No. 12955.00 ---
c 200 mm diameter No. 23121.00 ---
d 250 mm diameter No. 32888.00 ---

P. N. 1.6
Scour valve with all accessories
a 100 mm diameter No. 10036.00 ---
b 150 mm diameter No. 15546.00 ---
c 200 mm diameter No. 27746.00 ---
d 250 mm diameter No. 39466.00 ---

85
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No.
Complete Rate
1 2 3 4 5 6 7
123 Item No.123 :-
Supplying, fixing and commissioning Zero velocity valve with M S fabricated body with
flanged ends manufactured by ISO 9001 certified manufacturing company, conforming to
IS: 1538 / AWWA standards of specified diameter with all fixtures including all taxes, third
party inspection, transportation, loading, unloading, etc. complete.

Zero velocity valve with all accessories


Rate for 2016-17 (Rate in Rs.)
Test pressure
Diameter in mm Unit
10 15 20 25
kg/cm2 kgs/cm2 kgs/cm2 kgs/cm2
600 No. 223697 253146 270080 294353
650 No. 250716 272697 305733 327572
700 No. 293134 318891 357248 382865
750 No. 325245 353661 396219 424636
800 No. 392418 444269 474080 516810
900 No. 467396 529022 554908 615250
1000 No. 570166 570166 570166 764329
1050 No. 578023 578023 578023 803850
1100 No. 718077 803106 868097 946594
1200 No. 858259 934695 1051722 1125776
1400 No. 1278570 1393220 1568762 1679839
1500 No. 1470549 1604097 1804415 1937826
1600 No. 1503433 1639652 1843979 1980054
124 Item No.124 :-
Supplying, installing, testing and commissioning (SITC) electrically actuated Wafer type
flanged Butterfly valve conforming to BS:5155, of specified diameter and manufactured by
ISO 9001 certified manufacturing company, with gear box, electric motor and extension
stem and all other accessories for perfect linking with pipes on either side including lifting
and placing in correct position, cleaning ends, inserting gaskets into correct position, jointing
pipes and valve to form water tight joints, including all taxes, third party inspection,
transportation, loading, unloading, etc. complete.

P. N. 1.0
Butterfly valve with all accessories
a 400 mm diameter No. 39867
b 500 mm diameter No. 68715
c 600 mm diameter No. 98966
P. N. 1.6
Butterfly valve with all accessories
a 400 mm diameter No. 44081
b 500 mm diameter No. 72820
c 600 mm diameter No. 103072

86
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No.
Complete Rate
1 2 3 4 5 6 7
125 Item No.125 :-
Supplying, installing, testing and commissioning (SITC) electrically actuated Double
flanged Butterfly valve conforming to IS:13095, of specified diameter and manufactured
by ISO 9001 certified manufacturing company, with gear box, electric motor and extension
stem and all other accessories for perfect linking with pipes on either side including lifting
and placing in correct position, cleaning ends, inserting gaskets into correct position,
jointing pipes and valve to form water tight joints, including all taxes, third party inspection,
transportation, loading, unloading, etc. complete.

P. N. 1.0
Butterfly valve with all accessories (Double Flanged)
a 700 mm diameter No. 325315
b 800 mm diameter No. 405806
c 900 mm diameter No. 486081
d 1000 mm diameter No. 581699
e 1100 mm diameter No. 726259
f 1200 mm diameter No. 917277
P. N. 1.6
Butterfly valve with all accessories (Double Flanged)
a 700 mm diameter No. 364966
b 800 mm diameter No. 447402
c 900 mm diameter No. 553284
d 1000 mm diameter No. 674399
e 1100 mm diameter No. 826630
f 1200 mm diameter No. 1015487
126 Item No.126 :-
Providing and Supplying C.I. D/F angle type spring loaded Pressure Relief valves
manufactured by ISO 9001 certified manufacturing company with all fixtures including all
taxes, third party inspection, transportation, loading, unloading, etc. complete.
a) Pressure relief valves Type - P.N. 1
100 mm No. 16839
125 mm No. 22847
150 mm No. 26241
200 mm No. 57162
250 mm No. 80166
300 mm No. 105564
b) Pressure relief valves Type - P.N. 1.6
100 mm No. 20931
125 mm No. 28427
150 mm No. 32625
200 mm No. 71254
250 mm No. 99981
300 mm No. 132001

87
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No.
Complete Rate
1 2 3 4 5 6 7
127 Item No.127 :-
Providing and Supplying Air Cushion valves, manufactured by ISO 9001 certified
manufacturing company and conforming to AWWA standards with all fixtures including all
taxes, third party inspection, transportation, loading, unloading, etc. complete.

Rate for 2016-17 (Rate in Rs.)


Test pressure
Diameter in mm Unit
10 15 20 25
kg/cm2 kgs/cm2 kgs/cm2 kgs/cm2
100 No 71115 81783 89960 98952
150 No 108072 124282 136709 150380
200 No 115350 132652 145918 160509
128 Item No.128 :-
Supplying, fixing and commissioning ISI mark CI D/F Non Return Valves (Reflux Valves)
manufactured by ISO 9001 certified manufacturing company, conforming to IS: 5312 (Part
1 & 2) of specified diameter with all fixtures including all taxes, third party inspection,
transportation, loading, unloading, etc. complete.
1 a) Single door : Without by pass arrangement
Dia in mm Unit PN-1 PN-1.6
100 No. 6152 7912
125 No. 8784 11023
150 No. 10635 12337
200 No. 19117 26237
250 No. 32622 42122
300 No. 44701 58854
350 No. 73985 101366
400 No. 101854 117143
450 No. 119990 138215
500 No. 196507 224548
600 No. 288364 329943
1 b) Single door : With by pass arrangement
Dia in mm Unit PN-1 PN-1.6
100 No. 7248 7662
125 No. 9868 10708
150 No. 11721 12997
200 No. 21850 26252
250 No. 35716 39668
300 No. 47941 55132
350 No. 78603 92606
400 No. 105478 121301
450 No. 123408 141919
500 No. 200319 230363
600 No. 292229 336064

88
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No.
Complete Rate
1 2 3 4 5 6 7
1 c) Multi door
Dia in mm Unit PN-1 PN-2
700 No. 766255 731447
750 No. 838738 902119
800 No. 911222 1340988
900 No. `994060 1609184
1000 No. 1159737 1755473
1100 No. -- 2072435
1200 No. -- 2096816
129 Item No.129 :-
Manufacturing, Supplying and installing both side flanged M. S. Dismantling Joints of
specified diameter, manufactured by ISO 9001 certified manufacturing company, including
all taxes, transportation, loading, unloading , third party inspection charges, with all leads
and lifts etc complete . Thickness as per IS : 7322.
Nominal dia in mm
350 No. 57399
400 No. 65775
450 No. 71359
500 No. 85410
600 No. 99384
700 No. 110565
750 No. 113363
800 No. 135724
900 No. 141596
1000 No. 169611
1100 No. 183613
1200 No. 211623
1300 No. 239632
1400 No. 268185
1600 No. 296251
1800 No. 350822
2000 No. 436582
130 Item No.130 :-
Providing and fixing in position Expansion joints manufactured by ISO 9001 certified
manufacturing company for M.S. Rising Main of specified diameter conforming to detailed
specifications including matching the strakes and steel ring, all materials like synthetic
rubber, rubber ring, packings, nuts, bolts, etc complete with all taxes, transporting, loading,
unloading etc complete.
Expansion joints suitable for pipe diameters.
Dia in mm
300 No. 23646
400 No. 34126
450 No. 44390
500 No. 59513
600 No. 69915
700 No. 87035
750 No. 95913
800 No. 111620
900 No. 129598
1000 No. 155180
1200 No. 206097

89
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No.
Complete Rate
1 2 3 4 5 6 7

131 Item No.131 :-


Providing 'X' Ray Quality M.S. Welding in all positions with required number of runs, for
M.S. pipes internally and / or externally including gauging wherever necessary, fixing
appurtenances and other accessories in connection with pipe laying work as per
specification, using electrodes having weld mark E7018 (Low hydrogen electrodes),
including Surface preparation (i.e. Removal of scale, cleaning, etc.) including all materials,
labour, equipments, etc. complete.

A : Single 'V' Butt Joint


Butt Joint : Plate thickness
4 mm Rmt 144.00
5 mm Rmt 218.00
6 mm Rmt 367.00
8 mm Rmt 521.00
10 mm Rmt 748.00
12 mm Rmt 828.00
14 mm Rmt 1204.00
16 mm Rmt 1243.00
18 mm Rmt 1491.00
20 mm Rmt 1755.00
22 mm Rmt 1985.00
25 mm Rmt 2273.00
B : Fillet Type Joint
Fillet Weld Size
4 mm Rmt 153.00
5 mm Rmt 239.00
6 mm Rmt 315.00
8 mm Rmt 439.00
10 mm Rmt 671.00
12 mm Rmt 951.00
14 mm Rmt 1279.00
16 mm Rmt 1788.00

90
SECTION-7

SURVEYING AND INVESTIGATION

ITEM NO 132 TO 152

91
92
93
94
GOVERNMENT OF MAHARASHTRA
COMMON SCHEDULE OF RATES FOR 2016-17
SURVEYING AND INVESTIGATION

Rate for 2016-17


Sr. (Rate in Rs.)
Item Unit
No.
Completed Item Labour

1 2 3 4 5

SURVEY WORK - COMPLETED ITEM


(WITH TOTAL STATION)

132 Item No.132 :-


Double levelling using Digital State of art Total Km. 1501.00
Station to connect Geodetic Trigonometrical
survey, bench mark and establishing
permanent bench mark at Dam site at place
along the canal alignment, submergence and
in command area etc complete.(Excluding cost
of B.M. structure)

133 Item No.133 :-


Block contour survey of 10 x 10m grid for Ha. 1250.00
irrigation projects using digital state of art Total
station, Including transfer of entire data to
computer system in different geo referential
layer/ themes using features of standard
plotting Softwares compatible with canal
irrigation system design Softwares packages
including contour plotting at specified interval
and scale.

134 Item No.134 :-


Block contour survey of 15 x 15m grid for Ha. 842.00
irrigation projects using digital state of art Total
station, including transfer of entire data to
computer system in different georeferential
layer/ themes using features of standard
Softwares compatible with canal irrigation
system design Softwares packages including
contour plotting at specified interval and scale.

135 Item No.135 :-


Block contour survey of 20 x 20m grid for Ha. 631.00
irrigation projects using digital state of art Total
station, including transfer of entire data to
computer system in different georeferential
layer/ themes using features of standard
plotting Softwares compatible with canal
irrigation system design Softwares packages
including contour plotting at specified interval
and scale.

95
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No.
Completed Item Labour

1 2 3 4 5

136 Item No.136 :-


Block contour survey of 30 x 30m grid for Ha. 433.00
irrigation projects using digital state of art Total
station, including transfer of entire data to
computer system in different georeferential
layer/ themes using features of standard
plotting Softwares compatible with canal
irrigation system design Softwares packages
including contour plotting at specified interval
and scale.

137 Item No.137 :-


Block contour survey of 60 x 30m grid for Ha. 223.00
irrigation projects using digital state of art Total
station, including transfer of entire data to
computer system in different georeferential
layer/ themes using features of standard
plotting Softwares compatible with canal
irrigation system design Softwares packages
including contour plotting at specified interval
and scale.

138 Item No.138 :-


Block contour survey of 150 x 30m grid for Ha. 99.00
irrigation projects using digital state of art Total
station, including transfer of entire data to
computer system in different georeferential
layer/ themes using features of standard
plotting Softwares compatible with canal
irrigation system design Softwares packages
including contour plotting at specified interval
and scale.

139 Item No.139 :-


Carrying out line survey using digital state of Km. 1238.00
art Total station for fixing FRL/HFL including
C/s survey with levels at 20m interval/ survey
for 'L' section of alternative Dam site and 'L'
section of river 1Km u/s 1Km D/s of alternative
Dam line etc complete including transfer of
entire data to computer system in different
georeferential layer/ themes using features of
standard plotting Softwares compatible with
canal irrigation system design Softwares
packages including contour plotting at
specified interval and scale.

96
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No.
Completed Item Labour

1 2 3 4 5

140 Item No.140 :-


Survey for main canal, branches, distributaries Km. 1486.00
on falling contour including investigation of
alternative line, taking falling contour fixing
canal line, taking 'L' section and cross section
on final line and distributaries survey be ETS
etc complete. (Excluding fixing apex/ chainage
stones) including transfer of entire data to
computer system in different georeferential
layer/ themes using features of standard
plotting Softwares compatible with canal
irrigation system design Softwares packages
including contour plotting at specified interval
and scale. Absolutely linear survey for all
types of canals (Length of survey for L-section
and cross sections to be measured seperately
for payment)

141 Item No.141 :-


Providing and casting plain cement concrete No. 3825.00
structure as shown in the sketch attached
along with as Permanent Bench Mark (P.B.M)
at dam, command site, in submergence area,
along canal alignment, in area including
excavation necessary backfilling etc complete.

142 Item No.142 :-


Fixing precast RCC alignment blocks (Pillar) No. 460.85
on alternative dam site finally approved of
size 900 x 175 x 100 mm at 90 M interval
including fixing in 1:4:8 (600 x 450 x 450mm)
cement concrete, excavation, backfilling and
coloring etc as necessary. (Steel 0.75 Kg.)

SURVEY ITEMS FOR DEPARTMENTAL


EXECUTION (LABOUR RATES ONLY)

143 Item No.143 :-


Supplying labours for Double levelling to Km. 757.00
connect Geodetic Trignometrical Survey,
Bench mark and establishing the permanent
Bench mark at Dam site at place along the
canal alignment submergence and in
command area etc complete. (Excluding cost
of P.B.M. structure)

97
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No.
Completed Item Labour

1 2 3 4 5

144 Item No.144 :-


Supplying labours for Submergence survey Ha. 428.00
including establishment of temporary bench
mark to prepare submergence plan with 1 to
1.5 mt. interval contours etc complete (Grid
size 30 x 60 mt.)

145 Item No.145 :-


Supplying labours for Detailed survey of dam Ha. 832.00
seat and waste weir and borrow area finally
approved including mapping to the extent 3
meter above the top of dam level on either
flanks and 500 meter up-stream and 500m
down-stream, showing all important features,
rock outcrops, pools, water courses etc
complete. (Grid size 30 x 30M)

146 Item No.146 :-


Supplying labours for Survey for longitudinal Km. 2423.00
section of Alternative dam alignment and
longitudinal section of river 1.00km. up-stream
and 1.00 km. down-stream of alternative dam
alignment etc complete.

147 Item No.147 :-


Supplying labours for Contour survey for Ha. 186.00
command area including preparation of
contour map with 1.00m contour interval,
including establishing working temporary
bench mark in command area etc complete.
(Grid size 150 x 30m)

148 Item No.148 :-


Supplying labours for Survey for main canal, Km. 3029.00
branches, distributaries on falling contour,
including investigation of alternative line, taking
falling contour, fixing canal line, taking
longitudinal-section and cross-section of final
line and distributaries survey etc complete.

98
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No.
Completed Item Labour

1 2 3 4 5

INVESTIGATION & FOUNDATION


EXPLORATION

149 Item No.149 :-


Taking trial bore for detailed investigation with
NX diamond drill double tube in all sorts of soil
like soft murum, hard murum and boulders
including all materials such as casing pipes,
accessories, grease, steel balsams and other
such materials and or as required including
conveying such materials and machinery to
site of works, preserving the loose samples in
glass/plastic jar and core samples serially
numbered at site of work and conveying the
same to the head quarter of concerned office
as directed and submission of detailed bore log
sheet complete.(As directed by the Engineer in
charge)

(A) Over Burdon Rmt. 2000.00


(B) Soft Rock/Weathered rock Rmt. 3000.00
(C) Hard Rock other than quartzite Rmt. 3900.00

150 Item No.150 :-


Providing core boxes of non-teak jungle wood No. 3152.00
(normal) of size 1.50 x 0.35 x 0.10m for
preserving core samples with all fixtures and
fastening, painting, handles, locking
arrangement including material and labor etc
complete.

151 Item No.151 :-


Carrying out water intake test / permeability Test 461.85
test at any stage or depth as may be directed
by Engineer In charge by filling the bore hole
with water or air at specific pressure of
specified limit as and where directed etc
complete.

152 Item No.152 :-


Excavation for taking trial pits on final Cum. 88.40
alignment of dam line and canal at specified
interval and in Nalla-bed of size 2.00 x 2.00 x
2.50mtr. in length, breadth and depth
respectively or size as may be directed by the
Engineer In charge including backfilling trial
pits etc complete.

99
100
SECTION-8

HYDROLOGY

ITEM NO 153 TO 159

101
102
103
104
GOVERNMENT OF MAHARASHTRA
COMMON SCHEDULE OF RATES FOR 2016-17
HYDROLOGY

Rate for 2016-17


Sr. (Rate in Rs.)
Item Unit
No.
Completed Item Labour

1 2 3 4 5

153 Item No.153 :-


Standard Rain Gauge (Measurer) Per 1129.00
Providing person to take measurement at every Month
morning 8:30 am to SRG station, taking the
entry in the register. Send the reading daily to
Sub-Dn by post card & monthly progress
(reading) to Sub-Dn, including taking care of
instruments established on the station.
(Required Proforma / post card / Register etc.
will be supplied by concern Sub-Dn. The rate of
item is for 35 minutes per day working.
154 Item No.154 :-
Autographic Rain Gauge (Gauge Khalashi) Per 2418.00
Providing person to take measurement at every Month
morning 8:30 am of autographic rain gauge
station including changing graph at 8:30 am,
taking reading in the register, also sending
reading to Sub-Dn by post card & monthly
progress (reading) send to Sub-Dn, with taking
care of instruments established on the station.
(Required Proforma/post card/Register etc. will
be supplied by concern Sub-Dn.) The rate of
item is for 75 minutes per day working.
155 Item No.155 :-
Full Climatic Station (Gauge Karkoon) Per 15441.00
Providing person to take reading from the Month
scientific instruments established in the F.C.S
Station (Given below) including taking reading in
the register as per prescribed Proforma given by
the Sub-Dn, also send to concern Engineer in
the proforma time to time. The rate of item is for
daily working.

1) ARG 2) SRG 3) Pan Evaporimeter, 4) Pan


Water Temperature, 5) Thermometer (i. Dry,
ii. Wet, iii. Minimum, iv. Maximum) 6) Thermo
hygrograph. 7) Anemometer,8) Wind Vane, 9)
Sunshine Recorder.

105
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No.
Completed Item Labour

1 2 3 4 5

156 Item No.156 :-


Gauge Discharge Per 14960.00
(Gauge Khalashi/ Gauge Karkoon ) Month
Providing to supply of Gauge Khalashi/ Gauge
Karkoon (He is a good Swimmer & he must
have to take measurements in the river in rainy
& other season) including accidental insurance,
service tax. The rate of item is for daily working.

157 Item No.157 :-


Gauge Discharge Per 15904.00
(Gauge Khalashi/ Gauge Karkoon) Month
Providing Gauge Khalashi/ Gauge Karkoon to
take measurement by winch &Cradle with
current meter or by float method from required
compartment in the flood season, taking
measurements at every hour or instruction given
by concern Engineer, taking Water levels in four
times daily, change paper of AWLR and
Calculate Velocity as per given area. Taking all
readings in the register, send all readings to
Concern Engineer/ Higher Engineer as per
instructions in the prescribed proforma,
including accidental insurance, service tax. The
rate of item is for daily working.
158 Item No.158 :-
Gauge Discharge (Boat Driver) Per 16413.00
Providing Boat driver for GD Station to drive the Month
boat for taking measurements near
compartment in the Steady position. After taking
the measurement brought back the boat &
concern persons in the boat safely. Installed the
boat in out of danger area etc. complete,
including accidental insurance, service tax.
(Boat Driving Licence given by Govt. Authority
or authorised organization must be mandatory
to boat driver). The rate of item is for daily
working.

159 Item No.159 :-


Gauge Discharge (Boat Chowkidar) Per 15684.00
Providing Chowkidar to take care & Security of Month
boat (He is not an ordinary person, he is a good
swimmer, when the Water Level of river
increase or decrease, he must have tighten the
boat of safe place & taking care of boat in the
night.) including accidental insurance, service
tax. The rate of item is for daily working.

106
SECTION-9
ITEMS FOR VALUATION OF STRUCTURES IN
AFFECTED VILLAGES

ITEM NO 160 TO 191

107
108
109
110
GOVERNMENT OF MAHARASHTRA
COMMON SCHEDULE OF RATES FOR 2016-17
ITEMS FOR VALUATION OF STRUCTURES IN AFFECTED VILLAGES

Rate for 2016-17


Sr. (Rate in Rs.)
Item Unit
No.
Completed Item Labour
1 2 3 4 5

160 Item No.160 :-


Providing and constructing stone masonry in
mud mortar in foundation and plinth including
scaffolding, finishing etc. complete.
A) Up to Plinth Cum. 957.60
B) Super structure Cum. 1070.20
161 Item No.161 :-
Providing and constructing U.C.R. masonry in Cum. 1686.40
lime 1:6 mortar in foundation and plinth
including scaffolding, finishing etc. complete.
162 Item No.162 :-
Providing second class B.B. masonry with
conventional/ I.S. type bricks in mud mortar in
super structures, including racking out joints,
when plastering is to be done including
scaffolding and watering etc. complete.
A) For Super structure Cum. 4091.80
B) For foundation and Plinth Cum. 4031.90
163 Item No.163 :-
Providing and constructing arch like B.B. Cum. 2241.65
Masonry slab roofing including 'I' Section as a
bottom support and tie rods with scaffolding,
centering, etc complete.
164 Item No.164 :-
Providing and constructing gawhan for cattle Rmt. 1661.80
(0.6 x 10.0 M)
165 Item No.165 :-
Providing 50 mm. mud plaster including racking Sqm. 119.10
out joints , scaffolding all finishing etc. complete.
166 Item No.166 :-
Providing and constructing Kud walls including Sqm. 230.20
mud plaster with cow dung wash etc. complete.
167 Item No.167 :-
Providing 25 mm thick mud plaster to kud walls Sqm. 86.50
including cow dung wash etc. complete.
168 Item No.168 :-
Providing and constructing Kud roof/walls Sqm. 115.70
excluding mud plaster etc. complete.
169 Item No.169 :-
Providing and constructing Kud walls including Sqm. 410.90
mud plaster with cow dung wash etc. complete.

111
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No.
Completed Item Labour
1 2 3 4 5

170 Item No.170 :-


Providing and constructing Kud walls, splite & Sqm. 418.60
Bamboo knitted together & covered with 12 mm.
thick mud plaster etc. complete.
171 Item No.171 :-
Providing and constructing kud roofing Sqm. 418.50
excluding mud plaster etc. complete.
172 Item No.172 :-
Providing and fixing non teak wood Dhaba Sqm. 4075.90
including mud flooring and mud plaster on non
teak planks, rested on non teak rafter at 1.5
X2.5 m. intervals, including mud flooring over
the planks etc. complete (Jungle wood Dhaba )
173 Item No.173 :-
Providing and fixing teak wood dhaba including Sqm. 7952.60
mud flooring and mud plasters on non teak
wood planks rested on non teak wood rafters
1.5 X2.5 m. intervals including mud flooring etc.
complete.
174 Item No.174 :-
Providing and constructing wall of bamboo Sqm. 308.80
splited and knitted together including all labour
material lead and lift etc. complete.
175 Item No.175 :-
Providing and constructing mud boulder otta No. 841.70
with earthen Ranjan.
176 Item No.176 :-
Providing and constructing Mud Wall including Cum. 1245.20
preparation of mud mortars surface done
placing scaffolding etc.
177 Item No.177 :-
Providing and fixing non teak doors /windows 40 Sqm. 3762.00
mm. Thick ledged with 25 mm. Thick plain
planked shutters without ventilators /fan light
/iron bars including the frames of the sizes as
per standard specification, iron fixtures and
fastenings and finishing the wood work with
oiling etc. complete.
178 Item No.178 :-
Providing and fixing non teak doors / window II Sqm. 5668.00
class fully pannelled without ventilators /fan light
/iron bars including the frames of the sizes as
per standard specification, iron fixtures and
fastenings and finishing the wood work with
oiling etc. complete.

112
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No.
Completed Item Labour
1 2 3 4 5

179 Item No.179 :-


Providing and fixing non teak doors ledged and Sqm. 5480.30
braced with 20 mm. thick planked shutters
including the frame without sill with all fixture
and fastenings oiling varnishing etc. complete.
180 Item No.180 :-
Providing and fixing Jungle wood door of frame Sqm. 2367.70
60 mm X 100 mm for second class door's and
window with/ without ventilators fan light and
clear storey windows including chamfering /
rounding rebating and hold fast finishing with
one coat of primer etc complete
181 Item No.181 :-
Providing and fixing C T W frame with G I Sheet Sqm. 1946.70
Shutter
182 Item No.182 :-
Providing and fixing country teak wood plank Sqm. 1589.20
ceilling 12 mm. Thick with planked on
underside, longuled and grooved including
scaffolding , fixtures with oiling and two coats of
varnishing etc. complete. ( excluding battens
and joists)
183 Item No.183 :-
Providing and fixing non teak wood plank Sqm. 875.20
ceilling 12 mm. Thick with planked on
underside, longuled and grooved including
scaffolding , fixtures with oiling and two coats of
varnishing etc. complete. ( excluding battens
and joists)
184 Item No.184 :-
Providing and fixing wooden self of country teak Sqm. 755.70
wood plank 30 cm. wide and 20 mm. thick with
wooden brackets of 50mm. x 50mm without
fillets including all fixtures with oiling and
painting etc . complete.
185 Item No.185 :-
Providing and fixing eaves board of country teak Sqm. 409.80
wood plank 20 cm. x 20mm thick plan
decorative type including scaffolding & painting
with 2 coats etc. complete.
186 Item No.186 :-
Providing and fixing shutter to wall cupboard Sqm. 2688.50
made 12 mm. Thick teak wood/ particle board
one face with approved colour laminated face
borided with phenol formal desynthetic lipping,
beading oxidized iron fixtures & oil primer coat
etc. complete.

113
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No.
Completed Item Labour
1 2 3 4 5

187 Item No.187 :-


Providing & fixing xpm Jalli with teak wood /non
teak wood frame including fixing oiling etc.
complete.
i) Non teak wooden frame into wooden bar jalli Sqm. 1446.80

ii) N.T. Wooden frame & M.S. Bar Sqm. 898.40


iii) Country teak wooden frame with M.S. bar Sqm. 1370.35

iv) xpm. Jalli with wooden frame Sqm. 1309.20


v) Providing and fixing xpm jalli with non teak Sqm. 812.00
wood frame including fixing oiling etc. complete.

88 Item No.188 :-
Providing and fixing half round single country Sqm. 556.30
tiled roofing over bamboo battens including
nails, battens etc. complete.

189 Item No.189 :-


Providing and fixing medium grade G I pipe Rmt. 296.90
below C G I sheet roofing etc complete.

190 Item No.190 :-


Providing and fixing M S angle of size 35 x 35 x Rmt. 190.50
6 mm

191 Item No.191 :-


Providing and fixing half round single country Sqm. 649.70
tiled roofing over bamboo mats laid on half split
bamboo battens including all fastenings etc.
complete.

114
SECTION-10

GATE MANUFACTURING AND REPAIRS

ITEM NO 192 TO 208

115
116
117
118
2016-17

1 All materials / bought out components for embedded parts, gates, hoists and allied works
shall conform to relevant Indian standards as provided in Annexure-I.

2 The basic rates are INCLUSIVE of preparation of Q.A.P. / working drawings material
schedules etc., as per specifications and other technical data including revisions. If the
responsibility of the structural designs is on the contractor, additional 1% amount shall be
payable.

3 The basic rates are inclusive of 3 percent provision towards cost of packing, forwarding
and transportation of all materials from their source of supply up to work site. No separate
lead charges and loading unloading shall be added.

4 The basic rates are inclusive of Machinery mobilization (1.5%) & Demobilization (1.5%)
Charges on machinery charges.
5 The basic rates are inclusive of 1% labour welfare and 10% overhead charges.
6 The basic rates are inclusive of 1km lead charges of transportation, loading and unloading
charges of Gate parts at Site. Additional lead if any shall be considered in the rate
analysis.

7 Fabrication charges includes all welding charges including tack welding and full welding
and its testing.
8 The basic rates are inclusive of preparatory works such as rectification of damages,
repairing shop, painting, cleaning, positioning and anchoring first stage embedment.

9 The basic rates are inclusive of painting with one coat of 90% pure zinc rich primer and
2 coats of solvent less coal tar epoxy paint with sand blasting.

10 Incremental provisions for tribal area, hilly area etc. shall be made on labour component
only.
11 HOIST EQUIPMENT -1. Where sand blasting is not possible, hand and power tool/ chemical
cleaning be adopted without any additional cost.
12 The excise duty on material component is considered in the rate analysis of the finished
item. The excise duty on machinery and labour component is not included in the rate
analysis. However, separate provision shall be provided for excise duty on machinery and
labour component in the estimate as separate item. Against this provision reimbursement
to the contractor can be done. Such reimbursement shall be done on production of
voucher of actual paid excise duty by the contractor. This reimbursement shall be
minimum of excise duty actually paid by the contractor or entitled excise duty
reimbursement as provided in the contract. In contract separate schedule shall be
provided indicating maximum reimbursable excise duty and service tax against each item.

13 Excise duty is applicable on supply of finished fabricated parts. The cost of material is
inclusive of all taxes/ duties. Therefore for purpose of assessing excise duty 75% of the
total cost excluding the cost of material is considered and for assessing service tax on
erection 25% of total cost excluding the cost of materials is considered.

119
120
Annexure 1
List of IS codes

1 IS 4622 Recommendations for Structural design of fixed wheel gates

2 IS 2062 Hot rolled low, medium, high tensile Structural steel

Recommendations for Structural design of radial gates


3 IS 4623
(Second Revision)

4 IS1030 Carbon steel castings for general engineering purposes.

5 IS28 Phosphor bronze ingots and castings

6 IS305 Specification for Aluminum Bronze ingots and casting

7 IS 318 Specification for leaded tin bronze ingots and casting

8 IS 6911 stainless steel plate , sheet and strip

9 IS 209 Zinc Ingot specification

Guidelines for Design and use of Different type of Rubber seals for
10 IS 11855
hydraulic gates.

11 IS 14177 Guidelines for painting system for hydraulic gates and hoists.

12 IS 2485 Drop forged sockets for wire ropes for general engineering purposes

13 IS 325 -1996 Three phase induction motor specification

14 IS 2266-2000 Specification of wire ropes.

15 IS7443 Methods for load Rating of Warm Gears

16 IS 10210-1982 Design of hydraulic hoist for gates.

Recommendations for inspection, testing and maintenance of fixed


17 IS 7718-1991
wheel and slide gates (first revision).
Recommendation for structural design of medium and high head slide
18 IS 9349
gates

19 IS 210 Geay iron castings

20 IS 6938 Design for rope drum and chain hoist for hydraulic gates

21 IS 1030 Carbon steel and castings

22 IS 7215 Tolerances for fabrication of steel structures.

121
122
GOVERNMENT OF MAHARASHTRA
COMMON SCHEDULE OF RATES FOR 2016-17
GATE MANUFACTURING

Rate for 2016-17


Sr. (Rate in Rs.)
Item Unit
No. Completed
Labour
Item
1 2 3 4 5

(A) RADIAL GATE EMBEDMENT - Manufacturing,


Erection, Commissioning & Testing

192 Item No.192 :-


Manufacturing with QAP, fabrication, erection, MT 114636.00 15166.00
commissioning & testing of embedded parts of
Radial gate with parts consisting of Erection Jig,
Vertical Anchorages, Trunion Chair, Trunion Girder
box/Yoke Girders, Horizontal anchorages, Trunion
bracket assly, Wall plate assly, Sill beam assly,
trunion supports, Locking arrangement, etc. All
material used shall conformed to related IS Codes
specified in IS 4623. Above item covers Mild steel
confirming to IS 2062. The tolerances between
Components & assembly Shall confirm to IS
4623.the fits and tolerances between the bronze
bushing & hub shall be H7r6 (Interference fit )& with
pin shall be H7f7 (Clearance fit) and for antifriction
bearings with hub shall be H7 (Interference) &
antifriction bearing with pin shall be r6 (Interference )
as per IS 4623. Other Material includes C.S.
(IS1030), Brass (IS 28), P. Bronze (IS 305), Al.
Bronze (IS 318), S.S. (IS 6911), Zinc (IS 209),
Welding electrodes (AWS E6013 for general weld
joints & E7018 for X ray quality weld joints). It
includes all materials, Labour charges, machining
and machinery charges, 1km lead charges of
transportation, loading and unloading charges of
Gate parts at Site, Inspection & Quality control
charges, Sand blasting, Painting with one coat of
Zinc rich primer containing not less than 90% of zinc
on dry film to give total dry film thickness 70 +/- 5
microns and 2 coats of sloventless coal tar epoxy
paint applied to give minimum dry film thickness of
150+/- 5 micron per coat as per IS 14177, overhead
charges of 10%, and all incidential charges including
all duties, taxes, levies and insurance charges .The
embedment & gate assembly shall be reasonably
water tight, the maximum permissible leakage being
not more than 5 litres/min/m wetted length of seal.
The surface finish of seal plates should be within the
range of 1.6 to 6.3 m (IS 9349).
Note 1 - Provision for Excise duty reimbursement
Rs.3863/ Mt shall be made in the estimate.
Note 2 - Provision for Service tax on erection
Rs.1545/ Mt shall be made in the estimate.

123
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No. Completed
Labour
Item
1 2 3 4 5

193 RADIAL GATE LEAF - Manufacturing, Erection,


Commissioning & Testing

Item No.193 :-
Manufacturing with QAP, fabrication, erection, MT 107643.00 14203.00
commissioning & testing of Gate leaf of Radial gate
with parts consisting of End arm assly, Horizontal
Girder, Skin plate assly, tie flats/Channels, Bracing
Angles & Gusset plate etc. All material used shall
conformed to related IS Codes specified in IS 4623.
Above item covers Mild steel confirming to IS 2062.
The tolerances between Components & assembly
Shall confirm to IS 4623. The fits and tolerances
between the bronze bushing & hub shall be H7r6
(Interference fit )& with pin shall be H7f7 (Clearance
fit) and for antifriction bearings with hub shall be H7
(Interference) & antifriction bearing with pin shall be
r6 ( Interference ) as per IS 4623. Other Material
includes C.S. (IS1030), Brass (IS 28), P. Bronze (IS
305), Al. Bronze (IS 318), S.S. (IS 6911), Zinc (IS
209), Rubber seal (IS 11855), Welding electrodes
(AWS E6013 for general weld joints & E7018 for X
ray quality weld joints). It includes all materials,
Labour charges, machining and machinery charges,
1km lead charges of transportation, loading and
unloading charges of Gate parts at Site, Inspection &
Quality control charges, Sand blasting, Painting with
one coat of Zinc rich primer containing not less than
90 % of zinc on dry film to give total dry film
thickness 70+/-5 microns and 2 coats of sloventless
coal tar epoxy paint applied to give minimum dry film
thickness of 150+/- 5 micron per coat as per IS
14177, overhead charges of 10%, and all incidential
charges including all duties, taxes, levies and
insurance charges .The embedment & gate
assembly shall be reasonably water tight, the
maximum permissilble leakage being not more than
5 liters/min/m wetted length of seal. The surface
finish of seal plates should be within the range of 1.6
to 6.3 m (IS 9349).
Note 1 - Provision for Excise duty re-
imbursement Rs.3089/ Mt shall be made in the
estimate.
Note 2 - Provision for Service tax on erection
Rs.1235/ Mt shall be made in the estimate.

124
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No. Completed
Labour
Item
1 2 3 4 5

194 HOIST BRIDGE - Manufacturing, Erection,


Commissioning & Testing
Item No.194 :-
Manufacturing with QAP, fabrication, erection, MT 91389.00 18212.00
commissioning & testing of Hoist Bridge. All materials
used shall conformed to related IS Codes. Mild steel
used for manufacturing shall conform to IS 2062.
Welding electrodes (AWS E6013 for general weld
joints & E7018 for X ray quality weld joints). It includes
all materials, Labour charges, machining and
machinery charges, 1km lead charges of
transportation, loading and unloading charges of Gate
parts at Site, Inspection & Quality control charges,
Sand blasting, Painting with one coat of Zinc rich
primer containing not less than 90 % of zinc on dry film
to give total dry film thickness 70 +/- 5 microns and 2
coats of sloventless coal tar epoxy paint applied to give
minimum dry film thickness of 150+/- 5 micron per coat
as per IS 14177, overhead charges of 10%, and all
incidential charges including all duties, taxes, levies
and insurance charges.
Note 1 - Provision for Excise duty reimbursement
Rs.2677/ Mt shall be made in the estimate.
Note 2 - Provision for Service tax on erection
Rs.1071/ Mt shall be made in the estimate.

195 ROPE DRUM HOIST without Hoist Bridge -


Manufacturing, Erection, Commissioning & Testing
Item No.195 :-
Manufacturing with QAP, fabrication, erection, MT 195686.00 9698.00
commissioning & testing with 125 % of rated capacity
of Rope Drum Hoist consisting of central drive unit,
gear train frames, rope drums, gears, pinions, shafts, 3
phase electric motor, brake, reduction gear box, wire
ropes, gate position indicators, manual operation
arrangement, ICTP main switch, electric starter, etc. All
material used shall conformed to related IS Codes
specified in IS 6938. Above item covers Mild steel
confirming to IS 2062. the fits and tolerances between
the bronze bushing & hub shall be H7r6 (Interference
fit )& with pin shall be H7f7 (Clearance fit) and for
antifriction bearings with hub shall be H7 (Interference)
& antifriction bearing with pin shall be r6 (Interference )
as per IS 4623. Other Material includes C.I (IS 210),
C.S (IS1030), P. Bronze (IS 305), Al. Bronze (IS 318),
S.S (IS 6911), Wire rope (IS 2266), Wire rope sockets (
Is 2485), 3p S4 duty Induction Motor (IS 325),
Reduction gear box ( IS 7443), Welding electrodes
(AWS E6013 for general weld joints.
(Item contd. on next page)

125
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No. Completed
Labour
Item
1 2 3 4 5
& E7018 for X ray quality weld joints ).It includes all
materials, Labour charges, machining and machinery
charges, 1km lead charges of transportation, loading
and unloading charges of Gate parts at Site, Inspection
& Quality control charges, Sand blasting, Painting with
one coat of Zinc rich primer containing not less than
90 % of zinc on dry film to give total dry film thickness
70 +/- 5 microns and 2 coats of solvent less coal tar
epoxy paint applied to give minimum dry film thickness
of 150+/- 5 micron per coat as per IS 14177, overhead
charges of 10%, and all incidental charges including all
duties, taxes, levies and insurance charges
Note 1 - Provision for Excise duty reimbursement
Rs.4718/ Mt shall be made in the estimate.
Note 2 - Provision for Service tax on erection
Rs.1887/ Mt shall be made in the estimate.
196 VERTICAL LIFT BARRAGE GATE EMBEDMENT /
STOP LOG GATE EMBEDMENT - Manufacturing,
Errection, Commissioning & Testing
Item No.196 :-
Manufacturing with QAP, fabrication, erection, MT 115247.00 12829.00
commissioning & testing of embedded parts of V.L.
Barrage gate/Stop log gate Consisting of Primary
Embedments, Sill beam, Roller Track, Side guide, Side
seal kit etc.All material used shall conformed to
related IS Codes. Mild steel confirming to IS 2062.The
tolerances between Bushing/Bearing /Pin Should
confirm to IS 919 ( Part I & II). Other Material includes
C.S. (IS1030), Brass (IS 28), P. Bronze (IS 305), Al.
Bronze (IS 318), S.S. (IS 6911), Rubber seal (IS
11855), Welding electrodes (AWS E6013 for general
weld joints & E7018 for X ray quality weld joints). It
includes all materials, Labour charges, machining and
machinery charges, 1km lead charges of
transportation, loading and unloading charges of Gate
parts at Site, Inspection & Quality control charges,
Sand blasting, Painting with one coat of Zinc rich
primer containing not less than 90 % of zinc on dry film
to give total dry film thickness 70 +/- 5 microns and 2
coats of sloventless coal tar epoxy paint applied to give
minimum dry film thickness of 150+/- 5 micron per coat
as per IS 14177.The embedment & gate assembly
shall be reasonably water tight, the maximum
permissilble leakage being not more than 5 litres/min/m
wetted length of seal. The surface finish of seal plates
should be within the range of 1.6 to 6.3 m (IS 9349).
overhead charges of 10%, and all incidential charges
including all duties, taxes, levies and insurance
charges .
Note 1 - Provision for Excise duty reimbursement
Rs.2901/ Mt shall be made in the estimate.
Note 2 - Provision for Service tax on erection
Rs.1160/ Mt shall be made in the estimate.

126
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No. Completed
Labour
Item
1 2 3 4 5
197 VERTIAL LIFT BARRAGE GATE LEAF / STOP LOG
GATE LEAF - Manufacturing, Erection,
Commissioning & Testing
Item No.197 :-
Manufacturing with QAP, fabrication, erection, MT 103017.00 15001.00
commissioning & testing of Gate leaf of V.L.
Barrage gate Consisting of of following parts. Gate
Leaf, Horizontal girder, Guide roller assembly, &
Roller Assembly. All material used shall conformed
to related IS Codes. Mild steel confirming to IS
2062.The tolerances between Components &
assembly Shall confirm to IS 4623.the fits and
tolerances between the bronze bushing & hub shall
be H7r6 (Interference fit )& with pin shall be H7f7
(Clearance fit) and for antifriction bearings with hub
shall be H7 (Interference) & antifriction bearing with
pin shall be r6 (Interference ) as per IS 4623. Other
Material includes C.S.(IS1030), Bras (IS 28), P.
Bronze (IS 305), Al. Bronze (IS 318), S.S. (IS 6911),
Rubber seal (IS 11855), Welding electrodes (AWS
E6013 for general weld joints & E7018 for X ray
quality weld joints). It includes all materials, Labour
charges, machining and machinery charges, 1km
lead charges of transportation, loading and unloading
charges of Gate parts at Site, Inspection & Quality
control charges, Sand blasting, Painting with one
coat of Zinc rich primer containing not less than 90 %
of zinc on dry film to give total dry film thickness 70
+/- 5 microns and 2 coats of sloventless coal tar
epoxy paint applied to give minimum dry film
thickness of 150+/- 5 micron per coat as per IS
14177,The embedment & gate assembly shall be
reasonably water tight, the maximum permissible
leakage being not more than 5 liters/min/m length of
seal. overhead charges of 10%, and all incidential
charges including all duties, taxes, levies and
insurance charges.
Note 1 - Provision for Excise duty reimbursement
Rs.3375/ Mt shall be made in the estimate.
Note 2 - Provision for Service tax on erection
Rs.1350/ Mt shall be made in the estimate.
198 PYLON STRUCTURE - Manufacturing, Erection,
Commissioning & Testing
Item No.198 :-
Manufacturing with QAP, fabrication, erection, MT 91803.00 12987.00
commissioning & testing of Pylon Structure. All
materials used shall conformed to related IS Codes.
Mild steel used for manufacturing shall conform to IS
2062. Welding electrodes (AWS E6013 for general
weld joints & E7018 for X ray quality weld joints). It
includes all materials, Labour charges,
(Item contd. on next page)

127
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No. Completed
Labour
Item
1 2 3 4 5

machining & machinery charges, 1km lead charges


of transportation, loading and unloading charges of
Gate parts at Site, Inspection & Quality control
charges, Sand blasting, Painting with one coat of
Zinc rich primer containing not less than 90 % of zinc
on dry film to give total dry film thickness 70 +/- 5
microns and 2 coats of sloventless coal tar epoxy
paint applied to give minimum dry film thickness of
150+/- 5 micron per coat as per IS 14177, overhead
charges of 10%, and all incidential charges including
all duties, taxes, levies and insurance charges .
Note 1 - Provision for Excise duty reimbursement
Rs.2263/ Mt shall be made in the estimate.
Note 2 - Provision for Service tax on erection
Rs.905/ Mt shall be made in the estimate.

199 GOLIATH CRANE - Manufacturing, Erection,


Commissioning & Testing

Item No.199 :-
Manufacturing with QAP, fabrication, erection, MT 146591.00 9775.00
commissioning & testing with 125 % of rated capacity
of Goliath Crane consisting of drive unit, A Frame,
Main Frame, , LT Driving and driven trolleys, CT
Crab Including Central Drive unit, gear train frames,
rope drums, gears, pinions, shafts, Driving electric
motor, brake, reduction gear box, wire ropes, manual
operation arrangement, ICTP main switch, electric
starter, etc. All material used shall conformed to
related IS Codes specified in IS 6938. Above item
covers Mild steel confirming to IS 2062. the fits and
tolerances between the bronze bushing & hub shall
be H7r6 (Interference fit )& with pin shall be H7f7
(Clearance fit) and for antifriction bearings with hub
shall be H7 (Interference) and antifriction bearing
with pin shall be r6 (Interference ) as per IS 4623.
Other Material includes C.I (IS 210), C.S (IS1030),
P. Bronze (IS 305), Al. Bronze (IS 318), S.S (IS
6911), Wire rope (IS 2266), Wire rope sockets ( Is
2485), 3p S4 duty Induction Motor (IS 325),
Reduction gear box ( IS 7443), Welding electrodes
(AWS E6013 for general weld joints & E7018 for X
ray quality weld joints ). It includes all materials,
Labour charges, machining and machinery charges,
1km lead charges of transportation, loading and
unloading charges of Gate parts at Site, Inspection &
Quality control charges, Sand blasting, Painting with
one coat
(Item contd. on next page)

128
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No. Completed
Labour
Item
1 2 3 4 5

of Zinc rich primer containing not less than 90 % of


zinc on dry film to give total dry film thickness 70 +/-
5 microns and 2 coats of sloventless coal tar epoxy
paint applied to give minimum dry film thickness of
150+/- 5 micron per coat as per IS 14177, overhead
charges of 10%, and all incidential charges including
all duties, taxes, levies and insurance charges .
Note 1 - Provision for Excise duty reimbursement
Rs.2480/ Mt shall be made in the estimate.
Note 2 - Provision for Service tax on erection
Rs.992/ Mt shall be made in the estimate.
200 GOLIATH RAIL ARRANGEMENT - Manufacturing,
Erection, Commissioning & Testing
Item No.200 :-
Manufacturing with QAP, fabrication, erection, MT 83618.00 6165.00
commissioning & testing of Railing arrangement for
Goliath Crane.MS Material used shall conform to IS
2062. The Dimensions, shape and other
requirements of Crane rail sections conform to IS
3443.Welding electrodes (AWS E6013 for MS to MS
weld joints & E7016 for MS to rail weld joints ). It
includes all materials, Labour charges, machining
and machinery charges, 1 km lead charges of
transportation, loading and unloading charges of
Gate parts at Site, Inspection & Quality control
charges, Sand blasting, Painting with one coat of
Zinc rich primer containing not less than 90 % of zinc
on dry film to give total dry film thickness 70 +/- 5
microns as per IS 14177, overhead charges of 10%,
and all incidential charges including all duties, taxes,
levies and insurance charges.
Note 1 - Provision for Excise duty reimbursement
Rs.1771/ Mt shall be made in the estimate.
Note 2 - Provision for Service tax on erection
Rs.708/ Mt shall be made in the estimate.

201 LIFTING BEAM - Manufacturing, Errection,


Commissioning & Testing
Item No.201 :-
Manufacturing with QAP, fabrication, erection, MT 79820.00 8832.00
commissioning & testing of Lifting Beam.MS Material
used shall conform to IS 2062. All parts of Lifting
Beam like Guide rollers, Hooks, Pins, conform to IS
13591.Welding electrodes (AWS E6013 for MS to
MS weld joints & E7016 for MS to rail weld joints ). It
includes all materials, Labour charges, machining
and machinery charges, 1km lead charges of
transportation, loading and unloading charges of
Gate parts at Site, Inspection & Quality control
charges, Sand blasting, Painting with one coat of
Zinc rich primer containing not less than 90 % of
(Item contd. on next page)

129
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No. Completed
Labour
Item
1 2 3 4 5

zinc on dry film to give total dry film thickness 70 +/-


5 microns and 2 coats of sloventless coal tar epoxy
paint applied to give minimum dry film thickness of
150+/- 5 micron per coat as per IS 14177, overhead
charges of 10%, and all incidential charges including
all duties, taxes, levies and insurance charges .
Note 1 - Provision for Excise duty reimbursement
Rs.1980/ Mt shall be made in the estimate.
Note 2 - Provision for Service tax on erection
Rs.792/ Mt shall be made in the estimate.
202 OUTLET GATE-SLIDING TYPE EMBEDMENT -
Manufacturing, Erection, Commissioning &
Testing
Item No.202 :-
Manufacturing with QAP, fabrication, erection, MT 131272.00 14603.00
commissioning & testing of Sliding type gate
Embedments consisting of following parts. Sill
Beam, Track Girder, Vertical Seal & Horizontal Seal
assly., Guide Tee & Lining Plate. Anchorages etc.All
material used shall conformed to related IS Codes.
All material used shall conformed to related IS
Codes specified in IS 9349. Mild steel confirming to
IS 2062.The tolerances for embeded parts and in
components of gate are as per IS 9349. The
tolerances between Bushing/Bearing /Pin Should
confirm to IS 919 ( Part I & II). Other Material
includes C.S. (IS1030), Brass (IS 28), P. Bronze (IS
305), Al. Bronze (IS 318), S.S. (IS 6911), Rubber
seal (IS 11855), Welding electrodes (AWS E6013
for general weld joints & E7018 for X ray quality
weld joints). It includes all materials, Labour charges,
machining and machinery charges, 1km lead
charges of transportation, loading and unloading
charges of Gate parts at Site, Inspection & Quality
control charges, Sand blasting, Painting with one
coat of Zinc rich primer containing not less than 90 %
of zinc on dry film to give total dry film thickness 70
+/- 5 microns and 2 coats of sloventless coal tar
epoxy paint applied to give minimum dry film
thickness of 150+/- 5 micron per coat as per IS
14177, overhead charges of 10%, and all incidential
charges including all duties, taxes, levies and
insurance charges .The embedment & gate
assembly shall be reasonably water tight, the
maximum permissilble leakage being not more than
5 liters/min/m wetted length of seal. The surface
finish of seal plates should be within the range of 1.6
to 6.3 m (IS 9349).

Note 1 - Provision for Excise duty reimbursement


Rs.3357/ Mt shall be made in the estimate.
Note 2 - Provision for Service tax on erection
Rs.1343/ Mt shall be made in the estimate.

130
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No. Completed
Labour
Item
1 2 3 4 5
203 OUTLET GATE-SLIDING TYPE GATE LEAF -
Manufacturing, Erection, Commissioning &
Testing

Item No.203 :-
Manufacturing with QAP, fabrication, erection, MT 116517.00 14662.00
commissioning & testing of Gate leaf of Sliding type
gate Consisting of following parts. Skin plate
skeleton, End Verticals, Guide Brackets, vertical and
horizontal stiffeners etc. (As per Drg.) All material
used shall conformed to related IS Codes specified
in IS 9349. Mild steel confirming to IS 2062.The
tolerances for embeded parts and in components of
gate are as per IS 9349. The tolerances between
Bushing/Bearing /Pin Should confirm to IS 919 ( Part
I & II). Other Material includes C.S. (IS1030), Brass
(IS 28), P. Bronze (IS 305), Al. Bronze (IS 318), S.S.
(IS 6911), Rubber seal (IS 11855), Welding
electrodes (AWS E6013 for general weld joints &
E7018 for X ray quality weld joints). It includes all
materials, Labour charges, machining and machinery
charges, 1km lead charges of transportation, loading
and unloading charges of Gate parts at Site,
Inspection & Quality control charges, Sand blasting,
Painting with one coat of Zinc rich primer containing
not less than 90 % of zinc on dry film to give total dry
film thickness 70 +/- 5 microns and 2 coats of
sloventless coal tar epoxy paint applied to give
minimum dry film thickness of 150+/- 5 micron per
coat as per IS 14177, overhead charges of 10%, and
all incidential charges including all duties, taxes,
levies and insurance charges. The gates shall be
reasonably watertight. Leakage, if any, unless
otherwise specified, shall not normally exceed 5 and
10 litre/min/m wetted length of periphery of the
sealing surface, for medium and high head gates,
respectively as per IS 9349.
Note 1 - Provision for Excise duty reimbursement
Rs.2753/ Mt shall be made in the estimate.
Note 2 - Provision for Service tax on erection
Rs.1101/ Mt shall be made in the estimate.

204 OUTLET GATE ROLLER TYPE WITH BUSH IN


ROLLER- GATE LEAF - Manufacturing, Errection,
Commissioning & Testing
Item No.204 :-
Manufacturing with QAP, fabrication, erection, MT 123285.00 17207.00
commissioning & testing of parts of Roller type gate
leaf with bush in the roller consisting of following
parts. Skin plate skeleton, End verticals, Guide
bracket etc.(As per Drg.) All material used shall
conformed to related IS Codes specified in IS 4622.
(Item contd. on next page)

131
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No. Completed
Labour
Item
1 2 3 4 5
Mild steel confirming to IS 2062.The tolerances for
embeded parts of gate are as per IS 4622. Other
Material includes C.S. (IS1030), Brass (IS 28), P.
Bronze (IS 305), Al. Bronze (IS 318), S.S. (IS 6911),
Rubber seal (IS 11855), Welding electrodes (AWS
E6013 for general weld joints & E7018 for X ray
quality weld joints). The tolerances between
Components & assembly Shall confirm to IS
4623.the fits and tolerances between the bronze
bushing & hub shall be H7r6 (Interference fit )& with
pin shall be H7f7 (Clearance fit) and for antifriction
bearings with hub shall be H7 (Interference) &
antifriction bearing with pin shall be r6 (Interference )
as per IS 4623.The above items also include Sundry
Material, Workshop charges, Labour charges,
Inspection & Quality control charges, Sand blasting
with one coat of Zinc rich primer containing not less
than 90 % of zinc on dry film, should be applied to
give total dry film thickness 70 +/- 5 microns. Also 2
coats of slovent less coal tar epoxy paint should be
given with a minimum dry film thickness of 150+/- 5
micron per coat should be applied as per IS
14177.The gates shall be reasonably watertight.
Leakage, if any, unless otherwise specified, shall not
normally exceed 5 and 10 liter/min/m wetted length
of periphery of the sealing surface, for medium and
high head gates, respectively as per IS 9349.

Note 1 - Provision for Excise duty reimbursement


Rs.3347/ Mt shall be made in the estimate.
Note 2 - Provision for Service tax on erection
Rs.1339/ Mt shall be made in the estimate.

205 OUTLET GATE ROLLER TYPE WITH BEARING


IN ROLLER GATE LEAF - Manufacturing,
Erection, Commissioning & Testing
Item No.205 :-
Manufacturing with QAP, fabrication ,erection, MT 159608.00 17101.00
commissioning & testing of Gate leaf of Roller type
gate with Bearing in the roller consisting of following
parts. Skin plate skeleton, End verticals, roller
bearings, Guide bracket etc. (As per Drg.) All
material used shall conformed to related IS Codes
specified in IS 4622. Mild steel confirming to IS
2062.The tolerances for components of gate are as
per IS 4622The tolerances between Components &
assembly Shall confirm to IS 4623 the fits &
tolerances between the bronze bushing & hub shall
be H7r6 (Interference fit) & with pin shall be H7f7
(Clearance fit) and for antifriction bearings with hub
(Item contd. on next page)

132
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No. Completed
Labour
Item
1 2 3 4 5
shall be H7 (Interference) & antifriction bearing with
pin shall be r6 (Interference ) as per IS 4623. Other
Material includes C.S. (IS1030), Brass (IS 28), P.
Bronze (IS 305), Al. Bronze (IS 318), S.S. (IS 6911),
Rubber seal (IS 11855), Welding electrodes (AWS
E6013 for general weld joints & E7018 for X ray
quality weld joints). The above items also include
Sundry Material, Workshop charges, Labour
charges, Inspection & Quality control charges, Sand
blasting with one coat of Zinc rich primer containing
not less than 90 % of zinc on dry film, should be
applied to give total dry film thickness 70 +/- 5
microns. Also 2 coats of slovent less coal tar epoxy
paint should be given with a minimum dry film
thickness of 150+/- 5 micron per coat should be
applied as per IS 14177.The gates shall be
reasonably watertight. Leakage, if any, unless
otherwise specified, shall not normally exceed 5 and
10 liter/min/m wetted length of periphery of the
sealing surface, for medium and high head gates,
respectively as per IS 9349.
Note 1 - Provision for Excise duty reimbursement
Rs.3489/ Mt shall be made in the estimate.
Note 2 - Provision for Service tax on erection
Rs.1395/ Mt shall be made in the estimate.

206 SCREW STEM HOIST - Manufacturing, Erection,


Commissioning & Testing
Item No.206 :-
Manufacturing with QAP, fabrication, erection, MT 100649.00 9349.00
commissioning & testing with 125 % of rated capacity
of Screw stem hoist consisting of Screw stem, Nut,
Gear Pinion, Worm wheel, Shaft, Keys etc. All
material used shall conformed to IS Codes specified
in IS 11228.Mild steel confirming to IS 2062. Other
Material includes C.S. (IS1030), P. Bronze (IS 305),
Welding electrodes (AWS E6013 for general weld
joints & E7018 for X ray quality weld joints).The
tolerances between Components & assembly Shall
confirm to IS 4623.the fits and tolerances between
the bronze bushing and hub shall be H7r6
(Interference fit )& with pin shall be H7f7 (Clearance
fit) and for antifriction bearings with hub shall be H7
(Interference) & antifriction bearing with pin shall be
r6 (Interference ) as per IS 4623. It includes all
materials, Labour charges, machining and machinery
charges, 1km lead charges of transportation, loading
and unloading charges of Gate parts at Site,
Inspection & Quality control charges, Sand blasting,
Painting with one coat of Zinc rich primer containing
not less
(Item contd. on next page)

133
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No. Completed
Labour
Item
1 2 3 4 5
less than 90 % of zinc on dry film to give total dry film
thickness 70 +/- 5 microns and 2 coats of sloventless
coal tar epoxy paint applied to give minimum dry film
thickness of 150+/- 5 micron per coat as per IS 14177,
overhead charges of 10%, and all incidential charges
including all duties, taxes, levies and insurance
charges.
Note 1 - Provision for Excise duty reimbursement
Rs.2770/ Mt shall be made in the estimate.
Note 2 - Provision for Service tax on erection
Rs.1108/ Mt shall be made in the estimate.
207 Straight Needle K.T. Weir Gate- Manufacturing
Item No.207 :-
Manufacturing with QAP & fabrication of KT weir MT 81336.00 4777.00
needle gates - straight type size 2.15 x 0.5M- 94 Kg.
weight as per relevant Indian Standards with all
material, Mild steel confirming to IS 2062, Rubber seal
confirming to IS 4623 & Welding electrodes AWS
E6013 for general weld joints. It includes all materials,
Labour charges, machinery charges, 1km lead charges
of transportation, loading and unloading charges of
Gate parts at Site, Inspection & Quality control
charges, Sand blasting, Painting with one coat of Zinc
rich primer containing not less than 90 % of zinc on dry
film to give total dry film thickness 70 +/- 5 microns and
2 coats of sloventless coal tar epoxy paint applied to
give minimum dry film thickness of 150+/- 5 micron per
coat as per IS 14177, overhead charges of 10%, and
all incidential charges including all duties, taxes, levies
and insurance charges.
Note 1 - Provision for Excise duty reimbursement
Rs.1222/ Mt shall be made in the estimate.
208 Curved Needle K.T. Weir Gate- Manufacturing
Item No.208 :-
Manufacturing with QAP & fabrication of KT weir MT 96142.00 5987.00
needle gates - curved type size 2.15 x 0.5M- 75 Kg.
Weight as per relevant Indian Standards with all
material, Mild steel confirming to IS 2062, Rubber seal
confirming to IS 4623 & Welding electrodes AWS
E6013 for general weld joints. It includes all materials,
Labour charges, machinery charges, 1km lead
charges of transportation, loading and unloading
charges of Gate parts at Site, Inspection & Quality
control charges, Sand blasting, Painting with one coat
of Zinc rich primer containing not less than 90 % of
zinc on dry film to give total dry film thickness 70 +/- 5
microns and 2 coats of sloventless coal tar epoxy paint
applied to give minimum dry film thickness of 150+/- 5
micron per coat as per IS 14177, overhead charges of
10%, and all incidential charges including all duties,
taxes, levies and insurance charges.
Note 1 - Provision for Excise duty reimbursement
Rs.1524/ Mt shall be made in the estimate.

134
SECTION-11

FLOW MEASURING DEVICES

ITEM NO 209 TO 212

135
136
137
138
GOVERNMENT OF MAHARASHTRA
COMMON SCHEDULE OF RATES FOR 2016-17
FLOW MEASURING DEVICES

Rate for 2016-17


Sr. (Rate in Rs.)
Item Unit
No.
Completed Item Labour

1 2 3 4 5

209 Item No.209 :-


Providing and fixing gauge plate of Aluminum
composite panel sheet with exterior panel coated
with kynar 500(min 70%) PVDF coating with
computerized gauge marking with reflective radium
pasting, spray lamination with polyurethane
chemical for surface protection including material
reqd for fixing, nut bolts, washers, Nylon rope,
hanger, drilling machine etc. and including all
taxes.
Sqm. 23672.00 1430.00
210 Item No.210 :-
Providing, installing & erecting in correct line and
level, fiber glass reinforced plastics(FRP) " V
notch" of following sizes and discharge capacities,
for acurate measurement of water flowing through
open channel with prefabricated fiber glass lining
moulded engraved gauge marking ( in lit/sec and in
cms) including discharge table, capacity marking,
flow direction, sand treatment on the back side of "
V" notch ,testing , etc. complete and including all
taxes.
(Excluding base preparation ie CBL, canal
section other concrete etc.)

a FRP V notch having discharge capacity 15 lit/ sec No. 11213.00 477.00
of section 20 x 40 cms with upstream and
downstream channel
b FRP V notch having discharge capacity 30 lit/ sec No. 17442.00 596.00
of section 25 x 50 cms with upstream and
downstream channel
c FRP V notch having discharge capacity 45 lit/ sec No. 19697.00 715.00
of section 28 x 56 cms with upstream and
downstream channel
d FRP V notch having discharge capacity 60 lit/ sec No. 23609.00 834.00
of section 30 x 60 cms with upstream and
downstream channel
e FRP V notch having discharge capacity 90 lit/ sec No. 29888.00 953.00
of section 35 x 70 cms with upstream and
downstream channel
f FRP V notch having discharge capacity 120 lit/ sec No. 37748.00 1072.00
of section 42 x 84 cms with upstream and
downstream channel

139
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No.
Completed Item Labour

1 2 3 4 5

211 Item No.211 :-


Providing, installing & erecting in correct line and
level, fiber glass reinforced plastics(FRP) cut
throat flume (CTF) measuring devices on
calculated hump level for acurate measurement
of water flowing through open channel, with
prefabricated fiber glass lining moulded engraved
gauge marking ( in lit/sec and in cms.) including
discharge table, capacity marking, flow direction,
sand treatment on the back side of flume, testing,
etc. complete and including all taxes.
(Excluding CBL and hump preparation, canal
section and other concrete required for hump,
U/S and D/S slopes of hump etc.)

a Cut throat flume 10 x 90 cms -0.33 cusecs No. 4139.00 715.00


b Cut throat flume 10 x 90 cms 0.50 cusecs No. 4623.00 715.00
c Cut throat flume 20 x 90 cms -1.0 cusecs No. 9023.00 953.00
d Cut throat flume 20 x 90 cms -2.0 cusecs No. 9816.00 953.00
e Cut throat flume 20 x 90 cms -3.0 cusecs No. 11018.00 953.00
f Cut throat flume 20 x 90 cms -4.0 cusecs No. 11417.00 953.00
g Cut throat flume 40 x 80 cms -5.0 cusecs No. 27690.00 1430.00
h Cut throat flume 40 x 80 cms -6.0 cusecs No. 29285.00 1430.00
i Cut throat flume 40 x 80 cms 8.0 cusecs No. 30876.00 1430.00
j Cut throat flume 40 x 80 cms -10.0 cusecs No. 32477.00 1430.00
k Cut throat flume 40 x 80 cms 12.0 cusecs No. 34073.00 1430.00
l Cut throat flume 40 x 80 cms 15.0 cusecs No. 37264.00 1430.00
m Cut throat flume 40 x 80 cms -18.0 cusecs No. 38865.00 1430.00
n Cut throat flume 40 x 80 cms 20.0. cusecs No. 40461.00 1430.00
o Cut throat flume 100 x 270 cms -25 cusecs No. 66425.00 1906.00
p Cut throat flume 100 x 270 cms -30 cusecs No. 68773.00 1906.00
q Cut throat flume 100 x 270 cms -35 cusecs No. 73470.00 1906.00
r Cut throat flume 100 x 270 cms 40 cusecs No. 78161.00 1906.00
s Cut throat flume 100 x 270 cms -50 cusecs No. 82863.00 1906.00
t Cut throat flume 100 x 270 cms 60 cusecs No. 89907.00 1906.00
u Cut throat flume 100 x 270 cms -70 cusecs No. 94604.00 1906.00
v Cut throat flume 100 x 270 cms 80 cusecs No. 101639.00 1906.00

140
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No.
Completed Item Labour

1 2 3 4 5

212 Item No.212 :-


Providing , installing & erecting in correct line and
level, fiber glass reinforced plastics(FRP) parshall
flume on calculated hump level of following sizes
and discharge capacities, for acurate measurment
of water flowing through open channel with
prefabricated fiber glass lining moulded engraved
gauge marking ( in lit/sec and in cms) including
discharge table, capacity marking, flow direction,
sand treatment on the back side of flume, testing,
etc. complete and including all taxes.
(Excluding CBL and hump preparation, canal
section and other concrete required for hump,
U/sand D/S slopes of hump etc.)

a Parshall flume-242.80 x 437 cms-100 cusecs No. 243372.00 1906.00

b Parshall flume-243.80 x 437 cms-150 cusecs No. 259249.00 1906.00

c Parshall flume-426 x 595.50 cms-200 cusecs No. 465177.00 2859.00

d Parshall flume-426.70 x 595.50 cms-250 cusecs No. 476822.00 2859.00

e Parshall flume- 426 x 595.50 cms-300 cusecs No. 488159.00 2859.00

f Parshall flume-426.70x 595.50 cms-400 cusecs No. 516490.00 2859.00

g Parshall flume - 457 x 1189 cms -500 cusecs No. 852828.00 3812.00

h Parshall flume - 457 x 1189 cms -750 cusecs No. 909292.00 3812.00

i Parshall flume - 610 x 1311 cms -1000 cusecs No. 1220690.00 3812.00

j Parshall flume - 610 x 1311 cms -1250 cusecs No. 1295683.00 3812.00

k Parshall flume - 762 x 1341 cms -1500 cusecs No. 1346940.00 3812.00

141
142
SECTION-12

MARKING BLUE LINE AND RED LINE

ITEM NO 213 TO 219

143
144
145
146
GOVERNMENT OF MAHARASHTRA
COMMON SCHEDULE OF RATES FOR 2016-17
MARKING BLUE LINE & RED LINE

Rate for 2016-17


Sr. (Rate in Rs.)
Item Unit
No.
Completed Item Labour

1 2 3 4 5

213 Item No.213 :-


Fixing control points by Differential Global Position Km 1031.00
System (DGPS) instrument at every One Km.
along the both side of river including collection of
necessary flood data etc. complete including
labour welfare cess, service tax, labour insurance
and all applicable taxes etc. complete as directed
vide Technical circular of MERI Nashik
No.DSO/PB-4/1582 dated 16/11/2015.

214 Item No.214 :-


Traverse Survey along river with cross section at
100 m .c/c along river .The levels on cross section
shall be at every 30 m c/c beyond past locally
observed flood line, using Differential Global
Position System (DGPS) instrument including
labor, transportation, using sounding by boat in
river water in wet condition and transfer of entire
data to computer system in different geo
referential layers/ themes using features of
standard plotting software computable with
design software package including contour
plotting at required interval and at a scale and
following deliverables etc. all complete as directed
vide Technical circular of MERI Nashik
No.DSO/PB-4/1582 dated 16/11/2015.

A) Survey in dry condition Ha. 403.80


B) Survey in wet condition Ha. 449.75

215 Item No.215 :-


Delivering Contour map of 0.50 m. contour Ha. 35.90
interval by using standard software &
superimposing it on village map with scale1:5000
showing Prohibited line( Blue line) & Restricted
line (Red line) along with mapping of structures &
other details etc all complete as directed vide
Technical circular of MERI Nashik No.DSO/PB-
4/1582 dated 16/11/2015.

147
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No.
Completed Item Labour

1 2 3 4 5

216 Item No.216 :-


Providing computerised detailed cross section Sheet 324.00
drawings in two copies at 100 m interval with
actual profile of river (levels at every 30m.
distance along cross section) on A-3 size paper
with scale 1cm = 15m or 1cm = 30m which is
suitable as per site condition showing 25 year
return flood line (Blue line) and 100 years return
flood line (Red line) computed by software
analysis and submission in the form of soft and
hard copy as directed by Engineer in charge. So
as to use the data of above Item No.213 to 215 by
HEC-RAS Software. including submission of
check print and getting approval of Engineer in
charge etc all complete as directed vide Technical
circular of MERI Nashik No.DSO/PB-4/1582 dated
16/11/2015.

217 Item No.217 :-


Computation of Blue line ( 25 Year return flood Km 2429.00
line ) and red line ( 100 year return flood line ) by
using HEC-RAS software including estimation of
flood getting approval of competent authority for
the same giving all the precise necessary input
details into the software, viz. cross sectional and
longitudinal features of the stream, flow
obstructions etc. including site validation &
recalculation to the satisfaction of Engineer In
charge etc all complete as directed vide Technical
circular of MERI Nashik No.DSO/PB-4/1582 dated
16/11/2015.

218 Item No. 218 :-


Providing computerised detailed river alignment Sheet 978.00
with contours on A-1 size paper with scale 1 cm
equal to 15 m or 30m whichever is suitable as per
site condition. (one sheet for one Km. length of
river) with contour at 0.50 m. interval including
marking 25 years return flood level (Blue line) &
100 years return flood level (Red line) line &
showing locations of bridges, KT Weirs & other
permanent structures on each drawing along and
across the river as directed by Engineer in
Charge, including providing one color check print
& six hard copies(color print) with one soft copy
etc. all complete as directed vide Technical
circular of MERI Nashik No.DSO/PB-4/1582 dated
16/11/2015.

148
Rate for 2016-17
Sr. (Rate in Rs.)
Item Unit
No.
Completed Item Labour

1 2 3 4 5

219 Item No.219 :-


Marking of 25 years flood level ( blue line) & No. 441.00
100 years flood level ( Red line) on permanent
structures like Bridges, Temples & other
permanent structures along & across river
including painting, lettering at every not less
than 100 m. interval & not more than 500 m. on
both the banks of river, after the final approval of
flood level. as directed by engineer in charge etc.
all complete as directed vide Technical circular of
MERI Nashik No.DSO/PB-4/1582 dated
16/11/2015.

149