1.

0 Site Acquisition 6-12 months

2.0 Infrastructure work


2.1 Site clearance 1/2 months
2.2 Earthwork 1 month
2.3 Drainage & culvert 2-6 months
2.4a Roadworks - Subbase 1 month
2.4b Roadworks - Roadbase & surfacing 1 month
2.5 Power supply (HT, LT & Substation) 9 - 12 months
2.6 External water recticulation (piping & bulk meter) 3 - 6 months

3.0 Building works


3.1 Piling works 1 - 3 months
3.2 Substructure 1 months
3.3 Superstructure 3 - 6months
3.4 Architectural works 9 - 18 months
3.5 Gate & fencing 4 - 9 months
3.6 Internal wiring and plumbing works 9 - 18 months

4.0 Government & Statutory Approval


4.1 State Planning Authority & Land Survey - AVTC & Subdivision approval 12 - 18 months
4.2 Land Survey - Separate land title 18 - 24 months
4.3 Local Authority - Building plan application and approval 3 months
4.4 Local Authority - Road certificate & Occupation permit 1 month
4.5 Sibu Water Board 1month
4.6 SESCO 6 month
4.7 Ministry of Housing: Developer's license & sales permit approval 3 months
4.8 BOMBA - Fire safety Inspection 1month

5.0 Professional Consultancy & Services


5.1 Subdivsion Planning and Design 3 month
5.2 Land Surveying 3 month
5.3 Soil investigation 1month
5.4 Civil and Structural 1 - 2 month
5.5 Architectural 3 month
5.6 Mechanical and Electrical 1month
5.7 Quantity Surveying 1month
5.8 Legal whole duration
5.9 Accountancy & Secretarial whole duration
5.10 Project management whole duration