Академический Документы
Профессиональный Документы
Культура Документы
Wherever the location of a dam is, its ecological results are the same. The
environmental impacts of dams can be classified according to different criterions as
long term and short term impacts, the impacts in the vicinity of the structure and
impact further downstream from the structure. The magnitudes of the effects are
usually directly related to the size of the dam.
Prior to dam construction, most natural watercourses have a flow rate that varies
widely throughout the year in response to varying seasonal conditions. Of course
once a dam is constructed, the flow rate of the watercourse below a dam is
restricted. The dam itself and the need to control water releases for the various
purposes of the particular dam result in a flow rate that has a smaller range of values
and peaks than what would normally occur. This may have a detrimental effect on the
ecosystems downstream of the dam as flow volume and duration, water chemistry,
water temperature and sediment load are all altered. In instances where the dam
results in no water flow downstream of the dam destruction of ecosystems is
inherent.
Because water is held behind the dam and often released from some depth, the
temperature of the water below the dam is usually lower than it would be prior to dam
emplacement. The temperature of the water flow is often constant, not reflecting the
natural seasonal variations that would have been the case in the free-flowing
watercourse. Similarly, the chemistry of the water may be altered. Water exiting the
reservoir may be higher in dissolved salts or have lower oxygen levels than would be
the case for a free-flowing watercourse.
The impoundment of water behind a dam causes the velocity of the water to drop.
Sediment carried by the river is dropped in the still water at the head of the reservoir.
Below the dam, the water flows from the clear water directly behind the dam.
Because the watercourse no longer carries any sediment, the erosive potential of the
river is increased. Erosion of the channel and banks of the river below the dam will
ensue. Even further downstream, sediment deprivation affects shoreline processes
and biological productivity of coastal regions.
This document was prepared at the request of the Brown Hill Creek Working Party.
The objectives of this report are to:
1
highlight deficiencies in the environmental assessment that has been
undertaken to date and make recommendations as to further work required.
The construction of two flood control dams is likely to increase the level of protection
upstream of Cross Roads and downstream from Anzac Highway to 1:100 ARI. The
level of protection between Cross Road and Anzac Highway is likely to be increased
to a 1:20 ARI for a minority of properties and 1:50 ARI for the majority of properties
along this section of Brown Hill Creek.
Topography
Brown Hill Creek is a small intermittent stream on the western slopes of the Mount
Lofty Ranges. The stream flows six months of the year during periods of heavy
rainfall. Flooding of the creek occurs after periods of low intensity rainfall exceeding a
36 hour period.
The Brown Hill Creek catchment originates near Eagle on the Hill. The creek flows
north west in an unlined channel though the rural section before entering the urban
area near Old Belair Road. The channel remains unlined until it reaches Heywood
Avenue in Unley Park, after which point, the channel is concrete for the remainder of
its length. Major constrictions in the channel occur at Cross Roads, at the Glenelg-
Adelaide tramway and at Daly Street in Kurralta Park.
The catchment covers and area of 32km 2 (upstream of the airport) and flows through
the suburbs of Crafers West, Mitcham, Westbourne Park, Millswood, Ashford,
Kurralta Park and the Netley before discharging to the sea through the Patawalonga
Lake.
The Brown Hill Creek catchment consists mainly of rural land in the Hills Face Zone
and as such it mainly vegetated. The upper reaches of the catchment have medium
grades and defined riverine channels which retard flow and limit the spread of flood
waters out of the channel. The middle and lower reaches have defined channels, but
flatter grades hence flood waters are more likely to spread out of the channels in
major storm events.
2
Topography
Dam 1
The proposed site of Dam 1 (referred to as Basin 2 in the Master Plan) is located
several hundreds of metres upstream of the junction of Brown Hill Creek Road and
Tilleys Hill Road.
The area around the proposed site of Dam 1 has a long history of vegetation
clearance and landscape degradation. The site was historically used as market
garden irrigated from Brown Hill Creek. Historical irrigation practices have resulted in
significant alteration and disturbance of the stream bed. The majority of indigenous
riparian vegetation has been cleared however some significant tress are located in
close proximity to the site of the proposed Dam.
Currently vegetation at the site consists of woodland of mature Manna Gum trees
(Eucalyptus vimimalis) and scattered River Red gums (Eucalyptus camaldulensis)
over an understorey dominated with introduced species. Trees on the north western
slopes of the creek are suffering from die back most likely due to deforestation by
introduced Koala (Phascolarctus cinereus)
Dam 2
The proposed site of Dam 2 (referred to a Basin 4 in the Master Plan) is on the
southern arm of Brown Hill Creek towards the upper boundary Mitcham and Adelaide
Hills Councils. This site is located within a steep valley that has been cleared
previously for crop cultivation. Natural regeneration of both native vegetation and
exotic weed species has since occurred. The site is relatively inaccessible to both
pedestrian and vehicle access.
Currently vegetation at the site consists of woodland of mature trees of Manna Gum
(Eucalyptus viminalis) with some River Red Gums (Eucalyptus camaldulensis). There
is an extensive understorey of woody and herbaceous introduced species including
invasive pest olives and blackberry.
3
Aboriginal and European Heritage
The proposed Brown Hill Creek Flood Control Dams are in close proximity to both
Aboriginal and European heritage places. The significance of these sites is high and
the archaeological sensitivity to disturbance is high.
A desk top study of the locality of the proposed two flood control dams has revealed
that there are three (3) sites of aboriginal significance and 14 listed European
heritage places.
The three known Aboriginal heritage sites include an engraving site and two scar
trees.
Further to this, given that that locality of the proposed flood control dams is within the
claimed traditional lands of the Kaurna people and the hills face zone would have
provided significance shelter and resources for Aboriginal people there is a medium
to high potential for currently unknown buried and/or unrecorded Aboriginal sites to
be in the vicinity of the proposed development
Any Aboriginal sites, whether recorded or not recorded, within the Brown Hill Creek
Flood Control Dams area are protected under State and Commonwealth legislation
from activities that may damage or disturb the sites.
The fifteen European Heritage sites are listed on local government, State and
Commonwealth heritage lists. These sites include the former EW&S water tank and
water infrastructure (includes tank, brick well, stone valve well, dam wall, settling
pond, water fountain and associated pipework), Springfield House, Carrick Hill
Museum, Former Wheat Grainger Mines, Manure Pits, Birralee House, Former Holy
Innocents Church, St Johns School. Belair Railway Station and Signal Box, Sheoak
Riding School, Railway Cottages, and three un-named dwellings.
European heritage sites do not have the same blanket protection as Aboriginal
heritage sites however there are provisions under both the Heritage Places Act 1993
and the Development Act 1993 for European heritage sites listed on State and Local
heritage lists.
Recommendation
It is recommended that additional investigation and research into the presence
of both Aboriginal and European heritage sites be undertaken.
Environmental Implication
Flora
Preliminary surveys and database searched have indicated that the Pink-lipped
Spider-Orchid (Caladenia behri) and the Stiff White Spider-Orchid (Caldenia rigida)
4
are likely to grow in the area. Both these species of orchid are listed as endangered
pursuant to the Environment Protection Biodiversity Conservation Act 1999
An area of vegetation will need to be cleared for the construction of flood control
dams and to provide access to the site for construction equipment and vehicles.
Recommendation
It is recommended that both a detailed flora survey and ecological assessment
be undertaken in the location of the proposed flood control dams
Fauna
Preliminary surveys and database searched have indicated that the Chest-nut
Rumped Heath wren (Calamanthus pyrrhopygius parken) and the Southern Brown
Bandicoot (Isoden obesulus obesulus) may also habitate the area. Both these
species are listed as endangered pursuant to the Environment Protection Biodiversity
Conservation Act 1999.
Recommendation
It is recommended that both a detailed fauna survey and ecological
assessment be undertaken in the location of the proposed flood control dams
Water Quality
The existing waster quality with the Brown Hill Creek is of a good standard based on
historical data sourced from the Adelaide and Mount Lofty Ranges Natural Resource
Management (NRM) Board.
The construction of the flood control dams may possibly have an impact on water
quality by way of:
Degradation of water quality in the Brown Hill Creek downstream of the flood
control dams due to flow restrictions
Degradation of water quality in Brown Hill Creek upstream and downstream of
the flood control dams in the vicinity of road relocation works
Recommendation
It is recommended that a suitable erosion and sediment control management
plan be devised and implemented to minimise the risk to water quality during
and post construction of the flood control dams.
5
Additional Investigations
The documents currently in the possession of Council are concept designs only.
Limited construction details are provided in the reports. A formal development
application should provide the following details at a minimum:
A site plan drawn to scale, showing the proposed dams on the site, including;
the location of the entire dam including spillways (measured in metres) and
the distance of the dam to adjacent lot boundaries and buildings,
any storage area of materials including earth associated with the dam
construction,
the depth of the dams ( measured from the existing ground level before the
construction and the ground level after the construction);
the reason for the landfill. Is the completed landfill area intended to be used
for a particular purpose?
the staging (if any) of the landfill, including the commencement, duration
and completion of each stage.
the composition (eg. sand, clay, building rubble) and the source of the
landfill material/s;
6
the hours of operation of the landfill activities;
the public roads (the route) which vehicles will use to access the landfill
area/property;
the method of compaction of the land fill, - the machinery uses, hours of
operation, staging;
the method or type of revegetation of the landfill area. Detail staging, plant
species, growth rates, irrigation of vegetation;
the effect on the site and on adjoining sites of any changes to surface
drainage and changes to any water features on site.
9. A hydrological report may be required that demonstrates that the proposed dams
do not impede natural stream flow, nor the recharge of groundwater.
Planning Implications
The subject land is located in the Hills Face Zone within the City of Mitcham.
Filling where the height of filling of land exceeds 1 metre above natural ground
level except for underground homes, underground tanks, and cellars.
It is envisaged that the proposed flood control dams would involve excavation and/or
filling of land in excess of the specifications detailed above.
At this point is time there are three possible avenues that development assessment
may be undertaken.
7
DAC as the Planning Authority
Development Assessment Commission (DAC) is the relevant planing assessment
authority in relation to some development in the Hills face Zone, including:
The Development Regulations will require that the DAC provide the City of Mitcham
with an opportunity to provide written comment on the proposal. A six week period is
specified for comments to be provided by the Council to the Commission.
Pursuant to Section 49, the State Agency would lodge the application with the DAC
for planning assessment if
8
Other facilities that have traditionally been provided by the State (but not
necessarily only by the State) as community or public facilities
The City of Mitcham would be provided with the opportunity to provide a report to the
DAC regarding the proposal. The City of Mitcham has up to two months to submit the
report to the DAC.
It is unclear at this stage as to whether or not a State Agency will be undertaking the
development.
Pursuant to Section 46 of the Development Act 1993 the Minster may declare the
proposed development to be a project of major environmental, social or economic
importance by virtue of the likely presence and potential impact on endangered
species.
The Major Development Assessment Process is likely to be the most favourable and
appropriate assessment process for the following reason:
It provides greater opportunity for public input and comment. However it must
be noted that it does not provide members from the public with an appeal right
against any approved decision.
It must be noted that only the Minister can declare a development to be a Major
Project.
The application will be referred to the DAC for setting of assessment level and
guidelines and the DAC will consider the application and identify the key social,
environmental and economic issues relevant to the assessment of the proposed
development. The DAC may consult with relevant State agencies as part of this
process.
The three possible levels of detailed assessment may be required by the DAC are:
9
An Environmental Impact Statement (EIS) - required for the most
complex proposals, where there is a wide range of issues to be
investigated in depth;
A Public Environmental Report (PER) - sometimes referred to as a
'targeted EIS', required where the issues surrounding the proposal
need investigation in depth but are narrower in scope and relatively
well known;
A Development Report (DR) - the least complex level of assessment,
which relies principally on existing information.
The DAC will publicly issue a Guidelines document to the proponent as to what level
of assessment is required and what issues that assessment should address.
The Guidelines will be published on both the DAC website (www.dac.sa.gov.au) and
the Department of Planning and Local Government website www.planning.sa.gov.au)
and also be made available in hard copy and on CD-Rom.
The proponent will prepare an EIS, PER or DR, as directed by the Development
Assessment Commission. The length of time it takes a proponent to prepare the
assessment document is not set, and depends upon the level of assessment, the
complexity of the proposal and the sensitivity of the site. A DR generally takes the
shortest time, while an EIS takes the longest.
Once it is complete, the EIS, PER or DR is released for public and agency comment
for either three (DR) or six weeks (EIS, PER) and made available at the relevant local
council and on the Department of Planning and Local Government website. A
mandatory public meeting is held early in the exhibition period for an EIS or PER.
In Summary
There are a number of environmental and heritage issues that require further
investigations. The following recommendations are put forward to address these
issues.
Recommendation 1
It is highly recommended that additional investigation and research into the
presence of both Aboriginal and European heritage sites be undertaken.
Recommendation 2
It is recommended that both a flora survey and an ecological assessment be
undertaken undertaken in the location of the proposed flood control dams
Recommendation 3
It is recommended that both a detailed fauna survey and ecological
assessment be undertaken in the location of the proposed flood control dams.
Recommendation
10
It is recommended that a suitable erosion and sediment control management
plan be devised and implemented to minimise the risk to water quality during
and post construction of the flood control dams.
11
Appendix A
Brown Hill Creek Stormwater Project. - Preliminary Assessment of Flood Detention
Basins on Brown Hill Creek. Report on Stage 1 GHD October 2008
Brown Hill and Keswick Creeks Flood Mitigation study. Flood Management Plan.
Hydro- Electric Corporation15th December 2006
Flood Mitigation Study for Brown Hill and Keswick Creeks. Hydro Electric
Corporation. 5th August 2005
Urban Flood Risk Reduction and Stormwater Harvest. Technical Group. Brown Hill
Creek Stormwater Project. 14 October 2008
Brown Hill Creek and Keswick Creeks Flood Mitigation. A Review of the Justification
for the Construction of two Large Detention Dams in the Upper Reaches of Brown
Hill Creek. Peter Collins, John Wilson. July 2009.
Reducing the Flood Risk in the Brown Hill and Keswick Creek Catchments. Technical
Summary Report (Undated)
12