Вы находитесь на странице: 1из 26

ABSTRACT OF COST FOR THE CONSTRUCTION OF CEMENT CONCRETE ROAD WIDENING AND RCC

DIVIDER OF GANDHI ROAD FROM GANDHI JI STATUE ,PANI KI TANKI TO MAU ROAD MEHGAON (UNDE
URBAN INFRASTRUCTURE DEVELOPMENT SCHEME PHASE 2nd
RATES - BASED ON SCHEDULE OF RATES FOR GOVERNMENT OF MADHYA PRADESH URBAN
ADMINISTRATION AND DEVELOPMENT DEPARTMENT IN FORCE FROM 10th May 2012

S.No Particulars of Item item code Quantity Units

1 Excavation for roadway in soil including loading in 3.1/21 1750 CUM


truck for carrying of cut earth to embankment site
with all lifts and lead upto1000 meters and as per
elevant clauses of section-300.

2 Construction of granular sub-base by providing 4.1/30 525 CUM


coarse graded material, spreading in uniform layers
with on prepared surface, mixing by mix in place
method at OMC, and compacting with vibratory
roller to achieve the desired density, complete in all
respect and as per relevant clauses of section-400.
for grading-III Material

3 Providing and laying Cement Concrete grade M-10 6.10/61 350 CUM
Nominal mix with 20 mm graded crushed stone
aggregate, laid with a fixed form / slip form paver
with spreading the concrete by shovels mixing shall
be in mechanical mixer ,compacting by use of pin
plate and screed vibrators including formwork by
strong steel girders fixed by spikes.
4 Construction of dowel jointed, plain cement 6.3/60 875 CUM
concrete pavement in M-40 grade concrete over a
prepared sub base with 43 or higher grade cement,
maximum size of coarse aggregate not exceeding
25 mm, mixed in a batching and mixing plant as per
approved mix design, transported to site, laid with
a fixed form or slip form paver with electronic
sensor, spread, compacted and finished in a
continuous operation including provision of
contraction, expansion, construction and
longitudinal joints, joint filler, separation membrane,
seal ant primer ,joint sealant, de bonding strip,
placing of dowel bar and tie rod, admixtures as
approved, curing compound, finishing to lines and
grades as per approved drawings as per
IRC152002 and as per relevant clauses of section
602 of MORTH specifications complete but
excluding cost of steel in dowel bar & tie rod etc..

5 Mild Steel dowel bars 25 mm dia in 1 metre 25 mm 6.12.1/62 616 KG


dia bar weight is 3.85 Kg

6 Providing and laying reinforced cement concrete 6.9.1/ 700 RM


pipe 300 mm dia NP-4 for service ducts. 61

7 Reinforcement for R.C.C. work including 5.20.3/46 4230.96 KG


straightening, cutting, bending, placing In position
and binding including cost of binding wire upto floor
two level including all wastage etc. complete. Cold
twisted bars (0.50 % of R.C.C quantity

8 Centering and shuttering including strutting, 20.1.2 2800 SQM


propping etc. and removal of form for : Walls /2.9
(anythickness) including attached pilasters,
butteresses, plinth and string courses etc

9 Reinforced cement concrete work in walls (any 5.2.1/46 204.75 CUM


thickness), including attached pilasters, buttresses,
plinth and string courses, fillets, columns, pillars,
piers, abutments, posts and struts etc. upto floor
two level excluding cost of centering, shuttering,
finishing and reinforcement Cement concrete grade
M-20 (Nominal Mix) with 20 mm maximum size of
stone aggregate.
10 Filling by available excavated earth (excluding rock) 2.25/19 252 CUM
in trenches, plinth, sides of foundations etc. in
layers not exceeding 20 cm in depth, consolidating
each deposited layer by ramming and watering,
lead upto 50 m and lift up to1.5 m.

total
Grand Total Rs. 8539142.14
OAD WIDENING AND RCC ROAD
U ROAD MEHGAON (UNDER CM
PHASE 2nd
ADHYA PRADESH URBAN
May 2012

Rate Amount
Rs.
98 171500

600 315000

3046 1066100
4792 4193000

47.5 29260

1230 861000

59 249626.64

216 604800

5050 1033987.5
59 14868

total 8539142.14
d Total Rs. 8539142.14
DETAILS OF MEASUREMENTS FOR THE CONSTRUCTION OF CEMENT CONCRETE ROAD WIDENING AND
RCC ROAD DIVIDER OF GANDHI ROAD FROM GANDHI JI STATUE ,PANI KI TANKI TO MAU ROAD MEHGAO
(UNDER CM URBAN INFRASTRUCTURE DEVELOPMENT SCHEME PHASE 2nd
RATES - BASED ON SCHEDULE OF RATES FOR GOVERNMENT OF MADHYA PRADESH URBAN
ADMINISTRATION AND DEVELOPMENT DEPARTMENT IN FORCE FROM 10th May 2012

S.No Particulars of Item item code No L B H

1 Excavation for roadway in soil including loading 3.1/21 2 700 2.5 0.5
in truck for carrying of cut earth to embankment
site with all lifts and lead upto1000 meters and
as per elevant clauses of section-300.

2 Construction of granular sub-base by providing 4.1/30 2 700 2.5 0.15


coarse graded material, spreading in uniform
layers with on prepared surface, mixing by mix
in place method at OMC, and compacting with
vibratory roller to achieve the desired density,
complete in all respect and as per relevant
clauses of section-400. for grading-III Material.

3 Providing and laying Cement Concrete grade 6.10/61 2 700 2.5 0.1
M-10 Nominal mix with 20 mm graded crushed
stone aggregate, laid with a fixed form / slip
form paver with spreading the concrete by
shovels mixing shall be in mechanical mixer
,compacting by use of pin plate and screed
vibrators including formwork by strong steel
girders fixed by spikes.
4 Construction of dowel jointed, plain cement 6.3/60 2 700 2.5 0.25
concrete pavement in M-40 grade concrete
over a prepared sub base with 43 or higher
grade cement, maximum size of coarse
aggregate not exceeding 25 mm, mixed in a
batching and mixing plant as per approved mix
design, transported to site, laid with a fixed
form or slip form paver with electronic sensor,
spread, compacted and finished in a
continuous operation including provision of
contraction, expansion, construction and
longitudinal joints, joint filler, separation
membrane, seal ant primer ,joint sealant, de
bonding strip, placing of dowel bar and tie rod,
admixtures as approved, curing compound,
finishing to lines and grades as per approved
drawings as per IRC152002 and as per
relevant clauses of section 602 of MORTH
specifications complete but excluding cost of
steel in dowel bar & tie rod etc..

5 Mild Steel dowel bars 25 mm dia in 1 metre 25 6.12.1/62 32 X 5No X 2 x 0.50 X 160 X 3.05 = 616.00
mm dia bar weight is 3.85 Kg

6 Providing and laying reinforced cement 6.9.1/ 1 700


concrete pipe 300 mm dia NP-4 for service 61
ducts.
7 Reinforcement for R.C.C. work including 5.20.3/46 10 mm
straightening, cutting, bending, placing In 2x2666 No. 0.80= 4265.60x0.60=2559.36
position and binding including cost of binding
wire upto floor two level including all wastage 8 mm
etc. complete. Cold twisted bars (0.50 % of 2x3 No.x700=4200x0.398 = 1671.6
R.C.C quantity Total =4230.96 Kg

8 Centering and shuttering including strutting, 20.1.2 4 700


propping etc. and removal of form for : Walls /2.9
(anythickness) including attached pilasters,
butteresses, plinth and string courses etc
9 Reinforced cement concrete work in walls (any 5.2.1/46 2 700 0.2 0.6
thickness), including attached pilasters,
buttresses,plinth and string courses, fillets,
columns, pillars, piers, abutments, posts and
struts etc. upto floor two level excluding cost of
centering, shuttering, finishing and
reinforcement Cement concrete grade M-20
(Nominal Mix) with 20 mm maximum size of
stone aggregate.

2 700 (0.2+0.15)/2 0.15

10 Filling by available excavated earth (excluding 2.25/19 1 700 0.6 0.6


rock) in trenches, plinth, sides of foundations
etc. in layers not exceeding 20 cm in depth,
consolidating each deposited layer by ramming
and watering, lead upto 50 m and lift up to1.5
m.
CRETE ROAD WIDENING AND
ANKI TO MAU ROAD MEHGAON
ME PHASE 2nd
DHYA PRADESH URBAN
May 2012

Quantity Units

1750 CUM

525 CUM

350 CUM
875 CUM

X 160 X 3.05 = 616.00 Kg

700 RM

KG
5.60x0.60=2559.36

398 = 1671.6

2800 SQM
168 CUM

36.75

204.75
252 CUM
ESTIMATE FOR THE WORK OF CONSTRUCTION OF U SHAPE DRAIN AT POHA BY PASS NARBAR, SHIVPU
RATES - BASED ON SCHEDULE OF RATES FOR GOVERNMENT OF MADHYA PRADESH URBAN ADMINIST
AND DEVELOPMENT DEPARTMENT IN FORCE FROM 10th May 2012

S.No Particulars of Item Item Code Quantity Units

1 Earthwork in excavation by mechanical means (Hydraulic excavator ) / 3.16


manual means over areas(exceeding 30 cm in depth .1.5 m in width Vol-3
as well as 10 sqm on plan ) including disposal of excavated earth ,
lead upto 50 m and lift upto 1.5m ,disposed earth to be levelled and
neatly dressed All kinds of soil add extra 4km lead

1207.50 CUM
2 Providing and laying in position cement concrete of specified grade 4.1.6
excluding the cost of centering and shuttering All work up to plinth Vol-2
level. Cement concrete grade M 10 (Nominal Mix) with 40 mm
maximum size of stone aggregate

Base of "U" shape Drain 105 CUM


3 Centering and shuttering including strutting , propping etc .and 20.1.1
removal of form for : Walls ( any thickness ) including attached Vol-2
pilasters , butteresses , plinth and string courses etc

252 SQM
4 Providing and laying in position specified grade of cement concrete 5.1.1
excluding the cost of centering , shuttering ,finishing and Vol-2
reinforcement - All work up to plinth level : Cement concrete grade M-
20 (Nominal Mix) with 20 mm maximum size of stone aggregate

346.5 CUM
5 Reinforcement for R.C.C. work including straightening, cutting, 5.20.3 19040.18 k.g
bending, placing inposition and binding including cost of binding wire Vol-2
upto floor two level including all wastage etc. complete.
Cold twisted bars
0.7x 346.5 x 78.5= 19040.18 K.G

TOTAL Rs
SAY Rs 32.86 L
SS NARBAR, SHIVPURI (M.P.)
SH URBAN ADMINISTRATION
y 2012

Rate Amount
Rs.

99 119542.5

3528 370440.0

138 34776

4728 1638252
59 1123370.62

AL Rs 3286381.1
AY Rs 32.86 Lacs
MEASUREMENTS FOR THE WORK OF CONSTRUCTION OF U SHAPE DRAIN AT POHA BY PASS NARBA
SHIVPURI (M.P.)
RATES - BASED ON SCHEDULE OF RATES FOR GOVERNMENT OF MADHYA PRADESH URBAN ADMINISTR
AND DEVELOPMENT DEPARTMENT IN FORCE FROM 10th May 2012

S.No Particulars of Item Item Code No L B

1 Earthwork in excavation by mechanical means (Hydraulic 2.6.1


excavator ) / manual means over areas(exceeding 30 cm in Vol-2
depth .1.5 m in width as well as 10 sqm on plan ) including
disposal of excavated earth , lead upto 50 m and lift upto
1.5m ,disposed earth to be levelled and neatly dressed All
kinds of soil add extra 4km lead

1 700 1.5
2 Providing and laying in position cement concrete of 4.1.6
specified grade excluding the cost of centering and Vol-2
shuttering All work up to plinth level. Cement concrete
grade M 10 (Nominal Mix) with 40 mm maximum size of
stone aggregate

Base of "U" shape Drain 1 700 1.5


3 Centering and shuttering including strutting , propping 20.1.1
etc .and removal of form for : Walls ( any thickness ) Vol-2
including attached pilasters , butteresses , plinth and string
courses etc

U shape Drain (wall) (2x2)=4 4 700

4 Providing and laying in position specified grade of cement 5.1.1


concrete excluding the cost of centering , shuttering Vol-2
,finishing and reinforcement - All work up to plinth level :
Cement concrete grade M-20 (Nominal Mix) with 20 mm
maximum size of stone aggregate

Bottom 1 700 1.5


Wall 2 700 0.15

5 Reinforcement for R.C.C. work including straightening, 5.20.3


cutting, bending, placing inposition and binding including Vol-2
cost of binding wire upto floor two level including all
wastage etc. complete.
Cold twisted bars
0.7x 346.5 x 78.5= 19040.18 K.G
T POHA BY PASS NARBAR,

ESH URBAN ADMINISTRATION


ay 2012

H Quantity

1.15 1207.5

0.1 105

0.9 2520
2520

0.15 157.5
0.9 189
346.5
19040.18
ABSTRACT ESTIMATE FOR THE WORK OF CONSTRUCTION OF ELECTICAL WORK AT POHA BY PASS RO
RATES - BASED ON SCHEDULE OF RATES FOR GOVERNMENT OF MADHYA PRADESH UADD IN FORC
FROM 10th May 2012

S.No Particulars of Item Item Code Quantity Units

1 Providing and erecting 9mtrs. High hot galvanized 16.4/94 45 no


octagonal poles with bottom of 155mm A/F, top 70mm A/F Vol-4
made from 3mm thick HT plate & 260x260x16mm base
plate with 1500mm long decorative sword type double
arm bracket complte erected in an approved manner on
provided foundation. Suitable size & type of foundation
bolts. 4 nos. bolts type M20x750mm 'J' type foundation
bolts (EN8 grade)

2 Designing & casting with M-20 cement concrete 16.4/94 45 no


foundation suitable for 9 mtrs. Octagonal poles Vol-4
considering the safe soil bearing capacity at site as 10
T/sqm at 2 mtrs. Depth including excavation, foundation
nut bolts in an approved manner.

3 H.D. Sodium vapour fitting consisting of matallic cast 242/110 45 no


aluminium alloy housing highly polished anodised
aluminium reflector clear acrylic cover, gasket and
equipped with accessories; such as ballast, condensor,
ignitor, skirted ceramic lamp holder (without lamp) 70 watt

4 Earthing with G.I. Earth pipe 4.5 meter long and 40 mm 11.1/ 2 no
dia with masonary enclosure in cement mortor, cover 64
plate having locking arrangment on the top etc. (but
without charcoal or coke and salt) complete as required.

5 Add Extra for using salt and charcoal / coke for pipe earth 11.2.1/ 2 no
electrode as required including excavation & refilling. 64
Excavation 2.5 cum by manual labour

6 Earthing with Copper Earth plate 600 mm X 600 mm X 3 11.4/64 2 no


mm thick including accessories and providing masonary
encloser in cement mortor, cover plate having locking
arrangment on the top and G.I. watering pipe 20 mm dia
2.7 meter long etc. (but without charcoal or coke and salt)
complete as required.
7 Add Extra for using salt and charcoal / coke for G.I. Plate 11.5/64 2 no
or Copper plate earth electrode as required including
excavation & refilling.

8 Laying of one number PVC insluated and PVC sheated 14.10.1 700 m
power cable of 1.1 kV grade of size not exceeding 25 / 85
Sq.mm direct in ground including excavation, sand
cushioining, protective covering and refilling the pit etc. as
required.

9 Planting of Trees and their Maintenance for one Year 11.2/82 35 no


( Planting of trees by the road side (Avenue trees) in 0.60
m dia holes, 1 m deep dug in the ground, mixing the soil
with decayed farm yard / sludge mannure,planting the
saplings, back filling the trench, watering, fixing the tree
guard and maintaining the plants for one year)

10 Tree Guard with MS Angle Iron and Steel Wire (Providing 11.5/82 35 no
and fixing tree guard 0.60 square meter, 2.00 meter high
fabricated with MS angle iron 30x30x3 mm, MS iron 25x3
mm and steel wire 3mm dia welded and fabricated as per
design in two halves bolted together)

11 Labour rate for fabrication and fixing of tree guard as per 11.5.1 35
Item No.- 11.5 / 82

TOTAL Rs
SAY Rs 19.9
ORK AT POHA BY PASS ROAD
PRADESH UADD IN FORCE

Rate Amount
Rs.
24148 1086660

13500 607500

242 10890

1893 3786

663 1326

7618 15236
520 1040

247 172900

488 17080

2179 76265

171 5985

Rs 1998668
SAY Rs 19.9 Lacs
MEASURMENT FOR THE WORK OF CONSTRUCTION OF ELECTRICAL WORK AT POHA BY PASS RO
NARWAR

S.No Particulars of Item Item Code No L B

1 Providing and erecting 9mtrs. High hot galvanized 16.4/94 45


octagonal poles with bottom of 155mm A/F, top 70mm A/F
made from 3mm thick HT plate & 260x260x16mm base
plate with 1500mm long decorative sword type double arm
bracket complte erected in an approved manner on
provided foundation. Suitable size & type of foundation
bolts. 4 nos. bolts type M20x750mm 'J' type foundation
bolts (EN8 grade)

2 Designing & casting with M-20 cement concrete foundation 45


suitable for 9 mtrs. Octagonal poles considering the safe
soil bearing capacity at site as 10 T/sqm at 2 mtrs. Depth
including excavation, foundation nut bolts in an approved
manner.

3 H.D. Sodium vapour fitting consisting of matallic cast 242/110 45


aluminium alloy housing highly polished anodised
aluminium reflector clear acrylic cover, gasket and equipped
with accessories; such as ballast, condensor, ignitor, skirted
ceramic lamp holder (without lamp) 70 watt

4 Earthing with G.I. Earth pipe 4.5 meter long and 40 mm dia 11.1/ 2
with masonary enclosure in cement mortor, cover plate 64
having locking arrangment on the top etc. (but without
charcoal or coke and salt) complete as required.

5 Add Extra for using salt and charcoal / coke for pipe earth 11.2.1/ 2
electrode as required including excavation & refilling. 64
Excavation 2.5 cum by manual labour

6 Earthing with Copper Earth plate 600 mm X 600 mm X 3 11.4/64 2


mm thick including accessories and providing masonary
encloser in cement mortor, cover plate having locking
arrangment on the top and G.I. watering pipe 20 mm dia
2.7 meter long etc. (but without charcoal or coke and salt)
complete as required.

7 Add Extra for using salt and charcoal / coke for G.I. Plate or 11.5/64 2
Copper plate earth electrode as required including
excavation & refilling.

8 Laying of one number PVC insluated and PVC sheated 11.10.1 700
power cable of 1.1 kV grade of size not exceeding 25 / 85
Sq.mm direct in ground including excavation, sand
cushioining, protective covering and refilling the pit etc. as
required.
9 Planting of Trees and their Maintenance for one Year 11.2/82 35
( Planting of trees by the road side (Avenue trees) in 0.60 m
dia holes, 1 m deep dug in the ground, mixing the soil with
decayed farm yard / sludge mannure,planting the saplings,
back filling the trench, watering, fixing the tree guard and
maintaining the plants for one year)

10 Tree Guard with MS Angle Iron and Steel Wire (Providing 11.5/82 35
and fixing tree guard 0.60 square meter, 2.00 meter high
fabricated with MS angle iron 30x30x3 mm, MS iron 25x3
mm and steel wire 3mm dia welded and fabricated as per
design in two halves bolted together)

11 Labour rate for fabrication and fixing of tree guard as per 11.5.1 35
Item No.- 11.5 / 82
RK AT POHA BY PASS ROAD

H Quantity Unit

45 each

45 each

45 each

2 each

2 each

2 each

2 each

700 each
35 each

35 each

20 each
ESTIMATE FOR THE WORK OF CONSTRUCTION OF CC ROAD AT POHA BY PASS NAR
SHIVPURI (M.P.)
RATES - BASED ON SCHEDULE OF RATES FOR GOVERNMENT OF MADHYA PRADESH U
ADMINISTRATION AND DEVELOPMENT DEPARTMENT IN FORCE FROM 10th May 2012

S.NO.
1 ROAD
2 DRAIN
3 ELECTRICAL

TOTAL
CTION OF CC ROAD AT POHA BY PASS NARBAR,
VPURI (M.P.)
FOR GOVERNMENT OF MADHYA PRADESH URBAN
PARTMENT IN FORCE FROM 10th May 2012

8539142.14
3286381.12
1998668

13824191.26

Вам также может понравиться