DIVIDER OF GANDHI ROAD FROM GANDHI JI STATUE ,PANI KI TANKI TO MAU ROAD MEHGAON (UNDE
URBAN INFRASTRUCTURE DEVELOPMENT SCHEME PHASE 2nd
RATES - BASED ON SCHEDULE OF RATES FOR GOVERNMENT OF MADHYA PRADESH URBAN
ADMINISTRATION AND DEVELOPMENT DEPARTMENT IN FORCE FROM 10th May 2012
3 Providing and laying Cement Concrete grade M-10 6.10/61 350 CUM
Nominal mix with 20 mm graded crushed stone
aggregate, laid with a fixed form / slip form paver
with spreading the concrete by shovels mixing shall
be in mechanical mixer ,compacting by use of pin
plate and screed vibrators including formwork by
strong steel girders fixed by spikes.
4 Construction of dowel jointed, plain cement 6.3/60 875 CUM
concrete pavement in M-40 grade concrete over a
prepared sub base with 43 or higher grade cement,
maximum size of coarse aggregate not exceeding
25 mm, mixed in a batching and mixing plant as per
approved mix design, transported to site, laid with
a fixed form or slip form paver with electronic
sensor, spread, compacted and finished in a
continuous operation including provision of
contraction, expansion, construction and
longitudinal joints, joint filler, separation membrane,
seal ant primer ,joint sealant, de bonding strip,
placing of dowel bar and tie rod, admixtures as
approved, curing compound, finishing to lines and
grades as per approved drawings as per
IRC152002 and as per relevant clauses of section
602 of MORTH specifications complete but
excluding cost of steel in dowel bar & tie rod etc..
total
Grand Total Rs. 8539142.14
OAD WIDENING AND RCC ROAD
U ROAD MEHGAON (UNDER CM
PHASE 2nd
ADHYA PRADESH URBAN
May 2012
Rate Amount
Rs.
98 171500
600 315000
3046 1066100
4792 4193000
47.5 29260
1230 861000
59 249626.64
216 604800
5050 1033987.5
59 14868
total 8539142.14
d Total Rs. 8539142.14
DETAILS OF MEASUREMENTS FOR THE CONSTRUCTION OF CEMENT CONCRETE ROAD WIDENING AND
RCC ROAD DIVIDER OF GANDHI ROAD FROM GANDHI JI STATUE ,PANI KI TANKI TO MAU ROAD MEHGAO
(UNDER CM URBAN INFRASTRUCTURE DEVELOPMENT SCHEME PHASE 2nd
RATES - BASED ON SCHEDULE OF RATES FOR GOVERNMENT OF MADHYA PRADESH URBAN
ADMINISTRATION AND DEVELOPMENT DEPARTMENT IN FORCE FROM 10th May 2012
1 Excavation for roadway in soil including loading 3.1/21 2 700 2.5 0.5
in truck for carrying of cut earth to embankment
site with all lifts and lead upto1000 meters and
as per elevant clauses of section-300.
3 Providing and laying Cement Concrete grade 6.10/61 2 700 2.5 0.1
M-10 Nominal mix with 20 mm graded crushed
stone aggregate, laid with a fixed form / slip
form paver with spreading the concrete by
shovels mixing shall be in mechanical mixer
,compacting by use of pin plate and screed
vibrators including formwork by strong steel
girders fixed by spikes.
4 Construction of dowel jointed, plain cement 6.3/60 2 700 2.5 0.25
concrete pavement in M-40 grade concrete
over a prepared sub base with 43 or higher
grade cement, maximum size of coarse
aggregate not exceeding 25 mm, mixed in a
batching and mixing plant as per approved mix
design, transported to site, laid with a fixed
form or slip form paver with electronic sensor,
spread, compacted and finished in a
continuous operation including provision of
contraction, expansion, construction and
longitudinal joints, joint filler, separation
membrane, seal ant primer ,joint sealant, de
bonding strip, placing of dowel bar and tie rod,
admixtures as approved, curing compound,
finishing to lines and grades as per approved
drawings as per IRC152002 and as per
relevant clauses of section 602 of MORTH
specifications complete but excluding cost of
steel in dowel bar & tie rod etc..
5 Mild Steel dowel bars 25 mm dia in 1 metre 25 6.12.1/62 32 X 5No X 2 x 0.50 X 160 X 3.05 = 616.00
mm dia bar weight is 3.85 Kg
Quantity Units
1750 CUM
525 CUM
350 CUM
875 CUM
700 RM
KG
5.60x0.60=2559.36
398 = 1671.6
2800 SQM
168 CUM
36.75
204.75
252 CUM
ESTIMATE FOR THE WORK OF CONSTRUCTION OF U SHAPE DRAIN AT POHA BY PASS NARBAR, SHIVPU
RATES - BASED ON SCHEDULE OF RATES FOR GOVERNMENT OF MADHYA PRADESH URBAN ADMINIST
AND DEVELOPMENT DEPARTMENT IN FORCE FROM 10th May 2012
1207.50 CUM
2 Providing and laying in position cement concrete of specified grade 4.1.6
excluding the cost of centering and shuttering All work up to plinth Vol-2
level. Cement concrete grade M 10 (Nominal Mix) with 40 mm
maximum size of stone aggregate
252 SQM
4 Providing and laying in position specified grade of cement concrete 5.1.1
excluding the cost of centering , shuttering ,finishing and Vol-2
reinforcement - All work up to plinth level : Cement concrete grade M-
20 (Nominal Mix) with 20 mm maximum size of stone aggregate
346.5 CUM
5 Reinforcement for R.C.C. work including straightening, cutting, 5.20.3 19040.18 k.g
bending, placing inposition and binding including cost of binding wire Vol-2
upto floor two level including all wastage etc. complete.
Cold twisted bars
0.7x 346.5 x 78.5= 19040.18 K.G
TOTAL Rs
SAY Rs 32.86 L
SS NARBAR, SHIVPURI (M.P.)
SH URBAN ADMINISTRATION
y 2012
Rate Amount
Rs.
99 119542.5
3528 370440.0
138 34776
4728 1638252
59 1123370.62
AL Rs 3286381.1
AY Rs 32.86 Lacs
MEASUREMENTS FOR THE WORK OF CONSTRUCTION OF U SHAPE DRAIN AT POHA BY PASS NARBA
SHIVPURI (M.P.)
RATES - BASED ON SCHEDULE OF RATES FOR GOVERNMENT OF MADHYA PRADESH URBAN ADMINISTR
AND DEVELOPMENT DEPARTMENT IN FORCE FROM 10th May 2012
1 700 1.5
2 Providing and laying in position cement concrete of 4.1.6
specified grade excluding the cost of centering and Vol-2
shuttering All work up to plinth level. Cement concrete
grade M 10 (Nominal Mix) with 40 mm maximum size of
stone aggregate
H Quantity
1.15 1207.5
0.1 105
0.9 2520
2520
0.15 157.5
0.9 189
346.5
19040.18
ABSTRACT ESTIMATE FOR THE WORK OF CONSTRUCTION OF ELECTICAL WORK AT POHA BY PASS RO
RATES - BASED ON SCHEDULE OF RATES FOR GOVERNMENT OF MADHYA PRADESH UADD IN FORC
FROM 10th May 2012
4 Earthing with G.I. Earth pipe 4.5 meter long and 40 mm 11.1/ 2 no
dia with masonary enclosure in cement mortor, cover 64
plate having locking arrangment on the top etc. (but
without charcoal or coke and salt) complete as required.
5 Add Extra for using salt and charcoal / coke for pipe earth 11.2.1/ 2 no
electrode as required including excavation & refilling. 64
Excavation 2.5 cum by manual labour
8 Laying of one number PVC insluated and PVC sheated 14.10.1 700 m
power cable of 1.1 kV grade of size not exceeding 25 / 85
Sq.mm direct in ground including excavation, sand
cushioining, protective covering and refilling the pit etc. as
required.
10 Tree Guard with MS Angle Iron and Steel Wire (Providing 11.5/82 35 no
and fixing tree guard 0.60 square meter, 2.00 meter high
fabricated with MS angle iron 30x30x3 mm, MS iron 25x3
mm and steel wire 3mm dia welded and fabricated as per
design in two halves bolted together)
11 Labour rate for fabrication and fixing of tree guard as per 11.5.1 35
Item No.- 11.5 / 82
TOTAL Rs
SAY Rs 19.9
ORK AT POHA BY PASS ROAD
PRADESH UADD IN FORCE
Rate Amount
Rs.
24148 1086660
13500 607500
242 10890
1893 3786
663 1326
7618 15236
520 1040
247 172900
488 17080
2179 76265
171 5985
Rs 1998668
SAY Rs 19.9 Lacs
MEASURMENT FOR THE WORK OF CONSTRUCTION OF ELECTRICAL WORK AT POHA BY PASS RO
NARWAR
4 Earthing with G.I. Earth pipe 4.5 meter long and 40 mm dia 11.1/ 2
with masonary enclosure in cement mortor, cover plate 64
having locking arrangment on the top etc. (but without
charcoal or coke and salt) complete as required.
5 Add Extra for using salt and charcoal / coke for pipe earth 11.2.1/ 2
electrode as required including excavation & refilling. 64
Excavation 2.5 cum by manual labour
7 Add Extra for using salt and charcoal / coke for G.I. Plate or 11.5/64 2
Copper plate earth electrode as required including
excavation & refilling.
8 Laying of one number PVC insluated and PVC sheated 11.10.1 700
power cable of 1.1 kV grade of size not exceeding 25 / 85
Sq.mm direct in ground including excavation, sand
cushioining, protective covering and refilling the pit etc. as
required.
9 Planting of Trees and their Maintenance for one Year 11.2/82 35
( Planting of trees by the road side (Avenue trees) in 0.60 m
dia holes, 1 m deep dug in the ground, mixing the soil with
decayed farm yard / sludge mannure,planting the saplings,
back filling the trench, watering, fixing the tree guard and
maintaining the plants for one year)
10 Tree Guard with MS Angle Iron and Steel Wire (Providing 11.5/82 35
and fixing tree guard 0.60 square meter, 2.00 meter high
fabricated with MS angle iron 30x30x3 mm, MS iron 25x3
mm and steel wire 3mm dia welded and fabricated as per
design in two halves bolted together)
11 Labour rate for fabrication and fixing of tree guard as per 11.5.1 35
Item No.- 11.5 / 82
RK AT POHA BY PASS ROAD
H Quantity Unit
45 each
45 each
45 each
2 each
2 each
2 each
2 each
700 each
35 each
35 each
20 each
ESTIMATE FOR THE WORK OF CONSTRUCTION OF CC ROAD AT POHA BY PASS NAR
SHIVPURI (M.P.)
RATES - BASED ON SCHEDULE OF RATES FOR GOVERNMENT OF MADHYA PRADESH U
ADMINISTRATION AND DEVELOPMENT DEPARTMENT IN FORCE FROM 10th May 2012
S.NO.
1 ROAD
2 DRAIN
3 ELECTRICAL
TOTAL
CTION OF CC ROAD AT POHA BY PASS NARBAR,
VPURI (M.P.)
FOR GOVERNMENT OF MADHYA PRADESH URBAN
PARTMENT IN FORCE FROM 10th May 2012
8539142.14
3286381.12
1998668
13824191.26