ID Task Name Duration Start Finish Nov 26, '16 Dec 3, '16 Dec 10, '16 Dec 17,

Start Finish Nov 26, '16 Dec 3, '16 Dec 10, '16 Dec 17, '16 Dec 24, '16 Dec 31, '16 Jan 7, '17 Jan 14, '17 Jan 21, '17 Jan 28, '17 Feb 4, '17 Feb 11, '17 Feb 18, '17 Feb 25, '17 Mar 4, '17 Mar 11, '17 Mar 18, '17 Mar 25, '17
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
1 Project Cycle 96 days? Wed 11/23/16 Wed 3/29/17
2 Kick off meeting 1 day? Wed 11/23/16 Wed 11/23/16
3 Prequalification 6 days Wed 11/23/16 Wed 11/30/16
4 Material Submittal 29 days? Mon 11/28/16 Sat 12/31/16
5 Electrical 26 days? Thu 12/1/16 Sat 12/31/16
6 Mutli Core cables 7 days? Wed 12/7/16 Wed 12/14/16
7 Cable Tray 7 days? Wed 12/7/16 Wed 12/14/16
8 Emergency Light 7 days? Wed 12/7/16 Wed 12/14/16
9 Exit Light 7 days? Wed 12/7/16 Wed 12/14/16
10 Stand by Generator 7 days? Thu 12/1/16 Wed 12/7/16
11 Wiring accessories 7 days? Wed 12/7/16 Wed 12/14/16
12 Control cables 7 days? Sun 12/4/16 Sat 12/10/16
13 Isolators 1 day? Sat 12/31/16 Sat 12/31/16
14 SMB's & DB's 7 days? Sun 12/4/16 Sat 12/10/16
15 MCC panels 8 days? Sun 12/4/16 Mon 12/12/16
16 Earth Pit , Earth Rod , bare copper cable , Earth Bar 5 days?
& all other
Monaccessories
12/12/16 forSat
earthing
12/17/16
system
17 MV panel MCCB details 7 days? Sun 12/4/16 Sat 12/10/16
18 Cable Gland and lugs 5 days? Mon 12/12/16 Sat 12/17/16
19 Lux Calculation 5 days? Mon 12/12/16 Sat 12/17/16
20 Mechanical 15 days? Mon 11/28/16 Tue 12/13/16
21 Fire fighting 10 days? Mon 11/28/16 Wed 12/7/16
22 HDPE pipes 7 days? Thu 12/1/16 Wed 12/7/16
23 Tamper switch 9 days? Mon 11/28/16 Tue 12/6/16
24 Flow switch 9 days? Mon 11/28/16 Tue 12/6/16
25 Zone control valve 9 days? Mon 11/28/16 Tue 12/6/16
26 Air release valve 9 days? Mon 11/28/16 Tue 12/6/16
27 Fire hose cabinet 9 days? Mon 11/28/16 Tue 12/6/16
28 Check valve 9 days? Mon 11/28/16 Tue 12/6/16
29 Gate valve 9 days? Mon 11/28/16 Tue 12/6/16
30 OS & Y gate valve 9 days? Mon 11/28/16 Tue 12/6/16
31 Breeching Inlet 9 days? Mon 11/28/16 Tue 12/6/16
32 Fire extinguisher 9 days? Mon 11/28/16 Tue 12/6/16
33 Water flow switch 9 days? Mon 11/28/16 Tue 12/6/16
34 Butterfly Valve 9 days? Mon 11/28/16 Tue 12/6/16
35 Fire pipe fittings 9 days? Mon 11/28/16 Tue 12/6/16
36 Pipe supports 9 days? Mon 11/28/16 Tue 12/6/16
37 Test drain valve 9 days? Mon 11/28/16 Tue 12/6/16
38 HVAC 13 days? Wed 11/30/16 Tue 12/13/16
39 Pressurization fan 5 days? Tue 12/6/16 Sat 12/10/16
40 exhaust fan 5 days? Tue 12/6/16 Sat 12/10/16
41 fire damper with actuator 7 days? Wed 11/30/16 Tue 12/6/16
42 Smoke extraction system 7 days? Tue 12/6/16 Tue 12/13/16
43 AC units 7 days? Sun 12/4/16 Sat 12/10/16
44 GI sheet 7 days? Sun 12/4/16 Sat 12/10/16
45 Louver with actuator 7 days? Sun 12/4/16 Sat 12/10/16
46 Copper pipes 6 days? Wed 11/30/16 Mon 12/5/16
47 PVC pipes for Drain Line 6 days? Wed 11/30/16 Mon 12/5/16
48 Pipe rubber insulation 6 days? Wed 11/30/16 Mon 12/5/16
49 CIVIL 20 days? Tue 11/29/16 Wed 12/21/16
50 Ready Mix concrete 7 days? Thu 12/1/16 Wed 12/7/16
51 Soil test report 1 day? Tue 11/29/16 Tue 11/29/16
52 Reinforced Steel 7 days? Thu 12/1/16 Wed 12/7/16
53 Concrete strength report 7 days? Thu 12/1/16 Wed 12/7/16
54 Paint 6 days? Sat 12/10/16 Sat 12/17/16
55 Gypsum Board 6 days? Sat 12/10/16 Sat 12/17/16
56 Hand rails and ballustrades 6 days? Wed 12/14/16 Wed 12/21/16
57 Water proofing 6 days? Wed 12/14/16 Wed 12/21/16
58 Fire rated rolling shutter 6 days? Wed 12/14/16 Wed 12/21/16
59 Hollow Blocks 7 days? Thu 12/1/16 Wed 12/7/16
60 Fire rated paints 6 days? Sat 12/10/16 Sat 12/17/16
61 Drawings Submittal 54 days? Wed 11/23/16 Mon 1/30/17
62 Civil 21 days? Mon 11/28/16 Wed 12/21/16
63 Pump room 1 & 2 architectural drawings 3 days? Mon 11/28/16 Wed 11/30/16
64 Pump room 1 & 2 structural details 3 days? Sat 12/3/16 Mon 12/5/16
65 Gypsum layout ground floor 6 days? Sat 12/10/16 Sat 12/17/16
66 Hand rails and ballustrades 6 days? Wed 12/14/16 Wed 12/21/16
67 Electrical 54 days? Wed 11/23/16 Mon 1/30/17
68 Single Line Diagram 50 days? Tue 11/29/16 Mon 1/30/17
69 Emergency Lighting Layout 6 days? Mon 12/5/16 Sat 12/10/16
70 Exit Lighting Layout 6 days? Mon 12/5/16 Sat 12/10/16
71 FA systems Ground Floor 8 days? Tue 11/29/16 Tue 12/6/16
72 FA systems Mezanine Floor 3 days? Wed 11/23/16 Sat 11/26/16
73 FA riser diagram 8 days? Tue 11/29/16 Tue 12/6/16
74 Site cable routing & trench details 5 days? Mon 12/12/16 Sat 12/17/16
75 Roof cable tray layout and installation details 5 days? Wed 12/14/16 Tue 12/20/16
76 MCC panel schedule & installation detail 7 days? Sun 12/4/16 Sat 12/10/16
77 SMDB panel schedule & installation detail 8 days? Sun 12/4/16 Mon 12/12/16
78 DB Schedule & installation detail 8 days? Sun 12/4/16 Mon 12/12/16
79 Site layout 6 days? Mon 12/5/16 Sat 12/10/16
80 Mechanical 23 days? Wed 11/23/16 Tue 12/20/16
81 Fire fighting GF - warehouse 6 days? Wed 11/23/16 Wed 11/30/16
82 Fire fighting GF - Retail Area 5 days? Thu 11/24/16 Wed 11/30/16
83 Fire fighting MF - retail area 4 days? Fri 11/25/16 Wed 11/30/16
84 Pump room 1 ACMV layout 4 days? Thu 12/15/16 Tue 12/20/16
85 Pump room 2 ACMV layout 4 days? Thu 12/15/16 Tue 12/20/16
86 FF external piping layout 8 days? Tue 11/29/16 Tue 12/6/16
87 ACMV layout ground floor warehouse 6 days? Sat 12/10/16 Sat 12/17/16
88 ACMV layout ground floor retail area 6 days? Sat 12/10/16 Fri 12/16/16
89 ACMV layout FF retail area 6 days? Sat 12/10/16 Fri 12/16/16
90 ACMV layout roof floor warhouse area 6 days? Sat 12/10/16 Fri 12/16/16
91 Procurement 96 days? Wed 11/23/16 Wed 3/29/17
92 Electrical 84 days? Wed 12/7/16 Wed 3/29/17
93 Mutli Core cables 35 days? Wed 12/14/16 Mon 1/30/17
94 Cable Tray 14 days? Wed 12/14/16 Sun 1/1/17
95 Emergency Light 14 days? Wed 12/14/16 Sat 12/31/16
96 Exit Light 14 days? Wed 12/14/16 Sat 12/31/16
97 Stand by Generator 25 days? Wed 12/7/16 Sat 1/7/17
98 Wiring accessories 1 day? Wed 12/14/16 Thu 12/15/16
99 Control cables 5 days? Fri 12/30/16 Thu 1/5/17
100 Isolators 6 days? Thu 1/5/17 Thu 1/12/17
101 SMB's & DB's 19 days? Mon 12/12/16 Thu 1/5/17
102 MCC panels 19 days? Mon 12/12/16 Thu 1/5/17
103 Earth Pit , Earth Rod , bare copper cable , Earth Bar 5 days?
& all otherTue
accessories
1/10/17 for Tue
earthing
1/17/17
system
104 MV panel MCCB 1 day? Wed 3/29/17 Wed 3/29/17
105 Cable Gland and lugs 57 days? Tue 1/10/17 Wed 3/29/17
106 Fire fighting 41 days? Wed 12/7/16 Sat 1/28/17
107 HDPE pipes 20 days? Wed 12/14/16 Sat 1/7/17
108 Tamper switch 5 days? Mon 1/16/17 Sat 1/21/17
109 Flow switch 5 days? Mon 1/16/17 Sat 1/21/17
110 Zone control valve 5 days? Mon 1/16/17 Sat 1/21/17
111 Air release valve 4 days? Thu 12/15/16 Tue 12/20/16
112 Fire hose cabinet 4 days? Thu 12/15/16 Tue 12/20/16
113 Check valve 4 days? Thu 12/15/16 Tue 12/20/16
114 Gate valve 4 days? Thu 12/15/16 Tue 12/20/16
115 OS & Y gate valve 4 days? Thu 12/15/16 Tue 12/20/16
116 Breeching Inlet 5 days? Mon 1/23/17 Sat 1/28/17
117 Fire extinguisher 14 days? Mon 12/12/16 Thu 12/29/16
118 Water flow switch 5 days? Mon 1/23/17 Sat 1/28/17
119 Butterfly Valve 5 days? Mon 1/23/17 Sat 1/28/17
120 Fire pipe fittings 6 days? Wed 12/7/16 Tue 12/13/16
121 Pipe supports 6 days? Wed 12/7/16 Tue 12/13/16
122 Test drain valve 7 days? Wed 12/21/16 Thu 12/29/16
123 HVAC 30 days? Wed 11/23/16 Thu 12/29/16
124 Pressurization fan 1 day? Wed 11/23/16 Wed 11/23/16
125 exhaust fan 1 day? Wed 11/23/16 Wed 11/23/16
126 fire damper with actuator 18 days? Wed 12/7/16 Thu 12/29/16
127 Smoke extraction system 9 days? Mon 12/19/16 Thu 12/29/16
128 AC units 9 days? Mon 12/19/16 Thu 12/29/16
129 GI sheet 9 days? Mon 12/19/16 Thu 12/29/16
130 Louver with actuator 9 days? Mon 12/19/16 Thu 12/29/16
131 Copper pipes 9 days? Mon 12/19/16 Thu 12/29/16
132 PVC pipes for Drain Line 9 days? Mon 12/19/16 Thu 12/29/16
133 Pipe rubber insulation 9 days? Mon 12/19/16 Thu 12/29/16
134 Construction 74 days? Wed 11/30/16 Tue 3/7/17
135 Civil 64 days? Mon 12/5/16 Tue 2/28/17
136 Blinding for pump room 1 3 days? Mon 12/5/16 Wed 12/7/16
137 Excavation for pump room 2 6 days? Sat 12/10/16 Sat 12/17/16
138 Shuttering & steel works for base cocrete for pump 5 days?
room 1 Wed 12/7/16 Tue 12/13/16
139 Base concrete pouring for pump room 1 0 days? Wed 12/14/16 Wed 12/14/16 12/14
140 Shuttering & steel works for RCC wall sub structure 11 days?
for pump room
Thu 12/15/16
1 Fri 12/30/16
141 Concrete pouring for RCC wall sub structure for pump 3 days?
room 1 Fri 12/30/16 Tue 1/3/17
142 Shuttering and steel works for RCC slab for pump 9 room
days?1 Fri 12/30/16 Tue 1/10/17
143 Concrete pouring for RCC slab pump room 1 for pump 14 days?room 1 Tue 1/10/17 Mon 1/30/17
144 Reinstating the surface as per actual for pump room 4 days?
1 Tue 1/10/17 Sun 1/15/17
145 Blinding for pump room 2 0 days? Sat 12/17/16 Sat 12/17/16 12/17
146 Shuttering & steel works for base concrete for pump 7 days?
room 2 Mon 12/19/16 Tue 12/27/16
147 Base concrete pouring for pump room 2 0 days? Tue 12/27/16 Tue 12/27/16 12/27
148 Shuttering & steel works for RCC wall sub structure 20 days?
for pump room
Tue 12/27/16
1 Fri 1/20/17
149 Concrete pouring for RCC wall sub structure for pump 1 day?
room 1 Fri 1/20/17 Mon 1/23/17
150 Shuttering and steel works for RCC slab for pump10 room
days?1 Mon 1/23/17 Sun 2/5/17
151 Concrete pouring for RCC slab pump room 1 for pump 15 days?room 1 Mon 2/6/17 Sat 2/25/17
152 Reinstating the surface as per actual for pump room1 1day? Mon 2/27/17 Tue 2/28/17
153 Roller shutter 7 days? Wed 12/21/16 Fri 12/30/16
154 Hand rails and balustrades 4 days? Tue 1/10/17 Sun 1/15/17
155 Gypsum works 20 days? Thu 12/15/16 Tue 1/10/17
156 Block work 20 days? Thu 12/15/16 Tue 1/10/17
157 Mechanical 58 days? Mon 12/19/16 Tue 3/7/17
158 Installation of fire fighting Pipes @GF warehouse32 area
days? Mon 12/19/16 Mon 1/30/17
159 Installation of AC units 9 days? Mon 12/19/16 Fri 12/30/16
160 Installation of duct for stair case pressurization fans
20 days? Wed 12/21/16 Sat 1/14/17
161 Installation of fire fighting pipes @retail area first32
floor
days? Mon 12/19/16 Mon 1/30/17
162 Installation of exhaust fans & pressurization fans10 ondays?
roof Tue 2/14/17 Tue 2/28/17
163 Installation of pump for pump room 1 0 days? Tue 1/3/17 Tue 1/3/17 1/3
164 Installation of pipes & valves for pump room1 11 days? Thu 2/2/17 Fri 2/17/17
165 Installation of pump in pump room 2 0 days? Mon 1/23/17 Mon 1/23/17 1/23
166 Installation of Pump room2 pipes and valves 6 days? Mon 2/27/17 Tue 3/7/17
167 Electrical 63 days? Wed 11/30/16 Mon 2/20/17
168 Installation of GI conduits for FAS in Retail Area 38 days? Wed 11/30/16 Sun 1/15/17
169 Installation of GI conduit for Lighting 38 days? Wed 11/30/16 Sun 1/15/17
170 Cable and cable tray works 33 days? Thu 1/5/17 Mon 2/20/17
171 Excavation works for cable trenches electrical and3FAS days?and cable
Wedlaying
2/15/17 Mon 2/20/17
172 Installation of SMDB's and DB's 3 days? Wed 2/1/17 Sun 2/5/17
173 Installation of Light fixtures 18 days? Fri 1/20/17 Wed 2/15/17
174 Installation of FA devices 18 days? Fri 1/20/17 Wed 2/15/17
175 Installation of Generator 0 days? Tue 1/10/17 Tue 1/10/17 1/10
176 Testing and commissioning 14 days? Wed 3/1/17 Tue 3/21/17
177 AC system 4 days? Wed 3/1/17 Tue 3/7/17
178 FF pipes 5 days? Tue 3/14/17 Tue 3/21/17
179 Electrical Shut down T & C 0 days? Wed 3/15/17 Wed 3/15/17 3/15
180 Close out documentation - Hand over 5 days? Tue 3/21/17 Tue 3/28/17

Project: Afsal Task Split Progress Milestone Summary Project Summary External Tasks External Milestone Deadline
Date: Thu 11/24/16

Page 1