Before work begins, identify potential hazards and use and appropriate method to minimize
exposure risk to all workers
Listed below is a hazard analysis according to job to be done on the project:
POTENTIAL JOB PERFORMED TASK STEPS RISK LEVEL CONTROLS FOLLOW UP HAZARDS
Use low impact
Impact from Med shovel, Foreman digging Rotate Workers Excavation Earth Digging Slip (due to rain or Use of signage, exposure to high Low Additional Foreman amount of water on manpower excavated area) Use safety harness Fall High Foreman Erection of Scaffolds Readily available Hand Injuries Low First-Aider first-aid kit Erection and Use of safety Foreman Dismantling of Fall High harness Scaffolds and Other Working Platforms Dismantling of Ensure signage Scaffolds are in place and Supervisor Impact from falling clear to workers debris High and public Make sure main power must be Electrocution High turned off when Leadman Temporary Electrical installation is Wire Installation Connections/Installation ongoing Make sure fire Fire High extinguishers are Foreman readily available Use safety harness High Pouring of Fall Leadman Concrete Readily available Low Use of Scaffolds and first-aid kit Other Temporary Ensure the area Working Platforms where plastering is Plastering on Impact from falling Med done must be Leadman Walls debris secured with safety net Use safety harness Plastering on Fall High Foreman Walls Readily available Working at unprotected first-aid kit elevated working Ensure the area platforms or surfaces where plastering is Impact from fallig Piling of CHB wall Med done must be Supervisor debris secured with safety net