Problem 16.1-2:
A-B-C-E-G 15 weeks
A-B-D-F-G 17 weeks
Expected 38 week
Completion 38 week probabilit 42 week 42 week
Path Time Variance z-value y z-value probability
ABDFHJ 32.00 3.56 3.17 0.99+ 5.29 0.99+
ABDGIJ 35.50 4.13 1.23 0.89 3.20 0.99+
ACEFHJ 36.83 7.58 0.42 0.66 1.88 0.97
ACEGIJ* 40.33** 7.83 -0.83 0.20 0.60*** 0.73****
* Critical path is A-C-E-G-I-J.
** Expected project completion time 40.33 weeks.
*** Probability of completing project in 38 weeks or less is .20 or 20%.
**** Probability of completing project in 42 weeks or less is 0.73 or 73%.
Problem 16.9-10:
A-B-E-G-H 19 weeks
A-C-E-G-H 21 weeks
A-C-F-G-H 22 weeks critical path
A-D-F-G-H 19 weeks
Crashing:
1. Consider A, C, F, and G; reduce G by 1 week at a cost of $300.
ABEGH: 18 weeks. ACEGH: 20 weeks; ACFGH: 21 weeks; ADFGH: 18 weeks.
2. Consider A, C, and F; reduce A by 1 week at a cost of $400.
ABEGH: 17 weeks. ACEGH: 19 weeks; ACFGH: 20 weeks; ADFGH: 17 weeks.
3. Consider C and F; reduce C by 1 week at a cost of $500.
ABEGH: 17 weeks. ACEGH: 19 weeks; ACFGH: 19 weeks; ADFGH: 18 weeks.