Вы находитесь на странице: 1из 46

Chapter 5

Scheduling the Project


PERT AND CPM NETWORKS
History PERT
Program Evaluation and Review
Technique (PERT)
U.S. Navy for planning and control the polaris
missile program
Emphasis to complete project in shortest time
Ability to cope with uncertainty
Probabilistic activity durations
Multiple time estimate
Suitable for non-repetitive project management

EUT443 Engineering Management


History CPM
Critical Path Method (CPM)
Dupont De Nemours Inc.
Emphasis on tradeoff between cost and
completion time
Deterministic activity durations
Single estimate
Suitable for production management

EUT443 Engineering Management


The Language of PERT/CPM
Activity
task or set of tasks and use resources
represented by arrow
Event
state resulting from completion of one or more
activities
consume no resources or time
predecessor activities must be completed
represented by node
EUT443 Engineering Management
The Language of PERT/CPM
continued
Network
Show relationship between activities using
node and arrow
Milestones
events that mark significant progress
Path
series of connected activities between two
events (node)

EUT443 Engineering Management


The Language of PERT/CPM
concluded
Critical Path
set of activities on a path that if delayed will
delay completion of project
Critical Time
time required to complete all activities on the
critical path

EUT443 Engineering Management


Gantt Chart

Common and provide graphical view of activities


Doesnt indicate progress
Doesnt indicate relationship between activities

EUT443 Engineering Management


PERT and CPM

Show relationship between activities


More efficient especially for large project

EUT443 Engineering Management


Building the Network
AOA Network Activity on arrow
AON Network Activity on node

EUT443 Engineering Management


Table 5-1 A Sample Set of Project
Activities and Precedences
Task Predecessor
a --
b --
c a
d b
e b
f c, d
g e

EUT443 Engineering Management


Figure 5-1 Stage 1 of a Sample
AON Network

EUT443 Engineering Management


Figure 5-2 Stage 2 of a Sample
AON Network

EUT443 Engineering Management


Figure 5-3 A Completed Sample
AON Network

EUT443 Engineering Management


Figure 5-4 Stage 1 of a Sample
AOA Network

EUT443 Engineering Management


Figure 5-5 Stage 2 of a Sample
AOA Network

EUT443 Engineering Management


Figure 5-6a A Completed Sample
AOA Network

EUT443 Engineering Management


Figure 5-6b A Completed Sample AOA
Network Showing the Use of a Dummy Task

EUT443 Engineering Management


Table 5-2 A Sample Problem for Finding
the Critical Path and Critical Time
Activity Predecessor Duration
a -- 5 days
b -- 4
c a 3
d a 4
e a 6
f b, c 4
g d 5
h d, e 6
i f 6
j g, h 4

EUT443 Engineering Management


Figure 5-7 Stage 1 of a Sample
Network

EUT443 Engineering Management


Figure 5-8 A Complete Network

EUT443 Engineering Management


Figure 5-9 Information Contents
in an AON Node

EUT443 Engineering Management


Figure 5-10 The Critical Path and
Time for Sample Project

Critical path = longest path through the network


EUT443 Engineering Management
Critical Path
Critical path is a sequence of activities from start to finish
with zero slack. Critical activities are activities on the
critical path.

Critical path identifies the minimum time to complete


project

If any activity on the critical path is shortened or


extended, project time will be shortened or extended
accordingly

EUT443 Engineering Management


Activity Slack
Slack or Float Indicates how much allowance
each activity has, i.e how long it can be delayed
without affecting completion date of project?

Slack = difference between latest time and


earliest time

LST - EST = LFT - EFT = Slack

EUT443 Engineering Management


Activity Slack example
Activity Earliest Latest Earliest Latest Slack Critical
start (ES) start (LS) finish (EF) finish (LF) (LS-ES) path

A 0 0 5 5 0 Yes
B 0 6 6 12 6
C 5 8 9 12 3
D 5 7 8 10 2
E 5 5 6 6 0 Yes
F 6 6 10 10 0 Yes
G 10 10 24 24 0 Yes
H 9 12 21 24 3
I 24 24 26 26 0 Yes
EUT443 Engineering Management
Exercise

What is the minimum possible time to complete


the project?

EUT443 Engineering Management


Exercise

What is the minimum possible time to complete


the project?

EUT443 Engineering Management


PROJECT UNCERTAINTY AND
RISK MANAGEMENT
Calculating Probabilistic Activity
Times
Three Time Estimates
pessimistic (a)
most likely (m)
optimistic (b)

EUT443 Engineering Management


Figure 5-13 The Statistical Distribution of
all Possible Times for an Activity

EUT443 Engineering Management


Activity Expected Time and
Variance
( a + 4m + b)
TE =
6

(b a )
=
6

2
(b a )
Var = =
2

6
EUT443 Engineering Management
The Probability of Completing the
Project on Time
(D )
Z=
2

=NORMDIST(D,,,TRUE)

EUT443 Engineering Management


PERT Example
Precedences And Project Activity Times
Immediate Optimistic Most Likely Pessimistic EXP Var S.Dev
Activity Predecessor Time Time Time TE V

a - 10 22 22 20 4 2
b - 20 20 20 20 0 0
c - 4 10 16 10 4 2
d a 2 14 32 15 25 5
e b,c 8 8 20 10 4 2
f b,c 8 14 20 14 4 2
g b,c 4 4 4 4 0 0
h c 2 12 16 11 5.4 2.32
I g,h 6 16 38 18 28.4 5.33
j d,e 2 8 14 8 4 2
EUT443 Engineering Management
PERT Example
The complete network

d 6
2
(15,25)
j
a (8,4)
(20,4) e
(10,4)
1 f 7
3
b (14,4)
(20,0)
g
c
(4,0)
(10,4) i
(18,28.4)
h 5
4
(11,5.4)

EUT443 Engineering Management


PERT Example

EF=20 35
d 6
2
a (15,25) j
(20,4) (8,4)
b e
20 43
(20,0) (10,4)
f CRIT. TIME = 43
1 3 7
(14,4)
g
c (4,0)
(10,4) i
(18,28.4)
h 5
4
(11,5.4)
10 24

EUT443 Engineering Management


PERT Example
Critical Path Analysis (PERT)
Activity LS ES Slacks Critical ?
a 0 0 0 Yes

b 1 0 1

c 4 0 4

d 20 20 0 Yes

e 25 20 5

f 29 20 9

g 21 20 1

h 14 10 4

i 25 24 1

j 35 35 0 Yes
EUT443 Engineering Management
PERT Example
Assume, PM promised to complete the project in the fifty
days. What are the chances of meeting that deadline?
Calculate Z, where

Z = (D-S) / V

D = 50;
S (Scheduled date) = 20+15+8 =43;
V = (4+25+4) =33

Z = (50 43) / 5.745 Area = prob = 0.888

= 1.22 standard deviations.

The probability value of Z = 1.22, is 0.888


EUT443 Engineering Management
PERT Example
What deadline are you 95% sure of meeting

Z value associated with 0.95 is 1.645

D = S + 5.745 (1.645)
= 43 + 9.45
= 52.45 days

Thus, there is a 95 percent chance of finishing the project by


52.45 days.

EUT443 Engineering Management


THE GANNT CHART
Figure 5-23 A Gantt Chart of a
Sample Project

EUT443 Engineering Management


Figure 5-24 A Gantt Chart of Sample Project
Showing Critical Path, Path Connections, Slack, EST,
LST, EFT, and LFT

EUT443 Engineering Management


Figure 5-25 A Gantt Chart of a Day Care Project
Showing Expected Durations, Critical Path,
Milestone, and Resource Requirements

EUT443 Engineering Management


Figure 5-26 A Progress Report on a Day Care
Project Showing Actual Progress Versus Baseline

EUT443 Engineering Management


Other Methods
Graphical Evaluation and Review
Technique (GERT)
combines flowgraphs, probabilistic networks,
and decision trees
allows loops back to earlier events and
probabilistic branching

EUT443 Engineering Management


Copyright
Copyright 2005 John Wiley & Sons, Inc.
All rights reserved. Reproduction or translation of this work beyond that
permitted in Section 117 of the 1976 United States Copyright Act
without express permission of the copyright owner is unlawful.
Request for further information should be addressed to the
Permissions Department, John Wiley & Sons, Inc. The purchaser
may make back-up copies for his/her own use only and not for
distribution or resale. The Publisher assumes no responsibility for
errors, omissions, or damages, caused by the use of these programs
or from the use of the information herein.

EUT443 Engineering Management

Вам также может понравиться