Вы находитесь на странице: 1из 7

Marine Policy 36 (2012) 265271

Contents lists available at ScienceDirect

Marine Policy
journal homepage: www.elsevier.com/locate/marpol

A roadmap for marine spatial planning: A critical examination of the


European Commissions guiding principles based on their application
in the Clyde MSP Pilot Project
Cinneide
Wesley Flannery n, Micheal O
Ryan Institute for Environmental, Marine and Energy Research, National University of Ireland Galway, Galway, Ireland

a r t i c l e i n f o abstract

Article history: The European Commission has developed a set of common principles for marine spatial planning in the
Received 6 April 2011 European Union. A critical examination of these principles in practice is undertaken through an
Received in revised form evaluation of the Clyde Marine Spatial Planning Pilot Project. The principles are found to be lacking in
9 June 2011
specicity and somewhat inconsistent with the ecosystem based approach, which they advocate.
Accepted 10 June 2011
Available online 23 July 2011
Lessons for new marine spatial planning initiatives, relating particularly to stakeholder participation,
governance, data requirements, objective setting, and skills and knowledge needs, are derived from the
Keywords: Clyde Pilot.
Marine spatial planning & 2011 Published by Elsevier Ltd.
Ecosystem approach
Planning principles
Formative evaluation
Stakeholder participation

1. Introduction test MSP options for the sustainable development of its marine
resources. The SSMEI sought to develop these options through the
Marine spatial planning (MSP) has been promoted as a tool for establishment of a number of pilot projects, including the SSMEI
the sustainable management of the marine environment and as a Clyde Pilot, which is the primary focus of this paper. The Clyde
means of reducing conict between marine resource users [15]. It Pilot is a useful case study as it is one of the rst explicit efforts at
is dened as the rational organisation of the use of marine space MSP to produce a plan and because it also involved high levels of
and the interactions between its uses, to balance demands for stakeholder participation. Although the Clyde Pilot predates the
development with the need to protect the environment, and to publication of the ECs guiding principles, it anticipated several of
achieve social and economic objectives in an open and planned the guidelines and generally set out to act in accordance with
way [2]. The European Commission (EC) promotes the implemen- principles of ecosystem-based management. An assessment of the
tation of MSP in the European marine environment. Several Member general applicability and value of the ECs guiding principles
States have begun to implement MPS processes, including Germany, through an exploration of the Clyde Pilot project is presented in
the Netherlands, and the United Kingdom. The EC seeks to build on this paper. Processes and outputs of the SSMEI Clyde Pilot are
these experiences and work towards the implementation of a critically examined for evidence of compliance with the principles
coherent set of principles for maritime spatial planning across the for MSP as advanced by the EC. This involved a review of the nal
European Union (EU) [6]. To achieve this, the EC has outlined plan [8] together with annual and quarterly reports, minutes of
preliminary guiding principles for the further implementation of meetings, guidance documents provided by the SSMEI, and an
MSP in the EU marine environment [7]. At this stage these principles evaluation report [9]. Six in-depth semi-structured interviews
may be regarded as a work-in-progress to be further elaborated and also were conducted with members of the Clyde Pilot Steering
rened in the light of experiences. Group, drawn from a broad spectrum of interests including:
The Scottish Government initiated the Scottish Sustainable government departments and agencies, planning authorities,
Marine Environment Initiative (SSMEI) in 2002 to develop and environmental groups, and coastal communities. These inter-
views sought to further explore the Clyde Pilot in the context of
the ECs guiding principles. Due to the geographical location of the
n
Corresponding author. Tel.: 353 864040819.
Clyde Pilot, evaluation against the guiding principle, which
E-mail addresses: wesleyannery@gmail.com (W. Flannery), promotes cross-border cooperation and consultation was not
micheal.ocinneide@nuigalway.ie (M.O . Cinneide). applicable.

0308-597X/$ - see front matter & 2011 Published by Elsevier Ltd.


doi:10.1016/j.marpol.2011.06.003
266 Cinneide / Marine Policy 36 (2012) 265271
W. Flannery, M. O

In this paper, the results of ex-post formative evaluation of the argues the benets of a single administrative entity that leads
Clyde Pilot are presented. The ECs principles for MSP are MSP processes, although it concedes that existing governance
reviewed in the rst instance. A brief overview of the Clyde Pilot structures can achieve this objective and that new entities need
is then presented. Findings arising from an analysis of the Clyde not necessarily have to be created. The EC also argues that for
Pilots experiences are then outlined. These ndings form the MSP to be effectively implemented, it needs to be based on a
basis of a discussion and evaluation of the merits of the MSP legally binding framework [7]. The legal framework needs to
guidelines in their current form and how they might be further operate in accordance with international law and preferably
rened to good effect. within the framework of an EEZ that makes a marine spatial plan
easier to enforce [10]. The legal framework should provide for
inter-institutional cooperation, make administrative competen-
2. ECs principles for MSP cies clear and contain no equivocation as to who is to be bound by
the plan [10]. Cross-border cooperation is crucial to ensure the
In the Roadmap for Marine Spatial Planning the EC advocates harmonisation of plans across trans-boundary ecosystems [7].
the development of a common approach among Member States Such cooperation should facilitate the development of compatible
and advances key working principles [7]. The EC asserts that an standards and processes and may be facilitated by Regional Sea
ecosystem approach should be an overarching principle for Conventions such as OSPAR and HELCOM. Early communication,
MSP [7]. Ten further principles are included: (a) using MSP consultation and cooperation with neighbouring States are
according to area and type of activity; (b) dening objectives to required in order to develop a joint vision for MSP [10]. The EC
guide MSP; (c) developing MSP in a transparent manner; argues that there is also a need for cooperation between marine
(d) stakeholder participation; (e) coordination within Member and terrestrial planning processes so as to achieve consistency in
States; (f) ensuring the legal effect of national MSP; (g) cross- the coastal zone [7]. This can be facilitated through Integrated
border cooperation and consultation; (h) achieving coherence Coastal Zone Management (ICZM) processes.
between terrestrial and maritime spatial planning; (i) strong data Up-to-date and accurate environmental and socio-economic
and knowledge base; and (j) incorporating monitoring and data, information and scientic knowledge are fundamental to
evaluation in the planning process [7]. effective MSP [7]. MSP initiatives must also be sufciently
The principle of using MSP according to area and type of adaptive and exible to react to changes and new information [7].
activity states that management through MSP should be based on An adaptive approach allows for management strategies to be
the size, density, and characteristics of planned or existing evaluated, to learn from their success or failure, and for these
activities, their impacts, environmental vulnerability, and existing lessons to be incorporated into future strategies [12]. An adaptive
governance structures [7,10]. It argues that spatial plans may not approach to MSP requires regular monitoring and evaluation
need to encompass entire marine areas, for example, an entire mechanisms that enables marine managers to assess the extent
exclusive economic zone (EEZ), and that different planning to which spatial and temporal measures of their plans are leading
mechanisms may be employed depending on the intensity of to anticipated outcomes and to respond accordingly [13]. Mon-
human activity in an area and that areas vulnerability. It is itoring and evaluation needs to cover socio-economic, environ-
envisaged that densely used or particularly vulnerable areas mental, and governance objectives, with appropriate indicators
may require more prescriptive spatial plans, whereas areas with being dened early in the MSP process [10].
low density of use may only require general management
principles and that the decision to opt for a strict or more exible
approach should be subject to an evaluation process [7]. The EC
promotes the setting of strategic objectives for MSP at a regional 3. MSP principles in practice: SSMEI Clyde Pilot
or national level [7]. These strategic objectives are then to be
further dened by operational objectives. Strategic objectives are The SSMEI was developed in 2002 with the primary objective
usually aspirational whereas operational objectives generally are of developing and testing options for the delivery of MSP. The
articulated in terms of measurable quantities [11]. SSMEI Clyde Pilot sought to develop and implement a MSP
The need for MSP processes to be transparent and compre- process and an associated marine spatial plan, leading to an
hensible to the public, so as to enhance accountability and integrated and sustainable approach to the management of the
legitimacy, is stressed by the EC [7]. To ensure transparency, the Firth of Clyde as a whole. A pre-existing stakeholderregulator
decision-making process needs to be clear and decisions need to partnership, the Firth of Clyde Forum (FCF), comprising represen-
be communicated and justied to stakeholders [10]. The principle tatives of local authorities, development organisations, business
acknowledges the importance of fostering interaction between and community organisations, and individuals in their own right,
stakeholder groups and emphasises the need for open debate was charged with delivering this outcome. FCF members repre-
between different marine sectors and not just between decision- sent the projects Steering Group who provide general support
makers [7,10]. In the guiding principles, the EC also views and guidance to a small purposefully established project team [8].
stakeholder participation as a source of knowledge that can The Clyde Pilot planning area encompasses the marine and
improve MSP. The identication and inclusion of relevant stake- tidal extent of the Firth of Clyde, including the Clyde Estuary
holders at an early stage in the planning process is regarded as (Fig. 1). It extends seaward from the extreme high water mark,
vital to the timely identication of potential conicts and syner- overlapping with the jurisdiction of several terrestrial planning
gies between stakeholders [10]. Early engagement is also essen- authorities in the intertidal zone, to a line drawn from the tip of
tial so as to clarify goals and benets. Although substantial the Mull of Kintyre across to Finnarts Point [8]. A draft Marine
stakeholder participation generally prolongs the planning pro- Spatial Plan for the Firth of Clyde was issued for consultation in
cess, this delay may be balanced by a prompter implementation March, 2009, with the nal plan published in July, 2010. The plan
phase due to an increased sense of ownership of and commitment presents a cross-sectoral, long-term vision for the management of
to planned initiatives amongst stakeholders, arising from their Firth of Clyde [8]. As the plan has no statutory basis, it is highly
meaningful involvement [10]. indicative in function and largely reliant on sectoral interests
MSP is expected to simplify and accelerate decision-making, and planning authorities in the area, in terms of practical
licensing, and consenting procedures [10]. In this respect the EC implementation.
Cinneide / Marine Policy 36 (2012) 265271
W. Flannery, M. O 267

importance to the maintenance of biodiversity. It proposes these


areas be identied within the plan as Local Areas of Marine
Importance and that guidance be provided on their protection
from activities that disrupt ecosystem functioning, degrade nat-
ural habitats and reduce biodiversity. The nal plan does not
contain any such designations or guidance. The plan contains very
little spatial data and no spatial designations in respect of human
activities or policies. As one interviewee argued, the plan cannot
and should not be represented as a spatial plan. In its recom-
mendations for future statutory MSP in Scotland, the Clyde Pilot
suggests the division of marine regions into smaller planning
units, as appropriate, and the development of sub-regional plans
for particularly busy or sensitive areas.

3.3. Dening objectives to guide MSP

Three broad long-term aims and eight key objectives are


outlined in respect of the Clyde pilot. The aims, embracing the
three pillars of environmental, economic, and social sustainabil-
ity, relate, respectively, to the following:

 Maintaining and enhancing the biodiversity, landscape and


seascape of the Firth of Clyde, by protecting and improving its
natural resources.
 Providing a framework that supports current economic activ-
ity, opportunities for growth and attraction of investment.
 Maintaining the wellbeing and cultural diversity of coastal
communities [8].

These high-level, long-term aims are to be achieved through


eight key objectives: (a) developing an integrated suite of policies
and proposals for future development; (b) improving the knowledge
base of habitats, species and pressures; (c) promoting maritime
Fig. 1. Cylde Pilot planning area.
transportation; (d) enhancing understanding of the importance of
seascape and associated landscapes; (e) increasing participation in
marine-related recreational activities; (f) maintaining and improving
3.1. Ecosystem approach the wellbeing, culture, heritage and diversity of coastal commu-
nities; (g) increasing commercial condence through better-
There is evidence that the Clyde Pilot devoted considerable informed decision-making; (h) safeguarding and enhancing the
attention to the adoption of the ecosystem approach. A commis- quality of marine, coastal and intertidal habitats and species [8].
sioned report entitled Sustainable Development Criteria and the Stakeholders interviewed for the purpose of this study claim the
Ecosystem Approach was produced as part of SSMEI Phase II [14]. objectives are too sectorally focused and fall well short of the level of
This report includes a brief overview of the approach in general as integration that is consistent with the ecosystem approach. This is
well as the 12 principles for its adoption, as advanced by the echoed in an evaluation of the Clyde Pilot, which argues that future
Convention on Biological Diversity [14]. The ecosystem approach MSP efforts should focus on developing policies that mediate
was also elaborated in a discussion paper presented at the Steering between the aspirations of various sectors while safeguarding
Group meeting in May, 2007, in which it was dened as follows: ecosystem functioning [9].
Although objectives are largely aspirational, the Clyde Plan
a holistic method for management of human activities. It looks at contains four cross-cutting policy themes (environment, commu-
all the links among living and nonliving resources, rather than nities, heritage, and safety) and ve sectoral plans (recreation and
considering single issues in isolation. Ecosystem based plans focus tourism, shipping and transport, mariculture, shing, and energy
on the multiple activities occurring within specic areas that are and sub-sea infrastructure), which are intended to detail how
dened by ecosystem, rather than articial boundaries [15]. objectives are to be achieved. The cross-cutting themes and
sectoral plans are not supported through strategies or action
It was noted, however, that it was difcult to arrive at a
plans and predominately consist of further aspirational policies
consistent understanding of the ecosystem approach and to fully
and sectoral ambitions. For example, the rst policy under the
comprehend how it might be applied to MSP in the Clyde area [9].
environment cross-cutting theme, Policy ENV 1, highlights the
Some interviewees claim the Clyde Pilot adopted an overly
lack of detailed and useable knowledge regarding the marine
sectoral approach to plan formulation and that this inhibited
environment of the Clyde but proposes no actions or strategies to
efforts at implementing an ecosystem approach.
rectify this situation. The sectoral plans continue in a similar vein.
Policy R&T 8, for example, calls for integrated marketing of the
3.2. Using MSP according to area and type of activity Firth of Clyde and asserts a need for greater involvement and
cooperation between various stakeholders in this regard. It does
Although the Clyde Pilot made no effort to distinguish not, however, propose a course of action to foster greater
between intensely used and sparsely used areas within its cooperation between these stakeholders to implement this strat-
planning boundaries, it did identify a number of areas of special egy. The plan does contain a proposed action plan, which is
268 Cinneide / Marine Policy 36 (2012) 265271
W. Flannery, M. O

useful in highlighting potential partners for the implementation Some interviewees stated that the roles and responsibilities of
of the various policies outlined in the plan but does not contain the project team and the Steering Group should have been
any strategies for achieving these. Although it is not an action specied more clearly from the outset. This lack of clarity
plan, per se, it does impose time-lines on the Clyde Plans policies contributed to confusion regarding the ownership of the plan
by suggesting a target year for the delivery of each proposal. and the under-utilisation of stakeholder expertise [9]. One inter-
viewee claims the Steering Group were slow to take ownership of
the process and that it was only during the nal few months that
3.4. Stakeholder participation and transparency a sense of mutual obligation to work together to produce and
publish an agreed plan materialised. There was also a lack of
The Plan was developed by the SSMEI Clyde Pilot project team, understanding as to what was to be achieved by the participation
with support and guidance from a local stakeholderregulator of stakeholders in the Steering Group. A number of interviewees
Steering Group and input from sectoral interests. The Steering felt that expertise that resided within the group was not fully
Group, comprising of the FCF core group, consists of representa- exploited during the planning process. It was noted, for example,
tives from a wide range of marine industries and regulatory that the project team lacked professional planning expertise, with
bodies associated with the area. The plan was developed in a consequent knock-on effects on the overall quality of the plan; yet
largely transparent manner. Minutes of meetings were made the steering committee contained a number of terrestrial plan-
available on the Clyde Pilot project website and a number of ners. It was reported that some members of the Steering Group
public workshops were held for stakeholders, where the planning were frustrated by the amount of time they spent proof-reading
process was described in detail. Most interviewees claim that drafts of the plan [9]. In referring to this and related issues some
they report back to their constituencies from Steering Group interviewees commented that that their time and expertise could
meetings. One interviewee commented that this group was not have been used to better effect but that they understood that the
representative of stakeholders in the Clyde area, particularly as project team were working with limited resources and had to
local residents and shermen were under-represented. A promi- deliver the plan within an unrealistically short timeframe.
nent stakeholder group, the Community of Arran Seabed Trust
(COAST), in responding in writing to the draft plan, argued that
the planning process lacked transparency and that participation 3.5. Coordination within Member States
was conned to members of the FCF. Interviewees from the
Steering Group stated that they often dedicated the mornings of The Clyde Pilot sought to explore a voluntary stakeholder
meetings to FCF business and the afternoons to addressing the regulator partnership as a means of implementing MSP. The FCF
Clyde Pilot. The Clyde Pilot and the Clyde Forum were chaired by provided an existing governance structure on which to build this
the same person. These close links between FCF and the Steering partnership. Using a pre-existing body to lead MSP had a number
Group may have served to conate the two in the eyes of the of advantages. The FCF provided a ready-made platform through
public. which to connect with disparate stakeholder networks. Members
Wide public consultation was also employed during the of the FCF had already established good working relationships,
development of the plan [8]. An initial public consultation had built trust in one another and had become accustomed to
exercise focused on dening strategic objectives. Another con- working together in a planning context, having recently com-
sultation exercise offered the public an opportunity to review and pleted an ICZM project. Using the FCF as a vehicle to deliver MSP,
comment on the draft plan. Nine consultation events were held in the opinion of some interviewees avoided unnecessary dupli-
throughout the Firth of Clyde area. This resulted in 21 responses cation of effort as its members were largely representative of the
from individuals or community groups, 10 of which were from relevant stakeholders for any MSP initiative. Building on a pre-
the Isle of Arran. This indicates a generally low level of wider existing governance structure also had a number of disadvan-
community engagement despite considerable efforts on the part tages. Participation in the planning process was perceived by
of the project team to generate local interest in their proposals. some potential stakeholders to be the sole prerogative of mem-
Views expressed during the consultation process were considered bers of the FCF. A clearer division between the two groups might
during the development of the nal plan [8]. have better illustrated its openness to all stakeholders. COAST
Some interviewees also highlighted the need for a coherent further argued that the FCF should not have been tasked with
stakeholder engagement strategy to be formulated early in the developing the plan as it had the effect of largely conning
planning process. Steering Group members and participants at participation and dialogue to groups that were members of the
consultation sessions questioned the approach adopted at these forum. COAST claims that they were effectively excluded from
events and felt that presentations at such events should have participating in the Steering Group and were reduced to providing
focused more on the draft action plan rather than on the process comments on draft plans and policies. A number of interviewees
adopted to produce the draft plan [9]. To assist in developing from the Clyde Pilot Steering Committee explained that COAST
sectoral policies, subgroups were set up for each of the key sectors was excluded from the steering committee, as it is a single issue
on the Clyde: shipping and transport; conservation and biodiver- pressure group, concerned only with an extremely localised
sity; mariculture; shing; recreation and tourism. It proved problem in terms of the overall planning and management of
difcult for the project team to assess the future aspirations of the Clyde area. It is noted that some non-FCF bodies, such as
some sectoral groups. To overcome this, outside facilitation was Scottish Enterprise and Visit Scotland, sooner or later became
used in sectoral workshops to help determine strategic objectives involved in the Clyde Pilot and that involvement of outside groups
for each sector and these were taken into account in formulating improved the quality of dialogue and debate during the planning
the plans policies [8]. This sectoral-based approach was criticised process [9]. Another weakness associated with FCF is that it was
by some interviewees who saw it as militating against an not equipped for implementation of an ecosystem approach and
integrated holistic outcome. It facilitated dialogue within various that it failed to adapt to this task. The plan it produced reects
sectoral groups, and led each to focus largely on its own narrow this as it mainly consists of largely unrelated sectoral strategies.
objectives. Without due regard for impacts on other sectors the One interviewee commented that the Clyde Pilot was perceived
process was scarcely consistent with adopting the ecosystem by some as being largely a conservation-driven exercise, espe-
approach to MSP. cially as it was housed by Scottish Natural Heritage, and advised
Cinneide / Marine Policy 36 (2012) 265271
W. Flannery, M. O 269

that further MSP initiatives be housed in neutral premises so as which created a model of the marine environment based on
not to discourage some stakeholder groups from participating. observed correlations between habitats and various variables,
such as water depth and current speed, from which data had
3.6. Statutory standing and coherence with terrestrial plans been collected [8]. It has been further noted that an issues and
opportunities report would have helped the project team to
Producing a legally binding agreement was beyond the scope identify plan foci from the outset [16]. Interviewees state that a
and competence of the Clyde Pilot as it was tasked with devel- scoping report should have been prepared before the planning
oping and implementing a voluntary stakeholderregulator part- process commenced and that this exercise should have concen-
nership approach to MSP. It did try to ensure that its policies and trated on identifying what stakeholders perceived to be the main
proposals would be taken into account by statutory bodies, such issues and opportunities for MSP in the area as well as associated
as local planning authorities, when they were developing future information and data gaps. Some interviewees allege a dearth of
plans. The plan contains a number of terrestrially focused policies planning expertise within the project team, with knock-on
and proposals. As the plan has no statutory basis, there is no negative impacts on the quality of the planning process and the
guarantee that these will be taken on board when terrestrial plans eventual plan. With the project team consisting of just one full-
are revised. These policies and proposals act as supplementary time member and one-part time member, skills gaps were
non-statutory planning guidelines and suggestions for future regarded as inevitable. The Steering Group acknowledge that
terrestrial planning decisions. The Clyde Plan is also cognisant the project would have benetted considerably from additional
of other plans in the area and the need to integrate with these. For marine and policy development expertise [9].
example, there are two Regional Transport partnerships in the
area tasked with developing Regional Transport Strategies. These
strategies establish a framework for the development of transport 4. Analysis and conclusions
infrastructure and services in the area for the next 1520 years [8].
The Clyde Pilot Plan takes these strategies into account and also The Clyde Pilot project was established before the EC had
highlights specic transport infrastructure requirements of mar- published guiding principles for MSP. Furthermore, it was never
ine sectors [8]. The relationship between the Clyde Pilot and intended to have any statutory standing. The project, never-
terrestrial plans remained unclear throughout the planning pro- theless, set out to act in accordance with the general principles
cess and although local planning authorities broadly welcomed of the ecosystem approach and sought to incorporate many of the
the general guidance provided through the Clyde Plan, there is no principles subsequently advanced by the EC. Assessment of the
indication of how it may be taken into account in future Clyde Pilot, therefore, can provide useful lessons regarding these
terrestrial plans [9]. principles and especially the extent to which they may be
amenable to practical implementation.
3.7. Monitoring and evaluation To date, the SSMEI Clyde Pilot has largely failed to implement
the ecosystem based approach to marine management. A poorly
Using the SSMEI Phase II report as a basis, a number of developed understanding of this key concept, linked to inade-
sustainable development indicators were created and included in quate consideration of its true potential, is apparent. It is evident
a discussion paper produced for the Steering Group. The proposed that the Clyde Pilot did not emphasise the place-based nature of
indicators included institutional process criteria, marine environ- the ecosystem approach as a key element in the planning process,
ment criteria, economic prosperity criteria, and quality of life resulting in a predominately sectoral approach to policy formula-
criteria. Although these sustainable development indicators were tion taking precedence over territorial planning. Attempts at
discussed by the Steering Group during the planning process, they mediating between sectoral interests and at promoting cross-
were not further developed or included in the nal plan. The plan sectoral synergies were largely absent. The place-based nature
does include a proposal to develop a suite of indicators for species and integrated management dimensions of the ecosystem
and habitats that are particularly sensitive to certain activities. approach need to be further emphasised in future MSP guidelines.
There are no proposals to develop indicators by which to evaluate Grafting MSP onto existing governance structures appeals in
its policies or proposals or to monitor their impacts. The Clyde terms of administrative and related efciencies but may have
Pilot, however, does recognise the importance of monitoring plan served to frustrate efforts at implementing the ecosystem
implementation and suggests that it could be undertaken by approach, especially because of its long tradition of sectoral
Marine Scotland, a stakeholderregulator partnership, or by the management. This problem is compounded where existing agen-
proposed Scottish Marine Region Board [8]. cies do not have the authority to hold other government depart-
ments or agencies to account, or to compel them to comply with
3.8. Data and knowledge base the plan. Pre-existing inter-agency conict may lead to a reluc-
tance to share power and collaborate with other agencies. This
Various studies were conducted during the planning process to makes the adoption of an integrated approach difcult and slow
ll perceived knowledge gaps. One study investigated sectoral to accomplish [17]. Existing governance entities may also have a
interactions in the Firth of Clyde. The report, however, is largely history of conict with some marine stakeholders that may make
devoid of spatial data, which would have enabled the production them reluctant to engage in a process that reinforces the status
of a considerably better marine spatial plan, according to a quo [18]. Using existing structures may also raise issues regarding
number of interviewees. The State of the Clyde Report summarises transparency and accountability. These issues require full con-
existing environmental information. It describes the current sideration when deciding whether to create a new administrative
status and trends in key environmental variables. A socio-eco- agency to lead MSP or to assign the task to an existing entity. It is
nomic review provides an overview of employment and busi- wise to assess whether the existing institutional arrangement is
nesses that are based on the Clyde but it also lacks spatial data. t for purpose before entrusting it with the challenging task
A report on biodiversity collates existing knowledge on the Firth of MSP.
of Clyde. It reveals signicant knowledge gaps, both in terms of The EC principle of using MSP according to area and type of
the quality and spatial coverage of the information. In response, activity advises Member States to distinguish between intensely
an indicative Seabed Habitat Map was prepared using a technique, used and sparsely used areas and to concentrate MSP efforts on
270 Cinneide / Marine Policy 36 (2012) 265271
W. Flannery, M. O

the former. This recommendation is similar to an approach a sectoral basis with little or no emphasis on implementing cross-
favoured by some MSP theorists who use the terrestrial terms sectoral objectives. This indicates a need for an implementation
urban and rural to differentiate between them. Urban seas refer plan that gives practical effect to strategic objectives. Inclusion of
mainly to seas neighbouring built-up land areas, variously con- operational and measurable objectives would help ensure MSP
taining ports, shipping routes, naval bases, marine aggregate initiatives progress beyond generating well-meaning but ulti-
extraction, dumping zones, coastal and marine leisure industries, mately toothless plans. This may be achieved through the use of
waste disposal, and conservation initiatives [19]. Urban seas lie the SMART (Specic, Measurable, Achievable, Realistic, Time-
within the territorial sea and are somewhat concentrated around limited) principles when designing objectives [13,23] and through
key estuaries and rths beyond which lie vast rural seas with the use of detailed action plans. It is also vital that plan
marine uses typically extending from shing and sh farming, to implementation, evaluation and monitoring are considered dur-
offshore oil and gas elds, shipping lanes, military exercise areas, ing the planning process and incorporated ab initio into
extensive coastal and marine conservation designations, and marine plans.
marine renewable energy generation [19]. The effectiveness of MSP in mediating between stakeholder
An approach to MSP that is too narrowly focused on intensely aspirations is greatly inuenced by the participatory mechanisms
used marine areas ignores the uid, interconnected nature of the employed in the planning process [24]. While the mechanisms
marine environment and is at odds with implementing an employed in the Clyde Pilot did serve to stimulate participation
ecosystem approach. Such an approach is more likely to exacer- by key stakeholder groups, it achieved little in the way of
bate issues arising from the fragmented governance of the seas mediation between their varied goals. The use of a pre-existing
than resolve them. In this respect an urban/rural divide is not fully stakeholder forum proved benecial for the Clyde Pilot especially
compatible with an ecosystem-based approach and adds to in terms of fostering stakeholder participation in the planning
difculties in assessing environmental and socio-economic issues process. Local coastal partnerships, such as the FCF, have a key
in a holistic fashion. While the rural sea may be less intensively role to play in MSP initiatives as they provide a ready-made
used, it provides vital ecosystem services such as climate regula- platform for engaging with diverse networks of stakeholders.
tion and nutrient recycling. Focusing MSP efforts on urban seas Stakeholders in the FCF had developed trusting relationships with
may result in new development being pushed into less suitable one another. These benets are offset to some extent by attendant
and possibly more vulnerable areas. By concentrating on urban dangers of the Steering Group being perceived as an exclusive
seas, there is a danger that development in rural seas will be club, to which new members are not particularly welcome, and an
project-led, rather than plan-led, resulting in the sub-optimal use associated lack of transparency to outsiders. Benets in terms of
of marine space and resources. Furthermore, industries operating fostering broader participation are likely to accrue if a clear
in the rural seas, such as oil and gas, eventually come ashore, distinction is made between established partnerships and bodies
often traversing urban seas in doing so. How and where these entrusted with MSP initiatives. In certain circumstances, this may
industries come ashore is an extremely pertinent question for necessitate the establishment of new institutional structures. The
MSP. This is of particular concern because marine renewable Clyde Pilot also highlights dangers of engaging with stakeholders
energy, a key driver of MSP in EU waters [20] and one of the more on a predominantly sectoral basis. A participation strategy based
foot-loose marine sectors, is predominantly located in rural seas. on this approach does not foster dialogue amongst diverse
Failure to adequately include the renewable energy industries in stakeholders, with knock-on adverse implications for the formu-
marine spatial plans is likely to add uncertainty to the sector, fail lation of cross-sectoral policies and strategies. MSP guidelines
to integrate it with the development of onshore electricity that stress stakeholder participation also need to extol its poten-
transmission and distribution infrastructure, and ultimately hin- tial gains and how they may be realised.
der its long-term development. There may also be considerable The Clyde Pilot illustrates that a wide range of data, knowledge
difculty marrying urban and rural plans at a later date. and skills are needed to implement MSP. Failure to adequately
The Clyde Pilot is in a marine environment classied as an meet these needs, by drawing on the experience and expertise of
urban sea with considerable spatial variability in use intensity. the stakeholder Steering Group, for example, demonstrates a lack
Several areas are regarded as vulnerable. A piecemeal approach, of appreciation of the true potential of meaningful stakeholder
with separate and largely independent plans for various parts, participation. Lack of relevant knowledge, information, and data
will serve to aggravate issues arising from the fragmented is one of the most cited obstacles to implementing effective
governance of this marine environment. To avoid this, MSP integrated marine management [13]. MSP initiatives must make
guidelines should encourage an approach, which would see adequate provision for the collection of necessary high quality
detailed local level plans for intensely used or vulnerable areas data with adequate spatial resolution. The Clyde Pilot also
nested within larger area plans, with each having regard for demonstrates that MSP takes time, especially if its strong poten-
regional and national level plans and policies. The imperative of tial for tackling difcult problems is to be realised by moving
putting MSP on a rm statutory footing is also clear from the beyond general public participation to an iterative and interactive
Clyde Pilot. This is particularly necessary for marine plans to be process between key actors, including expert and non-expert
properly coordinated with terrestrial and other statutory plans. working together in a relationship of mutual obligation and trust.
The Clyde Pilot also demonstrated that clear understanding of The ECs guiding principles for MSP provide a useful frame-
how marine and terrestrial plans will be coordinated needs to be work for those engaging in MSP. The difculties experienced by
developed from the outset. the Clyde Pilot because it (a) had no legal basis, (b) did not dene
Promoting MSP initially at a strategic level, where attention is clearly measurable objectives to be used in the drafting, imple-
focused on establishing broad principles for marine management menting and monitoring of the plan, (c) did not fully realise the
rather than the formulisation of detailed area plans has been potential of stakeholder participation, (d) did not assemble the
emphasised [21]. A review of 49 marine ecosystem-based man- necessary data to produce a spatial plan, and (e) did not develop
agement plans found that they contained mainly strategic, aspira- mechanisms for coordinating with terrestrial plans, illustrate the
tional objectives with little or no attention given to measurable dangers of non-adherence to the guiding principles. Some princi-
operational objectives [22]. Similarly, the objectives of the Clyde ples need further clarication, elaboration and strengthening,
Plan are largely aspirational and poorly assimilated into the however, if the full potential of MSP is to be realised. Above all
relevant action plans, if at all. The action plans are produced on the place-based, integrated nature of the ecosystem approach
Cinneide / Marine Policy 36 (2012) 265271
W. Flannery, M. O 271

needs to be emphasised so as to avoid MSP processes resulting in [7] CEC. Communication from the commission: roadmap for maritime spatial
uncoordinated sectoral plans. planning: achieving common principles in the EU. Brussels. 25.11.2008.
COM(2008) 791 nal; 2008.
Inconsistency within the ECs guiding principles leading to [8] Donnelly JE, Thompson K, Ross D. Firth of Clyde marine spatial plan.
further fragmentation of the marine environment by implement- Clydebank: SSMEI Clyde Pilot; 2010.
ing MSP by type of sub-area, while advocating the ecosystem [9] Thompson K, Donnelly JE. Lessoons learned for marine spatial planning in
based approach, also needs to be resolved. A nested plan approach Scotland. Clydebank: SSMEI Clyde Pilot; 2010.
[10] CEC. Communication from the commission to the European parliament, the
may be more consistent with the ecosystem approach and still council, the European economic and social committee and the committee of
facilitate the development of detailed local plans for areas of the regions: maritime spatial planning in the EUachievements and future
intense activity or vulnerability. Although the Clyde Pilot did not development COM, vol. 771; 2010.
coordinate effectively with terrestrial development plans it [11] de la Mare WK. Marine ecosystem-based management as a hierarchical
control system. Marine Policy 2005;29:5768.
demonstrates, through its efforts at engaging with local transport [12] Lee K. Compass and gyroscope: integrating politics and science for the
strategies, the usefulness of coordinating with other plans. environment. Washington: Island Press; 1993.
The ECs principle of achieving coherence between terrestrial [13] Douvere F, Ehler C. The importance of monitoring and evaluation in adaptive
maritime spatial planning. Journal of Coastal Conservation 2010,
spatial planning and MSP also should encourage synergies with
doi:10.1007/s11852-010-0100-9.
other types of planning, particularly transport and energy planning. [14] Haskoning UK Ltd.. Sustainable development criteria and the ecosystem
approach: SSMEI desk study. Edinburgh: Scottish Executive; 2005.
[15] SSMEI Clyde Pilot. SSMEI Clyde pilot steering group meeting no 4, 30th May
Acknowledgements 2007, discussion paper 2: high level aims of the LMSP. Clydebank: SSMEI
Clyde Pilot; 2007.
[16] Marine Scotland. Scottish sustainable marine environment initiative project
Funding from The Irish Research Council for the Humanities evaluation. Edinburgh: Marine Scotland; 2010.
and Social Sciences in support of this study is acknowledged. [17] Guenette S, Alder J. Lessons from marine protected areas and integrated
The authors gratefully acknowledge helpful critical comments on ocean management initiatives in Canada. Coastal Management 2007;35:
5178.
a draft of the paper by Eugene Nixon of the Marine Institute, [18] Flannery W, O Cinneide M. Evaluating a collaborative approach to marine
Ireland. The authors thank Stephen Galvin for the production of spatial planning in Canadas eastern Scotian shelf integrated management
Fig. 1 and are deeply indebted to all interviewees who partici- initiative. Stepping into the water: a new domain for spatial planning. UK:
pated in the study. Shefeld Hallam University; 2010.
[19] Smith HD, Ballinger RC, Stojanovic T. The development basis of marine
spatial planning in the United Kingdom. Stepping into the water: a new
References domain for spatial planning. UK: Shefeld Hallam University; 2010.
[20] Jay S. Planners to the rescue: spatial planning facilitating the development of
offshore wind energy. Marine Pollution Bulletin 2010;60:4939.
[1] Crowder LB, Osherenko G, Young OR, Airame S, Norse EA, Baron N, et al.
[21] Jay S. Built at sea: marine management and the construction of marine
Resolving mismatches in US ocean governance. Science 2006;313:6178.
spatial planning. Town Planning Review 2010;81:17392.
[2] Douvere F. The importance of marine spatial planning in advancing ecosys-
[22] Arkema KK, Abramson SC. Dewsbury BM. Marine ecosystem-based manage-
tem-based sea use management. Marine Policy 2008;32:76271.
[3] Ehler C, Douvere F. Visions for a seachange: report of the rst international ment: from characterization to implementation. Frontiers in Ecology and the
workshop on marine spatial planning. Paris: UNESCO; 2007. Environment 2006;4:52532.
[4] Flannery W, O Cinneide M. Marine spatial planning from the perspective of a [23] Day J. The need and practice of monitoring, evaluating and adapting marine
small seaside community in Ireland. Marine Policy 2008;32:9807. planning and managementlessons from the Great Barrier Reef. Marine
[5] Young OR, Osherenko G, Ekstrom J, Crowder LB, Ogden J, Wilson JA, et al. Policy 2008;32:82331.
Solving the crisis in ocean governance: place-based management of marine [24] Ritchie H, Ellis G. A system that works for the sea? Exploring stakeholder
ecosystems. Environment 2007;49:2032. engagement in marine spatial planning Journal of Environmental Planning
[6] EU. Maritime spatial planning for the EUs seas and ocenas: whats it all and Management 2010;53:70123.
about?. Luxembourg: Publications ofce of the European Union; 2010.

Вам также может понравиться