Вы находитесь на странице: 1из 9

39 Steelwork

Erection

W H Arch BSc(Eng), MICE

Contents
39.1 Introduction 39/3

39.2 Effects of the site on a project 39/3

39.3 The effect of plant on design 39/3

39.4 Tolerances 39/5


39.4.1 Camber and vertical curvature of a
bridge 39/5
39.4.2 Tolerances across site butts or joints 39/6

39.5 The interaction of design and erection factors 39/6

39.6 Foundations and temporary supports 39/6

39.7 The partially completed structure 39/8

39.8 Stockyards and transport 39/8

39.9 Manpower and safety 39/9

39.10 Construction and management 39/10

39.11 Summary 39/10

Bibliography 39/10

This page has been reformatted by Knovel to provide easier navigation.


39.1 Introduction
It is not entirely by chance that the French refer to a bridge as a
work of art. For it is indeed a very close liaison between science,
and the art of its application, that makes for success in bridge
building. This is particularly true for bridges, but is also
applicable - though perhaps to a lesser degree - in other types of
structures.
A structure, of any type, is essentially designed for its
completed condition, and the act of achieving its successful
completion is that of coping with logistics of its components,
with the partially erected frame, and with the people who will be
involved in its erection.
Many variable factors affect the choice of erection method
which will be used in any particular case, but on the other hand
there are a number of common elements connected with any
erection plan which do not vary from job to job.
For any project to be successful it is essential that the designer
of the structure has clearly in mind how he visualizes the job will
be built. It may well be that the final scheme may vary from that
which was originally envisaged due to modifications and impro-
vements, but at least the original conception would have been
based on a completely thought out, fully integrated design.
The problems posed by the logistics of a job, the control of
materials flow, and also of the organization of the manpower
who will build the structure, are common.
Two examples of design points which the original conception
should be able to accommodate, immediately spring to mind.
The effects of temporary points of support and possible reversal
of stresses during bridge building, and secondly the orientation
of column webs and flanges to enable the closing beams to be
erected in the final stages of completion of a multi-storey frame.
Figure 39.1 This view of the deck of the Forth Road Bridge
during erection shows the changes in profile which can occur
during the erection process. Arrangements must be made to
39.2 Effects of the site on a project accommodate and follow such changes in the crane support
arrangements. The connections in the structure itself must also
The shape and location of the site on which a project is to be accommodate such changes and be designed accordingly
built will have had its effect on the basic design of the structure
to be erected.
For a tall building, for example, the size of the site, as well as dations are properly evaluated. In a bridge erection scheme, for
the eventual use of the building will have determined the column example, the whole stability of the project can depend upon the
centres; the height or number of storeys will have determined adequacy of a temporary pier and, therefore, on the foundations
the section of the column and, therefore, the weight. In a bridge under that pier.
the configuration of the area to be spanned together with the All temporary loads - even of such a transient nature as those
ground conditions will have determined the spans. Only in under the outriggers of a mobile crane - are important. Only by
uncomplicated cases will the economics of the actual design of full attention to such matters can the safety of the men working
the spans themselves be the sole determining factor in the choice on the job be safeguarded, and the safety of the structure itself
of span - or indeed of the method of construction. be assured against collapse.
Thus, the site through its bearing capacity, or through
existing structures or services, has a profound effect on the
design of the structure to be erected upon it. That the design of 39.3 The effect of plant on design
the structure is affected by site conditions is thus clear, but the
effect those same conditions have on the erection method to be Everyone is familiar with the contractor's plant yard. Items go
adopted is even more profound. there from one job, to be refurbished, tested as required, often
A restriction on access for the materials, or the presence of given a coat of paint, and there they lie ready to be sent out on
underground services can each affect the placing of cranes and to the next job.
thus the whole approach to the erection plan. The choice of erection plant which is to be used on the next
Time on a site costs money and a good scheme should, job will, therefore, mean that, for economic reasons, existing
therefore, aim to reduce as far as is practicable the number of tackle will be used where possible. There is, therefore, a need for
manhours required on that site by the maximum use of prefabri- plant which is as universally useful as possible. Mobile cranes,
cation and subassembly off site. If this is taken to extremes then either mounted on wheels or tracks are one example. At the
the components requiring to be lifted could become too large to other end of the scale are the special 'one-off' erection devices
transport or too heavy to lift. There is thus an optimum balance built to suit the peculiarities of a particular job. The chances of
for any one job, and in major construction projects it is not all the peculiarities repeating exactly on another job are remote,
often that what is right for one job is also right for another. and, therefore, the 'one-off' device is only used on the really big
The ground conditions will have been fully evaluated before jobs where the very high cost can be written off against that job.
the foundations of the structure are designed. It is of equal Whatever the type of plant which is being used to erect the
importance that the ground conditions under temporary foun- steel the economics of that job will be vastly affected by the
Figure 39.2 The mobile crane is a standard piece of equipment
for bridge erection. Points to note are the proper provision and
blocking of the outriggers and the use of the minimum radius
possible for handling the lifts

variance between the actual average weight of each piece to be A light lattice pole, guyed to the ground at suitable anchorage
lifted and the capacity of the crane at each relevant radius. Thus, points can be used to erect most single-storey frames and
in the ideal situation the weight of every piece should equal the girders.
capacities given by the safe-load indicator on the crane. Clearly, Special techniques are needed where the height of the frame
this is an ideal unlikely to be experienced, but a job on which a being erected requires that the pole - or the crane - be supported
conscious effort has been made in that direction will be a more on the frame itself as it grows upwards. The winch providing the
economic job to build. power to work the crane can either be arranged at ground level,
Where a contractor's plant yard and operational area is or to climb with the frame.
remote from access to plant hire companies, greater emphasis The choice of plant and the location of that plant during the
must be placed on a careful choice of universally useful pieces of various stages of building a complex frame will have a signifi-
equipment. Little emphasis can be placed on being able to hire a cant effect on the stress generated in the structure during
major piece of equipment which may be required for a particu- erection. Very careful thought must, therefore, be given to the
lar project. An approach often used by international contrac- need for temporary material in additional supports and to the
tors, building major projects in remote areas, is to buy all the need for additional permanent material to transmit the transient
equipment needed for a job and then to sell it on the local additional erection loads, stresses and deflections.
market at the end of the contract. This option is, generally The use of models can be an invaluable help in the positioning
speaking, not available to a local contractor working his local of plant for the best use to be made of the capacity available.
market by carrying out a large number of smaller contracts. He The increase in the availability of computer facilities is enabling
is in the same position as a small local contractor anywhere, but the optimization of erection methods, and the resultant require-
without the option of hiring the major plant he may need. ments in terms of additional material, manpower and plant, to
When making a choice between one mobile crane and be achieved more easily. In addition, a large number of alterna-
another, consideration must be given to the road conditions and tive possibilities can be considered. A scale model - made of
the distances to the likely locations on which the plant will be balsa or of cardboard - can also be invaluable as a method of
used. A truck-mounted crane can be driven on the roads, but a explaining to the erection squad exactly what they have to do,
crane mounted on caterpillar tracks requires a low-loader and and why.
special equipment to move it from one location to another. The The temporary supports and the erection cranes are arranged
existence of suitable maintenance and testing facilities may to safeguard the safety of the structure during erection. It is of
affect the choice between a hydraulically operated crane or one equal importance that full consideration is given to the many
operated by winches. working places where men will have to work during that
If the operational area is large and the likely workload is erection. The provision of safe means of access to these working
predominantly at the light end of the market, conditions may be places will have the dual benefit of improving the safety of the
such that the planning emphasis should move towards a more individual, and at the same time of speeding the flow of the
labour-intensive method using easily transportable equipment. work. Careful thought must be given to the use and location of
Figure 39.3 An erection pole is much lighter and is more easily erection pole is guyed at the top and bottom and should always be
broken down into small sections for transport than is a mobile crane used in as vertical position as possible. By the use of suitable
with an equivalent lifting capacity. This pole is being used to erect tackles in the overhead and ground guys it is possible to 'walk' the
the heavy girders of an overhead electric travelling crane. An pole from one erection to the next

safety nets since a badly used net can be a hindrance to the job The specification for each job will determine the tolerances
and can indeed be a safety hazard rather than providing the which can be accepted on that job, and these will reflect the
protection intended. purposes for which it is to be used. There are a number of
standards which give quantitative guidance on acceptable toler-
ances and these may be quoted in a specification for any
39.4 Tolerances particular job.

There are four main areas in which the question of tolerances


can affect the engineer. These are: (1) the accuracy of the 39.4.1 Camber and vertical curvature of a bridge
geometry of the structure in the horizontal and (2) the vertical Where a bridge is being built using large prefabricated compo-
planes; (3) the accuracy with which the components match at nents there is always a possibility that local dimensional varia-
joints and splices; and (4) lastly - but by no means least - the tions and twists can occur across the section. Measures must be
control of deformations in the structure, particularly where adopted to accommodate these effects so that force to bring the
welding is involved. bridge into contact with its bearings is not necessary. In some
There is only one way of achieving a specified tolerance, and cases it may be necessary to provide a temporary support on the
that is to control the operation right from the start. Begin with centreline of the bridge to allow the structure to take up its
accurate setting out, follow with accurate fabrication and finish natural shape before setting the bearings to suit. If this is
with careful erection. Work which is allowed to slip below necessary, care has to be taken to ensure that the required
standard can seldom be improved at a later stage. vertical curvature and camber are maintained as closely as
Whilst coarser tolerances can be accepted at the time the possible. It is important to ensure that controllable errors are
ground is being excavated, careful centrelines should be marked not allowed to remain uncorrected and that the adjustment to
on the foundations of columns or piers to ensure that when the the bearings is not used merely as a means of compensation for
steelwork is positioned on them it will be accurate. Levels of careless work.
both concrete and steelwork can be controlled by the careful use The use of machine levels and adjusting screws for levelling
of a dumpy level. It is far easier to place a column on to levelled the bearings will enable extreme accuracy to be attained in
pads than it is to pull the whole frame into position after it has setting the upper bearing surfaces of the bearings. There should
been erected. be a small air gap between the upper and lower halves of the
bearing during final setting to ensure an even distribution of the world. Careful site planning and control can ensure that
load across the bearing before the load is finally transferred. these high standards are maintained in the completed structure.
Great care must be taken to ensure that the bearing is
correctly placed below any diaphragm or stiffener in the struc-
ture above. 39.5 The interaction of design and
There should be no need to emphasize the effects which can be erection factors
caused by loads being applied at points not designed to receive
them, or of loads eccentric to their designed position. In section 39.3 consideration was given to the choice of plant
The specification of the bridge will lay down the precise which would be used in a particular project. The weight of the
tolerances permitted for position and level of the bearings in pieces to be lifted is clearly of paramount importance in this
relation to the structure they are supporting. In multi-span consideration.
continuous girders the tolerances are tighter than those for The weight of a component is a function of its size. Piece
simply supported members so far as level is concerned. The weights, therefore, affect the location of the splices connecting
position of bearings should be such that they are aligned the components. In addition there are local limitations, and
accurately with the centreline of diaphragms and stiffeners associated regulations, which limit the size of component that
shown on the drawing. can be transported. Thus, the site and any limitations imposed
The procedures in the fabricating shop, and the shop as- by its access limitations can affect the design just as much as the
sembly of adjacent sections which the specification may have capacity of the available crane on the job. All these points must
called for, will ensure that these components will recreate the be borne in mind in addition to the purely design consider-
camber called for when they are erected on the bearings we have ations.
been discussing. The 'nesting' of components must be considered during the
It is essential to ensure that the methods used for handling, design phase in order to minimize the volume required to be
stacking and subsequent erection do not cause permanent occupied by a given weight of material, particularly where
distortion of the components. Means of protection should be transportation by sea is involved. The cost penalties for ship-
provided not only to avoid damage to the slings used, but also to ping a bulky lightweight component are very heavy.
prevent damage to the component being lifted or stacked. The restrictions referred to, where size must be limited, can
Incorrect handling can cause deformations and it can also result in components which are uneconomical to erect. In these
damage any protective treatment which has been previously cases, consideration should be given to ways of enabling subas-
applied. Many of the points made in this section apply equally sembly or prefabrication to be carried out at site before finally
to the erection of a building frame. lifting the component into place. An example of this in the tall-
building field is shown in Figure 39.4. In this example the floor
39.4.2 Tolerances across site butts or joints beam stubs have been welded to the column shaft after arrival
on site, but before erection. There were a number of advantages
The jigs and shop erection procedures used to ensure accuracy in this procedure. The plain components would 'nest' well for
of shop fabrication will have minimized the errors in positioning transport, thus reducing the cost of transportation. The depth of
of stiffeners, etc. and will have kept distortions within practi- the floor girder sections could be increased at the columns in
cable limits. The responsibility of those on site is then to order to be able better to transmit the wind loads, and lastly the
reassemble the components and erect them into place. splices remaining to be made up in the air are in a much more
The tolerances allowable in the butt joints between the accessible location. Splices should be located just above a floor
components are dictated by the need to limit the eccentricity of level to give safe access for bolting up. The location of the splices
adjoining members and the secondary stresses those eccentrici- between sections of columns is limited both by the capacity of
ties would produce. The nature of the stresses, compression or the crane available for the erection, and also by the climbing
tension, to which the members will be subjected in service, cycle which has been decided upon. Three floor levels in one
affects the acceptable limits. The compression condition re- piece is normal, with a reduction towards the lower sections
quires a more severe limitation than does a connection loaded in where heavier scantlings will be used.
tension. A temporary or transient loading condition, say, during
erection, can of course reverse the permanent condition and this
must be taken into account when the connections are being
designed and fabricated.
If a butt in the flange plate of a girder is to be made by 39.6 Foundations and temporary
welding then care must be taken to limit the amount of 'cusping' supports
that can occur when the butt is completed. It may be necessary
to arrange to have the material preset in order to be able to The design of the permanent foundations for a structure will
compensate for the effects of shrinkage and distortion as the have been considered in very great detail when the structure was
welded area cools. in the design office. From the point of view of the erector,
The tolerances both of alignment at butts, and of straightness, however, the temporary condition must be examined. This
will be based on measurement taken over a gauge length applies more particularly to bridge building, but the principle
dependent on the spacing of stiffeners, and the amounts of applies in any erection plan. Not only can transient loadings and
allowable deviations will in general be based on the thickness of moments which will be applied to foundations during erection
the plate or flange being measured. Reference has already been exceed very considerably those which can occur after the
made to the relaxation that is possible in connections subject structure is complete, but temporary foundations may also be
only to tension loading. required.
There is clearly a balance between the maintenance of practi- Where temporary foundations are required, as much con-
cal limits on the accuracy of workmanship and the achievement sideration should be given to their design and construction as
of very high standards approaching perfection. The fabrication their importance to the safety of the erection scheme dictates.
industry has always been keenly aware of the need to maintain a The main foundations will not have been designed without
high standard of workmanship in its products whilst at the same reference being made to the results of test borings. Where loads
time ensuring that it remains competitive in the market places of are significant or the effects of settlement on the safety of the
Figure 39.4 A site-subassembled column section for a high-rise erection. In this case also moment connections could be more easily
building being erected. Site-subassembly enables more easily welded up in optimum conditions and the stub-beam connection
transportable components to be built up into economic units for reduced to an easily jigged and readily accessible connection

structure could be dangerous, then a trial boring should be put structures should be given careful consideration. They must be
down local to the temporary foundation to ensure that adequate incorporated in the original design conception. They must be
precautions are taken. adequate to carry the various loads and stresses to which they
The additional loads that must be considered when designing will be subjected during the progress of the work. It must be
temporary foundations should include those that arise from the remembered that temperature changes will result in the move-
incompleteness of the structure that they are supporting. The ment of the structure, and that these movements have to be
effects of wind loading and aerodynamic instability must be accommodated by the design of the temporary works. Remem-
considered. The weights of items of plant, plus the loads they are ber too, that the temporary structure will deflect when the load
carrying and any resultant uplift and dynamic loads due to comes on to it. There must be provision for relieving this load
movement, can affect the design. before the structure can be removed.
Particularly in bridgework there will be temporary piers to In buildings, the temporary structures most commonly used
place on the foundations discussed earlier, and also temporary are, again, props or columns used to support girder structures at
extensions to the permanent piers. These are commonly con- intermediate points during the construction, for example, large
structed of standard components which can be stored and re- lattice girders spanning distances too great to permit erection of
used on future work. In the event that specially designed and the component in one subassembly. It is important here to check
fabricated temporary supports are not being used, a check the adequacy of the beam carrying the prop, or of the lower
calculation should be made to ensure the adequacy of the column length being temporarily extended. It is not uncommon
standard components planned for use. where the temporary erection loads have to be accommodated
The points at which it is required to make connections for permanent additional material to be incorporated to provide
between the permanent structure and the temporary erection the additional carrying capacity required.
39.7 The partially completed structure must be carefully considered. It must be possible to construct
the permanent members without removing the temporary load-
We have considered the need for temporary supports during the carrying members, and to be able to remove the temporary
erection of a structure, and these considerations have dealt members afterwards.
principally with the need to shorten cantilevers during bridge The permanent structure must be capable of absorbing the
erection or to prop long girders during assembly in a building. loads induced by the temporary members. These can in many
However, all structures are designed to have a minimum cases frame into locations not intended to carry those loads
amount of redundancy and it follows, therefore, that until an when the frame is completed. Cases of eccentricity need special
erection procedure is complete the structure is at risk. It is to attention in view of the secondary stresses which can be induced.
eliminate this risk and to take due account of the changing stress
patterns that will arise during an erection procedure that the
engineer must be concerned. It has already been stressed that an 39.8 Stockyards and transport
erection scheme should be borne in mind when the original
design is being made, since only by that means can a feasible, We have seen that prefabrication enables manhours to be
safe and well regulated design be produced. expended on the ground rather than at a height, and thus
If a lattice girder structure is to be built out by cantilevering reduces to the absolute minimum the time that a site is occupied.
from a pier it is clear that the stresses in the members will be It is this factor that enables a steel frame to be put up so quickly,
reversed until the next pier is reached and the girder spans from and to provide an instant support for the follow-up trades.
pier to pier. Similarly, only when all the spans are completed will Inevitably, components must be transported from the factory
any continuity assumed by the designer be achieved. to the site. Nothing can ever be perfectly controlled, and a
Where the lattice girder is supported by piers or, in the case of stockyard is therefore necessary to absorb the differences
an arch rib, may be supported from above by temporary cables between materials arriving on site, and those actually required
(see Figure 39.5), very special stress patterns can develop. It may from day to day for erection. The effects of delays in the
be necessary to carry out a number of case studies at progressive transport system must be cushioned, otherwise expensive erec-
stages of erection in order to ensure that the most critical tion equipment and manpower would be kept idle.
condition for each member and for each connection has been It has been very truly said that a good stockyard control can
considered and adequately dealt with. make a successful job. The reverse is certainly true: if compo-
A building designed to derive its rigidity from shear walls or nents and fasteners are not sent out to the erection front as
from the composite action of the floor slab will be unstable until required there will be delays.
these features are completed. Temporary means of providing Incoming material must be recorded correctly, and located in
this rigidity must be arranged. order that it can be relocated and transported out when required
The location of these temporary members, and their stiffness without resorting to double handling. It is often convenient to
relative to adjacent members of the partially completed frame colour-code the material to conform either to types or area of

Figure 39.5 In the erection of an arch bridge, temporary supports calculated carefully for all erection stages and constant checks
are required to assist in cantilevering the two halves of the arch out made of the actual behaviour of the structure as it grows out of the
from the abutments. Transient loads, deformations and stress crown
reversals which occur during the erection process must all be
the project. Cranage will be provided to handle the weights of 39.9 Manpower and safety
components involved, with the same rules applying as were
discussed in section 39.2. A light crane with large coverage will None of the operations discussed in this chapter can be carried
be required to handle the light components, and all the heavy out without an adequate and sufficiently skilled number of men.
components will be placed under the heavy crane. A Goliath- The proper use of subassembly techniques can reduce the
type crane is often used for stockyard duties since it occupies number of manhours which have to be worked at a height, but
little ground area for its tracks and can easily cover a large area work has still to be done up on the open steel, and this must be
without reduction of capacity. properly planned.
Adequate roads - and rail tracks where required - must be Steel erection is a task that can only be learned by experience.
provided to give all-weather service. Axle loads of the vehicles Formal training can teach the basic skills of rigging, scaffolding,
using a stockyard are heavy and maintenance time on broken slinging, crane driving, burning and welding, but only ex-
roads is time lost for erection. perience can enable these skills to be applied on the job. It is the
Vehicles bringing material into a stockyard will be the normal individual erector who brings his expertise and skill; it is the
form of fixed axle or semi-trailer type of transport common on employer who must provide the planned erection method and
the public roads. Only in exceptional cases will it be necessary to adequate equipment to enable the erector to safely apply his
bring components on to site on special transport vehicles skill. He needs not only the crane and the spanners, but also a
requiring police escort. There are limitations imposed by law on safe place in which to work. Figure 39.6 shows a man working
both the weight and dimensions of loads that can be moved on on an unsafe platform. Not only is it dangerous for a person
the public highway and a knowledge of those restrictions is working in such conditions, but the safety of the whole job
essential. Additionally, many sites are located in places where could be put at risk. The provision of boxes to contain loose
the road layout, or low bridges, impose restrictions and a study tools, and good housekeeping in the handling of small compo-
of these must be undertaken before the component gets stuck nents in general can each help to ensure a smooth running, and a
and the site is disrupted. safe, job.
On-site transport is not restricted in the same way, and the In the UK, a large number of regulations control the manner
size of load is similarly subject to different controls. Site of the ordering of work on a construction site, and these,
subassembly can lead to awkward loads, and the safe loading together with summaries of them are available from HMSO and
and fixing of these on the site transport is important. from RoSPA. These cover such major items as the testing and
The proper control and distribution of fasteners is important. retesting of lifting equipment and the dimensional requirements
Bolts should be rebagged into 'sets' required for particular for working platforms and access ways. Many accidents,
connections or areas. This saves time at the splice, and also cuts though, are caused not by major problems, but by insufficient
down the waste of bolts when an excessive number are issued by attention being given to the small items.
the store. The proper storage of welding electrodes, their issue Thought given to the design and detailing of the steelwork
and conditioning while being held at the point of use are also itself can result in a real reduction in the risk of an accident
functions often delegated to the stockyard stores control func- occurring during erection.
tion. Accidents will always happen, but careful planning from the

Figure 39.6 An example of an unsafe working platform. To ask a


man to work under such conditions endangers not only the man on
the platform but also the safety of the other men with whom he is
working, and the safety of the whole job could be endangered
start will prevent a simple accident from escalating into a major 39.11 Summary
calamity.
The more complex a project becomes and the more services are
involved - a tall building is an excellent example - the greater
39.10 Construction management the need for early consultation and planning. In a tall building
where the lower floors can be approaching occupancy while
The construction manager is a man whose function is becoming those above are having services installed and those at the top are
increasingly important. The basic object of management on a still being framed, the whole complex construction pattern is
construction site is to have the right component at the right seen in microcosm.
place at the right time with adequate equipment and men to Accesses for foundation construction must integrate with the
handle it, and to repeat this over and again to complete the demolition of what was there before. Material arriving on site
structure on time and within a cost target. requires close control and schedules if traffic chaos and a
To this basic requirement must be added the co-ordination of hopelessly congested site are to be avoided.
a number of contractors, each with his own problems and The positioning of cranes and the stability of the partially
targets, together with an ability to overcome problems created completed frame and of any temporary works must be very
by other influences, often outside his direct control. carefully thought through.
There are a number of contractual forms within which The safety of those working on the structure and of those
construction work can be carried out, but one important feature working, and perhaps also living, in the vicinity of the new
of all these is that the roles of the parties to the contract are structure must be constantly considered.
clearly defined. It is essential that responsibilities are clearly Only by the co-operation of everybody who will be involved
defined in this way since we have seen how closely the original in the project, be it bridge or building, can the best design be
design affects the erection process and vice versa. These inter- made, the best construction method adopted and the earliest
connecting factors must be appreciated by all the parties or completion date obtained.
disputes, and perhaps tragedies, can result. All these factors - design, method of construction and con-
There is a variety of ways in which a prospective owner can struction time - must be optimized if the owner is to be able to
have the management of the construction of his project orga- make use of his new facility at the earliest possible time and so
nized. One factor common to all methods, however, is that the be able to generate revenue from his investment.
earlier in the time-scale all the parties who are to be involved can
add their particular expertise to the planning of that project,
then the sooner the project can be started, and the sooner it can Bibliography
be completed. The attainment of this ideal situation is made
easier with some forms of contract and management organiza- Arch, W. H. (1985) Structural steelwork erection. British Council for
tion than with others. Steel Erection, London
In what is being presented here as the ideal situation, a project Barron, T. (1963) Erection of constructional steelwork. Iliffe, London.
team is brought together at the inception of the planning of the Constrado (1972) Steel designers' manual (4th edn). Crosby Lockwood,
London.
project. This team will comprise those who will be directly Leech, L. V. (1972) Structural steelwork for students. Butterworths,
responsible for each of the phases of the project, from the London.
design, not only of the frame, but of all the associated services, O'Connor, C. (1971) Design of bridge superstructures.
right through to the site erection functions, at the other end of Wiley-Interscience, Chichester.
the planning and construction time-scale. Ward, F. C., Bryant, E. G. and Pound, R. P. (1970) 'Simply supported
The other end of the spectrum is the job where all the bridges in composite construction'. British Council for Steel Erection,
functions are carried out in watertight compartments, the London
designs being prepared in a number of engineers' offices, and the Journal
Building with steel: controlled circulation, British Steel Corporation,
contractors tendering in isolation. With this system no mean- address: 9 Albert Embankment, London SEl 7SN
ingful discussions can take place between those who either are,
or will be, most intimately involved with the project until so late
a time in the construction process that their contribution can
only be limited.

Вам также может понравиться