Академический Документы
Профессиональный Документы
Культура Документы
INTRODUCTION
This document presents the project assignment for EPSCOM 2009 to be completed by each
participating team. For ESPCOM 2009, the approach of the project is Project Based Learning (PBL). The
main objective of this PBL is to enable each participating student to learn from the project assignment by
solving practical electrical distribution system problems. It is also considered as a long term problem
solving assignment since the duration for completing the project is 3 months.
In order to solve the given problems and document the approach, each participating team needs to
make references to appropriate books, papers, reports as well as available documents from the web. It is
also necessary for the team to use power system simulation software that can perform load flow, short-
circuit and possibly transient stability calculations. To complete this project, the ETAP and
PSCAD/ETMDC simulation software have been used. To verify the simulation result manual calculations
were also made. Several basic formulas related to load flow, short circuit and relay time setting and
coordination are also presented in this report.
The main intake substation has another voltage transformation, i.e. 132/33kV. Parameters for the
two 45MVA transformers are stated in Figure 2.1. The NER for these two transformers is also sized in
1
accordance to the same principle as for the 132/11kV power transformers. The 11kV and 33kV buses are
arranged in single-bus single-breaker scheme with two buses connected through a bus-coupler breaker.
2
Figure 2.2. Typical Arrangement of PPU
Table 2.1 provides the list of substations in the DISCO-Net and the types of switches in the substation.
3
Table 2.2 tabulates the details for cable and their connectivity in the DISCO-Net System. The
cable data is referred to the TCI cable data for the positive sequence impedance of the cables.
4
Load at each substations are connected to the secondary side of either 11/0.433kV or 33/11kV
transformers. Table 2.3 lists the size of transformers at each substation based on the MTM data [1] and the
corresponding static loads connected to its secondary. The induction motor is as shown in Table 2.4.
5
Since 2 transformer shares the same NER, the current flowing through it is double the current
flowing at 1 transformer. Therefore, based on Ohms Law the NER will be reduced by half of its value.
The value of NER for 132/33kV transformer is 12.1.
Same as the 33kV network, this NER is shared by 2 transformer. Therefore, the value of NER for
132/11kV transformer is 2.