CHAPTER TWO

RESPONSIBILITY AND
AUTHORITY

THE RESIDENT PROJECT the performance of a construction contract. It is obvious that


REPRESENTATIVE AND each organization must establish lines of authority by desig-
nating the individuals who are authorized to make necessary
INSPECTORS AS MEMBERS decisions (see The One-to-One Concept in Chapter 1). If
OF THE CONSTRUCTION this is done in a careful, thoughtful manner, the project will
TEAM benefit. If it is done in a haphazard manner, the likelihood of
The effective management of a construction operation can be misunderstandings and disputes will increase.
achieved only through a well-coordinated team effort. The
Resident Project Representative and the inspectors are vital Agency Relationship
members of that team, for without them there would normally An agency relationship is established when one party, such
be no direct involvement in the construction of the project by as the owner or architect/engineer, designates another party,
the architect/engineer or the owner. The Resident Project such as a Resident Project Representative or inspector (the
Representative and the inspectors are the eyes and the ears of agent), to act on its behalf. Once the agency relationship is
the architect or engineer and the owner. Their authority and established, the owner or architect/engineer is bound by the
responsibility on the project is largely based upon that con- acts and omissions of its Resident Project Representative or
cept. To be sure, one architect or engineer may delegate more inspector, as its agent. If on-site representatives are not des-
or less authority to the Resident Project Representative or ignated and given the authority that they need, communica-
inspector than another architect or engineer; however, that is a tion will break down and confusion will result. There will
matter of employeremployee relations between the Resident also be some unanticipated legal ramifications.
Project Representative or inspector and his or her employer.
In addition, many federal construction contracts require a
resident inspector in the employ of the contractor under the Actual Authority
principle of contractor quality control (CQC). Generally, in the The most common way for an agency relationship to be
absence of specific instructions to the contrary, the guide- established is by an express grant of actual authority. The
lines in this chapter are considered by many members of the contract documents simply state that a particular individual
construction industry to be the normal standards. shall have the authority to make certain decisions. On public
construction projects, the existence of actual authority is
important because statutes protect public agencies against
LINES OF AUTHORITY ON acts or decisions of unauthorized individuals.
CONSTRUCTION PROJECTS
Almost all construction projects involve organizations.
Apparent Authority
The participantsowner, contractor, subcontractors, and An agency relationship can also be created when the owner
suppliersare not individuals. They are corporations, part- or architect/engineer allows another party to operate with
nerships, or other forms of business associations. the appearance of authority to act on behalf of the owner or
Organizational decision making can be ponderous. Yet architect/engineer. The contractors who reasonably believe
decisions and approvals are required on a daily basis during that they are dealing with a duly authorized agent will be