Академический Документы
Профессиональный Документы
Культура Документы
Geotechnical
I
Investigation
ti ti and d
Design for Piling
Works
Chris Haberfield
1
Outline
Client Moments
You get what you pay for
Benefits of Doing More
Case Studies
Closing Remarks
2
Client Moments
Just do a basic investigation the piling contractors can take the risk
A
A primary risk to my project involves the in-ground
in ground construction
construction
Can you guys help us out as we have a problem with our foundations ...
we have a geotechnical report .. but.....?
but.....?
The piling contractor cant install the piles to the design depth in the way
I want them to install them
I must have bored piles on this project, and you cant use bentonite or
polymer to install them
3
Client Moments
I am taking
t ki a conservative
ti approach....so
h I can go cheap
h on my
geotechnical advice/investigation
It
It worked down the road so it will work here
here
Your
Your proposal for the geotechnical investigation is too expensive I can
get one from Joe for half the price
We
We have to take the cheapest price I know we will pay for it in the end
but that is the policy
With g
geotechnical advice/investigation
g y
you get
g what yyou p
pay
y for
4
Levels of Geotechnical Input
Platinum
Gold
Silver
Bronze
5
You get what you pay for !
Bronze Silver Gold Platinum
Gold+comprehensive
Silver+moreboreholes,
boreholes>toedepthof
boreholes toe depth of insitu and laboratory
insituandlaboratory
Ground someinsitutestingfor
shallowboreholes piles testingformodulus,
modulus,laboratory
Investigation notestingand/orsampling SPTtesting strengthandpermeability,
testingforpermeability,
Indextesting staticpileloadtesting
modulusandstrength
6
Implications of Enhanced Geotechnical Input
7
Improved Strength Reduction Factors
Piling Code AS2159 2009
8
Hypothetical Example 1
9
Improved Strength Reduction factors
Same Design Parameters
10
Improved Parameters, Analysis and Design
11
Pile Construction Time
Improved Parameters, Analysis and Design
12
Hypothetical Example 2
13
Example 2 - Risks and Opportunities
Risks Opportunities
G
Groundwater/dewatering
d /d i system
Optimised pile lengths
Pile founding levels
e g piles founding at
e.g.
Si ifi- dykest opportunities
Significant
Socket lengths tdifferent
iti levels
for
f in
reducing
Differential foundation
settlement/tilt costs,
basalt/bedrock
Longer piles
construction time and riskfooting
Alternative
Construction difficulties systems
Delays Shorter construction time
Latent conditions
14
Case Studies
15
Case Study 1 Royal Domain Towers, Melbourne
0
weathering
EW - MW
dykes 10
Siltstone/Sandstone
~ 85 piles
Gold level investigation provided significant
Traditional
Depth (m)
serviceability
i d cost and time savings to project
bilit lloads
5 MN to 15 MN
20
Benefits - savings
design pile head Saving of 9.5 m 950 m socket length
settlement
ttl t : 1 % dia
di 950 m3 concretet
25 1400 m3 spoil
$$ + 42 days
Additional Cost for
1.2 m dia. pile, SL=
SL 15.3 MN
30 P
Pressuremetert testing,
t ti UCS
testing, analysis
on-site presence
Case Study 2 Freshwater Place, Melbourne
HW MW siltstone
HW-MW ilt t
(variable)
35 GARSP - as
70 x 1.2 m dia. Piles constructed
( l others)
(plus th )
60
Case Study 3 SU Building, Melbourne
19
Case Study 5 - Eureka Tower, Melbourne
Inferred Stratigraphy Section AA
Upper basalt
Lower basalt
Siltstone
Inferred Stratigraphy Section BB
Upper basalt
25m
Lower basalt
35 m
Siltstone
Limits of basalt
Upper Basalt
L
Lower B
Basalt
lt
CFA and Bored Pile solution
Case Study
Darwin
Deeply weathered
phyllite
Bored piles
27
Case Study 6 Nakheel Tower, Dubai
Initial investigation
Boreholes to 60 m,, one borehole to 120 m
lower standard of drilling, laboratory testing only (disturbed samples)
Preliminary recommendations piles possibly in excess of 120 m
d th (t
depth (to lilimit
it settlements)
ttl t )
Settlement estimate of about 500 mm risk of tilt
Subsequent
q Investigation
g
The Pl
Th Platinum
ti llevell iinvestigation
ti ti
Boreholes to 300 m, triple tube coring
Extensive laboratory testing for strength, stiffness and constitutive
gave everyone the confidence that
behaviour
this could be done
Extensive insitu testing including pressuremeter, crosshole seismic,
full scale pile load tests and construction trials
Extensive 3D finite element analysisy p
plus others
Settlement estimate of about 80 mm
Basement retention no anchors
30
Footing Layout
Barrette sizes
1.5
15mx2
2.8
8m
1.2m x 2.8 m
Raft thicknesses
2.5 m
4.0 m
6.0 m to 8.0 m
Case Study 7 Basement
Thank you
33