1 PRELIMINARES
1.1 LOCALIZACION Y REPLANTEO OBRA ARQUITECTONICA M2 $ 4,132.00
AUXILIAR DE OBRA 2 (B) Ins hh 0.14 7,595.09 $ 1,063.00
COMISION TOPOGRAFICA Ins hh 0.02 44,380.14 $ 666.00
MADERA DURMIENTE ORD 4*4 Ins ML 0.26 1,761.20 $ 458.00
OFICIAL OBRA 1 (A) Ins hh 0.14 13,041.42 $ 1,826.00
PUNTILLA CON Y SIN CABEZA 1 Ins lb 0.02 3,076.53 $ 62.00
HERRAMIENTA Y EQUIPO MENOR (%M.O.) Esp % 1.60 3,555.00 $ 57.00
Redondeo $ -
2 OBRAS EXTERIORES
2.1 EXCAVACION MANUAL EN MATERIAL COMUN (INCLUYE RETIRO) M3 $ 57,282.00 -
AUXILIAR DE OBRA 1 (A) Ins jr 0.40 60,761.94 $ 24,305.00
OFICIAL OBRA 2 (A) Ins jr 0.20 104,326.36 $ 20,865.00
VIAJE VOLQUETA M3 Ins M3 0.17 63,714.00 $ 10,621.00
HERRAMIENTA Y EQUIPO MENOR (%M.O.) Esp % 3.30 45,170.00 $ 1,491.00
Redondeo -
2.5 DILATACION ADOQUIN EN CONCRETO MONOCAPA COLOREADO 10*20*6 CMS (VEHICULAR) ML $ 12,384.00
SUMINISTRO E INSTALACION DE SARDINEL PREFABRICADO A-10, INCLUYE MORTERO DE PEGA SEGUN NORMA NTC-
2.7 ML $ 51,051.00
4109
AUXILIAR DE OBRA 1 (A) Ins jr 0.0800 60,761.94 $ 4,861.00
OFICIAL OBRA 2 (A) Ins jr 0.0200 104,326.36 $ 2,087.00
SARDINEL PREFABRICADO A-10 Ins ML 1.0300 40,311.25 $ 41,521.00
MORTERO 1:3 Ana M3 0.0050 470,503.00 $ 2,353.00
HERRAMIENTA Y EQUIPO MENOR (%M.O.) Esp % 3.30 6,948.00 $ 229.00
Redondeo -
3 CARPINTERIA METALICA
LAMINA COLL ROLED CAL 18 DE 2*1 Ins UND 0.6210 173,295.80 $ 107,617.00
PINTURA ANTICORROSIVO Ins gl 0.0500 35,905.17 $ 1,795.00
SOLDADURA ELECTRICA (SOLDADURA 7018) Ins kg 0.9702 11,418.27 $ 11,078.00
SUB-CONTRATO ORNAMENTACION Ins hr 0.6000 101,823.00 $ 61,094.00
HERRAMIENTA Y EQUIPO MENOR (%M.O.) Esp % 2.50 61,094.00 $ 1,527.00
Redondeo -
3.2 SUMINSITRO E INSTALACIN VENTANA LAMINA CAL. 18 CON VIDRIO INC. ANTICORR. M2 $ 213,024.00
ANGULO 3/4`` * 1/8`` Ins ML 1.94 1,630.09 $ 3,162.00
AUXILIAR DE OBRA 2 (B) Ins hh 2 7,595.09 $ 15,190.00
BISAGRA COMUN 2`` Ins UND 1.05 1,874.42 $ 1,968.00
LAMINA COLL ROLED CAL 18 DE 2*1 Ins UND 0.4 173,295.80 $ 69,318.00
MANIJA PARA VENTANA Ins UND 1 2,629.28 $ 2,629.00
OFICIAL OBRA 1 (A) Ins hh 1 13,041.42 $ 13,041.00
PINTURA ANTICORROSIVO Ins gl 0.23 35,905.17 $ 8,258.00
SOLDADURA ELECTRICA (SOLDADURA 7018) Ins kg 0.16 11,418.27 $ 1,827.00
SUB-CONTRATO ORNAMENTACION Ins hr 0.6 101,823.00 $ 61,094.00
VIDRIO 5 MM PELDAR Ins M2 1 34,750.05 $ 34,750.00
HERRAMIENTA Y EQUIPO MENOR (%M.O.) Esp % 2.00 89,325.00 $ 1,787.00
Redondeo
SUMINISTRO E INSTALACION DE BARANDAS EN TUBERA METLICA AGUA NEGRA D=2", C. 0.80, SOLDADO, SEGUN
3.4 ML $ 329,576.00
DISEO, INCLUYE ANTICORROSIVO Y PINTURA.
4 PAETES
4.1 PAETE LISO MUROS 1:4 M2 $ 18,273.00
AGUA Ins lt 3.63 $ 20.00 $ 73.00
AUXILIAR DE OBRA 2 (B) Ins hh 0.46 7,595.09 $ 3,494.00
OFICIAL OBRA 1 (A) Ins hh 0.46 13,041.42 $ 5,999.00
MORTERO 1:4 Ana M3 0.02 409,242.00 $ 8,185.00
HERRAMIENTA Y EQUIPO MENOR (%MO) Esp % 5.50 9,493.00 $ 522.00
Redondeo -
5 PINTURA
5.1 ESMALTE LAMINA LINEAL 3 MANOS ML $ 4,811.00
AUXILIAR DE PINTURA 1 (C) Ins hh 0.15 8,733.91 $ 1,310.00
DISOLVENTE THINER Ins gl 0.01 15,398.53 $ 154.00
LIJA Ins UND 0.16 1,094.25 $ 175.00
OFICIAL PINTURA (C) Ins hh 0.15 14,997.45 $ 2,250.00
PINTURA ESMALTE SINTETICO TIPO II Ins gl 0.02 49,590.17 $ 744.00
HERRAMIENTA Y EQUIPO MENOR (%MO) Esp % 5.00 3,560.00 $ 178.00
Redondeo -
6 INSTALACIONES ELECTRICAS
6.1 SUMINISTRO E INSTALACIN DE TUBERIA PVC CONDUIT 3/4". ML $ 14,653.00
ADAPTADOR TERMINAL 3/4`` CONDUIT Ins UND 2 558.01 $ 1,116.00
AUXILIAR DE INSTALACIONES 1 (B) Ins hh 0.4 8,354.72 $ 3,342.00
LIMPIADOR 1/4 PVC Ins gl 0.01 18,092.79 $ 181.00
OFICIAL INSTALACIONES (B) Ins hh 0.4 14,345.44 $ 5,738.00
SOLDADURA LIQUIDA PVC 1/4`` Ins gl 0.01 93,398.76 $ 934.00
TUBERA PVC CONDUIT 3/4`` Ins ML 1 3,042.08 $ 3,042.00
HERRAMIENTA Y EQUIPO MENOR (%MO) Esp % 3.30 9,080.00 $ 300.00
Redondeo -
7 CUBIERTAS
7.1 SUMINISTRO E INSTALACIN CUBIERTA TEJA ONDULADA THERMOACUSTICA 0.83 X 3.05 M2 $ 50,147.00
ELABORO