Академический Документы
Профессиональный Документы
Культура Документы
Abstract: This document describes the physical processes and the corresponding equations
determining on-bottom stability of offshore cables. It presents an overview of DNV offshore
design code RP-F109 On-Bottom Stability Design of Submarine Pipelines. Finally, on-
bottom stability for a set of FO-cables, power-cables, an umbilical and a pipeline are
calculated with RP-F109 at different geographical locations around the world. Vital
parameters for on-bottom stability are briefly discussed.
1. INTRODUCTION
Increasing demand for communication,
control and monitoring of offshore oil and
gas fields has called for fibre optic (FO)
links connecting to stationary surface
plants, to land or intra-field. URC1-LW URC1 - SA
2
Lift:
FL = w D C L (U w sin ( p t ) + U C )
1 2
2
24 kV Power 145 kV Power dU w
Inertia: FI = w D 2 C M
4 dt
Figure 3. Power Cables Where w is water density (kg/m3), D is
pipe outer diameter (m), Uw is the velocity
of an oscillatory flow (m/s) with angular
frequency p(s-1), UC is the current velocity
(m/s), ws (N/m) is the submerged weight, u is
coulomb friction coefficient and CL, CD, CM are
the lift, drag and added mass coefficients.
difference on each side. The pressure temporary phase and a more permanent
difference is caused by current. Penetration operational phase:
varies with seabed type and is larger on Temporary Phase:
soft clay/loose sand than on hard For temporary phases with duration in
clay/dense sand. excess of three days and less than12
Three different approaches regarding on- months, a 10-year return period applies.
bottom stability may be followed (ref [1]). This condition may be approximated by
the most severe condition among the
1. Allowingaccumulateddisplacement: following two combinations:
Acertainmaximumdisplacementisallowed.
Underthisapproach,thepipewillbreakoutof 1. The10yearreturnconditionforwaves
itscavitymanytimesduringanextremesea combinedwiththe1yearreturn
state.Thedisplacementunderbothextreme conditionforcurrent.
andlesssevereseastatesmightaccumulate
damageanditisimportanttobeawareofthis. 2. The1yearreturnconditionforwaves
combinedwiththe10yearreturncondition
2. Nobreakout(VirtualStability): forcurrent.
Somesmalldisplacementisallowed,normally
Operation:
lessthanhalfthepipediameter.Inthis
For permanent operational conditions and
approachthepipewillnevermoveoutofits temporary phases with duration in excess
cavity.Thesesmalldisplacementswillbuildup of 12 months, a 100-year return period
resistanceduetomorepenetrationintothe applies. When detailed information about
seabedand/ortrenching.Noaccumulated the joint probability of waves and current
displacements. is not available, this condition may be
approximated by the most severe condition
3. Absolutestability:
among the following two combinations:
Alltheloadsarelessthantheresistance
1. The100yearreturnconditionforwaves
forcesandthereisnolateralmovement.
combinedwiththe10yearreturn
The first and the second method will only conditionforcurrent.
work if the oscillatory component of the
load forces is large enough to move the 2. The10yearreturnconditionforwaves
pipe. At large water depth, the wave combinedwiththe100yearreturn
induced oscillatory current is negligible conditionforcurrent.
and only a steady state current will act on
the pipe. If this current is large enough to
move the pipe, and it is conservatively
assumed that the current acts in one
direction only, displacement will
accumulate in one direction only. Under
these conditions absolute stability is the
only reasonable approach to follow.