Вы находитесь на странице: 1из 27

SNAPSH TS

OF KEY ASIA PACIFIC POWER MARKETS


2016
Preface
I am delighted to present to you the Snapshots of Key
Asia Pacific Power Markets, in which we provide an
overview of the electric power sector in 11 major
and developing economies in the region.

This booklet grew out of our 2014 Asia Pacific


Power Academy in which we undertook a series
of workshops and presentations on power project
development and financing for colleagues and clients.

In this 2016 edition, we include a summary of


new changes in power regulations and policies,
opportunities for foreign investors, changes
impacting power project development and recent
examples of major power transactions.

Each individual snapshot has been prepared by


Baker & McKenzie lawyers practicing in and advising on
electric power matters in that jurisdiction and is based
on an ongoing and wide familiarity with that market.

We hope you find this publication a useful resource


and that it helps you in framing the material issues
and trends relating to investment in the power
sector in these countries.

I encourage you to contact us if you have any


questions. Please refer to the key contacts section at
the end of this booklet.

Anne Hung
Partner, Tokyo
Disclaimer anne.hung@bakermckenzie.com
This publication is intended to provide a general overview on the matters of interest and
does not constitute legal advice.
You should seek legal advice before relying or acting on any of the legal information
provided herein.
Copyright 2016: Baker & McKenzie
First edition: November 2014
Snapshots of Key Asia Pacific
Power Markets Table of Contents
1
4
(by Market Model) MODEL

MODEL

3
1 Australia (Model 4) 6

2
1
GEN 1 IPP

MODEL
Paul Curnow and Robert Gough
TRANSMITTER

1
India (Model 3) 10
GEN 1 IPP

DISTRIBUTOR
MODEL GEN 1 IPP Samir Desai
TRANSMITTER
RET 1 RET 2

Indonesia (Model 2) 14
WHOLESALE DIST 1 DIST 2
PURCHASING
AGENT
Luke Devine, Kirana D Sastrawijaya and
CUST 1 CUST 2
RET 1 RET 2
GENERATOR

Anita Karina Sungkono


TRANSMITTER
CUST 1 CUST 2
TRANSMITTER
DIST 1 DIST 2

DISTRIBUTOR RET 1 RET 2 Japan (Model 1) 18


RETAILER CUST 1 CUST 2
Anne Hung, Ean MacPherson and Masahiro Tanabe

CUSTOMER
Laos (Model 2) 22
Source: Vietnam MW Co., Ltd Sawanee Sethsathira, Chavapol Akkaravoranun and
* The yellow shaded box represents common ownership.
Pranisa Chinkulkitniwat

Malaysia (Model 2) 26
MARKET MODEL 1 Mark Lim and Faez Abdul Razak
Most regulated model where generation, transmission, distribution and retail of electricity
are conducted by the same entity, often a government monopoly or a regional monopoly by Myanmar (Model 2) 30
a public utility. John Hancock

MARKET MODEL 2 Philippines (Model 3) 34


Less regulated model where the private entities can generate and sell electricity to a central Felix Sy and Alexis Cimagala
governmentowned utility through a power purchase agreement. The government utility will
transmit to regional government/publicly owned distributors and retailers who will provide
electricity within its local market.
Taiwan (Model 2) 38
Tiffany Huang and Julia King

MARKET MODEL 3 Thailand (Model 2) 42


Further deregulated model where private generators and IPPs can sell electricity to a central Sawanee Sethsathira, Napas Na Pombejra
governmentowned transmitter or a regional government/publicly owned distributor or retailer
who will provide electricity within its local market.
and Pattadon Tejapaibul

Vietnam (Model 2) 46
MARKET MODEL 4 Chi Lieu Dang
Deregulated model where generation, transmission, distribution and retail are conducted by
separate entities, often being private or shifting toward privatization, and are freely traded.
SNAPSH TS
OF KEY ASIA PACIFIC POWER MARKETS
Australia
Installed capacity:
56,863 MW1 + 4,900 MW off-grid capacity
Market Model:
2016 Model 4

New changes in power sets out the governments The ACT Governments the state/territory level, Decentralized and Electricity demand and
regulations and approach to energy over 200 MW wind farm auction Victoria has released embedded generation: capacity issues: Demand
the coming years. The key was completed, with its Renewable Energy Rooftop solar is growing has been steadily falling
policies themes were increasing three projects receiving Roadmap (20% renewables rapidly in Australia. in Australia for a number
There have been a number competition, increasing 20-year feed-in tariffs. target by 2020); NSW Demand has historically of years with pressures
of very significant regulatory energy productivity and The successful project has a strong investment- been from the residential including increasing
and policy developments in investing in Australias developers are now focused Renewable Energy sector; however, the electricity prices, improved
2015: energy future. It has been seeking to implement Action Plan; Queensland commercial sector is energy efficiency, significant
criticized for its lack of and begin to operate the has committed to a 50% showing increasing uptake of rooftop solar
Australias Renewable acknowledgement of the projects. renewable energy target interest. It is further and the exit of some major
Energy Target (RET) was impacts of climate change by 2030; the ACT has expected that there will be energy users. In light of the
revised in June 2015 from on Australias electricity A number of major 100% renewable energy a rapid uptake of battery falling demand and excess
41,000 GWh to 33,000 future. LNG projects have target by 2025; and South storage in Australia capacity issues, the NEM
GWh of renewable energy recently come on line in Australia has released a as these technologies has forecast that 4,550 MW
by 2020. The revised RET The NSW government Queensland, including BG strategy paper aiming for progress. of capacity is intended to be
means approximately 23.5% committed to privatizing Groups USD20.4 billion AUD10 billion in low carbon withdrawn by 2022.2
of Australias electricity its electricity distribution Curtis Island project in generation investment by IFM Investors is looking to
generation must come from network (poles-and- May 2015. 2025. CEFC (debt financing) sell its interest in Pacific Pricing and metering
renewable sources by 2020. wires) following the and ARENA (grants) have Hydro for approximately reforms: Regulators are
March 2015 NSW elections. New opportunities for AUD2 billion. Australian looking at how the pricing
Australias carbon pricing also been retained and
Queenslands proposal foreign investors will continue to facilitate assets make up about and metering regulatory
scheme was abolished in to similarly privatize its 40% of Pacific Hydros frameworks may be
July 2015 and replaced by NSW poles-and-wires renewable energy
network was put on hold as investments. global earnings. Various reformed to help consumers
an Emissions Reduction privatization: The NSW
a result of the outcome of parties are reported to be improve their electricity
Fund (ERF). The ERF is a Government will offer
the Queensland elections in ACT Wind Auction II: preparing bids. efficiency.
AUD2.55 billion reverse 99-year leases of entities
early 2015. In August 2015 the ACT
auction fund that allocates that operate 49% of NSWs Recent changes that General investor matters:
Government announced
funding to projects that will Recent examples electricity distribution impact power project The falling Australian dollar
its second wind farm
reduce Australias carbon of major power infrastructure. It is (against the US dollar) means
emissions. Two rounds of expected the government
auction, due before the development projects in Australia have
auctions have been held
transactions will raise AUD20 billion
end of 2015 and expected
become relatively cheaper
to be approximately 200 There are a number of recent
in 2015, with 92.8 million The NSW government from the privatization. changes and trends that in 2015 for foreign investors.
MW of wind-generated
tonnes of carbon abatement recently finalized the capacity. Parties bid in a could impact power project Australias current foreign
Stronger renewables
having been purchased. The following: reverse auction, with the development by foreign legislation will be replaced
policy settings: Nationally,
next stage in the ERF will government awarding FiTs investors: with new legislation in
sale of Macquarie the revised RET requires
involve setting of emissions to successful projects. December 2015.
Generations coal-fired approximately 6,000 MW Decentralized generation:
baselines for large emitters of new renewable energy
including stationary energy. assets to AGL Energy for LNG in Queensland: The Australian Energy
USD1.5 billion; and capacity to be built by Regulator now provides
Queensland has opened
The federal government 2020. It is predicted guidance on how
sale of the 667 MW up a further 11,000 sq km
released its Energy White between 30 and 50 major prospective rooftop solar
Colongra gas-fired power for new LNG exploration
Paper in April 2015. This projects need to be built providers can obtain
station to Snowy Hydro for tenders in the southwest of
white paper is an important in the next five years, exemptions from license
USD190 million. the state.
policy document that requiring AUD40 billion requirements.
in new investment. At

1 This figure is the aggregate capacity of the National Electricity Market (NEM) and the South West Interconnected Systems (SWIS). The NEM consists of Queensland, NSW, Victoria, South Australia and Tasmania and has a capacity of 51,363 MW. The
SWIS covers southern Western Australia and has a capacity of approximately 5,500 MW.
2 Note: Withdrawal does not separately identify those units/stations for which there are plans to return it to the market in the future.

6 7
SNAPSH TS
OF KEY ASIA PACIFIC POWER MARKETS
Australia
Installed capacity:
56,863 MW + 4,900 MW off-grid capacity
Market Model:
2016 Model 4

Electricity market Significant investment in Financial barriers to community opposition to


trend for the near LNG export terminals, investment: challenge wind farm developments MAIN PLAYERS, INCLUDING
particularly in Queensland in obtaining a power in parts of Australia; and
future (although there are purchase agreement
Grid connection: ACTIVE FOREIGN INVESTORS
Investment in the near future currently restrictive (PPA), which is critical
regulatory arrangements for funding. Currently grid access can be a
will be largely in renewables, significant cost or barrier.
predominantly in wind and for gas exploration). limited or expensive
solar. Any investment in project financing
baseload power likely to be Requirements for public available; and
gas. bidding for greenfield Key local players
Decreasing demand
General trends include the
projects in electricity: there
following: Generally, there are no has been a decrease integrated retailers and
Electricity demand is
requirements, as generation in electricity demand generators (e.g., AGL, Origin
in most states/territories has in Australias eastern
expected to plateau (rather states for the past few
Energy, ERM Power);
been privatized.
than fall) this year, due years. large thermal generator owners
mainly to LNG projects Main issues for foreign and operators (e.g., Stanwell
coming in and population investors Typical hurdles for
growth. Demand had been a power project Corporation, Synergy); and
falling in the last few years Complexity of regulatory
developer renewable energy generators
mainly due to increased environment: Australias (e.g., SnowyHydro, HydroTasmania,
electricity prices, improved energy market is highly Lack of available finance,
energy efficiency, regulated and is (unusually due to excess capacity Infigen Energy).
significant uptake in within the Asia Pacific and falling electricity
rooftop solar and the exit region) a merchant demand;
of some major energy market with little vertical
users (e.g., the closure of integration of power Ability to obtain a PPA:
a number of aluminium utilities; and difficult to negotiate a
smelters); PPA with the integrated
FIRB notification or retailers that dominate
Certain jurisdictions are approval: generally not the market;
undertaking or considering an issue (and required to Key foreign investors
privatization of aspects of respond within regulated Project planning and
their electricity networks. timeframe). development: recently integrated retailers (e.g.,
there have been changes
A number of existing Issues that face both local and in some states that
EnergyAustralia, GDF Suez);
large coal-fired power foreign investors include the limit areas where large thermal generator owners and
stations have been following: wind projects can be operators (e.g., RATCH Australia);
decommissioned (or developed, and also
mothballed) recently, and Regulatory risk: e.g.,
regulatory changes in
renewable energy project developers
a number of coal and gas changes to rebates and (e.g., Neoen, Fotowatio Renewable
some states that limit
feed-in tariffs, uncertain
project proposals have
future of the CEFC and
ability to undertake Ventures, Union Fenosa Wind
been withdrawn; and exploration for gas.
ARENA; Australia and Tesla); and
There has been some
turbine manufacturers and developers
(e.g., GE, Siemens, Goldwind).

8 9
SNAPSH TS
India
Installed capacity:
278,733.62 MW
OF KEY ASIA PACIFIC POWER MARKETS (108,107.67 MW, 39% private)
2016 Market Model:
Model 31

New changes in power of India Ltd (SAIL). 2013. Of the total Singapore, with over also agreed to invest Recent changes that
regulations and policies The Environment investment amount, 242 MW of operating about USD2 billion in impact power project
The government of Ministry has permitted USD19 billion will be wind assets and 170 a joint venture with development
India has announced the transfer of contributed by the MW of assets under the Adani Group to Other than the push
a renewable power environmental state-owned Power construction. manufacture solar for renewable energy
production target of clearances granted to Grid Corporation of Enel Green Power power equipment. production, there have
175,000 MW by 2022, prior allottees to the India. acquired a majority New opportunities for not been any recent
consisting of 100,000 new allottees without Recent examples stake in wind and foreign investors changes of significance
MW from solar power, the need for a new of major power solar operator Foreign direct that have materially
60,000 MW from wind, approval request. transactions BLP Energy for investment in the impacted power project
10,000 MW from The government is Conventional power: approximately EUR30 Indian power sector development in India.
biomass and 5,000 MW working on creating a Jaiprakash Power million. BLP claims was approximately The state electricity
from small hydro. mechanism to address Ventures Ltd (JPVL) 772 MW of wind power USD9.7 billion from distribution companies
Under the Coal Mines stranded gas-based agreed to sell two projects in operation April 2000 to May have about USD39
(Special Provisions) generation in 2016 and hydropower projects or at various stages of 2015. billion in losses.
Ordinance 2014, in 2017 by the provision in Himachal Pradesh development. Investment Their financial health
2015 the government of subsidies for the to JSW Energy for Japans SoftBank opportunities for remains a critical
conducted three rounds import of liquefied about USD1.5 billion. announced plans to foreign investors are concern.
of auctions for the natural gas. invest USD20 billion in mostly expected to Investors continue to
JSW Energy
reallocation of coal Investments of reportedly has 20 GW of solar energy be in the renewable look for certainty of
blocks following the about USD35 billion agreed to acquire projects in India, energy field as regulation (tax policy,
ruling of the Supreme are proposed the 500 MW Bina together with Indias the government electricity regulation,
Court of India that to improve the Thermal Power from Bharti Enterprises has announced a etc.), stable fiscal and
previous allocations transmission sector Jaiprakash Power and Taiwans Foxconn renewable power monetary policies, and
between 1993 and to address chronic Ventures for about Technology Group. production target of a predictable legal
2010 were illegal. So transmission and USD528 million. SunEdison Inc. plans 175,000 MW by 2022, framework respectful
far, 34 coal blocks distribution losses and to invest USD15 consisting of 100,000 of commercial
Renewable power:
have been auctioned, aggregate technical billion in India by 2022 MW from solar power; practices and
while the rest have and commercial SunEdison signed a 60,000 MW from wind; contracts.
to develop solar and
been given to public losses, which were definitive agreement 10,000 MW from
wind projects with a
sector companies 23.04% and 25.38% to acquire Continuum biomass and 5,000
total capacity of 15
such as NTPC Ltd respectively in Wind Energy, MW from small hydro.
GW. SunEdison has
and Steel Authority

1 India displays the characteristics of Model 3 as a predominantly single-buyer model. Under Indias federal structure, intra-state distribution companies are owned and regulated by several states rather than on a unitary basis by the Central
Government of India.

10 11
SNAPSH TS
India
Installed capacity:
278,733.62 MW
OF KEY ASIA PACIFIC POWER MARKETS (108,107.67 MW, 39% private)
2016 Market Model:
Model 31

Electricity market trend Power procurement by state distribution of elective over large rural areas, inadequate
for the near future entities goes through a process
of competitive bidding on
energy to households,
industrial, commercial and
investment in distribution system,
improper billing and high pilferage.
MAIN PLAYERS, INCLUDING
Electricity demand growth is
expected to be 10 to 12% per
tariff (except for hydro and other users Gencos have little control. ACTIVE FOREIGN INVESTORS
renewables). There are two
year until 2017. power trading Distribution companies (about 95%
cases:
of the distribution network are state
The target for power capacity The main issues for foreign
Case 1 contemplates an open bid boards) also conduct regular load
addition during the 12th Plan investors are essentially
where the developer has to select shedding and intentional blackouts
period (up to 2017) is 88,000 MW. the same as those for
the fuel, location and technology in certain areas to manage demand. Government bodies:
The country added 12,510.4 MW Indian developers: cost of
of the proposed project. The
funds, credit-worthy power Coal is the most common fuel but
in 2014 to 2015 (until 15 January developer is also responsible for
purchasers, land acquisition is in very short supply domestically.
Central institutions like National
2015). obtaining all relevant approvals. Thermal Power Corporation Limited
and fuel supply. Imports are feasible but expensive,
However, a significant amount Case 2 involves bidding on the and they upset the power purchase (NTPC) and the State Electricity
of capacity is stranded owing basis of a fuel and location Typical hurdles for agreements and tariffs that were Boards (SEBs) continue to dominate
to the non-availability of gas. specified by the procuring a power project designed around cheaper, domestic the power sector in India. NTPC is
Currently, Indias gas-based entity. Government support developer coal.
Indias largest power producer.
capacity is about 27,123 MW, is to be provided in obtaining
with 14,305 MW being stranded The key problems hindering the Gas is comparatively expensive Power Grid Corporation of India
the necessary clearances and
growth of the power sector in to deliver to generators in India,
(i.e., operating at zero plant approvals and fuel supply. is the single largest transmission
load factor or PLF) with India include cost recovery, land primarily due to infrastructure
Main issues for foreign acquisition, fuel, environment constraints. utility in India.
the remainder operating at
approximately 30% PLF. investors and forest clearances. Barriers to entry are high in the
Most state power purchasers transmission and distribution
Requirements for public Foreign Direct Investment up to
segments, which are largely state
100% is permitted in the power (discoms in unbundled states
bidding for greenfield and SEBs in states that have monopolies.
sector, under the automatic
projects foreign investment route, for the not unbundled) have poor
The central government, through following: credit owing to large losses and Local companies:
the Power Finance Corporation, high debt (although a few are
generation and transmission profitable). Tariffs are politically Reports indicate that Adani Power is now Indias
has established a program for of electric energy produced
the development of ultra mega sensitive, as are subsidies and largest integrated power company with gross
in hydro electric, coal/lignite- other cost-related power supply
power projects (UMPP), each based thermal, oil- based arrangements.
power generation capacity of 8,620 MW.
delivering 4000 MW, located at thermal and gas-based
coal pits or on the coast. In addition, the average Tata Power is also a significant market participant
thermal power plants
Four UMPPs have been awarded transmission and distribution with a rival claim to being Indias largest private
renewable/non-conventional losses (T&D) exceed 25% producer, with 8,623 MW.
(three to Reliance Power and energy generation and
one to Tata Power); there are of total power generation
12 others in the pipeline. The
distribution compared to less than 15% for Reliance Power claims 6,000 MW of operational
government has announced developing economies. The T&D power generation assets.
plans to auction five new UMPPs. losses are due to substantial
energy sold at low voltage,
sparsely distributed loads Foreign companies:
India has only two foreign players operating
power plants: AES of the US and China Light and
1 India displays the characteristics of Model 3 as a predominantly single-buyer model. Under Indias federal structure,
intra-state distribution companies are owned and regulated by several states rather than on a unitary basis by the
Power (CLP). AES maintains a plant in Odisha.
Central Government of India. CLP is focused on renewable energy projects.
12 13
SNAPSH TS
OF KEY ASIA PACIFIC POWER MARKETS
Indonesia
Installed capacity:
53,535 MW (electrification ratio of 86.39%)

2016
Market Model:
Model 21

New changes in power The program consists of power Recent examples greenfield infrastructure plans for On 15 July 2015, the President developed through a PPP
plants with renewable energy, Indonesia, including in the power issued a new regulation scheme, the introduction
regulations and policies i.e., geothermal and hydro power
of major power sector. providing a central government of a direct appointment
In April 2015, the President plants, as well as coal-fired transactions guarantee for infrastructure mechanism and expanding
power plants with more efficient The introduction of the 35,000 financing. This guarantee can the types of investment return
announced a plan to develop Rajamandala 1x47MW
technology and gas-fired power MW Program and the extension be granted to international schemes that can be adopted
35,000 MW of new electricity hydro power project - This
plants. The government also of the Second Fast Track development finance in structuring PPP projects.
generation projects until 2019. is the first major power
extended the regulation on the Program will provide a lot of institutions (i.e., multilateral Specifically in the power
This plan is also a part of the project in Indonesia in recent
business viability guarantee opportunities for IPP developers, and bilateral foreign financial sector, the PPP scheme now
PLNs 2015-2024 Power Supply years to successfully raise
letter to support the Second Fast especially foreign investors. PLN institutions such as JBIC, can also be used to develop
Business Plan. For this program, international limited recourse
Track Power Program. has also announced plans to ADB and the World Bank) with power substations, in addition
PLN will build power plants to project financing without the procure more gas-fired power respect to loans (i) made by to power plants and power
produce around 10,000 MW of Government of Indonesia
In 2015, the MEMR issued plants. those institutions to eligible transmission infrastructure.
electricity. The remaining capacity providing a business viability
Regulation No. 3 of 2015 on borrowers in the form of
will be offered to independent guarantee. The guarantee for The government has taken
direct selection and direct state-owned enterprises and On 9 September 2015, the
power producers. Moreover, these this project was provided by steps to encourage the
appointment process by PLN. the state-owned infrastructure Minister of Finance issued
projects are estimated to require the Multilateral Investment development of power plants
The regulation provides ceiling financing company (PT Sarana a new regulation on debt
aggregate investments of more Guarantee Agency (MIGA). using renewable resources
benchmark tariffs for the same Multi Infrastruktur), and (ii) to equity ratio (DER) for
than IDR1,100 trillion (around Sponsors of the project are (e.g., geothermal, wind farm
projects. which are for the funding companies to calculate income
USD78 billion). Kansai Electric Power Co. and hydro).
of qualified infrastructure tax. Under the new regulation,
At the same time, the MEMR also and PT Indonesia Power (a the maximum allowable DER
The new Geothermal Law was
issued a new regulation on power subsidiary of PLN). Recent changes that projects.
for income tax purposes is 4 to
issued in September 2014 to
replace the 2003 Geothermal Law.
wheeling, which allows power impact power project Land acquisition issues remain 1. This new rule will become
suppliers with franchise areas Samas 50 MW wind power
Under the new law, geothermal
to cooperate with each other plant - PPA was executed in development one of the major obstacles in effective on 1 January 2016 and
activities are no longer classified infrastructure development. is not applicable for companies
for electricity supply in their May 2015. This is the first PPA In June 2015, Bank Indonesia,
as mining activities and can The newly issued Presidential engaging in the infrastructure
respective areas without tender. for a wind farm power plant in the central bank, issued a
be conducted in conservation Regulation No. 71 of 2012, which sector. However, the regulation
It also regulates the procedures Indonesia. new regulation requiring the
forest area. The new law also is an implementing regulation does not provide further
for leases of transmission and mandatory use of rupiah in of the Land Acquisition Law, criteria or explanation on
recentralizes the authority over Sumsel-10 1x600MW mine
distribution lines. transactions (with payments in allows and facilitates direct land what is meant by companies
licensing for geothermal power mouth coal-fired power
project - This project will cash and non-cash) conducted procurement by private entities. engaging in the infrastructure
generation to the Minister of On 29 June 2015, the MEMR
be the largest mine-mouth in the territory of Indonesia. The However, private entities will sector.
Energy and Mineral Resources issued a new feed-in-tariff
project in Indonesia and it is regulation states that strategic act as proxies of the relevant
(MEMR). In June 2014, the regulation for mini hydro power
infrastructure projects may be government institution or In April 2015, the government
government also issued a revision projects (having capacity of up to implemented using the public
exempted from the requirement BUMN. issued a new regulation
to the geothermal pricing regime. 10 MW). The previous regulation, private partnership scheme.
if approved by Bank Indonesia. on income tax facility. The
The new regulation reverts to a which featured rupiah-based
Hasang 3x13MW run-of-river However, until this date it is still In March 2015, the President income tax facility is available
geographically based tariff regime, tariffs, has been criticized by the
hydro power project in North not clear how this exemption issued a new regulation on for new projects as well as
but this time enhanced with an industry as having been set too
Sumatra, Indonesia. The PPA can be obtained. Pending the public private partnership expansions of existing projects.
added dimension of the timing low. The new regulation sets the
was signed on 19 August 2015. issuance of further guidelines (PPP). The new regulation The facilities are available for
of achieving the commercial tariffs in US dollar terms and
from Bank Indonesia and the introduces some key changes power generation projects with
operation date. generally increases the tariff
levels. PLN is also preparing a
New opportunities for MEMR, tariffs for PPAs and to PPP implementation rules a minimum investment value of
other project documents (e.g., in Indonesia, including the IDR30 billion or a minimum of
The Second Fast Track Power
new model PPA for mini-hydro foreign investors inclusion of new types of 100 employees.
Program, which was introduced onshore EPC contract) must
projects. Although tariff is set infrastructure that can be
in 2010 and was set to expire on Since taking office in 2014, be paid in rupiah although the
out in US dollars, payment of the
31 December 2014, has been President Joko Widodo has price might be indexed to the
invoice is in Indonesian rupiah.
extended until 31 December 2019. announced very ambitious USD - rupiah exchange rate.

1 State-owned PLN responsible for generation, transmission and distribution. PLN also purchases electricity from IPPs and surplus power from captive power producers.

14 15
SNAPSH TS
OF KEY ASIA PACIFIC POWER MARKETS
Indonesia
Installed capacity:
53,535 MW (electrification ratio of 86.39%)

2016
Market Model:
Model 2

Electricity market Indonesia also has potential Main issues for Typical hurdles for
trend for the near reserves for the development foreign investors a power project MAIN PLAYERS, INCLUDING
future of geothermal and hydro developer
power projects. The PLN has relied upon ACTIVE FOREIGN INVESTORS
The PLN Business Plan government also recently government subsidies Land acquisition can
indicates that up to 2024, increased the feed-in-tariff to partially cover the potentially cause delay
approximately 63.7% of for mini hydro projects and gap between costs and in financial close and
generation will be from coal, issued a new geothermal law. revenues. project completion,
19.2% natural gas (including mostly due to the land
A new regulation for power Government guarantee The main player is PLN, being the
LNG), 9% geothermal, 6.6% price issue.
wheeling was also issued in is generally not state utility company responsible
hydro, and 1.5% oil and other for generation, transmission and
2015. available. Sponsors agreement
fuel. distribution of power in Indonesia.
prevents a change in
Requirements for Foreign EPC limitations
Indonesia is one of the the shareholders of the Active foreign investors in power
public bidding for exist where certain
worlds largest coal exporters project company until at generation are mainly Japanese
types or capacity of
and has substantial coal greenfield projects least 5 years after COD, (Mitsubishi, Marubeni, Sumitomo,
power project can only
reserves that enable it to PLN holds and organizes restricting a party from Mitsui, J-power, Itochu, Kyushu Electric)
be undertaken by EPC
support the development of competitive public bidding. immediately exiting the and Korean (Korea Midland Power,
companies established
mine mouth power projects. project. Kepco, Posco and Samtan).
in Indonesia.
The recent regulatory Only in certain
circumstances may a power Forestry license could The rest are European (GDF-Suez),
development indicates that Local content
take years to obtain American (Chevron), Australian (Origin
the government encourages project be undertaken requirements for the
due to a complex Energy), Indian (Tata Power, Madhucon)
the development of mine- without a public bidding, provision of goods
bureaucratic system in and Chinese (China Huadian).
mouth power projects. including: and services to power
the Ministry of Forestry.
projects must meet a
The government also power projects using
certain level of local
issued a new regulation on renewable energy source
content.
direct selection and direct or local energy source
appointment process for (e.g., mine mouth and
PLN. The regulation provides marginal gas) Other potential investors such as EGCO
a simplified and shorter local electricity system and Ratchaburi Electricity (Thailand),
direct appointment and Malakoff (Malaysia), lectricit de
in crisis or in the state of
direct selection process and France (France), Daelim and YPP
emergency; or
ceiling benchmark tariffs for Corp. (Korea), Steag (Germany), Jindal
the purchase of power from capacity expansion of and Lanco Infratech (India), CMEC,
mine-mouth power plants, already operating power Sinohydro, Shanghai Electric (China),
coal-fired power plants, projects Gas Natural Fenosa and Abener Energia
gas power plants and hydro (Spain) also indicated their interests
in power projects in Indonesia by
power plants.
participating in pre-qualification process
and/or bids for power projects.

16 17
SNAPSH TS
OF KEY ASIA PACIFIC POWER MARKETS
Japan
Installed capacity:
287,000 MW
Market Model:
2016 Model 1 moving toward Model 4

New changes in power is expected in 2016 In April 2015, Tokyo Japan and construction Recent changes that OCCTO, the new
regulations and policies and unbundling of the Electric Power (TEPCO) of various foreign-owned impact power project organization established
transmission sector is and Chubu Electric large-scale solar projects development as the first step of
The Renewable Energy
expected by 2020. Power announced is now in progress. the electricity market
feed-in tariff (FIT) Local banks were
the establishment of reform, is planning to
program introduced in In July 2015 a government Foreign investors can traditionally reluctant
a new joint venture increase the capacity of
July 2012 has led to a panel officially accepted a also develop biomass, to finance foreign-
company JERA, which cross-regional electricity
boom in commercial- new proposed energy mix geothermal and other sponsored power
will procure LNG for transmission. These
scale solar projects. This for 2030. The proposal renewable energy projects. However, a
both power companies measures may facilitate
has caused problems for aims to increase the projects. The FIT rates number of foreign-
and is expected to be more renewable energy
utilities to connect all share of nuclear power set for these renewable sponsored large solar
one of the largest LNG project development
proposed solar projects. to close to the pre- energy sources are projects have now
buyers in the world. in various regions. In
New measures enabling Fukushima level (20-22%) expected to be maintained secured project financing
JERA will also own August 2015, OCCTO
more utilities to impose and to double the share at a rate favorable enough from local banks. This
most of the overseas announced its plans to
unlimited curtailment of renewable energy to to attract investors. trend is expected to
power assets of the increase the capacity of
on new projects without 22-24% continue in the coming
two utilities, making it The regional monopoly the frequency converter
compensation were Recent examples currently enjoyed by years.
a significant player in station in Shizuoka, which
therefore introduced in of major power Japanese utilities will
the international power The new FIT regulations is the intersection point of
January 2015 which have transactions be abolished in 2016,
market. implemented in the two frequency regions
resulted in a slowdown in resulting in the opening January 2015 allow in Japan.
the growth of new solar More mega solar power New opportunities for
up of a market worth 7.5 utilities to impose
projects. plants are being built. foreign investors Cultural and language
trillion yen. Both local unlimited curtailment
A number of plants barriers undermining
In April 2015, a new Foreign investors can and foreign investors on new projects without
over 100 MW in size successful business
organization named the develop commercial- will be able to enter the compensation in certain
were scheduled to start practices continue to exist
Organization of Cross- scale solar projects electricity retail market designated regions,
operation in late 2015 and in Japan. However, Japan
regional Coordination of by acquiring project in 2016. Various foreign including Hokkaido,
construction of one plant is taking steps to change
Transmission Operators approvals granted in electricity retailers Tohoku and Kyushu. As a
over 400 MW was planned into a more friendly place
(OCCTO) was established the first three years and generators are result, the development
to start in late 2015. for foreign visitors in
to coordinate cross- of the FIT program reported to be seeking and financing of solar
preparation for its hosting
regional electricity Increasing numbers of and by taking such opportunities in the power projects in these
of the upcoming 2020
transmission as part of coal-fired power plants projects through to Japanese power market regions has become more
Olympics. This cultural
a three-step electricity are being built. During construction and including in partnership difficult.
change may facilitate
market reform process. 2015, more than 40 plants operation. Numerous with Japanese companies.
foreign investors in doing
Full retail liberalization were reported to be foreign companies are
business in Japan.
planned for construction. now actively pursuing
solar power projects in

18 19
SNAPSH TS
OF KEY ASIA PACIFIC POWER MARKETS
Japan
Installed capacity:
287,000 MW
Market Model:
2016 Model 1 moving toward Model 4

Electricity market In August 2015, TEPCO Renewable energy


trend for the near announced the winning projects located some MAIN PLAYERS,
future bidder for its five thermal distance from the
power plant projects. This grid often face the INCLUDING
With the favorable FIT in
place, renewable energy
public tender was the
second tender for TEPCO
issues of high cost
and time delays due to
ACTIVE
projects will be further
developed.
following the one in 2012. the need to construct FOREIGN
TEPCO plans to conduct transmission lines for
New entrants will come additional tenders in the connecting with the grid. INVESTORS Key local players:

into the Japanese power near future. 10 regional utilities and J-Power
Renewable energy
market as a result of the Some IPPs (e.g., Marubeni)
Typical hurdles for a projects in the
EPC contractors in both conventional
electricity market reform power project developer Hokkaido region are
measures. and renewable power such as Sumitomo,
facing bottlenecks due
Various land issues have to lack of electricity Mitsubishi, Hitachi, Mitsui, Sharp etc.
New conventional power confronted renewable demand, limited Sharp, Kyocera, Panasonic, etc. as
baseload power facilities energy projects, which transmission capacity manufacturers of solar modules
will be constructed to include: to the mainland battery Various new local renewable energy entrants
compensate for the
continued closedown of (a) tight controls on and curtailment building commercial-scale solar plants
nuclear facilities. agricultural land that requirements.
generally forbid them New IPPs often
Participation by foreign from being used for
investors in the Japanese face challenges in
electricity projects; acquiring suitable sites
electricity market will
further expand. (b) restrictions against and environmental
development of forest permission (including
Requirements for public land, including on the proposed new strict
bidding for greenfield total percentage of controls on coal-fired
projects tree areas that may plants).
Several public tenders be cut to develop the
for new conventional land; and Foreign investors include numerous foreign
power plants are currently renewable energy developers such as
(c) difficulty in finding
underway pursuant Pacifico, Gestamp Solar, Sun Edison and
large areas of vacant
to the 2012 guidelines others, module suppliers such as Trina,
land due to Japans
introduced by the Japanese high population
Yingli and Canadian Solar, foreign investment
government to require density, mountainous funds and foreign EPC contractors.
local utilities to hold public terrain and existing
tenders when building intensive use of non-
thermal power plants mountain areas.
with new or replacement
capacity of 1 MW or more.

20 21
SNAPSH TS
OF KEY ASIA PACIFIC POWER MARKETS
Lao PDR
Installed capacity:
3,200 MW
Market Model:
2016 Model 22

New changes in power The Minister of Energy Don Sahong Dam more completed hydropower industry). Conversely, it is consulting services (legal,
regulations and and Mines announced the projects by end of 2019. Other worth noting that Lao PDR technical, financial and
In September 2015,
policies government is aiming for investment opportunities does not have adequate environmental advisory)
government approved
95% of households to have are still broadly available to amount of petroleum to the agencies of the
There has been no significant concession agreement
access to electricity by foreign investors. reserves. All petroleum Lao PDR Government.
change in the regulations. for the Don Sahong Dam
the year 2020 (from 89% products need to be Products stemming from
However, a number of small (260 MW) with Malaysian The government is actively
currently). imported (currently 70% such consultations may
developments in the energy developer Mega First trying to pursue its plan to
from Thailand and 30% potentially have a major
policies and regulations Recent examples Corporation Berhad.3 become the major source
from Vietnam). impact on the hydropower
of Lao PDR have been put of major power of power supply to the
The project has yet to be IPP process and thus shall
in place to ensure that the transactions approved by the Mekong
ASEAN Power Grid (Battery Recent changes that be closely monitored by
power industry (particularly of Asia) and still targeting impact power project
Xayaburi Hydroelectric River Commission, an investors.
the hydropower sector) is to increase the installed development
Power Project intergovernmental body
sustainable in the longer capacity from 3,200 MW Due to increased experience
made up of Thailand, The government has
term. One of the Mekong currently to 12,500 MW by in developing power
Cambodia, Laos and recently demonstrated
cascade hydropower 2020. projects and the growing
The Centre for Regulatory Vietnam supervising its commitment in
projects, with maximum pressure from the public
Impact Assessment for development along Open policy for foreign setting standardized
capacity of 1,260 MW. and NGOs, the Lao PDR
Draft Legislation was Southeast Asias main investors procedures concerning Government is enforcing
established to assess the Project was suspended waterway.4 the development,
Other than its hydropower environmental requirements
impact of draft legislations in 2012 due to heavy Construction is expected sector, Lao PDR also implementation and more strictly. Examples are
on the private sector prior criticisms from to begin end of 2015. possesses high potential monitoring of hydropower as follows:
to official enactment. environmental groups. for biofuels production. projects.
Work has resumed New opportunities for Although access to
Employment of foreign
The government is aiming The Ministry of Energy experts to study the
and as of August 2015, foreign investors electricity is on the rise,
to improve and expand and Mines has received impact on certain species
actual accumulated work Up until July 2015, the energy use in the country
transmission networks financing from the World of animals prior to
progress is 49%. government of Lao PDR is still mainly in the form
to facilitate growth and Bank to service the cost approving projects.
integration of the power Project is developed by approved domestic and of traditional fuels (use of of technical assistance
sector among ASEAN Xayaburi Power Company foreign companies to invest biomass such as wood and for capacity building Impose a requirement

countries via power Limited, a subsidiary of in 357 hydropower projects charcoal).5 in the hydropower and for developers to conduct
exchange programs. the Thai construction with a total generating mining sectors and fees thorough environmental
Lao PDR also has abundant
Transmission lines company Ch. Karnchang capacity of 26,147 MW. Local for consulting services. study to cover
coal reserves estimated
connecting central Lao Public Company Limited, and central governments Consulting firms were environmental impact on
to be sufficient to cover
PDR to the southern at an estimated USD3.8 signed MOUs aiming to invited to indicate their nearby rivers and canals
domestic demand for coal
provinces are expected to be billion. achieve the goal of having 45 interest in providing rather than just the main
(mainly used in cement
completed by early 2016.2 water source.

1 In Laos, (a) majority of generators are privatized (IPP, which usually required to co-invest with investment arms of the state [e.g., Electricite du Laos and Lao Holding State Enterprise]); (b) the state is the purchasing agent that solely purchases
electricity from the generators; and (c) transmission, distribution assets and retail businesses are owned by the state (Electricite du Laos)
2 Department of Energy Policy and Planning, Ministry of Energy and Mines, Lao P.D.R., 2015
3 The Diplomat (September 2015), available at http://thediplomat.com/2015/09/laos-officially-approves-controversial-dam-project/
4 Open Development, Mekong (October 2015), available at https://opendevelopmentmekong.net/ngos-push-for-postponement-of-don-sahong-dam-on-mekong/#!/story=post-905010&loc=13.9529784,105.9582884,7
5 International Energy Agency (2014), available at https://www.iea.org/media/technologyplatform/workshops/southeastasiabioenergy2014/Laos.pdf

22 23
SNAPSH TS
OF KEY ASIA PACIFIC POWER MARKETS
Lao PDR
Installed capacity:
3,200 MW
Market Model:
2016 Model 2

Electricity market Main issues for foreign Opposition from


trend for the near investors environmentalists: MAIN PLAYERS, INCLUDING
Mekong River is
future Limited access to relevant environmentally important ACTIVE FOREIGN INVESTORS
Future investment official regulations as it provides a range of
trends are likely to and inconsistency of wetland habitats and is
be predominantly publications by different one of the worlds largest
hydropower. In August governmental agencies; no inland fisheries.
2015 , the Lao Government centralized system
Agreement with riparian
approved 357 hydropower Limited precedents on countries: In 1995, Laos,
development projects with enforcement of security Thailand, Cambodia and
an estimated generating interest Vietnam established EGAT International Co., Ltd (Thai)
capacity of 26,147 MW (and the Mekong River Electricity Generating Public Company
approximately 115,118 Vagueness of regulations:
Commission (MRC) to Limited (EGCO) (Thai)
million KW per hour). Majority of the laws and
assist with management
The Lao Government has
regulations are drafted with
and coordinated use of the Ch. Karnchang (Thai), through subsidiary
sophisticated language, CK Power Public Company Limited
entered into MoUs with Mekongs resources. An
making regulatory
various local and central example is the Xayaboury Ratchburi Electricity Co.(RATCH) (Thai)
framework unclear and
governments to develop 45 project in which USD200
difficult to interpret. This
million worth of additional China International Water and Electric
more hydropower projects issue persists despite the
by 2019. This will result costs were incurred by Corporation (China)
establishment of the Centre
in 74 hydropower projects for Regulatory Impact
the Lao Government and Sinohydro (China)
(with a total generating developers to comply with
Assessment for Draft
MRC recommendations.6
Vietnam-Lao Power Joint Stock Co.
capacity of 10,000 MW Legislation, whose main
per year and production (VLPC) (Vietnam)
mission is to assess the
capacity of approximately impact of draft legislation
50,000 KW per hour) by the on the private sector.
year 2019.
Typical hurdles for a
Requirements for
power project developer
public bidding for
greenfield projects Relocation of inhabitants
from the project site
Lao government does not do (especially for hydropower
public bidding. Applications projects, which require
are sent to the competent large areas of land)
governmental agency, which
will be considered on case-
by-case basis.

6 Department of Energy Policy and Planning, Ministry of Energy and Mines, Lao P.D.R., 2015

24 25
SNAPSH TS
OF KEY ASIA PACIFIC POWER MARKETS
Malaysia
Installed capacity:
25,987 MW1
Market Model:
2016 Model 22

New changes in power The revisions to directly awarded The government is for solar projects as The Green Technology
regulations and policies the feed-in-tariff to 1Malaysia studying the impact of it seeks to develop Fund Scheme has
Following the degression rates in Development Berhad using nuclear fuel as up to 200 MW of been extended from 31
relation to biomass, (1MDB) a fuel source. If viable, solar farms annually December 2015 to 31
introduction of the 11th
biogas and solar there will be a need beginning 2016. December 2017.
Malaysia Plan,3 one of The sale of 1MDBs
the key focus areas is photovoltaic, which stake in Project for foreign companies Recent changes that The government is
pursuing green growth was proposed in 2014, 3B to TNB. Project with nuclear expertise impact power project committed to increase
for sustainability and also became effective 3B was originally and capabilities in development the development and
resilience. These as of January 2015. awarded to the the development of a There have not been usage of renewable
include exploring new The purpose of the consortium of 1MDB nuclear plant. many changes to energy and will release
revision is to make and Mitsui & Co. the power sector but 100MW capacity a
renewable energy The Sarawak State
RE more attractive to via an open tender those which could year for net metering
(RE) resources (e.g., Government is
developers and reflect process and marks notably impact power energy. Net energy
geothermal) and increasing its efforts
the lower technology the first involvement project development metering allows
enhancing the capacity of a foreign investor to harness the state's self-consumption of
and capability of cost. by foreign investors
in a Malaysian IPP abundant hydropower electricity generated
human capital in the Recent examples include:
project. potential and plans by solar photovoltaic
RE sector. of major power to construct several Foreign equity system users, while
transactions New opportunities for
The Malaysian dams. restrictions for large selling the excess
foreign investors
government is IPP Project 4A (1,000 IPP projects appear energy to utility
The RE sector is Green Technology to have been relaxed
committed to to1,400 MW gas-fired companies and this
steadily growing with Fund Scheme A whereby foreign
rationalizing energy plant) being directly may interest foreign
awarded to the new feed-in-tariff MYR3.5 billion fund to investors appear investors who have
subsidies. The move
consortium of Tenaga (FiT) capacity quotas improve supply and to be able to own operations in Malaysia
toward market-based
energy pricing will Nasional Berhad being issued twice utilization of green up to 49% equity in which rely on large
also continue to (TNB) and SIPP a year. However, technology. the IPP company usage of electricity (i.e.
supplement these Energy there is a 49% equity instead of 30% factory, plant) as a way
The Malaysian
efforts. restriction for foreign previously. to minimize costs.
IPP Project 4B government is thinking
(2,000 MW gas- investors under the of introducing utility-
fired plant) being FiT regime. scale quota auctions

1 As at end 2014, Peninsular Malaysia = 21, 060 MW, Sabah = 1, 404MW and Sarawak = 3, 523 MW.
2 Only the generation sector is open to IPPs.
3 The Malaysia Plan is an economic development plan for the country which is revised every five years.

26 27
SNAPSH TS
OF KEY ASIA PACIFIC POWER MARKETS
Malaysia
Installed capacity:
25,987 MW
Market Model:
2016 Model 2

Electricity market for less than 49% equity Typical hurdles for and O&M companies.
trend for the near shareholding by foreign a power project That said, obtaining MAIN PLAYERS, INCLUDING
future entities in the IPP. developer financing locally, either
through loans or the
ACTIVE FOREIGN INVESTORS
The trend is shifting Main issues for foreign There is no meaningful
debt market, for power
to renewable energy, investors change in law protection
projects is relatively easy
particularly solar. As Restrictions on land for power projects in
in Malaysia.
of January 2014, the ownership for foreign Malaysia.
installed capacity for entities, i.e., part foreign- There is no or very little Key local players:
renewable energy is owned IPPs need to use a room to negotiate on
approximately 163 MW lease. the Power Purchase TNB
with a total of over 500 Malakoff
49% restriction on Agreement with TNB.
MW of approved but not 1MDB
yet installed capacity foreign equity ownership For coal-fired power
under the feed-in-tariff for IPPs. plants, TNB is the
system. The renewable Risk allocation, offtaker as well as
energy target for Malaysia especially political the coal supplier via
is 11% of the power mix or force majeure risks and its subsidiary. Higher
roughly 2,080 MW by the inflation protections, can cost of third-party coal
year 2020. be a challenge for some supply is not guaranteed
pass-through. Key foreign players:
In addition to solar, the foreign expert credit
Malaysian government agencies. Challenging (but Mitsui & Co.
is considering including likely still possible) to SunEdison solar project
Uncertainty in the way
geothermal energy as the Malaysian energy obtain financing from developer and components
renewable energy eligible market regulator (i.e., international banks manufacturer
for the feed-in-tariff Suruhanjaya Tenaga) or foreign export First Solar solar
system but this has yet to awards tender bids, e.g., credit agencies due to components manufacturer
be finalized. not always based on decrease in protection
lowest tariff; awards via for financiers as
Requirements for
direct negotiation and not compared to other
public bidding for
open tender has recently jurisdiction, i.e., no
greenfield projects
been seen. meaningful change
The main requirement in law protection, no
for public bidding is local direct agreements
participation. Recent IPP between financiers
tenders have only allowed and construction

28 29
SNAPSH TS
OF KEY ASIA PACIFIC POWER MARKETS
Myanmar
Installed capacity:
4,800 MW
Market Model:
2016 Model 21

New changes in power The implementing develop a 225 MW New opportunities for More gas pipelines to coal and large-scale
regulations and policies rules have not yet been gas-fired IPP in foreign investors are being installed hydro, making it more
Since 2012 Myanmar promulgated. Myingyan. The bids Myanmar estimates around Yangon toward difficult to get such
has taken a number The new Electricity were called for by that by 2030, electricity the special economic projects off the ground.
of steps to liberalize Law established the Myanmar Electric demand will be between zones and industrial State and regional
its economy and open Electricity Regulatory Power Enterprise 9,100 and 14,542 areas, helping address governments can license
itself as a destination Commission (ERC), and the process was MW, requiring up to the difficulty of projects generating
for international whose role will include supervised by the 23,600 MW of installed sourcing fuel. less than 30 MW and
investors. With a formulating policy, IFC. capacity (the relatively Additional temporary not connected to the
current electrification preparing tariffs, Sumitomo high reserve capacity national grid. The draft
power generation
ratio of approximately advising the Ministry, Corporation won a is due to hydro, which new investment law
facilities are needed
33%, Myanmar has setting standards and bid to construct a 50 depletes during the dry devolves some of its
before large power
an ambitious target of performing inspections. MW gas-fired power season, accounting for powers to the states
projects become
achieving 100% by 2030 plant in the newly approximately 70% of and regions as well to
Myanmar is receiving operational.
and is developing its established Thilawa electricity mix). There approve such projects.
multi-lateral support New special economic
regulatory framework to Special Economic will be significant
with the ADB assisting in and industrial zones The national election
help it achieve its goal. Zone. opportunities for
developing a framework are being developed, held on 8 November
investors to construct
A new Electricity for competitive bidding. Mitsui & Co acquired 2015 was completed
and operate new power requiring significant
Law was enacted in The World Bank is a 44% stake in peacefully, with the NLD
plants, installing additional capacity.
2014. It distinguishes funding a study on Navigats Myanmar (Aung San Su Kyi-led)
temporary power Recent changes that
between generation, electricity tariffs and subsidiary operating Party procuring a simple
generation facilities, impact power project
transmission and the International a 50 MW gas-fired majority in Parliament.
extending and improving development
distribution and allows Finance Corporation has plant. A new president and
the distribution network Environmental
participation in these supported a recent IPP Myanmar Electric Cabinet will not likely
and providing off-grid or standards are
activities subject to project which included Power Enterprise be in place until March
mini-grid solutions. becoming more
approvals. Authority the introduction of a has commenced the 2016. It remains to be
to approve small- With over 100 GW stringent, requiring
modern PPA. bidding process for seen whether and what
scale and mid-size of hydro potential, more thorough
Recent examples of major short-term 5-year changes there will be in
projects not part of there are significant environmental impact
power transactions PPAs for Yangon (200 government policy after
the national grid has opportunities to invest assessments. There
Sembcorps successful MW) and Mingyan (75 that.
been devolved to the in hydro power plants. is strong opposition
bid to operate and MW).
states and regions.

1 Majority are state-owned producers but trends are leaning toward more IPPs. Distribution is conducted by state-owned Myanmar Electric Power Enterprise (MEPE). Under the draft Electricity Law, permission for large-scale power distribution may be
granted by the Ministry of Electric Power, although it is not known when this draft will become law

30 31
SNAPSH TS
OF KEY ASIA PACIFIC POWER MARKETS
Myanmar
Installed capacity:
4,800 MW
Market Model:
2016 Model 2

Electricity market trend Requirements for public Difficulties in taking and


for the near future bidding for greenfield enforcing security MAIN PLAYERS,
projects
Myanmar has a population Standardized PPAs used INCLUDING
of around 53 million, with an No legal requirement for In terms of state involvement,
electrification ratio of around public bidding; however,
Community resistance
against hydro and coal ACTIVE FOREIGN the main players are the
33%. There is enormous
potential for growth in the
bidding process is becoming
more frequent, e.g., bidding
projects INVESTORS Hydropower Generation
market. Current installed for the Mingyan power station Typical hurdles for Enterprise (HPGE) (hydro and
capacity is approximately supported by the World Bank's a power project coal); the MEPE (gas-fired
4,800 MW. recent tender process for short developer projects and electricity grid);
term gas power solutions won
The new Electricity Law came Process of obtaining and the Yangon Electricity
into force in 2014, devolving by Aggreko.
permits to generate Supply Corporation (YESC)
more authority for small- It is still possible to approach electricity is somewhat
and medium-scale power
(distribution in Yangon region)
MEPE and negotiate projects on opaque and may delay the
projects to the states with a bilateral basis. process.
MEPE still being the main
contact point for large-scale Main issues for foreign Obtaining financing may be
IPP projects. In addition, the investors difficult.
Myanmar Special Economic US citizens may not deal Obtaining Central Bank
Zones Law 2014 (SEZ Law) is with people or entities approval for loans can be
intended to encourage major (or entities controlled by time consuming. In terms of foreign investors, 41% of electricity is
projects in certain areas of them) who are on the SDN
Myanmar, with a wide range list maintained by the US A major Environmental produced from foreign direct investment. Significant
of investment incentives, Treasury. Impact Assessment Report players include:
quite apart from those already approved by the Ministry of
Many foreign investors also Environmental Conservation Hydro power projects: Shweli River Projects 3
available for other parts of consider the reputational
Myanmar under the Foreign and Forestry is required, projects: Shweli 1 (600 MW) built by Sinohydro
impact of dealing with
a process that may take 6
Investment Law 2012 (FIL). SDNs. Bureau 14 [Chinese]; Shweli 2 (460 MW) built by
These may prove to be an months to one year.
Legal framework still Sinohydro Bureau 15; and Shweli 3 (360 MW) built
added attraction. Skilled labor is difficult to
uncertain and developing. by Sino Hydro Bureau 14
Overall, the trend is likely to find.
Regulatory framework weak Yeywa Dam (790 MW) built by a Chinese
be inbound foreign investment
Less predictable
consortium and funded by China Exim Bank.
in power generation, which
has already begun. There Gas-fired projects: Toyo-Thai (100 MW) (Thailand)
Sovereign and general
are also additional foreign- credit risks impact financing APR Energy (100 MW) (USA)
funded investments in power Asiatech Energy (230 MW) (Singapore)
distribution projects. Financial system
underdeveloped Thailands Global Power Synergy PCL, Japans
Marubeni Corp and Myanmars EDEN Group (400
MW) (Thailand, Japan and Myanmar)
Sembcorp (225-500 MW) (Singapore)

32 33
Philippines

SNAPSH TS
OF KEY ASIA PACIFIC POWER MARKETS
Installed capacity:
Approximately 33,577 MW, of which
15,633 MW is dependable capacity
(as of April 2015)
2016 Market Model:
Model 3 transitioning to Model 41

New changes in power has also adopted the use of than last year due to lesser of energy power plants in favor unquantified potential for additional 2,000 MW. According
regulations and policies liquefied petroleum gas (LPG) applications for energy- of Energy World Corporation, solar. Opportunities also exist to the Department of Energy,
and compressed natural gas related projects and stricter Alsons Energy Development in the wind and biogas power the current installed capacity
The government is (CNG) to diversify the countrys rules for the 2014-2016 Corporation and First NatGas industry. in the country of about 16,250
continuously working toward fuel resources for transport Investments Priorities Plan Power Corp., among others. MW is expected to go up to
attracting local and foreign Capital expenditure for solar
and decrease vehicular (IPP). Hydroelectric plants comprise is expected to decrease 25,800 MW (an increase of
investors to venture into power emissions. about 50% of the new grants about 60% by 2030).5
projects. Recent examples while the rest are solar,
substantially in the future.
On 3 June 2015, DOE launched of major power Opportunities also exist At present, coal power plants
The Energy Regulatory the Energy Virtual One Shared diesel, natural gas, wind and comprise over 35% or 5,200
Commission (ERC) has transactions in greenfield generation
System (EVOSS), which aims coal-fired power generating MW of total available capacity
approved new capacity limits projects, joint venture with
to facilitate and streamline A certificate of facilities.4 in the Philippines. Growth
for generation companies so proponents of indicative
the process of RE applications commerciality was issued Aboitiz Power Corp. in coal is driven by relatively
that no firm can own, operate projects, retail electricity
side by side the increase in on 28 December 2014 (AboitizPower) and SunEdison lower electricity price and
or control more than 30% supply, and privatization
the efficiency of all concerned for the 50 MW Biliran awarded the Engineering, stable electricity supply
of the installed generation of NPC plants and NPC-
agencies while fostering a Geothermal Project, which Procurement and Construction generated by coal, being a
capacity of a grid or 25% in the Independent Power Producer
strong private-public sector will be gradually installed (EPC) contract for their first base load power plant.
case of the national installed contracts.
partnerships. The EVOSS is starting September 2016 joint solar power project
generating capacity.2 The Department of Energy Renewable energy resources
a joint undertaking of the up to November 2018. in Negros Occidental. The
has also recently opened such as wind and solar carry
At the onset of the Aquino DOE with the United States Once completed, this will EPC contractor, Nari Group
the 5th Philippine Energy higher break-even prices due
government, the energy sector Agency for International augment the power supply Corporation, will undertake
Contracting Round (PECR) for to the power plant utilization
outlined the following three Development (USAID) Building in the Mindanao region. the construction of the PHP3.5
exploration and development in relation to the resource
(3) major pillars as its overall Low Emission Alternatives In March 2015, Solar billion, 59 MW Negros Solar but are expected to grow with
guidepost and direction, to wit: of indigenous oil and gas, as
to Develop Economic Philippines (the countrys Energy Project. The Negros government support such
(a) ensure energy security; (b) well as coal.
Resilience and Sustainability largest solar provider) Solar Energy Project is set as the feed-in-tariff systems
achieve optimal energy pricing; (B-LEADERS) Project. began construction of the for commercial operations Recent changes that (FIT), which allow renewable
and (c) develop a sustainable In September 2015, the largest solar farm in Luzon, in the first quarter of 2016 impact power project energy developers to be paid
energy plan. The programs that 50 MW project in Calatagan, and will be one of the largest
will lead to the attainment of
DOE lifted the suspension development at premium from market
of Semirara Mining and Batangas. Solar Philippines solar power projects in the electricity rates, for energy
the pillars have been phased Philippines. The government expects
Power Corporations (SMPC) will develop, co-finance, generated by power sources
into short- (2010-2011), several new power facilities
operations for its Coal design and construct the New opportunities for such as wind, solar, run-
medium-(2011-2013) and long- to open in the next five
Operating Contract (COC) No. project, the first time of-river hydro and biomass
term (2013-2016) timelines. that any local company
foreign investors years. In Luzon, a total of
5 in Semirara Island, Caluya, 2,300 MW will be added to plants. Coal is expected to
The Department of Energy Antique.3 has taken an integrated The potential for renewable continue driving the growth in
energy is high: 2,000 MW the grid from June 2015
(DOE) has aggressively approach to solar farm total installed capacity in the
According to the Board of for biomass; 3,400 MW for until September 2019. The
introduced and promoted development. Philippines and is followed by
Investments, the Philippines hydropower, of which 1,700 Visayas grid is expected to be
the use of biofuels, mainly is expected to close 2015 with As of August 2015, the DOE renewable energy, gas plants
MW is small hydro; 1,070 MW augmented by about 442 MW,
sugarcane and cassava-based fewer approved domestic granted 49 certificates of and oil.
for geothermal; and 500 MW while Mindanao will get an
ethanol and biodiesel for and foreign investments endorsement for a number
transport. The government for wind, as well as large but

1 Prior to Republic Act 9136 (Electric Power Industry Reform Act or EPIRA), generation and transmission was under government monopoly (i.e., the National Power Corporation (NPC)). Now (a) generation is privatized with NPC-owned assets in the process
of being privatized; (b) transmission assets are publicly owned but operated and maintained by private corporation; and (c) distribution companies and retail electricity suppliers are privately owned and competitive.
2 The ERC has updated the limit to 3,917.32 MW from 3,612.42 MW as of March last year for the Luzon grid; 709.10 MW from 548.18 MW for the Visayas grid; and to 649.11 MW from 589.09 MW for the Mindanao grid. For Luzon, Visayas and Mindanao, the
limits represent 30% of the total installed capacity in the grids, which stands at 13,057.75 MW, 2,363.69 MW and 2,163.71 MW, respectively
3 Prior to the suspension, the Corporation was asked to implement safety precautions, procedures, and plans in its coal mining operations following an incident in June that left several dead.
4 List of Generation Companies Issued with Certificate of Endorsement (CoE) by DOE, Department of Energy, last update August 2015.
5 Philippine Energy Plan 2012-2030, Department of Energy

34 35
Philippines

SNAPSH TS
OF KEY ASIA PACIFIC POWER MARKETS
Installed capacity:
33,577 MW, of which 15,633 MW
is dependable capacity
(as of 31 December 2014)
2016 Market Model:
Model 3 transitioning to Model 4

Electricity market trend Renewable energy contracts permits/licenses from transmission and
for the near future are also awarded either both national government distribution systems MAIN PLAYERS, INCLUDING
through an open and and local government are inefficient; and (iii)
Investments in the near competitive selection process agencies are required) investment in the sector ACTIVE FOREIGN INVESTORS
future are mostly in coal and or direct negotiation. is low, coupled with the
natural gas. The Philippine Uncertainty in obtaining
high cost of investments
government, however, is also Main issues for foreign necessary permits (e.g.,
made during the
encouraging investments in investors obtaining environmental
countrys power crisis in Key players
renewables and is targeting an compliance certificates)
Limitations in allowable the 1990s.
additional installed capacity Possible changes in Generation
foreign equity in some
of about 15,000 MW from regulatory environment
renewable energy resources by
areas (e.g., exploration, NPC (for missionary areas)
development and utilization and incentive schemes
2030.6 (e.g., first come, first
Private generation companies
of renewable energy
In 2014, a total of 220 resources; obtaining water serve rule under the Major players in the generation sector:
Renewable Energy (RE) Service permits; land ownership) feed-in-tariff system) San Miguel Energy
Contracts were awarded Independent power Aboitiz Power Corp.
Bureaucratic delay and
with 3,184.1 MW of potential producers may find it First Gas/First Gen
lengthy administrative
capacity and 5.1 MW installed difficult to secure power AES Transpower
procedures (e.g., various
capacity. purchase agreements
permits/licenses from both Energy Development Corp.
Requirements for public national government and from credit-worthy
offtakers (i.e., electric K-Water
bidding for greenfield local government agencies
are required) cooperatives) KEPCO/Salcon Philippines
projects Solar Philippines
Uncertainty in obtaining High cost and mismatch
Generally none, as generation in demand and supply
under EPIRA has been necessary permits (e.g.,
obtaining environmental makes country reliant
privatized. on fossil fuels despite
compliance certificates)
Exceptions: setting a goal to have half
Possible changes in its energy needs met by Transmission
Privatization of remaining regulatory environment and renewables National Transmission Corporation
NPC power plants and NPC- incentive schemes (e.g.,
Independent Power Producer first come, first serve The Philippines has some (Transco, owner of transmission assets)
contracts rule under the feed-in-tariff of the most expensive National Grid Corporation of the
system) electricity in Southeast Philippines (a consortium between
Service contracts for oil Asia, averaging USD0.18
and coal exploration and Typical hurdles for a Philippine and Chinese corporations
per kilowatt hour in 2009
development under the power project developer because (i) archipelagic that operates and maintains Transcos
PECR is done through geography makes transmission assets)
public bidding or through Bureaucratic delay and
electricity costly in some
negotiations lengthy administrative Distribution
areas; (ii) generation,
procedures (e.g., various
Manila Electric Company as the largest electric
distribution utility in the Philippines
6 Energy Sector Accomplishment Report 2014, Department of Energy Annual Report, last update April 2015. other private distribution utilities and electric
cooperatives
36 37
SNAPSH TS
OF KEY ASIA PACIFIC POWER MARKETS
Taiwan
Installed capacity:
41,181 MW
Market Model:
2016 Model 21

New changes in power The Draft Amendment the next president and New opportunities for for renewable energy as Although the executed
regulations and policies establishes a sole grid new legislators by end of foreign investors it is the most promoted PPA has been honored
company that will be 2015 may create an even energy form by the and respected by TaiPower
The Executive Yuan state-owned and be more uncertainty to a bill, Demands for more Taiwan government. and the IPP in general, in
of Taiwan passed the responsible for adequate like the Draft Amendment, renewable energy opens 2008 and 2009, Taipower
draft amendment to up new opportunities for Currently, Taiwan suffers
supply of electricity which involves major policy from a very low Operating requested that all IPPs
the Electricity Act (the nationwide. changes. foreign investors in Taiwan amend signed
Reserve. Since the second
Draft Amendment) on PPAs to reduce fixed
Following the quarter of 2015, the
16 July 2015. This Draft The Draft Amendment Recent examples Percent Operating Reserve discount rate of the
Fukushima incident,
Amendment is a landmark removes restrictions on of major power has been constantly below capacity charge formula
establishments of power there has been
of Taiwan governments transactions 10 percent and even often stated in their respective
generation companies widespread public
effort to liberalize the power below 6 percent. Except PPAs to reflect much lower
and power retailers, and In April 2015, Tokyo opposition to nuclear
market, whose market for Taipowers relevant interest rate of the market.
further allows power Electric Power (TEPCO) power, with demands
framework and power on-going projects, there is None of the IPPs agreed to
generation companies to and Chubu Electric that government no clear timeline on when
company management do so.
sell electricity directly to Power announced remove nuclear power the competent authority
system has remained
certain end users without the establishment of plants entirely. will announce the fifth In March 2013, Taiwan Fair
unchanged for more than
price control by the a new joint venture round of IPP solicitation Trade Commission alleged
50 years. Among the Taiwan has three
government. company, JERA. JERA to increase power supply that all Taiwan IPPs acted
comprehensive amendment nuclear power plants
will become the owner capacity. in concert to reject such
articles, the most noticeable The Draft Amendment providing one-quarter
of the major portion of Investment returns for request, in violation of
changes are the following: establishes an of baseload power. All
the two utilities overseas foreign investors have Taiwan Fair Trade Act, and
independent power 6 nuclear reactors will
To end Taipowers power assets, including been good and there is imposed a penalty on each
dispatch center be decommissioned
monopoly in the power three Taiwanese IPPs less interest in looking IPP. The IPPs brought this
responsible for in 3 to 10 years. The
market, the Draft through share acquisition to divest unless they case to court and now the
general planning and fourth one (Lungmen)
Amendment mandatorily of overseas holding have a specific need to case is pending before the
implementation of power has been built, but
split Taipowers power companies. divest overseas interests.
operation and/or Taipei High Administrative
generation section and supply allocation for equal However, we note that
Several global players completion of the units Court.
transmission section to and fair access to the many IPPs are looking
power grid. are interested in Taiwans has been suspended toward expansion. The above case may
be owned by a generation
power market and due to safety and be deemed as a sign
company and a grid The enactment of the Recent changes that
looking for development environmental questioning the certainty
company, respectively. Draft Amendment has yet impact power project
opportunities, especially concerns. during PPA performance,
The two are not allowed to have a clear timeline development
in renewable energy which creates a risk for
to be shareholders of one because the Executive There might be a
due to the feed-in tariff Competition law issues foreign investment.
another. Yuan will still submit this considerable shortage
scheme adopted by between TaiPower and all
bill to the Legislative Yuan of power supply opened
relevant regulations. IPPs may cause negative
for review. Furthermore, up for the market in the
impact on Taiwan power
the general election for near future especially
market

1 (a) Generation open to IPPs but state-owned Taipower is still the major generator; (b) transmission and distribution assets owned by Taipower; and (c) Retail monopolized by Taipower.

38 39
SNAPSH TS
OF KEY ASIA PACIFIC POWER MARKETS
Taiwan
Installed capacity:
41,181 MW
Market Model:
2016 Model 2

Electricity market Requirements for Typical hurdles for


trend for the near public bidding for a power project MAIN PLAYERS, INCLUDING ACTIVE
future greenfield projects developer FOREIGN INVESTORS
Renewable energywind Taipower purchases Uncertainty of securing
and solar, in particular electricity, including clean PPA: The developer of a
is the most promoted energy. Currently and until new power generation
form of energy, although the promotional targets project must expend
it still has a relatively set by relevant regulations significant cost for the
small share of the overall are met, Taipower will bid preparation, without Taipower, the monopoly
installed capacity. purchase power generated any guarantee of a
transmitter, distributor and
by qualified clean energy favorable outcome.
The Ministry of Economic retailer
suppliers as approved in
Affairs proposed in August Uncertainty of securing IPPs, some with Japanese
due courses
2014 that construction of land use rights. For
the 4th Nuclear Power Main issues for projects involving state- investors
Plan be halted for three foreign investors owned land, mandatory Japanese companies
years until a national
Access to the Taiwan
maximum lease term playing significant
referendum could be held, is 20 years, which is roles in equipment
market is relatively
but no agreement reached extendable but without supply, construction and
limited, as it is primarily
on timing and terms of any guarantee
referendum. However,
monopolized by Taipower maintenance works; U.S.
there will be a demand Foreign investment does and European companies
for a new generator. Not not present a problem also join local market for
clear at this point if IPPs provided experience certain projects
will have a role in this and commitment to
development. Taiwanese authorities
are demonstrated

40 41
SNAPSH TS
Thailand
Installed capacity:
40,000 MW to be increased to 70,000 MW
OF KEY ASIA PACIFIC POWER MARKETS in 2036
2016 Market Model:
Model 21

New changes in power in 2036 has been reduced from exceeding 20% of the target receive the FiT, though these projects capacity of 50 MW, while each state (SEZ). Although the draft Bill on
65% to 40%, to be in line with the installed capacity. Thailand will be considered and selected agency/cooperative is not allowed to SEZ contains a grandfather clause
regulations and policies governments policy to decrease has already entered into under a new competitive public develop more than 5 MW capacity. allowing operators under the current
Launch of the Thailand Integrated dependency on natural gas. a number of MOUs with bidding process. Successful bids will be chosen via a IEAT law to maintain their existing
Energy Blueprint, a new long-term neighbouring countries for competitive bidding process, which rights and privileges, it also provides
master plan consolidating five
Thailands newest IPP project,
the purchase of imported Recent examples of major has been divided into two phases for investors under the new SEZ
the 930 MW Khanom Power
key plans as pillars for national Plant (Unit 4) to be owned and power. Recently, it has been power transactions (600 MW targeted for the first scheme to receive various benefits
energy development: (1) Power operated by Khanom Electricity announced that the Energy In June 2015, EGAT sponsored phase and 200 MW targeted for the (e.g., permission for land ownership
Development Plan 2015-2036 Generating Company Limited Policy and Planning Office the issuance and selling of EGAT second phase). Successful projects by foreigners, permission to bring
(PDP 2015); (2) Energy Efficiency (KEGCO), a subsidiary of EGCO, (EPPO) of Thailands Ministry Infrastructure Fund (EGATIF), will be awarded VSPP PPAs with in foreign experts, executives and
Plan 2015-2036 (EEP 2015); (3) is set to achieve commercial of Energy is considering which is the first state enterprise a fixed purchase price (THB5.66 specialists, exemption or reduction of
Alternative Energy Development operation in June 2016. negotiations with the infrastructure fund to be established per kilowatt hour) under the FiT taxes and duties, etc.).
Plan 2015-2036 (AEDP 2015); (4) Cambodian government to arrangement for a period of 25
a new oil roadmap setting out Coal-fired power plants purchase power from a 2,000
and listed on the Stock Exchange of
years. Recent changes that
Thailand. EGATIF will invest in the
targeted subsidies, removal of Under the PDP 2015, the installed MW coal-fired power plant. rights to the revenues generated by First phase: Proposal impact power project
existing subsidy on fossil fuels and capacity for clean coal projects Regulations on solar PV rooftop EGATs power plants. submissions for the first phase development
promotion of biofuels as fuel for is expected to increase to 25% projects were amended to closed in November 2015, after
transportation; and (5) a new gas of the target installed capacity. Gulf Energy Development: Potential changes in zoning laws
liberalize business. Solar PV Approximately USD2 billion which all qualified proposals (expected to be finalized by end of
roadmap to curb gas demand and Although future investment rooftop projects generating less will be placed in a single pool
establish the structure for LNG may increase, the development financing of 12 SPP gas-fired 2015) and related regulations may
than 1 MW capacity will not be power plant projects (with total from which final selections will affect power plant location.
facilities. may still be in doubt due to required to obtain electricity be made by lucky draw on 15
the continuing protests from capacity of 1,470 MW) by 8 local and Large-scale power projects (THB
The PDP 2015 was approved by the generating licenses or factory international financial institutions. December 2015. Selected bids
Energy Regulatory Commission of local community and potential operating licenses. will be required to commence the 1 billion plus) to be developed in
Thailand (ERC) and the National environment issues. B.Grimm Power Group: (i) THB17 sale and dispatch of electricity to conjunction with the public sector
The ERC has issued regulations billion financing of 3 SPP gas-fired (e.g., power plants jointly invested
Energy Policy Council (NEPC) in Renewables to replace the previously the grid by 30 September 2016.
May 2015, and was subsequently power plants located in Rayongs by EGAT or located on land leased
Under the PDP 2015 and existing Adder on purchase Amata City Industrial Estate (with a Second phase: No date has yet from a state agency) will be deemed
acknowledged by the Cabinet in June according to the new AEDP price of electricity generated by been announced for the opening
2015. Policies implemented under total capacity of 366 MW) by 2 local a Public-Private Partnership (PPP)
2015, investment in renewable renewable power projects with a banks and 2 international banks, of the second phase of bidding. project for the purposes of the
the new PDP 2015 are as follows: energy will be increased to 20% new Feed-In Tariff (FiT) for VSPPs and (ii) THB7.5 billion financing of Small private players who would new Private Investment in State
Fuel mix of the target installed capacity. generating less than 10 MW, 13 solar farms in various provinces like to develop solar PV rooftop Undertakings Act 2013 (PPP Act) and
The PDP 2015s fuel Biomass and waste-to-energy which will be granted for a period (with a total capacity of 114 MW) by 3 projects can more easily obtain thereby subject to the requirements
diversification policy increased projects will be driven. of 20 years (except for landfilled local banks. required approvals and sell applicable to PPP projects as
total installed capacity of clean Nuclear power gas-fired projects which will be electricity to PEA, MEA, or private stipulated thereunder, including,
coal-fired thermal power plants awarded for 10 years). Currently, New opportunities for users. amongst others, submission of
According to the PDP 2015,
from 20% to 25%, increased nuclear power projects will be
new FiT rules only apply to those foreign investors Third Party Access (TPA) Regime prospective PPP projects to the PPP
purchase of imported electricity projects which have duly executed Policy Committee, chaired by the
delayed by at least another 20 In September 2015, the ERC issued has been put in place. PTT and
from neighboring countries from PPAs with state power utilities Prime Minister, for consideration
years due to the Fukushima an invitation to bid for solar power PTT LNG have announced their
15% to 20%, and decreased (i.e., EGAT, MEA or PEA) but and approval. In September 2015,
incident and protests from the projects with a combined capacity TPA Codes regarding third-party
installed capacity of gas-fired have not dispatched electricity to the Cabinet approved a draft of the
local community where the of 800 MW to be developed by state access to their onshore pipeline
thermal power plants from 64% the grid, as well as for projects ministerial regulations which, when
power plant was planned to be agencies and certain cooperatives. and Liquefied Natural Gas (LNG)
to 40% in 2036. whose applications were accepted issued, will amend the PPP Act to
located. Interested state agencies/cooperatives terminal.
earlier in 2014 under the former increase the minimum value of PPP
Gas-fired power plants Purchase of electricity from need to partner with private investors The Thai government is presently
Adder scheme (regardless of projects from THB 1 billion to THB 5
Due to the imminent depletion of neighbouring countries whether the relevant PPA has with solar power experience. Each considering repealing the law on
private investor can participate in billion. The Cabinet also approved the
available natural gas in the Gulf The NEPC is looking to purchase been signed). Projects that have the Industrial Estate Authority of
more than one project but cannot implementation of a PPP Fast Track
of Thailand, the target installed electricity from neighbouring applied for a PPA but have not yet Thailand (IEAT) and replacing it with
sponsor more than an aggregate scheme for greenlighting selected
capacity for gas-fired projects countries in an amount not been accepted are also eligible to a law on Special Economic Zones top-priority PPP projects.

1 Electricity Generating Authority of Thailand (EGAT - state-owned enterprise) and IPPs are the main generators of the country. EGAT transmits and distributes electricity generated by itself and IPPs to Metropolitan Electricity
Authority (MEA - state-owned enterprise) and Provincial Electricity Authority (PEA - state-owned enterprise) to be further transmitted and distributed to users throughout the country.

42 43
SNAPSH TS
Thailand
Installed capacity:
40,000 MW to be increased to 70,000 MW
OF KEY ASIA PACIFIC POWER MARKETS in 2036
2016 Market Model:
Model 2

Electricity market trend and actively establishing a Main issues for foreign to Cabinet approval
for the near future firm presence in offshore investors on a case-by-case MAIN PLAYERS, INCLUDING
markets within the region. basis. Therefore, EGAT,
With Thailands decreasing No critical issues to be PEA and MEA would ACTIVE FOREIGN INVESTORS
dependency on natural gas, Requirements for public concerned: not agree to accept
investment trend in the bidding for greenfield the inclusion of any
The development of
near future is likely to be projects power plants and the arbitration clauses in
concentrated in alternative/ its PPA. In accordance
IPP projects: The ERC will sale electricity to EGAT,
renewables, in line with with ERC regulations,
announce invitations to PEA, MEA or to private/
global trends. However, the current standard Local
participate in IPP Solicitation industrial users is not
clean coal is still an agenda form of PPAs provide
rounds in accordance with restricted by the Thai
for diversification, and to
Foreign Business Act for any disputes under Electricity Generating
enhance national energy targeted installed capacity
requirements and solicit (FBA). The FBA will apply, the PPA to be referred Public Company Limited
security, electricity imports to experts appointed by
from neighboring countries requests for proposals among others, to activities (EGCO)
that are considered to be ERC for consideration,
are expected to rise. (RFPs) from investors.
as opposed to an
Ratchaburi Electricity
service business.
SPP projects: There is no arbitration tribunal. Company Limited (RATCH)
Among alternative/
renewable energy sources, public bidding process. Foreign investors can own Global Power Synergy
Investors are required freehold land in Thailand Company Limited (a
solar continues to be a top
to lodge an offer to sell (subject to conditions) for
choice for domestic and
use in connection with
subsidiary of PTT Group)
foreign investors alike; electricity to EGAT (or PEA
or MEA, depending on the their power projects upon B. Grimm Power Group
however, as the PDP 2015
size and location of the the projects receiving
focuses on driving biomass
project) to get approval to investment promotion from
and waste-to-energy
enter into the PPA with the the Board of Investment
projects in particular, a
relevant state offtaker (i.e., of Thailand (BOI), which is
rise in the number of these
EGAT, PEA or MEA). The normally granted.
alternative energy projects
offer will be considered in
can also be expected. In fact,
accordance with the public
Typical hurdles for
the PPP Policy Committee a power project
recently greenlighted the announcement of EGAT, PEA Key foreign investors include:
or MEA (as the case may be) developer
development of 2 waste-
to purchase electricity from New zoning laws:
J-POWER Group (through Gulf
to-energy power plant PPP
projects (with an estimated SPPs which is issued from additional restricted Electric Public Company Limited)
total investment value of time to time in accordance area for construction GDF Suez (through Glow Energy
with the direction of the PDP of industrial factories
USD176 million) on an
2015.
Public Company Limited by
expedited basis. (including power plants).
holding 69% equity stake therein)
The general trend among VSPP projects: A new Delay in issuance of factory
major Thai players is an competitive bidding system operating licenses.
increasing shift toward has recently been adopted
instead of the previously Acceptance of arbitration
outbound investment in
existing first-come, first- clauses in PPAs with EGAT,
neighboring countries
served basis. PEA or MEA is subject

44 45
SNAPSH TS
OF KEY ASIA PACIFIC POWER MARKETS
Vietnam
Installed capacity:
35,000 MW
Market Model:
2016 Model 21

New changes in power Amendments to current trillion (approximately For renewable energy, This equitization Vietnams current power
regulations and policies Power Master Plan VII to USD281 million) in there is generally a high process creates new supply, through 2015, is
reflect developed energy Dak Lak Province in potential for wind and opportunities for viewed as adequate by
A number of major new
strategy following changes the Central Highlands; solar power projects in investors and is crucial the business community;
laws impacting the
in the power market since (2) Cong Ly Trade and Vietnam, as the country for the establishment however, many firms are
business environment
2011. Services Company Ltd., lies in the path of of an independent expressing concern over
in general have been
a Vietnamese investor, strong and reliable wind wholesale market. Vietnams future power
adopted: Investment In September 2015, MOIT
implements Bac Lieu streams. The Master supply outlook. Majority of
Law, Enterprise Law, issued new regulations on Recent changes that
wind power project Plan gives a long-term firms surveyed, especially
Construction Law, procedures for investment impact power project
aiming at a capacity policy to prioritize those with foreign direct
Tendering Law, new in build-operate-transfer development
(after Phase II) of 120 and incrementally investment, are more
regulations on public- (BOT) thermal power
MW. For solar and raise the proportion A key objective of concerned with securing
private partnership (PPP) projects, contributing
biomass, many projects of electricity produced Vietnams electricity uninterrupted power
investment, etc. to completion of new
are currently being from renewable market reforms, with supply than they are with
PPP legal framework in
The Ministry of Industry done on an ad hoc energy sources (wind the equitization of moderate increases in
Vietnam.
and Trade (MOIT) approved basis since regulatory energy, solar energy, EVNs power generating electricity costs. With
a detailed design of the Recent examples and fiscal frameworks biomass energy, etc.) entities (GENCOs), many firms willing to
competitive electricity of major power are only just emerging. and targeted to reach is to encourage new absorb higher costs, this
wholesale market for transactions 4.5% of total power investment. More power presents an opportune
New opportunities for
Vietnam in August 2015. capacity by 2020. This project developments moment for renewable
Major BOT and IPP foreign investors
includes targets for wind and investments are power to lead private
Following the issuance thermal power projects in
BOT thermal power energy to reach 1,000 expected. sector investment in
of development support progress, including Duyen
remains a good option MW, biomass to reach renewable energy and
mechanisms for wind Hai 2, Van Phong 1, Quynh For BOT thermal power
to the extent that under 500MW. play an increasing role in
power projects in June Lap 1, Vinh Tan 1, Nghi projects, new rules
the PPP framework, securing Vietnams future
2011, biomass power Son 2, Vung Ang 2, Vinh From early 2015, an place strict time limits
it is generally easier power supply.
projects in March 2014, Tan 3, Song Hau 2, Long equitization plan for for investors to follow
to negotiate more
and projects using solid Phu 2 and Nam Dinh 1. EVNs power-generating during implementation. A key concern is dealing
favorable electricity
waste in May 2014, entities (GENCOs) was This addresses the with tension between
A number of wind power tariffs and obtain
Vietnam is reviewing and approved for GENCO 3 in status of delays in the Master Plan VIIs
projects have been more government
issuing a development 2016 with 6 power plants implementation of these continued reliance on coal
implemented: (1) HBRE guarantees. Moreover,
support mechanism for and a total capacity projects. power and support for
Wind Power Solution Co. investors can receive
solar power projects in of 4,564 MW, followed renewable energy.
invested in a 120 MW wind more fiscal and
2015. by the equitization of
farm at a value of VND6 financial incentives.
GENCO 1 and GENCO 2.

1 (a) Generation: competitive market; (b) transmission is state-owned; (c) wholesale: aim to establish competitive market (experimental from 2015-2016, complete by 2017-2021); and (d) retail: aim to establish competitive market (experimental from
2021-2023, complete after 2023).

46 47
SNAPSH TS
OF KEY ASIA PACIFIC POWER MARKETS
Vietnam
Installed capacity:
35,000 MW
Market Model:
2016 Model 2

Electricity market under the form of Public- Substantial investment


trend for the near Private Partnership (PPP). capital and technology MAIN PLAYERS,
future Accordingly, the government costs for renewable
has released lists of PPP energy projects are INCLUDING ACTIVE
Vietnam will experience
high electricity demand in
projects called for investment.
For other greenfield
required, but the price
of power sold to EVN FOREIGN
the near future. The total
capacity of power plants is
investment projects, there are
no reliable and specific legal
is rather low to provide
investors any profit, or
INVESTORS
targeted to be approximately guidelines on public bidding. too little to guarantee for
Key local players:
75,000 MW by 2020 and As such, for these projects, bank loans. Hydropower: generators (e.g., Vietnam Electricity
146,800 MW by 2030. there are generally no further
With EVNs financial Corporation (EVN), a state-owned enterprise and its
requirements compared to
Renewable energy: situation, foreign subsidiaries, Song Da Corporation)
prioritizing and projects in other sectors.
investors and banks are Thermal power generators (e.g., EVN; PetroVietnam
incrementally raising the Main issues for foreign unlikely to accept EVNs (PVN), a state-owned enterprise, for oil and gas);
proportion of electricity investors plan to purchase power Vinacomin (a state-owned enterprise, for coal-fired
produced from renewable from wind power plants
Policy and regulatory power); An Khanh Thermo-power JSC)
energy sources (wind without government
energy, solar energy, mechanisms need to be Renewable energy project developers (e.g., EVN;
guarantees.
biomass energy, etc.). further developed to enable Cong Ly Trade and Services Company Ltd.; Vietnam
renewable energy project Typical hurdles for Renewable Energy Joint Stock Company; Thuan
Hydropower: also development. a power project Binh Wind Power Stock Company; Phu Cuong
prioritizing development
Issues relating to developer Group; Thien Tan Group; REC Corp)
of hydropower projects for
multiple purposes (e.g., application processes, Financial constraints
flood control, water supply electricity tariffs, gaps
between standardized Site clearance and
and electricity production).
power purchase compensation are
Thermo-power: develop agreements (PPAs) complicated procedures
a reasonable number of and bankable PPAs and Lack of transparency in
thermo-power plants associated government governmental decisions
suitable to the supply approvals are not clear and Key foreign investors:
capacity and distribution of definite enough to allow
fuel sources. Thermal power generators: Formosa; AES; Malaysia-
investors to determine
based JAKS Resources Berhad; China Southern
Requirements for public whether renewable energy
prospects can meet local Power Grid Company (CSG); Sumitomo; Janakuasa;
bidding for greenfield Tai Kwang; Samsung; EGATi; Taka Power
regulations, as well as
projects minimize uncertainty and Renewable energy: GE, Vetas, WPD Energy Vietnam,
Public bidding requirement exercise of discretion in
HBRE Wind Power Solution, Greta Energy Inc., EAB
is currently only applied regulatory decisions.
to investment projects
Vietwindpower, Enfinity Asia Pacific Limited, Aerogie.
plus Solution AG, Terra Wood, Belectric Solar, Global
Shere, Doosan, CS Wind Tower, VINA HALLA Heavy
Industries

48 49
The Asia Pacific Energy, Mining & Contributors
Infrastructure Industry Group Australia Malaysia
Paul Curnow Mark Lim
With substantial experience in energy, Partner, Sydney Partner, Kuala Lumpur
mining and infrastructure across the globe, paul.curnow@bakermckenzie.com mark.lim@wongpartners.com
our lawyers leverage substantial insight Robert Gough Faez Abdul Razak
and experience to help you deftly navigate Associate, Sydney Associate, Kuala Lumpur
robert.gough@bakermckenzie.com faez.abdulrazak@wongpartners.com
the industry. We offer extensive knowledge
of various issues that you may face, the India Myanmar
commerciality to deliver practical solutions, Samir Desai
Of Counsel, Tokyo
John Hancock
Partner, Yangon
and the know-how to ensure robust planning samir.desai@bakermckenzie.com john.hancock@bakermckenzie.com
and risk management.
Indonesia Philippines
Power industry expertise Luke Devine
Head of AP Energy, Mining Infrastructure
Felix Sy
Partner, Manila
Foreign Legal Consultant, HHP, Jakarta felix.sy@quisumbingtorres.com
Our sound track record in power projects luke.devine@bakernet.com
from financing to development and operation Kirana D Sastrawijaya
Alexis Cimagala
Associate, Manila
includes numerous milestone projects in Associate Partner, Jakarta alexis.cimagala@quisumbingtorres.com
the Asia Pacific and throughout the world. We kirana.d.sastrawijaya@bakernet.com
Taiwan
primarily act for project developers, as well Anita Karina Sungkono
Tiffany Huang
Associate, Jakarta
as for lenders, governments, international anita.k.sungkono@bakernet.com
Partner, Taipei
tiffany.huang@bakermckenzie.com
agencies, contractors and operators.
Japan Julia King
As one of the world's largest international law Anne Hung Associate, Taipei
Partner, Tokyo julia.king@bakermckenzie.com
firms, we deliver on-the-ground legal support anne.hung@bakermckenzie.com
to help you confidently expand abroad. And as a Thailand
Ean MacPherson
firm with deep local roots wherever we operate, Partner, Tokyo
Sawanee Sethsathira
Partner, Bangkok
we offer a deep understanding of local markets, ean.macpherson@bakermckenzie.com
sawanee.sethsathira@bakermckenzie.com
first-mover advantage for new opportunities, Masahiro Tanabe
Napas Na Pombejra
and introductions to key local regulators and Associate, Tokyo
Associate, Bangkok
masahiro.tanabe@bakermckenzie.com
industry players. napas.napombejra@bakermckenzie.com
Lao PDR Pattadon Tejapaibul
Sawanee Sethsathira Associate, Bangkok
Partner, Bangkok pattadon.tejapaibul@bakermckenzie.com
sawanee.sethsathira@bakermckenzie.com
Vietnam
Chavapol Akkaravoranun
Chi Lieu Dang
Associate, Bangkok
Partner, Hanoi
chavapol.akkaravoranun@bakermckenzie.com
chilieu.dang@bakermckenzie.com
Pranisa Chinkulkitniwat
Associate, Bangkok
pranisa.chinkulkitniwat@bakermckenzie.com
www.bakermckenzie.com

Baker & McKenzie has been global since


inception. Being global is part of our DNA.

Our difference is the way we think, work and behave we


combine an instinctively global perspective with a genuinely
multicultural approach, enabled by collaborative relationships
and yielding practical, innovative advice. Serving our clients
with more than 4,200 lawyers in more than 45 countries, we
have a deep understanding of the culture of business the world
over and are able to bring the talent and experience needed to
navigate complexity across practices and borders with ease.

2016 Baker & McKenzie. All rights reserved. Baker & McKenzie International is a Swiss Verein with member law firms around the world. In
accordance with the common terminology used in professional service organizations, reference to a partner means a person who is a partner, or
equivalent, in such a law firm. Similarly, reference to an office means an office of any such law firm.

This may qualify as Attorney Advertising requiring notice in some jurisdictions. Prior results do not guarantee a similar outcome.

Вам также может понравиться