Академический Документы
Профессиональный Документы
Культура Документы
Objective Matrix
Inspection engineer exposed to QA/QC, responsible for Static Equipments
Integrity monitoring in refining industry having 4+ years of handful experience in oil &
gas plant shutdown/turnaround experienced technically in Static Equipments like
column, heat exchanger, stag, pressure vessels, fin fan cooler, storage tank, furnace,
regenerator, reactor & process piping inspection in India & Europe. The below listed shutdown
assignments was happened in On-shore locations, which are assignments offered by KLAIPEDA
UNIVERSITY Lithuania-Europe in behalf of clients.
B.E in GEO-INFORMATICS
M.S PETROLEUM TECHNOLOGICAL PROCESSES
Technical Certification
Professional Snapshot
API 660 Heat Exchangers API 661 Air Fin Coolers API 1104 Pipelines Welding
API RP 571 Damage Mechanisms affecting fixed equipment in refining industry
API RP 572 inspection of Pressure vessels API RP 577 Welding & metallurgy
API RP 1169 Pipeline Construction API 2201 Hot Tapping API 6 AM Material
API RP 579 Fitness for Service API RP 651 Cathodic Protection of Storage Tanks
SRINIVASAN CHANDRAN
GSM: +91-96009-68-921 (India), Mail to: geosrini@gmail.com
Handled Equipments
Pressure Vessels Heat Exchangers Air Fin Coolers Tower Columns Process Piping
Steam Coils Radiant Coils, Convection Coils, Super heated Coils Storage Tanks
Process Valves Economizer Coil Gasket Inspection Torque & Tensioning on Manway
& Nozzles
HEAT EXCHANGER
(Under API-660 & TEMA Tubular Exchanger Manufacturers Association)
To inspect the channel head, shell head for the preliminary inspection
To inspect the tube bundle for preliminary inspection
To inspect the internal cleaning inside both the channel head, shell head in all nozzle
joints, T joints, welding support joints, manway joints and also clean the soft scales &
debris
To inspect the bundle cleaning by water jetting & air blowing
Also to inspect the tube welded in tube sheet
Recommendation : plugging of leaky tubes, Re-rolling on roll leaky tubes
Gasket inspection, recommended for new gasket installation
After cleaning offer for the NDT cleaning(UT,MT,LT)
Hydro testing inspected shell & tube side
After box up inspected the witness of Torquing & Tensioning
FIN-FAN COOLERS
(Under API-661 & TEMA Tubular Exchanger Manufacturers Association)
PRESSURE VESSELS
(Under API-510 & ASME Sec VIII, Division I / II)
To inspected the P & I inspection for the removed the debris & soft scales
SRINIVASAN CHANDRAN
GSM: +91-96009-68-921 (India), Mail to: geosrini@gmail.com
Inspect the internal cleaning in all nozzles joints, all welding T joints,
bottom nozzles
After completed NDT in all joints
To remove the demister pad to inspect the condition, if used or new one
used
To inspect the final inspection & de-chocking in drain location
After box up, Torquing & tensioning in De-blinding areas
Belzona coating 1391 & 1311 will be recommended on gas service vessel
MPT will be conducted in cladding vessel (UTG not possible)
UTG recommended on all weld seams, both dish ends (Knuckle joint, Crown Joint, Centre
Joint)
Manway gasket seating face will be inspected for any corrosion, if so recommendation
will be given for face machining (Grinding) Skim-off
COLUMN
(Under ASME Sec VIII, Division I / II)
To inspect the p/l inspection in dish top, dish bottom, shell side
Inspect the all welding joints man-ways, all trays condition, distributers pipes, all T
welding joints
Also inspect the vortex breaker &covered by plastic cover
After internal cleaning offer for the NDT
If having demister pad inspect that condition. if need to be replaced & installed with new
demister pad
Inspect the final inspection, de-chocking in drain part &box up.
After box-up ,Torquing &tensioning witness to be carried out at all de-blinding location
PROCESS PIPING
(Under API-570, ASME B 16.5 & ASME B 31.3)
Raw material visual inspection & test certificates review refer with ASME sections
WPS, PQR & WPQ Witness & Review
Ensuring correct Line no, joint no, Material specification & grade as per design & drawing
Root gap, root face, bevel angle & straightness
If required pre heating and ensuring the temperature with thermal chalk and graph chart
Welder no, Slag, spatter, bead length & single or multi layer then shrinkage & good
penetration
Check surface & during welding ensure electrode heated or not and performer qualified
or not
If required post heating and ensuring the temperature with thermal chalk and graph
chart
After welding if required ensure stress relieving process & temperature range, soaking
hrs according
Before hydro test ensuring mechanical clearance & line history sheet has been
completed or not
After hydro test, water & air flushing inspection & air moisture inspection carried out
Combined hydro static test conducted inspection done in heat exchanger
Pneumatic test inspection conducted in RF pad using nipple hole
Pneumatic test was carried out in gas lines using plant-air
Gauge selection will be done according to not less than 2 times & shall not go more than
4 times of the test pressure.
Gauge calibration will be verified / ensured by witnessing Test Certificate
SRINIVASAN CHANDRAN
GSM: +91-96009-68-921 (India), Mail to: geosrini@gmail.com
Passport Details
Personnel Snapshot
Im SRINIVASAN Nationality : IndianS/o Mr.CHANDRAN
#37/1, Thiruvalluvar Nagar. Nellikuppam, Cuddalore district, Tamilnadu PIN: 607 105
Marital Status : Single Languages known : English & Tamil Blood Group : A+ve
Employment Expectation
Anywhere in India, Middle-East & Europe
Declaration
Hereby I declare that all the information mentioned above is true to the best of my
knowledge