Вы находитесь на странице: 1из 8

Invited Lecture at VI International Symposium on Lightning Protection ( VI SIPDA)

November 19 - 23, 2001, Santos, Brazil.

LIGHTNING PROTECTION ASPECTS


FOR APPLICATIONS OF OPTICAL FIBRE GROUND WIRE

William A. Chisholm Jody P. Levine and Craig Pon


Kinectrics (the former Ontario Hydro Research Division)

800 Kipling Avenue KL206 Toronto, Ontario CANADA M8Z 6C4 (W.A.Chisholm@ieee.org)

Abstract Three aspects of lightning protection are Easy local access to fibre-optic networks will improve
described for optical-fibre ground wire (OPGW) on local communications infrastructure by many orders of
overhead lines. Test methods for reproducing the observed magnitude. There is great synergy in developing areas
damage from direct lightning strokes to OPGW are where simultaneous cellular telephone network
converging but need further development. Application of
development is also intense. Transmission line towers
OPGW underneath the phase conductors is shown to
enhance line lightning reliability. Economic costs of this offer secure and favourable locations for both optical and
application are considered. Finally, the co-ordination of cell-phone repeaters. However, typical repeaters need
high-voltage line protection with low-voltage circuits for power. Small amounts of reliable electric power can be
OPGW accessories is considered to develop of surge arrester derived from the transmission line itself. Higher amounts
requirements from grounding impedance. of power will bring a low-voltage circuit from a
distribution system up to a transmission line tower that
may be struck by lightning many times in its design life.
1 INTRODUCTION Co-ordination of overvoltage protection of the two
networks will be needed for adequate link reliability.
Optical-fiber networks can be constructed efficiently
using the same towers as existing power transmission
systems. There are three important protection aspects 2 DIRECT DAMAGE TESTS AND STANDARDS
that need to be addressed in this application.
2.1 Field Observations
The OPGW is often substituted in place of a conventional
overhead groundwire, used for lightning protection at the In applications where overhead groundwires are replaced
top of the transmission towers. Direct lightning strokes with optical-fiber ground wire (OPGW), direct lightning
to cables causes metal loss and other damage. Simulation stroke damage can result in metal loss or broken strands.
of this damage in test methods should reflect the high Over time, the fiber may degrade, or in severe cases direct
probability of occurrence over the design life. Test levels thermal damage can occur. Reports of OPGW damage
must be related to the accepted risk. Selection of test in Brazil and other areas [1] suggest that the existing test
parameters for a typical test method is illustrated. Details specifications [2], which were met during acceptance
of the testing methods still need to be standardised and testing of the cables, have not protected the industry
some proposals are suggested. adequately from lightning damage.

In cases where risk of damage to OPGW from direct One estimate of the possible damage rate of OPGW can
strikes is extreme, it is possible to realise important be obtained from a survey of conductor damage on most
improvements in lightning protection by placing the of the Hydro-One distribution system. This 119,000-km
composite conductor below, rather than above, the phase network of one-phase and three-phase low-voltage
conductors. This underbuilt arrangement reduces the systems has an overall record of 1260 damaged
impressed insulator voltages under lightning conditions. conductors from lightning in six years. These damages
The reduction in backflashover rate is significant in areas occurred as follows:
of high soil resistivity.
574 damaged conductors, ranging from #2 up to
556 kcmil ACSR
1
Invited Lecture at VI International Symposium on Lightning Protection ( VI SIPDA)
November 19 - 23, 2001, Santos, Brazil.

362 damaged drop leads, usually bare copper of #4 similar in construction, size and stranding to some
AWG used up to 150 A. OPGW, a damaging lightning flash to OPGW on this
324 damaged secondary wires, ranging from #4 100-km line could be expected every year at the damage
Aluminum to #1/0 for normal 200-A service. rate of 1%. This would give a predicted damage rate of
one case per 100 km-year, in close agreement with an
The Hydro-One distribution system ACSR conductors are observed OPGW damage rate of 0.08 cases per year in
at an average height of 10 m and the average ground flash Japan [1].
density in the province is 1.0 flashes per km2 per year.
Using these values, it is possible to anticipate an average 2.3 Damage or Failure Criteria
number of 10,000 lightning flashes per year to the
network from Equation (1) below. Over six years, the The lightning damage from a 1% flash may be minor for
damage rate becomes (574 / 60,000) or about 1 % per example a single strand could break and the damage
lightning flash. may be repaired easily without affecting the optical link.
For this reason, users must be careful to specify an
appropriate damage criterion that reflects their reliability
2.2 Incidence of Lightning Strokes requirements. Typical damage criteria have included:

A ground flash density Ng (lightning strokes per square The number of broken strands exceeds a given integer
km per year) can be obtained for an area of OPGW The remaining tensile strength falls below 75% or
installation using automatic lightning detection equipment 80% of rated tensile strength
[3] and a sufficient period of observation to yield 400 A transient or permanent change in the optical
observations in the selected study area. In some areas attenuation of the fibers is measured
where automatic equipment has not been deployed, the The optical fibers are exposed to the environment
global measurements of Optical Transient Density can be after the test
used, along with an approximate conversion factor of 10
optical transients per ground flash [4]. The exposure interval Y in years between damage, and the
line length L in km, will be specified by the user. It may
The number of flashes to the overhead line can be not be realistic to expect that the product YL can exceed
estimated using the following expression [5]: 1200 - 1500 km-yr .

28ht0.6 b 2.4 Lightning Peak Current


N N g
10 (1)
Normally, for calculations of transmission line lightning
N is the flashes/100 km/year to the line performance, the peak magnitude of the first stroke in the
Ng is the ground flash density per km2 per year flash is of the greatest interest. The probability of a
ht is the height of the conductor (or overhead stroke current in excess of a value of I* kA is
groundwire) at the tower approximated from Bergers data [6] as [7-9]:
b is the overhead ground wire separation in m 1 (2)
P( I I *) 2.6
I *
When there are two or more overhead shield wires, the 1
31
total number of flashes N lightning shall be assumed to
where I* is in kA. The first stroke has a 1% chance of
split equally and uniformly along the exposed spans. A
exceeding a peak current of 180 kA. However, other
small proportion, equal to b divided by the span length in
parameters of the lightning flash may be more likely to
meters, can be deducted for direct strokes to the tower.
damage conductors. Figure 1 shows the effect of a
waveform approximating component 'A' of IEC 60794:
If possible, the proportion of positive and negative
120 kA peak, 25 s rise and action integral of 2 (kA)2s.
flashes should also be established. Otherwise a fraction
The most visible effect is that of the spraying of the fuse
of Fneg=95% negative and Fpos=5% positive flashes can
wire onto a broad patch of the surface of the conductor.
be used in subsequent calculations.
Damage is often imperceptible, and is limited to a slight
flattening of the surface of the strands. This effect is
A 100-km transmission line, with 35-m overhead
groundwires, will be struck approximately 100 times per typical of high-current (50-200 kA), slow-rise (4-40 s)
year in an area of moderate ground flash density (Ng = 4). short duration (10-300 s) test waves, and is entirely
To the extent that distribution system conductors are unlike the broken strands observed in the field.

2
Invited Lecture at VI International Symposium on Lightning Protection ( VI SIPDA)
November 19 - 23, 2001, Santos, Brazil.

(8)
1
85( Ppos 1)1 / 2.0 Q positive coulombs

Figure 1: Damage to OPGW from Lightning Impulse Current of 120 kA


(25s rise time, 2 (kA)2s, IEC 60794)

2.5 Total Flash Charge Figure 2: Damage to OPGW from Lightning Continuing Current
delivering 165 C ( 220 A x 750 ms, IEC 60794)
The amount of charge in the total flash is a dominant
factor in conductor damage. The charge, rather than the In contrast to the difficulty in generating a simulated
impulse peak or the integral of the square of current over lightning stroke with a steep rate of current rise, it is fairly
time, is correlated with arc damage mainly because the arc easy to build a test circuit to deliver total charge using a
root voltages tend to be constant for a wide range of DC source. The IEC 60794 standard [10] gives no
currents. Berger [5] gives observed levels of negative guidance on charge level, but does identify that most
and positive flash charges as follows: charge is to be delivered as a DC component (called
Component C) with a duration of 0.25 to 0.75 s. Polarity
Table 1: Typical Lightning Flash Charge Parameters [5] is not identified at all. Figure 2 shows the typical damage
to an OPGW for a total charge of 165 C, delivered as
Parameter Negative Flash Positive Flash 220 A for 0.75 s. The anticipated damage features,
Charge, coulombs Charge, coulombs
including metal erosion and broken strands, are
No. of Observations 94 26
95% will exceed 1.3 C 20 C reproduced by the test method.
Median 7.5 C 80 C
5% will exceed 40 C 350 C
2.6 Typical Worked Example for Test Parameters
Bergers data on total flash charge [5, Figure 3] can be A worked example has been provided as input for the
well approximated at the low-probability end of the data revision of IEEE Standard 1138 [2]. A double-circuit
by the following two equations: transmission line, with 45-m towers, was assumed to pass
through an area of the central USA where the ground flash
1 (3) density is 4.0 flashes per km2 per year. Based on
P(Qnegative)
Qnegative
1.7 Equation (1), this line will receive 110 flashes per 100 km
1 per year. Half of these flashes will strike each of the two
7 overhead shield wires, less probably at midspan and more
(4) probably near the tower. If a five-year return period
1
P(Q positive) 2.0 (Y=5) is used to determine an acceptable damage
Q positive
1 criterion, then the basic probability level for stroke
85 current, rate of rise and charge will be 1/(5x55) or
P=0.0036 assuming there is an OPGW only on one side of
Equations (3) and (4) need to be inverted to give the the line. Using an observed rate of 98% negative and 2%
charge test levels from the design probability level. positive flashes, the probability design levels for negative
and positive charge will be 0.0036/0.98 = 0.00371 and
For total negative flash charge: 0.0036/0.02 = 0.182, respectively.

Pneg =100 km /(Y * NOPGW * L * Fneg) (5) The negative probability level requires an extrapolation of
1
(6) Bergers observations. It is reassuring that a similar
7( Pneg 1)1 / 1.7 Qnegative coulombs extrapolation of the log-normal distributions of Bergers
negative stroke current data has been proven correct by
For total positive flash charge: supporting observations from wide-area lightning location
networks, collecting more than 107 flashes per year.
Ppos=100 km /(Y * NOPGW* L * Fpos) (7)

3
Invited Lecture at VI International Symposium on Lightning Protection ( VI SIPDA)
November 19 - 23, 2001, Santos, Brazil.

Using the probability models in Equations (2-8), the It has been recommended that IEEE adopt Component C
following threat levels are anticipated on average once of the IEC test method, along with the following
every five years: additional specifications to make the test more practical
and repeatable:
Peak negative stroke current -270 kA
Total negative flash charge -188 C Retain Component B to deliver 10 C for crisp
Total positive flash charge +180 C destruction of the fuse wire
Narrow the range of test currents and control the
The total negative flash charge of 188 C is near the charge using the duration
upper limit of 200 C recommended by IEC for its most Specify negative potential at the electrode
severe test [10]. In this case, with the low proportion of Specify electrode material as tungsten (least damage
positive strokes, the positive flash charge need not be by arcing)
tested. Positive flashes are less damaging per coulomb Specify a geometry of arc head that magnetically
because they have a lower arc root voltage. stabilizes the arc at the center of the test geometry

2.7 Proposed IEEE Test Method The lightning arc test should be performed on OPGW
samples that leave a minimum of 2 m on either side of the
The present IEEE Standard [2] for optical fibre ground test point, to allow good distribution of tension among the
wires holds that OPGW with adequate ampacity for strands. This is especially important if the failure criteria
typical transmission-line short-circuit requirements would will be established with a residual strength test. The
have ample I2t margin for any conceivable lightning cable should be terminated at each end and tensioned to
stroke. However, this approach does not consider either 205 % of ultimate tensile strength (UTS). This normal
the fast-rising nature of lightning or the high plasma operating tension will allow realistic strand movement.
temperature associated with lightning arc roots.
The recommended electrode is a non-thoriated tungsten
Generally, damage from simulation of the first stroke is rod with 3-4 mm diameter and hemispherical tip. The
minimal. Many possible standardized test waves for rod shall be mounted with its axis aligned with the radius
lightning can also be criticized for use within and OPGW of the cable, with the tip 4-6 cm from the cable surface.
standard. The IEEE 4s x 10s and 8s x 20s current The 4-6 cm gap is from IEC 60794 is probably too large
waves [11] are specific for surge arrester testing, and not for efficient reproduction of the lightning effects but is
particularly appropriate for simulation of conductor the closest thing to an industry standard. The rod shall be
damage, even at high test levels of up to 200 kA. The connected to the cable with a fuse wire that will melt
major effect of any of these waves is to melt the fuse wire during the component B wave.
and spray it onto the tops of the OPGW strands.
The surface of the cable in the test field can be externally
The IEC test specification [10] calls for a B component heated to 40 5 C, the maximum temperature of the
to discharge 10 C into the conductor with an average of OPGW in summer conditions. This carry-over
2 kA over 5 ms. This component exists mainly to ensure requirement from short-circuit tests is less important for
continuous current flow in a transition from the 200-kA, the lightning arc test because the arc temperature is high.
100-s impulse to the 200-A, 0.5-s continuing current of
component C. The applied waveform shall include an arc-initiation
component B and a continuing current component C
The continuing current does progressive damage to applied as one continuous discharge. The arc initiation
conductors as charge level increases. However, component is a current pulse of sufficient rise and
test-to-test consistency cannot be achieved using the IEC magnitude to melt the fuse wire on the rising edge, before
specifications alone. The proposed geometry includes a the current peak. The continuing current component is
rod electrode, a fuse wire and a spacing of 5 1 cm. intended to simulate the damaging effects of lightning.
For a stable arc, this geometry needs to be magnetically The direct current magnitude shall be verified with a short
balanced with symmetric return wiring. The choices of circuit in place of the fuse wire. The duration shall be
electrode material, radius and end treatments also affect adjusted to deliver the specified charge. The discharge
shot-to-shot consistency. The IEC spacing is biased shall meet the specifications provided in Table 2.
towards a stable arc with relatively high currents, and the
arc tends to wander for lower levels of charge exposure.

4
Invited Lecture at VI International Symposium on Lightning Protection ( VI SIPDA)
November 19 - 23, 2001, Santos, Brazil.

Table 2: Simulated Lightning Current Specifications negative charge requirement (-497 C) if 300 km of the
same line are to be operated in the same area without
Parameter Electrode Polarity
damage for ten years. In the latter case, users could be
Negative Positive
Arc initiation Peak 2 kA Perhaps the forced to implement redundant elements such as twin
component same OPGW or a grid rather than linear network topology.
Tail 3 0.5 ms
Continuing DC magnitude 225 265 A Perhaps 400 One option, not normally considered but attractive in
Current A
Total Charge Integral I dt Qnegative Qpositive
many respects, is to move the OPGW to a position under
20% 20% the phase conductors. This will eliminate exposure of
the OPGW to direct lightning flashes, and a much lighter
A single specified value of -250 A eliminates questions of conductor can then be used. In addition, there will be a
damage consistency for various current/time significant improvement in the lightning performance of
combinations. This level is high compared to most common transmission line configurations with an
continuing-current measurements on natural or triggered under-built OPGW installation. Generally, under-built
lightning but still realistic and easy to achieve in testing. shield wires can be as effective as partial use of surge
The tolerance on current accounts for ripple of arresters in improving lightning performance. Table 3
three-phase rectifiers. The tolerance on charge is carried shows typical results that could be obtained for one family
over from the original USA military standard 1757A [13] of double-circuit tower designs in Ontario (Ng=1) for an
to account for variations in arc behaviour during typical area of high soil resistivity.
testing. Table 3: Typical Performance Improvement through Addition of Single
Shield Wire, Located Under Existing Phase Conductors
The conductor damage from shot to shot can vary, so five
samples shall be tested with a negative electrode. If Normal Lightning Outage Rate With
Qpositive is more than twice Qnegative, then an additional five Voltage Class Outage Rate Underbuilt OPGW
115-kV 2-Circuit 7 / 100 km/year 1.8/100km/year
samples should be tested with a positive electrode 230-kV 2-Circuit 1 / 100 km/year 0.2/100km/year
potential. Standard welding handbooks suggest that a 500-kV 2-Circuit 0.3/100 km/year 0.05/100km/year
positive arc root is three times more damaging than
negative, meaning that positive lightning can often be less Lines with four overhead groundwires are already used
damaging than negative lightning in spite of higher charge near Itapu in Brazil. Inboard mounting of OPGW is a
levels. useful option for these lines. The choice of underbuilt,
rather than overhead location is an option that may also be
The selected damage criteria will normally be monitored feasible when OPGW are fitted to an existing line. There
during the electrical tests and tested to mechanical are many mechanical and electrical considerations that
destruction after the samples have cooled completely. affect the choice:

Improved testing techniques are available that have a Relative sag of phases and OPGW as a function of
better relation between typical lightning stress and typical circuit load
lightning parameters. One of these techniques, plasma Maintenance of adequate ground clearance
gouging, has the advantage of producing the correct
Quantity and positions of insulating phase-to-OPGW
plasma temperature of 30,000 K rather than an electric arc
spacers within spans
temperature of perhaps 6000 K [10]. However, the IEEE
Additional vertical and overturning wind and ice
also recognizes the merit of the IEC approach and
loads on towers from the OPGW
considers that it will be feasible to adjust test
specifications to match the increasing body of
Many of these concerns must be addressed in
observations of damage to existing OPGW.
conventional All-Dielectric Self Supporting (ADSS) cable
applications, which are another option in cases where
3 UNDER-BUILT OPGW APPLICATIONS
lightning damage is a concern. However, unlike ADSS,
It may not be realistic to expect damage-free operation of retrofit of high-strength OPGW underneath phase
OPGW for many years. For example, many OPGW can conductors can provide an opportunity to reduce
meet several damage criteria for 104 C of negative flash bottom-phase sags and improve thermal ratings at the
charge (corresponding to a 100-km length of line on 35-m same time that they improve lightning performance.
towers, exposed to one year of operation at Ng = 4).
However, few samples of practical OPGW can meet the

5
Invited Lecture at VI International Symposium on Lightning Protection ( VI SIPDA)
November 19 - 23, 2001, Santos, Brazil.

4 COORDINATION OF HV AND LV SYSTEMS 4.3 Solar panels

The widespread use of OPGW will sometimes require the Remote sites can obtain continuous power from solar
installation of repeaters, distribution routers and other panels, regulators and storage batteries at costs of roughly
electronic devices, powered from a connection to a $US 300 per continuous watt. This cost assumes a 50:1
low-voltage system. Several different approaches for oversupply factor for reliability in a fixed-panel
developing a low power from a high-voltage supply are installation, optimized for winter exposure at 45 North
described in the literature and experience. Most of these latitude. However, several issues limit the effectiveness
options can affect lightning performance, or in turn be of the solar panel solution. Partial shading of the solar
damaged by lightning. panels by tower members, additional wind load,
probability of damage to panels during handling and
4.1 Insulation of overhead groundwire sections installation, battery lifetime, adequate surge arrester
energy absorption capabilities and precise specification of
In Canada, overhead groundwire sections are sometimes wire routing all need to be considered.
insulated from the towers to minimize 1-MHz reradiation.
Usually, a single insulator disk can be used without 4.4 High-impedance resistive dividers
affecting lightning performance. The insulated OHGW
also develop induced currents from the resultant magnetic Specialised disc insulators, coated with semiconductive
field of the phase currents. These induced currents can be glaze, have been used sporadically for treatment of
used to provide power at several locations along the line. difficult contamination problems. Generally, a glaze
On a double-circuit 230-kV line, Hydro-One found that an current of 1 mA has been found to be effective, especially
insulated shieldwire, offset only 1 m from the center of the for improved icing performance. Strings of
tower, developed an open-circuit voltage of 1200-1700 V semiconducting-glaze disc insulators and specialised
with a short-circuit current of 50-75 A as the load currents high-impedance step-down transformers can provide ac
ranged from 580 to 780 A. Multi-tap measurements power at the level of 3 to 10 W per string. In this case,
showed that it would be feasible to develop tower currents the lower impedance of the power supply (compared to
of 3-14 A at three positions along the 49 km line. These electrostatic approaches) relaxes the requirements on
tower currents could be used to develop isolated impedance and commercial metallic oxide surge arresters
instrument power using current transformers (CT) as long can be used to protect the high-voltage side of the power
as the CT insertion impedances that are low compared to supply.
the tower footing resistances and the inductive reactance
of the OHGW loop. 4.5 External Power Supplies

4.2 Electrostatic potential dividers In cases where power levels are sufficiently high to need a
connection to a nearby distribution system, there is a
Insulation of overhead groundwire sections has also been novel surge co-ordination problem. A high-voltage
used to develop a high electrostatic voltage from the network, with possible fault currents of 30 kA, would
capacitive coupling of phase voltages. In these cases, rod generally introduce unexpected stresses into the secondary
gaps were provided to ensure an efficient flashover from side of the distribution line connection. Specifications for
OHGW to tower under any lightning surge condition. suitable ac surge protective devices may require
HydroQuebec [14] tested a 4-km isolated OHGW section, development of special components. The more complex
on a 735-kV single-phase line. They used a 50 kV to problem of lightning surge coordination from the stricken
220-V transformer and semiconductor regulator to deliver transmission tower through to the distribution system also
20 kW to a remote microwave station. In Saskatchewan, needs to be considered.
a 2-W instrument was powered using an aluminum panel
near an energized conductor. Generally, when a low-voltage supply is brought onto a
transmission tower, the lightning risk is great but some
Lightning protection of the high-impedance transformers appropriate protection options are reasonably clear. The
needed to step down the electrostatic voltage is difficult. tower can be treated as Lightning Protection Zone LPZ0
Metallic-oxide surge arresters provide too much shunt in the terms of IEC Standard 61312 [15]. The interior of
capacitance in this application. The transformer insul- a metal lattice tower will form a screened area
ation tends to puncture under lightning impulse before corresponding to LPZ1. A solid metallic enclosure to
protective gaps can operate, making this option less protect sensitive electronics will normally be present to
suitable for areas of high lightning flash density. form LPZ2. The surge arrester and bonding

6
Invited Lecture at VI International Symposium on Lightning Protection ( VI SIPDA)
November 19 - 23, 2001, Santos, Brazil.

requirements for adequate lightning performanceat each In cases where test parameters for reliable OPGW links
interface are well described in the IEC approach. lead to excessive cost, the use of lightweight OPGW,
strung below the phase conductors using inter-phase
However, the presence of tower fault current imposes spacers, may be competitive with ADSS installation,
additional requirements on the ac protection aspects. The especially if a significant improvement in lightning
potential rise at the tower base will be a function of the backflashover rates is desirable.
available fault current, tower footing resistance in the
line, the line length, the span length, the overhead There are many options for providing local power for
groundwire surge impedances and the substation optical repeaters, splitters and other interface components
grounding resistances. Considering a 20- resistance such as cellular telephone repeaters. Continuous, low
and a 300-m span length, the fault current at the center of power requirements of 100W or less can be provided with
a 100-km 230-kV line will be about 9 kA and the resulting power tapped from the transmission line itself, using
tower-base potential before fault clearing will be about insulated overhead groundwires or semiconductive-glaze
1 kV. According to Hasse [15], spark gap type lightning insulators. Higher power requirements involving the use
current arresters for the LPZ0 LPZ1 interface would only of a secondary service from a distribution system need
extinguish follow currents of 4 kA at the secondary system special attention to the additional ratings of protective
voltage and would thus be unsuitable in this special devices along with careful interpretation of existing IEC
application. With the high local voltage, Class C zinc recommendations.
oxide arresters would also need high energy absorption
capability compared to conventional cases. 6 REFERENCES

The service transformer should also receive special [1] M. Yokoya, Y. Katsuragi, Y. Goda, Y. Nagata, Y. Asano,
attention, considering the following choices: Development of Lightning-resistant Overhead Ground Wire,
IEEE Transactions of Power Delivery Vol.9 No.3, July 1994
Secondary surge arresters for all phases to pp.1517-1523.
ground, placed directly across secondary [2] IEEE Standard Construction of Composite Fiber Optic
terminals Overhead Ground Wire (OPGW) for Use on Electric Utility
Surge arrester, co-ordinated with transformer Power Lines, IEEE Standard 1138-1994
impulse withstand, directly across the
[3] O. Pinto Jr., I. Pinto, O. Mendes Jr., R. Gin, M. Saba,
transformer high-voltage bushing M. Lacerda, J. Diniz, A. Carvalho, A. Filho, L. Cherchiglia,
Fuse selection with adequate transient Lightning in Brazil, Proceedings of IV International Seminar
overload rating (typically not current-limiting on Lightning Protection, Sao Paulo, Brazil, Sept. 1997,
type)
[4] W.A. Chisholm, J. Beattie and W. Janischewskyj, Analysis of
Adequate secondary-to-primary impulse the Optical Transient Detector Measurements of Lightning over
strength between the transformer windings North and South America, Proceedings of V International
Symposium on Lightning Protection ( SIPDA), So Paulo,
A separation between primary and secondary neutrals may Brazil, May 1999.
be preferred in this application. Bonding at the [5] K.Berger, R.B.Anderson and H. Kroninger, Parameters of
transformer will allow a significant fraction of both Lightning Flashes, Electra, No. 41, pp 23-37, 1975
lightning stroke and transmission line fault current into the
neutrals of the distribution system. These neutral [7] Guide to Procedures for Estimating the Lightning Performance
of Transmission Lines, CIGRE Brochure 63, October 1991
conductors may not have sufficient cross-section area.
[8] IEEE Guide for Improving the Lightning Performance of
5 CONCLUSIONS Overhead Transmission Lines, IEEE Standard 1243-1997,
December 1997
Test parameters and methods for reproducing the [9] IEEE Guide for Improving the Lightning Performance of
observed damage types and rates on optical-fibre ground Electric Power Overhead Distribution Lines, IEEE Standard
wires (OPGW) need further refinement. Parts of the IEC 1410-1997, December 1997
test method, specifically the components B and C, can be
[10] IEC Standard 60794-4-1 Optical fibre cables Part 4-1: Aerial
effective. It has been recommended that the IEEE optical cables for high-voltage power lines, Jan. 1999
Standard 1138 adopt this test method along with a
reasonable way to estimate the required test levels as a [11] IEEE Standard Techniques for High-Voltage Testing, IEEE
function of line length and lightning exposure. Standard 4-1995, October 1995

7
Invited Lecture at VI International Symposium on Lightning Protection ( VI SIPDA)
November 19 - 23, 2001, Santos, Brazil.

[12] W.A. Chisholm and C. Pon, "Development of Realistic


Lightning Arc Tests for Optical Fiber Ground Wires (OPGW),
V International Symposium on Lightning Protection, Sao Paulo,
Brazil, May, 1999.

[13] Lightning Qualification Test Techniques for Aerospace Vehicles


and Hardware, USA Department of Defense Military Standard
MIL-STD-1757A, July 1983

[14] R. Berthiaume and R. Blais, Tapping the Overhead Wire on


Transmission Lines Produces a 20kW, 60Hz Power Supply,
IREQ Rapport 1626, Direction Electrinouqe et Asservissements,
March 1977.

[15] P. Hasse, Lightning Current Arresters and Overvoltage


Arresters Different Requirements Various Devices,
Proceedings of V International Symposium on Lightning
Protection ( SIPDA), So Paulo, Brazil, May 1999

Вам также может понравиться