Вы находитесь на странице: 1из 2

Reinstatement

work tips of Road Openings


pavement work tips no. 16 June 1999
INTRODUCTION EXCAVATION Key Summary
Road openings involve excavation or The thickness and
trenching of road pavement and subgrade an indication of the This issue of
materials for purposes such as the repair or quality of each layer, 'pavement work
installation of utilities (e.g. power, water, of in situ pavement tips' provides
sewage, etc.). materials should be general guidelines
A schematic representation of a trench noted at the time of for the effective
cutting in an existing road is shown in Fig. 1. removal to ensure reinstatement of
that minimum depths
openings made in
of material such as
road pavements
Asphalt Asphalt asphalt are used
Reinstatement during replacement.
Base, subbase Structural Excavations should be straight sided with
pavement

Reinstatement no reverse slopes to interfere with compaction


Select Backfill of reinstatement material. The width of
Subgrade Utility excavation should be generally wide enough
for the operation of mechanical compaction
Bedding
equipment.
Figure 1. Representation of Reinstatement
BACKFILL OF SUBGRADE
In many cases, statutory powers and MATERIALS
regulations of public utilities or road agencies Before commencing backfill operations, the
cover the reinstatement of road openings. bed of the trench should be thoroughly
The following notes are for general guidance compacted. Bedding materials must comply
only and should be read on the understanding with the requirements of the relevant utility.
that they may need to be qualified by Backfill should be selected material
conditions or agreements existing in each complying with the requirements of the road
State. authority. The excavated materials may be
In all cases, the safety of road users must be suitable, but expansive clay materials that swell
considered. and shrink with changes in moisture content
should be avoided. If the excavated material
GENERAL is used, each layer should be placed at
approximately the level from which it was
The general principle is that reinstatement
originally taken.
must provide a structural adequacy and
serviceability that is at least equal to that in Pervious materials such as sands, and some
existence prior to the road being disturbed. gravels, should also be avoided where there is
a risk that they may allow moisture to
Insitu pavements generally have well
accumulate in the trench and soften the
compacted materials due to original
subgrade.
construction standards and trafficking.
Disturbing the pavement material can create A typical specification for select backfill
AUSTROADS a plane of weakness and reduced capacity to requires a granular material having 100%
transfer loads. High standards of compaction passing a 37.5mm sieve, 10 to 40% passing a
of appropriate replacement materials are 75 micron sieve, and a PI of 5 to 20.
essential to avoid later settlement. continued on reverse

pavement work tips is produced by AUSTROADS in conjunction with AAPA


For more information
Reinstatement of Road Openings page 2 on any of the
construction practices
discussed in
Backfill materials should be placed in layers ASPHALT PAVEMENTS "pavement work tips",
of around 150mm thickness, at moisture Granular base and subbase layers should be please contact either
content close to optimum, and thoroughly replaced as discussed for sprayed seal your local
compacted using mechanical tampers. AUSTROADS
pavements, above. Pavement Reference
Cement stabilised soil may also be used, The asphalt thickness must be at least equal Group representative
particularly where stability in wet conditions to that in the existing pavement. Generally, or AAPA
is required or adequate compaction is difficult. tel (03) 9853 3595;
reinstatement of asphalt surfacing is similar fax (03) 9853 3484;
Rigid materials may not be permitted around in technique to pot hole repair. Edges of e-mail:
some service pipes and conduits and high existing pavement should be cut straight and info@aapa.asn.au
cement contents (more than 5%) should be vertical. The sides and base should be tack A complete list of
avoided in all cases as cracking may result. coated prior to placing asphalt. "pavement work tips"
issues is available on
GRANULAR PAVEMENTS WITH In some cases, a slight crown may be formed AAPA's web site:
in the asphalt surfacing to allow for subsequent www.aapa.asn.au
SPRAYED SEAL SURFACING
consolidation of the trench although the Issues may be
Suitable granular materials should be used amount of consolidation is somewhat difficult downloaded using
to match the profile of the existing pavement. to estimate. High standards of compaction of Adobe Acrobat
The quality must be at least equal to that Reader. Copies may
materials that minimise further consolidation also be obtained from
removed and have similar permeability under traffic are preferred. AAPA. Material may
characteristics. Re-use of contaminated be freely reproduced
As with sprayed seal surfacings, above, a
pavement materials should be avoided. providing the source
temporary surfacing may be applied for later
Depending on traffic volumes and road user is acknowledged.
completion of reinstatement.
safety requirements, the granular material may This edition was
Cold mix patching materials may be used as prepared by
be compacted flush with the adjacent seal and
temporary surfacing. In such cases, the full John Rebbechi in
left unsealed for several days to allow for consultation with
depth of cold mix should be removed when
further consolidation under traffic and members of the
placing the final asphalt surface. Cold mix National Asphalt
settlement in the trench prior to replacing the
materials are not generally suitable as Research
seal.
permanent surfacing of road openings. Coordination Group
Alternatively, a temporary surfacing may be (NARC).
used that is replaced or resurfaced as part of CONCLUSION
final reinstatement. Reinstatement of road openings should be carried out with materials
As far as practicable, the surface type and that provide a quality that is at least equal to the existing pavement.
texture should be matched to the adjacent High standards of compaction are required to avoid further settlement
pavement. Alternatively, the full lane width and depressions in the final surface. Where possible, the surfacing
may be resurfaced to provide uniform texture should be finished to match the texture, surface type and colour of
and friction characteristics. the rest of the pavement.

Figure 2: Neat reinstatement Figure 3: Poorly executed reinstatement

Вам также может понравиться