Академический Документы
Профессиональный Документы
Культура Документы
SEPTEMBER
3 4 5 6 7 8
No. Action Mon Tue Wed Thu Fri Sat
1 VMP
HOLIDAY
2 HVAC
SEPTEMBER
10 11 12 13 14 15
No. Action
Mon Tue Wed Thu Fri Sat
1 VMP
SEPTEMBER
17 18 19 20 21 22
No. Action
Mon Tue Wed Thu Fri Sat
1 VMP
HOLIDAY
2 HVAC
1 VMP
October
1 2 3 4 5 6
No. Action
Mon Tue Wed Thu Fri Sat
1 VMP
LIDAY
Planning and Schedule table (indicative only)
HOLIDAY
2 HVAC
October
8 9 10 11 12 13
No. Action
Mon Tue Wed Thu Fri Sat
1 VMP
October
15 16 17 18 19 20
No. Action
Mon Tue Wed Thu Fri Sat
1 VMP
HOLIDAY
Make OQ for AHUs
Collect information regarding the major components of the
HVAC system and about there qualification.
If information available, make protocol for the major components of the HVAC syste
October
22 23 24 25 26 27
No. Action
Mon Tue Wed Thu Fri Sat
1 VMP
HOLIDAY
HOLIDAY
Make OQ for AHUs
Collect information regarding the major components of the
HVAC system and about there qualification.
If information available, make protocol for the major components of the HVAC syste
October/November
29 30 31 1 2 3
No. Action
Mon Tue Wed Thu Fri Sat
1 VMP
November
5 6 7 8 9 10
No. Action
Mon Tue Wed Thu Fri Sat
1 VMP
Prepare attachments for VMP
2 HVAC
November
12 13 14 15 16 17
No. Action
Mon Tue Wed Thu Fri Sat
1 VMP
HOLIDAY
Make PQ for AHUs
Collect information regarding the major components of the
HVAC system and about there qualification.
If information available, make protocol for the major components of the HVAC syste
November
19 20 21 22 23 24
No. Action
Mon Tue Wed Thu Fri Sat
1 VMP
December
10 11 12 13 14 15
No. Action
Mon Tue Wed Thu Fri Sat
1 VMP
December
24 25 26 27 28 29
No. Action
Mon Tue Wed Thu Fri Sat
1 HVAC
HOLIDAY
Modification of AHU qualification as suggested during meeting
SOP for Enviromental Monitoring
Year 2013
January
7 8 9 10 11 12
No. Action
Mon Tue Wed Thu Fri Sat
1 HVAC
1 HVAC
HOLIDAY
Modification of AHU qualification as suggested during meeting with K.Tamas
SOP for Enviromental Monitoring
January
21 22 23 24 25 26
No. Action
Mon Tue Wed Thu Fri Sat
1 HVAC
January/February
28 29 30 31 1 2
No. Action
Mon Tue Wed Thu Fri Sat
1 HVAC
HOLIDAY
HOLIDAY
OQ/PQ of AHU as discussed during validation team meeting
with K. Tamaskar
Coding of diffusers and return air outlets of the HVAC system
February
11 12 13 14 15 16
No. Action
Mon Tue Wed Thu Fri Sat
1 HVAC
HOLIDAY
Revise the qualification test method in PQ of AHU
Coding of diffusers and return air outlets of the HVAC system
February
18 19 20 21 22 23
No. Action
Mon Tue Wed Thu Fri Sat
1 HVAC
1 HVAC
1 HVAC
HOLIDAY
Revising Validation Master Plan
March
18 19 20 21 22 23
No. Action
Mon Tue Wed Thu Fri Sat
1 HVAC
Collect data for the major components of HVAC from internet
Revising Validation Master Plan
2 Inspection of R&D laboratory
March
25 26 27 28 29 30
No. Action
Mon Tue Wed Thu Fri Sat
1 HVAC
HOLIDAY
Collect data for the major components of HVAC from internet
Revising Validation Master Plan
April
1 2 3 4 5 6
No. Action
Mon Tue Wed Thu Fri Sat
1 Validation project
Collect data for the major components of HVAC from internet
Revising Validation Master Plan
2 Inspection of Sterile Manufacturing area (3rd floor)
3 Inspection of Non Sterile Manufacturing area (2nd floor)
4 Inspection of Non Sterile Manufacturing area (1st floor)
April
8 9 10 11 12 13
No. Action
Mon Tue Wed Thu Fri Sat
1 Validation project
Collect data for the major components of HVAC from internet
HOLIDAY
Revising Validation Master Plan
HOLIDAY
2 Inspection of Non Sterile Manufacturing area (2nd floor)
3 Inspection of Non Sterile Manufacturing area (1st floor)
April
22 23 24 25 26 27
No. Action
Coding of the return air and supply air outlets for the new Mon Tue Wed Thu Fri Sat
1
Checking
factory. of the online documents in both sterile and non
HOLIDAY
2
sterile area.of the facility from maintenance point of view.
3 Inspection
May
6 7 8 9 10 11
No. Action
Mon Tue Wed Thu Fri Sat
Holiday
1
Holiday
2
Holiday
2
Holiday
1
Holiday
1
Holiday
2 Making validation protocols for other GANSON machines
July August
29 30 31 1 2 3
No. Action
Mon Tue Wed Thu Fri Sat
Holiday
2 Making validation protocols for other GANSON machines
5 6 7 8 9 10
No. Action
Mon Tue Wed Thu Fri Sat
Holiday
Holiday
2 Revision of protocols according to format in VMP
19 20 21 22 23 24
No. Action
Mon Tue Wed Thu Fri Sat
Revision of protocols according to format as discussed in
1
Validation team meeting.
26 27 28 29 30 31
No. Action
Mon Tue Wed Thu Fri Sat
Holiday
1
Validation team meeting.
September
2 3 4 5 6 7
No. Action
Mon Tue Wed Thu Fri Sat
Holiday
1
Validation team meeting with K. Tamaskarn
16 17 18 19 20 21
No. Action
Mon Tue Wed Thu Fri Sat
Revision of Validation Protocols according to the revised
Holiday
1
format.
23 24 25 26 27 28
No. Action
Mon Tue Wed Thu Fri Sat
Revision of Validation Protocols according to the revised
1
format.
Sept. October
30 1 2 3 4 5
No. Action
Mon Tue Wed Thu Fri Sat
Revision of Validation Protocols according to the revised
1
format.
7 8 9 10 11 12
No. Action
Mon Tue Wed Thu Fri Sat
Revision of Validation Protocols according to the revised
Holiday
1
format.
14 15 16 17 18 19
No. Action
Mon Tue Wed Thu Fri Sat
Revision of Validation Protocols according to the revised
1
format.
21 22 23 24 25 26
No. Action
Mon Tue Wed Thu Fri Sat
Revision of Validation Protocols according to the revised
Holiday
Holiday
1
format.
October Nov.
28 29 30 31 1 2
No. Action
Mon Tue Wed Thu Fri Sat
Holiday
Holiday
2 Perfomance Qualification of the Protocols
November
25 26 27 28 29 30
No. Action
Mon Tue Wed Thu Fri Sat
Holiday
Holiday
1 Perfomance Qualification of the Protocols
December
9 10 11 12 13 14
No. Action
Mon Tue Wed Thu Fri Sat
23 24 25 26 27 28
No. Action
Mon Tue Wed Thu Fri Sat
50% complete
80% complete
Details Remarks
70% complete
50% complete
Details Remarks
90% complete
50% complete
90%complete
90% complete
Details Remarks
Details Remarks
Under progress
Under progress
Under progress
Depends on the information
provided by K. Tamaskar
Details Remarks
Under Progress
Under Progress
Details Remarks
Depends on the information
provided by K. Tamaskar
Details Remarks
Details Remarks
Depends on the information
provided by K. Tamaskar
Details Remarks
Details Remarks
Depends on the information
provided by K. Tamaskar
Details Remarks
Details Remarks
Details Remarks
Details Remarks
Details Remarks
PQ not complete yet
Details Remarks
Details Remarks
Details Remarks
Details Remarks
Details Remarks
Details Remarks
Details Remarks
Details Remarks
Details Remarks
Details Remarks
Details Remarks
Details Remarks
Details Remarks
Details Remarks
Details Remarks
IQ/OQ for SFT-500, Multimill, Oblicon
blender completed
Details Remarks
Details Remarks
Details Remarks
Details Remarks
Details Remarks
Details Remarks
Details Remarks
Details Remarks
Details Remarks
Details Remarks
Details Remarks
Details Remarks
Details Remarks
Ganscoater GAC 800 IQ completed
Details Remarks
Details Remarks
Details Remarks
Details Remarks
Details Remarks
Details Remarks
Details Remarks
Details Remarks
Details Remarks
Details Remarks
Details Remarks
Not complete yet. Have to use other
reference (Validation SOP Syed Imtiaz
Haider)
Details Remarks
JANUAR
13
No. Action
Mon
JANUAR
20
No. Action
Mon
1
machine
2 Equipment and Room Coding for new factory
FEBRUA
3
No. Action
Mon
FEBRUA
17
No. Action
Mon
1 IQ/OQ FBD600
2 IQ/OQ V-Blender600
FEBRUARY/
24
No. Action
No. Action
Mon
3 Room Coding
March
3
No. Action
Mon
1 Room Coding
2 Equipment list and Coding
March
10
No. Action
Mon
March
17
No. Action
Mon
March
24
No. Action
Mon
March/ A
31
No. Action
Mon
HOLIDAY
1
2 Revise PQ of equipments
April
7
No. Action
Mon
1 Revise PQ of equipments
May
5
No. Action
Mon
Revise PQ of equipments as revised by K.
1
Tamaskar
May
12
No. Action
Mon
May
26
No. Action
Mon
Summarize and prepare attachments for
1
QVMP
June
9
No. Action
Mon
Summarize and prepare attachments for
1
QVMP
June
16
No. Action
Summarize and prepare attachments for Mon
1
QVMP
2 Prepare pending PQ protocols
June
23
No. Action
Mon
June/Ju
30
No. Action
Mon
Sept
15
No. Action
Mon
Sept
22
No. Action
Mon
Holiday
2 Risk Assessment for Manfucaturing processes
Oct/No
27
No. Action
Mon
QA inpection for the preparation of GMP
1
audit in November
2 Checking Manufacturing documents
3 Risk Assessment for Manufacturing processes
Nov
3
No. Action
Mon
QA inpection for the preparation of GMP
1
audit in November
2 Risk Assessment for Manufacturing processes
Nov
10
No. Action
Mon
QA inpection for the preparation of GMP
1
audit in November
2 Risk Assessment for Manufacturing processes
Nov
24
No. Action
Mon
QA inpection for the preparation of GMP
1
audit in November
2 Checking Manufacturing records
3 Risk Assessment for Manufacturing processes
Decemb
1
No. Action
Mon
Holiday
JANUARY
21 22 23 24 25
Details Remarks
Tue Wed Thu Fri Sat
JANUARY/FEBRUARY
28 29 30 31 1
Details Remarks
Tue Wed Thu Fri Sat
FEBRUARY
4 5 6 7 8
Details Remarks
Tue Wed Thu Fri Sat
HOLIDAY
FEBRUARY
18 19 20 21 22
Details Remarks
Tue Wed Thu Fri Sat
FEBRUARY/MARCH
25 26 27 28 1
Details Remarks
Details Remarks
Tue Wed Thu Fri Sat
HOLIDAY
March
4 5 6 7 8
Details Remarks
Tue Wed Thu Fri Sat
March
11 12 13 14 15
Details Remarks
Tue Wed Thu Fri Sat
HOLIDAY
March
18 19 20 21 22
Details Remarks
Tue Wed Thu Fri Sat
March
25 26 27 28 29
Details Remarks
Tue Wed Thu Fri Sat
HOLIDAY
March/ April
1 2 3 4 5
Details Remarks
Tue Wed Thu Fri Sat
HOLIDAY
Making manufacturing record for Placebo which will cover most of the equipments.
April
8 9 10 11 12
Details Remarks
Tue Wed Thu Fri Sat
Holiday
May
6 7 8 9 10
Details Remarks
Tue Wed Thu Fri Sat
Holiday
May
13 14 15 16 17
Details Remarks
Tue Wed Thu Fri Sat
Holiday
May
20 21 22 23 24
Details Remarks
Tue Wed Thu Fri Sat
Holiday
May
27 28 29 30 31
Details Remarks
Tue Wed Thu Fri Sat
Holiday
June
10 11 12 13 14
Details Remarks
Tue Wed Thu Fri Sat
Holiday
June
17 18 19 20 21
Details Remarks
Tue Wed Thu Fri Sat
Holiday
check Manufacturing records
June
24 25 26 27 28
Details Remarks
Tue Wed Thu Fri Sat
Holiday
June/July
1 2 3 4 5
Details Remarks
Tue Wed Thu Fri Sat
Holiday
August
19 20 21 22 23
Details Remarks
Tue Wed Thu Fri Sat
Holiday
Sept
9 10 11 12 13
Details Remarks
Tue Wed Thu Fri Sat
Holiday
Sept
16 17 18 19 20
Details Remarks
Tue Wed Thu Fri Sat
Holiday
Sept
23 24 25 26 27
Details Remarks
Tue Wed Thu Fri Sat
Holiday
Sept/Oct
30 1 2 3 4
Details Remarks
Tue Wed Thu Fri Sat
Holiday
Revsion Pending
Oct
7 8 9 10 11
Details Remarks
Tue Wed Thu Fri Sat
Holiday
Oct
14 15 16 17 18
Details Remarks
Tue Wed Thu Fri Sat
Holiday
Holiday
Oct
21 22 23 24 25
Details Remarks
Tue Wed Thu Fri Sat
Holiday
Holiday
Oct/Nov
28 29 30 31 1
Details Remarks
Tue Wed Thu Fri Sat
Holiday
Nov
4 5 6 7 8
Details Remarks
Tue Wed Thu Fri Sat
Holiday
Nov
11 12 13 14 15
Details Remarks
Tue Wed Thu Fri Sat
Holiday
Nov
25 26 27 28 29
Details Remarks
Tue Wed Thu Fri Sat
Holiday
December
2 3 4 5 6
Details Remarks
Tue Wed Thu Fri Sat
Holiday
ill cover most of the equipments.
Jan
5 6
No. Action
Mon Tue
Verifying Certificates and Documents of
1
Neela Water System
Jan
12 13
No. Action
Mon Tue
Verify Certificates and Documents of
1
Neela Water System
2 Verify GA drawing of the equipments
Jan
19 20
No. Action
Mon Tue
Jan
26 27
No. Action
Mon Tue
Ma
9 10
No. Action
Mon Tue
Ma
16 17
No. Action
Mon Tue
Ma
24 25
No. Action
Mon Tue
Marc
30 31
No. Action
Mon Tue
Verify the opening for the Supply air and
1
Return as per drawing.
A
6 7
No. Action
Mon Tue
Verify the switches and conduits against
1
the drawing
A
20 21
No. Action
Mon Tue
Verify the switches and conduits against
1
the drawing
M
4 5
No. Action
Mon Tue
M
11 12
No. Action
Mon Tue
M
18 19
No. Action
Mon Tue
Measure the position of the drains in
1
each room and put it on drawing.
Verify all the received machines against
2 the packing list and assign room number
to them for shifting
M
25 26
No.
Verify compressed Action
air points for process Mon Tue
Ju
1 2
No. Action
Mon Tue
Remove rejected NEELA valves and
1
there packing
Ju
8 9
No. Action
Mon Tue
Remove rejected NEELA valves and
1
there packing
Ju
15 16
No. Action
Mon Tue
June
29 30
No. Action
Doing impact assessment for the
Mon Tue
1
machines
Ju
6 7
No. Action
Mon Tue
Doing impact assessment for the
1
machines
Ju
13 14
No. Action
Mon Tue
Ju
20 21
No. Action
Doing impact assessment for the
Mon Tue
1
machines
July/A
27 28
No. Action
Doing impact assessment for the
Mon Tue
1
machines
Au
3 4
No. Action
Mon Tue
Au
17 18
No. Action
Mon Tue
Au
24 25
No. Action
Mon Tue
August/ S
31 1
No. Action
Mon Tue
1
Passbox
Incorporating risk assessment in the
2
Validation Protocol where ever possible
Sept
14 15
No. Action
Mon Tue
Sept
22 23
No. Action
Verification of the installation of Return
Mon Tue
Septembe
28 29
No. Action
Mon Tue
Oct
5 6
No. Action
Mon Tue
Oct
12 13
No. Action
Make LBS utility requirement as per room
Mon Tue
1
detail
2 Shift Autoclaves according to final drawing
Verify position of the new process drains
3
with technicians
Follow up of the installation of return
4 panel for HVAC and installation of
Passbox
Oct
19 20
No. Action
No. Action
Follow up of the work by Metechno
Mon Tue
1
contractor
2 Shift Autoclaves according to final drawing
Oct
26 27
No. Action
Follow up of the work by Metechno
Mon Tue
1
contractor
Nove
2 3
No. Action
Mon Tue
Nove
9 10
No. Action
Follow up of the work by Metechno
Mon Tue
1
contractor.
2 Passbox Installation
Nove
16 17
No. Action
Follow up of the work by Metechno
Mon Tue
1
contractor.
2 IQ Protocol document verification
Novembe
30 1
No. Action
Make the inventory of the equipments Mon Tue
Dece
7 8
No. Action
Mon Tue
Dece
14 15
No. Action
Make the inventory of the equipments Mon Tue
Dece
21 22
No. Action
Make the inventory of the equipments Mon Tue
Decembe
28 29
No. Action
Make the inventory of the equipments Mon Tue
Jan
4 29
No. Action
Make the inventory of the equipments Mon Tue
Holiday
January
14 15 16 17
Details
Wed Thu Fri Sat
Holiday
January
21 22 23 24
Details
Wed Thu Fri Sat
January
28 29 30 31
Details
Wed Thu Fri Sat
Feb
4 5 6 7
Details
Details
Wed Thu Fri Sat
Some points not clear from drawing
Feb
11 12 13 14
Details
Wed Thu Fri Sat
Holiday
March
4 5 6 7
Details
Wed Thu Fri Sat
Holiday
Holiday
March
11 12 13 14
Details
Wed Thu Fri Sat
March
18 19 20 21
Details
Wed Thu Fri Sat
Holiday
March
18 19 20 21
Details
Wed Thu Fri Sat
Holiday
March
26 27 28 29
Details
Wed Thu Fri Sat
March/ April
1 2 3 4
Details
Wed Thu Fri Sat
Holiday
April
8 9 10 11
Details
Wed Thu Fri Sat
April
22 23 24 25
Details
Wed Thu Fri Sat
May
6 7 8 9
Details
Wed Thu Fri Sat
Holiday
flooring work under
progress
May
13 14 15 16
Details
Wed Thu Fri Sat
Incomplete as flooring
work in sterile area under
progress
May
20 21 22 23
Details
Wed Thu Fri Sat
Changed Saturday
Holiday
May
27 28 29 30
Details
Wed Thu Fri Sat
Holiday
Holiday
June
3 4 5 6
Details
Wed Thu Fri Sat
Holiday
Packing material not
sufficient.
June
10 11 12 13
Details
Wed Thu Fri Sat
June
17 18 19 20
Details
Wed Thu Fri Sat
Holiday
June/ July
1 2 3 4
Details
Wed Thu Fri Sat
Holida
Collecting Information
y
July
8 9 10 11
Details
Wed Thu Fri Sat
Holida
y
July
15 16 17 18
Details
Wed Thu Fri Sat
Not done as working with
Klenzaids Engineer for
Ampoule tunnel line for
whole week
July
22 23 24 25
Details
Wed Thu Fri Sat
July/August
29 30 31 1
Details
Wed Thu Fri Sat
Holida
Holida
August
5 6 7 8
Details
Wed Thu Fri Sat
Holiday
August
12 13 14 15
Details
Wed Thu Fri Sat
Holida
August
19 20 21 22
Details
Wed Thu Fri Sat
Holiday
August
26 27 28 29
Details
Wed Thu Fri Sat
Working on Freeze
Holiday
Drier
August/ September
2 3 4 5
Details
Wed Thu Fri Sat
31 Aug- Went to
immigration for
making yearly VISA
September
9 10 11 12
Details
Wed Thu Fri Sat
Risk Assessment
not done as was
busy in transferring
Holiday
equipments in
rooms.
September
16 17 18 19
Details
Wed Thu Fri Sat
September
24 25 26 27
Details
Wed Thu Fri Sat
Holiday
September/ October
30 1 2 3
Details
Wed Thu Fri Sat
Marking on the panels
done to accommodate
Passbox
October
7 8 9 10
Details
Wed Thu Fri Sat
October
14 15 16 17
Details
Wed Thu Fri Sat
October
21 22 23 24
Details
Details
Wed Thu Fri Sat
October
28 29 30 31
Details
Wed Thu Fri Sat
Holida
y
November
4 5 6 7
Details
Wed Thu Fri Sat
November
11 12 13 14
Details
Wed Thu Fri Sat
Holiday
November
18 19 20 21
Details
Wed Thu Fri Sat
Holiday
November/December
2 3 4 5
Details
Wed Thu Fri Sat
Holiday
December
9 10 11 12
Details
Wed Thu Fri Sat
December
16 17 18 19
Details
Wed Thu Fri Sat
December
23 24 25 26
Details
Wed Thu Fri Sat
December/ January
30 31 1 2
Details
Wed Thu Fri Sat
HOLIDAY
January
30 31 1 2
Details
Wed Thu Fri Sat
HOLIDAY
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Wed- Go to Immigration
for transferring Visa in
new passport
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
WEEKLY ACTION PLAN - JAI - M/C INS
J
No. Action 11
Mon
1
Installation of Equipments with Ganson
Engineer
J
No. Action 18
Mon
1
Installation of Laminar flow in Dispensing
and Sampling areas
J
No. Action 25
Mon
1
Installation of Laminar flow in Dispensing
and Sampling areas
No. Action 1
Mon
1
Working with Mr. Tamaskar
No. Action 8
Mon
1
Working with Mr. Tamaskar
No. Action 15
Mon
1
Follow up installation of Laminar Flow
2
Making Tap water requirement points in
production area. Fe
No. Action 29
Mon
1
Making Protocols for FBP100L
2
Working with Mr. Tamaskar
No. Action 14
Mon
1
Checking of sealing by Metechno on
partition panels
Ma
No. Action 28
Mon
1
Follow up of installation of Plant steam and
compress air.
2
Working with Mr. Tamaskar and checking of
sealing by Metechno on partition panels
No. Action 4
Mon
1
Marking of drain location in Sterile Area
2
IQ of Freeze Drier (Component Check)
No. Action 11
Mon
1
IQ Autoclave Room no. 166,156
No. Action 18
Mon
1
IQ Autoclave Room no. 156,154,137,132
No. Action 25
Mon
1
Klenzaids washer and sterilizing tunnel
2
IQ WFI and PSG
No. Action 2
Mon
Holiday
1
Klenzaids washer and sterilizing tunnel
2
Ampoule filling machine
No. Action 9
Mon
1
Installation of WFI & Autoclave with
Pharmalab Engineer
No. Action 16
Mon
1
IQ Klenzaids washer and sterilizing tunnel
No. Action 23
Mon
1
Follow up QC partitioning
2
Klenzaids Ampoule filling machine
M
No. Action 30
Mon
1
Working with Khun Tamaskar
No. Action 13
Mon
1
IQ component check FBD 180 Kg line
2
IQ component check FBD 30 Kg line
No. Action 20
Mon
1
IQ component Dry Granulation line
2
IQ component check Ganscoater GAC 800
J
No. Action 27
Mon
1
Working with Khun Tamaskar
No. Action 4
Mon
1
IQ component check Ganscoater GAC 800
2
Verification of Socket in QC
No. Action 25
Mon
1
Working with Khun Tamaskar
No. Action 1
Mon
1
IQ component check Ganscoater GAC 1200
2
New Drain installation verification
No. Action 8
Mon
1
IQ component check VEGA TX30
No. Action 22
Mon
1
Follow up of Plug and Switch installation in
QC
A
No. Action 29
Mon
1
IQ of AHUs
2
Working with Mr. Tamaskar
Se
No. Action 12
Mon
1
Revise IQ of all AHUs according to new
supplier documents.
Se
No. Action 19
Mon
1
IQ of AHU-01
2
IQ of AHU-02
Septem
No. Action 26
Mon
1
IQ of AHU-03
2
IQ of AHU-04
O
No. Action 3
Mon
1
IQ of AHU-05
2
IQ of AHU-06
O
No. Action 10
Mon
1
IQ of AHU-07
2
IQ of AHU-08
O
No. Action 17
Mon
1
IQ of AHU-09
2
IQ of AHU-10
O
No. Action 24
Mon
1
IQ of AHU-11
2
IQ of AHU-12
3
Working with Khun Tamaskar
Octobe
No. Action 31
Mon
1
IQ of AHU-13
2
IQ of AHU-14
N
No. Action 7
Mon
1
IQ of AHU-15
2
IQ of AHU-16
N
No. Action 14
No. Action
Mon
1
IQ of AHU-17
2
IQ of AHU-18
N
No. Action 21
Mon
1
IQ of AHU-42
2
IQ of AHU-54
Novem
No. Action 28
Mon
1
IQ of AHU-19
2
IQ of AHU-20
D
No. Action 19
Mon
1
IQ of AHU-21
2
Holiday
IQ of AHU-23-1
D
No. Action 26
Mon
1
Working with Khun Tamaskar
1
IQ of AHU-23-2
2
IQ of AHU - 25
ION PLAN - JAI - M/C INSTALLATION, IQ,
Planned In process Done
January
12 13 14 15 16 Details
Tue Wed Thu Fri Sat
Holiday
January
19 20 21 22 23 Details
Tue Wed Thu Fri Sat
Holiday
January
26 27 28 29 30 Details
Tue Wed Thu Fri Sat
Feb
2 3 4 5 6 Details
Tue Wed Thu Fri Sat
Holiday
Feb
9 10 11 12 13 Details
Tue Wed Thu Fri Sat
Checking change in layout as
Feb
16 17 18 19 20 Details
Tue Wed Thu Fri Sat
Holiday
Holiday
Feb/March
1 2 3 4 5 Details
Tue Wed Thu Fri Sat
Holiday
March
15 16 17 18 19 Details
Tue Wed Thu Fri Sat
March/April
29 30 31 1 2 Details
Tue Wed Thu Fri Sat
Holiday
April
5 6 7 8 9 Details
Tue Wed Thu Fri Sat
April
12 13 14 15 16 Details
Tue Wed Thu Fri Sat
HOLIDAY
April
19 20 21 22 23 Details
Tue Wed Thu Fri Sat
Holiday
April
26 27 28 29 30 Details
Tue Wed Thu Fri Sat
May
3 4 5 6 7 Details
Tue Wed Thu Fri Sat
Holiday
Not Complete
Not Complete
May
10 11 12 13 14 Details
Tue Wed Thu Fri Sat
May
17 18 19 20 21 Details
Tue Wed Thu Fri Sat
Continue
Holiday
May
24 25 26 27 28 Details
Tue Wed Thu Fri Sat
May/ June
31 1 2 3 4 Details
Tue Wed Thu Fri Sat
HOLIDAY
June
14 15 16 17 18 Details
Tue Wed Thu Fri Sat
HOLIDAY
June
21 22 23 24 25 Details
Tue Wed Thu Fri Sat
June/ July
28 29 30 1 2 Details
Tue Wed Thu Fri Sat
HOLIDAY
July
5 6 7 8 9 Details
Tue Wed Thu Fri Sat
HOLIDAY
HOLIDAY
July
26 27 28 29 30 Details
Tue Wed Thu Fri Sat
Aug
2 3 4 5 6 Details
Tue Wed Thu Fri Sat
HOLIDAY
Aug
9 10 11 12 13 Details
Tue Wed Thu Fri Sat
HOLIDAY
HOLIDAY
HOLIDAY
from supplier
Aug
23 24 25 26 27 Details
Tue Wed Thu Fri Sat
Aug/ Sept
30 31 1 2 3 Details
Tue Wed Thu Fri Sat
HOLIDAY
September
13 14 15 16 17 Details
Tue Wed Thu Fri Sat
HOLIDAY
September
20 21 22 23 24 Details
Tue Wed Thu Fri Sat
September/October
27 28 29 30 1 Details
Tue Wed Thu Fri Sat
October
4 5 6 7 8 Details
Tue Wed Thu Fri Sat
October
11 12 13 14 15 Details
Tue Wed Thu Fri Sat
HOLIDAY
October
18 19 20 21 22 Details
Tue Wed Thu Fri Sat
October
25 26 27 28 29 Details
Tue Wed Thu Fri Sat
October/ November
1 2 3 4 5 Details
Tue Wed Thu Fri Sat
HOLIDAY
November
8 9 10 11 12 Details
Tue Wed Thu Fri Sat
HOLIDAY
November
15 16 17 18 19 Details
Details
Tue Wed Thu Fri Sat
November
22 23 24 25 26 Details
Tue Wed Thu Fri Sat
HOLIDAY
November/ December
29 30 1 2 3 Details
Tue Wed Thu Fri Sat
HOLIDAY
December
20 21 22 23 24 Details
Tue Wed Thu Fri Sat
Holiday
December
27 28 29 30 31 Details
Tue Wed Thu Fri Sat
HOLIDAY
Unable to complete as was
working with Khun
Tamaskar regarding FDA
comments.
HOLIDAY
Unable to complete as was
working with Khun
Tamaskar regarding FDA
comments.
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
WEEKLY ACTION PLAN - JAI - M/C INSTALLATION, IQ
Planned In process
January
No. Action 2 3 4 5
Mon Tue Wed Thu
Holiday
1
IQ of
AHU-23-2
January
No. Action 9 10 11 12
Mon Tue Wed Thu
1
IQ of
2
IQ of
AHU-24
AHU-25 January
No. Action 16 17 18 19
Mon Tue Wed Thu
1
IQ of
2
IQ of
AHU-26
AHU-27 January
No. Action 23 24 25 26
Mon Tue Wed Thu
1
IQ of
2
IQ of
AHU-33
AHU-34
January
No. Action 30 31 1 2
Mon Tue Wed Thu
1
IQ of
2
IQ of
AHU-35
AHU-36
/C INSTALLATION, IQ,
Done
6 7 Details Remarks
Fri Sat
Holiday
13 14 Details Remarks
Fri Sat
20 21 Details Remarks
Fri Sat
Holiday
27 28 Details Remarks
Fri Sat
3 4 Details Remarks
Fri Sat
Holiday